Professional Documents
Culture Documents
BRAMHAPURI TO TWO LANE WITH PAVED SHOULDER CONFIGURATION IN SECTION FROM DEORI TO
AMGAON (DESIGN CH. FROM KM. 0.000 TO KM. 38.200) IN THE STATE OF MAHARASHTRA ON EPC MODE.
NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600 to 12700
(LHS)
DETAILED ESTIMATE
Earthwork excavation for foundation of structures as per drawings and technical specifications, including
1 setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material including cost of dewatering As per MORT & H,
V REVISION CL. 304
0.00 cum
2 Plain cement concrete M15 in sub structure complete as per drawing and technical specification for
SubStructure below sill As per MORT & H, V REVISION SPECIFICATION NO.1500, 1700 & 2100
CH : 1/775 - 1/875, 2/300 - 2/400,
400
4/300 - 4/400, 6/600 - 6/700
I footing 1 x 2 400.00 0.00 0.00 0.00 cum
0.00 cum
3 Plain cement concrete M15 in sub structure complete as per drawing and technical specification for
SubStructure Above sill As per MORT & H, V REVISION SPECIFICATION NO.1500, 1700 & 2100
CH : 1/775 - 1/875, 2/300 - 2/400, 400
4/300 - 4/400, 6/600 - 6/700
Rect portion 1 x 2 400.00 0.4 2.67 854.40 cum
1922.20 cum
Providing weep holes in brick masonry /plain / reinforced concrete abutment, wing walls / return wall with
4 100 mm dia AC pipe, extending through the full width of the structure with slope of aV:20H towards
drawing face, complete as per drawing and techinical specifications. As per MORT & H, V REVISION
SPECIFICATION NO.2706, 2200
1600.00 Nos.
5 Providing and laying Granular material below stone pitching portion as filter media including cost,
conveyance, labour for filling, hire charges to T&p etc., Complete as per drawing and Techical specification
LHS
Ch:1775 - 1800 1 x 1 25 (5.645 + 5.807 ) 0.150 42.95 Cu.m
6 Granite rough stone dry packing for revertment including cost, conveyance, labour for filling, hire charges
to T&p etc., Complete as per drawing and Techical specification
LHS
Ch:1775 - 1800 1 x 1 25 (4.385 + 5.807 ) 0.300 76.44 Cu.m
RHS
Ch:1775 - 1800 1 x 1 25 (4.385 + 4.671 ) 0.300 67.92 Cu.m
NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600 to
12700 (LHS)
0.40
Earth Filling
2.67
2 1
0.15 0.075
0.75
0.850 0.400
1.40 0.00
R.W.SECTION
b (Toe)
DIMENSIONS (m)
SOIL PROPERTIES
Angle of Repose φ = 35 °
Angle of Wall Friction δ = 22.5 °
Angle of Surcharge β = 0 °
Angle of Internal Wall Slo α = 90 °
Unit Weight of Soil γ = 18.8 kN/m3
OTHER DETAILS
Grade of Concrete = M 25
NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600
to 12700 (LHS)
GS ASSOCIATES
COIMBATORE.
Offset of second footing on toe side = 0.00 m
SOIL PARAMETERS:
CONCRETE:
GS ASSOCIATES
COIMBATORE.
As per Cl. 710.1.1, when surface reinforcement at not provided, the permissbile stress
level shall be kept only upto 90% of the allowable stresses. After applying reduction factor of
90%,
The intensity of Earth Pressure is calculated using the "Coulomb's Formula" and the
coefficients of Active and Passive Earth Pressures are calculated as follows:
sin2 (α + φ) 1
ka = x x cosδ
sin2 (α) x sin(α - δ) (1+k)2
sin(φ+δ) * sin(φ-β)
Where, k=
sin(α-δ) * sin(α+β)
GS ASSOCIATES
COIMBATORE.
0.843 x 0.574
k=
0.924 x 1.000
= 0.724
0.671 1
= x
1 x 0.924 2.972
= 0.244
Pa = (1/2) x ka x γ x (H)2
= 16.35 kN
= 16.35 cos(0+22.5)
= 15.11 kN
Vertical component of Active Earth Pressure, Pav = Pa sin(0+22.5)
= 16.35 sin(0+22.5)
GS ASSOCIATES
COIMBATORE.
= 6.26 kN
The calculation of moment about the toe is tabulated below. Here, the anti-clockwise
moments are taken as positive and the clockwise moments are taken as negative.
4 0 * 0 * 24 0.00 0.00 0
5 0 * 0 * 24 0.00 0.00 0
6 0 * 0 * 24 0.00 0.00 0
GS ASSOCIATES
COIMBATORE.
Pah 15.11 15.11 0.89 13.45
RV RH -88.50
GS ASSOCIATES
COIMBATORE.
CHECK FOR SLIDING
μ RV
Factor of safety against slidng, Fs =
RH
tanδ RV
=
RH
tan22.5 * 59.12
=
15.11
∑MC
Factor of safety against overturning, Fo =
∑MAC
-75.05
=
13.45
∑MC
x=
GS ASSOCIATES
COIMBATORE.
x=
∑V
-88.50
=
59.12
= -1.5 m
e= (0 / 2) - -1.5
1.5 m
b/6 = 0/6
= 0 m
1.5 > 0
Since e>b/6, Tension is developed in the structure. Hence the structure is UNSAFE which
needs REDESIGN
59.12 6 * 1.5
= 1+
0.00
0.00
= #DIV/0! 1+ #DIV/0!
= #DIV/0! kN/m2
GS ASSOCIATES
COIMBATORE.
∑V 6e
Minimum pressure at the base, Pmin = 1-
b
b
59.12 6 * 1.5
= 1-
0.00
0.00
= #DIV/0! 1- #DIV/0!
= #DIV/0! kN/m2
SBC
Factor of safety against bearing Fbc =
capacity failure
Pmax
175
=
#DIV/0!
= #DIV/0! #DIV/0!
#DIV/0!
GS ASSOCIATES
COIMBATORE.
NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700
(RHS) & 12600 to 12700 (LHS)
0.4
2.07
2.67
0.6
GS ASSOCIATES,
COIMBATORE.
17
CHAPTER - I
RATE OF LABOUR AS PER SCHEDULE OF RATES
Sl.
Description Rate per
No.
Assumptions
1 Over head charges
Major bridges = 25%
Minor bridges = 20%
Road works = 10%
2 Contractors Profit = 10%
3
Lead for
Lead
1 Km
0-10 Km 8.69
10-20 Km 7.44
20-40 Km 6.40
40-80 Km 6.00
Above 80Km 5.04
Loading 26.30
Unloading 26.30
0 - 0 =
Conveyance for Well Gravel =
5
Distance
Nature of route
Sl. Name of quarry / to be Cost of
for
No. Kind of metal carried Extraction
Conveyance
(Km)
Distance
Nature of route
Sl. Name of quarry / to be Cost of
for
No. Kind of metal carried Extraction
Conveyance
(Km)
Cost of Cement
Cost of Cement (Rate as per PWD) = Rs:
Storage charges 5%
Rate per MT =
Cost of Steel
As per the PWD rate :
Cost of Steel upto 16mm dia Rs.
9
Rate (As per Revised Price Rate received from Hincol CHENNAI effective
from1.8.2011)
VAT 14.50%
Surcharge on Sales tax 0%
Storage Charges on base cost 5%
Transport Charges for 500 Kms
2 X 500 0.99924
Service Charges on transport charges 5%
Rs.
Cost of Crumb Bitumen @ Site Rs
11
Km
86.90
74.40
161.30
Km
86.90
0.00
86.90
Km
86.90
29.76
116.66
Km
43.45
14
0.00
43.45
15
50.00 /Rm
25.00 /each
15.00 /each
817.52 /Cum (929*0.88)
43.00 /Kg
210.00 /m
1.30 /1 No.
7.50 /1 No.
25.00 /Kg
19.00 /each
150.00 /KL
24.20 /Kg
24.20 /Kg
165.00 /Kg
726.00 /sqm
mm deep local rate] 726.00 /sqm
2750.00 /Rm
275.00 /lit
ent
6400.00 / MT
211.39
6611.39 / MT
el
HYSD MS bars
43000.00 43000.00
19
43000.00 43000.00
86000.00 86000.00
86000.00 86000.00
2 2
43000.00 43000.00
1815.56 1815.56
44815.56 44815.56
45.60 45.60
20
LSION :
32392.00
4534.88
0.00
36926.88
5354.40
0.00
1619.60
845.00
0.00
44745.88
or 43246 /MT
34033.00
4764.62
0.00
38797.62
5625.65
0.00
1701.65
999.24
0.00
47124.16
(or) 47124.00 /MT
21
1010.83 1010.83
5% 0.00 0.00
5% 1604.15 1564.15
39921.09 38950.85
39921.00 38951.00
22
32183.00 31383.00
4505.62 4393.62
0.00 0.00
asic cost + excise duty 36688.62 35776.62
1834.43 1788.83
0.00
38523.05 37565.45
999.24 999.24
0.00 0.00
1609.15 1569.15
41131.44 40133.84
41131.00 40134.00
39921.00 38951.00
9
Chapter - 17
1 Dozer D - 50 - A15 Cutting Cum /hour 100 Per hour 1423.00 1494.00
Clearing Cum /hour 150
2 Dozer D - 80 - A12 Cutting Cum /hour 150 Per hour 2400.00 2520.00
Clearing Cum /hour 250
7 Vibratory Roller 8 tonne GSB Cum /hour 60 Per hour 994.00 1044.00
WMM Cum /hour 60
Applying bitumen
16 Bitumen pressure distributor
tack coat
Sqm/hour 1750 Per hour 692.00 727.00
13
Applying Emulsion
17 Emulsion pressure distributor
tack coat
Sqm/hour 1750 Per hour 516.00 542.00
Hot mix plant - 120 TPH DBM / BM / SDBC /
18
capacity PC
Cum/hour 40 Per hour 15100.00 15855.00
28 Pot hole repair machine Repair of pot holes Cum/hour 4 Per hour 585.00 614.00
14
29 Bitumen Boiler oil fired Bitumen spraying Capacity in litre 1500 Per hour 128.00 134.00
15
30 GSB Plant 50 cum Poducing GSB Cum/hour 40 Per hour 670.00 704.00
31 Mastic Cooker Mastic waring coat Capacity in tonne 1 Per hour 40.00 42.00
32 Batching and mixing plant
a) 30 Cum capacity Concrete mixing Cum / hour 20 Per hour 1440.00 1512.00
b) 15 - 20 Cum capacity Concrete mixing Cum / hour 13 Per hour 1200.00 1260.00
Transportation of
Cum/hour 4.5 Per hour 600.00 630.00
33 Transit mixer
concrete mix to site
Cum/hour 3 Per hour 550.00 578.00
34
Concrete pump of 45 & 30 Cum
Cum / hour 33 Per hour 165.00 173.00
Pumping of concrete
capacity
Cum / hour 22 Per hour 165.00 173.00
35 Cranes
a) 0.40/0.28 cum Concrete mixing Cum / hour 2.5 Per hour 150.00 158.00
16
b) 0.10 Cum Concrete mixing Cum / hour 7.5 Per hour 150.00 158.00
17
41 Integrated stone crusher Crushing of spalls TPH 100 Per hour 5590.00 5870.00
Stressing of steel
42 Prestressing jack with pump
wires / strands
Per hour 83.00 87.00
43 Generator
a) 100 KVA
Generation of
KVA 100 Per hour 450.00 473.00
electric energy
b) 33 KVA KVA 50 Per hour 240.00 252.00
Pneumatic sinking
44 Pneumatic sinking plant
of wells
Cum / hour 1.5 to 2.0 Per hour 2690.00 2825.00
Per Km 14.50 15.00
45 Truck 5.50 cum per 10 tonnes Material transport Capacity / Cum 4.5
Per tonne
Km 1.60 2.00
46 Road marking machine Road marking Sqm / hour 100 Per hour 60.00 63.00
Mixing and laying
47 Mobile slurry seal equipment
slurry seal
Sqm / hour 2700 Per hour 650.00 683.00
Plate compactor / power
48
rammer
Per hour 100.00 105.00
18
Notes :The Usage rates given above are for the year 2001-2002. For subsequent years, escalation is requ
upon the market situation .
