for
Version 3.0
Table of Contents
1 Purpose of Document..............................................................................................................1
2 Project Scope...........................................................................................................................1
3 Systems Engineering Process..................................................................................................2
3.1 Systems Engineering Process Overview.........................................................................2
3.2 Concept of Operations.....................................................................................................3
3.3 System Requirements......................................................................................................3
3.4 Design..............................................................................................................................4
3.5 Systems Analysis and Control.........................................................................................6
3.5.1 Risk Management Plan............................................................................................6
3.5.2 Configuration Management Plan...........................................................................11
3.5.3 Verification and Validation Plan:...........................................................................14
3.5.4 Technical Reviews.................................................................................................16
3.5.5 Requirements Traceability.....................................................................................17
4 Applicable Documents...........................................................................................................18
Appendix: 14817 Compliance Related Tables – Preliminary........................................................19
Revision History
Filename Version Date Author Comment
ii
TMDD MS/ETMCC V3 SEMP
1 Purpose of Document
This document is a description of the system engineering plan that will be used for the
development of the Traffic Management Data Dictionary (TMDD MS/ETMCC) Version 3.0.
The Systems Engineering Management Plan (SEMP) is the top-level plan for managing the
systems engineering effort. The SEMP defines how the systems engineering portion of the
project will be organized, structured and conducted and how the total engineering process will be
controlled to provide a product that fulfills customer requirements. The SEMP will be used in
technical management of the project. The SEMP outline included in INCOSE SE Handbook,
Version 2a, Appendix C was used as a guide for the development of this SEMP. The format and
content of the SEMP has been tailored to fit the project.
2 Project Scope
The development of TMDD MS/ETMCC V3 will update the current version to incorporate
feedback received from deployments, address additional areas of scope and address issues
unresolved from the earlier version. Specifically the development will address the lessons
learned from a number of deployments (TRANSCOM, TxDOT, FDOT, CARS). The standard
will be extended to include data elements and message sets from the Clarus initiative and the
Archived Data User Service (ADUS) standards effort. In addition, the effort will update the data
dictionary meta data to conform to the ISO 14817 standard (which replaced the IEEE 1488 and
1489 standards that have now been withdrawn). Finally, the effort will address the unresolved
issues from the earlier versions.
1. Correct the deficiencies from Version 2.1 as identified in the Mitretek comments
(includes a complete verification and validation effort on all needs, requirements and
design elements in the document).
2. Correct the deficiencies from Version 2.1 as identified in the Generic Reference Model
(GRM) comments.
3. Assess needs, requirements and design element inputs as requested by the Clarus
Initiative and add those needs, requirements and design elements in a manner consistent
with the Systems Engineering Process (SEP).
4. Assess needs, requirements and design element inputs from the CARS states and add
those needs, requirements and design elements selected in a manner consistent with the
SEP.
5. Assess needs, requirements and design element inputs from ADUS and add those needs,
requirements and design elements selected in a manner consistent with the SEP.
6. Assess issues and integrate lessons learned from current deployments, specifically CARS,
TRANSCOM, FDOT and TXDOT into the TMDD MS/ETMCC Concept of Operations
(ConOps), requirements and design.
7. Use an SEP to ensure the completeness and correctness of TMDD MS/ETMCC V3
documents. The standard must be traceable and logically consistent.
8. Develop TMDD MS/ETMCC V3 conformant to ISO 14817.
9. Develop a TMDD MS/ETMCC V3 WSDL/SOAP specific model.
1
TMDD MS/ETMCC V3 SEMP
10. Develop a detailed conformance statement that addresses backwards compatibility and
provides clear and unambiguous instruction on how to extend the standard.
11. Participation in meetings by the chairman and/or a consultant of the following standard
areas shall be effected: ATIS, TCIP, IM, NTCIP Center-to-Center, ADUS. A
representative from the Clarus Initiative will be asked to attend meetings.
12. Provide a publication-ready TMDD MS/ETMCC V3 standard that fulfills objectives 1-11
above within 23 months from authorization to proceed (ATP) by the Federal Highway
Administration’s (FHWA) Contracts Office.
Due to the nature of this development effort, there is no software coding or hardware fabrication
involved in the final outputs. Nor is there testing per se. The effort will focus on concept of
operations (defined by user needs), system requirements (primarily functional requirements), and
design (both aspects of high level and detailed design). The following sections focus on the
process for performing the system engineering steps that are a part of this project.
