You are on page 1of 604

NAME OF WORK : UP-GRADATION OF NH-543 STARTING FROM GONDIA - AMGAON - DEORI- KORCHI

BRAMHAPURI TO TWO LANE WITH PAVED SHOULDER CONFIGURATION IN SECTION FROM DEORI TO
AMGAON (DESIGN CH. FROM KM. 0.000 TO KM. 38.200) IN THE STATE OF MAHARASHTRA ON EPC MODE.

NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600 to 12700
(LHS)

DETAILED ESTIMATE

SN Description no Length Width Depth Quantity Unit

Earthwork excavation for foundation of structures as per drawings and technical specifications, including
1 setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material including cost of dewatering As per MORT & H,
V REVISION CL. 304

CH : 1/775 - 1/875, 2/300 - 2/400, 400


4/300 - 4/400, 6/600 - 6/700

1 x 2 400.00 0.00 0.00 0.00 cum

0.00 cum

2 Plain cement concrete M15 in sub structure complete as per drawing and technical specification for
SubStructure below sill As per MORT & H, V REVISION SPECIFICATION NO.1500, 1700 & 2100
CH : 1/775 - 1/875, 2/300 - 2/400,
400
4/300 - 4/400, 6/600 - 6/700
I footing 1 x 2 400.00 0.00 0.00 0.00 cum

II footing 1 x 2 400.00 0.00 0.00 0.00 cum

III footing 1 x 2 400.00 0.00 0.00 0.00 cum

stem 1 x 2 400.00 (1.25+1.095)/2 = 1.300 0.00 0.00 cum

0.00 cum

3 Plain cement concrete M15 in sub structure complete as per drawing and technical specification for
SubStructure Above sill As per MORT & H, V REVISION SPECIFICATION NO.1500, 1700 & 2100
CH : 1/775 - 1/875, 2/300 - 2/400, 400
4/300 - 4/400, 6/600 - 6/700
Rect portion 1 x 2 400.00 0.4 2.67 854.40 cum

Triangle portion 1 x 2 400.00 (0.645)/2 = 0.425 2.67 907.80 cum

Parapet 1 x 2 400.00 0.40 0.50 160.00 cum

1922.20 cum
Providing weep holes in brick masonry /plain / reinforced concrete abutment, wing walls / return wall with
4 100 mm dia AC pipe, extending through the full width of the structure with slope of aV:20H towards
drawing face, complete as per drawing and techinical specifications. As per MORT & H, V REVISION
SPECIFICATION NO.2706, 2200

1 x 2 400 2.00 1600.00

1600.00 Nos.

5 Providing and laying Granular material below stone pitching portion as filter media including cost,
conveyance, labour for filling, hire charges to T&p etc., Complete as per drawing and Techical specification

LHS
Ch:1775 - 1800 1 x 1 25 (5.645 + 5.807 ) 0.150 42.95 Cu.m

Ch:1800 - 1825 1 x 1 25 (5.645 + 4.754 ) 0.150 39.00 Cu.m

Ch:1825 - 1850 1 x 1 25 (5.645 + 2.203 ) 0.150 29.43 Cu.m

Ch:1850 - 1875 1 x 1 25 (5.645 + 1.957 ) 0.150 28.51 Cu.m

Ch:2300 - 2325 1 x 1 25 (5.645 + 5.294 ) 0.150 41.02 Cu.m

Ch:2325 - 2350 1 x 1 25 (5.645 + 4.675 ) 0.150 38.70 Cu.m

Ch:2350 - 2375 1 x 1 25 (5.645 + 3.160 ) 0.150 33.02 Cu.m

Ch:2375 - 2400 1 x 1 25 (5.645 + 2.366 ) 0.150 30.04 Cu.m

Ch:4300 - 4325 1 x 1 25 (5.645 + 1.840 ) 0.150 28.07 Cu.m

Ch:4325 - 4350 1 x 1 25 (5.645 + 2.384 ) 0.150 30.11 Cu.m

Ch:4350 - 4375 1 x 1 25 (5.645 + 2.621 ) 0.150 31.00 Cu.m

Ch:4375 - 4400 1 x 1 25 (5.645 + 2.826 ) 0.150 31.77 Cu.m

Ch:6600 - 6625 1 x 1 25 (5.645 + 0.781 ) 0.150 24.10 Cu.m

Ch:6625 - 6650 1 x 1 25 (5.645 + 1.014 ) 0.150 24.97 Cu.m

Ch:6650 - 6675 1 x 1 25 (5.645 + 0.950 ) 0.150 24.73 Cu.m

Ch:6675 - 6700 1 x 1 25 (5.645 + 0.747 ) 0.150 23.97 Cu.m


RHS
Ch:1775 - 1800 1 x 1 25 (5.645 + 4.671 ) 0.150 38.69 Cu.m

Ch:1800 - 1825 1 x 1 25 (5.645 + 4.390 ) 0.150 37.63 Cu.m

Ch:1825 - 1850 1 x 1 25 (5.645 + 3.510 ) 0.150 34.33 Cu.m

Ch:1850 - 1875 1 x 1 25 (5.645 + 3.297 ) 0.150 33.53 Cu.m


Ch:2300 - 2325 1 x 1 25 (5.645 + 5.122 ) 0.150 40.38 Cu.m

Ch:2325 - 2350 1 x 1 25 (5.645 + 5.236 ) 0.150 40.80 Cu.m

Ch:2350 - 2375 1 x 1 25 (5.645 + 3.639 ) 0.150 34.82 Cu.m

Ch:2375 - 2400 1 x 1 25 (5.645 + 2.509 ) 0.150 30.58 Cu.m

Ch:4300 - 4325 1 x 1 25 (5.645 + 1.435 ) 0.150 26.55 Cu.m

Ch:4325 - 4350 1 x 1 25 (5.645 + 1.247 ) 0.150 25.85 Cu.m

Ch:4350 - 4375 1 x 1 25 (5.645 + 1.811 ) 0.150 27.96 Cu.m

Ch:4375 - 4400 1 x 1 25 (5.645 + 3.534 ) 0.150 34.42 Cu.m

Ch:6600 - 6625 1 x 1 25 (5.645 + 2.351 ) 0.150 29.99 Cu.m

Ch:6625 - 6650 1 x 1 25 (5.645 + 2.226 ) 0.150 29.52 Cu.m

Ch:6650 - 6675 1 x 1 25 (5.645 + 1.697 ) 0.150 27.53 Cu.m

Ch:6675 - 6700 1 x 1 25 (5.645 + 1.267 ) 0.150 25.92 Cu.m

TOTAL 1019.89 Cu.m

6 Granite rough stone dry packing for revertment including cost, conveyance, labour for filling, hire charges
to T&p etc., Complete as per drawing and Techical specification

LHS
Ch:1775 - 1800 1 x 1 25 (4.385 + 5.807 ) 0.300 76.44 Cu.m

Ch:1800 - 1825 1 x 1 25 (4.385 + 4.754 ) 0.300 68.54 Cu.m

Ch:1825 - 1850 1 x 1 25 (4.385 + 2.203 ) 0.300 49.41 Cu.m

Ch:1850 - 1875 1 x 1 25 (4.385 + 1.957 ) 0.300 47.57 Cu.m

Ch:2300 - 2325 1 x 1 25 (4.385 + 5.294 ) 0.300 72.59 Cu.m

Ch:2325 - 2350 1 x 1 25 (4.385 + 4.675 ) 0.300 67.95 Cu.m

Ch:2350 - 2375 1 x 1 25 (4.385 + 3.160 ) 0.300 56.59 Cu.m

Ch:2375 - 2400 1 x 1 25 (4.385 + 2.366 ) 0.300 50.63 Cu.m

Ch:4300 - 4325 1 x 1 25 (4.385 + 1.840 ) 0.300 46.69 Cu.m

Ch:4325 - 4350 1 x 1 25 (4.385 + 2.384 ) 0.300 50.77 Cu.m

Ch:4350 - 4375 1 x 1 25 (4.385 + 2.621 ) 0.300 52.55 Cu.m

Ch:4375 - 4400 1 x 1 25 (4.385 + 2.826 ) 0.300 54.08 Cu.m

Ch:6600 - 6625 1 x 1 25 (4.385 + 0.781 ) 0.300 38.75 Cu.m


Ch:6625 - 6650 1 x 1 25 (4.385 + 1.014 ) 0.300 40.49 Cu.m

Ch:6650 - 6675 1 x 1 25 (4.385 + 0.950 ) 0.300 40.01 Cu.m

Ch:6675 - 6700 1 x 1 25 (4.385 + 0.747 ) 0.300 38.49 Cu.m

RHS
Ch:1775 - 1800 1 x 1 25 (4.385 + 4.671 ) 0.300 67.92 Cu.m

Ch:1800 - 1825 1 x 1 25 (4.385 + 4.390 ) 0.300 65.81 Cu.m

Ch:1825 - 1850 1 x 1 25 (4.385 + 3.510 ) 0.300 59.21 Cu.m

Ch:1850 - 1875 1 x 1 25 (4.385 + 3.297 ) 0.300 57.62 Cu.m

Ch:2300 - 2325 1 x 1 25 (4.385 + 5.122 ) 0.300 71.30 Cu.m

Ch:2325 - 2350 1 x 1 25 (4.385 + 5.236 ) 0.300 72.16 Cu.m

Ch:2350 - 2375 1 x 1 25 (4.385 + 3.639 ) 0.300 60.18 Cu.m

Ch:2375 - 2400 1 x 1 25 (4.385 + 2.509 ) 0.300 51.71 Cu.m

Ch:4300 - 4325 1 x 1 25 (4.385 + 1.435 ) 0.300 43.65 Cu.m

Ch:4325 - 4350 1 x 1 25 (4.385 + 1.247 ) 0.300 42.24 Cu.m

Ch:4350 - 4375 1 x 1 25 (4.385 + 1.811 ) 0.300 46.47 Cu.m

Ch:4375 - 4400 1 x 1 25 (4.385 + 3.534 ) 0.300 59.39 Cu.m

Ch:6600 - 6625 1 x 1 25 (4.385 + 2.351 ) 0.300 50.52 Cu.m

Ch:6625 - 6650 1 x 1 25 (4.385 + 2.226 ) 0.300 49.58 Cu.m

Ch:6650 - 6675 1 x 1 25 (4.385 + 1.697 ) 0.300 45.62 Cu.m

Ch:6675 - 6700 1 x 1 25 (4.385 + 1.267 ) 0.300 42.39 Cu.m

TOTAL 1737.32 Cu.m


DESIGN OF PCC RETAINING WALL
NAME OF WORK : UP-GRADATION OF NH-543 STARTING FROM GONDIA - AMGAON - DEORI-
KORCHI BRAMHAPURI TO TWO LANE WITH PAVED SHOULDER CONFIGURATION IN SECTION
FROM DEORI TO AMGAON (DESIGN CH. FROM KM. 0.000 TO KM. 38.200) IN THE STATE OF
MAHARASHTRA ON EPC MODE.

NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600 to
12700 (LHS)

0.40

Earth Filling

2.67

2 1
0.15 0.075
0.75

0.850 0.400

1.40 0.00

R.W.SECTION

b (Toe)

DIMENSIONS (m)

WALL FOOTING OFFSETS

B1 0.40 FH1 0.00 OFT1 0.08

B2 0.00 FH2 0.00 OFT2 0.00

B3 0.85 FH3 0.00 OFT3 0.00

H 2.67 OFH1 0.75

H1 0.60 OFH2 0.00

H2 0.30 OFH3 0.00

SOIL PROPERTIES
Angle of Repose φ = 35 °
Angle of Wall Friction δ = 22.5 °

Angle of Surcharge β = 0 °
Angle of Internal Wall Slo α = 90 °
Unit Weight of Soil γ = 18.8 kN/m3

Safe Bearing Capacity of SBC = 175 kN/m2


Founding Strata

OTHER DETAILS

Type of Exposure = Moderate

Grade of Concrete = M 25

Density of Concrete = 24 kN/m3


DESIGN OF PCC RETAINING WALL
NAME OF WORK : UP-GRADATION OF NH-543 STARTING FROM GONDIA - AMGAON - DEORI-
KORCHI BRAMHAPURI TO TWO LANE WITH PAVED SHOULDER CONFIGURATION IN SECTION
FROM DEORI TO AMGAON (DESIGN CH. FROM KM. 0.000 TO KM. 38.200) IN THE STATE OF
MAHARASHTRA ON EPC MODE.

NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700 (RHS) & 12600
to 12700 (LHS)

GEOMETRIC PARAMETERS OF RETAINING WALL:

Width of retaining wall at the top = 0.40 m

Width of batter on the toe side = 0.00 m

Width of batter on the Heel side at first stage = 0.85 m

Width of retaining wall at end of first stage of batter = 1.25 m

Width of First footing = 0.00 m

Width of Second footing = 0.00 m

Width of retaining wall at founding level = 0.00 m

Height of Retaining wall above top of footing = 2.67 m

Height of first footing = 0.00 m

Height of second footing = 0.00 m

Height of thrid footing = 0.00 m

Total height of Retaining wall above the bottom of footing = 2.67 m

Offset of first footing on toe side = 0.08 m

GS ASSOCIATES
COIMBATORE.
Offset of second footing on toe side = 0.00 m

Offset of third footing on toe side = 0.00 m

Offset of first footing on heel side = 0.75 m

Offset of second footing on heel side = 0.00 m

Offset of third footing on heel side = 0.00 m

SOIL PARAMETERS:

Angle of repose of soil φ = 35.00 degree

Angle of wall friction δ = 22.50 degree

Angle of Surcharge of soil β = 0 degree

Angle of internal wall slope α = 90.00 degree


kN/m3
Unit weight of soil γ = 18.80
kN/m2
SBC of founding strata SBC = 175.00

CONCRETE:

Exposure condition = Moderate

Grade of Concrete for PCC = M 25


kN/m3
Unit Weight of Concrete = 24

Permissible Flextural Compressive stress = 8.33 MPa

Permissible Tensile stress = 0.61 MPa

GS ASSOCIATES
COIMBATORE.
As per Cl. 710.1.1, when surface reinforcement at not provided, the permissbile stress
level shall be kept only upto 90% of the allowable stresses. After applying reduction factor of
90%,

Permissible Flextural Compressive stress = 7.50 MPa

Permissible Tensile stress = 0.55 MPa


kN/m3
Unit Weight of Concrete = 22.00
kN
Intensity of External load per metre = 7.75
m
Eccentricity for the vertical load from toe side = 0.195

CALCULATION OF COEFFICIENT OF EARTH PRESSURE FOR DIFFERENT WALL SLOPES

ACTIVE EARTH PRESSURE:

The intensity of Earth Pressure is calculated using the "Coulomb's Formula" and the
coefficients of Active and Passive Earth Pressures are calculated as follows:

Lever arm for the Earth Pressure = 0.42 h


(As per Cl.207.1 of IRC:6-2000)

sin2 (α + φ) 1
ka = x x cosδ
sin2 (α) x sin(α - δ) (1+k)2

sin(φ+δ) * sin(φ-β)
Where, k=
sin(α-δ) * sin(α+β)

For Vertical face Top straight portion, α = 90.00 degree

sin ( 35 + 22.5 ) * sin ( 35 - 0 )


k=
sin ( 90 - 22.5 ) * sin ( 90 + 0 )

GS ASSOCIATES
COIMBATORE.
0.843 x 0.574
k=
0.924 x 1.000

= 0.724

sin^2 (90 + 35) 1


ka = x
sin^2 ( 90 ) x sin ( 90 - 22.5 ) ( 1 + 0.724 )^2

0.671 1
= x
1 x 0.924 2.972

= 0.244

Pa = (1/2) x ka x γ x (H)2

= (1/2) * 0.244 * 18.8 * (2.67)^2

= 16.35 kN

The total pressure acts inclined at 22.5 degree to the normal

The normal is at 0 degree to the horizontal

Horizontal component of Active Earth Pressure, Pah = Pa cos(0+22.5)

= 16.35 cos(0+22.5)

= 15.11 kN
Vertical component of Active Earth Pressure, Pav = Pa sin(0+22.5)

= 16.35 sin(0+22.5)

GS ASSOCIATES
COIMBATORE.
= 6.26 kN

The calculation of moment about the toe is tabulated below. Here, the anti-clockwise
moments are taken as positive and the clockwise moments are taken as negative.

Lever arm of portion 1 about the toe = -2

Lever arm of portion 2 about the toe = -1.8

Lever arm of portion 3 about the toe = -1.32

Lever arm of portion 4 about the toe = 0.00

Lever arm of portion 5 about the toe = 0.00

Lever arm of portion 5 about the toe = 0.00

Lever arm of Pav about the toe = 1.12

Lever arm of Pah about the toe = 0.89

Forces (kN) Moments about toe (knm)


Lever
Portion Weight arm, m
Vertical Horizontal Clockwise Anti-clockwise

1 1/2 * 2.67 * 0 * 24 0.00 -2.00 0

2 2.67 * 0.4 * 24 25.63 -1.80 -46.13

3 1/2 * 2.67 * 0.85 * 24 27.23 -1.32 -35.94

4 0 * 0 * 24 0.00 0.00 0

5 0 * 0 * 24 0.00 0.00 0

6 0 * 0 * 24 0.00 0.00 0

Pav 6.26 6.26 1.12 7.02

GS ASSOCIATES
COIMBATORE.
Pah 15.11 15.11 0.89 13.45

59.12 15.11 13.45 -75.05

RV RH -88.50

GS ASSOCIATES
COIMBATORE.
CHECK FOR SLIDING

μ RV
Factor of safety against slidng, Fs =
RH

tanδ RV
=
RH

tan22.5 * 59.12
=
15.11

= 1.62 >1.50 (SAFE)


Since the FOS against sliding is more than 1.50, the structure is SAFE against sliding

CHECK FOR OVERTURNING

∑MC
Factor of safety against overturning, Fo =
∑MAC

-75.05
=
13.45

= -5.58 <=2.00 (UNSAFE)


Since the FOS against overturning is less than 2.00, the structure is UNSAFE against
overturning. Hence REDESIGN

CHECK FOR TENSION


Eccentry, e =
b/2 - x

∑MC
x=

GS ASSOCIATES
COIMBATORE.
x=
∑V

-88.50
=
59.12

= -1.5 m

e= (0 / 2) - -1.5

1.5 m

b/6 = 0/6

= 0 m

1.5 > 0
Since e>b/6, Tension is developed in the structure. Hence the structure is UNSAFE which
needs REDESIGN

CHECK FOR BEARING CAPACITY FAILURE


∑V 6e
Maximum pressure at the base, Pmax = 1+
b
b

59.12 6 * 1.5
= 1+
0.00
0.00

= #DIV/0! 1+ #DIV/0!

= #DIV/0! kN/m2

GS ASSOCIATES
COIMBATORE.
∑V 6e
Minimum pressure at the base, Pmin = 1-
b
b

59.12 6 * 1.5
= 1-
0.00
0.00

= #DIV/0! 1- #DIV/0!

= #DIV/0! kN/m2
SBC
Factor of safety against bearing Fbc =
capacity failure
Pmax

175
=
#DIV/0!

= #DIV/0! #DIV/0!
#DIV/0!

GS ASSOCIATES
COIMBATORE.
NAME OF SUBWORK : Construction of Retaining Wall @ CH : 10/500 to 10/700
(RHS) & 12600 to 12700 (LHS)
0.4

2.07

2.67

0.6

0.75 1.25 0.08


0.00
0.00 0.00 0.00
0.00
0.00 0.00 0.00
0.00
0.00

GS ASSOCIATES,
COIMBATORE.
17

CHAPTER - I
RATE OF LABOUR AS PER SCHEDULE OF RATES

Sl.
Description Rate per
No.

A. As Per P.W.D Schedule of Rates


1 Blacksmith I Class 348.00 / day
2 Blacksmith II Class 320.00 / day
Mate/Supervisor
3
(Head Mazdoor) 329.00 / day
4 Mazdoor I Class 319.00 / day
Mazdoor II Class
5
(Dresser /Bhisti) 286.00 / day
Mason I Class
6
(Brick/Stone Work)
451.00 / day
Mason II Class
7
(Brick/Stone Work)
404.00 / day
8 Fitter Class - I 399.00 / day
9 Fitter Class - II 372.00 / day
10 Carpenter I Class 441.00 / day
11 Carpenter II Class 404.00 / day
12 Wooder 292.00 / day
13 Painter I Class 361.00 / day
14 Stone Cutter I Class 347.00 / day
15 Stone Cutter II Class 320.00 / day
Mazdoor for pitting trenching, sampling and drilling
16
works.
282.00 / day

17 Mazdoor for geophysical investigations works 282.00 / day


18 Plumber - I class 392.00 / day
19 Plumber - II class 364.00 / day
18

B) For Bituminous Works


As per Highways Schedule of Rates:
16 Bitumen Spryer Man 371.00 / day
17 Bitumen Raker Man 386.00 / day
18 Heat Master Operator 386.00 / day
19 Road Mazdoor Grade- I 319.00 / day
20 Road Mazdoor Grade-II 286.00 / day
21 Head Mazdoor 329.00 / day
22 Mini Hot Mix Plant Operator 386.00 / day
23 Gunnuting Plant Operator 323.00 / day
24 Gunnuting gun Operator 352.00 / day

Assumptions
1 Over head charges
Major bridges = 25%
Minor bridges = 20%
Road works = 10%
2 Contractors Profit = 10%
3

COMMON DATA - 2015-2016 (Bitumen & Emulsion rate as on

Rate for conveyance as per Schedule of rates

Lead for
Lead
1 Km

0-10 Km 8.69
10-20 Km 7.44
20-40 Km 6.40
40-80 Km 6.00
Above 80Km 5.04
Loading 26.30
Unloading 26.30

Lead for metal = 20


0 - 10 =
10 - 20 =
0 - 0 =
Conveyance for metal =
Lead for Gravel = 10
0 - 10 =
0 - 0 =
Conveyance for Gravel =
Lead for Sand = 14
0 - 10 =
10 - 14 =
Conveyance for Sand =
Lead for Well Gravel = 5
0 - 5 =
4

0 - 0 =
Conveyance for Well Gravel =
5

COMMON DATA - 2015-2016 (Bitumen & Emulsion rate as on

Distance
Nature of route
Sl. Name of quarry / to be Cost of
for
No. Kind of metal carried Extraction
Conveyance
(Km)

(1) (2) (3) (4) (5)

Hard Broken Stone IRC size:


1 90.00 mm 20 M.Road 367.00
2 75.00 mm 20 M.Road 410.00
3 63.00 mm 20 M.Road 531.00
4 53.00 mm 20 M.Road 645.00
5 46.50 mm 20 M.Road 865.00
6 45.00 mm 20 M.Road 865.00
7 37.50 mm 20 M.Road 883.00
8 26.50 mm 20 M.Road 835.00
9 25.00 mm 20 M.Road 835.00
10 22.40 mm 20 M.Road 1211.00
11 13.20 mm 20 M.Road 1124.00
12 11.20 mm 20 M.Road 763.00
13 6.70 mm 20 M.Road 566.00
14 6.00 mm 20 M.Road 566.00
15 5.60 mm 20 M.Road 566.00

16 4.75 mm & below 20 M.Road 502.00


6

Distance
Nature of route
Sl. Name of quarry / to be Cost of
for
No. Kind of metal carried Extraction
Conveyance
(Km)

(1) (2) (3) (4) (5)

Hard Broken Stone- ISS size


17 90mmISS 20 M.Road 364.00
18 80 mm ISS 20 M.Road 408.00
19 63 mm ISS 20 M.Road 471.00
20 50 mm ISS 20 M.Road 546.00
21 40 mm ISS 20 M.Road 848.00
22 25 mm ISS 20 M.Road 729.00
23 20 mm ISS 20 M.Road 1180.00
24 12 mm ISS 20 M.Road 1095.00
25 10 mm ISS 20 M.Road 806.00
26 6 mm ISS 20 M.Road 546.00
27 3 mm ISS 20 M.Road 492.00
28 Stone dust 20 M.Road 105.00
29 R.R. Masonry Work 20 M.Road 379.00
30 R.R. Revetment Work 20 M.Road 328.00
31 Bond Stones 20 M.Road 520.00
32 CRS arch work 20 M.Road 328.00
Coursed rubble stone for
33 20 M.Road 303.00
masonry
34 Gravel 10 M.Road 157.00
35 Sand for Mortar 14 M.Road 176.40
7

36 Sand for filling 14 M.Road 176.40


37 Quarry rubbish 20 M.Road 82.00

38 Bricks [1000 Nos.] (9" X 4 3/8" X 2 3/4" (II Class)


8

39 Cost of 100 mm dia AC pipes [Local rates]


40 Cost of collar for 100 mm dia AC pipes [Local rates]
41 Cost of MS clamp [Local rates]
42 Lime stone dust [SI. No.102 & Sch Item No. 66]
43 Corrosion resistant steel [ Local rates]
44 GI pipe 100 mm dia [Local rate]
45 GI bolt 10 mm dia [Local rate]
46 Galvanised MS flat clamp [ local rate]
47 Geletin 80 % [ local rate]
48 Electric detonators [ local rate]
49 Water [ local rate]
50 Bentonite [ local rate]
51 Admixture [ local rate]
52 Copper plate [ local Rate]
53 20 mm thick compressive fibre board [ local rate]
54 Pre moulded joint filler12 m longx20 mm thick and 300 mmm deep local rate]
55 NP4 RCC pipe 1000 mm dia [Local rate]
56 Cost of paint [ local rate]

Cost of Cement
Cost of Cement (Rate as per PWD) = Rs:

Storage charges 5%
Rate per MT =

Cost of Steel
As per the PWD rate :
Cost of Steel upto 16mm dia Rs.
9

Cost of Steel above 16mm dia Rs.


Total

Storage charges 5 %(basic rate)


Rate per MT =
Cost of binding wires Galvanised =
10

RATE FOR BITUMEN EMULSION :


Latest price of Bitumen Emulsion Rs:

Rate (As per Revised Price Rate received from Hincol CHENNAI effective
from1.8.2011)

Excise duty 14%


Cess

Sales Tax 14.5%


Surcharges 0%
Storage Charges on base cost 5%
Conveyance Charges 500 Kms
at Rs: 1.69 / Km / MT
Service Charges 5%

Cost of Emulsion bitumen @ site :

COST OF CRUMB RUBBER MODIFIED BITUMEN:

Cost of CRUMB Modified Bitumen Bulk (The Revised Price


Rs:
Rate received from IOC CHENNAI
Excise duty 14.00%
Cess

VAT 14.50%
Surcharge on Sales tax 0%
Storage Charges on base cost 5%
Transport Charges for 500 Kms
2 X 500 0.99924
Service Charges on transport charges 5%
Rs.
Cost of Crumb Bitumen @ Site Rs
11

COST OF BULK BITUMEN 60/70 GRADE FROM COCHIN

Basic price of bitumen


Excise duty 14%
Cess
Basic cost + excise duty
CENTRAL VAT 2%
Sub Total
Transport Charges 396 Km
2 X 396 1.2763
Service charges on transport charges
Storage charges on basic rate I.e. on 32083.00
Cost of bitumen at site per MT
or
12

COST OF BULK BITUMEN 60/70 GRADE FROM CHENNA

Basic price of bitumen


Excise duty 14%
Cess
Basic cost + excise duty
VAT 5%
Surcharge on sales tax 0%
Total
Transport Charges 500 Km
2 X 500 0.99924
Service charges on transport charges 0%
Storage charges on basic rate 5%
Cost of bitumen at site per MT
or
13

Emulsion rate as on 01.09.2015)

Km
86.90
74.40

161.30
Km
86.90
0.00
86.90
Km
86.90
29.76
116.66
Km
43.45
14

0.00
43.45
15

Emulsion rate as on 01.09.2015)

Stacking Total cost


Cartage
Charges Rs.

(6) (7) (8)

161.30 0.00 528.30


161.30 0.00 571.30
161.30 0.00 692.30
161.30 0.00 806.30
161.30 0.00 1026.30
161.30 0.00 1026.30
161.30 0.00 1044.30
161.30 0.00 996.30
161.30 0.00 996.30
161.30 0.00 1372.30
161.30 0.00 1285.30
161.30 0.00 924.30
161.30 0.00 727.30
161.30 0.00 727.30
161.30 0.00 727.30

161.30 0.00 663.30


16

Stacking Total cost


Cartage
Charges Rs.

(6) (7) (8)

161.30 0.00 525.30


161.30 0.00 569.30
161.30 0.00 632.30
161.30 0.00 707.30
161.30 0.00 1009.30
161.30 0.00 890.30
161.30 0.00 1341.30
161.30 0.00 1256.30
161.30 0.00 967.30
161.30 0.00 707.30
161.30 0.00 653.30
161.30 0.00 266.30
161.30 0.00 540.30
161.30 0.00 489.30
161.30 0.00 681.30
161.30 0.00 489.30

161.30 0.00 464.30

86.90 3.05 246.95


116.66 0.00 293.06
17

116.66 3.05 296.11


161.30 0.00 243.30
5460.00
18

50.00 /Rm
25.00 /each
15.00 /each
817.52 /Cum (929*0.88)
43.00 /Kg
210.00 /m
1.30 /1 No.
7.50 /1 No.
25.00 /Kg
19.00 /each
150.00 /KL
24.20 /Kg
24.20 /Kg
165.00 /Kg
726.00 /sqm
mm deep local rate] 726.00 /sqm
2750.00 /Rm
275.00 /lit

ent
6400.00 / MT

211.39
6611.39 / MT

el
HYSD MS bars
43000.00 43000.00
19

43000.00 43000.00
86000.00 86000.00
86000.00 86000.00
2 2
43000.00 43000.00

1815.56 1815.56
44815.56 44815.56
45.60 45.60
20

LSION :
32392.00

4534.88
0.00
36926.88
5354.40
0.00
1619.60

845.00
0.00
44745.88
or 43246 /MT

34033.00

4764.62
0.00
38797.62
5625.65
0.00
1701.65

999.24
0.00
47124.16
(or) 47124.00 /MT
21

GRADE FROM COCHIN

60/70 Gr. 80/100 Gr.


32083.00 31283.00
4491.62 4379.62
0.00 0.00
asic cost + excise duty 36574.62 35662.62
731.49 713.25
37306.11 36375.87

1010.83 1010.83
5% 0.00 0.00
5% 1604.15 1564.15
39921.09 38950.85
39921.00 38951.00
22

GRADE FROM CHENNAI

60/70 Gr. 80/100 Gr.