19
k and
H / 98 / dated 21.3.2002 .
Usage rates in Rs:
As per
2003-04 2004-05 2005-06 2006-07 2012-13 2007-08
rates rates rates rates rates rates
Chapter - 12
Foundation
Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m :
a) Labour :
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /
Tot
Total [
C) Contractor's profit 10% on 1395.07
Rate for 10 cum
Rate for 1 cum = 1534.58 /
Earth Work for foundation in ordinary
soil excluding dewatering = 153.46 /
-depth upto 3 m
16
Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m [Including dewatering]:
a) Labour :
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /
A. Manual Means:
(ii) Depth 3 m to 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.18 Nos Mate 329.00 /
4.50 Nos Mazdoor 319.00 /
A. Manual Means:
(iii) Depth above 6 m [including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.24 Nos Mate 329.00 /
6.00 Nos Mazdoor 319.00 /
B. MECHANICAL MEANS
(i) Depth upto 3 m [ including dewatering]:
Unit = = Cum
Taking Output = = 240 cum
a) Labour :
0.32 Nos Mate 329.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity
1302.00 /
Tot
Total [
Add for dewatering on cost of
5% labour & machinary
10469.28
T
(i) For major bridges and minor bridges
b) Overheads 25% on 10992.74
Total [
C) Contractor's profit 10% on 13740.93
Rate for 240 cum
Rate for 1 cum = 15115.02 /
B. MECHANICAL MEANS
(ii) Depth 3 m to 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 210 cum
a) Labour :
0.32 Nos Mate 329.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity 1302.00 /
Tot
Total [
Add for dewatering on cost of
7.5% labour & machinary
10469.28
T
(i) For major bridges and minor bridges
b) Overheads 25% on 11254.48
Total [
C) Contractor's profit 10% on 14068.10
Rate for 210 cum
Rate for 1 cum = 15474.91 /
Earth Work for foundation in ordinary
soil mechanically for depth 3 to 6 m
= 73.69 /
B. MECHANICAL MEANS
(iii) Depth above 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 180 cum
a) Labour :
0.40 Nos Mate 329.00 /
10.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity
1302.00 /
Tot
Total [
Add for dewatering on cost of
10.0% labour & machinary
11133.60
T
(i) For major bridges and minor bridges
b) Overheads 25% on 12246.96
Total [
C) Contractor's profit 10% on 15308.70
Rate for 180 cum
Rate for 1 cum = 16839.57 /
Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m [Excluding dewatering]:
a) Labour :
0.20 Nos Mate 329.00 /
5.00 Nos Mazdoor 319.00 /
A. MANUAL MEANS
(i) Depth upto 3 m [including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.35 Nos Mate 329.00 /
0.50 Nos Driller 282.00 /
0.25 Nos Blaster 282.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Air compressor 250 cfm with 2 jack
1.00 Hour hammer for drilling 319.00 /
Tot
Total [
C) Materials
3.50 Kg Blasting materials 25.00 /
14.00 Nos. Detonator electric 19.00 /
Tota
Total [a+
Add for dewatering on cost of labour and
10.0% machinary 3197.65
T
(i) For major bridges and minor bridges
d) Overheads 25% on 3870.92
Total [a+b+
e) Contractor's profit 10% on 4838.65
Rate for 10 cum
Rate for 1 cum = 5322.52 /
31
b) Material:
2500 Nos. Brick Class -I 5460.00 /
1.20 Cum Cement mortar 3979.78 /
Tot
Total [
(i) For major bridges and minor bridges
d) Overheads 25% on 22939.66
Total [a+
e) Contractor's profit 10% on 28674.58
a) Labour :
0.66 Nos Mate 329.00 /
7.50 Nos Mason class I 451.00 /
9.00 Nos Mazdoor 319.00 /
Tot
40
b) Material:
5.50 Cum Coarsed rubble stone 464.30 /
Bond Stone [35 Nos X 0.24 X 0.24
0.79 Cum X 0.39 =0.79 Cum] 681.30 /
12.8
A. Plain cement concrete M 15 [1:2:4 nominal mix] in foundation with cru
stone aggregates 40 mm nominal size mechanically mixed, place
foundation and compacted by vibrator including curing for 14 days.
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 57372.75
Total [a+b+c+
f) Contractor's profit 10% on 71715.94
Rate for 15 cum
44
-*/-*/-
49
*/-*/-*/-*/
51
12.8
F. Plain Cement concrete M 30 in foundation with crushed s
aggregates 40 mm nominal size mechanically mixed, place
foundation and compacted by vibrator including curing for 14 days
*/-*/-*/-*/
55
12.8
C. Reinforced Cement concrete M 20 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 66020.14
Total [a+b+c+
f) Contractor's profit 10% on 82525.18
Rate for 15 cum
56
-*/-*/-
57
12.8
E. Reinforced Cement concrete M 25 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days
-*/-*/-
61
*/-*/-/*-/*
63
12.8
G. Reinforced Cement concrete M 30 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days
Tot
Total [a+b+
-*/-*/-
65
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 530373.44
Total [a+b+c+
f) Contractor's profit 10% on 662966.80
Rate for 120 cum
66
12.8
H. Reinforced Cement concrete M 35 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days
-*/-*/-
69
*/-*/-/*-/*
71
Nos 46.06
Nos 1116.50
Total [a] 1162.56
r bridges
290.64
Total [a+b] 1453.20
145.32
= 1598.52
10
cum
es and culverts
232.51
72
cum
73
Nos 46.06
Nos 1116.50
1162.56
= 116.26
Total [a] 1278.82
r bridges
319.71
Total [a+b] 1598.53
159.85
= 1758.38
10
cum
es and culverts
255.76
Total [a+b] 1534.58
153.46
= 1688.04
10
74
cum
75
Nos 59.22
Nos 1435.50
1494.72
= 224.21
Total [a] 1718.93
r bridges
429.73
Total [a+b] 2148.66
214.87
= 2363.53
10
cum
es and culverts
343.79
Total [a+b] 2062.72
206.27
= 2268.99
10
cum
76
Nos 78.96
Nos 1914.00
1992.96
= 398.59
Total [a] 2391.55
r bridges
597.89
Total [a+b] 2989.44
298.94
= 3288.38
10
cum
es and culverts
478.31
Total [a+b] 2869.86
286.99
= 3156.85
/ 10
/ cum
77
Nos 105.28
Nos 2552.00
Total [a] 2657.28
Hour 7812.00
= 523.46
Total 10992.74
r bridges
2748.19
Total [a+b] 13740.93
1374.09
= 15115.02
240
cum
es and culverts
2198.55
Total [a+b] 13191.29
1319.13
78
= 14510.42
240
cum
79
Nos 105.28
Nos 2552.00
Total [a] 2657.28
Hour 7812.00
= 785.20
Total 11254.48
r bridges
2813.62
Total [a+b] 14068.10
1406.81
= 15474.91
210
cum
es and culverts
2250.90
Total [a+b] 13505.38
1350.54
= 14855.92
210
80
cum
81
Nos 131.60
Nos 3190.00
Total [a] 3321.60
Hour 7812.00
= 1113.36
Total 12246.96
r bridges
3061.74
Total [a+b] 15308.70
1530.87
= 16839.57
180
cum
es and culverts
2449.39
Total [a+b] 14696.35
1469.64
= 16165.99
82
180
cum
83
excluding dewatering]
Nos 65.80
Nos 1595.00
1660.80
= 0.00
Total [a] 1660.80
r bridges
415.20
Total [a+b] 2076.00
207.60
= 2283.60
10
cum
es and culverts
332.16
Total [a+b] 1992.96
199.30
= 2192.26
10
84
cum
85
excluding dewatering]
Nos 78.96
Nos 1914.00
Total [a] 1992.96
Hour 7812.00
Total [b] 7812.00
Total [a+b] 9804.96
= 0.00
Total 9804.96
r bridges
2451.24
Total [a+b] 12256.20
1225.62
= 13481.82
180
cum
es and culverts
1960.99
Total [a+b] 11765.95
1176.60
86
= 12942.55
180
cum
87
cluding dewatering]
Nos 115.15
Nos 141.00
Nos 70.50
Nos 2552.00
Total [a] 2878.65
Hour 319.00
Kg 87.50
Nos. 266.00
Total [C] 353.50
Total [a+b+c] 3551.15
= 319.77
Total 3870.92
r bridges
967.73
Total [a+b+c+d] 4838.65
483.87
= 5322.52
10
88
cum
89
es and culverts
774.18
Total [a+b+c+d] 4645.10
464.51
= 5109.61
10
cum
Nos 3.29
Nos 95.70
Total [a] 98.99
Cum 355.33
Total [b] 355.33
Total [a+b] 454.32
r bridges
113.58
Total [a+b+c] 567.90
56.79
= 624.69
1
cum
90
es and culverts
90.86
Total [a+b+c] 545.18
54.52
= 599.70
1
cum
91
Nos 210.56
Nos 451.00
Nos 4785.00
Total [a] 5446.56
Cum 13625.55
Cum 1978.16
Tonne 20561.43
KL 2700.00
Total [b] 38865.14
Hour 1398.00
Hour 2232.00
Hour 620.00
Total [c] 4250.00
Total [a+b+c] 48561.70
r bridges
12140.43
Total [a+b+c+d] 60702.13
92
6070.21
= 66772.34
15
cum
93
es and culverts
9712.34
Total [a+b+c] 58274.04
5827.40
= 64101.44
15
cum
Nos 13.16
Nos 287.10
Total [a] 300.26
Tonne 3371.81
Cum 307.71
Total [b] 3679.52
cum
Nos 157.92
Nos 1804.00
Nos 2552.00
Total [a] 4513.92
95
2867.46
= 31542.04
5
cum
es and culverts
4587.93
Total [a+b+c] 27527.59
2752.76
= 30280.35
5
cum
3 in foundation as per drawing and
96
Nos 217.14
Nos 3382.50
Nos 2871.00
Total [a] 6470.64
97
Cum 2553.65
Cum 538.23
Cum 5969.67
Total [b] 9061.55
Total [a+b] 15532.19
r bridges
3883.05
Total [a+b+c] 19415.24
1941.52
= 21356.76
5
cum
es and culverts
3106.44
Total [a+b+c] 18638.63
1863.86
= 20502.49
5
cum
98
d / uncoursed]
Nos 203.98
Nos 2706.00
Nos 2871.00
Total [a] 5780.98
Cum 2971.65
Cum 538.23
Cum 6168.66
Total [b] 9678.54
Total [a+b] 15459.52
r bridges
3864.88
Total [a+b+c+d] 19324.40
1932.44
= 21256.84
5
cum
es and culverts
3091.90
Total [a+b+c] 18551.42
99
1855.14
= 20406.56
5
cum
100
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67
Hour 1398.00
Hour 2232.00
Total [C] 3630.00
Total [a+b+c] 55166.11
0 2206.64
15
cum
es and culverts
11474.55
Total [a+b+c+d+e] 68847.30
6884.73
= 75732.03
15
cum
102
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34114.78
Total [b] 51397.89
Total [a+b] 58737.33
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 62367.33
0 2494.69
Total [d] 2494.69
Total [a+b+c+d] 64862.02
r bridges
16215.51
Total [a+b+c+d+e] 81077.53
8107.75
= 89185.28
103
15
cum
es and culverts
12972.40
Total [a+b+c+d+e] 77834.42
7783.44
= 85617.86
15
cum
104
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 39602.24
Total [b] 56885.35
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 67854.79
0 2544.55
Total [d] 2544.55
Total [a+b+c+d] 70399.34
r bridges
17599.84
Total [a+b+c+d+e] 87999.18
8799.92
= 96799.10
105
15
cum
es and culverts
14079.87
Total [a+b+c+d+e] 84479.21
8447.92
= 92927.13
15
cum
106
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 317016.23
Total [b] 455281.07
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 500554.43
0 18770.79
Total [d] 18770.79
Total [a+b+c+d] 519325.22
r bridges
129831.31
Total [a+b+c+d+e] 649156.53
64915.65
107
= 714072.18
120
cum
es and culverts
103865.04
Total [a+b+c+d+e] 623190.26
62319.03
= 685509.29
120
cum
108
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 40197.26
Total [b] 57480.37
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 68449.81
0 2395.74
Total [d] 2395.74
Total [a+b+c+d] 70845.55
r bridges
17711.39
Total [a+b+c+d+e] 88556.94
109
8855.69
= 97412.63
15
cum
es and culverts
14169.11
Total [a+b+c+d+e] 85014.66
8501.47
= 93516.13
15
cum
110
d concrete pump
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 321313.63
Total [b] 459578.47
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 504851.83
0 17669.81
Total [d] 17669.81
Total [a+b+c+d] 522521.64
r bridges
130630.41
Total [a+b+c+d+e] 653152.05
65315.21
= 718467.26
111
120
cum
es and culverts
104504.33
Total [a+b+c+d+e] 627025.97
62702.60
= 689728.57
120
cum
112
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 34445.35
Total [b] 52511.46
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 63480.90
0 2539.24
15
cum
es and culverts