2
TMDD MS/ETMCC V3 SEMP
ANSI/AIAA-G-043 Outline
1. Scope
2. Referenced Documents
3. User-Oriented Operational Description
4. Operational Needs
5. System Overview
6. Operational Environment
7. Support Environment
8. Operational Scenarios
Figure 2: Industry Standard Concept of Operations Outline
The new concept of operations section will reorganize and revise (particularly in the area of user
needs) the material in the referenced sections of TMDD V2. The new concept of operations
section will contain subsections per the above outline except for Referenced Document, System
Overview, and Operational Scenarios. The primary source of user needs update will be a User
Needs Workshop which is planned early in the development effort. The focus of the workshop
will be to gather needs (and associated requirements/ design inputs) from the following groups:
Archived Data User Service (ADUS) standards effort
Clarus Initiative
Deployers of TMDD V2 (e.g CARS, TRANSCOM, TxDOT, and FDOT)
Each group presenting at the workshop has been asked to identify, within the current hierarchy of
user needs, additional or modified needs.
Following the workshop, the full set of user needs (existing plus revisions from the workshop)
will be entered into the Rational RequisitePro requirements traceability tool as a beginning to the
overall tracing of needs to requirements to design (discussed in Section 3.5.5).
3
TMDD MS/ETMCC V3 SEMP
needs, this effort will build upon the requirements developed in V2. The current version of the
standard has requirements hierarchically organized in “Section 4.3 Features”. The plan for
version 3 development is to improve the representation of the current requirements, specifically
to ensure that each requirement is uniquely numbered (to support traceability). The requirements
will be augmented, modified as needed to address the new areas supported by V3 as well as the
lessons learned from deployments. These new/ modified requirements will be initially collected
at the User Needs Workshop described above, augmented by additional written inputs from
deployers. The full set of requirements will be entered into the Rational RequisitePro
requirements traceability tool in order to perform requirements traceability as discussed in
Section 3.5.5.
The process of requirements development will identify that these requirements are complete and
correct. This will make use of the Needs to Requirements Traceability Matrix (NRTM), which is
discussed in more detail in Section 3.5.5. For each requirement (either the existing ones or
newly defined ones) the following criteria will be reviewed:
1. Is it a “good” requirement? Some of the attributes of “good” requirements are:
Necessary (see bullet 2)
Clear (unambiguous)
Complete (see bullet 3)
Measurable (quantifiable)
Consistent (with each other)
Achievable (feasible)
Testable
Technology independent
2. Is the requirement mapped to one or more user needs? This will also address
whether the requirement is in fact needed.
3. Does the requirement satisfy the intent and all key items of the need?
3.4 Design
In the context of TMDD MS/EMTCC development, design is the definition of dialogs, messages,
data frames, and data elements. V2 has a set of messages, data frames and data elements
(together known as data concepts) defined. The general approach for updating of an existing
data concept is through the comment resolution process (See section 3.5.3). Newly defined
requirements, however, may develop into new or updated data concepts. The process for defining
new data concepts is to identify what information exchange is required to satisfy some new user
need. For example, a user need such as “Provide New Device Status Information” may result in
new requirements, which could in turn result in new dialogs and messages. To meet the new
requirements, existing data frames and data elements might be re-used (i.e., they already defined
and form parts of existing messages). However, if necessary, new data elements and data frames
(defining a new re-usable portion) can be created.
The TMDD V2 Annexes will be used as the source of the baseline of the TMDD V3 data
concepts. The Annexes contain messages, data frame, and data element definitions of the
TMDD.
4
TMDD MS/ETMCC V3 SEMP
Backwards Compatibility
One of the objectives of the project is to “develop a detailed conformance statement that
addresses backwards compatibility and provides clear and unambiguous instruction on how to
extend the standard”. To develop the conformance statement this effort will build upon work
done by the NTCIP committee. Their efforts will form a starting point for a definition of
backwards compatibility to be used in the development of TMDD V3. There are distinct
differences between TMDD, which is a center to center information standard, and NTCIP
standards, which are primarily center to field device standards, so the work done by NTCIP will
need to be revised and presented to the TMDD committee for discussion and approval. This
aspect of design will develop a general definition of backward compatibility as related to TMDD
and then provide a detailed set of “guidelines” on how this applies to specific message/ data.
