Professional Documents
Culture Documents
OF
VOLUME I
Submitted to
HIMALAYAN INFTASTRUCTURE FUND PVT. LTD.
Prepared by
Feedback Infrastructure Services Nepal Limited
UM-IHP 1
October, 2016
Feasibility Study Report
REPORT CONTENTS
UM-IHP 1
Feasibility Study Report
Abbreviation
ºC Degree Centigrade
AC Alternating Current
ACB Air Circuit Breaker
ACSR Aluminium Conductor Steel Reinforced
amsl Above Mean Sea Level
AVR Automatic Voltage Regulator
B/C Ratio Benefit Cost Ratio
BM Bench Mark
BOD Biological Oxygen Demand
BoQ Bill of Quantities
CB Circuit Breaker
Cm Centimeter
COD Chemical Oxygen Demand
cumecs Cubic Meter per Second
cusecs Cubic Feet per Second
D/L Distribution Line
D/S Downstream
DC Direct Current
DDC District Development Committee
DF Discount Factor
DHM Department of Hydrology and Meteorology
DHQ District Headquarter
Dwg. No. Drawing Number
EDM Electronic Distance Meter
EIA Environmental Impact Assessment
FDC Flow Duration Curve
FISNL Feedback Infrastructure Services Nepal Limited
FSR Feasibility Study Report
Fig Figure
FY Fiscal Year
GLOF Glacier Lake Outburst Flood
GoN Government of Nepal
GW Gigawatt
UM-IHP 2
Feasibility Study Report
UM-IHP 3
Feasibility Study Report
UM-IHP 4
Feasibility Study Report
EXECUTIVE SUMMARY
OF
UPPER MYAGDI-IHYDROPOWER PROJECT
Project lies in the left bank of the Myagdi River. Headworks site is located about 80m
downstream from confluence of Mudi and Myagdi River. Powerhouse is proposed just
upstream of the confluence between Marng and Myagdi River.Myagdi River is a snow-
fed river originating from the high mountains.
Proposed headworks site of Upper Myagdi-IHydropower Project lies at longitude 83º 21'
25" E and latitude 28º 30’ 54 N, at an elevation of 1355amsl. It is about
80mdownstream from the confluence with Mudi River. Catchment area of Myagdi River
at the proposed intake site is 665 km2.Proposed powerhouse site of Upper Myagdi
RiverHydropower Project lies at longitude 83º 22’ 57” E and latitude 28º 27' 40" N, at
an elevation of 1160m and located just upstream the confluence of Marang and
MyagdiRiver. Total catchment area at proposed powerhouse site is 768 km2.
Design discharge of the project at 40% exceedance flow has been found to be 33.6
m3/s. Design of the diversion weir and the headworks has been carried out considering
for 100 years return period flood discharge of 1453 m3/s.
UM-IHP 5
Feasibility Study Report
28km long single circuit 132kV Transmission line is required to to evacuate power from
project’s powerhouse up to proposed Dana Substation.
Total annual energy generation from the plant is 323.88GWh. However, the annual
energy available for sale excluding outage, station consumption and transmission
losses, totalling 5% comes out to be 307.68 GWh. Out of which 261.46GWh is the wet
energy and 46.22 GWh is the dry energy.
Cost estimate of Upper Myagdi-I Hydropower Project has been carried out based on
2016price level. Major cost components are divided into Land and support, Pre-
operating expenses, infra-structure works, main civil works, hydro-mechanical works
and electromechanical works & transmission line works. Cost of value added tax and
contingencies have also been considered in the cost estimate. Total construction cost of
the project without interest during construction as of 2016 is estimated at NRs. 8,108
Million.
Financial cost of the project includes taxes, duties, and price contingency during
construction and interest during construction. Based on the assumed disbursement of
the cash flow, the total financial cost of the project is estimated at NRs. 9,331 million.
The specific cost of the project by the end of construction comes out to be NRs. 174 .42
million (US$ 1.63 million) per MW.
Financial analysis of the project is carried out to assess the financial viability of the
project. PPA is expected to follow the prevailing practice in Nepal i.e. NRs. 8.40/kWh in
the dry season) and NRs. 4.80/kWh in wet season with annual escalation of 3% for five
times from the commercial operation date.
UM-IHP 6
Feasibility Study Report
Internal rate of return of the project (without IDC) worksout to be 16.78%. Likewise,
benefit cost ratio is 1.62 and NPV is NRs. 2,514 million. The average debt service
coverage ratio is 1.82 as summarised below.
UM-IHP 7
Feasibility Study Report
1.0 General
UM-IHP 8
Feasibility Study Report
Location : Underground
Type : Double bay intermittant flushing
No of Basin : 2
Size (L x W x H) : 120 m x 7.50 m x 11.5 m
Particle Size to be settled : 0.2 mm
Type : Simple
Diameter : 6.50 m
Height : 55 m
Normal Water level : 1359amsl
7.0 Penstock
8.0 Powerhouse
Location : Surface
Clear Size : 30 m x 16 m x 20 m (L x B x H)
Number of Units : 2 Nos.
Type of Turbine : Francis
Rated Capacity : 26.75 MW x 2 Nos.
UM-IHP 9
Feasibility Study Report
12.0 Generator
Generator - Type : Synchronous, salient pole
- Specification : 31760KVA, 11000 V, 50 Hz
- Synchronous Speed : 428.5rpm
- No. of Pole : 14
UM-IHP 10
Feasibility Study Report
Table of Contents
UM-IHP 11
Feasibility Study Report
UM-IHP 12
Feasibility Study Report
UM-IHP 13
Feasibility Study Report
UM-IHP 14
Feasibility Study Report
UM-IHP 15
Feasibility Study Report
List of Tables
UM-IHP 16
Feasibility Study Report
UM-IHP 17
Feasibility Study Report
List of Figures
FIGURE 2.1: PHYSIOGRAPHY OF THE NEPAL HIMALAYA (AFTER DAHAL AND HASEGAWA,
2008) AND LOCATION OF THE UMIHP SITE ................................................................. 23
FIGURE 2.2: CLIMATOLOGICAL MAP OF NEPAL AND LOCATION OF PROJECT AREA ........... 24
FIGURE 4.1: CATCHMENT OF MYAGDI RIVER AT HEADWORKS ....................................... 38
FIGURE 4.2: LONG TERM MEAN MONTHLY FLOW COMPARISON ..................................... 40
FIGURE4.3: ADOPTED MONTHLY FLOWS FOR UMIHP .................................................... 43
FIGURE 4.4: FLOW DURATION CURVE ........................................................................ 45
FIGURE 4.5: COMPARISON OF FLOOD FLOWS AT HEADWORKS ..................................... 48
FIGURE 4.6: COMPARISON OF FLOOD FLOWS AT POWERHOUSE/TAILRACE SITE ............. 50
FIGURE 4.7: RATING CURVE FOR HEADWORKS SITE .................................................... 51
FIGURE 4.8: RATING CURVE FOR TAILRACE SITE ......................................................... 51
FIGURE 4.9: RESULT OF PARTICLE SIZE DISTRIBUTION ............................................... 55
FIGURE 4.10: AVERAGE MINERAL CONTENT IN SEDIMENT ............................................ 56
FIGURE 5.1: GEOLOGICAL MAP OF THE NEPAL HIMALAYA (AFTER UPRETI AND LE FORT,
1999) ..................................................................................................................... 60
FIGURE 5.2: GEOLOGICAL MAP OF THE PROJECT AREA. (DEPARTMENT OF MINES &
GEOLOGY) ............................................................................................................... 62
FIGURE 5.3: CONTOUR DENSITY DIAGRAM OF INLET PORTAL SITE. ............................... 65
FIGURE 5.4: STEREOGRAPHIC PROJECTION OF MAIN JOINT AT INLET PORTAL SITE. ....... 66
FIGURE 5.5: ROSETTE DIAGRAM SHOWING TUNNEL ALIGNMENT .................................. 69
FIGURE 5.6: CONTOUR DENSITY DIAGRAM (HEADRACE TUNNEL). ................................. 70
FIGURE 5.7: STEREOGRAPHIC PROJECTION OF DISCONTINUITIES (HEADRACE TUNNEL) . 71
FIGURE 5.8: STEREOGRAPHIC PROJECTION OF DISCONTINUITIES (SURGE TANK AREA) .. 72
FIGURE 5.9: NGI Q-SYSTEM FROM BARTON AND GRIMSTAD 1993 ................................. 75
FIGURE 5.10: EARTHQUAKE EPICENTER MAP OF NEPAL (DMG, 2006) ............................. 80
FIGURE 5.11: ACTIVE FAULTS OF NEPAL HIMALAYAS (ADOPTED AFTER UPRETI 2009) ..... 83
FIGURE 5.12: SEISMIC HAZARD MAP OF NEPAL ........................................................... 86
FIGURE 5.13: SEISMIC RISK MAP OF NEPAL ................................................................ 87
FIGURE 5.14: SEISMIC RISK MAP OF INDIA ................................................................ 88
FIGURE 8.1: OPTIMIZATION OF HEADRACE TUNNEL CONCRETE LINED ......................... 108
FIGURE 8.2: GENERAL LAYOUT OF HEADWORKS AREA ............................................... 114
FIGURE 8.3: OPTIMIZATION OF STEEL LINED PENSTOCK ............................................ 116
FIGURE 8.4: GENERAL LAYOUT OF POWERHOUSE AREA ............................................. 117
FIGURE 8.5: TURBINE SELECTION CHART ................................................................. 118
FIGURE 8.6: TURBINE GENERATOR ARRANGEMENT .................................................... 123
FIGURE 8.7: SPIRAL CASE AND DRAFT TUBE DIMENSION ........................................... 125
FIGURE 8.8: DISTRIBUTOR DIMENSION.................................................................... 125
FIGURE 9.1: MONTHLY ENERGY (GWH) ..................................................................... 155
FIGURE 10.1: CONDUCTOR OPTIMIZATION ............................................................... 164
FIGURE 10.2: RELATIONS USED FOR CONDUCTOR OPTIMIZATION .............................. 165
FIGURE 10.2: TRANSMISSION LINE ROUTE OPTION ................................................... 167
UM-IHP 18
Feasibility Study Report
Chapter 1- Introduction
UM-IHP 19
Feasibility Study Report
1.1 Background
Nepal is in a phase of sustainable economic development characterized by harnessing
its maximum hydropower potential. According to the annual report (2014) of Nepal
Electricity Authority (NEA), the present total installed capacity of hydropower is nearly
733 MW. Similarly, thermal plant is generating 53.4 MW of electricity along with less
than 1 MW of solar plants. At present, nearly 312 MW is deficit in the national demand
and Nepal is importing nearly 102 MW of electricity from India. Power demand is
gradually increasing at the rate of approximately 80 MW per year but production growth
is only 40 MW. In order to meet the increasing power demand in an efficient manner,
there is an urgent need to identify and promote lower to medium sized hydropower
projects that can be implemented at the earliest. Thus, NEA and Department of
Electricity Development (DoED) has been encouraging such project development
practice from private sectors for harnessing the water resources potential in a
sustainable manner.
Realizing the fact that, efforts from the Government of Nepal only, will not be sufficient
anopen and free policy has been adopted for expediting hydropower development with
private sector investment. Necessary laws and regulations including the Hydropower
Development policy (2001) has been proclaimed to encourage the Independent Power
Producers (IPPs) to build, own, operate and transfer hydropower project. In this
context, Upper Myagdi-IHydropower Project (UMIHP) was identified in MyagdiDistrict of
Nepal and now it is in development phase.
Upper Maygdi I Hydropower Project (UMIHP) located on the leftt bank of Myagdi River
is a run-of-river type project. It is located in Myagdi District of Westernl Development
Region of Nepal. The entire project area (i.e. intake to powerhouse and tailrace) is
located in Mudi, Muna, Takam, Marang, Darbang Village Development Committee (VDC)
in Myagdi District.
UM-IHP 20
Feasibility Study Report
UM-IHP 21
Feasibility Study Report
UM-IHP 22
Feasibility Study Report
2.1 Location
Upper Myagdi-I Hydropower Project is situated at Myagdi District, Western
Development Region. Beni is the headquater of Myagdi District. Project area lies about
330 km northwest of Kathmandu.Geographically the area lies between latitude 28° 27'
30" N and 28° 31' 10" N and longitudes 83°20' 44” E and 83° 23' 06" E.
Figure 2.1: Physiography of the Nepal Himalaya (after Dahal and Hasegawa, 2008) and
location of the UMIHP site
2.2.2 Climate
Nepal experiences an exceptional climate variation owing to its steep gradient from high
Himalayas in north to plains in south. Five different climatic zones i.e.tropical, sub
tropical, temperate, alpine and tundra (Figure 2.2) have been classified from low land in
south to snow peaked Himalayas in north. The country as a whole receives most of
rainfall due to south-west monsoon, which arises from the Arabian Sea and passes
UM-IHP 23
Feasibility Study Report
through India before entering Nepal from eastern part during June-July. Difference
between the warm humid summer and the cold dry winter becomes more marked with
the change in the altitude. As the project area lies in the high altitude, the
catchmentarea experiences cool temperate to sub-arctic atmosphere. Like otherparts of
Nepal, this region is also influenced by the monsoon climate. Closest meteorological
station to the project site is Gujrakhani (Myagdi) located at Latitude 28°36' and
Longitude 83°13' at an elevation of 2513m. Relative humidity may be as high as 90%
during the wet season and as low as 40% during dry season.
2.2.3 Geology
Area between Arughat and Borang lies in the Lesser Himalaya of Central Nepal,
consisting of quartzite, schist, and phyllitic schist. Structurally,Main Central Thrust
(MCT) is located towards north of the project area. Rocks in this area aredeformed due
to presence of thrusts and folds.
2.3 Accessibility
Highway from Kathmandu to Beni is 300km long black top road and further about 30
km from Beni to powerhouse isfair weatherd earthen road whichis the main access road
UM-IHP 24
Feasibility Study Report
from Kathmandu to the project site. Further, around 10km access road is to be
constructed to make headwork site accessible.
UM-IHP 25
Feasibility Study Report
UM-IHP 26
Feasibility Study Report
Detailed topographical survey was executed covering the area from Headwork to
tailrace by depicting all the physical and manmade features as existing at the
site. Unique features which might be useful for references later aredepicted.
All the survey works were under taken using UTM grid co-ordinates and
elevations
All the permanent control points are made significant with concrete pillars or on
the stable boulders by marking with enamel paint
Closed traverse survey was carried out from the proposed sites covering
headworks, waterway and proposed powerhouse site.
All the permanent ground control stations were marked on permanent boulders
and with cement concrete.
Topographical maps of headworks site, tunnel alignment, powerhouse site and
tailrace sites are prepared in appropriate scales.