13204.03
Total [a+b+c+d+e] 79224.17
7922.42
= 87146.59
15
cum
114
d concrete pump
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 275430.58
Total [b] 419959.42
Total [a+b] 427330.78
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 465232.78
0 18609.31
Total [d] 18609.31
Total [a+b+c+d] 483842.09
r bridges
120960.52
Total [a+b+c+d+e] 604802.61
60480.26
= 665282.87
115
120
cum
es and culverts
96768.42
Total [a+b+c+d+e] 580610.51
58061.05
= 638671.56
120
cum
116
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39998.92
Total [b] 58065.03
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 69034.47
0 2588.79
Total [d] 2588.79
Total [a+b+c+d] 71623.26
r bridges
17905.82
Total [a+b+c+d+e] 89529.08
8952.91
= 98481.99
117
15
cum
es and culverts
14324.65
Total [a+b+c+d+e] 85947.91
8594.79
= 94542.70
15
cum
118
d concrete pump
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 319859.13
Total [b] 464387.97
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 509661.33
0 19112.30
Total [d] 19112.30
Total [a+b+c+d] 528773.63
r bridges
132193.41
Total [a+b+c+d+e] 660967.04
66096.70
= 727063.74
120
119
cum
es and culverts
105754.73
Total [a+b+c+d+e] 634528.36
63452.84
= 697981.20
120
cum
120
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 69365.04
0 2427.78
r bridges
17948.21
Total [a+b+c+d+e] 89741.03
8974.10
121
= 98715.13
15
cum
es and culverts
14358.56
Total [a+b+c+d+e] 86151.38
8615.14
= 94766.52
15
cum
122
d concrete pump
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 322635.91
Total [b] 467164.75
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 512438.11
0 17935.33
120
cum
es and culverts
106074.69
Total [a+b+c+d+e] 636448.13
63644.81
= 700092.94
120
cum
124
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22
Total [a+b] 67255.66
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 70885.66
0 2126.57
Total [d] 2126.57
Total [a+b+c+d] 73012.23
r bridges
18253.06
Total [a+b+c+d+e] 91265.29
9126.53
= 100391.82
125
15
cum
es and culverts
14602.45
Total [a+b+c+d+e] 87614.68
8761.47
= 96376.15
15
cum
126
d concrete pump
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 524603.07
0 15738.09
Total [d] 15738.09
Total [a+b+c+d] 540341.16
r bridges
135085.29
Total [a+b+c+d+e] 675426.45
67542.65
= 742969.10
127
120
cum
es and culverts
108068.23
Total [a+b+c+d+e] 648409.39
64840.94
= 713250.33
120
cum
44
Data for pile, pile cap, levelling course below pile cap and steel for
Pile foundation.
-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
172.80 Kg Admixture 24.20 /
50.28 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
48
d) Form work
On cost of materials and labour
towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under 488515.89
water concreteing with tremie
pipe
Total [d]
Rate for 120 cum Total [a+b+c+d]
Rate for 1 Cum 550843.68 /
= 4590.36
Data for Cast in situ pilec 750 mm dia
Unit = Rm
Taking Output = 15 Rm
a) Machinary
Hydraulic piling rig with power
unit and complete accessories
6.00 Hour including shifting from one bore
5464.00 /
to another bore location
Total [a+b+c]
(i) For major bridges and minor bridges
e) Overheads 25% on 72108.04
Total [a+b+c+d+e]
f) Contractor's profit 10% on 90135.05
Rate for 15 Rm
Rate for 1 Rm = 99148.56 /
Cast in situ 750 mm dia. pile in RCC M 35
grade using Batching plant
= 6609.90 /
51
-*/-*/-
12.24 Bored cast -in situ M 35 grade RC pile excluding
reinforcement complete as per drawing and techincal
specifications and removal of excavated earth with all lead
and lifts upto 1000 m
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
21.60 Kg Admixture 24.20 /
6.75 Cum Sand for mortar 293.06 /
52
b) Labour
0.16 Nos Mate 329.00 /
4.00 Nos Mazdoor 319.00 /
Total [b]
c) Materials
7.85 Cum Cost of concrete M 35 grade 4672.09 /
Total [c]
Total [a+b+c]
-*/-*/-
55
Rate for 10 Rm
Rate for 1 Rm = 109128.12 /
-*/-*/-
12.25 Bored cast -in situ M 35 grade RC pile excluding reinforcement
complete as per drawing and techincal specifications and removal of
excavated earth with all lead and lifts upto 1000 m
Pile diameter = 1200 mm
Case : I Using Concrete Mixer
MORT & H Specifitation No: 1100,1600 & 1700
Unit = Cum
Taking Output = 15 Cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
60
Total [a+b]
-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
64
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
172.80 Kg Admixture 24.20 /
50.28 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
Data for Cast in situ piles 1200 mm dia using batching plant:
Unit = Rm
Taking Output = 9 Rm
a) Machinary for boring and construction:
Rate for 9 Rm
Rate for 1 Rm = 125368.20 /
Cast in situ 1200 mm dia. pile in RCC M 35
grade using Batching plant
= 13929.80 /
67
-*/-*/-
12.37 Pile load test on single vertical pile in accordance with
IS:2911(Part-IV)
MORT& H Specification No : 1100
Unit = MT
Taking output = 1 MT
1 MT Initial and routine load test 300.00 /
1 MT Lateral load test 5000.00 /
Note: Although this item is incidental to work and is not required to
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work
-*/-*/-
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /
Total [a]
69
b) Material:
5.12 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 0.40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary 63218.04 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 65746.76
Total [a+b+c+d+e]
f) Contractor's profit 10% on 82183.45
Rate for 15 Cum
Rate for 1 cum = 90401.80 /
Total [a+b+c+d+e]
f) Contractor's profit 10% on 78896.11
Rate for 15 Cum
Rate for 1 cum = 86785.72 /
-*/-*/-
71
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.12 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /
Total [a+b+c]
d) Form work
On cost of materials, labhour and
4.00% machinary
58110.96
Total [d]
Total [a+b+c+d]
73
*/-*/-/*-/*
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.
a) Labour :
0.90 Nos Mate 329.00 /
74
Total [a]
75
b) Material:
5.99 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary 68969.95 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 71728.75
Total [a+b+c+d+e]
f) Contractor's profit 10% on 89660.94
Rate for 15 Cum
Rate for 1 cum = 98627.03 /
Total [a+b+c+d+e]
f) Contractor's profit 10% on 86074.50
Rate for 15 Cum
Rate for 1 cum = 94681.95 /
-*/-*/-
77
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.99 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /
Total [a+b+c]
d) Form work
Total [d]
Total [a+b+c+d]
79
*/-*/-/*-/*
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.
a) Labour :
0.90 Nos Mate 329.00 /
80
Total [a]
81
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary
69697.20 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 72485.09
Total [a+b+c+d+e]
f) Contractor's profit 10% on 90606.36
Rate for 15 Cum
Rate for 1 cum = 99667.00 /
Total [a+b+c+d+e]
f) Contractor's profit 10% on 86982.11
Rate for 15 Cum
Rate for 1 cum = 95680.32 /
-*/-*/-
83
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labhour and
4% machinary 64590.12
Total [d]
Total [a+b+c+d]
85
*/-*/-/*-/*
a) Labour :
86
Total [a]
87
b) Material:
6.33 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4% machinary
71217.82 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 74066.53
Total [a+b+c+d+e]
f) Contractor's profit 10% on 92583.16
Rate for 15 Cum
Rate for 1 cum = 101841.48 /
Total [a+b+c+d+e]
f) Contractor's profit 10% on 88879.84
Rate for 15 Cum
Rate for 1 cum = 97767.82 /
-*/-*/-
89
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.33 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /
Total [a+b+c]
d) Form work
On cost of materials, labhour and
4% machinary 66110.74
Total [d]
Total [a+b+c+d]
91
*/-*/-/*-/*
a) Labour :
92
b) Material:
4.13 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
-*/-*/-
95
Total [a+b+c]
d) Contractor's profit 10% on 60085.85
Rate for 1 MT
Rate for 1 MT = 66094.44 /
HYSD bars for piles = 66094.44 /
-*/-*/-
97
Total [a+b+c]
d) Contractor's profit 10% on 60393.49
Rate for 1 MT
Rate for 1 cum = 66432.84 /
Mild steel bars for piles = 66432.84 /
-*/-*/-
99
pile excluding
and techincal
th with all lead
Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60
Cum 5450.22
Cum 7243.02
Cum 2611.71
Kg 522.72
Cum 1978.16
Tonne 41585.65
Total [b] 59391.48
Total [a+b] 66744.08
100
0 3337.20
Cum = 70081.28
15
101
Hour 32784.00
Hour 178.50
Hour 241.80
Hour 93.00
Kg 7260.00
Total [a] 40557.30
Nos 46.06
Nos 1116.50
Total [b] 1162.56
Cum 30929.24
Total [c] 30929.24
Total [a+b+c] 72649.10
ges
18162.28
Total [a+b+c+d] 90811.38
9081.14
= 99892.52
15
Rm
102
d culverts
14529.82
Total [a+b+c+d+e] 87178.92
8717.89
= 95896.81
15
Rm
oncrete pump
Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52
Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89
Hour 13392.00
Hour 4188.00
103
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 526417.89
104
0 24425.79
Hour 32784.00
Hour 178.50
Hour 241.80
Hour 93.00
Kg 7260.00
Total [a] 40557.30
Nos 46.06
Nos 1116.50
Total [b] 1162.56
Cum 30388.18
Total [c] 30388.18
105
Rm
106
d culverts
14421.61
Total [a+b+c+d+e] 86529.65
8652.97
= 95182.62
15
Rm
pile excluding
and techincal
th with all lead
Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60
Cum 5450.22
Cum 7243.02
Cum 2611.71
Kg 522.72
Cum 1978.16
107
Tonne 41585.65
Total [b] 59391.48
Total [a+b] 66744.08
108
0 3337.20
Cum = 70081.28
15
Hour 32784.00
Hour 178.50
Hour 322.40
Hour 124.00
Kg 8470.00
Total [a] 41878.90
109
Nos 52.64
Nos 1276.00
Total [b] 1328.64
Cum 36675.91
Total [c] 36675.91
Total [a+b+c] 79883.45
ges
19970.86
Total [a+b+c+d] 99854.31
9985.43
= 109839.74
10
Rm
d culverts
15976.69
Total [a+b+c+d+e] 95860.14
9586.01
= 105446.15
10
Rm
110
oncrete pump
Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52
Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 526417.89
111
0 26320.89
= 552738.78
120
cum
112
Hour 32784.00
Hour 178.50
Hour 322.40
Hour 124.00
Kg 8470.00
Total [a] 41878.90
Nos 52.64
Nos 1276.00
Total [b] 1328.64
Cum 36158.36
Total [c] 36158.36
Total [a+b+c] 79365.90
ges
19841.48
Total [a+b+c+d] 99207.38
9920.74
113
= 109128.12
10
Rm
114
d culverts
15873.18
Total [a+b+c+d+e] 95239.08
9523.91
= 104762.99
10
Rm
ng reinforcement
ns and removal of
Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60
Cum 5450.22
Cum 7243.02
Cum 2611.71
115
Kg 522.72
Cum 1978.16
Tonne 41585.65
Total [b] 59391.48
116
0 3337.20
Cum = 70081.28
15
Hour 32784.00
Hour 178.50
Hour 403.00
Hour 155.00
Kg 9317.00
Total [a] 42837.50
Nos 59.22
Nos 1435.50
Total [b] 1494.72
117
Cum 47515.16
Total [c] 47515.16
Total [a+b+c] 91847.38
118
ges
22961.85
Total [a+b+c+d] 114809.23
11480.92
= 126290.15
9
Rm
d culverts
18369.48