32183.00 31383.00
4505.62 4393.62
0.00 0.00
asic cost + excise duty 36688.62 35776.62
1834.43 1788.83
0.00
38523.05 37565.45

999.24 999.24
0.00 0.00
1609.15 1569.15
41131.44 40133.84
41131.00 40134.00

39921.00 38951.00
9

Chapter - 17

HIRE CHARGES FOR MACHINARY


As per the rates specified in MOST Data Book and
as per Chief Engineer's (NH) Chennai Memo No: 10271 / opp. 1 / NH / 98 / dated 21.3.200
Description of Output of Machine Usage ra
S.
No Machine Activity Unit Output Unit 2001-02 2002-03
rates rates
Spreading Cum /hour 200

1 Dozer D - 50 - A15 Cutting Cum /hour 100 Per hour 1423.00 1494.00
Clearing Cum /hour 150

Spreading Cum /hour 300

2 Dozer D - 80 - A12 Cutting Cum /hour 150 Per hour 2400.00 2520.00
Clearing Cum /hour 250

Spreading Cum /hour 200

Cutting Cum /hour 200 1622.00


3 Motor Grader 3.35 metre blade Per hour 1545.00
GSB Cum /hour 50
10

3 Motor Grader 3.35 metre blade Per hour 1545.00

WMM Cum /hour 50

Ordinary soil Cum /hour 60


Hydraulic Excavator of 1 Cum
4
bucket
Marshy soil Cum /hour 60 Per hour 840.00 882.00
unsuitable soil Cum /hour 60

Soil loading Cum /hour 60


Front end loader 1 Cum bucket
5
capacity
Per hour 520.00 546.00
Aggregate loading Cum /hour 25
11

Per Km 15.60 16.00


Transportation of
Per tonne
6 Tipper - 5 Cum Soil, GSB, WMM, Capacity in Cum 5.5
Km 1.74 2.00
Hotmix, etc.
Per hour 200.00 210.00
Earth / soil Cum /hour 100

7 Vibratory Roller 8 tonne GSB Cum /hour 60 Per hour 994.00 1044.00
WMM Cum /hour 60

Soil Compaction Cum /hour 70


8 Smooth wheeled Roller 8 tonne Per hour 297.00 312.00
BM compaction Cum /hour 25

Cpacity in KL 6 Per Km 15.60 16.00


9 Water tanker Water transport
Per hour 200.00 210.00
10 Tractor Pulling Capacity in HP 50 Per hour 234.00 246.00
11 Rotavator Scarifying Cum/hour 25 Per hour 11.00 12.00
12 Ripper Scarifying Cum/hour 60 Per hour 18.00 19.00
13 Air compressor General purpose Capacity in cfm 170/250 Per hour 206.00 216.00
14 Wet Mix Plant 60 TPH Wet Mix Cum/hour 25 Per hour 777.00 816.00
Applying bitumen
15 Mechanical broom hydraulic
tack coat
Sqm/hour 1250 Per hour 230.00 242.00
12

Applying bitumen
16 Bitumen pressure distributor
tack coat
Sqm/hour 1750 Per hour 692.00 727.00
13

Applying Emulsion
17 Emulsion pressure distributor
tack coat
Sqm/hour 1750 Per hour 516.00 542.00
Hot mix plant - 120 TPH DBM / BM / SDBC /
18
capacity PC
Cum/hour 40 Per hour 15100.00 15855.00

Hot mix plant - 100 TPH DBM / BM / SDBC /


19
capacity PC
Cum/hour 30 Per hour 11167.00 11725.00

Hot mix plant - 60-90 TPH DBM / BM / SDBC /


20
capacity PC
Cum/hour 25 Per hour 8930.00 9377.00

Hot mix plant - 40-60 TPH DBM / BM / SDBC /


21
capacity PC
Cum/hour 17 Per hour 7150.00 7508.00
Hot mix plant - 6-10 TPH
22
capacity
PC Cum/hour 8 Per hour 1268.00 1331.00
Paver Finisher Hydrostatic with Paving of DBM / BM
23
sensor control 100 TPH / SDBC / PC
Cum/hour 40 Per hour 1725.00 1811.00

Paver Finisher Mechanical 100


Paving of WMM Cum/hour 40 Per hour 629.00 660.00
24
TPH
Paving of WMM Cum/hour 30 Per hour 629.00 660.00
25 Hydraulic Chip separator Surface dressing Sqm / hour 1500 Per hour 1700.00 1785.00
Rolling of Asphalt
26 Tandom road roller
surface
Cum/hour 30 Per hour 738.00 775.00
Rolling of Asphalt
27 Pneumatic road roller
surface
Cum/hour 25 Per hour 802.00 842.00

28 Pot hole repair machine Repair of pot holes Cum/hour 4 Per hour 585.00 614.00
14

29 Bitumen Boiler oil fired Bitumen spraying Capacity in litre 1500 Per hour 128.00 134.00
15

30 GSB Plant 50 cum Poducing GSB Cum/hour 40 Per hour 670.00 704.00
31 Mastic Cooker Mastic waring coat Capacity in tonne 1 Per hour 40.00 42.00
32 Batching and mixing plant

a) 30 Cum capacity Concrete mixing Cum / hour 20 Per hour 1440.00 1512.00
b) 15 - 20 Cum capacity Concrete mixing Cum / hour 13 Per hour 1200.00 1260.00
Transportation of
Cum/hour 4.5 Per hour 600.00 630.00
33 Transit mixer
concrete mix to site
Cum/hour 3 Per hour 550.00 578.00
34
Concrete pump of 45 & 30 Cum
Cum / hour 33 Per hour 165.00 173.00
Pumping of concrete
capacity
Cum / hour 22 Per hour 165.00 173.00
35 Cranes

a) 80 tonnes Lifting purpose Per hour 825.00 866.00


b) 35 tonnes Lifting purpose Per hour 550.00 578.00
c) 3 tonnes Lifting purpose Per hour 230.00 242.00
For pouring
36 Concrete bucket
concrete
Capacity in Cum 1 Per hour 10.00 11.00
37 Kerb casting machine Kerb making Rm / hour 80 Per hour 200.00 210.00
38 Concrete Mixer

a) 0.40/0.28 cum Concrete mixing Cum / hour 2.5 Per hour 150.00 158.00
16

b) 0.10 Cum Concrete mixing Cum / hour 7.5 Per hour 150.00 158.00
17

0.75 m to 1.2 m dia


39 Piling Rig with Bantonite Pump
Boring attachment
Rm / hour 2 to 3 Per hour 3525.00 3701.00

Concrete paver finisher with 40 Paving of concrete


40
HP Motor surface
Cum / hour 20 Per hour 1850.00 1943.00

41 Integrated stone crusher Crushing of spalls TPH 100 Per hour 5590.00 5870.00

Crushing of spalls TPH 200 Per hour 11760.00 12348.00

Stressing of steel
42 Prestressing jack with pump
wires / strands
Per hour 83.00 87.00

43 Generator

a) 100 KVA
Generation of
KVA 100 Per hour 450.00 473.00
electric energy
b) 33 KVA KVA 50 Per hour 240.00 252.00
Pneumatic sinking
44 Pneumatic sinking plant
of wells
Cum / hour 1.5 to 2.0 Per hour 2690.00 2825.00
Per Km 14.50 15.00
45 Truck 5.50 cum per 10 tonnes Material transport Capacity / Cum 4.5
Per tonne
Km 1.60 2.00
46 Road marking machine Road marking Sqm / hour 100 Per hour 60.00 63.00
Mixing and laying
47 Mobile slurry seal equipment
slurry seal
Sqm / hour 2700 Per hour 650.00 683.00
Plate compactor / power
48
rammer
Per hour 100.00 105.00
18

Notes :The Usage rates given above are for the year 2001-2002. For subsequent years, escalation is requ
upon the market situation .
19

k and
H / 98 / dated 21.3.2002 .
Usage rates in Rs:
As per
2003-04 2004-05 2005-06 2006-07 2012-13 2007-08
rates rates rates rates rates rates

1565.00 1636.00 1708.00 1779.00 2206.00 1779.00

2640.00 2760.00 2880.00 3000.00 3720.00 3000.00

1700.00 1777.00 1854.00 1931.00 2395.00 1931.00


20

924.00 966.00 1008.00 1050.00 1302.00 1050.00

572.00 598.00 624.00 650.00 806.00 650.00


21

17.00 18.00 19.00 20.00 24.00 20.00


2.00 2.00 2.00 2.00 3.00 2.00
220.00 230.00 240.00 250.00 310.00 250.00

1093.00 1143.00 1193.00 1243.00 1541.00 1243.00

327.00 342.00 356.00 371.00 460.00 371.00

17.00 18.00 19.00 20.00 24.00 20.00


220.00 230.00 240.00 250.00 310.00 250.00
257.00 269.00 281.00 293.00 363.00 293.00
12.00 13.00 13.00 14.00 17.00 14.00
20.00 21.00 22.00 23.00 28.00 23.00
227.00 237.00 247.00 258.00 319.00 258.00
855.00 894.00 932.00 971.00 1204.00 971.00
253.00 265.00 276.00 288.00 357.00 288.00
22

761.00 796.00 830.00 865.00 1073.00 865.00


23

568.00 593.00 619.00 645.00 800.00 645.00

16610.00 17365.00 18120.00 18875.00 23405.00 18875.00

12284.00 12842.00 13400.00 13959.00 17309.00 13959.00

9823.00 10270.00 10716.00 11163.00 13842.00 11163.00

7865.00 8223.00 8580.00 8938.00 11083.00 8938.00

1395.00 1458.00 1522.00 1585.00 1965.00 1585.00

1898.00 1984.00 2070.00 2156.00 2674.00 2156.00

692.00 723.00 755.00 786.00 975.00 786.00


692.00 723.00 755.00 786.00 975.00 786.00
1870.00 1955.00 2040.00 2125.00 2635.00 2125.00
812.00 849.00 886.00 923.00 1144.00 923.00

882.00 922.00 962.00 1003.00 1243.00 1003.00

644.00 673.00 702.00 731.00 907.00 731.00


24

141.00 147.00 154.00 160.00 198.00 160.00


25

737.00 771.00 804.00 838.00 1039.00 838.00


44.00 46.00 48.00 50.00 62.00 50.00

1584.00 1656.00 1728.00 1800.00 2232.00 1800.00


1320.00 1380.00 1440.00 1500.00 1860.00 1500.00
660.00 690.00 720.00 750.00 930.00 750.00
605.00 633.00 660.00 688.00 853.00 688.00
182.00 190.00 198.00 206.00 256.00 206.00
182.00 190.00 198.00 206.00 256.00 206.00

908.00 949.00 990.00 1031.00 1279.00 1031.00


605.00 633.00 660.00 688.00 853.00 688.00
253.00 265.00 276.00 288.00 357.00 288.00
11.00 12.00 12.00 13.00 16.00 13.00
220.00 230.00 240.00 250.00 310.00 250.00

165.00 173.00 180.00 188.00 233.00 188.00


26

165.00 173.00 180.00 188.00 233.00 188.00


27

3878.00 4054.00 4230.00 4406.00 5464.00 4406.00

2035.00 2128.00 2220.00 2313.00 2868.00 2313.00

6149.00 6429.00 6708.00 6988.00 8665.00 6988.00

12936.00 13524.00 14112.00 14700.00 18228.00 14700.00

91.00 95.00 100.00 104.00 129.00 104.00

495.00 518.00 540.00 563.00 698.00 563.00


264.00 276.00 288.00 300.00 372.00 300.00
2959.00 3094.00 3228.00 3363.00 4170.00 3363.00
16.00 17.00 17.00 18.00 22.00 18.00
2.00 2.00 2.00 2.00 2.00 2.00
66.00 69.00 72.00 75.00 93.00 75.00
715.00 748.00 780.00 813.00 1008.00 813.00

110.00 115.00 120.00 125.00 155.00 125.00


28

ars, escalation is required to be added depending


14

Chapter - 12

Foundation

Sl. No. Quantity Description Rate per

12.1 Excavation for Structures:


MORT & H Specifitation No: 304
I. In Ordinary Soil [Excluding dewatering]

Earthwork excavation for foundation of structures as per drawings


technical specifications, including setting out, construction of shoring
bracing, removal of stumps and other deleterious matter, dressing of s
and bottom and backfilling with approved material.

Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m :
a) Labour :
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /
Tot

(i) For major bridges and minor bridges


b) Overheads 25% on 1162.56
Total [
C) Contractor's profit 10% on 1453.20
Rate for 10 cum
Rate for 1 cum = 1598.52 /
Earth Work for foundation in ordinary
soil excluding dewatering = 159.85 /
-depth upto 3 m
(ii) For minor bridges in road packages and culverts
b) Overheads 20% on 1162.56
15

Total [
C) Contractor's profit 10% on 1395.07
Rate for 10 cum
Rate for 1 cum = 1534.58 /
Earth Work for foundation in ordinary
soil excluding dewatering = 153.46 /
-depth upto 3 m
16

I. In Ordinary Soil [Including dewatering]

Earthwork excavation for foundation of structures as per drawings


technical specifications, including setting out, construction of shoring
bracing, removal of stumps and other deleterious matter, dressing of s
and bottom and backfilling with approved material including cos
dewatering

Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m [Including dewatering]:
a) Labour :
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /

10% Add for dewatering on cost of labour 1162.56


Tot
(i) For major bridges and minor bridges
b) Overheads 25% on 1278.82
Total [
C) Contractor's profit 10% on 1598.53
Rate for 10 cum
Rate for 1 cum = 1758.38 /
Earth Work for foundation in ordinary
soil including dewatering for depth = 175.84 /
upto 3 m
(ii) For minor bridges in road packages and culverts
b) Overheads 20% on 1278.82
Total [
C) Contractor's profit 10% on 1534.58
Rate for 10 cum
Rate for 1 cum = 1688.04 /
17

Earth Work for foundation in ordinary


soil including dewatering for depth = 168.80 /
upto 3 m
18

A. Manual Means:
(ii) Depth 3 m to 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.18 Nos Mate 329.00 /
4.50 Nos Mazdoor 319.00 /

15% Add for dewatering on cost of labour 1494.72


Tot
(i) For major bridges and minor bridges
b) Overheads 25% on 1718.93
Total [
C) Contractor's profit 10% on 2148.66
Rate for 10 cum
Rate for 1 cum = 2363.53 /

Earth Work for foundation in ordinary


soil manually for 3m to 6 m depth = 236.35 /
including dewatering

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 1718.93
Total [
C) Contractor's profit 10% on 2062.72
Rate for 10 cum
Rate for 1 cum = 2268.99 /

Earth Work for foundation in ordinary


soil manually for 3m to 6 m depth = 226.90 /
including dewatering
19

A. Manual Means:
(iii) Depth above 6 m [including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.24 Nos Mate 329.00 /
6.00 Nos Mazdoor 319.00 /

20% Add for dewatering on cost of labour 1992.96


Tot
(i) For major bridges and minor bridges
b) Overheads 25% on 2391.55
Total [
C) Contractor's profit 10% on 2989.44
Rate for 10 cum
Rate for 1 cum = 3288.38 /

Earth Work for foundation in ordinary


= 328.84 /
soil manually for depth above 6 m

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 2391.55
Total [
C) Contractor's profit 10% on 2869.86
Rate for 10 cum
Rate for 1 cum = 3156.85

Earth Work for foundation in ordinary


= 315.69
soil manually for depth above 6 m
20

I. In Ordinary Soil [Including dewatering]

B. MECHANICAL MEANS
(i) Depth upto 3 m [ including dewatering]:
Unit = = Cum
Taking Output = = 240 cum
a) Labour :
0.32 Nos Mate 329.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity
1302.00 /

Tot
Total [
Add for dewatering on cost of
5% labour & machinary
10469.28

T
(i) For major bridges and minor bridges
b) Overheads 25% on 10992.74
Total [
C) Contractor's profit 10% on 13740.93
Rate for 240 cum
Rate for 1 cum = 15115.02 /

Earth Work for foundation in ordinary


= 62.98 /
soil mechanically for depth upto 3 m

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 10992.74
Total [
C) Contractor's profit 10% on 13191.29
21

Rate for 240 cum


Rate for 1 cum = 14510.42 /
Earth Work for foundation in ordinary
= 60.46 /
soil mechanically for depth upto 3 m
22

B. MECHANICAL MEANS
(ii) Depth 3 m to 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 210 cum
a) Labour :
0.32 Nos Mate 329.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity 1302.00 /

Tot
Total [
Add for dewatering on cost of
7.5% labour & machinary
10469.28

T
(i) For major bridges and minor bridges
b) Overheads 25% on 11254.48
Total [
C) Contractor's profit 10% on 14068.10
Rate for 210 cum
Rate for 1 cum = 15474.91 /
Earth Work for foundation in ordinary
soil mechanically for depth 3 to 6 m
= 73.69 /

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 11254.48
Total [
C) Contractor's profit 10% on 13505.38
Rate for 210 cum
Rate for 1 cum = 14855.92 /
23

Earth Work for foundation in ordinary


soil mechanically for depth 3 to 6 m
= 70.74 /
24

B. MECHANICAL MEANS
(iii) Depth above 6 m [ including dewatering]:
Unit = = Cum
Taking Output = = 180 cum
a) Labour :
0.40 Nos Mate 329.00 /
10.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity
1302.00 /

Tot
Total [
Add for dewatering on cost of
10.0% labour & machinary
11133.60

T
(i) For major bridges and minor bridges
b) Overheads 25% on 12246.96
Total [
C) Contractor's profit 10% on 15308.70
Rate for 180 cum
Rate for 1 cum = 16839.57 /

Earth Work for foundation in ordinary


soil mechanically for depth above 6 m
= 93.55 /

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 12246.96
Total [
C) Contractor's profit 10% on 14696.35
Rate for 180 cum
25

Rate for 1 cum = 16165.99 /


Earth Work for foundation in ordinary
soil mechanically for depth above 6 m
= 89.81 /
26

II. In Ordinary rock not requiring blasting [excluding dewatering]

Earthwork excavation for foundation of structures in ordinary rock


requiring blasting as per drawings and technical specifications, inclu
setting out, construction of shoring and bracing, removal of stumps
other deleterious matter, dressing of sides and bottom and backfilling
approved material excluding cost of dewatering

Unit = = Cum
Taking Output = = 10 cum
A. Manual Means:
(i) Depth upto 3 m [Excluding dewatering]:
a) Labour :
0.20 Nos Mate 329.00 /
5.00 Nos Mazdoor 319.00 /

0% Add for dewatering on cost of labour 1660.80


Tot
(i) For major bridges and minor bridges
b) Overheads 25% on 1660.80
Total [
C) Contractor's profit 10% on 2076.00
Rate for 10 cum
Rate for 1 cum = 2283.60 /
Earth work for foundation upto 3 m
manually in oridinary rock not = 228.36 /
requiring blasting
(ii) For minor bridges in road packages and culverts
b) Overheads 20% on 1660.80
Total [
C) Contractor's profit 10% on 1992.96
Rate for 10 cum
Rate for 1 cum = 2192.26 /
27

Earth work for foundation upto 3 m


manually in oridinary rock not = 219.23 /
requiring blasting
28

II. In Ordinary rock not requiring blasting [excluding dewatering]


B. MECHANICAL MEANS
(i) Depth upto 3 m [excluding dewatering]:
Unit = = Cum
Taking Output = = 180 cum
a) Labour :
0.24 Nos Mate 329.00 /
6.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity 1302.00 /
Tot
Total [
0.0% Add for dewatering on cost of labour 9804.96
T
(i) For major bridges and minor bridges
b) Overheads 25% on 9804.96
Total [
C) Contractor's profit 10% on 12256.20
Rate for 180 cum
Rate for 1 cum = 13481.82 /

Earth work for foundation upto 3 m


mechanically in oridinary rock not = 74.90 /
requiring blasting

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 9804.96
Total [
C) Contractor's profit 10% on 11765.95
29

Rate for 180 cum


Rate for 1 cum = 12942.55 /
Earth work for foundation upto 3 m
mechanically in oridinary rock not = 71.90 /
requiring blasting
30

III. In hard rock requiring blasting [including dewatering

A. MANUAL MEANS
(i) Depth upto 3 m [including dewatering]:
Unit = = Cum
Taking Output = = 10 cum
a) Labour :
0.35 Nos Mate 329.00 /
0.50 Nos Driller 282.00 /
0.25 Nos Blaster 282.00 /
8.00 Nos Mazdoor 319.00 /
Tot
b) Machinary
Air compressor 250 cfm with 2 jack
1.00 Hour hammer for drilling 319.00 /

Tot
Total [
C) Materials
3.50 Kg Blasting materials 25.00 /
14.00 Nos. Detonator electric 19.00 /
Tota
Total [a+
Add for dewatering on cost of labour and
10.0% machinary 3197.65
T
(i) For major bridges and minor bridges
d) Overheads 25% on 3870.92
Total [a+b+
e) Contractor's profit 10% on 4838.65
Rate for 10 cum
Rate for 1 cum = 5322.52 /
31

Earth work for foundation upto 3 m


manually in hard rock requiring blasting
= 532.25 /
32

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 3870.92
Total [a+b+
e) Contractor's profit 10% on 4645.10
Rate for 10 cum
Rate for 1 cum = 5109.61 /

Earth work for foundation upto 3 m


manually in hard rock requiring blasting
= 510.96 /

Sand Filling in Foundation Trenches as per Drawin


12.3.
Technical Specifications :
MORT & H Specifitation No: 304
Unit = Cum
Taking Output = 1 cum
a) Labour :
0.01 Nos Mate 329.00 /
0.30 Nos Mazdoor 319.00 /
Tot
b) Material:
1.20 Cum Sand for filling 296.11 /
Tot
Total [
(i) For major bridges and minor bridges
C) Overheads 25% on 454.32
Total [a+
d) Contractor's profit 10% on 567.90
Rate for 1 cum
Rate for 1 cum = 624.69 /
Sand filling in trenches = 624.69 /
33

(ii) For minor bridges in road packages and culverts


C) Overheads 20% on 454.32
Total [a+
C) Contractor's profit 10% on 545.18
Rate for 1 cum
Rate for 1 cum = 599.70 /

Sand filling in trenches = 599.70 /


34

12.4. Plain concrete 1:3:6 nominal mix in foundation with crushed s


aggregates 40 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days.

MORT & H Specifitation No: 2100


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.64 Nos Mate 329.00 /
1.00 Nos Mason class I 451.00 /
15.00 Nos Mazdoor 319.00 /
Tot
b) Material:
13.50 Cum 40 mm ISS metal 1009.30 /
6.75 Cum Sand for mortar 293.06 /
Cement (3.45-10% of 3.45 as per
3.11 Tonne cl 601.3.3
6611.39 /

18.00 KL Cost of water 150.00 /


Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
2.00 Hour Water tanker 310.00 /
Tot
Total [a+
(i) For major bridges and minor bridges
d) Overheads 25% on 48561.70
Total [a+b+
35

e) Contractor's profit 10% on 60702.13


Rate for 15 cum
Rate for 1 cum = 66772.34 /
PCC 1:3:6 for foundation = 4451.49 /
36

(ii) For minor bridges in road packages and culverts


C) Overheads 20% on 48561.70
Total [a+
C) Contractor's profit 10% on 58274.04
Rate for 15 cum

Rate for 1 cum = 64101.44 /

PCC 1:3:6 for foundation 4273.43 /


12.6 Cement mortar 1:3
MORT & H Specifitation No:
Unit = Cum
Taking Output = 1 cum
a) Labour :
0.04 Nos Mate 329.00 /
0.90 Nos Mazdoor 319.00 /
Tot
b) Material:
0.51 Tonne Cement 6611.39 /
1.05 Cum Sand for mortar 293.06 /
Tot
Total for cement mortar 1:3 = 3979.78 /

12.5. Brick masonry in cement mortar 1:3 in foundation complete ex


and plastering, as per drawing and techincal specifications
MORT & H Specifitation No: = 1300
Unit = Cum
Taking Output = 5 cum
a) Labour :
37

0.48 Nos Mate 329.00 /


4.00 Nos Mason class I 451.00 /
8.00 Nos Mazdoor 319.00 /
Tot
38

b) Material:
2500 Nos. Brick Class -I 5460.00 /
1.20 Cum Cement mortar 3979.78 /
Tot
Total [
(i) For major bridges and minor bridges
d) Overheads 25% on 22939.66
Total [a+
e) Contractor's profit 10% on 28674.58

Rate for 5 cum

Rate for 1 cum = 31542.04 /


Brick work in foundation in CM 1:3 = 6308.41 /
(ii) For minor bridges in road packages and culverts
C) Overheads 20% on 22939.66
Total [a+
C) Contractor's profit 10% on 27527.59
Rate for 5 cum
Rate for 1 cum = 30280.35 /
Rate for brick work in foundation in CM 1:3 = 6056.07 /
12.7 Stone masonry work in cement mortar 1:3 in foundation as
techincal specifications
MORT & H Specifitation No: = 1400
A. Square rubble courdsed rubble masonry [First resort]
MORT & H Specifitation No: = 1405.4
Unit = Cum
Taking Output = 5 cum
39

a) Labour :
0.66 Nos Mate 329.00 /
7.50 Nos Mason class I 451.00 /
9.00 Nos Mazdoor 319.00 /
Tot
40

b) Material:
5.50 Cum Coarsed rubble stone 464.30 /
Bond Stone [35 Nos X 0.24 X 0.24
0.79 Cum X 0.39 =0.79 Cum] 681.30 /

1.50 Cum Cement mortar 3979.78 /


Tot
Total [
(i) For major bridges and minor bridges
c) Overheads 25% on 15532.19
Total [a+
d) Contractor's profit 10% on 19415.24
Rate for 5 cum
Rate for 1 cum = 21356.76 /

Stone masonry in foundation in CM 1:3 = 4271.35 /

(ii) For minor bridges in road packages and culverts

c) Overheads 20% on 15532.19


Total [a+
d) Contractor's profit 10% on 18638.63
Rate for 5 cum
Rate for 1 cum = 20502.49 /

Stone masonry in foundation in CM 1:3 = 4100.50 /


41

B Random rubble masonry [Coursaed / uncoursed]


MORT & H Specifitation No: = 1405.3
Unit = Cum
Taking Output = 5 cum
a) Labour :
0.62 Nos Mate 329.00 /
6.00 Nos Mason class I 451.00 /
9.00 Nos Mazdoor 319.00 /
Tot
b) Material:
5.50 Cum Stone for RR masonry 540.30 /
Bond Stone
0.79 Cum [35 NosX0.24X0.24X0.39 =0.79 681.30 /
Cum]
1.55 Cum Cement mortar 1:3 3979.78 /
Tot
Total [
(i) For major bridges and minor bridges
c) Overheads 25% on 15459.52
Total [a+b+
d) Contractor's profit 10% on 19324.40
Rate for 5 cum
Rate for 1 cum = 21256.84 /
Random ruble masonry in CM 1:3 = 4251.37 /
(ii) For minor bridges in road packages and culverts
c) Overheads 20% on 15459.52
Total [a+
42

d) Contractor's profit 10% on 18551.42


Rate for 5 cum
Rate for 1 cum = 20406.56 /
Random ruble maasonry in CM 1:3 = 4081.31 /
43

12.8
A. Plain cement concrete M 15 [1:2:4 nominal mix] in foundation with cru
stone aggregates 40 mm nominal size mechanically mixed, place
foundation and compacted by vibrator including curing for 14 days.

MORT & H Specifitation No: 1500, 1700 & 2100


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
4.13 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tota
Total [a+
d) Form work
On cost of materials, labhour and
4% machinary
55166.11 /

Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 57372.75
Total [a+b+c+
f) Contractor's profit 10% on 71715.94
Rate for 15 cum
44

Rate for 1 cum = 78887.53 /


PCC M 15 for foundation concrete = 5259.17 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 57372.75
Total [a+b+c+
f) Contractor's profit 10% on 68847.30
Rate for 15 cum
Rate for 1 cum = 75732.03 /
PCC M 15 for foundation concrete = 5048.80 /
45

12.8 Plain cement concrete M 20 in foundation with crushed stone aggreg


B. 40 mm nominal size mechanically mixed, placed in foundation
compacted by vibrator including curing for 14 days.
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.16 Tonne Cement 6611.39 /
Tot
Total [
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
4.00% machinary 62367.33 /
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 64862.02
Total [a+b+c+
f) Contractor's profit 10% on 81077.53
Rate for 15 cum
46

Rate for 1 cum = 89185.28 /


PCC M 20 for foundation = 5945.69 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 64862.02
Total [a+b+c+
f) Contractor's profit 10% on 77834.42
Rate for 15 cum
Rate for 1 cum = 85617.86 /

PCC M 20 for foundation = 5707.86 /


47

12.8 Plain Cement concrete M 25 in foundation with crushed s


D. aggregates 40 mm nominal size mechanically mixed, place
foundation and compacted by vibrator including curing for 14 days
Case : I Using Concrete Mixer
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.99 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.75% machinary 67854.79 /
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 70399.34
Total [a+b+c+
f) Contractor's profit 10% on 87999.18
Rate for 15 cum
48

Rate for 1 cum = 96799.10 /

PCC M 25 for foundation using concrete mixer = 6453.27 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 70399.34
Total [a+b+c+
f) Contractor's profit 10% on 84479.21
Rate for 15 cum
Rate for 1 cum = 92927.13 /

PCC M 25 for foundation using concrete mixer = 6195.14 /

-*/-*/-
49

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
43.20 Cum 40 mm ISS metal 1009.30 /
43.20 Cum 20 mm ISS metal 1341.30 /
21.60 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
47.95 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.75% machinary
500554.43
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 519325.22
Total [a+b+c+
f) Contractor's profit 10% on 649156.53
50

Rate for 120 cum


Rate for 1 cum = 714072.18 /

PCC M 25 for foundation with batching plant = 5950.60 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 519325.22
Total [a+b+c+
f) Contractor's profit 10% on 623190.26
Rate for 120 cum
Rate for 1 cum = 685509.29 /

PCC M 25 for foundation with batching plant = 5712.58 /

*/-*/-*/-*/
51

12.8
F. Plain Cement concrete M 30 in foundation with crushed s
aggregates 40 mm nominal size mechanically mixed, place
foundation and compacted by vibrator including curing for 14 days

Case : I Using Concrete Mixer


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.08 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.50% machinary 68449.81 /
Tot
Total [a+b+

(i) For major bridges and minor bridges


e) Overheads 25% on 70845.55
Total [a+b+c+
52

f) Contractor's profit 10% on 88556.94


Rate for 15 cum
Rate for 1 cum = 97412.63 /

PCC M 30 for foundation using concrete mixer = 6494.18 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 70845.55
Total [a+b+c+
f) Contractor's profit 10% on 85014.66
Rate for 15 cum
Rate for 1 cum = 93516.13 /

PCC M 30 for foundation using concrete mixer = 6234.41 /


-*/-*/-
53

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
43.20 Cum 40 mm ISS metal 1009.30 /
43.20 Cum 20 mm ISS metal 1341.30 /
21.60 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.60 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.50% machinary
504851.83
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 522521.64
Total [a+b+c+
f) Contractor's profit 10% on 653152.05
Rate for 120 cum
54

Rate for 1 cum = 718467.26 /

PCC M 30 for foundation with batching plant = 5987.23 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 522521.64
Total [a+b+c+
f) Contractor's profit 10% on 627025.97
Rate for 120 cum
Rate for 1 cum = 689728.57 /

PCC M 30 for foundation with batching plant = 5747.74 /

*/-*/-*/-*/
55

12.8
C. Reinforced Cement concrete M 20 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days

Case : I Using Concrete Mixer


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.21 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
4.00% machinary 63480.90 /

Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 66020.14
Total [a+b+c+
f) Contractor's profit 10% on 82525.18
Rate for 15 cum
56

Rate for 1 cum = 90777.70 /

RCC M 20 for foundation using concrete mixer = 6051.85 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 66020.14
Total [a+b+c+
f) Contractor's profit 10% on 79224.17
Rate for 15 cum
Rate for 1 cum = 87146.59 /

RCC M 20 for foundation using concrete mixer = 5809.77 /

-*/-*/-
57

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
41.66 Tonne Cement 6611.39 /
Tot
Total [
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
4.00% machinary
465232.78 /
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 483842.09
Total [a+b+c+
f) Contractor's profit 10% on 604802.61
Rate for 120 cum
58

Rate for 1 cum = 665282.87 /

RCC M 20 for foundation with batching plant = 5544.02 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 483842.09
Total [a+b+c+
f) Contractor's profit 10% on 580610.51
Rate for 120 cum
Rate for 1 cum = 638671.56 /
RCC M 20 for foundation with batching plant = 5322.26 /
-*/-/*-/*-/*-/*-
59

12.8
E. Reinforced Cement concrete M 25 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days

Case : I Using Concrete Mixer


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.05 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.75% machinary
69034.47 /
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 71623.26
Total [a+b+c+
f) Contractor's profit 10% on 89529.08
Rate for 15 cum
60

Rate for 1 cum = 98481.99 /

RCC M 25 for foundation using concrete mixer = 6565.47 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 71623.26
Total [a+b+c+
f) Contractor's profit 10% on 85947.91
Rate for 15 cum
Rate for 1 cum = 94542.70 /

RCC M 25 for foundation using concrete mixer = 6302.85 /

-*/-*/-
61

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.38 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.75% machinary
509661.33
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 528773.63
Total [a+b+c+
f) Contractor's profit 10% on 660967.04
Rate for 120 cum
Rate for 1 cum = 727063.74 /
62

RCC M 25 for foundation with batching plant = 6058.86 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 528773.63
Total [a+b+c+
f) Contractor's profit 10% on 634528.36
Rate for 120 cum
Rate for 1 cum = 697981.20 /

RCC M 25 for foundation with batching plant = 5816.51 /

*/-*/-/*-/*
63

12.8
G. Reinforced Cement concrete M 30 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days

Case : I Using Concrete Mixer


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.50% machinary
69365.04

Tot
Total [a+b+

(i) For major bridges and minor bridges


e) Overheads 25% on 71792.82
Total [a+b+c+
f) Contractor's profit 10% on 89741.03
64

Rate for 15 cum


Rate for 1 cum = 98715.13 /

RCC M 30 for foundation using concrete mixer = 6581.01 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 71792.82
Total [a+b+c+
f) Contractor's profit 10% on 86151.38
Rate for 15 cum
Rate for 1 cum = 94766.52 /

RCC M 30 for foundation using concrete mixer = 6317.77 /

-*/-*/-
65

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.80 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.50% machinary
512438.11

Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 530373.44
Total [a+b+c+
f) Contractor's profit 10% on 662966.80
Rate for 120 cum
66

Rate for 1 cum = 729263.48 /


RCC M 30 for foundation concrete with batching
= 6077.20 /
plant

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 530373.44
Total [a+b+c+
f) Contractor's profit 10% on 636448.13
Rate for 120 cum
Rate for 1 cum = 700092.94 /
RCC M 30 for foundation concrete with batching
= 5834.11 /
plant
*/-*/-/*-/*
67

12.8
H. Reinforced Cement concrete M 35 in foundation with crushed s
aggregates 20 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days

Case : I Using Concrete Mixer


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Tot
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.33 Tonne Cement 6611.39 /
Tot
Total [
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
d) Form work
On cost of materials, labour and
3.00% machinary 70885.66 /
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 73012.23
Total [a+b+c+
f) Contractor's profit 10% on 91265.29
Rate for 15 cum
68

Rate for 1 cum = 100391.82 /

RCC M 35 for foundation using concrete mixer = 6692.79 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 73012.23
Total [a+b+c+
f) Contractor's profit 10% on 87614.68
Rate for 15 cum
Rate for 1 cum = 96376.15 /

RCC M 35 for foundation using concrete mixer = 6425.08 /

-*/-*/-
69

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Tot
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
50.64 Tonne Cement 6611.39 /
Tot
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Tot
Total [a+
d) Form work
On cost of materials, labhour and
3.00% machinary
524603.07
Tot
Total [a+b+
(i) For major bridges and minor bridges
e) Overheads 25% on 540341.16
Total [a+b+c+
f) Contractor's profit 10% on 675426.45
Rate for 120 cum
70

Rate for 1 cum = 742969.10 /

RCC M 35 for foundation with batching plant = 6191.41 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 540341.16
Total [a+b+c+
f) Contractor's profit 10% on 648409.39
Rate for 120 cum
Rate for 1 cum = 713250.33 /

RCC M 35 for foundation with batching plant = 5943.75 /

*/-*/-/*-/*
71

Rate per Amount

res as per drawings and


onstruction of shoring and
s matter, dressing of sides
l.

Nos 46.06
Nos 1116.50
Total [a] 1162.56

r bridges
290.64
Total [a+b] 1453.20
145.32
= 1598.52
10

cum

es and culverts
232.51
72

Total [a+b] 1395.07


139.51
= 1534.58
10

cum
73

res as per drawings and


onstruction of shoring and
s matter, dressing of sides
aterial including cost of

Nos 46.06
Nos 1116.50
1162.56
= 116.26
Total [a] 1278.82
r bridges
319.71
Total [a+b] 1598.53
159.85
= 1758.38
10

cum

es and culverts
255.76
Total [a+b] 1534.58
153.46
= 1688.04
10
74

cum
75

Nos 59.22
Nos 1435.50
1494.72
= 224.21
Total [a] 1718.93
r bridges
429.73
Total [a+b] 2148.66
214.87
= 2363.53
10

cum

es and culverts
343.79
Total [a+b] 2062.72
206.27
= 2268.99
10

cum
76

Nos 78.96
Nos 1914.00
1992.96
= 398.59
Total [a] 2391.55
r bridges
597.89
Total [a+b] 2989.44
298.94
= 3288.38
10

cum

es and culverts
478.31
Total [a+b] 2869.86
286.99
= 3156.85
/ 10

/ cum
77

Nos 105.28
Nos 2552.00
Total [a] 2657.28

Hour 7812.00

Total [b] 7812.00


Total [a+b] 10469.28

= 523.46

Total 10992.74
r bridges
2748.19
Total [a+b] 13740.93
1374.09
= 15115.02
240

cum

es and culverts
2198.55
Total [a+b] 13191.29
1319.13
78

= 14510.42
240

cum
79

Nos 105.28
Nos 2552.00
Total [a] 2657.28

Hour 7812.00

Total [b] 7812.00


Total [a+b] 10469.28

= 785.20

Total 11254.48
r bridges
2813.62
Total [a+b] 14068.10
1406.81
= 15474.91
210

cum

es and culverts
2250.90
Total [a+b] 13505.38
1350.54
= 14855.92
210
80

cum
81

Nos 131.60
Nos 3190.00
Total [a] 3321.60

Hour 7812.00

Total [b] 7812.00


Total [a+b] 11133.60

= 1113.36

Total 12246.96
r bridges
3061.74
Total [a+b] 15308.70
1530.87
= 16839.57
180

cum

es and culverts
2449.39
Total [a+b] 14696.35
1469.64
= 16165.99
82

180

cum
83

excluding dewatering]

ures in ordinary rock not


al specifications, including
g, removal of stumps and
bottom and backfilling with

Nos 65.80
Nos 1595.00
1660.80
= 0.00
Total [a] 1660.80
r bridges
415.20
Total [a+b] 2076.00
207.60
= 2283.60
10

cum

es and culverts
332.16
Total [a+b] 1992.96
199.30
= 2192.26
10
84

cum
85

excluding dewatering]

Nos 78.96
Nos 1914.00
Total [a] 1992.96

Hour 7812.00
Total [b] 7812.00
Total [a+b] 9804.96
= 0.00
Total 9804.96
r bridges
2451.24
Total [a+b] 12256.20
1225.62
= 13481.82
180

cum

es and culverts
1960.99
Total [a+b] 11765.95
1176.60
86

= 12942.55
180

cum
87

cluding dewatering]

Nos 115.15
Nos 141.00
Nos 70.50
Nos 2552.00
Total [a] 2878.65

Hour 319.00

Total [b] 319.00


Total [a+b] 3197.65

Kg 87.50
Nos. 266.00
Total [C] 353.50
Total [a+b+c] 3551.15
= 319.77
Total 3870.92
r bridges
967.73
Total [a+b+c+d] 4838.65
483.87
= 5322.52
10
88

cum
89

es and culverts
774.18
Total [a+b+c+d] 4645.10
464.51
= 5109.61
10

cum

es as per Drawing &

Nos 3.29
Nos 95.70
Total [a] 98.99

Cum 355.33
Total [b] 355.33
Total [a+b] 454.32
r bridges
113.58
Total [a+b+c] 567.90
56.79
= 624.69
1
cum
90

es and culverts
90.86
Total [a+b+c] 545.18
54.52
= 599.70
1

cum
91

tion with crushed stone


ixed, placed in foundation
days.