River cross-sections at proposed headworks, powerhouse and tailrace sites are
taken and profiles plotted
a) Scale :1:50,000
Sheet No : 2883 – 06
b) Scale : 1:25,000
Sheet No : 2883 – 10A
Sheet No : 2883 - 10B
UM-IHP 27
Feasibility Study Report
3.1.2 Surveying
A senior surveyor and his group carried out the detailed topographical survey of the
project area. All the datas necessary to determine the locations, coordinates and levels
were obtained by direct measurement in the field. To achieve the required accuracy and
standard,Total Stations with least count of 5” was used. Stepwise methodologies used
to conduct survey work are as follows.
Desk Study
Prior to the field survey, desk study was carried out by using topographical maps (Scale
1:50,000 and 1:25,000) published by Government of Nepal, Survey Department.
Detailed information about the project area for the survey was noted. Finally all the
available plans, profiles and location maps prepared during the identification of study
wascollected.
Reconnaissance survey
After finalizing the desk study, a team of multi-disciplinary experts were mobilized for
field verification. First step of survey was to reconnaissance the ground control stations
and detail topographical mapping around the project area.
Control Traversing
Basic control traverse survey was carried out from GPS Co-ordinates Reading Survey
points at Maran Khola Suspension Bridge near Power House site with the following
value of coordinates and elevation. Details of point’s information are presented in
following Table.
UM-IHP 28
Feasibility Study Report
Pentax Total Station with a least count of 5" was used for measuring horizontal and
vertical angles. One complete set of horizontal and vertical angles were observed during
the control traversing.
Horizontal Control
UM-IHP 29
Feasibility Study Report
mean distance adopted. Closing errors were distributed according the common survey
standards.
Altogether 39 control points were established in the first loop of main-traverse line,
7.03km in length. Different offset points were established wherever necessary around
the project area.
Vertical Control
Three sets of elevation readings (reciprocal reading) were observed to minimize the
index error for the ground control survey.Triangulation levelling method was run to
determine elevation accurately defining the position of all the ground control points
from head works to powerhouse site.
Computation of ∆h for each loop was checked, and all the loops were adjusted by the
Dell method so as to provide consistent heights for use in spot surveying.
Distance measurement was performed using Pentax total stations with standard
reflecting prism with an accuracy of 5mm ± 5ppm. Both back sighting and fore sighting
of direct distance were measured.Three complete sets of coordinates and elevations
were observed during the ground control survey. Three loop surveys was conducted
and adjusted as to provide consistent heights for use in spot surveying. Loop traverse
survey details are presented in Appendix A.
3.1.4 Accuracy
Closing errors were distributed according to common survey standards. Since, in all the
survey works, high accuracy survey instruments with a least count of 5" were
employed,accuracy in linear closing error in closed traverse is better than scale
1:10,000. Closing error is 0.015m in Northing, 0.010m in Easting and Elevation error is
0.029m for 7.03km of the main traverse line.
UM-IHP 30
Feasibility Study Report
used for map and cross- section preparation. Finally, the topographic map was
prepared in AutoCAD format.
The terrain features were surveyed by means of spot surveying. Spot positions were
taken by tacheometric method from different traverse points. Inaccessible points like
rock faces, top of cliff, landslide edge etc. were sighted from at least two known points
reading both the horizontal and vertical angles. Features such as riverbanks, high flood
level, landslides, cliff, house, cultivated lands, roads etc were recorded.
3.1.7 Mapping
Detailed topographical mapping of headworks site, audit tunnel, surge shaft,
powerhouse and tailrace area were carried out in required scale. Plans, section and
maps were prepared in digital environment by exploiting the AutoCAD, Land
Development software compatible to AutoCAD 2010.
UM-IHP 31
Feasibility Study Report
There are some of meteorological stations established by the DHM around the Myagdi
basin. Meteorological stations near to the headworks area are given in Table 3.3.
Annual precipitation and other relevant information of all these stations were taken
from "Climatologic Records of Nepal” compiled and published by the DHM. The average
precipitation calculated for the catchment at the intake site is 2336mm was computed
by Thiessen Method.
b) Climatological Records
UM-IHP 32
Feasibility Study Report
Annual maximum temperature in the project area generally occurs in June which ranges
from 10.20C to 20.70C. Similarly, minimum temperature generally occurs in January
which ranges from -0.20C to 110C (Water Statistics and Information, KP
Sharma).Records of temperature data of station at GurjaKhani are listed in the table
below.
Plate 3.1: Gauge installation and Hydrology team at Headworks (with gauge reader)
UM-IHP 33
Feasibility Study Report
UM-IHP 34
Feasibility Study Report
Selection of the layout of the project components such as diversion weir, tunnel inlet
portal, underground desander, tunnel alignment, surge tank, penstock alignment and
powerhouse location was done on the basis of geological and topographical condition of
the area.
Slope stability analysis of different structure area of the project was carried out on the
basis of aerial photo interpretation, geological observation and geological data analysis.
An analysis of the foliation plane to determine the stability of the rock mass at different
structure area of the project was done by using Lower Hemisphere Projection of the
foliation plane in Schmidt’s equal area net. The wedge formed by the planes was
analyzed with respect to the hill slope surface and tunnel alignment.
UM-IHP 35
Feasibility Study Report
UM-IHP 36
Feasibility Study Report
Catchment area measured from available topographical map at the proposed intake site
is found to be 665km². Length of the river (measured along Myagdi River) up to the
proposed headworks site is 31km. Division of area in different range of elevations is
given below.
Since powerhouse location is proposed at the left bank of Myagdi River (near the
confluence of Myagdi and Maran Khola), the catchment area at the powerhouse site of
Myagdi River is about 768km².Catchment basin of Myagdi River at headworks is shown
in Figure 4.1.
There are two meteorological stations in Myagdi River basin. One with Index No. 616 is
located at Gurjakhani (Lat. 28° 36' N; Long. 83° 13' E) at the elevation of 2530 m
above mean sea level, and the other with Index No. 629 at Baghara (Lat. 28° 34' N;
Long. 83°23' E) at the elevation of 2330m above mean sea level.Station at Baghara has
records of precipitation data only, whereas the station at Gurjakhani has climatological
UM-IHP 37
Feasibility Study Report
data including precipitation, temperature and relative humidity. Other information of the
precipitation stations are listed in Table 3.3.
UM-IHP 38
Feasibility Study Report
Annual maximum temperature in the project area generally occurs in June which ranges
from 10.20C to 20.70C. Similarly, the minimum temperature generally occurs in January
which ranges from -0.20C to 110C (Water Statistics and Information, KP Sharma).
Records of temperature data of station at GurjaKhani are listed in the Table 3.4.
For better hydrological analysis, stream flow data from two neighborhood gauging
stations are collected from latest DHM publication (DHM, 2008) for regional hydrology.
These data have been used with appropriate transposition factor to determine the
hydrologic design parameters of the project.
Reference hydrology for the project has been analysed from following methods. They
are:
Catchment Area Ratio Method
MIP (Medium Irrigation Project) Method
HYDEST method (WECS-DHM Method)
Medium Hydropower Study Project (MHSP) Method
UM-IHP 39
Feasibility Study Report
250
200
Discharges (m³/s)
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UM-IHP 40
Feasibility Study Report
c) WECS Method
Study is based on the flow records of DHM primary gauges from whole Nepal. This
method can be used for any un-gauged point of Nepal and requires catchment area and
the average monsoon rainfall over the basin. This method is used here mainly for the
purpose of cross-checking and verification. Flow results by this method are obtained
directly by the software called “HYDEST 2004” modified by DHM. Flow results are
presented in Table 4.3.
d) MHSP Method
Medium Hydropower Study Project (MHSP) under NEA in 1997 developed a method to
predict long-term flows, flood flows and flow duration curves at un-gauged sites
through regional regression technique. MHSP method has been used to estimate mean
monthly flow series at the proposed intake site. Daily flows, maximum and minimum
instantaneous flows of 66 hydrometric stations obtained from the DHM are used in the
regression. Input variables are similar to those used in WECS/DHM method. This
approach uses both monsoon wetness index and average precipitation of the area along
with catchment area of the Khola.
UM-IHP 41
Feasibility Study Report
Of these methods, mean monthly values computed from Catchment Area correlation
with data of Modi has been adopted. Basis for this adoption is due to following reasons.
UM-IHP 42
Feasibility Study Report
Long-term daily flow data from 1964 to 2006 are available from Modi Khola.
Since the catchments of Myagdi and Modi has similar characteristics, the
discharges can also be used for long term flow analysis, mean monthly flow
estimation, low flow analysis and flood flow estimations.
Measured discharges correlate with flow values computed from catchment area
correlation with Modi Khola.
Thus,mean monthly flows for Upper Myagdi-IHydropower Project at intake site istaken
as presented in Figure 4.3.
250
200
Discharge m3/s
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
UM-IHP 43
Feasibility Study Report
Probability of CAR
exceedance (m³/sec) No. of
(%) Monthly days Remarks
5 199.3 19
10 162.3 37
15 133.6 55
20 111.7 73
25 86.7 92
30 57.8 110
35 48 128
40 33.6 146 Q40%
45 26.3 165
50 23.5 183
55 20.2 201
60 17.8 219
65 16.3 238
70 14.5 256
75 13.3 274
80 12.5 292
85 11.9 311
90 10.9 329
95 9.4 347
Based on the annual flow duration curve, the lean flow (95 percentile) at the proposed
intake is obtained as9.4m³/s. The 40 percentile exceedence flow from the Flow
Duration Curve is obtained as 33.6m³/s. This Q40 discharge has been taken as design
discharge for the project. Adopted flow duration curves by Catchment correlation
method at Myagdi Intake site is presented in Figure 4.4.
UM-IHP 44
Feasibility Study Report
300.0
250.0
200.0
Discharge(m3/s)
150.0
100.0
50.0
0.0
0% 20% 40% 60%
% of Exceedence 80% 100% 120%
a. Gumbel Distribution
𝑄𝑇 = 𝑄 + 𝐾 ∙ 𝜎𝑛−1
UM-IHP 45
Feasibility Study Report
𝑌𝑇 − 𝑌𝑛
𝐾=
𝑆𝑛
𝑇
𝑌𝑇 = − 𝑙𝑛 ∙ 𝑙𝑛
𝑇−1
Where, 𝑄𝑇 = Discharge of T-yr Return Period
𝑄 = Average Discharge of Discharge series
𝜎𝑛−1 = Standard Deviation of Discharge series
𝑌𝑇 =
𝑌𝑛 =
T = Time Period
b. Log Pearson Type III distribution
𝑄𝑇 = 10𝑍𝑇
𝑍𝑇 = 𝑧 + 𝐾𝑧 ∙ 𝜎𝑧
Where, 𝑄𝑇 = Discharge of T-yr Return Period
𝑍𝑇 = Inverse of discharge variate
𝑧 = Mean value of the variate
𝐾𝑧 = Frequency factor depending on the return period
𝜎𝑧 =Standard Deviation of Discharge series
T = Time Period
c. Lognormal distribution
This method is similar to Log Pearson Type III except that the coefficient of skew
variate is taken as zero.
𝑄𝑇 = 10𝑍𝑇
𝑍𝑇 = 𝑧 + 𝐾𝑧 ∙ 𝜎𝑧
Where, 𝑄𝑇 = Discharge of T-yr Return Period
𝑍𝑇 = Inverse of discharge variate
𝑧 = Mean value of the variate
𝐾𝑧 =Frequency factor depending on the return period
𝜎𝑧 =Standard Deviation of Discharge series
T = Time Period
UM-IHP 46
Feasibility Study Report
Design frequency of flood is determined with basic consideration of risk involved and
cost of minimizing that risk. Risk factor is dependent on type and size of structure,
volume of water impounded by it and extent of damage in the event of failure of the
structure, which depends on the population and property downstream of the structure
likely to be affected by the worst eventuality of the failure of the structure.
Comparison of the flood flows at intake using various approaches is presented in the
Table 4.8.
Table 4.8 Flows comparison at Headworks
Return Flood flow calculation (m³/s)
period Frequency Gumbel Gumbel Log- Log-Normal HYDEST MHSP
(yrs) Analysis Distribution graphical Pearson Distribution Method Method
Method Method method Type III
Distribution
2 520 554 520 548 543 174
5 793 817 793 668 666 299 158
10 999 991 999 928 934 397
20 1,158 1,204 1,051 1,066 502 239
50 1,477 1,374 1,477 1,258 1,295 653 299
100 1,683 1,536 1,683 1,396 1,453 778 351
200 1,889 1,698 1,889 1,535 1,615 914
500 2,161 1,911 2,161 1,650 1,752 1,109
1000 2,072 2,367 1,862 2,007 1,272 559
UM-IHP 47
Feasibility Study Report
Standard project flood(SPF) is typically computed using hourly storm precipitation data
that is characteristic of the basin. Unfortunately such short term storm data is not
available for the basin or region. In place of the SPF, it was decided to use the 1 in 100
yr flood (Q100) determined by frequency analysis, which is of similar magnitude or
more conservative.
HYDEST method and MHSP approach gave relatively lower flood values with respect to
other methods. Therefore, these methods cannot be adopted for Myagdi River
catchment. Whereas Flood Frequency Analysis Method predicted nearly close flood
values to each other. While observing average values of results from these methods,
results computed from Log-normal distribution method are adopted for hydraulic design
of the headwork structuresas DHM has recommended in context of Nepal.
2,000
1,800
1,600
Flood Discharge (Q) m³/s
1,400
1,200
1,000
800
600
400
200
-
1 10 100 1000
Return Period (T) yrs
UM-IHP 48
Feasibility Study Report
UM-IHP 49
Feasibility Study Report
2,000
1,800
1,600
Flood Discharge (Q) m³/s
1,400
1,200
1,000
800
600
400
200
-
1 10 100 1000
Return Period (T) yrs
Recommended flood for the design of powerhouse and tailrace structures is 1678 m³/s
which is the 100-year flood predicted by Log-Normal Distribution Method.
UM-IHP 50
Feasibility Study Report
5
4.5
4
3.5
Height (m)
3
2.5
2
1.5
1
0.5
0
0 200 400 600 800 1000 1200 1400 1600
Discharge (m3/s)
Figure 4.7: Rating Curve for Headworks Site
3.5
2.5
Height (m)
1.5
0.5
0
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Discharge (m3/s)
UM-IHP 51
Feasibility Study Report
Table 4.10: Diversion Flood Values (m3/sec) for Different Return Periods
Return period (yrs) Construction Flood (m³/s)
10 47.04
20 52.85
50 60.35
A 20-year dry season flood has been adopted for river diversion works. Thus, the flood
value of 52.85m³/s has been adopted as diversion flood for headworks.