For the TMDD to be used in conjunction with the application profile standards, the 14817 data
concepts will be defined in an application profile-specific manner. These outputs are listed
below:
5
TMDD MS/ETMCC V3 SEMP
Therefore the TMDD V3 shall provide description of data concepts in ASN.1 for compatibility
with AP-DATEX, and in XML Schema (for Data Elements, Data Frames, and Messages), and
WSDL (for Dialogs).
In defining the WSDL dialogs for TMDD V3 the dialog structure laid out by the AP-C2CXML
shall be used. AP-C2CXML supports the following dialog (or messaging) patterns:
One-way. A concept intended for bulk data transfer, this messaging concept relies on
request of an XML file by its name.
Request-Response. This message pattern supports the sending of a TMDD messages
followed be a response. This is a typical synchronous pattern of communications.
Subscription-Publication. This message pattern supports a subscriber application
performing an initial request-response to set up future asynchronous responses from an
information publisher application.
The specific risks associated with the TMDD MS/ETMCC V3 development and plan for dealing
with these risks are defined below. The current update of the SEMP at midproject will highlight
some of the risks that have been encountered and update the mitigation efforts taken or underway
to deal with these risks.
Risk area #1: Don’t get correct or complete inputs at the Needs Assessment Workshop.
The development process, as described in the Project Management Plan identifies a Needs
Assessment Workshop, occurring early in the development process, as the primary venue for
6
TMDD MS/ETMCC V3 SEMP
obtaining new needs/ requirements from the Archived Data standards effort and from the Clarus
Initiative. This meeting will also be the primary input of lessons learned from deployments such
as CARS. The assumption in the project development cycle is that complete and correct inputs
will be obtained from all sources, enabling the development team to proceed with concept of
operations and requirements updates. What if this assumption is not correct-e.g. key
stakeholders do not provide inputs, or provide incomplete inputs. Or what if the effort does not
solicit input from all of the “right” players. This is a risk area that will need to be evaluated and
monitored. .
Risk area #2- New needs (or requirements) come in late in the process
What happens if new needs (or more likely new requirements) are identified after the “final”
needs or requirements have been developed (which is scheduled to occur in January 2007 for the
needs and in April 2007 for requirements)? This risk is raised in importance for this
development effort, because we do not plan on “deferring” any significant areas of the standard
to an ensuing development cycle.
Risk area #3- Scheduled review times are short (or over holiday periods) so we don’t get
adequate reviews
In order to maintain the overall schedule of developing the standard, the amount of time allotted
for review prior to each technical review has been set at 10 working days in most cases. In one
case (review of the second draft of the concept of operations) this review period falls during the
end of year holiday season. The risk that is identified is that key people will not give the
material an adequate review, resulting in a lack of consensus.
Risk area #4 – The user needs and requirements workshop provides an overwhelming collection
of new material which exceeds the available project budget.
It is possible that input obtained during the workshop and from comments received from
deployers will identify additional user needs and requirements that far exceed the concept of
modifications and updates to the TMDD V2 that was included in the project budget and work
plan. Note that this does not include new material we expect to receive for the CLARUS and
ADUS content. Example: There are many agencies who want to see significantly more detailed
information exchanged about a device to support microscopic device monitoring and
management. So for example, the “need” may be identified to add messages to deal with traffic
controller timing plan details, intersection configuration details, message logs, sign fonts, etc.
This need in turn creates the requirement to add C2C messages for significantly more of the
NTCIP data elements than expected. Such significant additions could take weeks of additional
effort when you include the ConOps, requirements, SRS, and finally the dialogs and messages –
plus all of the committee discussions and review comments.
Risk area #5 – the results of the workshop and the preliminary development of the ConOps and
requirements show that there are many changes requested that could “break” backward
compatibility.
There are many existing deployments which are using or attempting to use the messages shown
in V2, and this project has the goal of maintaining backward compatibility or dealing with the
consequences. Addressing the inputs from some deployers (e.g. problems they have encountered)
7
TMDD MS/ETMCC V3 SEMP
might cause changes that would impact backwards compatibility for other deployers. The risk is
that the development may not be able to satisfy both cases (changes requested by one developer
vs. backward compatibility for another).
Risk area #6 - Creating standards outputs that are ISO 14817 conformant.
TMDD is the first ITS standard to commit to create outputs that are ISO 14817 conformant and it
may be harder to do than expected. The risk is that some aspects of ISO 14817 might be difficult
to create or that they may be difficult to use with the tool set planned for the development.