Nos 210.56
Nos 451.00
Nos 4785.00
Total [a] 5446.56

Cum 13625.55
Cum 1978.16

Tonne 20561.43

KL 2700.00
Total [b] 38865.14

Hour 1398.00
Hour 2232.00
Hour 620.00
Total [c] 4250.00
Total [a+b+c] 48561.70
r bridges
12140.43
Total [a+b+c+d] 60702.13
92

6070.21
= 66772.34
15
cum
93

es and culverts
9712.34
Total [a+b+c] 58274.04
5827.40
= 64101.44

15

cum

Nos 13.16
Nos 287.10
Total [a] 300.26

Tonne 3371.81
Cum 307.71
Total [b] 3679.52
cum

dation complete excluding pointing


al specifications
94

Nos 157.92
Nos 1804.00
Nos 2552.00
Total [a] 4513.92
95

1000 Nos. 13650.00


Cum 4775.74
Total [b] 18425.74
Total [a+b] 22939.66
r bridges
5734.92
Total [a+b+c] 28674.58

2867.46

= 31542.04

5
cum
es and culverts
4587.93
Total [a+b+c] 27527.59
2752.76
= 30280.35
5
cum
3 in foundation as per drawing and
96

Nos 217.14
Nos 3382.50
Nos 2871.00
Total [a] 6470.64
97

Cum 2553.65

Cum 538.23

Cum 5969.67
Total [b] 9061.55
Total [a+b] 15532.19
r bridges
3883.05
Total [a+b+c] 19415.24
1941.52
= 21356.76
5

cum

es and culverts

3106.44
Total [a+b+c] 18638.63
1863.86
= 20502.49
5

cum
98

d / uncoursed]

Nos 203.98
Nos 2706.00
Nos 2871.00
Total [a] 5780.98

Cum 2971.65

Cum 538.23

Cum 6168.66
Total [b] 9678.54
Total [a+b] 15459.52
r bridges
3864.88
Total [a+b+c+d] 19324.40
1932.44
= 21256.84
5
cum
es and culverts
3091.90
Total [a+b+c] 18551.42
99

1855.14
= 20406.56
5
cum
100

n foundation with crushed


anically mixed, placed in
uring for 14 days.

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67

Hour 1398.00
Hour 2232.00
Total [C] 3630.00
Total [a+b+c] 55166.11

0 2206.64

Total [d] 2206.64


Total [a+b+c+d] 57372.75
r bridges
14343.19
Total [a+b+c+d+e] 71715.94
7171.59
= 78887.53
101

15
cum
es and culverts
11474.55
Total [a+b+c+d+e] 68847.30
6884.73
= 75732.03
15
cum
102

crushed stone aggregates


laced in foundation and
s.

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34114.78
Total [b] 51397.89
Total [a+b] 58737.33

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 62367.33

0 2494.69
Total [d] 2494.69
Total [a+b+c+d] 64862.02
r bridges
16215.51
Total [a+b+c+d+e] 81077.53
8107.75
= 89185.28
103

15
cum

es and culverts
12972.40
Total [a+b+c+d+e] 77834.42
7783.44
= 85617.86
15

cum
104

tion with crushed stone


nically mixed, placed in
uring for 14 days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 39602.24
Total [b] 56885.35

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 67854.79

0 2544.55
Total [d] 2544.55
Total [a+b+c+d] 70399.34
r bridges
17599.84
Total [a+b+c+d+e] 87999.18
8799.92
= 96799.10
105

15

cum

es and culverts
14079.87
Total [a+b+c+d+e] 84479.21
8447.92
= 92927.13
15

cum
106

and concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 317016.23
Total [b] 455281.07

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 500554.43

0 18770.79
Total [d] 18770.79
Total [a+b+c+d] 519325.22
r bridges
129831.31
Total [a+b+c+d+e] 649156.53
64915.65
107

= 714072.18
120

cum

es and culverts
103865.04
Total [a+b+c+d+e] 623190.26
62319.03
= 685509.29
120

cum
108

tion with crushed stone


nically mixed, placed in
uring for 14 days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 40197.26
Total [b] 57480.37

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 68449.81

0 2395.74
Total [d] 2395.74
Total [a+b+c+d] 70845.55

r bridges
17711.39
Total [a+b+c+d+e] 88556.94
109

8855.69
= 97412.63
15

cum

es and culverts
14169.11
Total [a+b+c+d+e] 85014.66
8501.47
= 93516.13
15

cum
110

d concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 321313.63
Total [b] 459578.47

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 504851.83

0 17669.81
Total [d] 17669.81
Total [a+b+c+d] 522521.64
r bridges
130630.41
Total [a+b+c+d+e] 653152.05
65315.21
= 718467.26
111

120

cum

es and culverts
104504.33
Total [a+b+c+d+e] 627025.97
62702.60
= 689728.57
120

cum
112

ation with crushed stone


ixed, placed in foundation
days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 34445.35
Total [b] 52511.46

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 63480.90

0 2539.24

Total [d] 2539.24


Total [a+b+c+d] 66020.14
r bridges
16505.04
Total [a+b+c+d+e] 82525.18
8252.52
= 90777.70
113

15

cum

es and culverts
13204.03
Total [a+b+c+d+e] 79224.17
7922.42
= 87146.59
15

cum
114

d concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 275430.58
Total [b] 419959.42
Total [a+b] 427330.78

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 465232.78

0 18609.31
Total [d] 18609.31
Total [a+b+c+d] 483842.09
r bridges
120960.52
Total [a+b+c+d+e] 604802.61
60480.26
= 665282.87
115

120

cum

es and culverts
96768.42
Total [a+b+c+d+e] 580610.51
58061.05
= 638671.56
120
cum
116

dation with crushed stone


ixed, placed in foundation
days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39998.92
Total [b] 58065.03

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 69034.47

0 2588.79
Total [d] 2588.79
Total [a+b+c+d] 71623.26
r bridges
17905.82
Total [a+b+c+d+e] 89529.08
8952.91
= 98481.99
117

15

cum

es and culverts
14324.65
Total [a+b+c+d+e] 85947.91
8594.79
= 94542.70
15

cum
118

d concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 319859.13
Total [b] 464387.97

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 509661.33

0 19112.30
Total [d] 19112.30
Total [a+b+c+d] 528773.63
r bridges
132193.41
Total [a+b+c+d+e] 660967.04
66096.70
= 727063.74
120
119

cum

es and culverts
105754.73
Total [a+b+c+d+e] 634528.36
63452.84
= 697981.20
120

cum
120

dation with crushed stone


ixed, placed in foundation
days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 69365.04

0 2427.78

Total [d] 2427.78


Total [a+b+c+d] 71792.82

r bridges
17948.21
Total [a+b+c+d+e] 89741.03
8974.10
121

= 98715.13
15

cum

es and culverts
14358.56
Total [a+b+c+d+e] 86151.38
8615.14
= 94766.52
15

cum
122

d concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 322635.91
Total [b] 467164.75

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 512438.11

0 17935.33

Total [d] 17935.33


Total [a+b+c+d] 530373.44
r bridges
132593.36
Total [a+b+c+d+e] 662966.80
66296.68
= 729263.48
123

120

cum

es and culverts
106074.69
Total [a+b+c+d+e] 636448.13
63644.81
= 700092.94
120

cum
124

dation with crushed stone


ixed, placed in foundation
days

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22
Total [a+b] 67255.66

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
Total [a+b+c] 70885.66

0 2126.57
Total [d] 2126.57
Total [a+b+c+d] 73012.23
r bridges
18253.06
Total [a+b+c+d+e] 91265.29
9126.53
= 100391.82
125

15

cum

es and culverts
14602.45
Total [a+b+c+d+e] 87614.68
8761.47
= 96376.15
15

cum
126

d concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 524603.07

0 15738.09
Total [d] 15738.09
Total [a+b+c+d] 540341.16
r bridges
135085.29
Total [a+b+c+d+e] 675426.45
67542.65
= 742969.10
127

120

cum

es and culverts
108068.23
Total [a+b+c+d+e] 648409.39
64840.94
= 713250.33
120

cum
44

Data for pile, pile cap, levelling course below pile cap and steel for
Pile foundation.

Sl. No. Quantity Description Rate per

12.23. Bored cast -in situ M 35 grade RC pile excluding


reinforcement complete as per drawing and techincal
specifications and removal of excavated earth with all lead
and lifts upto 1000 m

Pile diameter = 750 mm


Case : I Using Concrete Mixer
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 Cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
21.60 Kg Admixture 24.20 /
6.75 Cum Sand for mortar 293.06 /
6.29 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
45

On cost of materials and labour


towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under
66744.08
water concreteing with tremie
pipe

Cost of concrete M 35 grade for 15


Cost of concrete M 35 grade for one cum 70081.28 /
= 4672.09
46

Data for Cast in situ pilec 750 mm dia


Unit = Rm
Taking Output = 15 Rm
a) Machinary
Hydraulic piling rig with power
unit and complete accessories
6.00 Hour including shifting from one bore
5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage
357.00 /

0.30 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.30 Hour disposal of muck from pile bore 310.00 /
hole
300.00 Kg Bentonite 24.20 /
Total [a]
b) Labour
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /
Total [b]
c) Materials
6.62 Cum Cost of concrete M 35 grade 4672.09 /
Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 72649.10
Total [a+b+c+d]
e) Contractor's profit 10% on 90811.38
Rate for 15 Rm
Rate for 1 Rm = 99892.52 /
Cast in situ 750 mm dia. pile in RCC M 35
grade using concrete mixer
= 6659.50 /
47

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 72649.10
Total [a+b+c+d+e]
f) Contractor's profit 10% on 87178.92
Rate for 15 Rm
Rate for 1 Rm = 95896.81 /

Cast in situ 750 mm dia. pile in RCC M 35


grade using concrete mixer
= 6393.12 /

-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
172.80 Kg Admixture 24.20 /
50.28 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
48

6.00 Hour Loader 1 cum capacity 806.00 /


Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /

6.00 Hour Concrete pump 256.00 /


Total [c]
Total [a+b+c]
49

d) Form work
On cost of materials and labour
towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under 488515.89
water concreteing with tremie
pipe

Total [d]
Rate for 120 cum Total [a+b+c+d]
Rate for 1 Cum 550843.68 /
= 4590.36
Data for Cast in situ pilec 750 mm dia
Unit = Rm
Taking Output = 15 Rm
a) Machinary
Hydraulic piling rig with power
unit and complete accessories
6.00 Hour including shifting from one bore
5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage 357.00 /

0.30 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.30 Hour disposal of muck from pile bore 310.00 /
hole
300.00 Kg Bentonite 24.20 /
Total [a]
b) Labour
0.14 Nos Mate 329.00 /
3.50 Nos Mazdoor 319.00 /
Total [b]
c) Materials
6.62 Cum Cost of concrete M 35 grade 4590.36 /
Total [c]
50

Total [a+b+c]
(i) For major bridges and minor bridges
e) Overheads 25% on 72108.04
Total [a+b+c+d+e]
f) Contractor's profit 10% on 90135.05
Rate for 15 Rm
Rate for 1 Rm = 99148.56 /
Cast in situ 750 mm dia. pile in RCC M 35
grade using Batching plant
= 6609.90 /
51

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 72108.04
Total [a+b+c+d+e]
f) Contractor's profit 10% on 86529.65
Rate for 15 Rm
Rate for 1 Rm = 95182.62 /
Cast in situ 750 mm dia. pile in RCC M 35
grade using Batching plant
= 6345.51 /

-*/-*/-
12.24 Bored cast -in situ M 35 grade RC pile excluding
reinforcement complete as per drawing and techincal
specifications and removal of excavated earth with all lead
and lifts upto 1000 m

Pile diameter = 1000 mm


Case : I Using Concrete Mixer
MORT & H Specifitation No: 1100,1600 & 1700
Unit = Cum
Taking Output = 15 Cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]

b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
21.60 Kg Admixture 24.20 /
6.75 Cum Sand for mortar 293.06 /
52

6.29 Tonne Cement 6611.39 /


Total [b]
Total [a+b]
53

On cost of materials and labour


towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under
66744.08
water concreteing with tremie
pipe

Cost of concrete M 35 grade for 15


Cost of concrete M 35 grade 70081.28 /
= 4672.09
Data for Cast in situ piles 1000 mm dia
Unit = Rm
Taking Output = 10 Rm
a) Machinary for boring and construction:

Hydraulic piling rig with power


unit and complete accessories
6.00 Hour including shifting from one bore 5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage
357.00 /

0.40 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.40 Hour disposal of muck from pile bore 310.00 /
hole
350.00 Kg Bentonite 24.20 /
Total [a]
54

b) Labour
0.16 Nos Mate 329.00 /
4.00 Nos Mazdoor 319.00 /
Total [b]
c) Materials
7.85 Cum Cost of concrete M 35 grade 4672.09 /
Total [c]
Total [a+b+c]

(i) For major bridges and minor bridges


d) Overheads 25% on 79883.45
Total [a+b+c+d]
e) Contractor's profit 10% on 99854.31
Rate for 10 Rm
Rate for 1 Rm = 109839.74 /
Cast in situ 1000 mm dia. pile in RCC M 35
grade using concrete mixer
= 10983.97 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 79883.45
Total [a+b+c+d+e]
f) Contractor's profit 10% on 95860.14
Rate for 10 Rm
Rate for 1 Rm = 105446.15 /

Cast in situ 1000 mm dia. pile in RCC M 35


grade using concrete mixer
= 10544.62 /

-*/-*/-
55

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
172.80 Kg Admixture 24.20 /
50.28 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
Total [a+b+c]
56

On cost of materials and labour


towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under 526417.89
water concreteing with tremie
pipe

Rate for 120 cum


Rate for 1 cum = 552738.78 /

Rate for RCC M 35 grade concrete using


= 4606.16 /
Batching plant
57

Data for Cast in situ piles 1000 mm dia


Unit = Rm
Taking Output = 10 Rm
a) Machinary for boring and construction:

Hydraulic piling rig with power


unit and complete accessories
6.00 Hour including shifting from one bore
5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage
357.00 /

0.40 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.40 Hour disposal of muck from pile bore 310.00 /
hole

350.00 Kg Bentonite 24.20 /


Total [a]
b) Labour
0.16 Nos Mate 329.00 /
4.00 Nos Mazdoor 319.00 /
Total [b]
c) Materials
7.85 Cum Cost of concrete M 35 grade 4606.16 /
Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 79365.90
Total [a+b+c+d]
e) Contractor's profit 10% on 99207.38
58

Rate for 10 Rm
Rate for 1 Rm = 109128.12 /

Cast in situ 1000 mm dia. pile in RCC M 35


grade using Batching plant
= 10912.81 /
59

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 79365.90
Total [a+b+c+d+e]
f) Contractor's profit 10% on 95239.08
Rate for 10 Rm
Rate for 1 Rm = 104762.99 /

Cast in situ 1000 mm dia. pile in RCC M 35


grade using Batching plant
= 10476.30 /

-*/-*/-
12.25 Bored cast -in situ M 35 grade RC pile excluding reinforcement
complete as per drawing and techincal specifications and removal of
excavated earth with all lead and lifts upto 1000 m
Pile diameter = 1200 mm
Case : I Using Concrete Mixer
MORT & H Specifitation No: 1100,1600 & 1700
Unit = Cum
Taking Output = 15 Cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
60

21.60 Kg Admixture 24.20 /


6.75 Cum Sand for mortar 293.06 /
6.29 Tonne Cement 6611.39 /
Total [b]
61

Total [a+b]

On cost of materials and labour


towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under
66744.08
water concreteing with tremie
pipe

Cost of concrete M 35 grade for 15


Cost of concrete M 35 grade for 1cum 70081.28 /
= 4672.09
Data for Cast in situ piles 1200 mm dia
Unit = Rm
Taking Output = 9 Rm
a) Machinary for boring and construction:
Hydraulic piling rig with power
unit and complete accessories
6.00 Hour including shifting from one bore 5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage
357.00 /

0.50 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.50 Hour disposal of muck from pile bore 310.00 /
hole

385.00 Kg Bentonite 24.20 /


Total [a]
b) Labour
0.18 Nos Mate 329.00 /
4.50 Nos Mazdoor 319.00 /
Total [b]
c) Materials
62

10.17 Cum Cost of concrete M 35 grade 4672.09 /


Total [c]
Total [a+b+c]
63

(i) For major bridges and minor bridges


d) Overheads 25% on 91847.38
Total [a+b+c+d]
e) Contractor's profit 10% on 114809.23
Rate for 9 Rm
Rate for 1 Rm = 126290.15 /
Cast in situ 1200 mm dia. pile in RCC M 35
grade using concrete mixer
= 14032.24 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 91847.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 110216.86
Rate for 9 Rm
Rate for 1 Rm = 121238.55 /
Cast in situ 1200 mm dia. pile in RCC M 35
grade using concrete mixer
= 13470.95 /

-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
64

b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
172.80 Kg Admixture 24.20 /
50.28 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /

6.00 Hour Concrete pump 256.00 /


Total [b]
Total [a+b+c]

On cost of materials and labour


towards cost of forming sump,
protective bunds, chiselling and
5.00% making arrangements for under
526417.89
water concreteing with tremie
pipe

Rate for 120 cum


Rate for 1 cum = 552738.78 /

RCC M 35 grade concrete using Batching plant = 4606.16 /


65

Data for Cast in situ piles 1200 mm dia using batching plant:
Unit = Rm
Taking Output = 9 Rm
a) Machinary for boring and construction:

Hydraulic piling rig with power


unit and complete accessories
6.00 Hour including shifting from one bore
5464.00 /
to another bore location

Light crane for lowering


0.50 Hour reinforcement guage 357.00 /

0.50 Hour Loader 1 cum bucket capacity 806.00 /


Tipper 5.5 cum capacity for
0.50 Hour disposal of muck from pile bore 310.00 /
hole

385.00 Kg Bentonite 24.20 /


Total [a]
b) Labour
0.18 Nos Mate 329.00 /
4.50 Nos Mazdoor 319.00 /
Total [b]
c) Materials
10.17 Cum Cost of concrete M 35 grade 4606.16 /
Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 91176.87
Total [a+b+c+d]
e) Contractor's profit 10% on 113971.09
66

Rate for 9 Rm
Rate for 1 Rm = 125368.20 /
Cast in situ 1200 mm dia. pile in RCC M 35
grade using Batching plant
= 13929.80 /
67

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 91176.87
Total [a+b+c+d+e]
f) Contractor's profit 10% on 109412.24
Rate for 9 Rm
Rate for 1 Rm = 120353.46 /

Cast in situ 1200 mm dia. pile in RCC M 35


grade using Batching plant
= 13372.61 /

-*/-*/-
12.37 Pile load test on single vertical pile in accordance with
IS:2911(Part-IV)
MORT& H Specification No : 1100
Unit = MT
Taking output = 1 MT
1 MT Initial and routine load test 300.00 /
1 MT Lateral load test 5000.00 /
Note: Although this item is incidental to work and is not required to
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work

-*/-*/-
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.

B RCC Grade M 20:


Unit = Cum
Taking output = 15 Cum
Case-I Using Concrete Mixer:
68

a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
69

b) Material:
5.12 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 0.40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary 63218.04 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 65746.76
Total [a+b+c+d+e]
f) Contractor's profit 10% on 82183.45
Rate for 15 Cum
Rate for 1 cum = 90401.80 /

RCC M 20 for pile cap using concrete mixer = 6026.79 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 65746.76
70

Total [a+b+c+d+e]
f) Contractor's profit 10% on 78896.11
Rate for 15 Cum
Rate for 1 cum = 86785.72 /

RCC M 20 for pile cap using concrete mixer = 5785.71 /

-*/-*/-
71

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.16 Nos Mate 329.00 /
0.38 Nos Mason class I 451.00 /
2.50 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.12 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /

0.75 Hour Concrete pump 256.00 /


Total [b]
72

Total [a+b+c]
d) Form work
On cost of materials, labhour and
4.00% machinary
58110.96

Total [d]
Total [a+b+c+d]
73

(i) For major bridges and minor bridges


e) Overheads 25% on 60435.40
Total [a+b+c+d+e]
f) Contractor's profit 10% on 75544.25
Rate for 15 cum
Rate for 1 cum = 83098.68 /

RCC M 20 for Pile cap with batching plant = 5539.91 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 60435.40
Total [a+b+c+d+e]
f) Contractor's profit 10% on 72522.48
Rate for 15 cum
Rate for 1 cum = 79774.73 /

RCC M 20 for Pile cap with batching plant = 5318.32 /

*/-*/-/*-/*
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.

B RCC Grade M 25:


Unit = Cum
Taking output = 15 Cum
Case-I Using Concrete Mixer:

a) Labour :
0.90 Nos Mate 329.00 /
74

1.50 Nos Mason class I 451.00 /


20.00 Nos Mazdoor for concreting 319.00 /

Mazdoor for breaking pile head,


1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
75

b) Material:
5.99 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary 68969.95 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 71728.75
Total [a+b+c+d+e]
f) Contractor's profit 10% on 89660.94
Rate for 15 Cum
Rate for 1 cum = 98627.03 /

RCC M 25 for pile cap using concrete mixer = 6575.14 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 71728.75
76

Total [a+b+c+d+e]
f) Contractor's profit 10% on 86074.50
Rate for 15 Cum
Rate for 1 cum = 94681.95 /

RCC M 25 for pile cap using concrete mixer = 6312.13 /

-*/-*/-
77

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.16 Nos Mate 329.00 /
0.38 Nos Mason class I 451.00 /
2.50 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.99 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /

0.75 Hour Concrete pump 256.00 /


Total [b]
78

Total [a+b+c]
d) Form work

On cost of materials, labhour and


4% machinary
63862.87

Total [d]
Total [a+b+c+d]
79

(i) For major bridges and minor bridges


e) Overheads 25% on 66417.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 83021.73
Rate for 15 cum
Rate for 1 cum = 91323.90 /

RCC M 25 for Pile cap with batching plant = 6088.26 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 66417.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 79700.86
Rate for 15 cum
Rate for 1 cum = 87670.95 /

RCC M 25 for Pile cap with batching plant = 5844.73 /

*/-*/-/*-/*
12.38. Cement concrete for reinforced cement concrete in pile cap
complete as per drawing and techinical specifications.

A. RCC Grade M 30:


Unit = Cum
Taking output = 15 Cum
Case-I Using Concrete Mixer:

a) Labour :
0.90 Nos Mate 329.00 /
80

1.50 Nos Mason class I 451.00 /


20.00 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
81

b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4.00% machinary
69697.20 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 72485.09
Total [a+b+c+d+e]
f) Contractor's profit 10% on 90606.36
Rate for 15 Cum
Rate for 1 cum = 99667.00 /

RCC M 30 for pile cap using concrete mixer = 6644.47 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 72485.09
82

Total [a+b+c+d+e]
f) Contractor's profit 10% on 86982.11
Rate for 15 Cum
Rate for 1 cum = 95680.32 /

RCC M 30 for pile cap using concrete mixer = 6378.69 /

-*/-*/-
83

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.16 Nos Mate 329.00 /
0.38 Nos Mason class I 451.00 /
2.50 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /

0.75 Hour Concrete pump 256.00 /


84

Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labhour and
4% machinary 64590.12

Total [d]
Total [a+b+c+d]
85

(i) For major bridges and minor bridges


e) Overheads 25% on 67173.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 83967.15
Rate for 15 cum
Rate for 1 cum = 92363.87 /

RCC M 30 for Pile cap with batching plant = 6157.59 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 67173.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 80608.46
Rate for 15 cum
Rate for 1 cum = 88669.31 /

RCC M 30 for Pile cap with batching plant = 5911.29 /

*/-*/-/*-/*

12.38. Cement concrete for reinforced cement concrete in pile cap


complete as per drawing and techinical specifications.

A. RCC Grade M 35:


Unit = Cum
Taking output = 15 Cum
Case-I Using Concrete Mixer:

a) Labour :
86

0.90 Nos Mate 329.00 /


1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor for concreting 319.00 /
Mazdoor for breaking pile head,
1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
87

b) Material:
6.33 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]
d) Form work
On cost of materials, labour and
4% machinary
71217.82 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 74066.53
Total [a+b+c+d+e]
f) Contractor's profit 10% on 92583.16
Rate for 15 Cum
Rate for 1 cum = 101841.48 /

RCC M 30 for pile cap using concrete mixer = 6789.43 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 74066.53
88

Total [a+b+c+d+e]
f) Contractor's profit 10% on 88879.84
Rate for 15 Cum
Rate for 1 cum = 97767.82 /

RCC M 30 for pile cap using concrete mixer = 6517.85 /

-*/-*/-
89

Case : II Using Batching Plant, transit mixer and concrete pump


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.16 Nos Mate 329.00 /
0.38 Nos Mason class I 451.00 /
2.50 Nos Mazdoor for concreting 319.00 /

Mazdoor for breaking pile head,


1.00 Nos bendingbars, cleaning, etc.
319.00 /

Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.33 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
C) Machinary
0.75 Hour Batching Plant 20 Cum / hour 2232.00 /
0.75 Hour Generator 100 KVA 698.00 /
0.75 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
2.00 Hour lead upto 1 Km 930.00 /

0.75 Hour Concrete pump 256.00 /


Total [b]
90

Total [a+b+c]
d) Form work
On cost of materials, labhour and
4% machinary 66110.74

Total [d]
Total [a+b+c+d]
91

(i) For major bridges and minor bridges


e) Overheads 25% on 68755.17
Total [a+b+c+d+e]
f) Contractor's profit 10% on 85943.96
Rate for 15 cum
Rate for 1 cum = 94538.36 /

RCC M 35 for Pile cap with batching plant = 6302.56 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 68755.17
Total [a+b+c+d+e]
f) Contractor's profit 10% on 82506.20
Rate for 15 cum
Rate for 1 cum = 90756.82 /

RCC M 35 for Pile cap with batching plant = 6050.45 /

*/-*/-/*-/*

12.39. Levelling course for pile cap in Plain Cement concrete M


15 for 100 mm thick below pile cap

MoRT & H Specification No : 1100 & 1700


Unit = Cum
Taking output = 15 Cum
Using Concrete Mixer:

a) Labour :
92

0.86 Nos Mate 329.00 /


1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor for concreting 319.00 /
Total [a]
93

b) Material:
4.13 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
Total [a+b+c]

(i) For major bridges and minor bridges


d) Overheads 25% on 55166.11
Total [a+b+c+d]
e) Contractor's profit 10% on 68957.64
Rate for 15 Cum
Rate for 1 cum = 75853.40 /

Levelling course below pile capin M 15 = 5056.89 /

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 55166.11
Total [a+b+c+d]
e) Contractor's profit 10% on 66199.33
94

Rate for 15 Cum


Rate for 1 cum = 72819.26 /

Levelling course below pile capin M 15 = 4854.62 /

-*/-*/-
95

12.40. Supplying, fitting and placing uncoated HYSD bar reinforcement in


pile foundation complete as per drawing and technical specifications.

MoRT & H Specification No : 1600


Unit = MT
Taking output = 1 MT

Labour for cutting, bendingshifting to site, tying and


a)
placing in position:
0.40 Nos Mate 329.00 /
2.00 Nos Black smith 348.00 /
6.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
1.05 Tonne HYSD bars 44815.56 /
6.00 Kg Binding wire 45.60 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 50071.54
Total [a+b+c+d]
d) Contractor's profit 10% on 62589.43
Rate for 1 MT
Rate for 1 MT = 68848.37 /
HYSD bars for piles = 68848.37 /
(ii) For minor bridges in road packages and culverts
c) Overheads 20% on 50071.54
96

Total [a+b+c]
d) Contractor's profit 10% on 60085.85
Rate for 1 MT
Rate for 1 MT = 66094.44 /
HYSD bars for piles = 66094.44 /
-*/-*/-
97

12.41. Supplying, fitting and placing uncoated Mild steel reinforcement in


pile foundation complete as per drawing and technical specifications.

MoRT & H Specification No : 1600


Unit = MT
Taking output = 1 MT

Labour for cutting, bendingshifting to site, tying and


a)
placing in position:

0.43 Nos Mate 329.00 /


2.25 Nos Black smith 348.00 /
6.50 Nos Mazdoor 319.00 /
Total [a]
b) Material:
1.05 Tonne MS BAR 44815.56 /
6.00 Kg Binding wire 45.60 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 50327.91
Total [a+b+c+d]
d) Contractor's profit 10% on 62909.89
Rate for 1 MT
Rate for 1 cum = 69200.88 /
Mild steel bars for piles = 69200.88 /
(ii) For minor bridges in road packages and culverts
c) Overheads 20% on 50327.91
98

Total [a+b+c]
d) Contractor's profit 10% on 60393.49
Rate for 1 MT
Rate for 1 cum = 66432.84 /
Mild steel bars for piles = 66432.84 /
-*/-*/-
99

pile cap and steel for

Rate per Amount

pile excluding
and techincal
th with all lead

Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60

Cum 5450.22
Cum 7243.02
Cum 2611.71
Kg 522.72
Cum 1978.16
Tonne 41585.65
Total [b] 59391.48
Total [a+b] 66744.08
100

0 3337.20

Cum = 70081.28
15
101

Hour 32784.00

Hour 178.50

Hour 241.80

Hour 93.00

Kg 7260.00
Total [a] 40557.30

Nos 46.06
Nos 1116.50
Total [b] 1162.56

Cum 30929.24
Total [c] 30929.24
Total [a+b+c] 72649.10
ges
18162.28
Total [a+b+c+d] 90811.38
9081.14
= 99892.52
15

Rm
102

d culverts
14529.82
Total [a+b+c+d+e] 87178.92
8717.89
= 95896.81
15

Rm

oncrete pump

Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52

Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89

Hour 13392.00
Hour 4188.00
103

Hour 4836.00

Hour 13950.00

Hour 1536.00
Total [c] 37902.00
Total [a+b+c] 526417.89
104

0 24425.79

Total [d] 24425.79


Total [a+b+c+d] 550843.68
120

Hour 32784.00

Hour 178.50

Hour 241.80

Hour 93.00

Kg 7260.00
Total [a] 40557.30

Nos 46.06
Nos 1116.50
Total [b] 1162.56

Cum 30388.18
Total [c] 30388.18
105

Total [a+b+c] 72108.04


ges
18027.01
Total [a+b+c+d+e] 90135.05
9013.51
= 99148.56
15

Rm
106

d culverts
14421.61
Total [a+b+c+d+e] 86529.65
8652.97
= 95182.62
15

Rm

pile excluding
and techincal
th with all lead

Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60

Cum 5450.22
Cum 7243.02
Cum 2611.71
Kg 522.72
Cum 1978.16
107

Tonne 41585.65
Total [b] 59391.48
Total [a+b] 66744.08
108

0 3337.20

Cum = 70081.28
15

Hour 32784.00

Hour 178.50

Hour 322.40

Hour 124.00

Kg 8470.00
Total [a] 41878.90
109

Nos 52.64
Nos 1276.00
Total [b] 1328.64

Cum 36675.91
Total [c] 36675.91
Total [a+b+c] 79883.45

ges
19970.86
Total [a+b+c+d] 99854.31
9985.43
= 109839.74
10

Rm

d culverts
15976.69
Total [a+b+c+d+e] 95860.14
9586.01
= 105446.15
10

Rm
110

oncrete pump

Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52

Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 526417.89
111

0 26320.89

= 552738.78
120

cum
112

Hour 32784.00

Hour 178.50

Hour 322.40

Hour 124.00

Kg 8470.00
Total [a] 41878.90

Nos 52.64
Nos 1276.00
Total [b] 1328.64

Cum 36158.36
Total [c] 36158.36
Total [a+b+c] 79365.90
ges
19841.48
Total [a+b+c+d] 99207.38
9920.74
113

= 109128.12
10

Rm
114

d culverts
15873.18
Total [a+b+c+d+e] 95239.08
9523.91
= 104762.99
10

Rm

ng reinforcement
ns and removal of

Nos 296.10
Nos 676.50
Nos 6380.00
Total [a] 7352.60

Cum 5450.22
Cum 7243.02
Cum 2611.71
115

Kg 522.72
Cum 1978.16
Tonne 41585.65
Total [b] 59391.48
116

Total [a+b] 66744.08

0 3337.20

Cum = 70081.28
15

Hour 32784.00

Hour 178.50

Hour 403.00

Hour 155.00

Kg 9317.00
Total [a] 42837.50

Nos 59.22
Nos 1435.50
Total [b] 1494.72
117

Cum 47515.16
Total [c] 47515.16
Total [a+b+c] 91847.38
118

ges
22961.85
Total [a+b+c+d] 114809.23
11480.92
= 126290.15
9

Rm

d culverts
18369.48
Total [a+b+c+d+e] 110216.86
11021.69
= 121238.55
9

Rm

oncrete pump

Nos 289.52
Nos 1353.00
Nos 5742.00
Total [a] 7384.52
119

Cum 86916.24
Cum 41787.36
Cum 15825.24
Kg 4181.76
Tonne 332420.77
Total [b] 481131.37
Total [a+b] 488515.89

Hour 13392.00
Hour 4188.00
Hour 4836.00

Hour 13950.00

Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 526417.89

0 26320.89

= 552738.78
120

cum
120

ching plant:

Hour 32784.00

Hour 178.50

Hour 403.00

Hour 155.00

Kg 9317.00
Total [a] 42837.50

Nos 59.22
Nos 1435.50
Total [b] 1494.72

Cum 46844.65
Total [c] 46844.65
Total [a+b+c] 91176.87
ges
22794.22
Total [a+b+c+d] 113971.09
11397.11
121

= 125368.20
9

Rm
122

d culverts
18235.37
Total [a+b+c+d+e] 109412.24
10941.22
= 120353.46
9

Rm

ccordance with

MT 300.00
MT 5000.00
is not required to
is required to be
rk

rete in pile cap


ications.
123

Nos 296.10
Nos 676.50
Nos 6380.00

Nos 319.00

Total [a] 7671.60


124

Tonne 33850.33
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 51916.44

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 63218.04

0 2528.72

Total [d] 2528.72


Total [a+b+c+d] 65746.76
ges
16436.69
Total [a+b+c+d+e] 82183.45
8218.35
= 90401.80
15

Cum

d culverts
13149.35
125

Total [a+b+c+d+e] 78896.11


7889.61
= 86785.72
15

Cum
126

d concrete pump

Nos 52.64
Nos 171.38
Nos 797.50

Nos 319.00

Total [a] 1340.52

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 33850.33
Total [b] 51916.44
Total [a+b] 53256.96

Hour 1674.00
Hour 523.50
Hour 604.50

Hour 1860.00

Hour 192.00
Total [b] 4854.00
127

Total [a+b+c] 58110.96

0 2324.44

Total [d] 2324.44


Total [a+b+c+d] 60435.40
128

ges
15108.85
Total [a+b+c+d+e] 75544.25
7554.43
= 83098.68
15

cum

d culverts
12087.08
Total [a+b+c+d+e] 72522.48
7252.25
= 79774.73
15

cum

rete in pile cap


ications.