Low flows are presented here in order to provide an insight into one of the important
hydrologic characteristics of the basin, the extreme flows. Although the frequency of
this extreme parameter may have impact on the long term energy generation, it is not
directly used in any aspect of the project design. Energy calculations are based on long
term average daily or monthly flows and not the low flow statistics. Low flows of
different return periods at the intake site of the project are determined by Regional and
Low Flow Frequency Analysis Methods. Regional Low Flow Frequency Analysis Method
is done by HYDEST Method whereas Low Flow Frequency Analysis Method is done by
Gumbel Distribution Method. Summary of floods from different methods of estimation
for different return periods are presented in table below.
UM-IHP 52
Feasibility Study Report
Moreover river sediments consist of quartz grains obtained after rock crushing and
washing away of fine particles. In fact, quartz (SiO2) content is the predominating one.
The microscopic, thermo-graphic and/or X-ray structural analyses of sediment samples
show the presence of other mineral ingredients (feldspar, mica, magnetite, clay,
montmorillonite), etc., and rocks (igneous, sedimentary and metamorphic) in them.
When a water sample has been collected from the stream, the concentration of
suspended sediments is obtained through analysis. Bed load sediment sample is
collected from river bottom. Concentration is determined by mass (weight) analysis by
filtration of sediment sample using filter paper. Collected samples are dried at 105°C
and then weighed by means of precise analytical (mechanical or electronic) balance.
Total sediment load is calculated by measurement of river discharge and total
concentration of river sediments.
UM-IHP 53
Feasibility Study Report
Catchment area of Myagdi River basin at the proposed intake site is 213 km2 in High
Himalaya, 297.9km2 in High Mountain and 153.9 km2 in Middle Mountain. Hence,
annual sediment yield will be 1,575,750 tons at the intake site. For the mean annual
discharge of 62.36 m3/s, this corresponds to a mean annual daily concentration of
about 824 parts per million by weight (ppm) at the intake site.
Hence, from the above equation, the total annual suspended sediment yield is about
2,405,588 tons which is equivalent to a mean annual daily concentration of about
1,223 parts per million by weight (ppm) at the intake site using the mean annual
discharge of 62.36 m3/s.
UM-IHP 54
Feasibility Study Report
a) Concentration Analysis
Collected samples were analyzed in Hydro Lab, Kathmandu. There were altogether 11
number of samples analyzed in the year 2015. Standard filtration method was used to
analyze the sediment concentration. Whatman filter paper was used for filtration
analysis.Computation of concentration data of the whole sampling period is shown in
Table 4.12
Table 4.12: Results of Sediment Concentration
S. Sampling date Sample Gauge Remarks
No. number Concentration height (cm)
(PPM)
1 2072/04/09 UM1 778 1.98
2 2072/04/12 UM2 650 1.99
3 2072/04/18 UM3 577 3.67
4 2072/04/22 UM4 744 3.68
5 2072/04/25 UM5 5,195 3.82
6 2072/04/28 UM6 4,573 3.18
7 2072/05/01 UM7 978 3.89
8 2072/05/07 UM8 1,219 3.73
9 2072/05/10 UM9 248 3.82
10 2072/05/13 UM10 319 3.81
11 2072/05/16 UM11 184 3.61
UM-IHP 55
Feasibility Study Report
Minerals
Others
26%
Mica Quartz
12% 57%
Feldspar
5%
4.11 Conclusions
Following pertinent data hasbeen recommended for feasibility study of Upper Myagdi-I
Hydropower Project.
Since the long term flow data of intake location is not available, mean monthly
and daily flows have been derived from the data of adjacent gauging station
established by the DHM and compared with the flow generated from the gauging
station near the intake area.
The flows generated from the gauge readings are a little bit on higher side than
that generated from other three methods. This is primarily due to high snow
contribution and high rainfall intensity in Myagdi catchment. Therefore, the flows
generated from gauge readings are acceptable and recommended for the design
of project.
As there is no record of instantaneous flood flows at the intake area, the data
have been generated from the DHM’s gauging station in the Modi River at
Nayapul (Jhaprebagar) and the flood values are calculated by different statistical
distribution methods recommended by the DHM. Results are quite closer to each
UM-IHP 56
Feasibility Study Report
other and it is recommended to adopt the value from log normal distribution for
further analysis and design although as DHM recommends in the context of
Nepal.
Flow duration curves are developed based on data generated from correlation
with Chepe Khola. The discharge at 40% probability of exceedance for Upper
Myagdi Khola at the proposed intake is computed as 33.6 m³/sec.Q40 discharge
of 33.6m³/s is taken as design discharge for Upper Myagdi-I Hydropower
Project.
At least 10% of the driest flow shall be released downstream to maintain the
river ecosystem
To be in safe side, it is recommended to consider 1 in 20 years dry flood to
design the cofferdam.
Flow measurement, daily gauge reading and sediment sampling should be
continued even after the feasibility study and flow data should be revised prior to
detail design of the project.
Maximum sediment concentration (5195 PPM) was obserbed on 10August 2015.
Average content of Quartz, Mica and Feldspar are 57%, 12 % and 5%
respectively.
UM-IHP 57
Feasibility Study Report
UM-IHP 58
Feasibility Study Report
5.1 Introduction
Main purpose of the study is to obtain information on regional geology of the project
area, to study detail geological condition of the locations of proposed project structures,
to prepare detailed engineering geological map (1:1,000), to carry out Rock Mass
Classification using “RMR” and “Q” systems for the design of the structures, to assess
the slope stability of the project area including especially the tunnel alignment, to
propose the support system of the tunnel alignment, to carry out construction material
survey.
Geologically, Nepal Himalaya is divided into five major zones, from north to south. A
brief summary of this zone follows in order to provide the background information
about regional geological condition of the project site.
UM-IHP 59
Feasibility Study Report
Figure 5.1: Geological map of the Nepal Himalaya (after Upreti and Le Fort, 1999)
UM-IHP 60
Feasibility Study Report
zone. Lesser Himalaya is divided into the Midland and Surkhet Groups. The total
thickness of the Midland Group is about 8 km. This group comprises four formations,
which consist of phyllite, dolomite, and metasedimentary rocks.
Ghanpokhara Formation has grey metasandstone intercalates with dark grey phyllite
and dolomite. Total thickness of the litho unit is 800 m.
UM-IHP 61
Feasibility Study Report
greenish grey quartzite. Dip directions of rocks ranges from 340° to 010° (northwest to
northeast) with dip amount ranging from 25° to 50° Figure 5.2
Left bank of Myagdi Khola within project area has mostly exposed bedrock and thin to
thick colluvial deposit. Exposed rockarephyllite and phyllite with quartzite makes
exposure on both bank at weir area. Proposed settling basin lies on alluvial terrace
deposit. Proposed tunnel alignment encounters different lithology as passes through
mostly phyllite, schist, and occasional bands of thin to thick quartzite. Proposed
structures; surge tank, penstock, powerhouse and tailrace lies on phyllite and schist
with quartzite intercalation.
Project Area
Figure 5.2: Geological Map of the Project area. (Department of Mines & Geology)
UM-IHP 62
Feasibility Study Report
Proposed weir axis is located at about 100 m downstream from the confluence of
Myagdi Khola and Mudi Khola (Plate 1). Rocks are exposed in both banks except
riverbed. Exposed bedrock in steep slope of Myagdi Khola is fine grained, grey to
greenish grey phyllite with quartzite intercalation. Quartz veins are present in the
exposure with deformed boudin structures. The rocks are thick to massive, medium
hard and moderately weathered.
Rock Mass Classification using CSIR classification has been carried out in the vicinity of
the headworks area which gave the RMR values in the range of 42 to 64. Thus, the rock
can be classified as fair to good rock.
UM-IHP 63
Feasibility Study Report
Due to steep topography all the structures of headworks are proposed underground.
Inlet portal/ Intake lie at the left bank of the Myagdi River (Plate 5.2). The area consists
of thick to massive, fresh to slightly weathered, greyish grey to grey medium strong
phyllite with quartzite having three 3 sets of major joints. A detailed discontinuity
survey was carried out in several directions on the different rock exposures around the
headworks area. Around 50 joint measurements were collected from the rock
exposures. The detailed joint mapping revealed mainly three sets of joint along the
tunnel with some random sets. The joints are tight to moderately open, moderately
spaced, continuity less than 5 m, rough, irregular and occasionally smooth and filling
materials as sand, silt and few are free of filling materials.
The statistical analysis of major joints has been analyzed and projected in lower
hemisphere of stereo net .Lower hemisphere stereographic projection in equal angle
net of measured discontinuities from headworks area is shown in Figure 5.3 and Figure
5.4. The stereographic projection shows wedge failure between J1 and J2 with respect
to natural hill slope (45/320) which is also reflected in the topography of left bank of
Myagdi Khola within project area.
Rock quality is estimated and presented in Table 5.1. The value of Jn (joint set number)
is taken double to calculate the Q-value for the portal.
UM-IHP 64
Feasibility Study Report
Fisher
Concentrations
% of total per 1.0 % area
0.00 ~ 2.50 %
2.50 ~ 5.00 %
5.00 ~ 7.50 %
7.50 ~ 10.00 %
10.00 ~ 12.50 %
12.50 ~ 15.00 %
15.00 ~ 17.50 %
W E 17.50 ~ 20.00 %
20.00 ~ 22.50 %
22.50 ~ 25.00 %
No Bias Correction
Max. Conc. = 20.1144%
Equal Angle
Lower Hemisphere
50 Poles
50 Entries
UM-IHP 65
Feasibility Study Report
Orientations
ID Trend / Plunge
1 174 / 46
4
3 2 285 / 20
1 3 041 / 17
4 321 / 15
W E
2
3 4
Table 5.2: Orientation and characteristics of discontinuity of rock at Inlet portal of headrace
Tunnel
UM-IHP 66
Feasibility Study Report
Underground settling basin is proposed on left bank of Myagdi River due to the
unavailability of space on surface. Desander is located about 100m downstream from
the proposed intake site. Two caverns for desanding basin are proposed and the
caverns are connected with the portals by means of approach tunnel. Geologically, the
basin area also lies in the rocks of the Ranimatta Formation of the Midland Group.
Intercalation of fine-grained, grey quartzite; grey phyllitic schist and phyllite is present
in the location. Surface over the desanding basin is covered by thin recent colluvial
deposits.Rock mass classification is presented in Table 5.3.
In general, the rock along the tunnel is considered to be weak to medium strong in
strength. The rock is hard with expected to be intact compressive strength in the range
of 50-150 MPa. The rock is slightly to moderately weathered. The rock is exposed
mainly in the small streams and at higher elevation in the form of steep cliff along the
tunnel route. Bedrock is mostly covered by thick to very thin veneer of colluvial deposit
along the tunnel alignment. No major faults and thrusts crossing the tunnel are noticed
during the present mapping however several thin bands of shear zones are noticed in
the tunnel route mainly along the tributaries. This zone is categorized as poor rock,
UM-IHP 67
Feasibility Study Report
which is to be supported properly with concrete lining. The mapping in the river
sections and hill slopes were projected to the tunnel horizon in order to produce the
required geological information along the tunnel route. The geological condition along
the tunnel alignment is mainly based on surface mapping.
Table 5.4: Orientation and characteristics of discontinuity of rock at headrace tunnel around
Khara area
Table 5.5: Orientation and characteristics of discontinuity of rock at headrace tunnel around
Basbot (Adit I)
UM-IHP 68
Feasibility Study Report
diagram below (Figure 5.5). Such relation of tunnel axis to the discontinuities is
favorable for tunneling works.
The rock mass quality that may represent the rock quality along headrace tunnel is
based on Rock Mass Rating and Q-system. Tentative projected rock mass quality with
respect to the dimension of structure depicted in the geological cross section is
presented in Table 5.6.
Table 5.6: Rock mass class and its tentative representation along the HRT
S.N Rock mass class Length Percentage Q value RMR
1 Fair to Good 800 14 5-10 42-62
2 Fair 2100 37 4-8 45-55
3 Poor 1550 27 1-3 35
4 Very Poor 800 14 0.2-1 15
5 Extremely Poor 450 8 <0.1 <10
The tunnel covers about 20% fair to good rock mass and 35% of fair rock mass. The
rest 25% is expected to cover by poor rock mass. The very poor rock mass is estimated
to be about 15% and 5 % as extremely poor rock mass of the tunnel length which
needs concrete lining along with steel ribs. The poor section will be treated with
UM-IHP 69
Feasibility Study Report
concrete lining only. It is recommended that all the non pressure tunnel section with
good and fair rock mass will have fibre shotcrete lining (10 cm thick) only and all the
pressure tunnel section will need fibre reinforced shotcrete (10 cm thick for fair rock
mass and 15 cm thick for poor to very poor rock mass) along with 30 cm thick concrete
lining. The set ribs are recommended for very poor rock mass. The rock classification is
based on surface geological mapping along the tunnel route and more detailed
geological condition will be achieved only after the excavation of the tunnel section.
The contour density diagram and stereographic projection of main joints for the
headrace tunnel are shown in Figure 5.6& Figure 5.7.
UM-IHP 70
Feasibility Study Report
Table 5.7: Orientation and characteristics of discontinuity of rock at Surge Tank area
Descriptions Ex- Foliation Joint Joint (J1) Joint(J2)
Orientation dip/dip dir 35º/015º 85º/290º 55º/185º
Spacing (cm) 20-200 25-150 50-200
Aperture (mm) 0.1-1 >5 <5
Roughness Filling Slightly Rough Undulating Rough Planar Rough
Filling Silty Clay Silty Clay Silty Clay
Weathering Slight Moderate Moderate
Persistence (m) >2 2-4 1-3
Water Dry Dry Dry
UM-IHP 71
Feasibility Study Report
Statistical analysis of major joints in the surge tank has been analyzed and projected in
lower hemisphere of stereonet. The analysis gives the following major joint sets. The
stereographic projection of main joints is shown in Figure 5.8. Analysis shows that there
is no any stability problem will occur around surge tank area
Orientations
ID Trend / Plunge
1 192 / 54
2 110 / 04
1:FP
3 004 / 35
4 072 / 50
1 m 048 / 72
Friction Angle
W 2:J1 E
4:HS
3:J2
Equal Angle
Lower Hemisphere
4 Poles
4 Entries
UM-IHP 72
Feasibility Study Report
5.5.1 Q System
Rock mass classification NGI Q-System (simplified from Grimstad and Barton, 1993
Figure 5.10) is one of the popular methods to classify the rock mass quality. In this
system the rock tunneling index Q-value is the key parameters in the estimation of rock
support. This Q – System considers six different parameters. The assessment of the
rock mass quality, Q, was done by rating of the six parameters.