Total [a+b+c+d+e] 110216.86
11021.69
= 121238.55
9
Rm
oncrete pump
Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52
119
Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 526417.89
0 26320.89
= 552738.78
120
cum
120
ching plant:
Hour 32784.00
Hour 178.50
Hour 403.00
Hour 155.00
Kg 9317.00
Total [a] 42837.50
Nos 59.22
Nos 1435.50
Total [b] 1494.72
Cum 46844.65
Total [c] 46844.65
Total [a+b+c] 91176.87
ges
22794.22
Total [a+b+c+d] 113971.09
11397.11
121
= 125368.20
9
Rm
122
d culverts
18235.37
Total [a+b+c+d+e] 109412.24
10941.22
= 120353.46
9
Rm
ccordance with
MT 300.00
MT 5000.00
is not required to
is required to be
rk
Nos 296.10
Nos 676.50
Nos 6380.00
Nos 319.00
Tonne 33850.33
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 51916.44
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 63218.04
0 2528.72
Cum
d culverts
13149.35
125
Cum
126
d concrete pump
Nos 52.64
Nos 171.38
Nos 797.50
Nos 319.00
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 33850.33
Total [b] 51916.44
Total [a+b] 53256.96
Hour 1674.00
Hour 523.50
Hour 604.50
Hour 1860.00
Hour 192.00
Total [b] 4854.00
127
0 2324.44
ges
15108.85
Total [a+b+c+d+e] 75544.25
7554.43
= 83098.68
15
cum
d culverts
12087.08
Total [a+b+c+d+e] 72522.48
7252.25
= 79774.73
15
cum
Nos 296.10
129
Nos 676.50
Nos 6380.00
Nos 319.00
Tonne 39602.24
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 57668.35
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 68969.95
0 2758.80
Cum
d culverts
14345.75
131
Cum
132
d concrete pump
Nos 52.64
Nos 171.38
Nos 797.50
Nos 319.00
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39602.24
Total [b] 57668.35
Total [a+b] 59008.87
Hour 1674.00
Hour 523.50
Hour 604.50
Hour 1860.00
Hour 192.00
Total [b] 4854.00
133
0 2554.51
ges
16604.35
Total [a+b+c+d+e] 83021.73
8302.17
= 91323.90
15
cum
d culverts
13283.48
Total [a+b+c+d+e] 79700.86
7970.09
= 87670.95
15
cum
Nos 296.10
135
Nos 676.50
Nos 6380.00
Nos 319.00
Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 69697.20
0 2787.89
Cum
d culverts
14497.02
137
Cum
138
d concrete pump
Nos 52.64
Nos 171.38
Nos 797.50
Nos 319.00
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60
Total [a+b] 59736.12
Hour 1674.00
Hour 523.50
Hour 604.50
Hour 1860.00
Hour 192.00
139
0 2583.60
ges
16793.43
Total [a+b+c+d+e] 83967.15
8396.72
= 92363.87
15
cum
d culverts
13434.74
Total [a+b+c+d+e] 80608.46
8060.85
= 88669.31
15
cum
Nos 296.10
Nos 676.50
Nos 6380.00
Nos 319.00
Tonne 41850.11
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 59916.22
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 71217.82
0 2848.71
Cum
d culverts
14813.31
143
Cum
144
d concrete pump
Nos 52.64
Nos 171.38
Nos 797.50
Nos 319.00
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22
Total [a+b] 61256.74
Hour 1674.00
Hour 523.50
Hour 604.50
Hour 1860.00
Hour 192.00
Total [b] 4854.00
145
0 2644.43
ges
17188.79
Total [a+b+c+d+e] 85943.96
8594.40
= 94538.36
15
cum
d culverts
13751.03
Total [a+b+c+d+e] 82506.20
8250.62
= 90756.82
15
cum
concrete M
& 1700
147
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
148
Tonne 27305.05
Cum 1978.16
Cum 8175.33
Cum 5432.27
Cum 1305.86
Total [b] 44196.67
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 55166.11
ges
13791.53
Total [a+b+c+d] 68957.64
6895.76
= 75853.40
15
Cum
d culverts
11033.22
Total [a+b+c+d] 66199.33
6619.93
149
= 72819.26
15
Cum
150
reinforcement in
cal specifications.
Nos 131.60
Nos 696.00
Nos 1914.00
Total [a] 2741.60
Tonne 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50071.54
ges
12517.89
Total [a+b+c+d] 62589.43
6258.94
= 68848.37
1
MT
d culverts
10014.31
151
reinforcement in
cal specifications.
Nos 141.47
Nos 783.00
Nos 2073.50
Total [a] 2997.97
Tonne 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50327.91
ges
12581.98
Total [a+b+c+d] 62909.89
6290.99
= 69200.88
1
MT
d culverts
10065.58
153
CHAPTER - 13
Sl. No. Quantity Description Rate per
13.1. Brickwork in Cement mortar 1:3 in substructure complete
excluding pointing as per drawing and technical
specification
Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 4536.93
Total [a+b+c+d]
e) Contractor's profit 10% on 5671.16
Rate for 1 cum
Rate for 1 cum = 6238.28 /
Brickwork in CM 1:3 for sub structure = 6238.28 /
76
*/-*/-/*-/*
Total [a+b+c]
e) Contractor's profit 10% on 621.06
Rate for 10 Sqm
Rate for 1 sqm = 683.17 /
Pointing Brickwork in CM 1:3 for sub = 68.32 /
structure
*/-*/-/*-/*
78
b) Material:
1.000 Cum Stone for RR masonry work 540.30 /
0.160 Cum Bond stones 681.30 /
0.330 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
c) Scaffolding
5% On cost of materials, labour and 2919.54
machinary
Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
c) Overheads 25% on 3065.52
Total [a+b+c]
d) Contractor's profit 10% on 3831.90
Rate for 1 Cum
Rate for 1 cum = 4215.09 /
Random rubble masonry in Cement = 4215.09 /
mortar 1:3 for sub structure
a. PCC M 15 :
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
4.13 Tonne Cement 6611.39 /
Total [b]
83
Total [a+b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
PCC M 15 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
84
d) Form work
On cost of materials, labour and
10% machinary 55166.11 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 60682.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 75853.40
Rate for 15 cum
Rate for 1 cum = 83438.74 /
PCC M 15 for substructure upto 5 m = 5562.58 /
height
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 60682.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 72819.26
Rate for 15 cum
Rate for 1 cum = 80101.19 /
PCC M 15 for substructure upto 5 m = 5340.08 /
height
PCC M 15 - from 5m to 10m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
Add for extra lift on cost of
2% materials, labour and machinary
55166.11 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 61786.04
85
Total [a+b+c+d+e]
f) Contractor's profit 10% on 77232.55
Rate for 15 cum
Rate for 1 cum = 84955.81 /
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
Add for extra lift on cost of
2% materials, labour and machinary
62367.33 /
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 67854.79 /
Total [d]
Total [a+b+c+d]
91
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 77354.46
Total [a+b+c+d+e]
f) Contractor's profit 10% on 96693.08
Rate for 15 cum
Rate for 1 cum = 106362.39 /
PCC M 25 for sub structure using concrete
mixer from 5 m to 10 m height
= 7090.83 /
92
Total [a+b+c+d+e]
f) Contractor's profit 10% on 688262.34
Rate for 120 cum
Rate for 1 cum = 757088.57 /
PCC M 25 for substructure with batching plant
for height upto 5 m
= 6309.07 /
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 78032.79
Total [a+b+c+d+e]
f) Contractor's profit 10% on 97540.99
Rate for 15 cum
Rate for 1 cum = 107295.09 /
PCC M 30 for substructure using concrete mixer
for height from 5 m to 10 m
= 7153.01 /
99
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 575531.09
Total [a+b+c+d+e]
f) Contractor's profit 10% on 719413.86
Rate for 120 Cum
Rate for 1 cum = 791355.25 /
PCC M 30 for substructure with batching plant
for height from 5 m to 10 m
= 6594.63 /
102
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift
62885.88 /
On cost of materials, labour and
12% machinary for form work 62885.88 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 71689.91
Total [a+b+c+d+e]
f) Contractor's profit 10% on 89612.39
Rate for 15 Cum
Rate for 1 cum = 98573.63 /
RCC M 20 for substructure using concrete mixer
for height from 5 m to 10 m
= 6571.58 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 71689.91
Total [a+b+c+d+e]
f) Contractor's profit 10% on 86027.89
Rate for 15 Cum
Rate for 1 cum = 94630.68 /
RCC M 20 for substructure using concrete mixer
for height from 5 m to 10 m
= 6308.71 /
-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
106
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
Total [a+b+c]
RCC M 20 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 465232.78 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 511756.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 639695.08
Rate for 120 cum
Rate for 1 cum = 703664.59 /
RCC M 20 for substructure with batching = 5863.87 /
plant for height upto 5 m
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 511756.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 614107.27
Rate for 120 cum
Rate for 1 cum = 675518.00 /
RCC M 20 for substructure with batching = 5629.32 /
plant for height upto 5 m
-*/-/*-/*-/*-/*-
108
Total [c]
13.5.f. RCC M25 Using Batching Plant, transit mixer and concrete p
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.38 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [c]
RCC M 25 - upto 5 m height using batching plan
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
509661.33
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 560627.46
Total [a+b+c+d+e]
114
d) Form work
On cost of materials, labour and
10% machinary
69365.04
Total [d]
Total [a+b+c+d]
d) Form work
On cost of materials, labour and
1.6% machinary for extra lift
512438.11
On cost of materials, labour and
11.5% machinary for form work 512438.11
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 579567.50
Total [a+b+c+d+e]
f) Contractor's profit 10% on 724459.38
Rate for 120 cum
Rate for 1 cum = 796905.32 /
RCC M 30 for Sub structure with batching plant
for height from 5 -10 m
= 6640.88 /
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.33 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
1.4% machinary for extra lift 70885.66
On cost of materials, labour and
11.0% machinary for form work
70885.66
Total [d]
Total [a+b+c+d]
125
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
50.64 Tonne Cement 6611.39 /
Total [b]
C) Machinary
126
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
127
d) Form work
On cost of materials, labour and
10% machinary
524603.07
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 577063.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 721329.23
Rate for 120 cum
Rate for 1 cum = 793462.15 /
RCC M 35 for substructure with batching plant
for height upto 5 m
= 6612.18 /
Total [d]
Total [a+b+c+d]
128
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages 44815.56 /
6.00 Kg Binding wires 45.60 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 50211.30
Total [a+b+c]
d) Contractor's profit 10% on 62764.13
Rate for 1 MT
Rate for 1 cum = 69040.54 /
HYSD reinforcement for substructure = 69040.54 /
(ii) For minor bridges in road packages and culverts
130
### Back filling behind abutment, wing walls / return wall complete as per
techinical specifications.