Nos 296.10
129

Nos 676.50
Nos 6380.00

Nos 319.00

Total [a] 7671.60


130

Tonne 39602.24
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 57668.35

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 68969.95

0 2758.80

Total [d] 2758.80


Total [a+b+c+d] 71728.75
ges
17932.19
Total [a+b+c+d+e] 89660.94
8966.09
= 98627.03
15

Cum

d culverts
14345.75
131

Total [a+b+c+d+e] 86074.50


8607.45
= 94681.95
15

Cum
132

d concrete pump

Nos 52.64
Nos 171.38
Nos 797.50

Nos 319.00

Total [a] 1340.52

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39602.24
Total [b] 57668.35
Total [a+b] 59008.87

Hour 1674.00
Hour 523.50
Hour 604.50

Hour 1860.00

Hour 192.00
Total [b] 4854.00
133

Total [a+b+c] 63862.87

0 2554.51

Total [d] 2554.51


Total [a+b+c+d] 66417.38
134

ges
16604.35
Total [a+b+c+d+e] 83021.73
8302.17
= 91323.90
15

cum

d culverts
13283.48
Total [a+b+c+d+e] 79700.86
7970.09
= 87670.95
15

cum

rete in pile cap


ications.

Nos 296.10
135

Nos 676.50
Nos 6380.00

Nos 319.00

Total [a] 7671.60


136

Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 69697.20

0 2787.89

Total [d] 2787.89


Total [a+b+c+d] 72485.09
ges
18121.27
Total [a+b+c+d+e] 90606.36
9060.64
= 99667.00
15

Cum

d culverts
14497.02
137

Total [a+b+c+d+e] 86982.11


8698.21
= 95680.32
15

Cum
138

d concrete pump

Nos 52.64
Nos 171.38
Nos 797.50

Nos 319.00

Total [a] 1340.52

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60
Total [a+b] 59736.12

Hour 1674.00
Hour 523.50
Hour 604.50

Hour 1860.00

Hour 192.00
139

Total [b] 4854.00


Total [a+b+c] 64590.12

0 2583.60

Total [d] 2583.60


Total [a+b+c+d] 67173.72
140

ges
16793.43
Total [a+b+c+d+e] 83967.15
8396.72
= 92363.87
15

cum

d culverts
13434.74
Total [a+b+c+d+e] 80608.46
8060.85
= 88669.31
15

cum

rete in pile cap


ications.
141

Nos 296.10
Nos 676.50
Nos 6380.00

Nos 319.00

Total [a] 7671.60


142

Tonne 41850.11
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 59916.22

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 71217.82

0 2848.71

Total [d] 2848.71


Total [a+b+c+d] 74066.53
ges
18516.63
Total [a+b+c+d+e] 92583.16
9258.32
= 101841.48
15

Cum

d culverts
14813.31
143

Total [a+b+c+d+e] 88879.84


8887.98
= 97767.82
15

Cum
144

d concrete pump

Nos 52.64
Nos 171.38
Nos 797.50

Nos 319.00

Total [a] 1340.52

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22
Total [a+b] 61256.74

Hour 1674.00
Hour 523.50
Hour 604.50

Hour 1860.00

Hour 192.00
Total [b] 4854.00
145

Total [a+b+c] 66110.74

0 2644.43

Total [d] 2644.43


Total [a+b+c+d] 68755.17
146

ges
17188.79
Total [a+b+c+d+e] 85943.96
8594.40
= 94538.36
15

cum

d culverts
13751.03
Total [a+b+c+d+e] 82506.20
8250.62
= 90756.82
15

cum

concrete M

& 1700
147

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
148

Tonne 27305.05
Cum 1978.16
Cum 8175.33
Cum 5432.27
Cum 1305.86
Total [b] 44196.67

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 55166.11

ges
13791.53
Total [a+b+c+d] 68957.64
6895.76
= 75853.40
15

Cum

d culverts
11033.22
Total [a+b+c+d] 66199.33
6619.93
149

= 72819.26
15

Cum
150

reinforcement in
cal specifications.

to site, tying and

Nos 131.60
Nos 696.00
Nos 1914.00
Total [a] 2741.60

Tonne 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50071.54
ges
12517.89
Total [a+b+c+d] 62589.43
6258.94
= 68848.37
1
MT
d culverts
10014.31
151

Total [a+b+c] 60085.85


6008.59
= 66094.44
1
MT
152

reinforcement in
cal specifications.

to site, tying and

Nos 141.47
Nos 783.00
Nos 2073.50
Total [a] 2997.97

Tonne 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50327.91
ges
12581.98
Total [a+b+c+d] 62909.89
6290.99
= 69200.88
1
MT
d culverts
10065.58
153

Total [a+b+c] 60393.49


6039.35
= 66432.84
1
MT
74

CHAPTER - 13
Sl. No. Quantity Description Rate per
13.1. Brickwork in Cement mortar 1:3 in substructure complete
excluding pointing as per drawing and technical
specification

MORT & H Specification No: 1300 & 2200


Unit = Cum
Taking Output = 1 cum
a) Labour :
0.06 Nos Mate 329.00 /
0.80 Nos Mason class I 451.00 /
0.80 Nos Mazdoor 319.00 /
Total [a]
Cement mortar 1:3
Unit = Cum
Taking Output = 1 cum
i) Labour :
0.04 Nos Mate 329.00 /
0.90 Nos Mazdoor 319.00 /
Total [i]
ii) Material:
0.51 Tonne Cement 6611.39 /
1.05 Cum Sand for mortar 293.06 /
Total [ii]
Cement mortar 1:3 = 3979.78 /
b) Material:
500 Nos. Bricks Class I 5460.00 /
0.24 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
c) Form work
5% On cost of materials, labour and 4320.89
machinary
Total [c]
75

Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 4536.93
Total [a+b+c+d]
e) Contractor's profit 10% on 5671.16
Rate for 1 cum
Rate for 1 cum = 6238.28 /
Brickwork in CM 1:3 for sub structure = 6238.28 /
76

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 4536.93
Total [a+b+c+d]
e) Contractor's profit 10% on 5444.32
Rate for 1 cum
Rate for 1 cum = 5988.75 /
Brickwork in CM 1:3 for sub structure = 5988.75 /

*/-*/-/*-/*

13.2. Pointing with Cement mortar 1:3 on Brickwork in


substructure complete as per drawing and technical
specification

MORT & H Specification No: 1300 & 2200


Unit = Sqm
Taking Output = 10 Sqm
a) Labour :
0.04 Nos Mate 329.00 /
0.50 Nos Mason class I 451.00 /
0.50 Nos Mazdoor 319.00 /
Total [a]
b) Material:
0.03 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 517.55
Total [a+b+c]
d) Contractor's profit 10% on 646.94
Rate for 10 Sqm
Rate for 1 cum = 711.63 /
Pointing Brickwork in CM 1:3 for sub = 71.16 /
structure

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 517.55
77

Total [a+b+c]
e) Contractor's profit 10% on 621.06
Rate for 10 Sqm
Rate for 1 sqm = 683.17 /
Pointing Brickwork in CM 1:3 for sub = 68.32 /
structure

*/-*/-/*-/*
78

13.3. Plastering with Cement mortar 1:3 on Brickwork in


substructure complete as per drawing and technical
specification
MORT & H Specification No: 1300 & 2200
Unit = Sqm
Taking Output = 10 Sqm
a) Labour :
0.04 Nos Mate 329.00 /
0.50 Nos Mason class I 451.00 /
0.50 Nos Mazdoor 319.00 /
Total [a]
b) Material:
0.144 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 971.25
Total [a+b+c]
d) Contractor's profit 10% on 1214.06
Rate for 10 Sqm
Rate for 1 sqm = 1335.47 /
Plastering brickwork in Cement mortar 1:3 = 133.55 /
for sub structure

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 971.25
Total [a+b+c]
e) Contractor's profit 10% on 1165.50
Rate for 10 Sqm
Rate for 1 sqm = 1282.05 /
Plastering brickwork in Cement mortar 1:3 = 128.21 /
for sub structure
*/-*/-/*-/*
79

13.4. Stone masonry work in Cement mortar 1:3 for substructure


complete as per drawing and technical specification

A. Random Ruble Masonry [Coarsed / uncoarsed]:


MORT & H Specification No: 1400 & 2200
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.10 Nos Mate 329.00 /
1.20 Nos Mason class I 451.00 /
1.20 Nos Mazdoor 319.00 /
Total [a]
80

b) Material:
1.000 Cum Stone for RR masonry work 540.30 /
0.160 Cum Bond stones 681.30 /
0.330 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
c) Scaffolding
5% On cost of materials, labour and 2919.54
machinary
Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
c) Overheads 25% on 3065.52
Total [a+b+c]
d) Contractor's profit 10% on 3831.90
Rate for 1 Cum
Rate for 1 cum = 4215.09 /
Random rubble masonry in Cement = 4215.09 /
mortar 1:3 for sub structure

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 3065.52
Total [a+b+c]
e) Contractor's profit 10% on 3678.62
Rate for 1 Cum
Rate for 1 cum = 4046.48 /
Random rubble masonry in Cement = 4046.48 /
mortar 1:3 for sub structure
*/-*/-/*-/*

B. Coarsed rubble Masonry:


MORT & H Specification No: 1400 & 2200
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.12 Nos Mate 329.00 /
81

1.50 Nos Mason class I 451.00 /


1.50 Nos Mazdoor 319.00 /
Total [a]
b) Material:
1.100 Cum Coarsed rubble stone 464.30 /
0.160 Cum Bond stones 681.30 /
0.300 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]
c) Scaffolding
5% On cost of materials, labour and 3008.15
machinary
Total [c]
Total [a+b+c]
82

(i) For major bridges and minor bridges


c) Overheads 25% on 3158.56
Total [a+b+c]
d) Contractor's profit 10% on 3948.20
Rate for 1 Cum
Rate for 1 cum = 4343.02 /
Coarsed rubble masonry in CM 1:3 for sub = 4343.02 /
structure

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 3158.56
Total [a+b+c]
e) Contractor's profit 10% on 3790.27
Rate for 1 Cum
Rate for 1 cum = 4169.30 /
Coarsed rubble masonry in CM 1:3 for sub = 4169.30 /
structure
*/-*/-/*-/*
13.5. Plain cement concrete in sub structure complete as per
drawing and technical specification

a. PCC M 15 :
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
4.13 Tonne Cement 6611.39 /
Total [b]
83

Total [a+b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
PCC M 15 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
84

d) Form work
On cost of materials, labour and
10% machinary 55166.11 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 60682.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 75853.40
Rate for 15 cum
Rate for 1 cum = 83438.74 /
PCC M 15 for substructure upto 5 m = 5562.58 /
height
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 60682.72
Total [a+b+c+d+e]
f) Contractor's profit 10% on 72819.26
Rate for 15 cum
Rate for 1 cum = 80101.19 /
PCC M 15 for substructure upto 5 m = 5340.08 /
height
PCC M 15 - from 5m to 10m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
Add for extra lift on cost of
2% materials, labour and machinary
55166.11 /

For form work on cost of


12% materials, labour and machinary
55166.11 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 61786.04
85

Total [a+b+c+d+e]
f) Contractor's profit 10% on 77232.55
Rate for 15 cum
Rate for 1 cum = 84955.81 /

Rate for PCC M 15 for substructure for 5 = 5663.72 /


m to 10 m height
86

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 61786.04
Total [a+b+c+d+e]
f) Contractor's profit 10% on 74143.25
Rate for 15 cum
Rate for 1 cum = 81557.58 /
Rate for PCC M 15 for substructure for 5 = 5437.17 /
m to 10 m height

13.5. b. PCC M 20 for substructure using Concrete mixer:


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.16 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
PCC M 20 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
87

On cost of materials, labour and


10% machinary
62367.33 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 68604.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 85755.08
Rate for 15 cum
Rate for 1 cum = 94330.59 /
PCC M 20 for substructure with concrete = 6288.71 /
mixer upto 5 m height
88

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 68604.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 82324.87
Rate for 15 cum
Rate for 1 cum = 90557.36 /
PCC M 20 for substructure with concrete = 6037.16 /
mixer upto 5 m height

PCC M 20 - from 5m to 10m height:

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
Add for extra lift on cost of
2% materials, labour and machinary
62367.33 /

On cost of materials, labour and


12% machinary 62367.33 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 71098.76
Total [a+b+c+d+e]
f) Contractor's profit 10% on 88873.45
Rate for 15 Cum
Rate for 1 cum = 97760.80 /

PCC M 20 for substructure with concrete = 6517.39 /


mixer from 5 -10m height
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 71098.76
Total [a+b+c+d+e]
f) Contractor's profit 10% on 85318.51
Rate for 15 Cum
Rate for 1 cum = 93850.36 /
89

PCC M 20 for substructure with concrete = 6256.69 /


mixer from 5 -10m height
90

13.5. c. PCC M 25 using concrete mixer for sub structure:


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.99 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
PCC M 25 - upto 5m height:

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 67854.79 /
Total [d]
Total [a+b+c+d]
91

(i) For major bridges and minor bridges


e) Overheads 25% on 74640.27
Total [a+b+c+d+e]
f) Contractor's profit 10% on 93300.34
Rate for 15 cum
Rate for 1 cum = 102630.37 /
PCC M 25 for sub structure using concrete
mixer upto 5 m height
= 6842.02 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 74640.27
Total [a+b+c+d+e]
f) Contractor's profit 10% on 89568.32
Rate for 15 cum
Rate for 1 cum = 98525.15 /
PCC M 25 for sub structure using concrete
mixer upto 5 m height
= 6568.34 /
-*/-*/-
PCC M 20 - from 5m to 10 m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift 67854.79 /
On cost of materials, labour and
12% machinary for form work 67854.79 /

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 77354.46
Total [a+b+c+d+e]
f) Contractor's profit 10% on 96693.08
Rate for 15 cum
Rate for 1 cum = 106362.39 /
PCC M 25 for sub structure using concrete
mixer from 5 m to 10 m height
= 7090.83 /
92

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 77354.46
Total [a+b+c+d+e]
f) Contractor's profit 10% on 92825.35
Rate for 15 cum
Rate for 1 cum = 102107.89 /
PCC M 25 for sub structure using concrete
mixer from 5 m to 10 m height
= 6807.19 /
-*/-*/-
93

PCC M 25 using Batching Plant, transit mixer and concrete p


13.5.c. substructure:
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
43.20 Cum 40 mm ISS metal 1009.30 /
43.20 Cum 20 mm ISS metal 1341.30 /
21.60 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
47.95 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
PCC M 25 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 500554.43
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 550609.87
94

Total [a+b+c+d+e]
f) Contractor's profit 10% on 688262.34
Rate for 120 cum
Rate for 1 cum = 757088.57 /
PCC M 25 for substructure with batching plant
for height upto 5 m
= 6309.07 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 550609.87
Total [a+b+c+d+e]
f) Contractor's profit 10% on 660731.84
Rate for 120 cum
Rate for 1 cum = 726805.02 /
PCC M 25 for substructure with batching plant
for height upto 5 m
= 6056.71 /
*/-*/-*/-*/
95

PCC M 25 - from 5m to 10m height:


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift 500554.43 /

On cost of materials, labour and


12% machinary forform work 500554.43
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 570632.05
Total [a+b+c+d+e]
f) Contractor's profit 10% on 713290.06
Rate for 120 cum
Rate for 1 cum = 784619.07 /
PCC M 25 for substructure with batching plant
for height from 5 m to 10 m
= 6538.49 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 570632.05
Total [a+b+c+d+e]
f) Contractor's profit 10% on 684758.46
Rate for 120 cum
Rate for 1 cum = 753234.31 /
PCC M 25 for substructure with batching plant
for height from 5 m to 10 m
= 6276.95 /
*/-*/-*/-*/
13.5.d. PCC M 30 using concrete mixer for substructure:
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
96

20.00 Nos Mazdoor 319.00 /


Total [a]
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.08 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
97

PCC M 30 - upto 5m height:


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
68449.81 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 75294.79
Total [a+b+c+d+e]
f) Contractor's profit 10% on 94118.49
Rate for 15 cum
Rate for 1 cum = 103530.34 /
PCC M 30 for substructure using concrete mixer
for height upto 5 m
= 6902.02 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 75294.79
Total [a+b+c+d+e]
f) Contractor's profit 10% on 90353.75
Rate for 15 cum
Rate for 1 cum = 99389.13 /
PCC M 30 for substructure using concrete mixer
for height upto 5 m
= 6625.94 /

PCC M 30 - from 5m to 10m height:


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift
68449.81 /

On cost of materials, labour and


12% machinary for form work
68449.81
Total [d]
98

Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 78032.79
Total [a+b+c+d+e]
f) Contractor's profit 10% on 97540.99
Rate for 15 cum
Rate for 1 cum = 107295.09 /
PCC M 30 for substructure using concrete mixer
for height from 5 m to 10 m
= 7153.01 /
99

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 78032.79
Total [a+b+c+d+e]
f) Contractor's profit 10% on 93639.35
Rate for 15 cum
Rate for 1 cum = 103003.29 /
PCC M 30 for substructure using concrete mixer
for height from 5 m to 10 m
= 6866.89 /
*/-*/-*/-*/
PCC M 30 using batching plant, transit mixer and concrete p
13.5.d. substructure:

MORT & H Specification No: 1500, 1700 & 2200


Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
43.20 Cum 40 mm ISS metal 1009.30 /
43.20 Cum 20 mm ISS metal 1341.30 /
21.60 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.60 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
PCC M 30 - upto 5m height:
a) Labour charges
b) Cost of materials
100

c) Hire charges for machinary


Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
504851.83
Total [d]
Total [a+b+c+d]
101

(i) For major bridges and minor bridges


e) Overheads 25% on 555337.01
Total [a+b+c+d+e]
f) Contractor's profit 10% on 694171.26
Rate for 120 cum
Rate for 1 cum = 763588.39 /
PCC M 30 for substructure with batching plant
for height upto 5 m
= 6363.24 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 555337.01
Total [a+b+c+d+e]
f) Contractor's profit 10% on 666404.41
Rate for 120 cum
Rate for 1 cum = 733044.85 /
PCC M 30 for substructure with batching plant
for height upto 5 m
= 6108.71 /

PCC M 30 - from 5m to 10m height:


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift
504851.83 /

On cost of materials, labour and


12% machinary for form work
504851.83

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 575531.09
Total [a+b+c+d+e]
f) Contractor's profit 10% on 719413.86
Rate for 120 Cum
Rate for 1 cum = 791355.25 /
PCC M 30 for substructure with batching plant
for height from 5 m to 10 m
= 6594.63 /
102

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 575531.09
Total [a+b+c+d+e]
f) Contractor's profit 10% on 690637.31
Rate for 120 Cum
Rate for 1 cum = 759701.04 /
PCC M 30 for substructure with batching plant
for height from 5 m to 10 m
= 6330.84 /
*/-*/-*/-*/
103

13.5.e. Reinforced Cement concrete for substructure with crushed


stone aggregates 20 mm nominal size mechanically mixed,
placed in substructure and compacted by vibrator including
curing for 14 days
Case : I Using Concrete Mixer
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.12 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
RCC M 20 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 62885.88 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 69174.47
Total [a+b+c+d+e]
104

f) Contractor's profit 10% on 86468.09


Rate for 15 Cum
Rate for 1 cum = 95114.90 /
RCC M 20 for Sub structure using concrete
mixer for height upto 5 m
= 6340.99 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 69174.47
Total [a+b+c+d+e]
f) Contractor's profit 10% on 83009.36
Rate for 15 Cum
Rate for 1 cum = 91310.30 /
RCC M 20 for Sub structure using concrete
mixer for height upto 5 m
= 6087.35 /
105

RCC M 20 - From 5m to 10m height:

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift
62885.88 /
On cost of materials, labour and
12% machinary for form work 62885.88 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 71689.91
Total [a+b+c+d+e]
f) Contractor's profit 10% on 89612.39
Rate for 15 Cum
Rate for 1 cum = 98573.63 /
RCC M 20 for substructure using concrete mixer
for height from 5 m to 10 m
= 6571.58 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 71689.91
Total [a+b+c+d+e]
f) Contractor's profit 10% on 86027.89
Rate for 15 Cum
Rate for 1 cum = 94630.68 /
RCC M 20 for substructure using concrete mixer
for height from 5 m to 10 m
= 6308.71 /
-*/-*/-
Case : II Using Batching Plant, transit mixer and concrete pump
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
106

18.00 Nos Mazdoor 319.00 /


Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
41.66 Tonne Cement 6611.39 /
Total [b]
Total [a+b]
107

C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
Total [a+b+c]
RCC M 20 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary 465232.78 /
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 511756.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 639695.08
Rate for 120 cum
Rate for 1 cum = 703664.59 /
RCC M 20 for substructure with batching = 5863.87 /
plant for height upto 5 m
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 511756.06
Total [a+b+c+d+e]
f) Contractor's profit 10% on 614107.27
Rate for 120 cum
Rate for 1 cum = 675518.00 /
RCC M 20 for substructure with batching = 5629.32 /
plant for height upto 5 m
-*/-/*-/*-/*-/*-
108

RCC M 20 - from 5m to 10m height:


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
2% machinary for extra lift
465232.78 /
On cost of materials, labour and
12% machinary for form work
465232.78 /
Total [d]
Total [a+b+c+d]
109

(i) For major bridges and minor bridges


e) Overheads 25% on 530365.37
Total [a+b+c+d+e]
f) Contractor's profit 10% on 662956.71
Rate for 120 cum
Rate for 1 cum = 729252.38 /

RCC M 20 for substructure with batching =


6077.10 /
plant for height from 5 to 10m
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 530365.37
Total [a+b+c+d+e]
f) Contractor's profit 10% on 636438.44
Rate for 120 cum
Rate for 1 cum = 700082.28 /
RCC M 20 for substructure with batching =
5834.02 /
plant for height from 5 to 10m
-*/-/*-/*-/*-/*-

13.5.f. RCC M 25 using concrete mixer


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.05 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
110

Total [c]

RCC M 25 - upto 5m height using concrete mixe


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
69034.47 /
Total [d]
Total [a+b+c+d]
111

(i) For major bridges and minor bridges


e) Overheads 25% on 75937.92
Total [a+b+c+d+e]
f) Contractor's profit 10% on 94922.40
Rate for 15 cum
Rate for 1 cum = 104414.64 /
RCC M 25 for substructure using concrete mixer
for height upto 5 m
= 6960.98 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 75937.92
Total [a+b+c+d+e]
f) Contractor's profit 10% on 91125.50
Rate for 15 cum
Rate for 1 cum = 100238.05 /
RCC M 25 for substructure using concrete mixer
for height upto 5 m
= 6682.54 /

RCC M 25 - from 5 to 10 m height using concrete m


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
1.8% machinary for extra lift
69034.47
On cost of materials, labour and
11.8% machinary for form work
69034.47
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 78423.16
Total [a+b+c+d+e]
f) Contractor's profit 10% on 98028.95
Rate for 15 cum
Rate for 1 cum = 107831.85 /
RCC M 25 for substructure using concrete mixer
for height from 5 - 10 m
= 7188.79 /
112

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 78423.16
Total [a+b+c+d+e]
f) Contractor's profit 10% on 94107.79
Rate for 15 cum
Rate for 1 cum = 103518.57 /
RCC M 25 for substructure using concrete mixer
for height from 5 - 10 m
= 6901.24 /
-*/-*/-
113

13.5.f. RCC M25 Using Batching Plant, transit mixer and concrete p
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.38 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [c]
RCC M 25 - upto 5 m height using batching plan

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
509661.33
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 560627.46
Total [a+b+c+d+e]
114

f) Contractor's profit 10% on 700784.33


Rate for 120 cum
Rate for 1 cum = 770862.76 /
RCC M 25 for substructure concrete with =
6423.86 /
batching plant for height upto 5 m

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 560627.46
Total [a+b+c+d+e]
f) Contractor's profit 10% on 672752.95
Rate for 120 cum
Rate for 1 cum = 740028.25 /
RCC M 25 for substructure concrete with =
6166.90 /
batching plant for height upto 5 m
*/-*/-/*-/*
115

RCC M 25 - from 5 m to 10 m height using batching


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
1.8% machinary for extra lift 509661.33
On cost of materials, labour and
11.8% machinary for form work 509661.33
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 578975.27
Total [a+b+c+d+e]
f) Contractor's profit 10% on 723719.09
Rate for 120 cum
Rate for 1 cum = 796091.00 /
RCC M 25 for substructure with batching = 6634.09 /
plant for height from 5 - 10 m

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 578975.27
Total [a+b+c+d+e]
f) Contractor's profit 10% on 694770.32
Rate for 120 cum
Rate for 1 cum = 764247.35 /
RCC M 25 for substructure with batching = 6368.73 /
plant for height from 5 - 10 m
*/-*/-/*-/*
13.5.g. RCC M 30 Using Concrete Mixer:
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
116

0.86 Nos Mate 329.00 /


1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]
117

RCC M 30 - upto 5 m height using concrete mixe


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]

d) Form work
On cost of materials, labour and
10% machinary
69365.04

Total [d]
Total [a+b+c+d]

(i) For major bridges and minor bridges


e) Overheads 25% on 76301.54
Total [a+b+c+d+e]
f) Contractor's profit 10% on 95376.93
Rate for 15 cum
Rate for 1 cum = 104914.62 /
RCC M 30 for substructure using concrete mixer
for height upto 5 m
= 6994.31 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 76301.54
Total [a+b+c+d+e]
f) Contractor's profit 10% on 91561.85
Rate for 15 cum
Rate for 1 cum = 100718.04 /
RCC M 30 for substructure using concrete mixer
for height upto 5 m
= 6714.54 /

RCC M 30 - from 5 m to 10 m height using concrete


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
118

On cost of materials, labour and


1.6% machinary for extra lift
69365.04
On cost of materials, labour and
11.5% machinary for form work
69365.04
Total [d]
Total [a+b+c+d]

(i) For major bridges and minor bridges


e) Overheads 25% on 78451.86
Total [a+b+c+d+e]
f) Contractor's profit 10% on 98064.83
Rate for 15 cum
Rate for 1 cum = 107871.31 /
RCC M 30 for substructure using concrete mixer
for height from 5-10 m
= 7191.42 /
119

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 78451.86
Total [a+b+c+d+e]
f) Contractor's profit 10% on 94142.23
Rate for 15 cum
Rate for 1 cum = 103556.45 /
RCC M 30 for substructure using concrete mixer
for height from 5-10 m
= 6903.76 /
-*/-*/-

13.5.g. RCC M 30 Using Batching Plant, transit mixer and concr


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
48.80 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
RCC M 30 - for substructure upto 5 m height using batch
a) Labour charges
b) Cost of materials
120

c) Hire charges for machinary


Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
512438.11
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 563681.92
Total [a+b+c+d+e]
f) Contractor's profit 10% on 704602.40
Rate for 120 cum
Rate for 1 cum = 775062.64 /
RCC M 30 for Sub structure with batching plant
for height upto 5 m
= 6458.86 /
121

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 563681.92
Total [a+b+c+d+e]
f) Contractor's profit 10% on 676418.30
Rate for 120 cum
Rate for 1 cum = 744060.13 /
RCC M 30 for Sub structure with batching plant
for height upto 5 m
= 6200.50 /

RCC M 30 - for substructure from 5 - 10 m height using batching


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]

d) Form work
On cost of materials, labour and
1.6% machinary for extra lift
512438.11
On cost of materials, labour and
11.5% machinary for form work 512438.11
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 579567.50
Total [a+b+c+d+e]
f) Contractor's profit 10% on 724459.38
Rate for 120 cum
Rate for 1 cum = 796905.32 /
RCC M 30 for Sub structure with batching plant
for height from 5 -10 m
= 6640.88 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 579567.50
Total [a+b+c+d+e]
f) Contractor's profit 10% on 695481.00
Rate for 120 cum
Rate for 1 cum = 765029.10 /
122

RCC M 30 for Sub structure with batching plant


for height from 5 -10 m
= 6375.24 /
*/-*/-/*-/*
RCC M 35 Using concrete mixer
13.5.g.
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total [a]
123

b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.33 Tonne Cement 6611.39 /
Total [b]
C) Machinary
6.00 Hour Concrete mixer 040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b]

RCC M 35 - upto 5 m height using concrete mixe


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
10% machinary
70885.66 /
Total [d]
Total [a+b+c+d]

(i) For major bridges and minor bridges


e) Overheads 25% on 77974.23
Total [a+b+c+d+e]
f) Contractor's profit 10% on 97467.79
Rate for 15 cum
Rate for 1 cum = 107214.57 /
RCC M 35 for substructure using concrete mixer
for height upto 5 m
= 7147.64 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 77974.23
Total [a+b+c+d+e]
f) Contractor's profit 10% on 93569.08
Rate for 15 cum
Rate for 1 cum = 102925.99 /
124

RCC M 35 for substructure using concrete mixer


for height upto 5 m
= 6861.73 /

RCC M 35 - for substructure from 5-10 m height


using concrete mixer:

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
1.4% machinary for extra lift 70885.66
On cost of materials, labour and
11.0% machinary for form work
70885.66
Total [d]
Total [a+b+c+d]
125

(i) For major bridges and minor bridges


e) Overheads 25% on 79675.48
Total [a+b+c+d+e]
f) Contractor's profit 10% on 99594.35
Rate for 15 cum
Rate for 1 cum = 109553.79 /
RCC M 35 for substructure using concrete mixer
for height 5 m to 10 m
= 7303.59 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 79675.48
Total [a+b+c+d+e]
f) Contractor's profit 10% on 95610.58
Rate for 15 cum
Rate for 1 cum = 105171.64 /
RCC M 35 for substructure using concrete mixer
for height 5 m to 10 m
= 7011.44 /
-*/-*/-

RCC M 35 for substruture Using Batching Plant


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total [a]

b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
50.64 Tonne Cement 6611.39 /
Total [b]
C) Machinary
126

6.00 Hour Batching Plant 20 Cum / hour 2232.00 /


6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total [b]
RCC M 35 - for substructure upto 5 m height using batch

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
127

d) Form work
On cost of materials, labour and
10% machinary
524603.07
Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 577063.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 721329.23
Rate for 120 cum
Rate for 1 cum = 793462.15 /
RCC M 35 for substructure with batching plant
for height upto 5 m
= 6612.18 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 577063.38
Total [a+b+c+d+e]
f) Contractor's profit 10% on 692476.06
Rate for 120 cum
Rate for 1 cum = 761723.67 /
RCC M 35 for substructure with batching plant
for height upto 5 m
= 6347.70 /
-*/-*/-

RCC M 35 - for substructure from 5 -10 m heigh


using batching plant:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c]
d) Form work
On cost of materials, labour and
1.4% machinary for extra lift
524603.07
On cost of materials, labour and
11.0% machinary for form work
524603.07

Total [d]
Total [a+b+c+d]
128

(i) For major bridges and minor bridges


e) Overheads 25% on 589653.85
Total [a+b+c+d+e]
f) Contractor's profit 10% on 737067.31
Rate for 120 cum
Rate for 1 cum = 810774.04 /
RCC M 35 for substructure with batching plant
for height 5 - 10 m
= 6756.45 /
129

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 589653.85
Total [a+b+c+d+e]
f) Contractor's profit 10% on 707584.62
Rate for 120 cum
Rate for 1 cum = 778343.08 /
RCC M 35 for substructure with batching plant
for height 5 - 10 m
= 6486.19 /
-*/-*/-
Supplying, fitting and placing HYSD bar reinforcement in
13.6. complete as per drawing and techincal specificaion
MORT & H Specification No: 1600 & 2200
Unit = MT
Taking Output = 1 MT
Labour for cutting, bending, shifting to site, tying
a) position

0.34 Nos Mate 329.00 /


2.00 Nos Blacksmith 348.00 /
6.50 Nos Mazdoor 319.00 /
Total [a]

b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages 44815.56 /
6.00 Kg Binding wires 45.60 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 50211.30
Total [a+b+c]
d) Contractor's profit 10% on 62764.13
Rate for 1 MT
Rate for 1 cum = 69040.54 /
HYSD reinforcement for substructure = 69040.54 /
(ii) For minor bridges in road packages and culverts
130

e) Overheads 20% on 50211.30


Total [a+b+c+d+e]
f) Contractor's profit 10% on 60253.56
Rate for 1 MT
Rate for 1 cum = 66278.92 /

HYSD reinforcement for substructure = 66278.92 /


-*/-*/-
131

Supplying, fitting and placing Mild steel reinforcement in


13.7. complete as per drawing and techincal specificaion
MORT & H Specification No: 1600 & 2200
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tying
0.28 Nos position
Mate 329.00 /
1.50 Nos Blacksmith 348.00 /
5.50 Nos Mazdoor 319.00 /
Total [a]
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
6.00 Kg Binding wires 45.60 /
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
c) Overheads 25% on 49698.56
Total [a+b+c]
d) Contractor's profit 10% on 62123.20
Rate for 1 MT
Rate for 1 cum = 68335.52 /

Mild steel reinforcement for substructure = 68335.52 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 49698.56
Total [a+b+c+d+e]
f) Contractor's profit 10% on 59638.27
Rate for 1 MT
Rate for 1 cum = 65602.10 /

Mild steel reinforcement for substructure = 65602.10 /


-*/-*/-
132

13.8. Providing weep holes in brick masonry /plain / reinforc


abutment, wing walls / return wall with 100 mm dia AC pip
through the full width of the structure with slope of aV:
drawing face, complete as per drawing and techinical specifi

MORT & H Specification No: 2706 & 2200


Unit = Nos.
Taking Output = 30 Nos.
Labour for cutting, bending, shifting to site, tying
a) position
0.03 Nos Mate 329.00 /
0.50 Nos Mason 451.00 /
0.25 Nos Mazdoor 319.00 /
Total [a]
b) Material:
AC pipe 100 mm dia [including
31.50 RM wastage at 5%] 50.00 /
30.00 Nos. MS clamp 15.00 /
10.00 Nos. Collar for AC pipes [ Average] 25.00 /
0.05 Cum Cement mortar 1:3 3979.78 /
Total [b]
Total [a+b]

(i) For major bridges and minor bridges


c) Overheads 25% on 2789.11
Total [a+b+c]
d) Contractor's profit 10% on 3486.39
Rate for 30 Nos.
Rate for 1 cum = 3835.03 /
Weep holes = 127.83 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 2789.11
Total [a+b+c+d+e]
f) Contractor's profit 10% on 3346.93
Rate for 30 Nos.
133

Rate for 1 cum = 3681.62 /


Weep holes = 122.72 /
-*/-*/-
134

### Back filling behind abutment, wing walls / return wall complete as per
techinical specifications.

MORT & H Specification No: 710.1.4 of IRC :78 & 2200


Unit = Cum
Taking Output = 10 Cum
a) Labour
0.28 Nos Mate 329.00 /
7.00 Nos Mazdoor 319.00 /
Total [a]
b) Material:
12.00 Cum Granular material 246.95 /
Total [b]
C) Machinary

2.50 Hour Plate compactor /power rammer 155.00 /

0.05 Hour Water tanker 310.00 /


Total [c]
Total [a+b+c]
(i) For major bridges and minor bridges
d) Overheads 25% on 5691.52
Total [a+b+c+d]
e) Contractor's profit 10% on 7114.40
Rate for 10 Cum
Rate for 1 cum = 7825.84 /
Back filling behind abutment, wing walls / return
wall
= 782.58 /

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 5691.52
Total [a+b+c+d]
e) Contractor's profit 10% on 6829.82
Rate for 10 Cum
Rate for 1 cum = 7512.80 /
Back filling behind abutment, wing walls / return
wall
= 751.28 /
135

-*/-*/-
13.10. Providing and laying of filter media with granular materi
crushed aggregates satisfying the requirements laid dow
2504.2.2 of MORT & H specifications to a thickness of not l
mm with smaller size towards the wall and provided ov
surface behind abutment, wing walls and return walls to th
compacted to a firm condition complete as per drawing a
specifications.