Q= RQD/Jn* Jr/Ja*Jw/SRF,
Where,
RQD= Rock quality designation
Jn= Joint set number,
Jr= Joint roughness number
Ja= Joint alteration number,
Jw= Joint water reduction factor
SRF = Stress reduction factor
Barton’s rock support chart also incorporates equivalent excavation dimension, which is
the ratio between the span or height of an underground opening and an excavation
support ratio (ESR). ESR mainly reflects degree of safety and support demand by an
underground opening. For water tunnels, shafts and penstock tunnels an ESR of 1.6 is
defined.
Barton et.al (1980) provides additional information on rock bolt length. The length L of
rockbolts can be estimated from the excavation width B and the Exacavtion Support
Ratio (ESR):
L = 2+ 0.15B
ESR
UM-IHP 73
Feasibility Study Report
Therefore by the above equation length of rock bolt for headrace tunnel in Upper
Myagdi I HEP comes 1.6 ̴ 2m.
Similarly the rock support design proposed by Sunuwar in the contest of Nepal
Himalaya is also worth full to mentioned here. According to the rock properties and size
of a tunnel the rock support is divided into six classes (Sunuwar 2005) and the designed
rock support for 4 m diameter tunnel is shown in Table 5.8.
UM-IHP 74
Feasibility Study Report
Table 5.8: Recommended rock support in the headrace tunnel (Sunuwar, 2005), (Span = 4
m, ESR = 1.6)
S.N Rock class/ Q-value Support amount Remarks
Type RMR
1 I >4 Spot bolting at crown and Blocky to massive, well
FAIR TO GOOD ROCK > 56 unstable wedge. 5 cm fibre interlocked, competent
reinforced shotcrete only at stable rock.
fractured and loose area.
UM-IHP 75
Feasibility Study Report
UM-IHP 76
Feasibility Study Report
Table 5.10: Predicted rock mass quality and support design for Headrace Tunnel
UM-IHP 77
Feasibility Study Report
The headrace tunnel will be in hydrostatic condition during its operation. Since the
designed rock support in the table is not water tight, the concept of pre-injection
grouting should be applied at the required length of headrace tunnel to control possible
water leakage during operation.
5.6 Construction Material
Construction material sites were observed mostly along the both banks of Myagdi Khola
within the stretch of project area. From the field observation three major potential sites
were investigated. Coarse material in the headworks site on the right bank can be used
as riprap material. Confluence of Maran Khola and Myagdi Khola is another potential
site for the construction material site. There is no major potential site for the fine
aggregate due to high gradient River. Major source of fine aggregate could be Darbang
area and Kali Gandaki River.
The tentative volume could be exploited from the mentioned deposit are tabulated in
the table below (Table 11).Most of the deposits consist of about 70 - 80% coarse
aggregate (gravels to boulders) and about 20 - 30% fines (silt to sand).Coarse
aggregate mainly consists of gneiss (60%) , quartzite (25%) and phyllite schist (15
%).
Table 5.11: Summary of different sources for construction materials
2 At the confluence of Maran Old and recent alluvial terrace 2400*1.5= Around
and Myagdi Khola deposit consists of boulder, 3600 Powerhouse
gravel in the matrix of silty area
sand.
UM-IHP 78
Feasibility Study Report
Plate-5.3: Potential site for construction material in river deposit around Darbang Area
5.7 Seismicity
5.7.1 General
Evolution of the Great Himalayan Arc is the result of collision between the Indian and
Eurasian Tectonic Plates over a distance of 2400km from Pakistan in the west and
Burma in the east. The Himalayas are located near plate boundary. Therefore,
Himalayan region is considered to be seismically active zone. Seismic activity in the
Himalayas results from the strike slipping of the Indian basement along a sub-horizontal
decollement interface, which is known as Main Himalayan Thrust (MHT). It coincides
with MFT in south and roots alongMCT isbeneath the High Himalaya and southern
Tibet. Magnitude and recurrence of Himalayan earthquake depend upon the geometry
UM-IHP 79
Feasibility Study Report
and plate velocity of Indian plate with respect to Tibetan plate. Convergence rate of
Indian Plate in the Himalayan region is estimated to be about 20 mm/year.
Recent seismicity condition and historical records indicate that the Himalaya has
experienced recurrence of great earthquakes. National Seismological Centre
(Department of Mines and Geology, 2006) has been recording small to medium sized
earthquakes that frequently occurring in the territory of Nepal. Earthquakes Epicenter
Map of Nepal shows that medium sized earthquakes (6 to 7 magnitude) are mostly
confined to the MHT between the foot hills and the Higher Himalaya, Figure 5.11. The
data of the recorded earthquake indicates that the recurrence of earthquake 6<M<7 in
western Nepal is one time in six years, Table 5.13. However, uncertainty of the strong
ground tremor is very high since the active fault systems in the vicinity of the project
area are not reported.
UM-IHP 80
Feasibility Study Report
In the last century, four great earthquakes have occurred due to sudden release of
accumulated stresses in the active geological faults of the Himalaya. Nepal has
historically experienced several great earthquakes (Chitrakar and Pandey, 1986; DMG,
2006). The 1934 Bihar-Nepal Great Earthquake was one among the four large
earthquakes of the whole Himalaya with a magnitude of Ms 8.3. Occurrence of other
significant historical great earthquakes (M>7.5) in 1255, 1408, 1810 and 1833 are also
mentioned in literatures (Chitrakar and Pandey, 1986; Bilham et al, 1995).
UM-IHP 81
Feasibility Study Report
Table 5.12: Recurrence of earthquake in Nepal between the period 1994 and 2000 (after
DMG, 2006).
Paleoseismology deals with the history of earthquakes: their location, magnitude and
frequency of occurrence.Thus, by study of the past occurrences of large earthquakes, it
is possible to forecast the likelihood of future earthquakes in terms of location,
magnitude and probable timing. It identifies and studies the source of earthquakes
(active faults), their potential to produce future large earthquakes from their past
records, and to try to forecast and provide information on future earthquake activity,
usually using some probabilistic approach. Paleoseismological activities in the Nepal
Himalaya have been evidenced from the sediments of Kathmandu valley and Terai plain
(Gajurel et al., 1998; Nakata et al., 1998; Lavé et al, 2005; Yule et al., 2006). A detailed
active fault map prepared in the Nepalese Himalaya indicates that source of earthquake
i.e. active faults are situated very far from the project site (Upreti, 2009, Figure 5.11).
Seismic hazard map prepared by Department of Mines and Geology (2002) using a peak
horizontal acceleration at bedrock has a 10% probability of being exceeded over 50
years.
UM-IHP 82
Feasibility Study Report
Figure 5.11: Active faults of Nepal Himalayas (Adopted after Upreti 2009)
This is the tectonic contact between the Higher Himalayas and Tibetan Tethys Sediment
Zone. It is the less active seismo-tectonic structure.
5.7.2.2 Main Central Thrust (MCT)
This is the tectonic contact between the Higher Himalayas and Lesser Himalayas. It is a
north dipping thrust fault which at one time was a convergent plate boundary. The MCT
was active during the early phases of Himalayan orogeny but is now considered to be
less active as compared to Main Boundary Thrust (MBT). Based on historical records
(1800’s to 1986) the largest earthquake recorded in the MCT zone in the Himalaya was
a 7.5 magnitude in August 28, 1916.
This is the active tectonic contact between the Lesser Himalayas and the Siwaliks. The
MBT has been the source of very large earthquakes in the past. It is reported that the
maximum potential earthquakes in this feature has a magnitude of 8.0. The project site
is located at about 5 km north of MBT which is considered to be near distance from the
UM-IHP 83
Feasibility Study Report
project site. Therefore, less seismic risk associated with this feature is expected for the
project.
5.7.2.4 Himalayan Frontal Fault (HFF)
This is a tectonic feature located at the boundary of the Siwalik and the Terai. This fault
is also considered to be active. The maximum earthquake potential of this fault is 6.5 in
magnitude. The project site is located very far from this feature hence less seismic risk
caused due to this feature is expected.
Nepal has experienced a number of large earthquakes over the past few decades which
have caused the substantial damage of life and property. A microseismic epicenter map
of Nepal Himalaya and adjoining region (1:2,000,000) prepared by the National
Seismological Centre, Department of Mines and Geology, 2006 has been presented in
Figure 5.11for reference. The map shows the distribution pattern of theearthquake
epicenters in Nepal and adjoining region. The map also suggests that the far western
Nepal is seismically more active than the Eastern Nepal. It is also clear from the map
that there is a dense cluster of earthquake epicenters in far western Nepal, less in
Eastern Nepal and least in Central Nepal.
Records of seismic activities are limited in the Nepal Himalayas and hence correlation of
seismic events with the adjacent Himalayan Region would be a useful source of
information for designing the hydraulic structures. Several Seismicity studies have been
carried out for various projects in the country during the study and engineering design
phases and seismic design coefficient are derived for those projects. Theoretically,
Nepalese standard and Indian Standard are two basic criteria to derive the design
coefficient for the design of hydraulic structures in the absence of detailed seismicity
study of the projects. Therefore, based on seismicity study carried out for other projects
and theoretical methods, the basic design coefficient for Khola Project can be derived
based on Nepalese standard and Indian Standard.
In order to determine the seismic coefficient a seismic design code for Nepal has been
prepared. The country is divided into three seismic risk zones based on allowable
bearing capacity of three types of soil foundation. The Upper Myagdi IHydropower
Project is located in the Zone -3 of seismic risk zone map of Nepal, Figure 5.14 and the
soil foundation at the dam site belong to average soil type. Therefore, the basic
horizontal seismic coefficient is considered to be 0.08. By using the empirical method,
UM-IHP 84
Feasibility Study Report
the effective design coefficient according to seismic design code of Nepal is given by
the equation,
For the maximum acceleration of 250 gal according to Seismic Hazard Map of Nepal,
Figure 5.12, (Published by DMG, National seismological Center - September 2002) and
reduction factor of 0.6 the calculated effective design seismic coefficientfor the Project
is approximately 0.15 according to Nepalese Standard.
In order to determine the design horizontal coefficient, a seismic risk map for India has
been prepared. The map is published Criteria for Earthquake Resistant Design of
structures in India. The country is divided into five seismic risk zones in the Indian
Standard, Figure 5.14.According to seismic risk map of India, project area lies in the
fifth seismic risk zone of India (Zone V). Therefore, based on the national building code
of India (IS: 4326-1993), Project is located in the Zone V and recommended basic
coefficient of horizontal seismic acceleration for this Zone is 0.08 gal.
Therefore, the design horizontal seismic coefficient for the weir at Project is 0.16
according to Indian Standard.
However, it is suggested to use 0.15 values as a design horizontal seismic coefficient for
the Project.
UM-IHP 85
Feasibility Study Report
UM-IHP 86
Feasibility Study Report
UM-IHP 87
Feasibility Study Report
UM-IHP 88
Feasibility Study Report
Conclusions
The project area lies in Lesser Himalayan succession. Main lithology of the project area
is phyllite/schist and quartzite. Left bank of the Myagdi Khola has mostly bedrock
exposures where right bank has colluvial deposits with few landslides and river crossing.
Head works constitute a diversion weir, intake and approach canal. Diversion weir will
be founded on alluvial deposit and other structures will be founded on bed rock.
Underground settling basin is located on bed rock of phyllite with quartzite.
Scattered boulders along the banks of the rivers can be crushed and used for coarse
aggregate. Deposits for fine aggregate might be inadequate in the project area, which
are found as scattered patches along the river section. Adequate fine aggregate can be
extract from Darbang and Kaligandaki.
Recommendations
As discussed earlier, the assessment of the rock mass quality in this feasibility study at
Upper Myagdi-I Hydroelectric Project is mainly based on the surface mapping and
geological traverse survey. Hence, there is a strong need for further sub-surface
investigation at critical locations of the project so that more information on the
mechanical characteristics of the rock mass is achieved. Therefore, following sub-
surface investigations are recommended:
UM-IHP 89
Feasibility Study Report
A. Geophysica Survey
Geophysical survey should be carried out at the following locations:
B. Drilling
Exploration drilling should be carried out at the following locations:
At the left bank of Myagdi Khola near by under sluice location covering 25 m
depths.
At settling basin area covering 20m depth
At surge shaft location covering 50m depth.
At penstock alignment covering 15m depth
At powerhouse location covering 25m depth.
UM-IHP 90
Feasibility Study Report
UM-IHP 91
Feasibility Study Report
Alternate I
One possible alternative is tunnel alignment through right side of Myagdi which is
longer than left side due to some river crossing and colluvial deposit. Landslides are
also encountered in this option.Also suitable location of surface power house and surge
shaft was not found for the right bank alignment.
Alternate II
Headwork of the project has been fixed at about 70m downstream of the confluence
between Mudi Khola and MyagdiRiver. This project has been optimized to generate
53,500kW electricity. Design discharge has been fixed as33.6 m3/s. Tunnel alignment
lies in theleft bank. Regarding the surge shaft, underground with partially exposed
penstock was studied.But for the cost saving purpose, it was avoided.
Alternate III
This layout is proposed as a modification of alternative II. In this alternative, tunnel
passes through left bank of Myagdi River with exposed surge shaft.
UM-IHP 92
Feasibility Study Report
UM-IHP 93
Feasibility Study Report
7.1 Introduction
This chapter presents the methodology and assumptions considered for the
optimization of the project to determine the optimum cost effective project size i.e. the
Optimum Plant Capacity. The optimization study is conducted to determine the
optimum plant capacity.
The optimization study is carried out taking a range of technically viable alternative
plant capacities. As per available mean monthly river discharge data and available head,
energy calculated at different plant capacities. Project cost at different capacity is
derived by calculating the cost of major items of different structures involved in the
project such as diversion weir, settling basin, water conveyance system, powerhouse
and tailrace. Optimization study includes the cost of different alternatives and their
financial parameters. Alternative with minimum generation cost has been selected as
the optimum project size.
Its objective is to determine the element size, which maximizes the benefits of power
supply. Optimization procedure in this study follows the general procedure outlined
below.
Selection of the procedures to be optimized and their range and thus establishing series
of alternatives.For each alternative, carrying out the conceptual design and produce
cost estimate.For each alternative, assessment of its performance and estimate its
benefits:
Comparison of the costs and benefits and carrying out economic analysis.
UM-IHP 94
Feasibility Study Report
For each case of the installed capacity, a preliminary layout on the available
topographical map was carried out and preliminary cost estimate is derived including
electro-mechanical costs. Common costs like cost for environmental mitigation, access
road and transmission line are not considered in this study. For each case, energy
calculation depending on the available hydrological data was carried out to determine
the dry and wet energy.
The major project structures which differ from one case to another with different
installed capacity are listed below.
Ogee shapedweir & Undersluice
Intake & Desanding basin
Headrace tunnel & Construction adits
Surge shaft& Penstock
Powerhouse and tailrace
Hydro-mechanical structures like gates and trash-racks
Electro-mechanical equipment like turbine, generator, power transformer and
valves etc.