Risks that may affect the project will fall into three general categories:
Technical (risks affecting the completeness or correctness of the resulting standard)
Schedule (risks that cause schedule slippage)
Cost (risks that cause cost to exceed budget)
8
TMDD MS/ETMCC V3 SEMP
Given these three dimensions, the risk areas for the project can be analyzed and prioritized. This
is summarized in Table 1.
Table 2: Summary of Risk Analysis and Prioritization
Risk Area Category Magnitude Likelihood Priority
Risk area #1: Don’t get correct or Technical Medium Medium 1
complete inputs at the Needs
Assessment Workshop
Risk area #2- New needs (or Technical, Medium Low 2
requirements) come in late in the Schedule,
process and Cost
Risk area #3- Scheduled review times Technical Small Low 3
are short (or over holiday periods) so
we don’t get adequate reviews
Risk area #4 – Large amount of new Technical, Medium Medium 1
requirements exceed project Schedule,
expectations. and cost
Risk area #5 – Backward compatibility Technical, Medium Low 2
problems are encountered with Schedule,
deployments. and cost
Risk area #6 – Creating standards Technical, Low Medium 2
outputs that are ISO 14817 conformant
Risk area #1: Don’t get correct or complete inputs at the Needs Assessment Workshop represents
a primarily technical risk that new needs or requirements will not be captured early enough in the
development process. The magnitude of the impact is judged to be medium since missed needs
or requirements could result in errors in the standard that would require committee rework at a
later date. The likelihood is judged to be medium since some key participants in the process
(deployers) will not be funded to attend the needs assessment workshop, and may not choose to
attend. From a prioritization standpoint this is judged to be the highest priority risk and one that
will be closely monitored.
Risk area #2- New needs (or requirements) come in late in the process represents a primarily a
technical risk, but does have cost and schedule components if the new requirements require
additional iteration through of parts of the process. The magnitude of this risk is also judged to
be medium, due to potential to impact schedule or cost. The likelihood is considered low,
because of some of the risk mitigation features built into the project plan (see discussion below).
From a prioritization standpoint this is judged to be the second highest risk and one that will be
closely monitored. Update at mid project- this risk did occur an have an impact on both
schedule and budget. Our original plan called for development of user needs (in the Concept of
Operations), then requirements, and then design. The expectation was that some minor edits to
needs would occur after the “final Concept of Operations deliverable” and that some minor edits
would occur after the delivery of the final Functional Requirements deliverable; however the
magnitude of the changes to these aspects of the program, months after we have completed the
final Task 2 documents has been considerable. We continue to get requests to review and rewrite
portions of the user needs. As we continue the design we are also seeing significant rewrites of
9
TMDD MS/ETMCC V3 SEMP
the functional requirements sections. It is clear that sufficient review of these outputs was not
accomplished as we delivered the initial outputs and we still have to expend considerable time
and hours working these sections of the standard. As a lesson learned for future, it seems likely
that all standards efforts will have the same issue- the committee just isn’t used to viewing the
standard from a needs standpoint and project plans should expect considerable rewrite later in the
process.
Risk area #3- Scheduled review times are short (or over holiday periods) so we don’t get
adequate reviews is primarily a technical risk. The magnitude of the risk is judged to be small,
since there are multiple reviews and the impact from any one review is diluted. The likelihood is
small as well, given the planned approach to technical reviews discussed below. From a
prioritization standpoint this is judged to be lowest of the identified risks, but it will be
monitored during the development. Update at mid project- the issue of adequate review has
occurred and had an impact on both schedule and cost. The amount and scope of comments we
continue to get on the Concept of Operations and functional requirements indicate that the initial
reviews were not adequate. The observation (in hindsight) is that the TMDD committee
members, who are drawn from the deployment community, don’t resonate to needs/ requirements
like they do to design, and we find over and over again that the real needs/ requirements are not
defined until the details of design are debated.