MORT & H Specification No: 710.1.4 of IRC :78 & 2200


Unit = Cum
Taking Output = 10 Cum
a) Labour
0.32 Nos Mate 329.00 /
7.00 Nos Mazdoor 286.00 /
1.00 Nos Mazdoor 319.00 /
Total [a]
136

b) Material:
Sand for filling 296.11
Gravel 246.95
Sand for mortar 293.06
836.12 /
Granular material = 278.71
Filter media conforming to
12.00 Cum clause 2504.2.2. of MORT &H 278.71 /
specification
Total [b]
C) Machinary
0.06 Hour Water tanker 310.00 /
Total [c]
Total [a+b+c]

(i) For major bridges and minor bridges


d) Overheads 25% on 5789.40
Total [a+b+c+d]
e) Contractor's profit 10% on 7236.75
Rate for 10 Cum
Rate for 1 cum = 7960.43 /
Filter media behind abutment, wing walls and
return wall
= 796.04 /

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 5789.40
Total [a+b+c+d]
e) Contractor's profit 10% on 6947.28
Rate for 10 Cum
Rate for 1 cum = 7642.01 /
Filter media behind abutment, wing walls and
return wall
= 764.20 /
-*/-*/-
137

Rate per Amount


bstructure complete
ng and technical

Nos 19.74
Nos 360.80
Nos 255.20
Total [a] 635.74

Nos 13.16
Nos 287.10
Total [i] 300.26

Tonne 3371.81
Cum 307.71
Total [ii] 3679.52
cum

1000 2730.00
Cum 955.15
Total [b] 3685.15
Total [a+b] 4320.89

0 216.04

Total [c] 216.04


138

Total [a+b+c] 4536.93


bridges
1134.23
Total [a+b+c+d] 5671.16
567.12
= 6238.28
1
cum
139

es and culverts
907.39
Total [a+b+c+d] 5444.32
544.43
= 5988.75
1
cum

on Brickwork in
ing and technical

Nos 13.16
Nos 225.50
Nos 159.50
Total [a] 398.16

Cum 119.39
Total [b] 119.39
Total [a+b] 517.55
bridges
129.39
Total [a+b+c] 646.94
64.69
= 711.63
10
Sqm

es and culverts
103.51
140

Total [a+b+c] 621.06


62.11
= 683.17
10
Sqm
141

on Brickwork in
ing and technical

Nos 13.16
Nos 225.50
Nos 159.50
Total [a] 398.16

Cum 573.09
Total [b] 573.09
Total [a+b] 971.25
bridges
242.81
Total [a+b+c] 1214.06
121.41
= 1335.47
10
Sqm

es and culverts
194.25
Total [a+b+c] 1165.50
116.55
= 1282.05
10
Sqm
142

1:3 for substructure


pecification

oarsed]:

Nos 32.90
Nos 541.20
Nos 382.80
Total [a] 956.90
143

Cum 540.30
Cum 109.01
Cum 1313.33
Total [b] 1962.64
Total [a+b] 2919.54

0 145.98

Total [c] 145.98


Total [a+b+c] 3065.52
bridges
766.38
Total [a+b+c] 3831.90
383.19
= 4215.09
1
Cum

es and culverts
613.10
Total [a+b+c] 3678.62
367.86
= 4046.48
1
Cum

Nos 39.48
144

Nos 676.50
Nos 478.50
Total [a] 1194.48

Cum 510.73
Cum 109.01
Cum 1193.93
Total [b] 1813.67
Total [a+b] 3008.15

0 150.41
Total [c] 150.41
Total [a+b+c] 3158.56
145

bridges
789.64
Total [a+b+c] 3948.20
394.82
= 4343.02
1
Cum

es and culverts
631.71
Total [a+b+c] 3790.27
379.03
= 4169.30
1
Cum

e complete as per

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67
146

Total [a+b] 51536.11

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
44196.67
3630.00
Total [a+b+c] 55166.11
147

0 5516.61
Total [d] 5516.61
Total [a+b+c+d] 60682.72
bridges
15170.68
Total [a+b+c+d+e] 75853.40
7585.34
= 83438.74
15

cum

es and culverts
12136.54
Total [a+b+c+d+e] 72819.26
7281.93
= 80101.19
15

cum

to 10m height:
7339.44
44196.67
3630.00
Total [a+b+c] 55166.11

0 1103.32

0 6619.93

Total [d] 6619.93


Total [a+b+c+d] 61786.04
bridges
15446.51
148

Total [a+b+c+d+e] 77232.55


7723.26
= 84955.81
15

cum
149

es and culverts
12357.21
Total [a+b+c+d+e] 74143.25
7414.33
= 81557.58
15

cum

g Concrete mixer:

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34114.78
Total [b] 51397.89

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
51397.89
3630.00
Total [a+b+c] 62367.33
150

0 6236.73
Total [d] 6236.73
Total [a+b+c+d] 68604.06
bridges
17151.02
Total [a+b+c+d+e] 85755.08
8575.51
= 94330.59
15

cum
151

es and culverts
13720.81
Total [a+b+c+d+e] 82324.87
8232.49
= 90557.36
15

cum

to 10m height:

7339.44
51397.89
3630.00
Total [a+b+c] 62367.33

0 1247.35

0 7484.08
Total [d] 8731.43
Total [a+b+c+d] 71098.76
bridges
17774.69
Total [a+b+c+d+e] 88873.45
8887.35
= 97760.80
15

Cum

es and culverts
14219.75
Total [a+b+c+d+e] 85318.51
8531.85
= 93850.36
15
152

Cum
153

structure:

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 39602.24
Total [b] 56885.35

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:

7339.44
56885.35
3630.00
Total [a+b+c] 67854.79

0 6785.48
Total [d] 6785.48
Total [a+b+c+d] 74640.27
154

bridges
18660.07
Total [a+b+c+d+e] 93300.34
9330.03
= 102630.37
15

cum

es and culverts
14928.05
Total [a+b+c+d+e] 89568.32
8956.83
= 98525.15
15

cum

to 10 m height:
7339.44
56885.35
3630.00
Total [a+b+c] 67854.79

0 1357.10

0 8142.57

Total [d] 9499.67


Total [a+b+c+d] 77354.46
bridges
19338.62
Total [a+b+c+d+e] 96693.08
9669.31
= 106362.39
15

cum
155

es and culverts
15470.89
Total [a+b+c+d+e] 92825.35
9282.54
= 102107.89
15

cum
156

mixer and concrete pump for

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 317016.23
Total [b] 455281.07

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
5m height:
7371.36
455281.07
37902.00
Total [a+b+c] 500554.43

0 50055.44
Total [d] 50055.44
Total [a+b+c+d] 550609.87
bridges
137652.47
157

Total [a+b+c+d+e] 688262.34


68826.23
= 757088.57
120

cum

es and culverts
110121.97
Total [a+b+c+d+e] 660731.84
66073.18
= 726805.02
120

cum
158

to 10m height:
7371.36
455281.07
37902.00
Total [a+b+c] 500554.43

0 10011.09

0 60066.53
Total [d] 70077.62
Total [a+b+c+d] 570632.05
bridges
142658.01
Total [a+b+c+d+e] 713290.06
71329.01
= 784619.07
120

cum

es and culverts
114126.41
Total [a+b+c+d+e] 684758.46
68475.85
= 753234.31
120

cum

tructure:

Nos 282.94
Nos 676.50
159

Nos 6380.00
Total [a] 7339.44

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 40197.26
Total [b] 57480.37

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
160

5m height:
7339.44
57480.37
3630.00
Total [a+b+c] 68449.81

0 6844.98
Total [d] 6844.98
Total [a+b+c+d] 75294.79
bridges
18823.70
Total [a+b+c+d+e] 94118.49
9411.85
= 103530.34
15

cum

es and culverts
15058.96
Total [a+b+c+d+e] 90353.75
9035.38
= 99389.13
15

cum

to 10m height:
7339.44
57480.37
3630.00
Total [a+b+c] 68449.81

0 1369.00

0 8213.98
Total [d] 9582.98
161

Total [a+b+c+d] 78032.79


bridges
19508.20
Total [a+b+c+d+e] 97540.99
9754.10
= 107295.09
15

cum
162

es and culverts
15606.56
Total [a+b+c+d+e] 93639.35
9363.94
= 103003.29
15

cum

mixer and concrete pump for

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 43601.76
Cum 57944.16
Cum 20893.68
Cum 15825.24
Tonne 321313.63
Total [b] 459578.47

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
5m height:
7371.36
459578.47
163

37902.00
Total [a+b+c] 504851.83

0 50485.18
Total [d] 50485.18
Total [a+b+c+d] 555337.01
164

bridges
138834.25
Total [a+b+c+d+e] 694171.26
69417.13
= 763588.39
120

cum

es and culverts
111067.40
Total [a+b+c+d+e] 666404.41
66640.44
= 733044.85
120

cum

o 10m height:
7371.36
459578.47
37902.00
Total [a+b+c] 504851.83

0 10097.04

0 60582.22

Total [d] 70679.26


Total [a+b+c+d] 575531.09
bridges
143882.77
Total [a+b+c+d+e] 719413.86
71941.39
= 791355.25
120

Cum
165

es and culverts
115106.22
Total [a+b+c+d+e] 690637.31
69063.73
= 759701.04
120

Cum
166

ucture with crushed


mechanically mixed,
by vibrator including

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 33850.33
Total [b] 51916.44

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
7339.44
51916.44
3630.00
Total [a+b+c] 62885.88

0 6288.59
Total [d] 6288.59
Total [a+b+c+d] 69174.47
bridges
17293.62
Total [a+b+c+d+e] 86468.09
167

8646.81
= 95114.90
15
Cum
es and culverts
13834.89
Total [a+b+c+d+e] 83009.36
8300.94
= 91310.30
15

Cum
168

to 10m height:

7339.44
51916.44
3630.00
Total [a+b+c] 62885.88

0 1257.72

0 7546.31
Total [d] 8804.03
Total [a+b+c+d] 71689.91
bridges
17922.48
Total [a+b+c+d+e] 89612.39
8961.24
= 98573.63
15

Cum

es and culverts
14337.98
Total [a+b+c+d+e] 86027.89
8602.79
= 94630.68
15

Cum

and concrete pump

Nos 276.36
Nos 1353.00
169

Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 275430.58
Total [b] 419959.42
Total [a+b] 427330.78
170

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
Total [a+b+c] 465232.78
5m height:
7371.36
419959.42
37902.00
Total [a+b+c] 465232.78

0 46523.28
Total [d] 46523.28
Total [a+b+c+d] 511756.06
bridges
127939.02
Total [a+b+c+d+e] 639695.08
63969.51
= 703664.59
120

cum

es and culverts
102351.21
Total [a+b+c+d+e] 614107.27
61410.73
= 675518.00
120

cum
171

to 10m height:
7371.36
419959.42
37902.00
Total [a+b+c] 465232.78

0 9304.66

0 55827.93
Total [d] 65132.59
Total [a+b+c+d] 530365.37
172

bridges
132591.34
Total [a+b+c+d+e] 662956.71
66295.67
= 729252.38
120

cum

es and culverts
106073.07
Total [a+b+c+d+e] 636438.44
63643.84
= 700082.28
120

cum

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 39998.92
Total [b] 58065.03

Hour 1398.00
Hour 2232.00
173

Total [c] 3630.00

using concrete mixer:


7339.44
58065.03
3630.00
Total [a+b+c] 69034.47

0 6903.45
Total [d] 6903.45
Total [a+b+c+d] 75937.92
174

bridges
18984.48
Total [a+b+c+d+e] 94922.40
9492.24
= 104414.64
15

cum

es and culverts
15187.58
Total [a+b+c+d+e] 91125.50
9112.55
= 100238.05
15

cum

ght using concrete mixer:


7339.44
58065.03
3630.00
Total [a+b+c] 69034.47

1242.62

0 8146.07
Total [d] 9388.69
Total [a+b+c+d] 78423.16
bridges
19605.79
Total [a+b+c+d+e] 98028.95
9802.90
= 107831.85
15

cum
175

es and culverts
15684.63
Total [a+b+c+d+e] 94107.79
9410.78
= 103518.57
15

cum
176

mixer and concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 319859.13
Total [b] 464387.97

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
using batching plant:

7371.36
464387.97
37902.00
Total [a+b+c] 509661.33

0 50966.13
Total [d] 50966.13
Total [a+b+c+d] 560627.46
bridges
140156.87
Total [a+b+c+d+e] 700784.33
177

70078.43
= 770862.76
120

cum

es and culverts
112125.49
Total [a+b+c+d+e] 672752.95
67275.30
= 740028.25
120

cum
178

ight using batching plant:


7371.36
464387.97
37902.00
Total [a+b+c] 509661.33

9173.90

0 60140.04
Total [d] 69313.94
Total [a+b+c+d] 578975.27
bridges
144743.82
Total [a+b+c+d+e] 723719.09
72371.91
= 796091.00
120

cum

es and culverts
115795.05
Total [a+b+c+d+e] 694770.32
69477.03
= 764247.35
120

cum
179

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
180

using concrete mixer


7339.44
58395.60
3630.00
Total [a+b+c] 69365.04

0 6936.50

Total [d] 6936.50


Total [a+b+c+d] 76301.54

bridges
19075.39
Total [a+b+c+d+e] 95376.93
9537.69
= 104914.62
15

cum

es and culverts
15260.31
Total [a+b+c+d+e] 91561.85
9156.19
= 100718.04
15

cum

ight using concrete mixer


7339.44
58395.60
3630.00
Total [a+b+c] 69365.04
181

0 1109.84

0 7976.98
Total [d] 9086.82
Total [a+b+c+d] 78451.86

bridges
19612.97
Total [a+b+c+d+e] 98064.83
9806.48
= 107871.31
15

cum
182

es and culverts
15690.37
Total [a+b+c+d+e] 94142.23
9414.22
= 103556.45
15

cum

nsit mixer and concrete pump

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 322635.91
Total [b] 467164.75

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
m height using batching plant:
7371.36
467164.75
183

37902.00
Total [a+b+c] 512438.11

0 51243.81
Total [d] 51243.81
Total [a+b+c+d] 563681.92
bridges
140920.48
Total [a+b+c+d+e] 704602.40
70460.24
= 775062.64
120

cum
184

es and culverts
112736.38
Total [a+b+c+d+e] 676418.30
67641.83
= 744060.13
120

cum

eight using batching plant:


7371.36
467164.75
37902.00
Total [a+b+c] 512438.11

0 8199.01

0 58930.38
Total [d] 67129.39
Total [a+b+c+d] 579567.50
bridges
144891.88
Total [a+b+c+d+e] 724459.38
72445.94
= 796905.32
120

cum

es and culverts
115913.50
Total [a+b+c+d+e] 695481.00
69548.10
= 765029.10
120
185

cum

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44
186

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 41850.11
Total [b] 59916.22

Hour 1398.00
Hour 2232.00
Total [b] 3630.00

using concrete mixer:


7339.44
59916.22
3630.00
Total [a+b+c] 70885.66

0 7088.57
Total [d] 7088.57
Total [a+b+c+d] 77974.23

bridges
19493.56
Total [a+b+c+d+e] 97467.79
9746.78
= 107214.57
15
cum
es and culverts
15594.85
Total [a+b+c+d+e] 93569.08
9356.91
= 102925.99
15
187

cum

from 5-10 m height


mixer:

7339.44
59916.22
3630.00
Total [a+b+c] 70885.66

0 992.40

0 7797.42
Total [d] 8789.82
Total [a+b+c+d] 79675.48
188

bridges
19918.87
Total [a+b+c+d+e] 99594.35
9959.44
= 109553.79
15

cum

es and culverts
15935.10
Total [a+b+c+d+e] 95610.58
9561.06
= 105171.64
15

cum

sing Batching Plant

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71
189

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [b] 37902.00
m height using batching plant:

7371.36
479329.71
37902.00
Total [a+b+c] 524603.07
190

0 52460.31
Total [d] 52460.31
Total [a+b+c+d] 577063.38
bridges
144265.85
Total [a+b+c+d+e] 721329.23
72132.92
= 793462.15
120

cum

es and culverts
115412.68
Total [a+b+c+d+e] 692476.06
69247.61
= 761723.67
120

cum

from 5 -10 m height


g plant:
7371.36
479329.71
37902.00
Total [a+b+c] 524603.07

0 7344.44

0 57706.34

Total [d] 65050.78


Total [a+b+c+d] 589653.85
191

bridges
147413.46
Total [a+b+c+d+e] 737067.31
73706.73
= 810774.04
120

cum
192

es and culverts
117930.77
Total [a+b+c+d+e] 707584.62
70758.46
= 778343.08
120

cum

ar reinforcement in substructure
pecificaion

, shifting to site, tying and placing in

Nos 111.86
Nos 696.00
Nos 2073.50
Total [a] 2881.36

MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 50211.30
bridges
12552.83
Total [a+b+c] 62764.13
6276.41
= 69040.54
1
MT

es and culverts
193

10042.26
Total [a+b+c+d+e] 60253.56
6025.36
= 66278.92
1

MT
194

el reinforcement in substructure
pecificaion

, shifting to site, tying and placing in


Nos 92.12
Nos 522.00
Nos 1754.50
Total [a] 2368.62

MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49698.56
bridges
12424.64
Total [a+b+c] 62123.20
6212.32
= 68335.52
1

MT

es and culverts
9939.71
Total [a+b+c+d+e] 59638.27
5963.83
= 65602.10
1

MT
195

nry /plain / reinforced concrete


100 mm dia AC pipe, extending
with slope of aV:20H towards
nd techinical specifications.

, shifting to site, tying and placing in

Nos 9.87
Nos 225.50
Nos 79.75
Total [a] 315.12

RM 1575.00
Nos. 450.00
Nos. 250.00
Cum 198.99
Total [b] 2473.99
Total [a+b] 2789.11

bridges
697.28
Total [a+b+c] 3486.39
348.64
= 3835.03
30
Nos.

es and culverts
557.82
Total [a+b+c+d+e] 3346.93
334.69
= 3681.62
196

30
Nos.
197

wall complete as per drawing and

Nos 92.12
Nos 2233.00
Total [a] 2325.12

Cum 2963.40
Total [b] 2963.40

Hour 387.50

Hour 15.50
Total [c] 403.00
Total [a+b+c] 5691.52
bridges
1422.88
Total [a+b+c+d] 7114.40
711.44
= 7825.84
10

Cum

es and culverts
1138.30
Total [a+b+c+d] 6829.82
682.98
= 7512.80
10

Cum
198

with granular materials / stone


uirements laid down in clause
a thickness of not less than 600
ll and provided over the entire
nd return walls to the full height
e as per drawing and techinical

Nos 105.28
Nos 2002.00
Nos 319.00
Total [a] 2426.28
199

Cum 3344.52

Total [b] 3344.52

Hour 18.60
Total [c] 18.60
Total [a+b+c] 5789.40

bridges
1447.35
Total [a+b+c+d] 7236.75
723.68
= 7960.43
10

Cum

es and culverts
1157.88
Total [a+b+c+d] 6947.28
694.73
= 7642.01
10

Cum
107

Chapter - 12
Foundation
Sl. No. Quantity Description Rate per
14.1. Furnishing and placing reinforced / presressed Cement concrete
superstructure as per drawing and techinical specifications.

Case I RCC Grade M 20 using concrete mixer


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total
b) Material:
5.12 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-20 FOR SOLID SLAB SUPERSTRUCTURE USING
MIXER
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of materials,Labour and machinary = [a+b+c
a. UPTO 5 m HEIGHT
d) Form work
108

On cost of materials, labour and


20% machinary
62885.88 /
Total [a+b+c

(i) For major bridges and minor bridges


e) Overheads 25% on 75463.06
Total [a+b+c+d
f) Contractor's profit 10% on 94328.83
Rate for 15 Cum
Rate for 1 cum = 103761.71 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 6917.45 /
109

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 75463.06
Total [a+b+c+d
f) Contractor's profit 10% on 90555.67
Rate for 15 Cum
Rate for 1 cum = 99611.24 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 6640.75 /

b. FROM 5m TO 10 m HEIGHT
Cost of materials,Labour and machinary = [a+b+c
d) Form work
On cost of materials, labour and
25% machinary
62885.88 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 98259.19
Rate for 15 Cum
Rate for 1 cum = 108085.11 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7205.67 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 94328.82
Rate for 15 Cum
Rate for 1 cum = 103761.70 /
RCC M 20 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 6917.45 /

II RCC M-20 FOR T-BEAM & SLAB SUPERSTRUCTURE


CONCRETE MIXER
a. UPTO 5 m HEIGHT
Cost of materials,Labour and machinary = [a+b+c
110

d) Form work
On cost of materials, labour and
25% machinary 62885.88 /

Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 98259.19
Rate for 15 Cum
Rate for 1 cum = 108085.11 /
RCC M 20 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7205.67 /
111

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 78607.35
Total [a+b+c+d
f) Contractor's profit 10% on 94328.82
Rate for 15 Cum
Rate for 1 cum = 103761.70 /
RCC M 20 for T-Beam & slab using concrete
mixer for height upto 5 m
= 6917.45 /

b. FROM 5 m TO 10 m HEIGHT USING CONCRETE M


Cost of materials,Labour and machinary = [a+b+c
d) Form work
On cost of materials, labour and
30% machinary
62885.88 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 81751.64
Total [a+b+c+d
f) Contractor's profit 10% on 102189.55
Rate for 15 Cum
Rate for 1 cum = 112408.51 /
RCC M 20 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 7493.90 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 81751.64
Total [a+b+c+d
f) Contractor's profit 10% on 98101.97
Rate for 15 Cum
Rate for 1 cum = 107912.17 /
RCC M 20 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 7194.14 /
-*/-*/-*/
Case : II RCC M 20 FOR SOLID SLAB Using Batching Plant

MORT & H Specification No: 1500, 1700 & 2200


Unit = Cum
112

Taking Output = 120 cum


a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
40.92 Tonne Cement 6611.39 /
Total
113

C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Total
RCC M 20
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b
a. For SOLID SLAB HEIGHT UPTO 5.0 M

Cost of materials, labour and machinary =

d) Form work
On cost of materials, labour and
20% machinary
460340.35 /

Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 552408.42
Total [a+b+c+d
f) Contractor's profit 10% on 690510.53
Rate for 120 cum
Rate for 1 cum = 759561.58 /
RCC M 20 for Solid slab with batching plant for
height upto 5 m
= 6329.68 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 552408.42
Total [a+b+c+d
f) Contractor's profit 10% on 662890.10
Rate for 120 cum
Rate for 1 cum = 729179.11 /
114

RCC M 20 for Solid slab with batching plant for


height upto 5 m
= 6076.49 /
b) For SOLID SLAB HEIGHT FROM 5.0 M TO 10 M

Cost of materials, labour and machinary =


d) Form work
On cost of materials, labour and
25% machinary 460340.35 /
Total
Total [a+b+c
115

(i) For major bridges and minor bridges


e) Overheads 25% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 719281.80
Rate for 120 cum
Rate for 1 cum = 791209.98 /
RCC M 20 for Solid slab with batching plant for
height from 5 m - 10 m
= 6593.42 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 690510.53
Rate for 120 cum
Rate for 1 cum = 759561.58 /
RCC M 20 for Solid slab with batching plant for
height from 5 m - 10 m
= 6329.68 /

a. For T BEAM & SLAB HEIGHT UPTO 5.0 M


Cost of materials, labour and machinary =

d) Form work
On cost of materials, labour and
25% machinary 460340.35 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 719281.80
Rate for 120 on
Rate for 1 cum = 791209.98 /
RCC M 20 for T-beam & slab with batching plant
for height upto 5 m
= 6593.42 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 575425.44
Total [a+b+c+d
f) Contractor's profit 10% on 690510.53
116

Rate for 120 on


Rate for 1 cum = 759561.58 /
RCC M 20 for T-beam & slab with batching plant
for height upto 5 m
= 6329.68 /

b) For T - BEAM & SLAB HEIGHT FROM 5.0 M TO 10


Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
30% machinary
460340.35 /
Total [a+b+c
117

(i) For major bridges and minor bridges


e) Overheads 25% on 598442.46
Total [a+b+c+d
f) Contractor's profit 10% on 748053.08
Rate for 120 on
Rate for 1 cum = 822858.39 /
RCC M 20 for T-beam & slab with batching plant
for height from 5-10 m
= 6857.15 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 598442.46
Total [a+b+c+d
f) Contractor's profit 10% on 718130.95
Rate for 120 on
Rate for 1 cum = 789944.05 /

RCC M 20 for T-beam & slab with batching plant


for height from 5-10 m
= 6582.87 /

-*/-*/-*/

Case I RCC Grade M-25 using concrete mixer


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total
b) Material:
5.99 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
118

6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /


6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-25 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
20% machinary 68637.79 /
Total [a+b+c
119

(i) For major bridges and minor bridges


e) Overheads 25% on 82365.35
Total [a+b+c+d
f) Contractor's profit 10% on 102956.69
Rate for 15 Cum
Rate for 1 cum = 113252.36 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7550.16 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 82365.35
Total [a+b+c+d
f) Contractor's profit 10% on 98838.42
Rate for 15 Cum
Rate for 1 cum = 108722.26 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7248.15 /

b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary
68637.79 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 85797.24
Total [a+b+c+d
f) Contractor's profit 10% on 107246.55
Rate for 15 Cum
Rate for 1 cum = 117971.21 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7864.75 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 85797.24
Total [a+b+c+d
120

f) Contractor's profit 10% on 102956.69


Rate for 15 Cum
Rate for 1 cum = 113252.36 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7550.16 /
121

II RCC M-25 FOR T-BEAM & SLAB SUPERSTRUCTURE


CONCRETE MIXER
a. UPTO 5 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary
68637.79 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 85797.24
Total [a+b+c+d
f) Contractor's profit 10% on 107246.55
Rate for 15 Cum
Rate for 1 cum = 117971.21 /
RCC M-25 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7864.75 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 85797.24
Total [a+b+c+d
f) Contractor's profit 10% on 102956.69
Rate for 15 Cum
Rate for 1 cum = 113252.36 /
RCC M-25 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7550.16 /

b. FROM 5 m TO 10 m HEIGHT USING CONCRETE M


Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
30% machinary 68637.79 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 89229.13
Total [a+b+c+d
122

f) Contractor's profit 10% on 111536.41


Rate for 15 Cum
Rate for 1 cum = 122690.05 /
RCC M-25 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 8179.34 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 89229.13
Total [a+b+c+d
f) Contractor's profit 10% on 107074.96
Rate for 15 Cum
Rate for 1 cum = 117782.46 /
RCC M-25 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 7852.16 /

-*/-*/-*/
123

Case : II RCC M-25 FOR SOLID SLAB Using Batching Plant


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.84 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
18.00 Nos Mazdoor 319.00 /
Total
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.20 Cum Sand for mortar 293.06 /
47.95 Tonne Cement 6611.39 /
Total
C) Machinary

6.00 Hour Batching Plant 20 Cum / hour 2232.00 /

6.00 Hour Generator 100 KVA 698.00 /


6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total
RCC M-25
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. For SOLID SLAB HEIGHT UPTO 5.0 M
d) Form work
On cost of materials, labour and
20% machinary
506877.04 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
124

e) Overheads 25% on 608252.45


Total [a+b+c+d
f) Contractor's profit 10% on 760315.56
Rate for 120 cum
Rate for 1 cum = 836347.12 /
RCC M-25 for Solid slab with batching plant for
height upto 5 m
= 6969.56 /
125

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 608252.45
Total [a+b+c+d
f) Contractor's profit 10% on 729902.94
Rate for 120 cum
Rate for 1 cum = 802893.23 /
RCC M-25 for Solid slab with batching plant for
height upto 5 m
= 6690.78 /
b) For SOLID SLAB HEIGHT FROM 5.0 M TO 10 M
Cost of materials, Labour and machinary

d) Form work
On cost of materials, labour and
25% machinary 506877.04 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 791995.38
Rate for 120 cum
Rate for 1 cum = 871194.92 /
RCC M-25 for Solid slab with batching plant for
height from 5 m - 10 m
= 7259.96 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 760315.56
Rate for 120 cum
Rate for 1 cum = 836347.12 /
RCC M-25 for Solid slab with batching plant for
height from 5 m - 10 m
= 6969.56 /

a. For T BEAM & SLAB HEIGHT UPTO 5.0 M


Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
25% machinary 506877.04 /
126

Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 791995.38
Rate for 120 cum
Rate for 1 cum = 871194.92 /
RCC M-25 for T-beam & slab with batching plant
for height upto 5 m
= 7259.96 /
127

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 633596.30
Total [a+b+c+d
f) Contractor's profit 10% on 760315.56
Rate for 120 cum
Rate for 1 cum = 836347.12 /
RCC M-25 for T-beam & slab with batching plant
for height upto 5 m
= 6969.56 /
b) For T - BEAM & SLAB HEIGHT FROM 5.0 M TO 10
Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
30% machinary
506877.04 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 658940.15
Total [a+b+c+d
f) Contractor's profit 10% on 823675.19
Rate for 120 cum
Rate for 1 cum = 906042.71 /

RCC M-25 for T-beam & slab with batching plant


for height from 5 - 10 m
= 7550.36 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 658940.15
Total [a+b+c+d
f) Contractor's profit 10% on 790728.18
Rate for 120 Cum
Rate for 1 cum = 869801.00 /

RCC M-25 for T-beam & slab with batching plant


for height from 5 - 10 m
= 7248.34 /

-*/-*/-*/
Case I RCC Grade M-30 using concrete mixer
MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
128

Taking Output = 15 cum


a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
129

C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-30 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
20% machinary 69697.20 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 83636.64
Total [a+b+c+d
f) Contractor's profit 10% on 104545.80
Rate for 15 Cum
Rate for 1 cum = 115000.38 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7666.69 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 83636.64
Total [a+b+c+d
f) Contractor's profit 10% on 100363.97
Rate for 15 Cum
Rate for 1 cum = 110400.37 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7360.02 /

b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary 69697.20 /
Total
130

Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 87121.50
Total [a+b+c+d
f) Contractor's profit 10% on 108901.88
Rate for 15 Cum
Rate for 1 cum = 119792.07 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7986.14 /
131

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 87121.50
Total [a+b+c+d
f) Contractor's profit 10% on 104545.80
Rate for 15 Cum
Rate for 1 cum = 115000.38 /
RCC M-30 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7666.69 /

II RCC M-30 FOR T-BEAM & SLAB SUPERSTRUCTURE


a. UPTO 5 m HEIGHT CONCRETE MIXER
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
25% machinary 69697.20 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 87121.50
Total [a+b+c+d
f) Contractor's profit 10% on 108901.88
Rate for 15 Cum
Rate for 1 cum = 119792.07 /
RCC M-30 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7986.14 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 87121.50
Total [a+b+c+d
f) Contractor's profit 10% on 104545.80
Rate for 15 Cum
Rate for 1 cum = 115000.38 /
RCC M-30 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7666.69 /

b. FROM 5 m TO 10 m HEIGHT USING CONCRETE M


Cost of materials, labour and machinary =
132

d) Form work
On cost of materials, labour and
30% machinary
69697.20 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 90606.36
Total [a+b+c+d
f) Contractor's profit 10% on 113257.95
Rate for 15 Cum
Rate for 1 cum = 124583.75 /
RCC M-30 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 8305.58 /
133

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 90606.36
Total [a+b+c+d
f) Contractor's profit 10% on 108727.63
Rate for 15 Cum
Rate for 1 cum = 119600.39 /
RCC M-30 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 7973.36 /
-*/-*/-*/
Case : II RCC M-30 FOR SOLID SLAB Using Batching Plant
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
19.00 Nos Mazdoor 319.00 /
Total
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.60 Cum Sand for mortar 293.06 /
48.79 Tonne Cement 6611.39 /
Total
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
6.00 Hour Loader 1 cum capacity 806.00 /
Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km
930.00 /
6.00 Hour Concrete pump 256.00 /
Total
RCC M-30
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
134

Cost of materials, labour and machinary =


a. For SOLID SLAB HEIGHT UPTO 5.0 M
d) Form work
On cost of materials, labour and
20% machinary
512880.00 /
Total
Total [a+b+c
135

(i) For major bridges and minor bridges


e) Overheads 25% on 615456.00
Total [a+b+c+d
f) Contractor's profit 10% on 769320.00
Rate for 120 cum
Rate for 1 cum = 846252.00 /
RCC M-30 for Solid slab with batching plant for
height upto 5 m
= 7052.10 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 615456.00
Total [a+b+c+d
f) Contractor's profit 10% on 738547.20
Rate for 120 cum
Rate for 1 cum = 812401.92 /
RCC M-30 for Solid slab with batching plant for
height upto 5 m
= 6770.02 /
b) For SOLID SLAB HEIGHT FROM 5.0 M TO 10 M
Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
25% machinary 512880.00 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 641100.00
Total [a+b+c+d
f) Contractor's profit 10% on 801375.00
Rate for 120 cum
Rate for 1 cum = 881512.50 /
RCC M-30 for Solid slab with batching plant for
height from 5 m - 10 m
= 7345.94 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 641100.00
Total [a+b+c+d
f) Contractor's profit 10% on 769320.00
Rate for 120 cum
Rate for 1 cum = 846252.00 /
136

RCC M-30 for Solid slab with batching plant for


height from 5 m - 10 m
= 7052.10 /

a. For T BEAM & SLAB HEIGHT UPTO 5.0 M


Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
25% machinary
512880.00 /
Total [a+b+c
137