Quantity estimate and tentative costs are calculated for each of these structures. Water
conveyance system is the major variable in the cost of different alternatives and is
optimum for the given head and discharge characteristics of the installed capacity. For
electro-mechanical costs supplier’s quotations of various recent projects in Nepal is
based on per kilowatt cost of equipment on “water to wire basis”. Since detailed rate
analysis was not carried out,unit rates for various works based on the projects of similar
nature has been considered.
UM-IHP 95
Feasibility Study Report
Financial evaluation was carried out using discounted cash flow techniques for each
case to determine economic indicators like benefit-cost (B/C) ratio, internal rate of
return (IRR) and net present value(NPV) of the project. Economic indicators for all the
cases were tabulated and appropriate charts were drawn. The case producing the
maximum RoE, B/C ratio and minimum specific energy cost was then selected as the
optimum and detailed studies should be carried out for this option.
7.2.1 Hydrology
Capacity and energy potential of a particular option is dependent on the river flows.
Long term mean monthly flows at the intake site of the project are derived from
hydrological analysis carried out in detail for this project. Mean monthly flow series is
shown in Table 7.1.
These flows have been used in the computations of dry and wet energies and the
capacity potential for project optimization
To maintain the aquatic life in the dewatered reach of the river, 10% of the minimum
monthly flow, i.e., 1.049m3/s will be released from the headworks. Percentage flow
equal or that exceeding of the project is presented below.
UM-IHP 96
Feasibility Study Report
Sizes of all individual structures for each capacity option were computed to determine
the respective cost of the structure for the purpose of optimization. As the flood
hydrology does not change for the different cases, the design of weir and undersluice
has been kept constant. However, change in the installed capacity changes the design
discharge; accordingly, the sizes of settling basin and mainly the penstock pipe cost
were adjusted. The diameters of the penstock are designed based on the annual costs
and benefits. Powerhouse size is also changed inconsideration to the equipment
capacity.
Preliminary quantity and cost estimates were developed for all the cases considered.
Only the major items were computed in detail, while minor items were estimated based
on the rates and data of similar structures of other projects. As the optimization is a
relative process, it was considered sufficiently reliable for comparison purposes. Unit
rates were derived from completed projects in Nepal of this range of capacity of recent
projects undertaken by NEA and other private developers with some modifications.
Electro-mechanical equipment costs have been estimated with reference to similar size
of projects and from quotations of different suppliers and manufacturers and also based
UM-IHP 97
Feasibility Study Report
on the recent projects by private developers. The cost estimates also considered the
costs for access roads, infrastructure development and environmental mitigation costs.
Technical contingencies have been taken into account for obtaining the total
implementation cost of the alternative.
7.2.3 Range of Options and Energy Production
In order to determine the optimum installed capacity of the project, a total of four
alternatives ranging from38.70 MW to 70.5 MW with varying exceedence flows ranging
from 35% to 50% flow exceedence were considered to derive the optimum plant
capacity. Different alternative capacity and corresponding energy generation capacity
have been calculated.
As the project is run-of-river scheme, energy productions were calculated for all
alternatives considering average monthly flows as given in Table 7.1. The energy
produced is categorized into dry and wet energy. The design discharge given above
were derived for each of the flows assuming an overall efficiency of turbine, generator
and transformer as 86.40% and the head loss for each design flow is calculated in the
water conveyance system.
Gross head is calculated from the water level at the surge tank to the normal level of
tailrace. The summary of range of options and various types of energy produced are
given in Table 7.3. and detailed estimate of cost is given in Table 7.4
UM-IHP 98
Feasibility Study Report
UM-IHP 99
Feasibility Study Report
7.3 Conclusions
With respect to B/C ratio, internal rate of return and the specific energy cost,optimum
installed capacity is determined as 53.5MW.
Being a run-of-river project, lower installation is preferred as the higher installation will
only increase the production of secondary energy in the wet season, which is very hard
to realize in the Nepal Power system. Hence, plant capacity of 53.5 MW is selected as
the optimum case and recommended for the detail engineering of the project. The
optimum plant capacity of 53.5 MW corresponds to the design discharge of 33.6m3/s,
which is 40% of flow exceedance of Myagdi River.
UM-IHP 100
Feasibility Study Report
UM-IHP 101
Feasibility Study Report
8.1.1 Headworks
The headworks design is basically governed by the type of river, quantity of flow of
water and sediment, type of scheme, etc. For Myagdi Khola, the headworks layout has
been fixed considering quantity of flow of water and sediment in the river, design
discharge, existing topography, geological conditions and optimum utilization of space
needed. Besides, the project has been designed taking into consideration of the
efficient operation during all normal situations. Followings have been the basic
principles for design of the headworks for upper Myagdi I HPP:
a. Diversion works
The construction works across the river will be basically done during dry season time
during which the flow in the river will be less. However flood events are also possible
during such time, therefore coffer dam and diversion tunnel are necessary for
preventing any flood effect during construction period in the river channel. The
diversion tunnel in principle is designed to pass any potential dry season flood. The dry
season of months from November to April is regarded at the time of construction of
diversion weir, intake, undersluice and other pertinent structure and in particularly the
foundation works of these structures.
UM-IHP 102
Feasibility Study Report
The 1 in 20 years return period dry season flood is estimated as 52.85m3/s. This
discharge is selected for sizing of the river diversion works. The design has been carried
out by using Manning's formula taken into consideration of limiting velocity for
transporting the particle size larger than 50 mm. Details area as below
b. Overflow Weir
The diversion weir is composed of an uncontrolled concrete overflow weir having length
52m. In addition, two bed load flushing undersluice with vertical sliding gates are
provisioned. The crest level is fixed at an elevation 1359.00 amsl. The head over the
crest has been calculated by using the weir formula.
Q C L H 3/ 2
Where,
C : weir discharge coefficient and assumed 2.20 for broad crest weir
L : weir length in meters
H : flow depth over crest in meters
The diversion weir is designed to pass 1 in 100 years flood, which is estimated as 1453
m3/s. The flood water level for 100 years flood at the weir area has been determined
assuming that the flushing gates remain closed due to operating failure.Crest elevation
of diversion weir is fixed at elevation of 1359 amsl.Stability of weir is checked applying
following criteria:
Where
F = Factor of safety
c = cohesion (value = 0)
UM-IHP 103
Feasibility Study Report
Factor of safety against sliding should be equal to or greater than 1.5 for Normal
Operating Condition.
Factor of safety should be equal to or greater than 1.3 in case of Design Flood & OBE.
Factor of safety should be equal to or greater than 1.5 for normal operating condition &
1.3 for Design flood & OBE.The resultant force must fall within the middle third of the
base for all condition of loading uplift.
UM-IHP 104
Feasibility Study Report
C. Undersluice
A two bay undersluice having width 4m for each bay has been designed to prevent bed
load entering to the intake and possible build up of the bed load in front of the intake.
For controlling flow through the undersluice two gates have been provisioned. The
undersluice has been designed with the characteristics given below:
The maximum capacity of the undersluice at 100 years return period flood has
estimated by using orifice formula with the details given below:
Maximum discharge through submerged undersluice orifice for the design flood of 100
years return period in the river has been calculated using following relation and the
details.
Qmax C A 2 9.81 H
Where,
C : Coefficient equivalent to 0.67
H : Effective head over the orifice in meter
A : Opening area in square meters
d. Intake
Side intake has been designed to divert design discharge of 33.6m3/sec and 20%
additional discharge required to flush the sediment from the settling basins. Hence, the
designed discharge for the intake will be 40.32m3/sec. The intake sill level has been
UM-IHP 105
Feasibility Study Report
raised by 3.20m from the invert of undersluice to prevent the sediment entrance to the
intake.
The intake orifices have been designed as submerged orifices. The minimum
submergence of 0.3 m has been provided during normal flow in the river so that
floating debris does not pass through the orifices. Stoplogs and vertical slide gates have
been provisioned for controlling the discharge during high flood in case of emergency
and for maintenance purpose. The size of the orifice has been determined considering
low velocity to minimize head loss and entry of floating debris. The discharge that can
pass through the intake orifice has been calculated based on available head over the
crest and geometry of the orifice.
The design basis of each of the waterway structures are discussed below.
Headrace Tunnel
UM-IHP 106
Feasibility Study Report
The headrace tunnel alignment has been fixed based on the factors listed above. The
cross section of the Headrace Tunnel will be inverted-D in shape. It has been fixed
considering the practical approach. Inverted-D shaped tunnel provides comfort in
vehicular movement with extra space at the invert and sufficient overhead space for
ventilation and other general use. The diameter of the tunnel has been determined
after optimization. Basically, there are two different types of rock support for the
tunnel, concrete lining and shotcrete lining. It is an inverted D-shaped section with 4
m. in diameter.
The permissible velocity of flow and the potential headloss determines the hydraulic
requirement of the tunnel. Permissible velocity of 1.5m/sec in the shotcrete lined
section and 3m/sec for concrete lined section has been adopted for preliminary sizing of
the tunnel. Darcy Weisbach formula has been used to determine the headloss and
Colebrook and White formula has been used to determine the friction coefficient to be
used in the Darcy Weisbach formula
fLV 2
hl
2 gD
The frictional coefficient is determined using Colebrook and White formula, which is given by:
1
2.51
2 log 10
f
3.7 D Re f
UM-IHP 107
Feasibility Study Report
sections. The purpose of optimization has been to determine the economically optimum
and practically possible size tunnel that will yield maximum benefit. The cost of
construction and the benefit of saving headloss are the two parameters that determine
optimum size of tunnel. The cost of per meter length of tunnel construction is
determined from the quantity of works and their prevailing market rates. The value of
benefit loss per meter length of tunnel is determined from the possible per unit rate of
energy. The details of optimization are shown in the following Figure.
(i) provides a free reservoir surface close to the discharge regulation mechanism,
(ii) supplies the additional water required by the turbine during load demand until the
water velocity in tunnel has accelerated to the new steady state value,
(iii) stores water during load rejection until the conduit velocity has been retarded to
the new steady state value, and
(iv) Protects to the penstock itself against detrimental effects of water hammer.
i. Hydraulic Design
UM-IHP 108
Feasibility Study Report
For calculating the top level and bottom level of the surge shaft, the worst combination
of friction, load condition and reservoir water levels are considered. Both worst
conditions of up-surge and down-surge in addition to stability conditions are considered
in determining the water levels and shaft size.
Zi 1 Zi dz
The dynamic equation:
The change in velocity during the time dt is obtained as:
dV Z c V V K
dt L
g
UM-IHP 109
Feasibility Study Report
Lt = Length of tunnel
hfo = Head loss in tunnel
Ho = Net head
g = acceleration due to gravity
Time of Oscillation:
Maximum Upsurge
UM-IHP 110
Feasibility Study Report
Upsurge:
The powerhouse dimensions have been fixed based on the space requirement for
electro-mechanical items. The spacing of the turbines, dimension of the spiral casings,
space for service and maintenance of equipment, the geometry of the bifurcation, inlet
penstock pipe and outlet arrangement, etc have been considered in the dimensioning of
the powerhouse. The turbine center line has been fixed based on the average annual
monsoon flood level in tailrace outlet and turbine setting requirement to prevent
cavitation. The control building arrangement has been fixed based on the space
requirement for installation of different controlling equipment and other general
purpose usage. The tailrace canal is designed as free flow canal but will be box culvert
in shape so that backfilling on top would be done.
The dimension of the tailrace canal is fixed using the manning’s equation which is given
by:
2 1
1
Q AR 3 S 2
n
where, Q = Discharge (m3/s)
n = friction coefficient
UM-IHP 111
Feasibility Study Report
A = Area of flow, m2
R = Hydraulic Radius, m
S = Slope
Weir axis lies at about 100 meters downstream of the confluence of Myagdi&Mudikhola.
Rocks are exposed in both banks except riverbed. Exposed bedrock in steep slope of
Myagdi Khola is fine grained, grey to greenish grey phyllite with quartzite intercalation.
Quartz veins are present in the exposure with deformed boudin structures. Rocks are
thick to massive, medium hard and moderately weathered.
Foliation planes are measured along North east direction with Dip varying from 350 to
500. Other two prominent joint sets dip towards southwest and northwest at average of
70° to almost vertical. Joints are mostly tight occasionally slightly open, smooth, planer,
moderately spaced with moderate persistence. Intake area lies in recent alluvium
deposit.
Desanding system located at about 140.0m distance from the intake has two basins
designed to trap the sand silt of sizes equal to or greater than 0.2mm. These basins are
provided with flushing system to clean out the sediment deposits frequently. There are
vertical sliding gates at Upstream and down stream of the basin which will be used to
carry out the flushing of the sediment deposits. The flushing tunnel contains two parts
–upper part for inspection purposes and lower part for the discharge of sediment
loaded flow. The sediment flushing will be handled by using gates.
The mild pressurized headrace tunnel starts immediate downstream of the feeder
tunnels coming out of the desanding basins. It is approximately 500.00 meters long. It
has an inverted D-shaped section with finished diameter of 4.00 meters.
HRT will likely to pass through major portion of phyllite with quartzite rocks beginning
from the inlet. Downstream stretch of the alignment, then, passes through phyllite,
UM-IHP 112
Feasibility Study Report
schist and quartzite. The phyllite/schist of the stretch are fine to medium grained, grey
to greenish grey, weak to medium weak, slightly to moderately weathered. The
quartzite is fine to medium grained, grey to greenish grey, strong, slightly to
moderately weathered. However, several thin bands of shear zones are observed within
the Phyllitc Quatrzite at some locations along the tunnel alignment. The exact thickness
of these shear zones can be traced only after the tunnel excavation. No other major
structures such as fault and thrust are noticed in the tunnel section.The rock supporting
system comprising of steel fiber/wiremesh reinforced shotcrete and rockbolts is applied
according to the type of rock.
Surge shaft is located about 5500.00 meters downstream from the intake. It has a
orifice at its bottom. The diameter of the surge shaft is fixed at 6.50 meter. The
penstock starts from 60m far from the surge shaft. Penstock is about 770.00 meters
long.
At the left side there is two number of sediment flushing sluiceway with a width of 4
meters. The invert of the sluiceway has the elevation EL.1352.00. The sluiceway is
separated from the rest of the weir with a reinforced concrete wall. The excavated
surfaces will be provided with the steel fiber/wiremesh reinforced Shotcrete and
fullygrouted rockbolts (Refer drawing UMIHP-HW-001 to 004 in Vol II).
he intake is located at the left side to withdraw the design discharge 33.6 cumecs. Its
size is about 3.5 meter high and 4 meter wide with an intermediate pier of 1.5 m
thickness. A rack cleaning machine will be required to clean the rack of the intake.