-*/-*/-
13.10. Providing and laying of filter media with granular materi
crushed aggregates satisfying the requirements laid dow
2504.2.2 of MORT & H specifications to a thickness of not l
mm with smaller size towards the wall and provided ov
surface behind abutment, wing walls and return walls to th
compacted to a firm condition complete as per drawing a
specifications.
b) Material:
Sand for filling 296.11
Gravel 246.95
Sand for mortar 293.06
836.12 /
Granular material = 278.71
Filter media conforming to
12.00 Cum clause 2504.2.2. of MORT &H 278.71 /
specification
Total [b]
C) Machinary
0.06 Hour Water tanker 310.00 /
Total [c]
Total [a+b+c]
Nos 19.74
Nos 360.80
Nos 255.20
Total [a] 635.74
Nos 13.16
Nos 287.10
Total [i] 300.26
Tonne 3371.81
Cum 307.71
Total [ii] 3679.52
cum
1000 2730.00
Cum 955.15
Total [b] 3685.15
Total [a+b] 4320.89
0 216.04
es and culverts
907.39
Total [a+b+c+d] 5444.32
544.43
= 5988.75
1
cum
on Brickwork in
ing and technical
Nos 13.16
Nos 225.50
Nos 159.50
Total [a] 398.16
Cum 119.39
Total [b] 119.39
Total [a+b] 517.55
bridges
129.39
Total [a+b+c] 646.94
64.69
= 711.63
10
Sqm
es and culverts
103.51
140
on Brickwork in
ing and technical
Nos 13.16
Nos 225.50
Nos 159.50
Total [a] 398.16
Cum 573.09
Total [b] 573.09
Total [a+b] 971.25
bridges
242.81
Total [a+b+c] 1214.06
121.41
= 1335.47
10
Sqm
es and culverts
194.25
Total [a+b+c] 1165.50
116.55
= 1282.05
10
Sqm
142
oarsed]:
Nos 32.90
Nos 541.20
Nos 382.80
Total [a] 956.90
143
Cum 540.30
Cum 109.01
Cum 1313.33
Total [b] 1962.64
Total [a+b] 2919.54
0 145.98
es and culverts
613.10
Total [a+b+c] 3678.62
367.86
= 4046.48
1
Cum
Nos 39.48
144
Nos 676.50
Nos 478.50
Total [a] 1194.48
Cum 510.73
Cum 109.01
Cum 1193.93
Total [b] 1813.67
Total [a+b] 3008.15
0 150.41
Total [c] 150.41
Total [a+b+c] 3158.56
145
bridges
789.64
Total [a+b+c] 3948.20
394.82
= 4343.02
1
Cum
es and culverts
631.71
Total [a+b+c] 3790.27
379.03
= 4169.30
1
Cum
e complete as per
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67
146
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
44196.67
3630.00
Total [a+b+c] 55166.11
147
0 5516.61
Total [d] 5516.61
Total [a+b+c+d] 60682.72
bridges
15170.68
Total [a+b+c+d+e] 75853.40
7585.34
= 83438.74
15
cum
es and culverts
12136.54
Total [a+b+c+d+e] 72819.26
7281.93
= 80101.19
15
cum
to 10m height:
7339.44
44196.67
3630.00
Total [a+b+c] 55166.11
0 1103.32
0 6619.93
cum
149
es and culverts
12357.21
Total [a+b+c+d+e] 74143.25
7414.33
= 81557.58
15
cum
g Concrete mixer:
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34114.78
Total [b] 51397.89
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
51397.89
3630.00
Total [a+b+c] 62367.33
150
0 6236.73
Total [d] 6236.73
Total [a+b+c+d] 68604.06
bridges
17151.02
Total [a+b+c+d+e] 85755.08
8575.51
= 94330.59
15
cum
151
es and culverts
13720.81
Total [a+b+c+d+e] 82324.87
8232.49
= 90557.36
15
cum
to 10m height:
7339.44
51397.89
3630.00
Total [a+b+c] 62367.33
0 1247.35
0 7484.08
Total [d] 8731.43
Total [a+b+c+d] 71098.76
bridges
17774.69
Total [a+b+c+d+e] 88873.45
8887.35
= 97760.80
15
Cum
es and culverts
14219.75
Total [a+b+c+d+e] 85318.51
8531.85
= 93850.36
15
152
Cum
153
structure:
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 39602.24
Total [b] 56885.35
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
56885.35
3630.00
Total [a+b+c] 67854.79
0 6785.48
Total [d] 6785.48
Total [a+b+c+d] 74640.27
154
bridges
18660.07
Total [a+b+c+d+e] 93300.34
9330.03
= 102630.37
15
cum
es and culverts
14928.05
Total [a+b+c+d+e] 89568.32
8956.83
= 98525.15
15
cum
to 10 m height:
7339.44
56885.35
3630.00
Total [a+b+c] 67854.79
0 1357.10
0 8142.57
cum
155
es and culverts
15470.89
Total [a+b+c+d+e] 92825.35
9282.54
= 102107.89
15
cum
156
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 317016.23
Total [b] 455281.07
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
5m height:
7371.36
455281.07
37902.00
Total [a+b+c] 500554.43
0 50055.44
Total [d] 50055.44
Total [a+b+c+d] 550609.87
bridges
137652.47
157
cum
es and culverts
110121.97
Total [a+b+c+d+e] 660731.84
66073.18
= 726805.02
120
cum
158
to 10m height:
7371.36
455281.07
37902.00
Total [a+b+c] 500554.43
0 10011.09
0 60066.53
Total [d] 70077.62
Total [a+b+c+d] 570632.05
bridges
142658.01
Total [a+b+c+d+e] 713290.06
71329.01
= 784619.07
120
cum
es and culverts
114126.41
Total [a+b+c+d+e] 684758.46
68475.85
= 753234.31
120
cum
tructure:
Nos 282.94
Nos 676.50
159
Nos 6380.00
Total [a] 7339.44
Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 40197.26
Total [b] 57480.37
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
160
5m height:
7339.44
57480.37
3630.00
Total [a+b+c] 68449.81
0 6844.98
Total [d] 6844.98
Total [a+b+c+d] 75294.79
bridges
18823.70
Total [a+b+c+d+e] 94118.49
9411.85
= 103530.34
15
cum
es and culverts
15058.96
Total [a+b+c+d+e] 90353.75
9035.38
= 99389.13
15
cum
to 10m height:
7339.44
57480.37
3630.00
Total [a+b+c] 68449.81
0 1369.00
0 8213.98
Total [d] 9582.98
161
cum
162
es and culverts
15606.56
Total [a+b+c+d+e] 93639.35
9363.94
= 103003.29
15
cum
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 321313.63
Total [b] 459578.47
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
5m height:
7371.36
459578.47
163
37902.00
Total [a+b+c] 504851.83
0 50485.18
Total [d] 50485.18
Total [a+b+c+d] 555337.01
164
bridges
138834.25
Total [a+b+c+d+e] 694171.26
69417.13
= 763588.39
120
cum
es and culverts
111067.40
Total [a+b+c+d+e] 666404.41
66640.44
= 733044.85
120
cum
o 10m height:
7371.36
459578.47
37902.00
Total [a+b+c] 504851.83
0 10097.04
0 60582.22
Cum
165
es and culverts
115106.22
Total [a+b+c+d+e] 690637.31
69063.73
= 759701.04
120
Cum
166
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 33850.33
Total [b] 51916.44
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
51916.44
3630.00
Total [a+b+c] 62885.88
0 6288.59
Total [d] 6288.59
Total [a+b+c+d] 69174.47
bridges
17293.62
Total [a+b+c+d+e] 86468.09
167
8646.81
= 95114.90
15
Cum
es and culverts
13834.89
Total [a+b+c+d+e] 83009.36
8300.94
= 91310.30
15
Cum
168
to 10m height:
7339.44
51916.44
3630.00
Total [a+b+c] 62885.88
0 1257.72
0 7546.31
Total [d] 8804.03
Total [a+b+c+d] 71689.91
bridges
17922.48
Total [a+b+c+d+e] 89612.39
8961.24
= 98573.63
15
Cum
es and culverts
14337.98
Total [a+b+c+d+e] 86027.89
8602.79
= 94630.68
15
Cum
Nos 276.36
Nos 1353.00
169
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 275430.58
Total [b] 419959.42
Total [a+b] 427330.78
170
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 465232.78
5m height:
7371.36
419959.42
37902.00
Total [a+b+c] 465232.78
0 46523.28
Total [d] 46523.28
Total [a+b+c+d] 511756.06
bridges
127939.02
Total [a+b+c+d+e] 639695.08
63969.51
= 703664.59
120
cum
es and culverts
102351.21
Total [a+b+c+d+e] 614107.27
61410.73
= 675518.00
120
cum
171
to 10m height:
7371.36
419959.42
37902.00
Total [a+b+c] 465232.78
0 9304.66
0 55827.93
Total [d] 65132.59
Total [a+b+c+d] 530365.37
172
bridges
132591.34
Total [a+b+c+d+e] 662956.71
66295.67
= 729252.38
120
cum
es and culverts
106073.07
Total [a+b+c+d+e] 636438.44
63643.84
= 700082.28
120
cum
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39998.92
Total [b] 58065.03
Hour 1398.00
Hour 2232.00
173
0 6903.45
Total [d] 6903.45
Total [a+b+c+d] 75937.92
174
bridges
18984.48
Total [a+b+c+d+e] 94922.40
9492.24
= 104414.64
15
cum
es and culverts
15187.58
Total [a+b+c+d+e] 91125.50
9112.55
= 100238.05
15
cum
1242.62
0 8146.07
Total [d] 9388.69
Total [a+b+c+d] 78423.16
bridges
19605.79
Total [a+b+c+d+e] 98028.95
9802.90
= 107831.85
15
cum
175
es and culverts
15684.63
Total [a+b+c+d+e] 94107.79
9410.78
= 103518.57
15
cum
176
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 319859.13
Total [b] 464387.97
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
using batching plant:
7371.36
464387.97
37902.00
Total [a+b+c] 509661.33
0 50966.13
Total [d] 50966.13
Total [a+b+c+d] 560627.46
bridges
140156.87
Total [a+b+c+d+e] 700784.33
177
70078.43
= 770862.76
120
cum
es and culverts
112125.49
Total [a+b+c+d+e] 672752.95
67275.30
= 740028.25
120
cum
178
9173.90
0 60140.04
Total [d] 69313.94
Total [a+b+c+d] 578975.27
bridges
144743.82
Total [a+b+c+d+e] 723719.09
72371.91
= 796091.00
120
cum
es and culverts
115795.05
Total [a+b+c+d+e] 694770.32
69477.03
= 764247.35
120
cum
179
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
180
0 6936.50
bridges
19075.39
Total [a+b+c+d+e] 95376.93
9537.69
= 104914.62
15
cum
es and culverts
15260.31
Total [a+b+c+d+e] 91561.85
9156.19
= 100718.04
15
cum
0 1109.84
0 7976.98
Total [d] 9086.82
Total [a+b+c+d] 78451.86
bridges
19612.97
Total [a+b+c+d+e] 98064.83
9806.48
= 107871.31
15
cum
182
es and culverts
15690.37
Total [a+b+c+d+e] 94142.23
9414.22
= 103556.45
15
cum
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 322635.91
Total [b] 467164.75
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
m height using batching plant:
7371.36
467164.75
183
37902.00
Total [a+b+c] 512438.11
0 51243.81
Total [d] 51243.81
Total [a+b+c+d] 563681.92
bridges
140920.48
Total [a+b+c+d+e] 704602.40
70460.24
= 775062.64
120
cum
184
es and culverts
112736.38
Total [a+b+c+d+e] 676418.30
67641.83
= 744060.13
120
cum
0 8199.01
0 58930.38
Total [d] 67129.39
Total [a+b+c+d] 579567.50
bridges
144891.88
Total [a+b+c+d+e] 724459.38
72445.94
= 796905.32
120
cum
es and culverts
115913.50
Total [a+b+c+d+e] 695481.00
69548.10
= 765029.10
120
185
cum
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
186
Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
0 7088.57
Total [d] 7088.57
Total [a+b+c+d] 77974.23
bridges
19493.56
Total [a+b+c+d+e] 97467.79
9746.78
= 107214.57
15
cum
es and culverts
15594.85
Total [a+b+c+d+e] 93569.08
9356.91
= 102925.99
15
187
cum
7339.44
59916.22
3630.00
Total [a+b+c] 70885.66
0 992.40
0 7797.42
Total [d] 8789.82
Total [a+b+c+d] 79675.48
188
bridges
19918.87
Total [a+b+c+d+e] 99594.35
9959.44
= 109553.79
15
cum
es and culverts
15935.10
Total [a+b+c+d+e] 95610.58
9561.06
= 105171.64
15
cum
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71
189
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
m height using batching plant:
7371.36
479329.71
37902.00
Total [a+b+c] 524603.07
190
0 52460.31
Total [d] 52460.31
Total [a+b+c+d] 577063.38
bridges
144265.85
Total [a+b+c+d+e] 721329.23
72132.92
= 793462.15
120
cum
es and culverts
115412.68
Total [a+b+c+d+e] 692476.06
69247.61
= 761723.67
120
cum
0 7344.44
0 57706.34
bridges
147413.46
Total [a+b+c+d+e] 737067.31
73706.73
= 810774.04
120
cum
192
es and culverts
117930.77
Total [a+b+c+d+e] 707584.62
70758.46
= 778343.08
120
cum
ar reinforcement in substructure
pecificaion
Nos 111.86
Nos 696.00
Nos 2073.50
Total [a] 2881.36
MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50211.30
bridges
12552.83
Total [a+b+c] 62764.13
6276.41
= 69040.54
1
MT
es and culverts
193
10042.26
Total [a+b+c+d+e] 60253.56
6025.36
= 66278.92
1
MT
194
el reinforcement in substructure
pecificaion
MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49698.56
bridges
12424.64
Total [a+b+c] 62123.20
6212.32
= 68335.52
1
MT
es and culverts
9939.71
Total [a+b+c+d+e] 59638.27
5963.83
= 65602.10
1
MT
195
Nos 9.87
Nos 225.50
Nos 79.75
Total [a] 315.12
RM 1575.00
Nos. 450.00
Nos. 250.00
Cum 198.99
Total [b] 2473.99
Total [a+b] 2789.11
bridges
697.28
Total [a+b+c] 3486.39
348.64
= 3835.03
30
Nos.