(i) For major bridges and minor bridges


e) Overheads 25% on 641100.00
Total [a+b+c+d
f) Contractor's profit 10% on 801375.00
Rate for 120 cum
Rate for 1 cum = 881512.50 /
RCC M-30 for T-beam & slab with batching plant
for height upto 5 m
= 7345.94 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 641100.00
Total [a+b+c+d
f) Contractor's profit 10% on 769320.00
Rate for 120 cum
Rate for 1 cum = 846252.00 /
RCC M-30 for T-beam & slab with batching plant
for height upto 5 m
= 7052.10 /
b) For T - BEAM & SLAB HEIGHT FROM 5.0 M TO 10
Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
30% machinary 512880.00 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 666744.00
Total [a+b+c+d
f) Contractor's profit 10% on 833430.00
Rate for 120 cum
Rate for 1 cum = 916773.00 /
RCC M-30 for T-beam & slab with batching plant
for height from 5 - 10 m
= 7639.78 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 666744.00
Total [a+b+c+d
f) Contractor's profit 10% on 800092.80
Rate for 120 Cum
Rate for 1 cum = 880102.08 /
138

RCC M-30 for T-beam & slab with batching plant


for height from 5 - 10 m
= 7334.18 /
-*/-*/-*/

Case I RCC Grade M-35 using concrete mixer


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
139

b) Material:
6.33 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-35 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
18% machinary
71217.82 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 84037.03
Total [a+b+c+d
f) Contractor's profit 10% on 105046.29
Rate for 15 Cum
Rate for 1 cum = 115550.92 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7703.39 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 84037.03
Total [a+b+c+d
f) Contractor's profit 10% on 100844.44
Rate for 15 Cum
Rate for 1 cum = 110928.88 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7395.26 /
140

b. FROM 5m TO 10 m HEIGHT
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
23% machinary
71217.82 /
Total
Total [a+b+c
141

(i) For major bridges and minor bridges


e) Overheads 25% on 87597.92
Total [a+b+c+d
f) Contractor's profit 10% on 109497.40
Rate for 15 Cum
Rate for 1 cum = 120447.14 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 8029.81 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 87597.92
Total [a+b+c+d
f) Contractor's profit 10% on 105117.50
Rate for 15 Cum
Rate for 1 cum = 115629.25 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height 5 to 10m
= 7708.62 /

II RCC M-35 FOR T-BEAM & SLAB SUPERSTRUCTURE


a. UPTO 5 m HEIGHT CONCRETE MIXER
Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
23% machinary
71217.82 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 87597.92
Total [a+b+c+d
f) Contractor's profit 10% on 109497.40
Rate for 15 Cum
Rate for 1 cum = 120447.14 /
RCC M-35 for T-Beam & slab using concrete
mixer for height upto 5 m
= 8029.81 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 87597.92
Total [a+b+c+d
142

f) Contractor's profit 10% on 105117.50


Rate for 15 Cum
Rate for 1 cum = 115629.25 /
RCC M-35 for T-Beam & slab using concrete
mixer for height upto 5 m
= 7708.62 /

b. FROM 5 m TO 10 m HEIGHT USING CONCRETE M


Cost of materials, labour and machinary =
d) Form work
On cost of materials, labour and
28% machinary
71217.82 /
Total
Total [a+b+c
143

(i) For major bridges and minor bridges


e) Overheads 25% on 91158.81
Total [a+b+c+d
f) Contractor's profit 10% on 113948.51
Rate for 15 Cum
Rate for 1 cum = 125343.36 /
RCC M-35 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 8356.22 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 91158.81
Total [a+b+c+d
f) Contractor's profit 10% on 109390.57
Rate for 15 Cum
Rate for 1 cum = 120329.63 /
RCC M-35 for T -Beam & slab using concrete
mixer for height 5 to 10m
= 8021.98 /

-*/-*/-*/
Case : II RCC M-35 FOR SOLID SLAB Using Batching Plant
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 120 cum
a) Labour :
0.88 Nos Mate 329.00 /
3.00 Nos Mason class I 451.00 /
19.00 Nos Mazdoor 319.00 /
Total
b) Material:
64.80 Cum 20 mm ISS metal 1341.30 /
43.20 Cum 10 mm ISS metal 967.30 /
54.00 Cum Sand for mortar 293.06 /
50.64 Tonne Cement 6611.39 /
Total
C) Machinary
6.00 Hour Batching Plant 20 Cum / hour 2232.00 /
6.00 Hour Generator 100 KVA 698.00 /
144

6.00 Hour Loader 1 cum capacity 806.00 /


Transit mixer 4.0 cum capacity
15.00 Hour lead upto 1 Km 930.00 /
6.00 Hour Concrete pump 256.00 /
Total
RCC M-35
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
145

a. For SOLID SLAB HEIGHT UPTO 5.0 M


d) Form work
On cost of materials, labour and
18% machinary
524935.23 /
Total
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 619423.57
Total [a+b+c+d
f) Contractor's profit 10% on 774279.46
Rate for 120 cum
Rate for 1 cum = 851707.41 /
RCC M-35 for Solid slab with batching plant for
height upto 5 m
= 7097.56 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 619423.57
Total [a+b+c+d
f) Contractor's profit 10% on 743308.28
Rate for 120 cum
Rate for 1 cum = 817639.11 /
RCC M-35 for Solid slab with batching plant for
height upto 5 m
= 6813.66 /

b) For SOLID SLAB HEIGHT FROM 5.0 M TO 10 M


Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
23% machinary 524935.23 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 807087.91
Rate for 120 cum
Rate for 1 cum = 887796.70 /
RCC M-35 for Solid slab with batching plant for
height from 5 m - 10 m
= 7398.31 /
146

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 774804.40
Rate for 120 cum
Rate for 1 cum = 852284.84 /
RCC M-35 for Solid slab with batching plant for
height from 5 m - 10 m
= 7102.37 /
147

a. For T BEAM & SLAB HEIGHT UPTO 5.0 M


Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
23% machinary
524935.23 /

Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 807087.91
Rate for 120 cum
Rate for 1 cum = 887796.70 /
RCC M-35 for T-beam & slab with batching plant
for height upto 5 m
= 7398.31 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 645670.33
Total [a+b+c+d
f) Contractor's profit 10% on 774804.40
Rate for 120 cum
Rate for 1 cum = 852284.84 /
RCC M-35 for T-beam & slab with batching plant
for height upto 5 m
= 7102.37 /
b) For T - BEAM & SLAB HEIGHT FROM 5.0 M TO 10
Cost of materials, Labour and machinary
d) Form work
On cost of materials, labour and
28% machinary 524935.23 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 671917.09
Total [a+b+c+d
f) Contractor's profit 10% on 839896.36
Rate for 120 cum
Rate for 1 cum = 923886.00 /
148

RCC M-35 for T-beam & slab with batching plant


for height from 5 - 10 m
= 7699.05 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 671917.09
Total [a+b+c+d
f) Contractor's profit 10% on 806300.51
Rate for 120 Cum
Rate for 1 cum = 886930.56 /
RCC M-35 for T-beam & slab with batching plant
for height from 5 - 10 m
= 7391.09 /
-*/-*/-*/
149

Supplying, fitting and placing HYSD bar reinforcement in


14.2 complete as per drawing and techincal specificaion
MORT & H Specification No: 1600
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /

8.00 Kg Binding wires 45.60 /


Total
Total [a
(i) For major bridges and minor bridges
c) Overheads 25% on 51161.90
Total [a+b
d) Contractor's profit 10% on 63952.38
Rate for 1 MT
Rate for 1 cum = 70347.62 /

HYSD reinforcement for superstructure = 70347.62 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 51161.90
Total [a+b+c+d
f) Contractor's profit 10% on 61394.28
Rate for 1 MT
Rate for 1 cum = 67533.71 /

HYSD reinforcement for superstructure = 67533.71 /


-*/-*/-
150

Supplying, fitting and placing Mild steel reinforcement in


14.2. complete as per drawing and techincal specificaion
MORT & H Specification No: 2200
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.28 Nos position
Mate 329.00 /
1.50 Nos Blacksmith 348.00 /
5.50 Nos Mazdoor 319.00 /
Total
151

b) Material:
MS bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
6.00 Kg Binding wires 45.60 /
Total
Total [a
(i) For major bridges and minor bridges
c) Overheads 25% on 49698.56
Total [a+b
d) Contractor's profit 10% on 62123.20
Rate for 1 MT
Rate for 1 cum = 68335.52 /

Mild steel reinforcement for superstructure = 68335.52 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 49698.56
Total [a+b+c+d
f) Contractor's profit 10% on 59638.27
Rate for 1 MT
Rate for 1 cum = 65602.10 /

Mild steel reinforcement for superstructure = 65602.10 /


-*/-*/-
Providing and laying Cement Concrete wearing coat M-30 gra
14.4. concrete mixer and excluding reinforcement:
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
152

5.40 Cum 10 mm ISS metal 967.30 /


6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6611.39 /
Total
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
153

CC M 30
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of M - 30 grade concrete for 15 cum
Cost of M - 30 grade concrete for 1cum =
1.00 Cum M-30 grade concrete 4646.48 /
Mazdoor for cleaning deck slab
0.15 Nos concrete surface
319.00 /

To
(i) For major bridges and minor bridges
e) Overheads 25% on 4694.33
To
f) Contractor's profit 10% on 5867.91
Rate for 1 Cum
Rate for 1 CUM = 6454.70 /

Wearing coat in CC M 30 = 6454.70 /


(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 4694.33
To
f) Contractor's profit 10% on 5633.20
Rate for 1 Cum
Rate for 1 cum = 6196.52 /

Wearing coat in CC M 30 = 6196.52 /


*/-*/-*/-*/
154

14.5. Providing and laying 12 mm thick mastic Asphat wearing co


deck slab excluding prime coat with paving grade bitume
requirements given in Table -500-29, prepared by using mas
laid to required level and slope after cleaning the surf
providing anti-skid surface with bitumen precoated fine grad
chipping of 9.5 mm nominal size at the rate of 0.005 cum per
an approximate spacing of 10 cm center to center in b
pressed into surface when the temperature of surface not les
protruding 1 mm to 4 mm over mastic surface, all complete
515

MORT & H Specification No: 515 & 2702


Unit = Sqm
Taking Output = 72.46 Sqm [2 tonnes] [0.869 cum]
density of 2.3 tonnes /
a) Labour :
0.49 Nos Mate 329.00 /
11.00 Nos Mazdoor 286.00 /
1.25 Nos Mazdoor skilled 319.00 /
Total
155

Cost of 6.7 mm 727.30


6 mm 727.30
5.6 mm 727.30
4.75 mm & below 663.30
2845.20 /4 = 711.30
b) Material:
Bitumen 60/70 at 10.2 % by
0.204 tonne weight of mix = 2 X 10.2/100 = 39921.00 /
0.204 tonne

Crusher stone dust at 31.9% by


weight of mix = 2x31.9/100 =
0.390 Cum 0.638 tonnes = 0.638/1.625 =
266.30 /
0.39 cum

Lime stone dust filler with


calcium carbonate content not
0.360 MT less than 80% by weight at 817.52 /
17.92% by weight of mix = 2 X
17.92/100 = 0.36 MT

Coarse aggregates 3.35 mm to


9.5 mm at 40% by weight of mix
0.550 Cum = 2 x 40/100 = 0.80 MT =
711.30 /
0.8/1.456 = 0.55 cum

Pre coated stone chips of 13.2


mm nominal size for skid
0.036 Cum resistance = 72.46 x 0.005/10 = 1285.30 /
0.036 cum

Bitumen for coating of chips at


0.00105 MT 2% by weight = 0.036 x 1.456 x 39921.00 /
2 / 100 = 0.001048MT = 1.05 Kg

Total
C) Machinary
0.06 Hour Mechanical broom 288.00 /
0.06 Hour Air compressor 250 cfm 258.00 /

6.00 Hour Mastic cooker 1 tonne capacity 50.00 /

Bitumen Boiler 1500 litres


6.00 Hour capacity
160.00 /
156

Tractor for towing and


1.00 Hour positioning of mastic cooker and 293.00 /
bitumen boiler

Total
CC M 30
Total (a+b+c)
(i) For major bridges and minor bridges
e) Overheads 25% on 14313.18
To
f) Contractor's profit 10% on 17891.48
Rate for 72.46 Sqm
Rate for 1 Sqm = 19680.63 /
Mastic Asphalt = 271.61 /
157

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 14313.18
To
f) Contractor's profit 10% on 17175.82
Rate for 72.46 Sqm
Rate for 1 Sqm = 18893.40 /
Mastic Asphalt = 260.74 /
*/-*/-*/-*/

14.6. Construction of precast RCC railing of M 30 grade, aggr


exceeding 12mm, true to line and grad, tolerance of vertical
to exceed 1 in 500, cenre to centre spacing between verti
exceed 2000 mm, leaving adequate space between ve
expansion, complete as per approved drawings a
specifications.

MORT & H Specification No: 1500, 1600 & 1700 & 2703
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum
233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
158

RCC M-30 USING CONCRETE MIXER

a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69697.20 /
= 4646.48 /
159

Cost of HYSD bar reinforcements:


Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /

8.00 Kg Binding wires 45.60 /


Total
Total [a
Rate for 1 MT
RCC M-30 Railing USING CONCRETE MIXER
Unit = Rm
Taking Output = 48 Rm
RCC M 30 mix excluding steel
4.092 Cum reinforcement
4646.48 /

For fromwork for casting in


5% casting yard 4646.48 /

HYSD bars including 5 % for


0.865 MT overlaps and wastages
51161.90 /

For handling and fixing of


5% precast panels in position
63500.76 /

Rate for 48 Rm
Rate for 1 Rm = 66675.80 /

RCC M 30 hand rails cast in casting yard 1389.08 /

*-*-*-*-*-*-
160

14.7. Construction of precast RCC railing of M 30 grade in-sit


nominal size aggregates, true to line and grade, tolerance o
post not to exceed 1 in 500, cenre to centre spacing betwee
not to exceed 2000 mm, leaving adequate space between v
expansion, complete as per approved drawings a
specifications.

MORT & H Specification No: 1500, 1600 & 1700 & 2703
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
161

b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69697.20 /
= 4646.48 /
Cost of HYSD bar reinforcements:
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages 44815.56 /
8.00 Kg Binding wires 45.60 /
Total
Total [a
Rate for 1 MT
RCC M-30 Railing USING CONCRETE MIXER
Unit = Rm
Taking Output = 48 Rm
RCC M 30 mix excluding steel
4.092 Cum reinforcement
4646.48 /

For fromwork for casting in


12% casting yard 4646.48 /
162

HYSD bars including 5 % for


0.865 MT overlaps and wastages
51161.90 /

(i) For major bridges and minor bridges


e) Overheads 25% on 63826.02
To
f) Contractor's profit 10% on 79782.53
Rate for 48 Rm
Rate for 1 cum = 87760.78 /
RCC M 30 hand rails cast-in situ = 1828.35 /
163

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 63826.02
To
f) Contractor's profit 10% on 76591.22
Rate for 48 Rm
Rate for 1 cum = 84250.34 /
RCC M 30 hand rails cast-in situ = 1755.22 /
*/-*/-*/-*/

14.9 Drainage spouts complete as per drawing and specifications

MORT & H Specification No: 2705


Unit = 1 No.
Taking Output = 1 No.
a) Labour :
For fabrication
0.02 Nos Mate 329.00 /
0.02 Nos Black smith 348.00 /
0.02 Nos Mazdoor 319.00 /
For fixing in position
0.01 Nos Mate 329.00 /
0.01 Nos Mason class I 451.00 /
0.20 Nos Mazdoor 319.00 /
Total
b) Material:
Corrosion resistant structural
4.00 Kg steel
43.00 /

6.00 m GI pipe 100 mm dia 210.00 /


6.00 Nos. GI bolt 10 mm dia 1.30 /
2.00 Nos. GaIvanised MS flat clamp 7.50 /
Total
Cost of materials and labour

For electrodes, cutting gas,


5% sealent, anticorrosive bituminous 1546.32 /
paint, mild steel grating etc.
164

(i) For major bridges and minor bridges


e) Overheads 25% on 1623.64
To
f) Contractor's profit 10% on 2029.55
Rate for 6M
Rate for 1 M/NO = 2232.51 /
Drainage spout = 372.09 /
165

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 1623.64
To
f) Contractor's profit 10% on 1948.37
Rate for 6M
Rate for 1 M/NO = 2143.21 /

Drainage spout = 357.20 /


*/-*/-*/-*/

14.10. Plain cement concrete M 15 grade levelling course bel


approach slab complete as per drawing and techni
specification

MORT & H Specification No: 1500, 1700 & 2200


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 319.00 /
Total
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
4.13 Tonne Cement 6611.39 /
Total
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
Total [a+b
(i) For major bridges and minor bridges
166

d) Overheads 25% on 55166.11


Total [a+b+c
e) Contractor's profit 10% on 68957.64
Rate for 15 cum
Rate for 1 cum = 75853.40 /

PCC M 15 below approach slab = 5056.89 /


167

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 55166.11
Total [a+b+c
e) Contractor's profit 10% on 66199.33
Rate for 15 cum
Rate for 1 cum = 72819.26 /

PCC M 15 below approach slab = 4854.62 /


*-*-*-*-*-*-

14.11 RCC railing of M 30 grade approach slab including reinforce


work complete as per approved drawings and technical speci

MORT & H Specification No: 1500, 1600 & 1700 & 2704
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 319.00 /
Total
b) Material:
6.10 Tonne Cement 6611.39 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum
233.00 /

6.00 Hour Generator 33 KVA 372.00 /


Total
RCC M-30 USING CONCRETE MIXER
a) Labour charges
b) Cost of materials
168

c) Hire charges for machinary


Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69684.04 /
= 4645.60 /
Cost of HYSD bar reinforcements:

Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 329.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 319.00 /
Total
169

b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
8.00 Kg Binding wires 45.60 /
Total
Total [a
Rate for 1 MT
RCC M-30 For approach slab USING CONCRETE MIXE
reinforcements
Unit = Cum
Taking Output = 1 Cum
RCC M 30 mix excluding steel
1.000 Cum reinforcement 4645.60 /

For fromwork for casting in


2% casting yard
4645.60 /

HYSD bars including 5 % for


0.050 MT overlaps and wastages
51161.90 /

(i) For major bridges and minor bridges


e) Overheads 25% on 7296.61
To
f) Contractor's profit 10% on 9120.76
Rate for 1 Cum
Rate for 1 cum = 10032.84 /
RCC M 30 for approach slab using concrete
mixer including reinforcements
= 10032.84 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 7296.61
To
f) Contractor's profit 10% on 8755.93
Rate for 1 Cum
Rate for 1 cum = 9631.52 /
170

RCC M 30 for approach slab using concrete


mixer including reinforcements
= 9631.52 /

*/-*/-*/-*/
171

14.18. Filler Joint


[i] Providing and fixing12mm thick corrugated copper plate in e
complete as per drawing and technical specifications

MORT & H Specification No: 2605


Unit = Rm
Taking Output = 12 Rm
a) Labour for cutting bending, carrying and fixing, etc.
0.04 Nos Mate 329.00 /
0.50 Nos Mazdoor 286.00 /
0.50 Nos Mazdoor [Skilled] 319.00 /
Total
b) Material:
Copper plate- 12 m long x 250
55.00 Kg mm wide 165.00 /
Total

(i) For major bridges and minor bridges


e) Overheads 25% on 9390.66
To
f) Contractor's profit 10% on 11738.33
Rate for 12 Rm
Rate for 1 Rm = 12912.16 /
Filler with copper plate = 1076.01 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 9390.66
To
f) Contractor's profit 10% on 11268.79
Rate for 12 Rm
Rate for 1 Rm = 12395.67 /
Filler with copper plate = 1032.97 /
*/-*/-*/-*/
172

[ii] Providing and fixing 20 mm thick compressible fibre board


joint complete as per drawing and technical specifications

MORT & H Specification No: 2605


Unit = Rm
Taking Output = 12 Rm
a) Labour for cutting bending, carrying and fixing, etc.
0.01 Nos Mate 329.00 /
0.10 Nos Mazdoor 286.00 /
0.10 Nos Mazdoor [Skilled] 319.00 /
Total
173

b) Material:

20 mm thick compressible fibre


3.00 Sqm board 12 m long x 25 cm deep
726.00 /

Total

(i) For major bridges and minor bridges


e) Overheads 25% on 2241.79
To
f) Contractor's profit 10% on 2802.24
Rate for 12 Rm
Rate for 1 Rm = 3082.46 /
20 mm thick fibre board = 256.87 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 2241.79
To
f) Contractor's profit 10% on 2690.15
Rate for 12 Rm
Rate for 1 Rm = 2959.17 /

20 mm thick fibre board = 246.60 /


*/-*/-*/-*/

[iii] Providing and fixing 20 mm thick premoulded joint filler in e


for fixed ends of simple supported spans not exceeding 10 m
horizontal movement upto 20 mm covered with sealent co
drawing and technical specifications
MORT & H Specification No: 2605
Unit = Rm
Taking Output = 12 Rm
a) Labour:
0.01 Nos Mate 329.00 /
0.20 Nos Mazdoor 286.00 /
0.10 Nos Mazdoor [Skilled] 319.00 /
Total
b) Material:
174

Pre moulded joint filler12 m


3.60 Sqm longx20 mm thick and 300 mmm 726.00 /
deep local rate]

Total
175

(i) For major bridges and minor bridges


e) Overheads 25% on 2705.99
To
f) Contractor's profit 10% on 3382.49
Rate for 12 Rm
Rate for 1 Rm = 3720.74 /

20 mm thick premoulded joint filler = 310.06 /


(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 2705.99
To
f) Contractor's profit 10% on 3247.19
Rate for 12 Rm
Rate for 1 Rm = 3571.91 /
20 mm thick premoulded joint filler = 297.66 /
*/-*/-*/-*/

[iv] Providing and filling joint sealing compound complete as pe


technical specifications
MORT & H Specification No: 2605
Unit = Rm
Taking Output = 12 Rm
a) Labour:
0.02 Nos Mate 329.00 /
0.50 Nos Mazdoor 286.00 /
0.10 Nos Mazdoor [Skilled] 319.00 /
Total
b) Material:
0.012 Cum Sand 293.06 /
0.001 tonne Bitumen 80/100 grade 38951.00 /
Total

(i) For major bridges and minor bridges


e) Overheads 25% on 220.43
To
176

f) Contractor's profit 10% on 275.54


Rate for 12 Rm
Rate for 1 Rm = 303.09 /
Joint sealing compound 1 cm depth = 25.26 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 220.43
To
f) Contractor's profit 10% on 264.52
Rate for 12 Rm
Rate for 1 Rm = 290.97 /
Joint sealing compound 1 cm depth = 24.25 /
*/-*/-*/-*/
177

Rate per Amount

ed Cement concrete in
ecifications.

te mixer

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Tonne 33850.33
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 51916.44

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE

7339.44
51916.44
3630.00
[a+b+c] 62885.88
178

0 12577.18
Total [a+b+c+d] 75463.06

bridges
18865.77
Total [a+b+c+d+e] 94328.83
9432.88
= 103761.71
15

Cum
179

s and culverts
15092.61
Total [a+b+c+d+e] 90555.67
9055.57
= 99611.24
15

Cum

[a+b+c] 62885.88

0 15721.47
Total [a+b+c+d] 78607.35
bridges
19651.84
Total [a+b+c+d+e] 98259.19
9825.92
= 108085.11
15

Cum

s and culverts
15721.47
Total [a+b+c+d+e] 94328.82
9432.88
= 103761.70
15

Cum

UPERSTRUCTURE USING
MIXER

[a+b+c] 62885.88
180

0 15721.47

Total [a+b+c+d] 78607.35


bridges
19651.84
Total [a+b+c+d+e] 98259.19
9825.92
= 108085.11
15
Cum
181

s and culverts
15721.47
Total [a+b+c+d+e] 94328.82
9432.88
= 103761.70
15

Cum

NG CONCRETE MIXER
[a+b+c] 62885.88

0 18865.76
Total [a+b+c+d] 81751.64
bridges
20437.91
Total [a+b+c+d+e] 102189.55
10218.96
= 112408.51
15

Cum

s and culverts
16350.33
Total [a+b+c+d+e] 98101.97
9810.20
= 107912.17
15

Cum

g Batching Plant
182

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 270538.15
Total [b] 415066.99
183

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00

7371.36
415066.99
37902.00
Total [a+b+c] 460340.35
5.0 M
(a+b+c) 460340.35

0 92068.07

Total [a+b+c+d] 552408.42


bridges
138102.11
Total [a+b+c+d+e] 690510.53
69051.05
= 759561.58
120

cum

s and culverts
110481.68
Total [a+b+c+d+e] 662890.10
66289.01
= 729179.11
120
184

cum

5.0 M TO 10 M

(a+b+c) 460340.35

0 115085.09
Total [d] 115085.09
Total [a+b+c+d] 575425.44
185

bridges
143856.36
Total [a+b+c+d+e] 719281.80
71928.18
= 791209.98
120

cum

s and culverts
115085.09
Total [a+b+c+d+e] 690510.53
69051.05
= 759561.58
120

cum

PTO 5.0 M
(a+b+c) 460340.35

0 115085.09
Total [a+b+c+d] 575425.44
bridges
143856.36
Total [a+b+c+d+e] 719281.80
71928.18
= 791209.98
120

on

s and culverts
115085.09
Total [a+b+c+d+e] 690510.53
69051.05
186

= 759561.58
120

on

ROM 5.0 M TO 10 M
(a+b+c) 460340.35

0 138102.11
Total [a+b+c+d] 598442.46
187

bridges
149610.62
Total [a+b+c+d+e] 748053.08
74805.31
= 822858.39
120

on

s and culverts
119688.49
Total [a+b+c+d+e] 718130.95
71813.10
= 789944.05
120

on

te mixer

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Tonne 39602.24
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 57668.35
188

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7339.44
57668.35
3630.00
[a+b+c] 68637.79

0 13727.56
Total [a+b+c+d] 82365.35
189

bridges
20591.34
Total [a+b+c+d+e] 102956.69
10295.67
= 113252.36
15

Cum

s and culverts
16473.07
Total [a+b+c+d+e] 98838.42
9883.84
= 108722.26
15

Cum

[a+b+c] 68637.79

0 17159.45
Total [d] 17159.45
Total [a+b+c+d] 85797.24
bridges
21449.31
Total [a+b+c+d+e] 107246.55
10724.66
= 117971.21
15

Cum

s and culverts
17159.45
Total [a+b+c+d+e] 102956.69
190

10295.67
= 113252.36
15

Cum
191

UPERSTRUCTURE USING
MIXER

[a+b+c] 68637.79

0 17159.45
Total [d] 17159.45
Total [a+b+c+d] 85797.24
bridges
21449.31
Total [a+b+c+d+e] 107246.55
10724.66
= 117971.21
15

Cum

s and culverts
17159.45
Total [a+b+c+d+e] 102956.69
10295.67
= 113252.36
15

Cum

NG CONCRETE MIXER
[a+b+c] 68637.79

0 20591.34
Total [d] 20591.34
Total [a+b+c+d] 89229.13
bridges
22307.28
Total [a+b+c+d+e] 111536.41
192

11153.64
= 122690.05
15

Cum

s and culverts
17845.83
Total [a+b+c+d+e] 107074.96
10707.50
= 117782.46
15

Cum
193

g Batching Plant

Nos 276.36
Nos 1353.00
Nos 5742.00
Total [a] 7371.36

Cum 86916.24
Cum 41787.36
Cum 15883.85
Tonne 317016.23
Total [b] 461603.68

Hour 13392.00

Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
5
7371.36
461603.68
37902.00
[a+b+c] 506877.04
5.0 M

0 101375.41
Total [d] 101375.41
Total [a+b+c+d] 608252.45
bridges
194

152063.11
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120

cum
195

s and culverts
121650.49
Total [a+b+c+d+e] 729902.94
72990.29
= 802893.23
120

cum

5.0 M TO 10 M
= 506877.04

0 126719.26
Total [a+b+c+d] 633596.30
bridges
158399.08
Total [a+b+c+d+e] 791995.38
79199.54
= 871194.92
120

cum

s and culverts
126719.26
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120

cum

PTO 5.0 M
= 506877.04

0 126719.26
196

Total [a+b+c+d] 633596.30


bridges
158399.08
Total [a+b+c+d+e] 791995.38
79199.54
= 871194.92
120

cum
197

s and culverts
126719.26
Total [a+b+c+d+e] 760315.56
76031.56
= 836347.12
120

cum

ROM 5.0 M TO 10 M
= 506877.04

0 152063.11
Total [a+b+c+d] 658940.15
bridges
164735.04
Total [a+b+c+d+e] 823675.19
82367.52
= 906042.71
120

cum

s and culverts
131788.03
Total [a+b+c+d+e] 790728.18
79072.82
= 869801.00
120

Cum

te mixer
198

Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60

Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60
199

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7671.60
58395.60
3630.00
[a+b+c] 69697.20

0 13939.44
Total [a+b+c+d] 83636.64
bridges
20909.16
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15

Cum

s and culverts
16727.33
Total [a+b+c+d+e] 100363.97
10036.40
= 110400.37
15

Cum

[a+b+c] 69697.20

0 17424.30
Total [d] 17424.30
200

Total [a+b+c+d] 87121.50


bridges
21780.38
Total [a+b+c+d+e] 108901.88
10890.19
= 119792.07
15

Cum
201

s and culverts
17424.30
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15

Cum

UPERSTRUCTURE USING
MIXER
[a+b+c] 69697.20

0 17424.30
Total [d] 17424.30
Total [a+b+c+d] 87121.50
bridges
21780.38
Total [a+b+c+d+e] 108901.88
10890.19
= 119792.07
15

Cum

s and culverts
17424.30
Total [a+b+c+d+e] 104545.80
10454.58
= 115000.38
15

Cum

NG CONCRETE MIXER
[a+b+c] 69697.20
202

0 20909.16
Total [d] 20909.16
Total [a+b+c+d] 90606.36
bridges
22651.59
Total [a+b+c+d+e] 113257.95
11325.80
= 124583.75
15

Cum
203

s and culverts
18121.27
Total [a+b+c+d+e] 108727.63
10872.76
= 119600.39
15

Cum

g Batching Plant

Nos 289.52
Nos 1353.00
Nos 6061.00
Total [a] 7703.52

Cum 86916.24
Cum 41787.36
Cum 16001.08
Tonne 322569.80
Total [b] 467274.48

Hour 13392.00
Hour 4188.00
Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
0
7703.52
467274.48
37902.00
204

[a+b+c] 512880.00
5.0 M

0 102576.00
Total [d] 102576.00
Total [a+b+c+d] 615456.00
205

bridges
153864.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120

cum

s and culverts
123091.20
Total [a+b+c+d+e] 738547.20
73854.72
= 812401.92
120

cum

5.0 M TO 10 M
= 512880.00

0 128220.00
Total [a+b+c+d] 641100.00
bridges
160275.00
Total [a+b+c+d+e] 801375.00
80137.50
= 881512.50
120

cum

s and culverts
128220.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120
206

cum

PTO 5.0 M
= 512880.00

0 128220.00
Total [a+b+c+d] 641100.00
207

bridges
160275.00
Total [a+b+c+d+e] 801375.00
80137.50
= 881512.50
120

cum

s and culverts
128220.00
Total [a+b+c+d+e] 769320.00
76932.00
= 846252.00
120

cum

ROM 5.0 M TO 10 M
= 512880.00

0 153864.00
Total [a+b+c+d] 666744.00
bridges
166686.00
Total [a+b+c+d+e] 833430.00
83343.00
= 916773.00
120

cum

s and culverts
133348.80
Total [a+b+c+d+e] 800092.80
80009.28
= 880102.08
120
208

Cum

te mixer

Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
209

Tonne 41850.11
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 59916.22

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
7671.60
59916.22
3630.00
[a+b+c] 71217.82

0 12819.21
Total [a+b+c+d] 84037.03
bridges
21009.26
Total [a+b+c+d+e] 105046.29
10504.63
= 115550.92
15

Cum

s and culverts
16807.41
Total [a+b+c+d+e] 100844.44
10084.44
= 110928.88
15

Cum
210

[a+b+c] 71217.82

0 16380.10
Total [d] 16380.10
Total [a+b+c+d] 87597.92
211

bridges
21899.48
Total [a+b+c+d+e] 109497.40
10949.74
= 120447.14
15

Cum

s and culverts
17519.58
Total [a+b+c+d+e] 105117.50
10511.75
= 115629.25
15

Cum

UPERSTRUCTURE USING
MIXER
[a+b+c] 71217.82

0 16380.10
Total [d] 16380.10
Total [a+b+c+d] 87597.92
bridges
21899.48
Total [a+b+c+d+e] 109497.40
10949.74
= 120447.14
15

Cum

s and culverts
17519.58
Total [a+b+c+d+e] 105117.50
212

10511.75
= 115629.25
15

Cum

NG CONCRETE MIXER
[a+b+c] 71217.82

0 19940.99
Total [d] 19940.99
Total [a+b+c+d] 91158.81
213

bridges
22789.70
Total [a+b+c+d+e] 113948.51
11394.85
= 125343.36
15

Cum

s and culverts
18231.76
Total [a+b+c+d+e] 109390.57
10939.06
= 120329.63
15

Cum

g Batching Plant

Nos 289.52
Nos 1353.00
Nos 6061.00
Total [a] 7703.52

Cum 86916.24
Cum 41787.36
Cum 15825.24
Tonne 334800.87
Total [b] 479329.71

Hour 13392.00
Hour 4188.00
214

Hour 4836.00
Hour 13950.00
Hour 1536.00
Total [c] 37902.00
5
7703.52
479329.71
37902.00
[a+b+c] 524935.23
215

5.0 M

0 94488.34
Total [d] 94488.34
Total [a+b+c+d] 619423.57
bridges
154855.89
Total [a+b+c+d+e] 774279.46
77427.95
= 851707.41
120

cum

s and culverts
123884.71
Total [a+b+c+d+e] 743308.28
74330.83
= 817639.11
120

cum

5.0 M TO 10 M
= 524935.23

0 120735.10
Total [a+b+c+d] 645670.33
bridges
161417.58
Total [a+b+c+d+e] 807087.91
80708.79
= 887796.70
120

cum
216

s and culverts
129134.07
Total [a+b+c+d+e] 774804.40
77480.44
= 852284.84
120

cum
217

PTO 5.0 M
= 524935.23

0 120735.10

Total [a+b+c+d] 645670.33


bridges
161417.58
Total [a+b+c+d+e] 807087.91
80708.79
= 887796.70
120

cum

s and culverts
129134.07
Total [a+b+c+d+e] 774804.40
77480.44
= 852284.84
120

cum

ROM 5.0 M TO 10 M
= 524935.23

0 146981.86
Total [a+b+c+d] 671917.09
bridges
167979.27
Total [a+b+c+d+e] 839896.36
83989.64
= 923886.00
120
218

cum

s and culverts
134383.42
Total [a+b+c+d+e] 806300.51
80630.05
= 886930.56
120

Cum
219

reinforcement in superstructure
ecificaion

shifting to site, tying and placing in


Nos 144.76
Nos 1044.00
Nos 2552.00
Total [a] 3740.76

MT 47056.34

Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
bridges
12790.48
Total [a+b+c] 63952.38
6395.24
= 70347.62
1

MT

s and culverts
10232.38
Total [a+b+c+d+e] 61394.28
6139.43
= 67533.71
1

MT
220

reinforcement in superstructure
ecificaion

shifting to site, tying and placing in


Nos 92.12
Nos 522.00
Nos 1754.50
Total [a] 2368.62
221

MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49698.56
bridges
12424.64
Total [a+b+c] 62123.20
6212.32
= 68335.52
1

MT

s and culverts
9939.71
Total [a+b+c+d+e] 59638.27
5963.83
= 65602.10
1

MT

aring coat M-30 grade using


nt:

Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60

Cum 10864.53
222

Cum 5223.42
Cum 1978.16
Tonne 40329.49
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
223

7671.60
58395.60
3630.00
ete for 15 cum 69697.20
4646.48
Cum 4646.48

Nos 47.85

Total 4694.33
bridges
1173.58
Total 5867.91
586.79
= 6454.70
1

Cum

s and culverts
938.87
Total 5633.20
563.32
= 6196.52
1

Cum
224

Asphat wearing course on top of


ving grade bitumen meeting the
ared by using mastic cooker and
cleaning the surface, including
precoated fine graded hard stone
e of 0.005 cum per 10 sqm and at
er to center in both directions,
e of surface not less than 1000 C,
rface, all complete as per clause

2 tonnes] [0.869 cum] assuming a


ensity of 2.3 tonnes / cum

Nos 161.21
Nos 3146.00
Nos 398.75
Total [a] 3705.96
225

tonne 8143.88

Cum 103.86

MT 294.31

Cum 391.22

Cum 46.27

MT 41.92

Total [b] 9021.46

Hour 17.28
Hour 15.48

Hour 300.00

Hour 960.00
226

Hour 293.00

Total [b] 1585.76

14313.18
bridges
3578.30
Total 17891.48
1789.15
= 19680.63
72.46
Sqm
227

s and culverts
2862.64
Total 17175.82
1717.58
= 18893.40
72.46
Sqm

M 30 grade, aggregate size not


olerance of vertical RCC post not
cing between vertical post not to
pace between vertical post for
ved drawings and technical

00 & 1700 & 2703

Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60

Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
228

CRETE MIXER
7671.60
58395.60
3630.00
[a+b+c] 69697.20
15
Cum
229

shifting to site, tying and placing in


Nos 144.76
Nos 1044.00
Nos 2552.00
Total [a] 3740.76

MT 47056.34

Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90

Cum 19013.40

0 232.32

MT 44255.04

Total 63500.76

0 3175.04

= 66675.80
48

Rm
230

M 30 grade in-situ with 20 mm


grade, tolerance of vertical RCC
tre spacing between vertical post
e space between vertical post for
ved drawings and technical

00 & 1700 & 2703

Nos 296.10
Nos 676.50
Nos 6699.00
Total [a] 7671.60
231

Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
[a+b+c] 69697.20
15
Cum

shifting to site, tying and placing in


Nos 144.76
Nos 1044.00
Nos 2552.00
Total [a] 3740.76

MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90

Cum 19013.40

0 557.58
232

MT 44255.04

Total 63826.02
bridges
15956.51
Total 79782.53
7978.25
= 87760.78
48
Rm
233

s and culverts
12765.20
Total 76591.22
7659.12
= 84250.34
48
Rm

and specifications

Nos 6.58
Nos 6.96
Nos 6.38

Nos 3.29
Nos 4.51
Nos 63.80
Total [a] 91.52

Kg 172.00

m 1260.00
Nos. 7.80
Nos. 15.00
Total [b] 1454.80
[a+b] 1546.32

0 77.32
234

Total 1623.64
bridges
405.91
Total 2029.55
202.96
= 2232.51
6
m
235

s and culverts
324.73
Total 1948.37
194.84
= 2143.21
6

velling course below


wing and technical

Nos 282.94
Nos 676.50
Nos 6380.00
Total [a] 7339.44

Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27305.05
Total [b] 44196.67

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 55166.11
bridges
236

13791.53
Total [a+b+c+d] 68957.64
6895.76
= 75853.40
15

cum
237

s and culverts
11033.22
Total [a+b+c+d] 66199.33
6619.93
= 72819.26
15

cum

including reinforcementand form


and technical specifications.