Intake gate with stop log is provided about 14m far from the intake trash rack location.
Size of intake gate is 4m wide and 3.5m high. The rock support system comprising steel
UM-IHP 113
Feasibility Study Report
fiber/wiremesh reinforced shotcrete and rock bolts will be applied to the excavation
surfaces (Refer drawing UMIHP-HW-005&006in Vol II).
At a distance of 175 meter downstream from the intake the desanding arrangement has
been situated. It has two basins connected with two feeder tunnels. The basins are
provided with the inlet zones as well as outlet zones. The basin is 7.50m wide, 11.5 m
high and 120 meter long. The basin is equipped with vertical gates at its its end to
facilitate the flushing phenomena of the basin. At the end of the basin there is flushing
channel of width 3.0 meters. The flushing channel will be provided with a layer of 10
cm. thick abrasion resistant concrete. For operation of gates an enlargement of the
upper part of the desanding basin will be done to accommodate the gate hoisting
devices (Refer drawing UMIHP-SB-001 to 003 in Vol II).
Flushing tunnel will have an access facility for walkway on its upper part & discharging
section for sediment loaded flow on its lower part. The lower part is lined with a layer of
abrasion resistant concrete. The flow is regulated with the use of gate.
For excavation purposes an adit is planned to reach on the crown of the Desander
cavern. A small pilot tunnel will be made along its length. It helps to know the
conditions of the rock in the cavern & accordingly the support system can be made.
UM-IHP 114
Feasibility Study Report
Major rock type through which the headrace tunnel passes is Schist/Phyllitic Quartzite
on its upstream part. The downstream part lies on gneiss.schist.quartzite & phyllite. The
phyllite/schist is fine to medium grained, grey to greenish grey, strong to medium
weak, slightly to moderately weathered. Quartzite is fine to medium grained, grey to
greenish grey, strong, slightly to moderately weathered. Several thin bands of shear
zones are observed within Phyllitic Quartzite at different locations along the tunnel
alignment. In average the rock along the tunnel alignment is expected to have medium
strength.
Different Rock support types are developed. According to rock type the suitable support
system has to be applied. The rock support system comprises of steel fiber/wiremesh
reinforced shotcrete & rockbolts. The grouting will be carried out as per site
conditions.(Refer drawing UMIHP-HRT-001in Vol II).
The surge shaft is located about 5500 m.from desanding arrangement and will be the
shaft type. It will be about 55 m. high and 6.50 m. in diameter.
Penstock will start from the lower elbow. The penstock will be about 770 m long m
(Refer drawing UMIHP-PP-001 in Vol II). The contact grouting & consolidation grouting
will be carried out as per site requirements in the penstock tunnel part.
UM-IHP 115
Feasibility Study Report
Units will have the center line fixed at EL.1160.80. Valve floor, turbine floor, generator
floor andmachine hall will make the power house. Valve floor is comprised of the inlet
valve, pumps & all its related pipes. Turbine floor will have equipments related to
governor, mechanical workshop & cooling pipes. Generator floor will have switchgear
rooms. There will be loading, unloading area, rotor erection pad, maintenance area in
Machine hall. An overhead travelling crane will come in the machine hall to hoist the
equipments.
Tailrace cannel of about 220 m long will be a free flow type. It will be 4 m wide and
3.30 m high. The vertical gates in the tailrace cannel have been provided. At the end
there is a weir to keep the water maintained at the min. WL. Stone pitching is foreseen
on the side of the river for the protection against the scourm (Refer drawing UMIHP-
PH-001 to 005 in Vol II).
UM-IHP 116
Feasibility Study Report
Selection of type of turbine primarily depends upon the net head available and design
discharge. For the rated net head of 183.38meter and unit design discharge of
16.80m3/s, Francis Turbine having vertical shaft arrangement is the choice of the
turbine as presented in Figure 8.5
Selection of Turbine is carried out considering both the 2 units and 3 units option.
Rated discharge for two unit and three unit option is 16.8m3/s(marked by blue)and
11.2 m3/s (marked by green) respectively. With both the options the turbine for Upper
Myagdi-I Hydropower Projectfalls under Vertical Shaft Francis category.
UM-IHP 117
Feasibility Study Report
Selection of number of units is based on the assumption that minimum number of units
could be installed for the more economic development of the project, reliability of
generation, and minimum loss of power during maintenance and operation at difference
stage of time. Unit capacity is generally determined by considering the available
discharge throughout the seasons, load demand, type of operations, efficiency of the
machine, etc. Single unit is not preferred due to the fact that total generation loss will
occur in time of the unit breakdown and hence two or three units will be suitable for the
Project. With the rated flow of 33.60m3/s of the project, for two units the unit rated
flow is 16.80 m3/s. The leastdischarge for Upper Myagdi-I Hydropower Project is 9.441
m3/s for the month of March. Percentage rated flow for unit turbine for two units option
UM-IHP 118
Feasibility Study Report
during least discharge is about 56.20%. Similarly, the percentage rated flow for unit
turbine during least discharge for three unit options comes out to be 84.29%.
Hence, with three unit option, whenever the units will be running, they are expected to
run at the higher discharge thus running at the higher efficiency. Definite boost in dry
season energy is expected as compared to two unit option. It is also worthwhile to
mention here that with the three units option there is expected increase in cost of
powerhouse, hydro-mechanical (for trifurcation), tailrace and the operation cost after
power generation.Francis Turbine as identified from section 1.1.1 above may be
operated over a range of flows approximately 40 to 105% of rated discharge. Below
40% rated discharge, there can be an area of operation where vibration and/or power
surges occur. Had the percentage rated flow for unit turbine during least discharge less
than 40%, we would have opted for 3 units
Therefore, for a given design discharge and net head available at powerhouse, 33.60
m3/s and 183.38 m respectively, two units vertical axis Francis turbine is recommended
and succeeding discussions are based on it.
In calculating the required power output for turbine and generator for this study,
certain values of efficiency are assumed:
UM-IHP 119
Feasibility Study Report
Hydraulic Turbine
Governors
Pressure oil system
Main Inlet valve
Cooling water system
Drainage and Dewatering System
Mechanical workshop and equipment
Ventilation and air conditioning system
Fire protection system
Powerhouse overhead travelling crane
General design and performance specification for the mechanical equipment shall be
based on the standards issued by IEC and other publications such as Water Power and
Dam Construction, United States Department of the Interior BUREAU OF RECLAMATION
(USBR), IS-12800 (Part I) etc. On the above basis the design and selection of the
turbines are based on the following criteria derived from the main design parameters:
The unit should be sized to allow 27.8 MW to be delivered from each unit
at rated head and discharge continuously.
Turbine design and manufacturing shall permit easy dismantling of major
components for repair and maintenance based on a programme of routine
preventive maintenance.
Turbine shall be designed to achieve its best performance at rated head
and discharge.
UM-IHP 120
Feasibility Study Report
Two turbine units shall be identical making it possible to interchange between any of
the units. These turbines will be designed to operate continuously between minimum
and maximum output and within the head range presented in table below without
exceeding the permissible stresses, vibrations and bearing temperatures and without
undue cavitations. Further detailed information about the turbine operation during flood
periods and part load will be studied in the next phase of the study.
It shall be equipped with a self lubricating oil type guide bearing. Bearing will consist of
support or housing and a removable bearing sheet. It’sguide bearing will be of self
lubricated and water cooled and complete with oil reservoir and water cooling coil.
Turbine runner and the guide vanes will be made of stainless cast or welded steel, and
thus resistant to cavitation and sand erosion. In addition the turbine will be equipped
with replaceable wearing plates and labyrinth rings (rotating type on the runner and
fixed on the turbine head cover and bottom ring), all made of stainless steel. To
facilitate maintenance, all guide vane bearings, joints of regulating mechanism etc. will
be self lubricating type. In addition, the link between the guide vanes and the
regulating ring will be equipped with a self-restoring safety system to prevent an
overstress of the regulating mechanism, if one or several guide vanes are blocked by
squeezed trash material or any other reason
Draft cone will be equipped with two hinged-door manholes and accessible all around.
The draft tube cone will be dismantable to enable an easy replacement of the runner
from downwards of the spiral case of the turbine.
All turbine instrumentation, such as unit control boards, and governor control cabinets
will be located close to the relevant units on the turbine floor. This is advantageous for
commissioning, service and maintenance.
Parameters Unit Specification
UM-IHP 121
Feasibility Study Report
Turbine Components
I. Runner
The runner will be of the reaction type. Turbine runner will be Forged disc type having
stainless steel 13-4 Cr-Ni material. The blades are manually ground to the hydraulic
shape.
Runner will be designed to withstand the loads imposed by any combination of fully
open wicket gate operation at any speed including maximum runaway speed and
maximum head without exceeding the stress limits.
Runner shall be coupled with shaft through shear pin & central bolt. The runner and
shaft coupling is realized by several pins that transmit the torque. This design with
central bolt and shear pins consists of a central bolt from draft tube side to fix the
runner to the shaft. The torque transmission to the shaft shall be done via shear pins.
UM-IHP 122
Feasibility Study Report
Spiral case and stay rings are designed to withstand maximum transient pressures
under the worst condition of head and load with adequate safety margin. Hence, it will
be pressure tested in workshop at 1.5 times of the design pressure.
UM-IHP 123
Feasibility Study Report
protected by facing plates. Wearing ring will provide a seal between the runner and the
stationary part of the turbine and is bolted to the head cover assembly. Inspection
holes are provided to check the seal gaps.
Head cover consists of head cover, facing plates, coupling connection with stay ring,
hole for wicket gate stem bearing, coupling provision for runner crown seal wear ring,
holes for relief pipes, connection for clearance check at crown seal position and
coupling provision for shaft seal.
Head cover is a single plate design made of Structural Carbon Steel plates according to
IS 2062.
Bottom ring and discharge rings are made of Structural Carbon Steel plates according to
IS 2062.
V. Wicket Gates
Wicket gates are machined according to hydraulic shape and are mounted between the
head Cover &bottom ring. To allow for smooth movement of the wicket gates, self
lubricated bearings are used. The self-lubricated bearings are mounted in the bearing
housing. A thrust ring is provided at the upper stem.
Wicket gates are casted from ASTM A 743 Grade CA-6 NM.
All parts of Draft tube are made of Carbon Steel Plates according to IS 2062
UM-IHP 124
Feasibility Study Report
Based on site conditions specified above, the preliminary turbine dimensions are
calculated using Turbine-pro application. Some major dimensions of turbine and its
accessories are presented in Figure below. The runner diameter and runner weight is
approx. 1.549m and 3,183kg respectively.
UM-IHP 125
Feasibility Study Report
8.4.2.3 Governors
Each turbine unit will be provided with an efficient automatic governing system of
adequate capacity to control the turbine under all conditions. Control and operation of
the turbines will be possible either from the station control room or from the local unit
control panel for the purpose of commissioning and testing.
Control of the turbine will be accomplished by controlling the opening of the guide
vanes, with minimum loss of water so that pressure in the penstock never exceed given
limit. Governors will be designed and equipped for taking the unit automatically to the
rated speed at no-load operation. When the generator is connected to the grid, the
regulating parameters will be changed and load setting will be possible. Governors will
allow proper sharing of load between the two units under any condition of load and
speed without hunting. When the power house is interconnected with the existing
power system, units will be capable of synchronising with the other power stations in
the system.
Each unit will consists of a Digital Electronic Governor with Proportional Integral
Derivative (PID) action while running on isolated as well as on Load Sharing Module.
It will control the speed of the turbine via modulation of the guide vanes. The
governing system should be highly accurate and rugged.
UM-IHP 126
Feasibility Study Report
a. Two nos. (Single acting) wicket gate servomotor (Open by oil pressure & close by
spring action).
b. One no. (Single acting) butterfly valve servomotor (Open by oil pressure and close
by counter weight).
c. Hydraulic Brake of Generator.
For application stated above, pressurized oil is required. Two nos. of Gear pumps, one
as main & other as stand-by which driven by electrical motors, supply oil to the system.
Loading / unloading of the pumps shall be made by the signals given from pressure
switch provided at oil pressure line. The standard oil pressure unit operates under a
pressure of 64 bars. The high pressure units are advantageous because they require
smaller servomotors and associated parts. In addition, they use bladder accumulators
(viz. Nitrogen), thus eliminating the need for a separate high compressed air station.
A common accumulator (bladder type) is provided for MIV & Turbine wicket gate, which
maintain the required pressure in the system and also shall use for pressure oil supply
during emergency operation or pump failure. The capacity of the accumulator shall be
sufficient to meet the pressure oil requirements.
Butterfly type main inlet valves will be used for each unit. The valves are operated by
oil pressure supplied from the pressure oil servomotor of the governor. The valve will
be closed by counter weight. Each inlet valve will be provided with a pressure oil
operated by-pass valve. The by-pass valve will be of needle valve type and operated by
pressure oil to be supplied from the governor system.
UM-IHP 127
Feasibility Study Report
Due to the risk of high content of suspended sediment in the “raw” water during the
monsoon period, two circuit cooling system has been chosen.
One closed loop water circuit; the characteristic of this circuit is such that treated water
is circulated in closed loop through heat exchangers of different components to be
cooled; the loop also consists of an external heat exchanger in which raw water is used
for cooling the water in closed circuit.
(The heat exchanger in which water circulated in closed loop exchanges heat with raw
water from tailrace is referred to as “external heat exchanger”)
Two numbers of external heat exchangers, one on service and one as standby shall be
placed at tail race itself for each unit, where treated coolant in closed loop exchanges
heat with the cooled water of tail race.
The closed loop system branches to supply cooling water in many parts namely:
1. Branch circuit for oil-to-water heat exchanger in combined thrust and guide
bearing
2. Branch circuit for air-to-water heat exchanger in generator
3. Branch circuit for oil-to-water heat exchanger in generator guide bearing
4. Branch circuit for oil-to-water heat exchanger in turbine guide bearing
5. Branch circuit for turbine shaft seal cooler
6. Branch circuit for oil-to-water heat exchanger in governor
Each closed loop system will be equipped with two (2) units of floor mounted pumps -
one on service and one on standby.
Drainage and dewatering systems for the project are provided as follows:
(a) Station Drainage
Drainage water from different parts of the power station is collected in a deep drainage
sump. The drainage water from the sump is removed by two submersible water pumps
to the tailrace.
UM-IHP 128
Feasibility Study Report
The dewatering system is designed to collect the water drained out from draft tube,
turbine space & spiral case into the dewatering pit and then this water is pumped out
from dewatering pit with the help of submersible pumps into the tailrace channel.
Suitable size pump is provided to pump out the drained water from dewatering pit to
tailrace. The pumps are submersible type and when dewatering is required, the pumps
are lowered into the dewatering pit using chain pulley block. The pumps are operated
using a local electrical control panel near the pit in manual mode.