Risk Area 4 - Large amount of new requirements exceeds project expectations. This is primarily
a technical risk and has been a long standing issue of discussion within the TMDD program in
the past. The distinction between the high level device abstraction and how to handle off-hours
operation has been an issue which was previously dealt with. However, since some of the early
deployers have used C2C communications for detailed device management, this is likely to
become an issue again; hence, the likelihood is medium that this will occur depending on the
participants at the workshop. If it does occur, it is likely to affect the schedule and budget as the
additional dialogs and message sets are developed to support these requirements. Update at mid
project- this risk has occurred and has had an impact on schedule and budget. The scope of the
requirements document has grown considerably since the beginning of the program, with over
1100 requirements now defined. In addition, the team has undergone a complete rewrite of these
requirements to achieve a consistent style and to fully define the “optional” aspects of the
requirements. One of the risk mitigations we put in place was to use an automated requirement
tracking tool, Requisite Pro, to manage the requirements and their traceability. Unfortunately the
team had a difficult time getting the committee to agree to the final form of the requirements and
the wholesale rewrite of the requirements forced the development team to delay putting
information into the traceability tool (which requires reentry of the requirements each time they
are “reorganized” or rewritten in any significant way). The tool will ultimately provide a very
good measure of assurance that the trace is complete and correct, but the effort to populate the
tool and make the initial mapping has proven to be far greater than anticipated. Finally, the
extent of new requirements has far exceeded our original project specifications. This is partly
due to the ambiguity in the scope of the project relating to fixing “deficiencies” in the standard.
The committee has defined a number of areas that represent new capabilities for TMDD (e.g.
passing routes, second-by-second traffic signal control information, and turning movements). As
10
TMDD MS/ETMCC V3 SEMP
we have proceeded to design, the effort required to address these new areas (requirements and
design) has grown considerably.
Risk area #5 – the results of the workshop and the preliminary development of the ConOps and
requirements show that there are many changes requested that could “break” backward
compatibility. There are many existing deployments which are using or attempting to use the
messages shown in V2, and we need to identify a mechanism for maintaining backward
compatibility or dealing with the consequences. The likelihood that this will occur is medium.
The impact should be low as one mechanism available to solve the issues is to keep the old
messages and simply add new messages to meet the updated needs and approaches.
Risk area #6 - Creating standards outputs that are ISO 14817 conformant. This is primarily a
technical risk, although it could impact schedule or cost if not handled properly. Given a good
mitigation plan the impact of this risk should be low. Based upon the initial review of ISO
14817 requirements (see section 3.5.3.1) the likelihood of occurrence is judged to be medium.
Risk area #3- Scheduled review times are short (or over holiday periods) so we don’t get
adequate reviews
The three primary mitigations to this risk area are
1. Invite the full set of affected stakeholders to each technical review. So if one reviewer
does not get a full review, there will be others who do.
2. Hold many of the technical reviews via webcast or similar so physical presence isn’t
required. This will increase attendance at the reviews, particularly by those parties who
aren’t directly funded to attend meetings.
11
TMDD MS/ETMCC V3 SEMP
3. Hold real technical walkthroughs that cover the changes page by page- allowing detailed
comments to be made and recorded on the spot.
Updated mitigation at mid project- Subgroups have been identified for 7 key areas of the
standard. These small groups of experts in the particular area will perform a detailed review of
the sections of the standard relating to their expertise and will engage in several telecons with the
development team to identify and resolve issues relating to the subgroups area of expertise. As
part of this effort the subgroups will closely review the requirements as well as the design.
Risk area #6 - Creating standards outputs that are ISO 14817 conformant.
The primary mitigation for this risk is to develop an example set of ISO 14817 conformant
outputs early in Phase 2 of the effort, so that any issues relating to this risk can be identified early
and resolved. Subtask 2.3.1 has been created to create these example outputs. Examples of
interface dialog, message, data frame, and data element will be created.
12
TMDD MS/ETMCC V3 SEMP
This plan for configuration management of the TMDD MS/ETMCC V3 development effort
identifies an initial set of outputs that will form the baseline and discusses the planned process
for managing the configuration of the baseline outputs.
All of the documentation created on the project will employ a document numbering scheme that
contains document name, version (if applicable), and date of document creation.
13
TMDD MS/ETMCC V3 SEMP
A comments database will be maintained to track comments and resolution status, as well as to
define the resolution itself and impact on the TMDD V3 (specifically, tracing to any ConOps,
Requirements, and Data Concepts requiring a change).
Key fields from the Comments Tracking and Resolution table are shown below.
ITE receives comment(s) and assigns a comment ID. Commenters are expected to
provide comments using a standardized comment form.
Comment is forwarded to developers.
Comments Database is updated to log comment.
Developer proposes resolution and identifies what standards items that will be changed.
Comments and Resolution Authority (Steering Committee) provides approval of
resolution. (Note that some comments will be presented to the TMDD MS/ETMCC
Steering Committee for approval at meetings, while others will be circulated
electronically and discussed and approved via teleconference)
TMDD V3 is updated.
14
TMDD MS/ETMCC V3 SEMP
Once all comments have been disposed the TMDD is ready for general public release.