es and culverts
557.82
Total [a+b+c+d+e] 3346.93
334.69
= 3681.62
196
30
Nos.
197
Nos 92.12
Nos 2233.00
Total [a] 2325.12
Cum 2963.40
Total [b] 2963.40
Hour 387.50
Hour 15.50
Total [c] 403.00
Total [a+b+c] 5691.52
bridges
1422.88
Total [a+b+c+d] 7114.40
711.44
= 7825.84
10
Cum
es and culverts
1138.30
Total [a+b+c+d] 6829.82
682.98
= 7512.80
10
Cum
198
Nos 105.28
Nos 2002.00
Nos 319.00
Total [a] 2426.28
199
Cum 3344.52
Hour 18.60
Total [c] 18.60
Total [a+b+c] 5789.40
bridges
1447.35
Total [a+b+c+d] 7236.75
723.68
= 7960.43
10
Cum
es and culverts
1157.88
Total [a+b+c+d] 6947.28
694.73
= 7642.01
10
Cum
107
Chapter - 12
Foundation
Sl. No. Quantity Description Rate per
14.1. Furnishing and placing reinforced / presressed Cement concrete
superstructure as per drawing and techinical specifications.
b. FROM 5m TO 10 m HEIGHT
Cost of materials,Labour and machinary = [a+b+c
d) Form work
On cost of materials, labour and
25% machinary
62885.88 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 98259.19
Rate for 15 Cum
Rate for 1 cum = 108085.11 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7205.67 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 94328.82
Rate for 15 Cum
Rate for 1 cum = 103761.70 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 6917.45 /
d) Form work
On cost of materials, labour and
25% machinary 62885.88 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 98259.19
Rate for 15 Cum
Rate for 1 cum = 108085.11 /
RCC M 20 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7205.67 /
111
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Total
RCC M 20
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b
a. For SOLID SLAB HEIGHT UPTO 5.0 M
d) Form work
On cost of materials, labour and
20% machinary
460340.35 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 552408.42
Total [a+b+c+d
f) Contractor's profit 10% on 690510.53
Rate for 120 cum
Rate for 1 cum = 759561.58 /
RCC M 20 for Solid slab with batching plant for
height upto 5 m
= 6329.68 /
d) Form work
On cost of materials, labour and
25% machinary 460340.35 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 719281.80
Rate for 120 on
Rate for 1 cum = 791209.98 /
RCC M 20 for T-beam & slab with batching plant
for height upto 5 m
= 6593.42 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 690510.53
116
-*/-*/-*/
b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary
68637.79 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 85797.24
Total [a+b+c+d
f) Contractor's profit 10% on 107246.55
Rate for 15 Cum
Rate for 1 cum = 117971.21 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7864.75 /
-*/-*/-*/
123
d) Form work
On cost of materials, labour and
25% machinary 506877.04 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 791995.38
Rate for 120 cum
Rate for 1 cum = 871194.92 /
RCC M-25 for Solid slab with batching plant for
height from 5 m - 10 m
= 7259.96 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 760315.56
Rate for 120 cum
Rate for 1 cum = 836347.12 /
RCC M-25 for Solid slab with batching plant for
height from 5 m - 10 m
= 6969.56 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 791995.38
Rate for 120 cum
Rate for 1 cum = 871194.92 /
RCC M-25 for T-beam & slab with batching plant
for height upto 5 m
= 7259.96 /
127
-*/-*/-*/
Case I RCC Grade M-30 using concrete mixer
MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
128
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-30 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
20% machinary 69697.20 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 83636.64
Total [a+b+c+d
f) Contractor's profit 10% on 104545.80
Rate for 15 Cum
Rate for 1 cum = 115000.38 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7666.69 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 83636.64
Total [a+b+c+d
f) Contractor's profit 10% on 100363.97
Rate for 15 Cum
Rate for 1 cum = 110400.37 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7360.02 /
b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary 69697.20 /
Total
130
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 87121.50
Total [a+b+c+d
f) Contractor's profit 10% on 108901.88
Rate for 15 Cum
Rate for 1 cum = 119792.07 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7986.14 /
131
d) Form work
On cost of materials, labour and
30% machinary
69697.20 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 90606.36
Total [a+b+c+d
f) Contractor's profit 10% on 113257.95
Rate for 15 Cum
Rate for 1 cum = 124583.75 /
RCC M-30 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 8305.58 /
133
b) Material:
6.33 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-35 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
18% machinary
71217.82 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 84037.03
Total [a+b+c+d
f) Contractor's profit 10% on 105046.29
Rate for 15 Cum
Rate for 1 cum = 115550.92 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7703.39 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 84037.03
Total [a+b+c+d
f) Contractor's profit 10% on 100844.44
Rate for 15 Cum
Rate for 1 cum = 110928.88 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7395.26 /
140
b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
23% machinary
71217.82 /
Total
Total [a+b+c
141
-*/-*/-*/
Case : II RCC M-35 FOR SOLID SLAB Using Batching Plant
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
19.00 Nos Mazdoor 319.00 /
Total
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
50.64 Tonne Cement 6611.39 /
Total
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
144
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 807087.91
Rate for 120 cum
Rate for 1 cum = 887796.70 /
RCC M-35 for T-beam & slab with batching plant
for height upto 5 m
= 7398.31 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 774804.40
Rate for 120 cum
Rate for 1 cum = 852284.84 /
RCC M-35 for T-beam & slab with batching plant
for height upto 5 m
= 7102.37 /
b) For T - BEAM & SLAB HEIGHT FROM 5.0 M TO 10
Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
28% machinary 524935.23 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 671917.09
Total [a+b+c+d
f) Contractor's profit 10% on 839896.36
Rate for 120 cum
Rate for 1 cum = 923886.00 /
148
b) Material:
MS bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
6.00 Kg Binding wires 45.60 /
Total
Total [a
(i) For major bridges and minor bridges
c) Overheads 25% on 49698.56
Total [a+b
d) Contractor's profit 10% on 62123.20
Rate for 1 MT
Rate for 1 cum = 68335.52 /
CC M 30
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of M - 30 grade concrete for 15 cum
Cost of M - 30 grade concrete for 1cum =
1.00 Cum M-30 grade concrete 4646.48 /
Mazdoor for cleaning deck slab
0.15 Nos concrete surface
319.00 /
To
(i) For major bridges and minor bridges
e) Overheads 25% on 4694.33
To
f) Contractor's profit 10% on 5867.91
Rate for 1 Cum
Rate for 1 CUM = 6454.70 /
Total
C) Machinary
0.06 Hour Mechanical broom 288.00 /
0.06 Hour Air compressor 250 cfm 258.00 /
Total
CC M 30
Total (a+b+c)
(i) For major bridges and minor bridges
e) Overheads 25% on 14313.18
To
f) Contractor's profit 10% on 17891.48
Rate for 72.46 Sqm
Rate for 1 Sqm = 19680.63 /
Mastic Asphalt = 271.61 /
157
MORT & H Specification No: 1500, 1600 & 1700 & 2703
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum
233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
158
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69697.20 /
= 4646.48 /
159
Rate for 48 Rm
Rate for 1 Rm = 66675.80 /
*-*-*-*-*-*-
160
MORT & H Specification No: 1500, 1600 & 1700 & 2703
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
161
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69697.20 /
= 4646.48 /
Cost of HYSD bar reinforcements:
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages 44815.56 /
8.00 Kg Binding wires 45.60 /
Total
Total [a
Rate for 1 MT
RCC M-30 Railing USING CONCRETE MIXER
Unit = Rm
Taking Output = 48 Rm
RCC M 30 mix excluding steel
4.092 Cum reinforcement
4646.48 /
MORT & H Specification No: 1500, 1600 & 1700 & 2704
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum
233.00 /
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
169
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
8.00 Kg Binding wires 45.60 /
Total
Total [a
Rate for 1 MT
RCC M-30 For approach slab USING CONCRETE MIXE
reinforcements
Unit = Cum
Taking Output = 1 Cum
RCC M 30 mix excluding steel
1.000 Cum reinforcement 4645.60 /
*/-*/-*/-*/
171
b) Material:
Total
Total
175
ed Cement concrete in
ecifications.