A mechanical workshop will be equipped with machine tools and devices appropriate for
the maintenance and repair of all mechanical components and machining of the smaller
components of the mechanical electrical equipment and hydraulic steel structures.
This system provides the fresh air to working personnel and removes the heat
generated by mechanical and electrical equipment. It also provides the smoke exhaust
ventilation in case of fire to minimize the circulation of smoke and production of
combustion. Ventilation and air conditioning system consists of fresh air handling unit
and air conditioning unit.
The fresh air handling unit is installed inside the ventilation room and consists of air
filters and three air admission fans, two “on duty” and one “stand by”. The unit sucks
air from outside and distributes it via appropriate ducting to different locations of
generator floor, turbine floor or other places such as control room.
The ventilation system will mainly consists of necessary numbers of axial ventilation
fans installed in appropriate locations. The various powerhouse rooms and areas like
switch- gear room, office floor, machine hall floor whose ambient are not air
conditioned are continuously supplied with fresh filtered outside air.
The Fire Fighting System is designed to safe guard equipment installed in the
powerhouse & switchyard area.The fire protection system shall comprise of following
main parts;
1) Fire Hydrant System for Power House & switchyard and Pump House Equipment
UM-IHP 129
Feasibility Study Report
The Hydrant system consists of over ground piping network, which is fed by 2 Nos. of
horizontal centrifugal pumps to be installed in Powerhouse. The Hydrant valves are
installed on the stand post, which is connected to the main header pipe and each
hydrant valve is strategically located around Power House equipment.In the event of
fire, with the rapid fall in header pressure due to opening of hydrant valve the common
fire pump shall start automatically. In case of failure of main fire pump the standby fire
pump will come into operation at a time.
2) CO2 fire protection for Generator and Water Spray System for protection of
Transformers and switchyard equipments
Automatic High Velocity Water Spray System will be used to protect power
Transformers located in switchyard area. The transformers and switchyard equipments
will be surrounded by a ring fitted with open high velocity spray nozzles. The ring main
will be connected to the spray system header through a wet pilot deluge valve fitted
with water motor gong and with upstream and downstream Gate Valves. The header
will remain charged with water under pressure up (7.0 bar) to the inlet of the deluge
valve
Generator fire protection will be provided by a CO2 deluge system. The activation of CO2
fire protection system will be conditional to the operation of the flame or smoke
detectors in the generator pit combined with the operation of the generator differential
protection. The extinguisher release will only be initiated after a preset time delay and
confirmation by operators in order to allow evacuation of the personnel in the hall at
that moment. The extinguisher release will first initiate Unit shutdown procedures by
opening circuit breaker and excitation system before release.
A double girder Electric Overhead Travelling (EOT) crane having main hook capacity of
85 tons will be installed inside the powerhouse. It will be used for lifting and handling
any equipment during installation, maintenance, and operation of the plant. Basic data
UM-IHP 130
Feasibility Study Report
and governing dimensions of the powerhouse crane are given below in Table 8.1.The
crane shall be complete in shape conforming to the standards of the Power House
service. Supply shall include current collector, down shop angle conductor with bracket,
insulator.The LT rails shall be supplied long with the crane.
8.4.3.1 Generator
The stator winding of the generator will be made of individually insulated stranded
copper conductors, stacked and form pressed to constitute coils or half coils with the
design cross section. Each coil will be insulated for the full generator voltage.
The rotor will be of the salient pole type and built in accordance with the best practice
and designed to withstand safely all overloads and other stresses encountered during
UM-IHP 131
Feasibility Study Report
abnormal operating or runaway speed conditions. The poles will be built of thin steel
laminations, bolted under high pressure and furnished with dovetails for fastening to
the rotor rim. Rotor will be designed so as to allow dismantling of the poles without
excessive disassembly of the stator or rotor. The damper winding will be installed on
pole faces with interconnecting type windings in order to maintain the stable operation
of the generator.
The generator shaft will adopt single shaft structure. It will have maximum rigidity and
strength so as to guarantee no abnormal deformation and vibration at various speeds
(including maximum runaway speed) when run together with the turbine. The
generator shaft shall be made of a high quality medium carbon steel, properly heat
treated and accurately machined all over and polished at the bearing surface sand at all
accessible points for alignment checks. A complete set of test reports covering
metallurgical strength, & ultrasonic tests performed on each shaft shall be furnished.
The generators will have enough electric heaters and dehumidifiers and arranged in fan
shield of generator to protect it from moisture during shut down and to enable a start
up at any time without drying procedure. Insulation and other parts of the generator
will not be damaged when electric heater runs.
Description Parameters
Type Salient pole, synchronous
Capacity 31760kVA
Power Factor 0.85
Generating Voltage 11kV
Frequency 50Hz
UM-IHP 132
Feasibility Study Report
Class of Insulation F
Protection IP54
Excitation System Type Static
Efficiency ≥ 97%
Heating class B
Number of Poles 14
Synchronous Speed 428.5
Generator Cooling TEWAC
Generator fire protection will be provided by CO2. The activation of the CO2 fire
protection system will be conditional to the operation of the flame or smoke detectors in
the generator hall combined with the operation of the generator differential protection
or a manual push button instruction. Upon receipt of a signal from the fire detectors
and of the generator differential relays, an alarm will be initiated. The CO2 release will
only be initiated after a preset time delay in order to allow evacuation of the personnel
in the hall at that moment unless the operation is aborted by manual interruption
instruction.
As per IEC 60034-1, the rated voltage of generator with minimum rated output of
2500kVA lies between 11kV<Un≤15kV. Hence, considering the size of the generator,
insulation problem, switchgear connection and common practice, the generator voltage
of 11kV is selected.
These switchgear panels will have inbuilt bus bar cabinets housed in its back. Each
generator’s output terminals shall be connected to this 11 kV bus bar system with XLPE
UM-IHP 133
Feasibility Study Report
cable of adequate size. Switchgear and other protection and control components will
accompany them in the switchgear panel to complete the incoming generation power
circuit. Individual switchgear panels for each generator incomer and outgoing feeder
will be provided to complete the generation level switchgear system. This switchgear
system will work in co-ordination with the control panels accommodated in the control
room.
Neutral Grounding will be high resistance grounding type, provided with a dry type low
resistance connected to the secondary of distribution transformer.
Distribution transformer will be of 50Hz, enclosed dry type, air natural (AN) cooled.
The Primary of Transformer will be connected solidly between Neutral of Generator and
the Ground.
Ground current will be limited to 3 to 15Amp when the single phase to ground fault
occurs in the Generator terminal.
Primary voltage rating of distribution transformer will be 11kV and the secondary will be
240V.
Distribution transformer and Resistor will be mounted on a separate panel near to each
generator.
Each generator will be equipped with static excitation system consisting digitally
controlled Automatic Voltage Regulator (AVR) equipment, excitation transformers,
thyristors and auxiliary equipments and power supply.
Excitation system will be fully automatic with a provision for automatic change over to
the manual control system. Both the automatic and manual operation circuit will be
provided with independent power supply and phase control unit.
UM-IHP 134
Feasibility Study Report
Excitation power shall be taken from the generator itself, through a branch-off from the
generator terminal bus bars. Excitation will be independent of any outside power supply
except for field flashing during initial built up of generator voltage.4
Excitation transformer will be AN cooled, of dry insulated type using non -flammable
Class F insulating material. Rated power of this transformer shall be 10% above the
power necessary for the excitation of one unit.
Two full-wave rectifier bridges (thyristor converters) connected in parallel so that one
bridge may be removed for maintenance whilst retaining full load excitation without any
restrictions.
Excitation shall be suitable for maintaining the voltage for a grid voltage variation of ±
5% & for a frequency variation of ±3%. AVR shall be sensitive enough to track and
respond the changes upto +/- 0.5% of normal voltage (average of 3 phases) of the
Generator when operating under steady load conditions (for any load) or excitation
within operating range and shall initiate corrective action without hunting. Response
time of excitation system shall be less than 20ms.
After the initial maximum voltage following any load rejection up to 100% of rated load,
the AVR shall restore the terminal voltage to a value not more than 5% above or below
the voltage being held before load rejection and shall maintain the voltage within these
limits throughout the period of generator over speed.
UM-IHP 135
Feasibility Study Report
a. Two auto channel with one manual mode for voltage control
b. Voltage / frequency during accelerating and decelerating of machine
c. Power factor / KVAR control mode
d. Reactive power shedding
e. KVAR limit
f. Diode failure indication
Besides these, equipment for limiting and regulating (both automatic/manual mode) on
generator rotor current shall be included. Voltage setting devices and necessary control
switches shall be included.
Power transformers are used to step-up the generated power so as to evacuate the
generated power to the nearest substation. Main transformer in Upper Myagdi I
Hydropower Project shall have three single phase, outdoor, oil immersed, ONAN type,
each of 10500kVA, to form single three phase bank on each unit. There shall also be a
provision of one spare transformer.
UM-IHP 136
Feasibility Study Report
Table 8.4: Data for Auxiliary Transformer and isolation transformer at UMIHP
UM-IHP 137
Feasibility Study Report
3 Cooling ONAN
4 Rating 1000 kVA
5 Maximum Voltage Primary side – 12kV and Secondary Side – 12kV
6 Rated Lightning Impulse withstand Primary side - 75kV and Secondary Side 75kV
Voltage
7 Power Frequency Induced Over Voltage Primary side - 28kV and Secondary Side 28kV
8 Type of Tap changing Off Load on star voltage side
9 Tap Changing Range ±10% in Steps of 2.5
10 Vector Group reference Dyn11
8.4.3.9 MV Switchgears
Each Generator shall be synchronized with 11 kV Vacuum Circuit Breaker (VCB). All the
generators circuit breakers and fuse switches will be arranged in one row accessible
from the front side with sufficient space on both side of the switchgear assembly for
safe operations.
UM-IHP 138
Feasibility Study Report
A. Current Transformer
The current transformers will be of dry, synthetic resin insulated type. All secondary
connections will be connected to a terminal block which will be located in a dust-proof
and watertight terminal box and will be clearly labeled. An earth connection to the
housing will be provided.
The core for measuring purposes will have the following characteristics:
Accuracy class 0.5
The rating, burden and location of current transformer shall be as specified in Single
Line Diagram (SLD).
B. Voltage Transformer
The indoor voltage transformers will be of the single-phase dry synthetic resin type. All
primary and secondary connections will be clearly marked. An earth connection to the
housing will be provided. Earthing of the cores and the neutrals will be done on the
transformers and not on the terminal boxes.The windings for measuring purposes will
be designed for accuracy according to class 0.5.
Voltage transformers will have an additional secondary winding for earth fault
protection, connected in open delta with a resistive burden. The accuracy class will be
3P.
Secondary will be provided with miniature circuit breakers with alarm contacts and
primary will be protected with a fuse.
Burdens of all windings will not be less than 125% of the overall computed (design)
burden of the connected apparatus including cables.
UM-IHP 139
Feasibility Study Report
Particular Specifications
Type Indoor, oil-immersed
Frequency 50Hz
C. Lightning Arrestors
Lightning arresters will be of the gapless metal oxide (MOA) type. Generator will be
protected against incoming voltage surges by means of lightning arresters connected
between phases and earth.
Outdoor lightning arresters will be mounted on steel structures and will be fitted with a
pressure relief device. Surge counters shall be supplied. Earth conductor from the
arrester to the counter, as well as the terminal of the counter, will be suitably insulated
or screen protected against accidental touching. Lightning Arrestors for the protection
of generator will be of rated voltage 12kV.
Frequency 50Hz
UM-IHP 140
Feasibility Study Report
Metal enclosed, Cubicle indoor type, three phase vacuum circuit breakers are used in
the 11kV side of Power house equipments. This includes, Generator Circuit Breaker (2
Nos), Delta side of Station auxiliary Transformer (2Nos) and Delta side of Power
Transformer (1 Nos)
It is proposed that one emergency generator set be installed in the diesel generator
building to provide an emergency source of power in the event of a system and power
outage. Diesel generator would be of adequate rating to supply sufficient power to
enable the black starting of one unit, and the operation of drainage pumps, a governor
oil pump, a bearing oil pump, an air compressor for governor system, and feed the
battery chargers. Diesel generator for power house purpose will be of 350kVA, 400V,
50Hz, 3 phase type. The diesel generator shall have heating class B, insulation class F
and IP23 type of Protection of enclosure.
For the utmost reliability, control, protection, alarm, and tele-metering equipment will
be fed from a dc supply. Emergency lighting can be dc, autonomous individual units or
with UPS (uninterruptable power supply). For the purpose of this study, a dc battery
supplied emergency lighting has been selected. The DC Auxiliary system in UMIHP will
have 110V/450Ah DC battery bank. A DC–DC converter shall generate 48V DC,
from110V DC system and 24V DC, if required. Vented Type Lead Acid batteries are used
for DC Auxiliary system of UMIHP.
1 No. float and float cum boost charger (SCR controlled) operating on 3 Phase,415 V,
50 Hz, AC supply of solid state design to charge the battery shall be used. The
operation of the charger shall be automatic. Normally, float charger will be feeding the
UM-IHP 141
Feasibility Study Report
load and charging battery. In case battery requires boost charging the same shall be
done automatically
Low grounding resistance will be achieved by increasing the grounding area i.e.,
interconnecting the powerhouse ground system with the tailrace pond and other areas.
Ground resistivity measurements will be required which will be performed during the
detail design of the grounding grid.
Power House roof shall be provided with Lightning spikes properly connected to ground
mat.
The power plant shall have black start facilities and shall be able to operate in islanding
mode operation. Detail of islanding mode of the operation shall be as fixed in the
connection agreement or as per the NEA grid code.
For communications between UAKH power house, other power houses / substations
together with the Load Dispatch Center (LDC) of NEA, trunk dialing telephone system
UM-IHP 142
Feasibility Study Report
(either CDMA, V-SAT communication or Landline phone will be used) and provision of
communication system via fibre optic cable is also considered.
Optical fibre cable strung through overhead distribution poles will be used for means of
communication and data exchange between Powerhouse and Headworks.
In the control room one or more telephone service will also be installed for trunk dialing
communications with the LDC and other substations.
8.4.3.15 Illumination
400V/230V, 50 Hz, 4 wire star connections supply will provide single phase supply for
the illumination circuits for normal lighting.
Normal lighting in the rooms of the power house through corresponding Distribution
Boards (DBs) will be by fluorescent fixtures and energy efficient PL-S fixtures. Apart
from this arrangement; emergency DC supply circuits and fixtures will provide
illuminations, in critical areas when supply from Station auxiliary transformer fails. In
the main entrance incandescent lamp lighting fixtures will be installed. Lighting level /
illuminations designed are presented below:
450 lux – for the Control room, Office room, Electrical workshop, Mechanical workshop,
service bay, turbine floor, Generator floor and MIV floor.