00 & 1700 & 2704

Nos 282.94
Nos 676.50
Nos 6699.00
Total [a] 7658.44

Tonne 40329.49
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58395.60

Hour 1398.00

Hour 2232.00
Total [c] 3630.00
CRETE MIXER
7658.44
58395.60
238

3630.00
[a+b+c] 69684.04
15
Cum
nforcements:

shifting to site, tying and placing in


Nos 144.76
Nos 1044.00
Nos 2552.00
Total [a] 3740.76
239

MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 51161.90
= 51161.90
CONCRETE MIXER including
nts

Cum 4645.60

0 92.91

MT 2558.10

Total 7296.61
bridges
1824.15
Total 9120.76
912.08
= 10032.84
1

Cum

s and culverts
1459.32
Total 8755.93
875.59
= 9631.52
1
240

Cum
241

d copper plate in expansion joint


ecifications

arrying and fixing, etc. :


Nos 13.16
Nos 143.00
Nos 159.50
Total [a] 315.66

Kg 9075.00
Total [b] 9075.00
[a+b] 9390.66
bridges
2347.67
Total 11738.33
1173.83
= 12912.16
12
Rm
s and culverts
1878.13
Total 11268.79
1126.88
= 12395.67
12
Rm
242

essible fibre board in expansion


al specifications

arrying and fixing, etc. :


Nos 3.29
Nos 28.60
Nos 31.90
Total [a] 63.79
243

Sqm 2178.00

Total [b] 2178.00


[a+b] 2241.79
bridges
560.45
Total 2802.24
280.22
= 3082.46
12
Rm
s and culverts
448.36
Total 2690.15
269.02
= 2959.17
12

Rm

lded joint filler in expansion joint


not exceeding 10 m to cater for a
ed with sealent complete as per

Nos 3.29
Nos 57.20
Nos 31.90
Total [a] 92.39
244

Sqm 2613.60

Total [b] 2613.60


[a+b] 2705.99
245

bridges
676.50
Total 3382.49
338.25
= 3720.74
12

Rm
s and culverts
541.20
Total 3247.19
324.72
= 3571.91
12
Rm

nd complete as per drawing and

Nos 6.58
Nos 143.00
Nos 31.90
Total [a] 181.48

Cum 3.52
tonne 38.95
Total [b] 38.95
[a+b] 220.43
bridges
55.11
Total 275.54
246

27.55
= 303.09
12
Rm
s and culverts
44.09
Total 264.52
26.45
= 290.97
12
Rm
142

Chapter - 12

Foundation
Sl. No. Quantity Description Rate per

15.1. Providing and laying boulders apron on river bed for


protection against scour with stone boulders weighing not
less than 40 Kg each complete as per drawing and
technical specifications

A. Boulder laid dry without wire crates


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.04 Nos Mate 329.00 / Nos
0.35 Nos Mason class I 451.00 / Nos
0.75 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
1.00 Tonne Stone 489.30 / Tonne
0.20 Cum Stone spalls 266.30 / Cum
Total [b]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 952.82
Total [a+b+c+d+e]
f) Contractor's profit 10% on 1191.03
Rate for 1 Cum =
Rate for 1 cum = 1310.13 / 1
Boulder laid without wire crates = 1310.13 / Cum
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 952.82
143

Total [a+b+c+d+e]
f) Contractor's profit 10% on 1143.38
Rate for 1 Cum =
Rate for 1 cum = 1257.72 / 1

Boulder laid without wire crates = 1257.72 / Cum

*-*-*-*-*-*-
144

15.1. Providing and laying apron with Cement Concrete blocks of size
0.50 X 0.50 m cast - in situ and made with nominal size M 1
cement concrete with a minimum cement content of 250 Kg /
per IRC 21-2000

MORT & H Specifitation No: 2503


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 / Nos
1.50 Nos Mason class I 451.00 / Nos
20.00 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 / Cum
4.05 Cum 20 mm ISS metal 1341.30 / Cum
1.35 Cum 10 mm ISS metal 967.30 / Cum
6.75 Cum Sand for mortar 293.06 / Cum
4.13 Tonne Cement 6611.39 / Tonne
Total [b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 / Hour
6.00 Hour Generator 33 KVA 372.00 / Hour
Total [b]
Total [a+b+c]
d) Form work
For excavation for preparation of
bed, nominal surface
2% reinforcement and filling of
55166.11 / 0
granular material

Total [d]
Total [a+b+c+d]
(i) For major bridges and minor bridges
e) Overheads 25% on 56269.43
Total [a+b+c+d+e]
145

f) Contractor's profit 10% on 70336.79


Rate for 15 cum =
Rate for 1 cum = 77370.47 / 15
PCC M 15 C blocks for apron = 5158.03 / cum
146

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 56269.43
Total [a+b+c+d+e]
f) Contractor's profit 10% on 67523.32
Rate for 15 cum =
Rate for 1 cum = 74275.65 / 15
PCC M 15 C blocks for apron = 4951.71 / cum

15.4. Providing and laying pitching on side slopes laid over prepar
media including boulder apron laid dry in front of toe of emba
complete as per drawing and technical specifications.

A. With stone / boulders


MORT & H Specifitation No: 2504
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.04 Nos Mate 329.00 / Nos
0.35 Nos Mason class I 451.00 / Nos
0.75 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
Soling stones for revetment works
1.00 Cum weight not less than 40 Kg 489.30 / Cum

0.20 Cum Stone spallls 266.30 / Cum


Total [b]
Total [a+b]
(i) For major bridges and minor bridges
C) Overheads 25% on 952.82
Total [a+b+c]
d) Contractor's profit 10% on 1191.03
Rate for 1 Cum =
Rate for 1 cum = 1310.13 / 1
147

Pitching side slopes with boulders = 1310.13 / Cum


148

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 952.82
Total [a+b+c+d+e]
f) Contractor's profit 10% on 1143.38
Rate for 1 Cum =
Rate for 1 cum = 1257.72 / 1

Pitching side slopes with boulders = 1257.72 / Cum

B. With CC blocks of size 0.30 X 0.30 X 0.30m

MORT & H Specifitation No: 2504


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 / Nos
1.50 Nos Mason class I 451.00 / Nos
20.00 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 / Cum
4.05 Cum 20 mm ISS metal 1341.30 / Cum
1.35 Cum 10 mm ISS metal 967.30 / Cum
6.75 Cum Sand for mortar 293.06 / Cum
4.13 Tonne Cement 6611.39 / Tonne
Total [b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 / Hour
6.00 Hour Generator 33 KVA 372.00 / Hour
Total [b]
Total [a+b+c]
d) Form work
149

For excavation for nominal


2% surface reinforcement and filling 55166.11 / 0
of granular material

Total [d]
Total [a+b+c+d]
150

(i) For major bridges and minor bridges


e) Overheads 25% on 56269.43
Total [a+b+c+d+e]
f) Contractor's profit 10% on 70336.79
Rate for 15 cum =
Rate for 1 cum = 77370.47 / 15
Pitching side slopes with CC blocks = 5158.03 / cum
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 56269.43
Total [a+b+c+d+e]
f) Contractor's profit 10% on 67523.32
Rate for 15 cum =
Rate for 1 cum = 74275.65 / 15
Pitching side slopes with CC blocks = 4951.71 / cum

15.5. Providing and laying filter material underneath pitching in slopes


complete as per drawing and technical specifications.
MORT & H Specifitation No: 2504
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.05 Nos Mate 329.00 / Nos
1.00 Nos Mazdoor 286.00 / Nos
0.25 Nos Mazdoor -skilled 319.00 / Nos
Total [a]
Coarse sand = 296.11
Fine sand = 293.06
Gravel = 246.95
836.12 /3 = 278.71 / Cum
b) Material:
1.20 Cum Graded materials 278.71 / Cum
Total [b]
Total [a+b]
151

(i) For major bridges and minor bridges


C) Overheads 25% on 716.65
Total [a+b+c]
d) Contractor's profit 10% on 895.81
Rate for 1 Cum =
Filter materials below the side slope = 985.39 / Cum
pitching
(ii) For minor bridges in road packages and culverts
C) Overheads 20% on 716.65
Total [a+b+c+d+e]
d) Contractor's profit 10% on 859.98
Rate for 1 Cum =
Rate for 1 cum = 945.98 / 1
Filter materials below the side slope = 945.98 / Cum
pitching

15.8 Providing and laying flooring laid over concrete flooringcomplete


drawing and technical specifications.
A. Rubble stone laid in cement mortar 1:3
MORT & H Specifitation No: 2505
Unit = Cum
Taking Output = 1 Cum
Cement mortar 1:3
MORT & H Specifitation No:
Unit = Cum
Taking Output = 1 cum
a) Labour :
0.04 Nos Mate 329.00 / Nos
0.90 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
0.51 Tonne Cement 6611.39 / Tonne
152

1.05 Cum Sand for mortar 293.06 / Cum


Total [b]
Total for cement mortar 1:3 = 3979.78 / cum
153

Cement Concrete M 15 nominal mix


MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 329.00 / Nos
1.50 Nos Mason class I 451.00 / Nos
20.00 Nos Mazdoor 319.00 / Nos
Total [a]
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 / Cum
4.05 Cum 20 mm ISS metal 1341.30 / Cum
1.35 Cum 10 mm ISS metal 967.30 / Cum
6.75 Cum Sand for mortar 293.06 / Cum
4.13 Tonne Cement 6611.39 / Tonne
Total [b]
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 / Hour
6.00 Hour Generator 33 KVA 372.00 / Hour
Total [b]
Cost of M 15 nominal mix for 15 cum = a+b+c
M 15 nominal mix for 1 Cum = 55166.11 / 15
= 3677.74 / cum
a) Material:
1.00 Cum stone 489.30 / Cum
0.20 Cum Stone spalls 266.30 / Cum
0.33 Cum Cement mortar 1:3 3979.78 / Cum
Cement concrete M 15 nominal
0.50 Cum mix for bedding
3677.74 / Cum

Total [b]
b) Labour :
0.08 Nos Mate 329.00 / Nos
0.50 Nos Mason class I 451.00 / Nos
1.50 Nos Mazdoor -skilled 319.00 / Nos
154

Total [a]
c) Total [a+b]
on cost of account for excavation,
proper preparation of bed on cost of
1% cement mortar and cement concrete 3152.20
for bedding
155

(i) For major bridges and minor bridges


C) Overheads 25% on 4456.60
Total [a+b+c]
d) Contractor's profit 10% on 5570.75
Rate for 1 Cum =
Rubble stone laid in CM 1:3 = 6127.83 / Cum
(ii) For minor bridges in road packages and culverts
C) Overheads 20% on 4456.60
Total [a+b+c+d+e]
d) Contractor's profit 10% on 5347.92
Rate for 1 Cum =
Rate for 1 cum = 5882.71 / 1
Rubble stone laid in CM 1:3 = 5882.71 / Cum

B. Flooring with cement concrete blocks Grade M 15

MORT & H Specifitation No: 2505


Unit = Cum
Taking Output = 1 Cum
(i) For major bridges and minor bridges
a) Material:
Concrete grade M 15
1.00 Cum [as per item 12.8 (A)
5259.17 / Cum
1.00 Cum Cement concrete bedding 3677.74 / Cum
Total [b]
1% on cost of account for excavation, 8936.91
proper preparation ofRate
bed for 1 Cum =
Flooring with CC blocks Gr. M15 = 9026.28 / Cum
(ii) For minor bridges in road packages and culverts
a) Material:
Concrete grade M 15
1.00 Cum [asper item 12.8 (A)
5048.80 / Cum

1.00 Cum Cement concrete bedding 3677.74 / Cum


156

Total [b]
1% on cost of account for excavation, 8726.54
proper preparation ofRate
bed for 1 Cum =

Flooring with CC blocks Gr. M15 = 8813.81 / Cum


157

15.9. Dry rubble stone flooring

MORT & H Specifitation No: 2505


Unit = Cum
Taking Output = 1 cum
a) Material:
1.00 Cum stone 489.30 / Cum
0.20 Cum Stone spalls 266.30 / Cum
Total [b]
b) Labour :
0.10 Nos Mate 329.00 / Nos
0.50 Nos Mason class I 451.00 / Nos
1.50 Nos Mazdoor -skilled 319.00 / Nos
Total [a]
c) Total [a+b]
For trimming and preparation of base
1% i.e. on labour cost 736.90

(i) For major bridges and minor bridges


C) Overheads 25% on 1286.83
Total [a+b+c]
d) Contractor's profit 10% on 1608.54
Rate for 1 cum =
Dry Rubble stone flooring = 1769.39 / cum
(ii) For minor bridges in road packages and culverts
C) Overheads 20% on 1286.83
Total [a+b+c+d+e]
d) Contractor's profit 10% on 1544.20
Rate for 1 cum =
Rate for 1 cum = 1698.62 / 1

Dry Rubble stone flooring = 1698.62 / cum


158

15.11. Construction of Flexible apron 1 m thick comprising of loos


boulders weighing not less than 40 Kg beyond curtain wall
MORT & H Specifitation No: 2507.2.
Unit = Cum
Taking Output = 1 cum
a) Material:
1.00 Cum stone 489.30 / Cum
0.20 Cum Stone spalls 266.30 / Cum
Total [b]
b) Labour :
0.05 Nos Mate 329.00 / Nos
0.25 Nos Mason class I 451.00 / Nos
1.00 Nos Mazdoor -skilled 319.00 / Nos
Total [a]
c) Total [a+b]
1% For trimming and preparation of bed 990.76

(i) For major bridges and minor bridges


C) Overheads 25% on 1000.67
Total [a+b+c]
d) Contractor's profit 10% on 1250.84
Rate for 1 cum =
Flexible apron = 1375.92 / cum
(ii) For minor bridges in road packages and culverts
C) Overheads 20% on 1000.67
Total [a+b+c+d+e]
d) Contractor's profit 10% on 1200.80
Rate for 1 cum =
Rate for 1 cum = 1320.88 / 1
Flexible apron = 1320.88 / cum
159

16.1. Removal of existing Cement concrete wearing coat includ


disposal complete as per technical specification without caus
detrimental effect to any part of the bridge structure and rem
dismantled material with all lifts and lead upto 1000m

MORT & H Specifitation No: 2809


Unit = Sqm
Taking Output = 10 Sqm
a) Labour :
0.06 Nos Mate 329.00 / Nos
1.00 Nos Mazdoor 319.00 / Nos
Total [a]
b) Machinary
Air compressor with Pneumatic
1.00 Hour breaker / jack hammer along with 319.00 / Hour
accessories
0.50 Hour Tractor trolley 363.00 / Hour
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
e) Overheads 25% on 839.24
Total [a+b+c]
f) Contractor's profit 10% on 1049.05
Rate for 10 Sqm =
Rate for 1 cum = 1153.96 / 10
Removal of CC wearing coat = 115.40 / Sqm

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 839.24
Total [a+b+c+d+e]
f) Contractor's profit 10% on 1007.09
Rate for 10 Sqm =
Rate for 1 cum = 1107.80 / 10
Removal of CC wearing coat = 110.78 / Sqm
160

16.2. Removal of existing asphaltic concrete wearing coat comprisin


mmthick asphaltic concrete laid over 12 mmthick mastic
including disposal with all left and lead upto 1000 m
MORT & H Specifitation No: 2809
Unit = Sqm
Taking Output = 10 Sqm
a) Labour :
0.03 Nos Mate 329.00 / Nos
0.75 Nos Mazdoor 319.00 / Nos
Total [a]
b) Machinary
Air compressor with Pneumatic
0.75 Hour breaker / jack hammer along with 319.00 / Hour
accessories
0.40 Hour Tractor trolley 363.00 / Hour
Total [b]
Total [a+b]
(i) For major bridges and minor bridges
e) Overheads 25% on 633.57
Total [a+b+c]
f) Contractor's profit 10% on 791.96
Rate for 10 Sqm =
Rate for 1 Sqm = 871.16 / 10
Removal of wearing coat with Asphaltic
concrete and mastic asphalt
= 87.12 / Sqm

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 633.57
Total [a+b+c+d+e]
f) Contractor's profit 10% on 760.28
Rate for 10 Sqm =
Rate for 1 Sqm = 836.31 / 10
Removal of wearing coat with Asphaltic
concrete and mastic asphalt
= 83.63 / Sqm
161

STATE DATA
1 Gravel packing to rough stone dry packing for revetments

Unit = Cum
Taking Output = 10 Cum
11.60 Cum Gravel 246.95 / Cum
7.10 Nos Mazdoor skilled 319.00 / Nos
3.50 Nos Mazdoor 286.00 / Nos
Rate for 10 cum =
(i) For major bridges and minor bridges
e) Overheads 25% on 6130.52
Total [a+b+c]
f) Contractor's profit 10% on 7663.15
Rate for 10 Cum =
Rate for 1 cum = 8429.47 / 10

Gravel packing to rough stone dry packing = 842.95 / Cum

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 6130.52
Total
f) Contractor's profit 10% on 7356.62
Rate for 10 Cum =
Rate for 1 cum = 8092.28 / 10

Gravel packing to rough stone dry packing = 809.23 / Cum

2 Granite rough stone dry packing for revetment

Most Specification No:


Unit = Cum
Taking Output = 10 Cum
11.00 Cum Rough stone for revetment 489.30 / Cum
162

3.50 Nos stone packer 292.00 / Nos


10.60 Nos Mazdoor skilled 319.00 / Nos
7.10 Nos Mazdoor 286.00 / Nos
Total
163

(i) For major bridges and minor bridges


e) Overheads 25% on 11816.30
Total [a+b+c]
f) Contractor's profit 10% on 14770.38
Rate for 10 Cum =
Rate for 1 cum = 16247.42 / 10

Granite rough stone dry packing = 1624.74 / Cum

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 11816.30
Total
f) Contractor's profit 10% on 14179.56
Rate for 10 cum =
Rate for 1 cum = 15597.52 / 10

Granite rough stone dry packing = 1559.75 / cum


164

Amount

13.16
157.85
239.25
410.26

489.30
53.26
542.56
952.82

238.21
1191.03
119.10
1310.13

190.56
165

1143.38
114.34
1257.72
166

rete blocks of size 0.50 X


nominal size M 15 grade
ntent of 250 Kg / cum as

282.94
676.50
6380.00
7339.44

8175.33
5432.27
1305.86
1978.16
27305.05
44196.67

1398.00
2232.00
3630.00
55166.11

1103.32

1103.32
56269.43

14067.36
70336.79
167

7033.68
77370.47
168

11253.89
67523.32
6752.33
74275.65

laid over prepared filter


nt of toe of embankment
cations.

13.16
157.85
239.25
410.26

489.30

53.26
542.56
952.82

238.21
1191.03
119.10
1310.13
169

190.56
1143.38
114.34
1257.72

282.94
676.50
6380.00
7339.44

8175.33
5432.27
1305.86
1978.16
27305.05
44196.67

1398.00
2232.00
3630.00
55166.11
170

1103.32

1103.32
56269.43
171

14067.36
70336.79
7033.68
77370.47

11253.89
67523.32
6752.33
74275.65

pitching in slopes
cations.

16.45
286.00
79.75
382.20

334.45
334.45
716.65
172

179.16
895.81
89.58
985.39

143.33
859.98
86.00
945.98

e flooringcomplete as per

13.16
287.10
300.26

3371.81
173

307.71
3679.52
174

282.94
676.50
6380.00
7339.44

8175.33
5432.27
1305.86
1978.16
27305.05
44196.67

1398.00
2232.00
3630.00
55166.11

489.30
53.26
1313.33

1838.87

3694.76

26.32
225.50
478.50
175

730.32
4425.08

31.52

4456.60
176

1114.15
5570.75
557.08
6127.83

891.32
5347.92
534.79
5882.71

15

5259.17
3677.74
8936.91
89.37
9026.28

5048.80

3677.74
177

8726.54
87.27
8813.81
178

489.30
53.26
542.56

32.90
225.50
478.50
736.90
1279.46

7.37

1286.83

321.71
1608.54
160.85
1769.39

257.37
1544.20
154.42
1698.62
179

mprising of loose stone


curtain wall

489.30
53.26
542.56

16.45
112.75
319.00
448.20
990.76
9.91
1000.67

250.17
1250.84
125.08
1375.92

200.13
1200.80
120.08
1320.88
180

aring coat including its


tion without causing any
structure and removal of
1000m

19.74
319.00
338.74

319.00

181.50
500.50
839.24

209.81
1049.05
104.91
1153.96

167.85
1007.09
100.71
1107.80
181

ng coat comprising of 50
mmthick mastic asphalt
00 m

9.87
239.25
249.12

239.25

145.20
384.45
633.57

158.39
791.96
79.20
871.16

126.71
760.28
76.03
836.31
182

2864.62
2264.90
1001.00
6130.52

1532.63
7663.15
766.32
8429.47

1226.10
7356.62
735.66
8092.28

5382.30
183

1022.00
3381.40
2030.60
11816.30
184

2954.08
14770.38
1477.04
16247.42

2363.26
14179.56
1417.96
15597.52
157

Sl. No. Quantity Description Rate per Amount


5.15. SLURRY SEAL:
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and water on a
road surface including cleaning of surface, mixingof slurry seal in a
suitable mobile polant, laying and compacting to provide even riding
surface

Case -I: 5 mm thickness:


MORT & H Specification No: 516
Unit = Sqm
Taking Output = 16000Sqm
Taking density of 2.20 tonne per cum,
Weigt of mix = 176tonnes
a) Labour :
0.24 Nos Mate 329.00 / Nos 78.96
6.00 Nos Mazdoor 286.00 / Nos 1716.00
Total [a] 1794.96
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Mobile slurry seal equipment 1008.00 / Hour 6048.00
6.00 Hour Front end loader 1 cum bucket 806.00 / Hour 4836.00
capa city
6.00 Hour Tipper 5.5 cum capacity for 310.00 / Hour 1860.00
carriage of aggregate from
stockpile on road side to slurry
equipment, bitumen emulsion
and filler

6.00 Hour Pneumatic tyred power ro ller 1243.00 / Hour 7458.00


with individual whee l load not
exceeding 1.5 tonne
6.00 Nos Water tanker 6 KL capacity 310.00 / Nos 1860.00
Total [b] 26118.00
c) Material:
19.36 Tonne Residual binde r at 11% of mix = 43246.00 / Tonne 837242.56
80 X 2.20 X 0.11 = 19.36
tonne

102.08 Cum Fine aggregates 4.75 mm and 663.30 / Cum 67709.66


below [87 % of total mi x = 8 0 x 2 .2 x
0.87 = 1 53 .1 2 to nne taki ng de nsity as
1.5 = 15 3.12 /1.5 = 1 02.08 cu m]

3.52 tonne Filler at 2% of total mix = 80 x 6611.39 / tonne 23272.10


2.2 x 0.02 = 3.52 tonne- cement
12.00 KL Cost of water 150.00 / KL 1800.00
Total [b] 930024.32

Total [a+b+c] 957937.28


d)Overheads 10% on 957937.28 95793.73
Total [a+b+c] 1053731.01
e)Contractor's profit 10% on 1053731.01 105373.10
Rate for 16000Sqm = 1159104.11
Rate for 1 sqm = 1159104.11 / 16000
Slurry seal for 5 mm thickness = 72.44 / Sqm
*/-*/-/*-/*
Case-II: 3 mm thickness:
MORT & H Specification No: 516
Unit = Sqm
Taking Output = 20000Sqm
Taking density of 2.20 tonne per cum,
a) Labour :
0.20 Nos Mate 329.00 / Nos 65.80
5.00 Nos Mazdoor 286.00 / Nos 1430.00
Total [a] 1495.80
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Mobile slurry seal equipment 1008.00 / Hour 6048.00
6.00 Hour Front end loader 1 cum bucket 806.00 / Hour 4836.00
capa city
6.00 Hour Tipper 5.5 cum capacity for 310.00 / Hour 1860.00
carriage of aggregate from
stockpile on road side to slurry
equipment, bitumen emulsion
and filler

6.00 Nos Water tanker 6 KL capacity 310.00 / Nos 1860.00


Total [b] 18660.00
c) Material:
17.16 Tonne Residual binder at 13% of mix = 43246.00 / Tonne 742101.36
60 X 2.20 X 0.13 = 17.16 tonne

74.80 Cum Fine aggregates 3 mm and 663.30 / Cum 49614.84


below {87% of total mi x = 60 x 2.2 x x
0.85 = 112.2 to nne takin g d en sity as
1.5 = 112 .2 /1.5 = 7 4.80 cum]

2.64 tonne Filler at 2% of total mix = 60 x 6611.39 / tonne 17454.07


2.2 x 0.02 = 2.64 tonne

12.00 KL Cost of water 150.00 / KL 1800.00


Total [b] 810970.27

Total [a+b+c] 831126.07


d)Overheads 10% on 831126.07 83112.61
Total [a+b+c] 914238.68
e)Contractor's profit 10% on 914238.68 91423.87
Rate for 20000Sqm = 1005662.55
Rate for 1 sqm = 1005662.55 / 20000
Slurry seal for 3 mm thickness = 50.28 / Sqm

Case - III: 1.5 mm thickness:


MORT & H Specification No: 516
Unit = Sqm
Taking Output = 24000Sqm
Taking density of 2.20 tonne per cum,
a) Labour :
0.20 Nos Mate 329.00 / Nos 65.80
5.00 Nos Mazdoor 286.00 / Nos 1430.00
Total [a] 1495.80
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Mobile slurry seal equipment 1008.00 / Hour 6048.00
6.00 Hour Front end loader 1 cum bucket 806.00 / Hour 4836.00
capa city
6.00 Hour Tipper 5.5 cum capacity for 310.00 / Hour 1860.00
carriage of aggregate from
6.00 Nos Water tanker 6 KL capacity
stockpile on road side to slurry 310.00 / Nos 1860.00
equipment, bitumen emulsion Total [b] 18660.00
and filler
c) Material:
12.67 Tonne Residual binder at 16% of mix = 43246.00 / Tonne 547926.82
36 X 2.20 X 0.16 = 12.67 tonne

43.30 Cum Fine aggregates 2.36 mm and 663.30 / Cum 28720.89


below 8 2% of to tal mix [3 6 x 2.2 x x
0.82 = 64.94 tonn e taki ng den sity as
1.5 = 64 .94 /1.5 = 43 .3 0 cum]

1.58 tonne Filler a t 2 % of total mix 6611.39 / tonne 10446.00


[36 x 2.2 x 0.02 = 1.58 tonne
12.00 KL Cost of water 150.00 / KL 1800.00
Total [b] 588893.71

Total [a+b+c] 609049.51


d)Overheads 10% on 609049.51 60904.95
Total [a+b+c] 669954.46
e)Contractor's profit 10% on 669954.46 66995.45
Rate for 24000Sqm = 736949.91
Rate for 1 sqm = 736949.91 / 24000
Slurry seal for 1.5 mm thickness = 30.71 / Sqm
*/-*/-/*-/*

518. FOG SPRAY:


Providing and applying low viscosity bitumen emulsion for sealing cracks
less than 3 mm wide or incipient fretting or disintegration in an existing
bituminous surfacing

MORT & H Specification No: 516


Unit = Sqm
Taking Output = 10500Sqm
a) Labour :
0.12 Nos Mate 329.00 / Nos 39.48
3.00 Nos Mazdoor 286.00 / Nos 858.00
Total [a] 897.48
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Bitumen emulsion pressure 800.00 / Hour 4800.00
distributor
Total [b] 8856.00
c) Material:
7.88 Tonne Bitumen emulsion at 0.75 Kg per 43246.00 / Tonne 340778.48
sqm
Total [b] 340778.48
Total [a+b+c] 350531.96
d)Overheads 10% on 350531.96 35053.20
Total [a+b+c] 385585.16
e)Contractor's profit 10% on 385585.16 38558.52
Rate for 10500Sqm = 424143.68
Rate for 1 Sqm = 424143.68 / 10500
Fog Spray = 40.39 / Sqm
*/-*/-/*-/*

522. Crack Prevention Courses:


Case - I: Sress absorbing membrane [SAM] crack width less than 6 mm

Providing and laying of a stress absorbing membrane over a cracked


road surface, with crack width below 6 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 9 Kg per 10 sqm and spreading 5.6 mm crushed
stone aggregates at 0.11 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and surface
finished to conform to clause 902.

MORT & H Specification No: 522


Unit = Sqm
Taking Output = 10500Sqm
a) Labour :
0.24 Nos Mate 329.00 / Nos 78.96
6.00 Nos Mazdoor 286.00 / Nos 1716.00
Total [a] 1794.96
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Bitumen pressure distributer 1073.00 / Hour 6438.00
6.00 Hour Hydraulic chip spreader 2635.00 / Hour 15810.00
6.00 Hour Smooth wheeled road roller 8-10 460.00 / Hour 2760.00
tonnes
Total [b] 29064.00
c) Material:
9.45 Tonne Modified binder 0.00 / Tonne 0.00
105.00 Cum Crushed stone aggregate 727.30 / Cum 76366.50
5.6 mm size
Total [b] 76366.50
Total [a+b+c] 107225.46
d)Overheads 10% on 107225.46 10722.55
Total [a+b+c] 117948.01
e)Contractor's profit 10% on 117948.01 11794.80
Rate for 10500Sqm = 129742.81
Rate for 1 Sqm = 129742.81 / 10500
Crack prevension cours e - SAM for less than = 12.36 / Sqm
6 mm crack w idth

*/-*/-/*-/*

Case - II: Sress absorbing membrane [SAM] crack width


6 mm to 9 mm
Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width 6 mm to 9 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 11 Kg per 10 sqm and spreading 11.2 mm crushed
stone aggregates at 0.12 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and surface
finished to conform to clause 902.

MORT & H Specification No: 522


Unit = Sqm
Taking Output = 10500Sqm
a) Labour :
0.24 Nos Mate 329.00 / Nos 78.96
6.00 Nos Mazdoor 286.00 / Nos 1716.00
Total [a] 1794.96
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Bitumen pressure distributer 1073.00 / Hour 6438.00
6.00 Hour Hydraulic chip spreader 2635.00 / Hour 15810.00
6.00 Hour Smooth wheeled road roller 8-10 460.00 / Hour 2760.00
tonnes
Total [b] 29064.00
c) Material:
9.45 Tonne Modified binder 0.00 / Tonne 0.00
105.00 Cum Crushed stone aggregate 924.30 / Cum 97051.50
11.2 mm size
Total [b] 97051.50
Total [a+b+c] 127910.46
d)Overheads 10% on 127910.46 12791.05
Total [a+b+c] 140701.51
e)Contractor's profit 10% on 140701.51 14070.15
Rate for 10500Sqm = 154771.66
Rate for 1 Sqm = 154771.66 / 10500
Crack prevens ion course - SAM for 6 mm to 9 = 14.74 / Sqm
mm crack w idth
*/-*/-/*-/*

Case - III: Sres s absorbing m embrane [SAM] crack width above 9


mm and cracked area above 50 %

Providing and laying of a stress absorbing membrane over a cracked


road surface, with crack width above 9 mm and cracked area above 50 %
after cleaning with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 Kg per 10 sqm and spreading
11.2 mm crushed stone aggregates at 0.12 cum per 10 sqm with
hydraulic chip spreader, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.