te mixer
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Tonne 33850.33
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 51916.44
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7339.44
51916.44
3630.00
[a+b+c] 62885.88
178
0 12577.18
Total [a+b+c+d] 75463.06
bridges
18865.77
Total [a+b+c+d+e] 94328.83
9432.88
= 103761.71
15
Cum
179
s and culverts
15092.61
Total [a+b+c+d+e] 90555.67
9055.57
= 99611.24
15
Cum
[a+b+c] 62885.88
0 15721.47
Total [a+b+c+d] 78607.35
bridges
19651.84
Total [a+b+c+d+e] 98259.19
9825.92
= 108085.11
15
Cum
s and culverts
15721.47
Total [a+b+c+d+e] 94328.82
9432.88
= 103761.70
15
Cum
UPERSTRUCTURE USING
MIXER
[a+b+c] 62885.88
180
0 15721.47
s and culverts
15721.47
Total [a+b+c+d+e] 94328.82
9432.88
= 103761.70
15
Cum
NG CONCRETE MIXER
[a+b+c] 62885.88
0 18865.76
Total [a+b+c+d] 81751.64
bridges
20437.91
Total [a+b+c+d+e] 102189.55
10218.96
= 112408.51
15
Cum
s and culverts
16350.33
Total [a+b+c+d+e] 98101.97
9810.20
= 107912.17
15
Cum
g Batching Plant
182
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 270538.15
Total [b] 415066.99
183
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
7371.36
415066.99
37902.00
Total [a+b+c] 460340.35
5.0 M
(a+b+c) 460340.35
0 92068.07
cum
s and culverts
110481.68
Total [a+b+c+d+e] 662890.10
66289.01
= 729179.11
120
184
cum
5.0 M TO 10 M
(a+b+c) 460340.35
0 115085.09
Total [d] 115085.09
Total [a+b+c+d] 575425.44
185
bridges
143856.36
Total [a+b+c+d+e] 719281.80
71928.18
= 791209.98
120
cum
s and culverts
115085.09
Total [a+b+c+d+e] 690510.53
69051.05
= 759561.58
120
cum
PTO 5.0 M
(a+b+c) 460340.35
0 115085.09
Total [a+b+c+d] 575425.44
bridges
143856.36
Total [a+b+c+d+e] 719281.80
71928.18
= 791209.98
120
on
s and culverts
115085.09
Total [a+b+c+d+e] 690510.53
69051.05
186
= 759561.58
120
on
ROM 5.0 M TO 10 M
(a+b+c) 460340.35
0 138102.11
Total [a+b+c+d] 598442.46
187
bridges
149610.62
Total [a+b+c+d+e] 748053.08
74805.31
= 822858.39
120
on
s and culverts
119688.49
Total [a+b+c+d+e] 718130.95
71813.10
= 789944.05
120
on
te mixer
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Tonne 39602.24
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 57668.35
188
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7339.44
57668.35
3630.00
[a+b+c] 68637.79
0 13727.56
Total [a+b+c+d] 82365.35
189
bridges
20591.34
Total [a+b+c+d+e] 102956.69
10295.67
= 113252.36
15
Cum
s and culverts
16473.07
Total [a+b+c+d+e] 98838.42
9883.84
= 108722.26
15
Cum
[a+b+c] 68637.79
0 17159.45
Total [d] 17159.45
Total [a+b+c+d] 85797.24
bridges
21449.31
Total [a+b+c+d+e] 107246.55
10724.66
= 117971.21
15
Cum
s and culverts
17159.45
Total [a+b+c+d+e] 102956.69
190
10295.67
= 113252.36
15
Cum
191
UPERSTRUCTURE USING
MIXER
[a+b+c] 68637.79
0 17159.45
Total [d] 17159.45
Total [a+b+c+d] 85797.24
bridges
21449.31
Total [a+b+c+d+e] 107246.55
10724.66
= 117971.21
15
Cum
s and culverts
17159.45
Total [a+b+c+d+e] 102956.69
10295.67
= 113252.36
15
Cum
NG CONCRETE MIXER
[a+b+c] 68637.79
0 20591.34
Total [d] 20591.34
Total [a+b+c+d] 89229.13
bridges
22307.28
Total [a+b+c+d+e] 111536.41
192
11153.64
= 122690.05
15
Cum
s and culverts
17845.83
Total [a+b+c+d+e] 107074.96
10707.50
= 117782.46
15
Cum
193
g Batching Plant
Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36
Cum 86916.24
Cum 41787.36
Cum 15883.85
Tonne 317016.23
Total [b] 461603.68
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
5
7371.36
461603.68
37902.00
[a+b+c] 506877.04
5.0 M
0 101375.41
Total [d] 101375.41
Total [a+b+c+d] 608252.45
bridges
194
152063.11
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120
cum
195
s and culverts
121650.49
Total [a+b+c+d+e] 729902.94
72990.29
= 802893.23
120
cum
5.0 M TO 10 M
= 506877.04
0 126719.26
Total [a+b+c+d] 633596.30
bridges
158399.08
Total [a+b+c+d+e] 791995.38
79199.54
= 871194.92
120
cum
s and culverts
126719.26
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120
cum
PTO 5.0 M
= 506877.04
0 126719.26
196
cum
197
s and culverts
126719.26
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120
cum
ROM 5.0 M TO 10 M
= 506877.04
0 152063.11
Total [a+b+c+d] 658940.15
bridges
164735.04
Total [a+b+c+d+e] 823675.19
82367.52
= 906042.71
120
cum
s and culverts
131788.03
Total [a+b+c+d+e] 790728.18
79072.82
= 869801.00
120
Cum
te mixer
198
Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
199
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7671.60
58395.60
3630.00
[a+b+c] 69697.20
0 13939.44
Total [a+b+c+d] 83636.64
bridges
20909.16
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15
Cum
s and culverts
16727.33
Total [a+b+c+d+e] 100363.97
10036.40
= 110400.37
15
Cum
[a+b+c] 69697.20
0 17424.30
Total [d] 17424.30
200
Cum
201
s and culverts
17424.30
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15
Cum
UPERSTRUCTURE USING
MIXER
[a+b+c] 69697.20
0 17424.30
Total [d] 17424.30
Total [a+b+c+d] 87121.50
bridges
21780.38
Total [a+b+c+d+e] 108901.88
10890.19
= 119792.07
15
Cum
s and culverts
17424.30
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15
Cum
NG CONCRETE MIXER
[a+b+c] 69697.20
202
0 20909.16
Total [d] 20909.16
Total [a+b+c+d] 90606.36
bridges
22651.59
Total [a+b+c+d+e] 113257.95
11325.80
= 124583.75
15
Cum
203
s and culverts
18121.27
Total [a+b+c+d+e] 108727.63
10872.76
= 119600.39
15
Cum
g Batching Plant
Nos 289.52
Nos 1353.00
Nos 6061.00
Total [a] 7703.52
Cum 86916.24
Cum 41787.36
Cum 16001.08
Tonne 322569.80
Total [b] 467274.48
Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
0
7703.52
467274.48
37902.00
204
[a+b+c] 512880.00
5.0 M
0 102576.00
Total [d] 102576.00
Total [a+b+c+d] 615456.00
205
bridges
153864.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120
cum
s and culverts
123091.20
Total [a+b+c+d+e] 738547.20
73854.72
= 812401.92
120
cum
5.0 M TO 10 M
= 512880.00
0 128220.00
Total [a+b+c+d] 641100.00
bridges
160275.00
Total [a+b+c+d+e] 801375.00
80137.50
= 881512.50
120
cum
s and culverts
128220.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120
206
cum
PTO 5.0 M
= 512880.00
0 128220.00
Total [a+b+c+d] 641100.00
207
bridges
160275.00
Total [a+b+c+d+e] 801375.00
80137.50
= 881512.50
120
cum
s and culverts
128220.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120
cum
ROM 5.0 M TO 10 M
= 512880.00
0 153864.00
Total [a+b+c+d] 666744.00
bridges
166686.00
Total [a+b+c+d+e] 833430.00
83343.00
= 916773.00
120
cum
s and culverts
133348.80
Total [a+b+c+d+e] 800092.80
80009.28
= 880102.08
120
208
Cum
te mixer
Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
209
Tonne 41850.11
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 59916.22
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7671.60
59916.22
3630.00
[a+b+c] 71217.82
0 12819.21
Total [a+b+c+d] 84037.03
bridges
21009.26
Total [a+b+c+d+e] 105046.29
10504.63
= 115550.92
15
Cum
s and culverts
16807.41
Total [a+b+c+d+e] 100844.44
10084.44
= 110928.88
15
Cum
210
[a+b+c] 71217.82
0 16380.10
Total [d] 16380.10
Total [a+b+c+d] 87597.92
211
bridges
21899.48
Total [a+b+c+d+e] 109497.40
10949.74
= 120447.14
15
Cum
s and culverts
17519.58
Total [a+b+c+d+e] 105117.50
10511.75
= 115629.25
15
Cum
UPERSTRUCTURE USING
MIXER
[a+b+c] 71217.82
0 16380.10
Total [d] 16380.10
Total [a+b+c+d] 87597.92
bridges
21899.48
Total [a+b+c+d+e] 109497.40
10949.74
= 120447.14
15
Cum
s and culverts
17519.58
Total [a+b+c+d+e] 105117.50
212
10511.75
= 115629.25
15
Cum
NG CONCRETE MIXER
[a+b+c] 71217.82
0 19940.99
Total [d] 19940.99
Total [a+b+c+d] 91158.81
213
bridges
22789.70
Total [a+b+c+d+e] 113948.51
11394.85
= 125343.36
15
Cum
s and culverts
18231.76
Total [a+b+c+d+e] 109390.57
10939.06
= 120329.63
15
Cum
g Batching Plant
Nos 289.52
Nos 1353.00
Nos 6061.00
Total [a] 7703.52
Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71
Hour 13392.00
Hour 4188.00
214
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
5
7703.52
479329.71
37902.00
[a+b+c] 524935.23
215
5.0 M
0 94488.34
Total [d] 94488.34
Total [a+b+c+d] 619423.57
bridges
154855.89
Total [a+b+c+d+e] 774279.46
77427.95
= 851707.41
120
cum
s and culverts
123884.71
Total [a+b+c+d+e] 743308.28
74330.83
= 817639.11
120
cum
5.0 M TO 10 M
= 524935.23
0 120735.10
Total [a+b+c+d] 645670.33
bridges
161417.58
Total [a+b+c+d+e] 807087.91
80708.79
= 887796.70
120
cum
216
s and culverts
129134.07
Total [a+b+c+d+e] 774804.40
77480.44
= 852284.84
120
cum
217
PTO 5.0 M
= 524935.23
0 120735.10
cum
s and culverts
129134.07
Total [a+b+c+d+e] 774804.40
77480.44
= 852284.84
120
cum
ROM 5.0 M TO 10 M
= 524935.23
0 146981.86
Total [a+b+c+d] 671917.09
bridges
167979.27
Total [a+b+c+d+e] 839896.36
83989.64
= 923886.00
120
218
cum
s and culverts
134383.42
Total [a+b+c+d+e] 806300.51
80630.05
= 886930.56
120
Cum
219
reinforcement in superstructure
ecificaion
MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
bridges
12790.48
Total [a+b+c] 63952.38
6395.24
= 70347.62
1
MT
s and culverts
10232.38
Total [a+b+c+d+e] 61394.28
6139.43
= 67533.71
1
MT
220
reinforcement in superstructure
ecificaion
MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49698.56
bridges
12424.64
Total [a+b+c] 62123.20
6212.32
= 68335.52
1
MT
s and culverts
9939.71
Total [a+b+c+d+e] 59638.27
5963.83
= 65602.10
1
MT
Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
Cum 10864.53
222
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
223
7671.60
58395.60
3630.00
ete for 15 cum 69697.20
4646.48
Cum 4646.48
Nos 47.85
Total 4694.33
bridges
1173.58
Total 5867.91
586.79
= 6454.70
1
Cum
s and culverts
938.87
Total 5633.20
563.32
= 6196.52
1
Cum
224
Nos 161.21
Nos 3146.00
Nos 398.75
Total [a] 3705.96
225
tonne 8143.88
Cum 103.86
MT 294.31
Cum 391.22
Cum 46.27
MT 41.92
Hour 17.28
Hour 15.48
Hour 300.00
Hour 960.00
226
Hour 293.00
14313.18
bridges
3578.30
Total 17891.48
1789.15
= 19680.63
72.46
Sqm
227
s and culverts
2862.64
Total 17175.82
1717.58
= 18893.40
72.46
Sqm
Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
228
CRETE MIXER
7671.60
58395.60
3630.00
[a+b+c] 69697.20
15
Cum
229
MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90
Cum 19013.40
0 232.32
MT 44255.04
Total 63500.76
0 3175.04
= 66675.80
48
Rm
230
Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
231
Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
[a+b+c] 69697.20
15
Cum
MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90
Cum 19013.40
0 557.58
232
MT 44255.04
Total 63826.02
bridges
15956.51
Total 79782.53
7978.25
= 87760.78
48
Rm
233
s and culverts
12765.20
Total 76591.22
7659.12
= 84250.34
48
Rm
and specifications
Nos 6.58
Nos 6.96
Nos 6.38
Nos 3.29
Nos 4.51
Nos 63.80
Total [a] 91.52
Kg 172.00
m 1260.00
Nos. 7.80
Nos. 15.00
Total [b] 1454.80
[a+b] 1546.32
0 77.32
234
Total 1623.64
bridges
405.91
Total 2029.55
202.96
= 2232.51
6
m
235
s and culverts
324.73
Total 1948.37
194.84
= 2143.21
6
Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67
Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 55166.11
bridges
236
13791.53
Total [a+b+c+d] 68957.64
6895.76
= 75853.40
15
cum
237
s and culverts
11033.22
Total [a+b+c+d] 66199.33
6619.93
= 72819.26
15
cum
Nos 282.94
Nos 676.50
Nos 6699.00
Total [a] 7658.44
Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
Hour 1398.00
Hour 2232.00
Total [c] 3630.00
CRETE MIXER
7658.44
58395.60
238
3630.00
[a+b+c] 69684.04
15
Cum
nforcements:
MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90
CONCRETE MIXER including
nts
Cum 4645.60
0 92.91
MT 2558.10
Total 7296.61
bridges
1824.15
Total 9120.76
912.08
= 10032.84
1
Cum
s and culverts
1459.32
Total 8755.93
875.59
= 9631.52
1
240
Cum
241
Kg 9075.00
Total [b] 9075.00
[a+b] 9390.66
bridges
2347.67
Total 11738.33
1173.83
= 12912.16
12
Rm
s and culverts
1878.13
Total 11268.79
1126.88
= 12395.67
12
Rm
242
Sqm 2178.00
Rm
Nos 3.29
Nos 57.20
Nos 31.90
Total [a] 92.39
244
Sqm 2613.60
bridges
676.50
Total 3382.49
338.25
= 3720.74
12
Rm
s and culverts
541.20
Total 3247.19
324.72
= 3571.91
12
Rm
Nos 6.58
Nos 143.00
Nos 31.90
Total [a] 181.48
Cum 3.52
tonne 38.95
Total [b] 38.95
[a+b] 220.43
bridges
55.11
Total 275.54
246
27.55
= 303.09
12
Rm
s and culverts
44.09
Total 264.52
26.45
= 290.97
12
Rm
142
Chapter - 12
Foundation
Sl. No. Quantity Description Rate per
Total [a+b+c+d+e]
f) Contractor's profit 10% on 1143.38
Rate for 1 Cum =
Rate for 1 cum = 1257.72 / 1
*-*-*-*-*-*-
144
15.1. Providing and laying apron with Cement Concrete blocks of size
0.50 X 0.50 m cast - in situ and made with nominal size M 1
cement concrete with a minimum cement content of 250 Kg /
per IRC 21-2000
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 56269.43
Total [a+b+c+d+e]
145
15.4. Providing and laying pitching on side slopes laid over prepar
media including boulder apron laid dry in front of toe of emba
complete as per drawing and technical specifications.