When all comments are resolved the comments database will be added to the version of the
TMDD for which the standard applies (see next section).
Comments will be a rolling database to track all comments throughout the life of the TMDD V3.
15
TMDD MS/ETMCC V3 SEMP
The Requirements-Message Set Data Concepts traceability table will verify that requirements
trace to a “data concept” of the TMDD: data element, data frame, message, or interface dialog.
This table, called the Requirements Traceability Matrix (RTM) will be created from the Rational
RequisitePro traceability tool. The table will map from requirements to dialogs and messages.
The typical dialog is in the form of a request mesage/ response message. Due to the nature of the
requirements some of the requirements will map to the request message of the dialog and some
will map to the response message of the dialog. The table will then be extended (or possibly
done as a second table) to show the mapping of requirements to data frames/ elements. This
latter mapping will address the mapping of subrequirements to the portions of a message
satisfying each requirement. The verification and validation of this mapping will follow a
similar two step process as given above:
1. The contractor team will create the RTM and perform the initial check that all
requirements are satisfied by design elements.
2. Stakeholders will review and comment on the mapping of requirements to design
elements to ensure that all the requirements are completely covered by the design.
In this way, the RTM will be used to verify and validate that the message set solution satisfies
one or more information exchange requirements.
Section C.3 of the 14817 standard states that a data dictionary need only contain definitional
information related to the following data concepts: data elements, data frames, messages, and
interface dialogues. Tables A.1 through A.4 in the appendix of this document (organized by data
concept type) shows the list of 14817 meta attributes that apply to a data concept and whether
they are mandatory or optional. Two additional columns have been added: the first indicates
whether the MiniEdit tool (version 2.0.410) supports the attribute, and the second column shows
whether the meta attribute will be maintained for TMDD V3.
16
TMDD MS/ETMCC V3 SEMP
There are two additional issues related to ISO 14817 compliance that will have to be addressed
in the development effort. ISO 14817 does not state how to relax the mandatory attribute in the
case of no ISO authority able to assign on ASN Object Identifier (OID) or acting as a data
registry. So to fully comply, ITE will need to obtain an ISO node to grant ASN OIDs.
ISO 14817 also does not state how to relax the mandatory attribute in the case of no established
data registry. This relates to the ISO 14817 requirement that import and export of data elements
(i.e., reference to a data element) shall be to a data registry. At present there is no data registry to
which this could apply.
17
TMDD MS/ETMCC V3 SEMP
The following provides a discussion of the process that is anticipated for conducting the
technical walkthroughs.
Since TMDD MS/ETMCC V3 is an update to TMDD V2.1, at each step along the development
path it is possible to define the changes that have occurred from the previous version. The plan
for each walkthrough is to go through the portion of the standard being reviewed (e.g. concept of
operations) page by page, discussing the changes and soliciting comments on the proposed
changes. Each technical review will have a draft review output made available two weeks prior
to the meeting for review by the TMDD MS/ETMCC Steering Committee and other interested
parties. Comments received prior to the walkthroughs and comments received at the
walkthroughs will be entered into the comment database. As a part of each walkthrough the
changes to the comment database (new comments and resolutions to old comments) will be
reviewed with the walkthrough attendees.
To perform this traceability we will use the Rational RequisitePro software tool to automate the
process.
Two types of traceability will be managed throughout the development process: 1) Concept of
Operations to Requirements traceability, called a Needs to Requirements traceability, and 2)
Requirements to Design traceability, called a Requirements Traceability.
18
TMDD MS/ETMCC V3 SEMP
will be developed based on the information put into the tool. Key fields from the NRTM are
shown below.
The Project Use section will be a topic of discussion with the Steering Committee. Should it
continue as in the current version (where it defines a universal vs project specific requirement) or
should it be replaced by an actual conformance indication – e.g. mandatory vs optional). The
same goes for the Additional Project Requirements/ Comments column. This might continue as
in V2, or be modified to contain comments, possibly relating to conformance.
Throughout the project these tables will be updated at each step in the process.
4 Applicable Documents
The following documents are referenced in this system engineering management plan:
ITE/ AASHTO Standards for Traffic Management Center to Center Communications, Version
2.1, June 1, 2005
19
TMDD MS/ETMCC V3 SEMP
20
TMDD MS/ETMCC V3 SEMP
21
TMDD MS/ETMCC V3 SEMP
22
TMDD MS/ETMCC V3 SEMP
23
TMDD MS/ETMCC V3 SEMP
24