MORT & H Specification No: 522


Unit = Sqm
Taking Output = 10500Sqm
a) Labour :
0.24 Nos Mate 329.00 / Nos 78.96
6.00 Nos Mazdoor 286.00 / Nos 1716.00
2.00 Nos Mazdoor skilled 319.00 / Nos 638.00
Total [a] 2432.96
b) Machinary:
6.00 Hour Mechanical broom 357.00 / Hour 2142.00
6.00 Hour Air compressor 250 cfm 319.00 / Hour 1914.00
6.00 Hour Bitumen pressure pressure 1073.00 / Hour 6438.00
distributor at 1 750 sqm per hour
6.00 Hour Hydraulic chip spreader 2635.00 / Hour 15810.00
6.00 Hour Smooth wheeled roller 8-10 460.00 / Hour 2760.00
tonnes
Total [b] 29064.00
c) Material:
`` 15.75 Tonne Modified binder 47124.00 / Tonne 742203.00
126.00 Cum Crushed stone aggregate 924.30 / Cum 116461.80
11.2 mm size

Total [b] 858664.80


Total [a+b+c] 890161.76
d)Overheads 10% on 890161.76 89016.18
Total [a+b+c] 979177.94
e)Contractor's profit 10% on 979177.94 97917.79
Rate for 10500Sqm = 1077095.73
Rate for 1 Sqm = 1077095.73 / 10500
Crack prevension course - SAM for crack = 102.58 / Sqm
width above 9 mm and above 50 %

*/-*/-/*-/*

8.1. Cast - in - situ Cement Concrete M 20 Kerb:


Construction of cement concrete kerb with top and bottom width 115 and
165 mm respecively, 250 mm high in M 20 grade PCC on M 10 grade
foundation 150 mm thick, foundation having 50 mm projection beyond
kerb stone, kerb stone laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 408.

MORT & H Specification No: 408


Unit = Rm
Taking Output = 360Rm
a) Labour :
0.72 Nos Mate 329.00 / Nos 236.88
2.00 Nos Mason 451.00 / Nos 902.00
16.00 Nos Mazdoor 319.00 / Nos 5104.00
Total [a] 6242.88
b) Machinary:
6.00 Hour Kerb casting machine at 310.00 / Hour 1860.00
60 metre / hour
158

12.00 Hour Concrete mixer 0.48 / 0.28 cum 233.00 / Hour 2796.00
capa city
5.00 Hour Water tanker 6 KL capacity 310.00 / Hour 1550.00
Total [b] 6206.00
c) Material:
21.79 Cum Crushed stone aggregate 20 1341.30 / Cum 29226.93
mm nominal size 59%

10.90 Cum Coarse sand 30 % 293.06 / Cum 3194.35

5.70 tonne Cement 6611.39 / tonne 37684.93

30.00 KL Cost of wateer 150.00 / KL 4500.00


Total [b] 74606.21
Total [a+b+c] 87055.09
c)Overheads 10% on 87055.09 8705.51
Total [a+b+c] 95760.60
d)Contractor's profit 10% on 95760.60 9576.06
Rate for 360Rm = 105336.66
Rate for 1 Sqm = 105336.66 / 360
Cast - in - situ kerb with M 20 concrete = 292.60 / Rm

*/-*/-/*-/*
Providing and laying open graded premix carpet of 20 mm thick on
prepared surface in a single course as wearing course composed of
specified size of stone aggregates premix with a bituminous binder in
mini hot mix plant 6-10 tonne laying manually and rolling with power roller
8-10 tonne but excluding cost of primer / tack coat

MORT & H Specification No: 509


Unit = Sqm
Taking Output = 500Sqm
a) Labour :
1.35 Nos Mate 329.00 / Nos 444.15
21.00 Nos Mazdoor 286.00 / Nos 6006.00
6.00 Nos Hot mazdoor / bucketman for 371.00 / Nos 2226.00
bitume n
Total [a] 8676.15
b) Machinary:
4.00 Hour Mini hot mix plant - 6/10 tonne 1965.00 / Hour 7860.00
3.00 Hour Bitumen boiler oil fired 1500 lit 198.00 / Hour 594.00
capa city out put 250 Kg / hour
6.00 Hour Power roller 8-10 tonnes 460.00 / Hour 2760.00
Total [b] 11214.00
c) Miscellaneous items:
5% Sundries such as mainta nance 11214.00 560.70
and control of diversion, sign
boards, night w atchman, control
of traffic and for quality control

L.S. Miscellaneous items such as L.S. 25.00


tarring outfits, bournal, coconut
oil, soap and wheel barrow s, etc.

Total [c] 585.70


d) Materials:
9.00 Cum Crushed stone aggregate 1285.30 / Cum 11567.70
13.2 mm size
4.50 Cum Crushed stone aggregate 924.30 / Cum 4159.35
11.2 mm size
0.73 tonne Bitumen 60/70 gr.at site 39921.00 / tonne 29142.33
Total [d] 44869.38
Total [a+b+c+d] 65345.23
c)Overheads 10% on 65345.23 6534.52
Total [a+b+c] 71879.75
d)Contractor's profit 10% on 71879.75 7187.98
Rate for 500Sqm = 79067.73
Rate for 1 Sqm = 79067.73 / 500
PC 20 mm thick = 158.14 / Sqm
*/-*/-/*-/*
8.9. Painting two coats on new concrete surfaces
Painting two coats after filling the surface with synthetic enamel paint in
all shades on new plastered concrete surfaces
MORT & H Specification No: 803
Unit = Sqm
Taking Output = 40Sqm
a) Labour :
0.12 Nos Mate 329.00 / Nos 39.48
2.00 Nos Painter 361.00 / Nos 722.00
1.00 Nos Mazdoor 319.00 / Nos 319.00
Total [a] 1080.48
d) Materials:
6.00 Litre Paint conforming to requirement 275.00 / Litre 1650.00
of clause 803.3
Total [b] 1650.00
Rate for 40 Sqm 2730.48
Rate for 1 Sqm = 2730.48 / 40
Painting the conc rete surface w ithout = 68.26 / Sqm
overhead and contractor's profit
*/-*/-/*-/*

8.3 Printing new letters and figures of any shade:


Printing new letters and figures of any shade with synthetic enamel paint
black or any other approved colour to give an even shade
MORT & H Specification No: 801
Unit = per cm height per letter
Taking Output = 1600per cm height per letter
a) Labour :
0.07 Nos Mate 329.00 / Nos 23.03
1.25 Nos Painter 361.00 / Nos 451.25
0.50 Nos Mazdoor 319.00 / Nos 159.50
Total [a] 633.78
d) Materials:
0.50 Litre Paint conforming to requirement 275.00 / Litre 137.50
of clause 803.3
Total [b] 137.50
Rate for 1600per cm height per letter 771.28
Rate for 1 Sqm = 771.28 / 1600
Printing letters without ov erhead and = 0.48 / per cm height per
contractor's profit letter
*/-*/-/*-/*
M 15 Grade of concrete
Unit = Cum
Taking Output = 15cum
a) Labour :
0.86 Nos Mate 329.00 / Nos 282.94
1.50 Nos Mason class I 451.00 / Nos 676.50
20.00 Nos Mazdoor 319.00 / Nos 6380.00
Total [a] 7339.44
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 / Cum 8175.33
4.05 Cum 20 mm ISS metal 1341.30 / Cum 5432.27
1.35 Cum 10 mm ISS metal 967.30 / Cum 1305.86
6.75 Cum Sand for mortar 293.06 / Cum 1978.16
4.13 Tonne Cement 6611.39 / Tonne 27305.05
Total [b] 44196.67
Total [a+b] 51536.11
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 / Hour 1398.00
6.00 Hour Generator 33 KVA 372.00 / Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 55166.11

d) Form work
On cost of materials, labhour and
4.00% 55166.11 / 0 2206.64
machinary
Total [d] 2206.64
Total [a+b+c+d] 57372.75
Rate for 1 cum = 57372.75 / 15
Rate for PCC M 15 conc rete without overhead =
and c ontractor's profit 3824.85 / Cum
Rate for earthwork for foundation for Km stones
Unit = = Cum
Taking Output = = 10cum
A. Manual Means:
(i)Depth upto 3 m :
a) Labour :
0.14 Nos Mate 329.00 / Nos 46.06
3.50 Nos Mazdoor 319.00 / Nos 1116.50
Total [a] 1162.56
Rate for 10cum = 1162.56
Rate for 1 cum = 1162.56 / 10
Earth Work for foundation in ordinary
soil without overhead and contractor's = 116.26 / cum
profit

8.14 KILOMETRE STONE


Reinforced cement concrete M 15 grade kilometer stone of standard
design as per IRC:8-1980, fixing in position including painting and
printing, etc.

I) 5 th KM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 6Nos.
2.35 Cum M 15 grade concrete 3824.85 / Cum 8988.40
22.08 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 989.53
1.68 Cum Excavation in soil for foundation 116.26 / Cum 195.32
9.85 Sqm Painting two coats on concrete 68.26 / Sqm 672.36
surface
1800 per cm Lettering on Km post [average 0.48 / per cm 864.00
per letter 30 le tte rs o f 10 cm height each] per letter

Total [a] 11709.61

Transportation and fixing


Labour

0.26 Nos Mate 329.00 / Nos 85.54


0.60 Nos Mason 451.00 / Nos 270.60
Mazdo or including loading and
6.00 Nos unloading
319.00 / Nos 1914.00
Machinary Total [b] 2270.14
6.00 hours Tractor trolley 363.00 / hours 2178.00
Total [c] 2178.00
Total [a+b+c] 16157.75
c)Overheads 10% on 16157.75 1615.78
Total [a+b+c] 17773.53
d)Contractor's profit 10% on 17773.53 1777.35
Rate for 6Nos. = 19550.88
Rate for 1 No. = 19550.88 / 6
5th Km stone including painting and lettering = 3258.48 / Nos.
and fixing at site

II)Ordinary KM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 14Nos.
3.77 Cum M 15 grade concrete 3824.85 / Cum 14419.68
26.32 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 1179.55
2.77 Cum Excavation in soil for foundation 116.26 / Cum 322.04
11.41 Sqm Painting two coats on concrete 68.26 / Sqm 778.85
surface
1680 per cm Lettering on Km post [average 0.48 / per cm 806.40
per letter 30 le tte rs o f 10 cm height each] per letter

Total [a] 17506.52


Transportation and fixing
Labour
0.32 Nos Mate 329.00 / Nos 105.28
1.00 Nos Mason 451.00 / Nos 451.00
Mazdo or including loading and
7.00 Nos 319.00 / Nos 2233.00
unloading
Machinary Total [b] 2789.28
6.00 hours Tractor trolley 363.00 / hours 2178.00
Total [c] 2178.00

Total [a+b+c] 22473.80


c)Overheads 10% on 22473.80 2247.38
Total [a+b+c] 24721.18
d)Contractor's profit 10% on 24721.18 2472.12
Rate for 14Nos. = 27193.30
Rate for 1 No. = 27193.30 / 14
Ordinary Km stone including painting and = 1942.38 / Nos.
lettering and fixing at site

III)HM stone
MORT & H Specification No: 804
Unit = Nos.
Taking Output = 33Nos.
1.58 Cum M 15 grade concrete 3824.85 / Cum 6043.26
66.00 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 2957.83
1.39 Cum Excavation in soil for foundation 116.26 / Cum 161.60
6.27 Sqm Painting two coats on concrete 68.26 / Sqm 427.99
surface
330 per cm Lettering on Km post [average 0.48 / per cm 158.40
per letter 30 le tte rs o f 10 cm height each] per letter

Total [a] 9749.08


Transportation and fixing
Labour
0.34 Nos Mate 329.00 / Nos 111.86
1.50 Nos Mason 451.00 / Nos 676.50
Mazdoor including loadin g and
7.00 Nos unloading
319.00 / Nos 2233.00
Machinary Total [b] 3021.36
6.00 hours Tractor trolley 363.00 / hours 2178.00
Total [c] 2178.00
Total [a+b+c] 14948.44
c)Overheads 10% on 14948.44 1494.84
Total [a+b+c] 16443.28
d)Contractor's profit 10% on 16443.28 1644.33
Rate for 33Nos. = 18087.61
Rate for 1 No. = 18087.61 / 33
HM stone including painting, lettering and = 548.11 / Nos.
fixing at site

8.16. Boundary Pillar


MORT & H Specification No: 806
Unit = Nos.
Taking Output = 57Nos.
1.25 Cum M 15 grade concrete 3824.85 / Cum 4781.06
79.80 Kg Steel reinforcement at 5Kg/sqm 44815.56 / Kg 3576.28
10.72 Cum Excavation in soil for foundation 116.26 / Cum 1246.31
11.97 Cum Stone spalls 266.30 / Cum 3187.61
2280 per cm Lettering on Km post [average 0.48 / per cm 1094.40
per letter 30 le tte rs o f 10 cm height each] per letter

Total [a] 13885.66


Transportation and fixing
Labour

0.57 Nos Mate 329.00 / Nos 187.53


14.25 Nos Mazdoor 319.00 / Nos 4545.75
Machinary Total [b] 4733.28
6.00 hours Tractor trolley 363.00 / hours 2178.00
Total [c] 2178.00
Total [a+b+c] 20796.94
c)Overheads 10% on 20796.94 2079.69
Total [a+b+c] 22876.63
d)Contractor's profit 10% on 22876.63 2287.66
Rate for 57Nos. = 25164.29
Rate for 1 No. = 25164.29 / 57
HM stone including painting, lettering and = 441.48 / Nos.
fixing at site

9.1. PCC 1:3:6 in foundation for pipe culverts


Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days.
MORT & H Specifitation No: 408
Unit = Cum
Taking Output = 15cum
a) Labour :
0.64 Nos Mate 329.00 / Nos 210.56
1.00 Nos Mason class I 451.00 / Nos 451.00
15.00 Nos Mazdoor 319.00 / Nos 4785.00
Total [a] 5446.56

b) Material:
13.80 Cum 40 mm ISS metal 1009.30 / Cum 13928.34
6.90 Cum Sand for mortar 293.06 / Cum 2022.11
2.97 Tonne Cement(3.3-10 % of 3.3) 6611.39 / Tonne 19635.83
18.00 KL Cost of water 150.00 / KL 2700.00
Total [b] 38286.28
Total [a+b] 43732.84
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 / Hour 1398.00
6.00 Hour Generator 33 KVA 372.00 / Hour 2232.00
3.00 Hour Water tanker 310.00 / Hour 930.00
Total [b] 4560.00
Total [a+b+c] 48292.84
C)Overheads 10% on 48292.84 4829.28
Total [a+b+c] 53122.12
159

C)Contractor's profit 10% on 53122.12 5312.21


Rate for 15cum = 58434.33
Rate for 1 cum = 58434.33 / 15

PCC 1:3:6 for foundation for pipe culverts 3895.62 / cum

9.2. Laying RCC pipe NP4 concrete pipe on first class bedding in single row
Laying RCC pipe NP4 for culverts on first class bedding of granular
materialin single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets.

MORT & H Specifitation No: 2900


Unit = Rm
Taking Output = 12.5Rm
a) Labour :
0.18 Nos Mate 329.00 / Nos 59.22
0.50 Nos Mason class I 451.00 / Nos 225.50
4.00 Nos Mazdoor 319.00 / Nos 1276.00
Total [a] 1560.72
b) Material:
0.07 Cum Sand for mortar 293.06 / Cum 20.51
0.05 tonne Cement 6611.39 / tonne 330.57
Granular material passing
0.00 Cum 5.6mm sieve for bedding
246.95 / Cum 0.00
Total [b] 351.08

Total [a+b+c] 1911.80


C)Overheads 10% on 1911.80 191.18
Total [a+b+c] 2102.98
C)Contractor's profit 10% on 2102.98 210.30
Rate for 12.5Rm = 2313.28
Rate for 1 cum = 2313.28 / 12.5

Fixing of 1000 mm dia NP-4 pipes in single row = 185.06 / Rm

Supply of NP4 RCC pipes = 2750.00 / Rm

9.2. Laying RCC pipe NP4 concrete pipe on first class bedding in two rows
Laying RCC pipe NP4 for culverts on first class bedding of granular
material in two rows including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets.

MORT & H Specifitation No: 2900


Unit = Rm
Taking Output = 12.5Rm
a) Labour :
0.36 Nos Mate 329.00 / Nos 118.44
1.00 Nos Mason class I 451.00 / Nos 451.00
8.00 Nos Mazdoor 319.00 / Nos 2552.00
Total [a] 3121.44
b) Material:
0.14 Cum Sand for mortar 293.06 / Cum 41.03
0.10 tonne Cement 6611.39 / tonne 661.14
Granular material passing
9.00 Cum 5.6mm sieve for bedding
0.00 / Cum 0.00

Total [b] 702.17


Total [a+b+c] 3823.61
C)Overheads 10% on 3823.61 382.36
Total [a+b+c] 4205.97
C)Contractor's profit 10% on 4205.97 420.60
Rate for 12.5Rm = 4626.57
Rate for 1 cum = 4626.57 / 12.5

Fixing of 1000 mm dia NP-4 pipes in two rows = 370.13 / Rm


174

COMMON DATA - 2015-2016 (Bitumen & Emulsion rate as on 01.09.2015)

Circle: MADURAI Division: Madurai

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
1 Earthwork for foundation in ordinary soil: 304
A. By mechanical means
i) Depth up to 3 m excluding 159.85 / Cum 153.46 / Cum
dewatering
ii) Depth up to 3 m including 175.84 / Cum 168.80 / Cum
dewatering
iii) Depth 3 m to 6 m including 236.35 / Cum 226.90 / Cum
dewatering
Depth 3 m to 6 m including 236.35 / Cum 226.90 / Cum
dewatering
iv) Depth above 6 m including 328.84 / Cum 315.69 / Cum
dewatering
B. By Mechanical means
i) Depth upto 3 m including 62.98 / Cum 60.46 / Cum
dewatering
ii) Depth 3 to 6 m including 73.69 / Cum 70.74 / Cum
dewatering
iii) Depth above 6 m including 93.55 / Cum 89.81 / Cum
dewatering
2 Earthwork for foundation in ordinary rock 304
not requiring blasting
A. Manual means
i) Depth upto 3 m excluding 228.36 / Cum 219.23 / Cum
dewatering
B. Mechanical means:

i) Depth upto 3 m excluding 74.90 / Cum 71.90 / Cum


dewatering and not requiring
blasting

ii) Depth upto 3 m excluding 532.25 / Cum 510.96 / Cum


dewatering and requiring blasting

3 Sand filling-304 624.69 / Cum 599.70 / Cum

377659397.xlsxabstract
175

4 PCC 1:3:6 for foundation-2100 4451.49 / Cum 4273.43 / Cum


using 40mm metal

5 Cement mortar 1:3 without 3979.78 / Cum


contractor profit and overheads
6 Brickwork in CM 1:3 for 6308.41 / Cum 6056.07 / Cum
foundation-1300
7 Stone masonry in CM 1:3 for 4271.35 / Cum 4100.50 / Cum
foundation-1405.4

8 Random rubble masonry in C. M 4251.37 / Cum 4081.31 / Cum


1:3(coursed/uncoursed)-1405.3

9 PCC M 15 for foundation using 5259.17 / Cum 5048.80 / Cum


concrete mixer-1500,1700&2100

10 PCC M 20 for foundation using 5945.69 / Cum 5707.86 / Cum


concrete mixer
11 PCC M 25 for foundation

a. Using concrete mixer 6453.27 / Cum 6195.14 / Cum


b. Using batching plant 5950.60 / Cum 5712.58 / Cum
12 PCC M 30 for foundation
a. Using concrete mixer 6494.18 / Cum 6234.41 / Cum
b. Using batching plant 5987.23 / Cum 5747.74 / Cum
13 RCC M 20 for foundation
a. Using concrete mixer 6051.85 / Cum 5809.77 / Cum
b. Using batching plant 5544.02 / Cum 5322.26 / Cum
14 RCC M 25 for foundation

a. Using concrete mixer 6565.47 / Cum 6302.85 / Cum

b. Using batching plant 6058.86 / Cum 5816.51 / Cum

15 RCC M 30 for foundation


a. Using concrete mixer 6581.01 / Cum 6317.77 / Cum
b. Using batching plant 6077.20 / Cum 5834.11 / Cum
16 RCC M 35 for foundation
a. Using concrete mixer 6692.79 / Cum 6425.08 / Cum
b. Using batching plant 6191.41 / Cum 5943.75 / Cum

377659397.xlsxabstract
176

17 Cast in situ 750 mm dia pipein RCC M 35 grade


a. Using concrete mixer 6659.50 / Cum 6393.12 / Cum

Using batching plant 6609.90 / Cum 6345.51 / Cum


18 Cast in situ 1000 mm dia pipein RCC M 35 grade

a. Using concrete mixer 10983.97 / Cum 10544.62 / Cum


Using batching plant 10912.81 / Cum 10476.30 / Cum
19 Cast in situ 1200 mm dia pipein RCC M 35 grade
a. Using concrete mixer 14032.24 / Cum 13470.95 / Cum

b. Using batching plant 13929.80 / Cum 13372.61 / Cum


20 Pile load test
21 Initial load test 300.00 / MT
22 Latreral load test 5000.00 / MT
23 Pile cap in RCC M 20
a. Using concrete mixer 6026.79 / Cum 5785.71 / Cum
b. Using batching plant 5539.91 / Cum 5318.32 / Cum
24 Pile cap in RCC M 25
a. Using concrete mixer 6575.14 / Cum 6312.13 / Cum
b. Using batching plant 6088.26 / Cum 5844.73 / Cum
25 Pile cap in RCC M 30
a. Using concrete mixer 6644.47 / Cum 6378.69 / Cum
b. Using batching plant 6157.59 / Cum 5911.29 / Cum
26 Pile cap in RCC M 35
a. Using concrete mixer 6789.43 / Cum 6517.85 / Cum
b. Using batching plant 6302.56 / Cum 6050.45 / Cum
27 Levelling course below pile cap 5056.89 / Cum 4854.62 / Cum
using concrete mixer
28 HYSD reinforcement for piles 68848.37 / MT 66094.44 / MT
29 MS reinforcement for piles 69200.88 / MT 66432.84 / MT
30 Brickwork in CM 1:3 1300&2200 6238.28 / Cum 5988.75 / Cum

31 Pointing Brickwork in CM 1:3- 71.16 / Sqm 68.32 / Sqm


1300&2200

377659397.xlsxabstract
177

32 Plastering in CM 1:3-1300&2200 133.55 / Sqm 128.21 / Sqm

33 RR masonry in CM 1:3 4215.09 / Cum 4046.48 / Cum


(coursed/uncoursed) 1400&2200

34 CR masonry in CM 1:3( first sort ) 4343.02 / Cum 4169.30 / Cum


1400&2200
35 PCC M 15 for substructure
1500,1700&2200
a. Height upto 5m 5562.58 / Cum 5340.08 / Cum
b. Height 5m to 10 m 5663.72 / Cum 5437.17 / Cum
36 PCC M 20 for substructure using concrete mixer

a. Height upto 5m 6288.71 / Cum 6037.16 / Cum


b. Height 5m to 10 m 6517.39 / Cum 6256.69 / Cum
37 PCC M 25 for substructure using concrete mixer

a. Height upto 5m 6842.02 / Cum 6568.34 / Cum

b. Height 5m to 10 m 7090.83 / Cum 6807.19 / Cum

38 PCC M 25 for substructure using batching plant

a. Height upto 5m 6309.07 / Cum 6056.71 / Cum


b. Height 5m to 10 m 6538.49 / Cum 6276.95 / Cum
39 PCC M 30 for substructure using concrete mixer

a. Height upto 5m 6902.02 / Cum 6625.94 / Cum


b. Height 5m to 10 m 7153.01 / Cum 6866.89 / Cum

40 PCC M 30 for substructure using batching plant

a. Height upto 5m 6363.24 / Cum 6108.71 / Cum


b. Height 5m to 10 m 6594.63 / Cum 6330.84 / Cum
41 RCC M 20 for substructure using concrete mixer

a. Height upto 5m 6340.99 / Cum 6087.35 / Cum


b. Height 5m to 10 m 6571.58 / Cum 6308.71 / Cum
42 RCC M 20 for substructure using batching plant

377659397.xlsxabstract
178

a. Height upto 5m 5863.87 / Cum 5629.32 / Cum


b. Height 5m to 10 m 6077.10 / Cum 5834.02 / Cum
43 RCC M 25 for substructure using concrete mixer

a. Height upto 5m 6960.98 / Cum 6682.54 / Cum


b. Height 5m to 10 m 7188.79 / Cum 6901.24 / Cum
44 RCC M 25 for substructure using batching plant

a. Height upto 5m 6423.86 / Cum 6166.90 / Cum


b. Height 5m to 10 m 6634.09 / Cum 6368.73 / Cum
45 RCC M 30 for substructure using concrete mixer

a. Height upto 5m 6994.31 / Cum 6714.54 / Cum


b. Height 5m to 10 m 7191.42 / Cum 6903.76 / Cum
46 RCC M 30 for substructure using batching plant
a. Height upto 5m 6458.86 / Cum 6200.50 / Cum
b. Height 5m to 10 m 6640.88 / Cum 6375.24 / Cum
47 RCC M 35 for substructure using concrete mixer

a. Height upto 5m 7147.64 / Cum 6861.73 / Cum


b. Height 5m to 10 m 7303.59 / Cum 7011.44 / Cum
48 RCC M 35 for substructure using batching plant

a. Height upto 5m 6612.18 / Cum 6347.70 / Cum

b. Height 5m to 10 m 6756.45 / Cum 6486.19 / Cum


49 HYSD bar reinforcement for sub 69040.54 / MT 66278.92 / MT
structure 1600&2200
50 MS bar reinforcement for sub 68335.52 / MT 65602.10 / MT
structure 1600&2200
51 Weep holes with 100mm dia AC 127.83 / Nos. 122.72 / Nos.
pipe 2706&2200
52 Back filling behind abutment, wing 782.58 / Cum 751.28 / Cum
and return walls (Granular
materials-710.1.4 of
IRC78&MORT&H 2200)

377659397.xlsxabstract
179

53 Filter media behind abutment, 796.04 / Cum 764.20 / Cum


wing and return walls(Granular
materials satisfying requirements
laid down in 2504.2.2 of
MORT&H-710.1.4 of
IRC78&MORT&H 2200)

54 RC C M 20 Solid Slab Superstructure using concrete


mixer 1500,1600&1700
a. For height upto 5 m 6917.45 / Cum 6640.75 / Cum
b. For height 5 - 10 m 7205.67 / Cum 6917.45 / Cum
55 RC C M 20 T beam & slab Superstructure using
concrete mixer 1500,1600&1700
a. For height upto 5 m 7205.67 / Cum 6917.45 / Cum
b. For height 5 - 10 m 7493.90 / Cum 7194.14 / Cum
56 RC C M 20 Solid Slab Superstructure using batching
plant 1500,1600&1700
a. For height upto 5 m 6329.68 / Cum 6076.49 / Cum
b. For height 5 - 10 m 6593.42 / Cum 6329.68 / Cum
57 RC C M 20 T beam & slab Superstructure using
batching plant 1500,1600&1700
a. For height upto 5 m 6593.42 / Cum 6329.68 / Cum

b. For height 5 - 10 m 6857.15 / Cum 6582.87 / Cum

58 RC C M 25 solid slab Superstructure using concrete


mixer 1500,1600&1700
a. For height upto 5 m 7550.16 / Cum 7248.15 / Cum

b. For height 5 - 10 m 7864.75 / Cum 7550.16 / Cum

59 RC C M 25 T beam & slab Superstructure using


concrete mixer1500,1600&1700
a. For height upto 5 m 7864.75 / Cum 7550.16 / Cum
b. For height 5 - 10 m 8179.34 / Cum 7852.16 / Cum
60 RC C M 25 solid slab Superstructure using batching
plant1500,1600&1700
a. For height upto 5 m 6969.56 / Cum 6690.78 / Cum
b. For height 5 - 10 m 7259.96 / Cum 6969.56 / Cum
61 RC C M 25 T beam & slab Superstructure using
batching plant 1500,1600&1700
a. For height upto 5 m 7259.96 / Cum 6969.56 / Cum

377659397.xlsxabstract
180

b. For height 5 - 10 m 7550.36 / Cum 7248.34 / Cum


62 RC C M 30 solid slab Superstructure using concrete
mixer1500,1600&1700
a. For height upto 5 m 7666.69 / Cum 7360.02 / Cum
b. For height 5 - 10 m 7986.14 / Cum 7666.69 / Cum
63 RC C M30 T beam & slab Superstructure using
concrete mixer1500,1600&1700
a. For height upto 5 m 7986.14 / Cum 7666.69 / Cum
b. For height 5 - 10 m 8305.58 / Cum 7973.36 / Cum
64 RC C M 30 solid slab Superstructure using
batchingplant1500,1600&1700
a. For height upto 5 m 7052.10 / Cum 6770.02 / Cum

b. For height 5 - 10 m 7345.94 / Cum 7052.10 / Cum

65 RC C M 30 T beam & slab Superstructure using


batching plant 1500,1600&1700
a. For height upto 5 m 7345.94 / Cum 7052.10 / Cum
b. For height 5 - 10 m 7639.78 / Cum 7334.18 / Cum
66 RC C M 35 solid slab Superstructure using concrete
mixer1500,1600&1700
a. For height upto 5 m 7703.39 / Cum 7395.26 / Cum

b. For height 5 - 10 m 8029.81 / Cum 7708.62 / Cum

67 RC C M35 T beam & slab Superstructure using


concrete mixer1500,1600&1700
a. For height upto 5 m 8029.81 / Cum 7708.62 / Cum
b. For height 5 - 10 m 8356.22 / Cum 8021.98 / Cum
68 RC C M 35 solid slab Superstructure using
batchingplant1500,1600&1700
a. For height upto 5 m 7097.56 / Cum 6813.66 / Cum
b. For height 5 - 10 m 7398.31 / Cum 7102.37 / Cum
69 RCC M 35 T-Beam and slab Superstructure using
batching plant1500,1600&1700
a. For height upto 5 m 7398.31 / Cum 7102.37 / Cum
b. For height 5 - 10 m 7699.05 / Cum 7391.09 / Cum
70 HYSD bar reinforcement for 70347.62 / MT 67533.71 / MT
superstructure1600
CONFIRMING TO IS 1786

377659397.xlsxabstract
181

71 MS bar reinforcement for 68335.52 / MT 65602.10 / MT


superstructure1600
72 CC Wearing coat in M 30 6454.70 / cum 6196.52 / cum
Concrete using concrete mixer-
2702 (excluding reinforcement)
73 Wearing coat in Mastic Asphalt 271.61 / Sqm 260.74 / Sqm
12mm thick-515&2702 (60/70
grade bitumen)
74 RCC M 30 Railing cast in casting 1389.08 / Rm
yard 1500,1600,1700&2703

75 RCC M 30 Railing cast in 1828.35 / Rm 1755.22 / Rm


situ1500,1600,1700&2703
76 Drainage spout 2705 372.09 / Each 357.20 / Each
77 PCC M 15 Levelling course 5056.89 / Cum 4854.62 / Cum
below approach slab-2700
using concrete mixer
78 RCC M 30 approach slab using 10032.84 / Cum 9631.52 / Cum
concrete mixer including
reinforcement1500,1600,1700&27
04
79 Copper plate expansion joint 1076.01 / Rm 1032.97 / Rm
12mm thick(2605)
80 20 mm thick fibre board 256.87 / Rm 246.60 / Rm
expansion joint-2605
81 20 mm thick premoulded joint 310.06 / Rm 297.66 / Rm
filler-2605
82 Joint sealing compound 1 cm 25.26 / Rm 24.25 / Rm
depth-2605
83 Boulder without wire crates-2503 1310.13 / cum 1257.72 / cum

84 PCC M 15 for CC blocks for 5158.03 / cum 4951.71 / cum


apron (0.5x0.5x0.5m)-2503
85 Pitching side slopes with 1310.13 / cum 1257.72 / cum
stone/boulders over filter media-
2504
86 Pitching side slopes with CC 5158.03 / cum 4951.71 / cum
blocks over filter media-2504-
(0.3x0.3x0.3m)
87 Filter materials below side slope 985.39 / cum 945.98 / cum
pitching -2504
88 Rubble stone laid in CM 1:3 over 6127.83 / cum 5882.71 / cum
cc bedding-2505

377659397.xlsxabstract
182

89 Flooring with CC blocks M 15 9026.28 / cum 8813.81 / cum


over cc bedding-2505
90 Dry rubble stone Flooring-2506 1769.39 / cum 1698.62 / cum

91 Flexible apron 1 m thick Dry 1375.92 / cum 1320.88 / cum


rubble stone Flooring -2507.2
92 Dismantling CC wearing course- 115.40 / sqm 110.78 / sqm
2809
93 Dismantling AC wearing course- 87.12 / sqm 83.63 / sqm
2809
94 Gravel packing to rough stone dry 842.95 / cum 809.23 / cum
packing
95 Rough stone dry packing for 1624.74 / cum 1559.75 / cum
revetment
96 Slurry seal for 5 mm thickness- 72.44 / Sqm
516
97 Slurry seal for 3 mm thickness- 50.28 / Sqm
516
98 Slurry seal for 1.5 mm thickness- 30.71 / Sqm
516
99 Fog spray-518 40.39 / Sqm

100 Crack prevention course SAM for 12.36 / Sqm


less than 6 mm crack-522
101 Crack prevention course SAM for 14.74 / Sqm
6 mm to 9 mmcrack-522
102 Crack prevention course SAM for 102.58 / Sqm
more than 9 mm crack-522
103 Cement Kerb M 20 using 292.60 / Rm
concrete mixer-408
104 20 mm thick PC using mini hot 158.14 / Sqm
mix plant -511-60/70 grade
bitumen
105 5th KM stone including painting, 3258.48 / each
lettering and fixing-804

106 KM stone including painting, 1942.38 / each


lettering and fixing-804

107 HM stone including painting, 548.11 / each


lettering and fixing-804

377659397.xlsxabstract
183

108 Boundary pillar including lettering 441.48 / each


and fixing but excluding painting-
806-IRC 25-1967

109 Pipe culverts:


a. Foundation in CC 1:3:6-408 3895.62 / cum

b. Supply of NP4 1000 mm RCC 2750.00 / Rm


pipes confirming to IS 458&
cluase 1010 MORT&H

c. Fixing of NP4 1000 mm single 185.06 / Rm


row RCC pipes specification 2900

d. Fixing of NP4 1000 mm two row 370.13 / Rm


RCC pipes specification 2900

377659397.xlsxabstract

You might also like