Total [d]
Total [a+b+c+d]
150
Total [b]
b) Labour :
0.08 Nos Mate 329.00 / Nos
0.50 Nos Mason class I 451.00 / Nos
1.50 Nos Mazdoor -skilled 319.00 / Nos
154
Total [a]
c) Total [a+b]
on cost of account for excavation,
proper preparation of bed on cost of
1% cement mortar and cement concrete 3152.20
for bedding
155
Total [b]
1% on cost of account for excavation, 8726.54
proper preparation ofRate
bed for 1 Cum =
STATE DATA
1 Gravel packing to rough stone dry packing for revetments
Unit = Cum
Taking Output = 10 Cum
11.60 Cum Gravel 246.95 / Cum
7.10 Nos Mazdoor skilled 319.00 / Nos
3.50 Nos Mazdoor 286.00 / Nos
Rate for 10 cum =
(i) For major bridges and minor bridges
e) Overheads 25% on 6130.52
Total [a+b+c]
f) Contractor's profit 10% on 7663.15
Rate for 10 Cum =
Rate for 1 cum = 8429.47 / 10
Amount
13.16
157.85
239.25
410.26
489.30
53.26
542.56
952.82
238.21
1191.03
119.10
1310.13
190.56
165
1143.38
114.34
1257.72
166
282.94
676.50
6380.00
7339.44
8175.33
5432.27
1305.86
1978.16
27305.05
44196.67
1398.00
2232.00
3630.00
55166.11
1103.32
1103.32
56269.43
14067.36
70336.79
167
7033.68
77370.47
168
11253.89
67523.32
6752.33
74275.65
13.16
157.85
239.25
410.26
489.30
53.26
542.56
952.82
238.21
1191.03
119.10
1310.13
169
190.56
1143.38
114.34
1257.72
282.94
676.50
6380.00
7339.44
8175.33
5432.27
1305.86
1978.16
27305.05
44196.67
1398.00
2232.00
3630.00
55166.11
170
1103.32
1103.32
56269.43
171
14067.36
70336.79
7033.68
77370.47
11253.89
67523.32
6752.33
74275.65
pitching in slopes
cations.
16.45
286.00
79.75
382.20
334.45
334.45
716.65
172
179.16
895.81
89.58
985.39
143.33
859.98
86.00
945.98
e flooringcomplete as per
13.16
287.10
300.26
3371.81
173
307.71
3679.52
174
282.94
676.50
6380.00
7339.44
8175.33
5432.27
1305.86
1978.16
27305.05
44196.67
1398.00
2232.00
3630.00
55166.11
489.30
53.26
1313.33
1838.87
3694.76
26.32
225.50
478.50
175
730.32
4425.08
31.52
4456.60
176
1114.15
5570.75
557.08
6127.83
891.32
5347.92
534.79
5882.71
15
5259.17
3677.74
8936.91
89.37
9026.28
5048.80
3677.74
177
8726.54
87.27
8813.81
178
489.30
53.26
542.56
32.90
225.50
478.50
736.90
1279.46
7.37
1286.83
321.71
1608.54
160.85
1769.39
257.37
1544.20
154.42
1698.62
179
489.30
53.26
542.56
16.45
112.75
319.00
448.20
990.76
9.91
1000.67
250.17
1250.84
125.08
1375.92
200.13
1200.80
120.08
1320.88
180
19.74
319.00
338.74
319.00
181.50
500.50
839.24
209.81
1049.05
104.91
1153.96
167.85
1007.09
100.71
1107.80
181
ng coat comprising of 50
mmthick mastic asphalt
00 m
9.87
239.25
249.12
239.25
145.20
384.45
633.57
158.39
791.96
79.20
871.16
126.71
760.28
76.03
836.31
182
2864.62
2264.90
1001.00
6130.52
1532.63
7663.15
766.32
8429.47
1226.10
7356.62
735.66
8092.28
5382.30
183
1022.00
3381.40
2030.60
11816.30
184
2954.08
14770.38
1477.04
16247.42
2363.26
14179.56
1417.96
15597.52
157
*/-*/-/*-/*
*/-*/-/*-/*
12.00 Hour Concrete mixer 0.48 / 0.28 cum 233.00 / Hour 2796.00
capa city
5.00 Hour Water tanker 6 KL capacity 310.00 / Hour 1550.00
Total [b] 6206.00
c) Material:
21.79 Cum Crushed stone aggregate 20 1341.30 / Cum 29226.93
mm nominal size 59%
*/-*/-/*-/*
Providing and laying open graded premix carpet of 20 mm thick on
prepared surface in a single course as wearing course composed of
specified size of stone aggregates premix with a bituminous binder in
mini hot mix plant 6-10 tonne laying manually and rolling with power roller
8-10 tonne but excluding cost of primer / tack coat
d) Form work
On cost of materials, labhour and
4.00% 55166.11 / 0 2206.64
machinary
Total [d] 2206.64
Total [a+b+c+d] 57372.75
Rate for 1 cum = 57372.75 / 15
Rate for PCC M 15 conc rete without overhead =
and c ontractor's profit 3824.85 / Cum
Rate for earthwork for foundation for Km stones
Unit = = Cum
Taking Output = = 10cum
A. Manual Means:
(i)Depth upto 3 m :
a) Labour :
0.14 Nos Mate 329.00 / Nos 46.06
3.50 Nos Mazdoor 319.00 / Nos 1116.50
Total [a] 1162.56
Rate for 10cum = 1162.56
Rate for 1 cum = 1162.56 / 10
Earth Work for foundation in ordinary
soil without overhead and contractor's = 116.26 / cum
profit
I) 5 th KM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 6Nos.
2.35 Cum M 15 grade concrete 3824.85 / Cum 8988.40
22.08 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 989.53
1.68 Cum Excavation in soil for foundation 116.26 / Cum 195.32
9.85 Sqm Painting two coats on concrete 68.26 / Sqm 672.36
surface
1800 per cm Lettering on Km post [average 0.48 / per cm 864.00
per letter 30 le tte rs o f 10 cm height each] per letter
II)Ordinary KM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 14Nos.
3.77 Cum M 15 grade concrete 3824.85 / Cum 14419.68
26.32 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 1179.55
2.77 Cum Excavation in soil for foundation 116.26 / Cum 322.04
11.41 Sqm Painting two coats on concrete 68.26 / Sqm 778.85
surface
1680 per cm Lettering on Km post [average 0.48 / per cm 806.40
per letter 30 le tte rs o f 10 cm height each] per letter
III)HM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 33Nos.
1.58 Cum M 15 grade concrete 3824.85 / Cum 6043.26
66.00 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 2957.83
1.39 Cum Excavation in soil for foundation 116.26 / Cum 161.60
6.27 Sqm Painting two coats on concrete 68.26 / Sqm 427.99
surface
330 per cm Lettering on Km post [average 0.48 / per cm 158.40
per letter 30 le tte rs o f 10 cm height each] per letter
b) Material:
13.80 Cum 40 mm ISS metal 1009.30 / Cum 13928.34
6.90 Cum Sand for mortar 293.06 / Cum 2022.11
2.97 Tonne Cement(3.3-10 % of 3.3) 6611.39 / Tonne 19635.83
18.00 KL Cost of water 150.00 / KL 2700.00
Total [b] 38286.28
Total [a+b] 43732.84
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 / Hour 1398.00
6.00 Hour Generator 33 KVA 372.00 / Hour 2232.00
3.00 Hour Water tanker 310.00 / Hour 930.00
Total [b] 4560.00
Total [a+b+c] 48292.84
C)Overheads 10% on 48292.84 4829.28
Total [a+b+c] 53122.12
159
9.2. Laying RCC pipe NP4 concrete pipe on first class bedding in single row
Laying RCC pipe NP4 for culverts on first class bedding of granular
materialin single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets.
9.2. Laying RCC pipe NP4 concrete pipe on first class bedding in two rows
Laying RCC pipe NP4 for culverts on first class bedding of granular
material in two rows including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets.
Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
1 Earthwork for foundation in ordinary soil: 304
A. By mechanical means
i) Depth up to 3 m excluding 159.85 / Cum 153.46 / Cum
dewatering
ii) Depth up to 3 m including 175.84 / Cum 168.80 / Cum
dewatering
iii) Depth 3 m to 6 m including 236.35 / Cum 226.90 / Cum
dewatering
Depth 3 m to 6 m including 236.35 / Cum 226.90 / Cum
dewatering
iv) Depth above 6 m including 328.84 / Cum 315.69 / Cum
dewatering
B. By Mechanical means
i) Depth upto 3 m including 62.98 / Cum 60.46 / Cum
dewatering
ii) Depth 3 to 6 m including 73.69 / Cum 70.74 / Cum
dewatering
iii) Depth above 6 m including 93.55 / Cum 89.81 / Cum
dewatering
2 Earthwork for foundation in ordinary rock 304
not requiring blasting
A. Manual means
i) Depth upto 3 m excluding 228.36 / Cum 219.23 / Cum
dewatering
B. Mechanical means:
377659397.xlsxabstract
175
377659397.xlsxabstract
176
377659397.xlsxabstract
177
377659397.xlsxabstract
178
377659397.xlsxabstract
179
377659397.xlsxabstract
180
377659397.xlsxabstract
181
377659397.xlsxabstract
182
377659397.xlsxabstract
183
377659397.xlsxabstract