300 lux – for the LV-switchgear room, MV- switchgear room, Battery room and other
facilities.
200 lux – for the pump pits and surge tank area.
150 lux – for the stair cases.
Socket outlets will be provided in the office room, control room, battery room, service
bay, alternator and turbine floor.
Computer supervisory and control system at UMIHP shall adopt the full distributed
mode in open environment in accordance with international open system concepts so
that compatibility of selection of various computers, transplantability of system
expanding and renewal of equipment shall be assured
UM-IHP 143
Feasibility Study Report
Computer supervisory and control system shall have station control level (main control
level) and local control unit level.
Station control level, real time supervisor and control centre of the plant shall be
responsible for automatic functions of the whole plant (AGC, AVC, generating
optimization control etc.), historical data process (various operation tables, operation
archives of important equipments and various operating parameters etc) and man
machine dialogue of whole plant (operation monitor of plant equipment, accident and
failure alarm, manual intervention of operating equipment, modifying and setting of
various parameters for the Computer Supervisory and Control System). Station control
level shall be made up of the relevant equipment located at computer room and central
control room. Main computer will adopt dual computers for redundancy and hot
standby. At normal condition a computer works and the other is backing-up. When
master computer receives failure, the main computer is changed-over by back-up.
Local Control unit (LCU) shall have turbine-generator local control unit. Each LCU shall
manipulate production procedures and accomplish the supervision and control functions
under controlling. LCUs will be connected with the production procedures by means of
input and output interface, with the network by communication interface and
exchanging information with main control level through network. The information shall
be exchanged among LCUs. LCUs may be independent from main control level
relatively. They shall directly finish real time data acquisition and pre-processing,
supervision, adjustment and control etc. of unit equipment conditions with station
control level divorced.
Operator’s console in the central control room shall be equipped with CRT display that
displays operation conditions of the power station. When the power station is under
normal operation, the operator can monitor the conditions of each equipment in the
power station. Major monitoring items shall be as follow:
UM-IHP 144
Feasibility Study Report
When the system receives any fault or the equipment has abnormality during operation,
the supervisory control system shall automatically give alarm in both sound and picture
striking to the eye to indicate nature, location, time and abnormal parameter values of
the event.
132kV outdoor type switchyard shall be constructed near the powerhouse to evacuate
the generated power. Switchyard components shall be suitable for hot, humid and
moderately polluted environment. Switchgear system for this switchyard shall be
equipped with circuit breakers, current transformers, potential transformers,
disconnecting switches with/without earthing and lightning arrestors and synchronous
check relay etc. for 132 kV incoming and outgoing circuits. Switchgear system here will
work in coordination with the associated control panels accommodated in the control
room and shall ensure the overall protection of the switchyard.
Measuring and protection equipments shall be installed for 132kV side protection of the
outgoing line as well as the interconnection substation as shown in the SLD. Technical
details of measuring and protection equipment shall be as follows:
UM-IHP 145
Feasibility Study Report
Frequency 50Hz
Particular Specifications
Type Outdoor
Frequency 50Hz
Particular Specifications
Type Indoor
Frequency 50Hz
Hydraulic Steel Structures at Head Works, Desander, Tunnel Inlet, and Tailrace of
Upper Upper Myagdi-IHydropower Project mainly consist of the following:
UM-IHP 146
Feasibility Study Report
Head Works
Undersluice/Spillway
Stoplogs
Intake
Trashracks
Stoplogs
Intake gates
Desander
Desander Flushing gates
Tunnel Inlet
Tunnel Inlet gates
Powerhouse
Draft tube gates
Tailrace
Tailrace outlet gates
In order to prevent the entry of the sediments in to the intake, two vertical gates are
provided on the left bank. Size of the opening is of 4.0m wide and 4.8m high to flush
the bedload sediments which will be accumulated in front of the Intake.The Invert level
of the flushing gate is fixed at elevation of 1352.00m
UM-IHP 147
Feasibility Study Report
Stoplogs will be provided at under sluice and spillway for maintenance of gates and
other structures and flow regulation. They will be made of structural steel and shall be
all welded construction. Skin plate and seal arrangement will be on the upstream side.
The uppermost element will be equipped with filling valve, which will be opened by the
dead weight of the grappling beam and closed by springs. Rubber seals will be of music
note shape at sides and of rectangular shape at the bottom. Embedded parts will
include the guide and seal frames, as well as dogging devices for storage of the
stoplogs in the slots and respective storage pit. Gantry Cranes for handling stoplogs will
be provided.
Gantry crane will be capable of raising and lowering the stoplogs with a grappling beam
and lifting small loads during maintenance and repair of gates. The crane will be of a
welded box type construction with four legs supported on wheels. The wheel will be
tracked on rail. It will be electrically operated and driven by two synchronous drive
wheels.
Vertical lift fixed wheel type gate will be provided at intake for regulation of flow. It
shall consist of gate leaf, guide frame, guide rollers, and hoisting equipment. It will be
made of structural steel as stated above and will be of all welded construction. Rubber
seals will be provided for water tightness of the gates. Guide frame of gate will consist
of a sill beam, side frames, and lintel beam. Hoisting equipment of suitable capacity will
be provided for lifting and lowering the gate. The principal dimensions and main
features of the gates are presented below:
Clear width : 4m
Height : 3.5m
Sill elevation : El. 1354.70
Total number of gates : 1
The intake trash-rack shall prevent larger floating, or semi-floating matters entering the
intake and settling basins.
Three sets of Trashrack will be provided at the Intake for the purpose of preventing
injurious matter and floating matter going to the water turbines and other equipment.
Clear opening (width between bars) of the rack bars will be smaller than the smallest
UM-IHP 148
Feasibility Study Report
opening between the runner blades. Trash rack will be designed to withstand the
impact forces, static loads and vibration phenomena which are likely to occur due to the
flow of water through rack bars. Suitable trash cleaning equipment will be provided at
coarse and fine trashracks.
Each trash rack will be made of structural steel plates spaced parallel to each other by
spacers. It will be supported by horizontal beam, built up type construction and fixed
by the steel bolts, nuts and washer. Rack bar spacing will be of suitable size.
It will consist of the bar elements, supporting beams and all other necessary
components. The trashrack panels will be fixed on the supporting beams using
corrosion-resisting bolts, nuts and washers. The bars elements of the trash rack will be
of rectangular section bars. Suitable thickness of the bars shall be used. All bar
elements shall be rigidly fixed on the supporting beams to prevent vibration.
Supporting beams will be of I-beam, H-beam, built-up and/or angle type steel
construction and all or both ends of the beams shall be embedded in the concrete
structure. The maximum deflection of the supporting beams shall be less than 1/500 of
the clear span at the centre under full load.
Stoplogs will be provided for repair and maintenance of Intake gate. It will be handled
by the gantry crane at Intake. They will be stored partly in the upper section of the
stoplog slot and in the separate storage pit if required near the operating deck.
The gates shall consist of gate leaf, guide frame, guide rollers, and hoisting equipment.
The gates will be made of structural steel as stated above and will be of all welded
construction. Rubber seals will be provided for water tightness of the gates. The guide
frame of gate will consist of a sill beam, side frames, and lintel beam. The hoisting
equipment of suitable capacity will be provided for lifting and lowering the gate.
UM-IHP 149
Feasibility Study Report
and 5.00 m high. Vertical gates are operated by a hoisting mechanism. The gates are
fixed at sill level of 1333.08m
Tailrace gate of size of 4.5m wide and 3.5m high are provided at the outlet of the
powerhouse. This gate prevents the back water flow from the Myagdi Khola in the case
of flash flooding and maintenance purpose. Vertical gates are operated by a hoisting
mechanism.
The Steel penstock of Upper Myagdi-IHydropower Project will consist of straight pipes,
bends, branches (manifolds), trust collar, seepage rings, manholes and other necessary
components. The internal design pressure will be the sum of the static water pressure
and water hammer. The external pressure, being the ground water pressure, is
calculated from the vertical distance from the steel lining axis to the ground surface on
the top of the hill.
Density of the steel is 7850 kg/m3. Penstock will be designed to take of internal and
external pressure by shell itself. Total length of penstock pipe is 770m and the diameter
of the pipe is 3000mm. Thickness of the steel liner will vary from 14mm to 24mm.
UM-IHP 150
Feasibility Study Report
UM-IHP 151
Feasibility Study Report
9.1 Introduction
This chapter includes power and energy scenario of the project and the country.
Regarding the generated power and energy, NEA is solely responsible for the planning
and distribution of power & energy generated by its own as well as private hydropower
plants. All the private developers require PPA with NEA prior to the construction of
hydropower plants. Hence, NEA is the sole buyer of the power generated from the
project. Once the power is generated, it will be connected to the national grid and the
private hydropower plants get paid as per the rate in Power Purchase Agreement.
UM-IHP 152
Feasibility Study Report
Mangsir
Baisakh
Ashwin
Chaitra
Bhadra
Falgun
Jestha
Ashad
Poush
Kartik
Magh
Days
Avg, m 4.91 13.88 14.11 14.11 14.11 14.11 12.62 4.43 2.79 2.93 2.53 2.96
The monthly flow (m3/s) available for energy generation at intake site of Upper Myagdi-
I is given below:
Mangsir
Baisakh
Ashwin
Chaitra
Bhadra
Falgun
Jestha
Ashad
Poush
Kartik
Magh
17.55 33.60 33.60 33.60 33.60 33.60 31.85 16.25 10.65 11.25 9.45 11.35
As seen from the above monthly data, the monthly discharge on the river varies from
9.45 m3/s to 33.60 m3/s. Since the efficiency of the Francis turbine is dependent of
UM-IHP 153
Feasibility Study Report
discharges, the generation capability of the plant will depend on the number of turbine
unit selected. For this project the number of units proposed is two.
P = 9.81 x x Q x H (kW)
Therefore,
P = 9.81 x 0.8829 x 33.6 x 183.62= 53.44 ̴ 53.50MW
Where:
η = 0.8829 (combined efficiency of Francis turbine, generator and transformer)
Q = 33.6 m3/s (design flow)
H = 183.62 m (Effective head)
UM-IHP 154
Feasibility Study Report
Note:
1. Dry Season (Mid-Dec/Paush to Mid-Apr/Chaitra) 46.22GWh
2. Wet Season (Mid-Apr/Baisakh to Mid Dec/Marga) 261.46GWh
3. Total energy 307.68 GWh
45.00
40.00
35.00
30.00
Energy (GWh)
25.00
20.00
15.00
10.00
5.00
0.00
Months
UM-IHP 155
Feasibility Study Report
UM-IHP 156
Feasibility Study Report
Objective of this report is to develop the most optimum power evacuation scheme for
the Project up to INPS (Integrated Nepal Power System) on techno-economic basis. In
order to do this, it is necessary to review the existing INPS, its future generation &
transmission plans as well as its future load forecast. The study and analysis has been
performed as per standard practices. All available power evacuation options have been
explored in the study and the most optimum scheme(s) identified among the
possibilities on technical and economic basis.
Annual peak power demand of the Integrated Nepal Power System (INPS) in fiscal year
2013/14 is estimated to be 1,201MW, with 410MW power estimated to have been shed.
Out of the 791MW of power actually supplied, 436.4MW was contributed by NEA hydro,
22MW by NEA thermal, 216.4MW by IPP hydro and the rest 116.2MW was import.
Compared to the preceding fiscal year’s figure of 1,094.6 MW, the annual peak power
demand of the INPS registered a growth rate of 9.7 %.
UM-IHP 157
Feasibility Study Report
From Bharatpur substation a s/c 132 kV line is running to Pokhara via Damauli. One
each s/c ACSR Duck 132 kV lines are connecting Marshyangdi P/S to Bharatpur and
Suichatar substations. One each s/c ACSR Cardinal 132 kV lines are connecting Middle-
Marshyangdi P/S to Marsyangdi P/S. 132 kV d/c ACSR Duck line is connecting
Kaligandaki P/S to Butwal substation where as Kaligandaki is also connected to Pokhara
substation by 132 kV s/c ACSR Duck line. Modi P/S is also connected to Pokhara
substation by 132 kV s/c ACSR Bear line. Kulekhani-II is connected to Kathmandu and
Hetauda by 132 kV d/c ACSR Bear lines (only one circuit strung each). Kulekhani-I is
connected to Kathmandu and Hetauda by 132 kV d/c ACSR Wolf lines. Hetauda
connects Birgunj by 66 kV d/c ACSR Wolf line. 132 kV s/c ACSR Bear lines connect
Khimti-I and Ankhu to Lamosanghu which is further connected to Kathmandu by 132 kV
d/c ACSR Bear line.
UM-IHP 158
Feasibility Study Report
The Kathmandu valley absorbs a considerable fraction of the INPS load and the supply
to Kathmandu area is mainly through,
UM-IHP 159
Feasibility Study Report
Many more hydropower plants are planned for construction in near future. The
generation plants coming in future are as follows,
10.5 Substation
Transmission system reinforcements that have been taking place are mainly driven by
load growth and partly by generation additions.
Following are list of substations that are planned to be constructed within FY 2016/17.
Table 10.3: Planned substations
S.No. Substations Remarks
1 Khimti 220/132 kV HPP connecting to Khimti and Tamakoshi area
2 Phidim 132 kV Kabeli Corridor
3 Kabeli 132 kV Kabeli Corridor
4 Godak (Ilam) 132 kV Kabeli Corridor
5 Tadikuna (Khudi Hub) 132 kV Marsyangdi Corridor
6 Udipur Hub (New Middle Marsyangdi) 132 kV Marsyangdi Corridor
7 Anbukhaireni (New Marsyangdi) 220/132 kV System Reinforcement
UM-IHP 160
Feasibility Study Report
In order to meet the increasing load demand and for power evacuation from plants as
per the Generation Expansion Plan, NEA has developed transmission expansion plan.
The transmission lines as per Government 38 point that are planned to be constructed
within FY 2016/17.
UM-IHP 161
Feasibility Study Report
Cost estimate for 132 kV and 220 kV is based on NEA’s Transmission System Master
Plan 1998 (TSMP-1998). The estimated cost for lines with conductor sizes and voltages
of our concern are as shown in the table below.
Table 10.6: Transmission Line Costs [kUS$/km, excl. of taxes and duties]
Conductors per phase 132 kV 220 kV
s/c d/c s/c d/c
1 x Wolf 59.3 94.8 - -
1 x Bear 77.0 123.2 - -
1 x Bison - - 102.2 163.5
UM-IHP 162
Feasibility Study Report
132kV and 220kV cost estimate is based on NEA's TSMP-1998. The estimated
substation costs for various voltages of our concern are as shown in the table below.
The following maximum transport weights are assumed to apply for Nepal.
UM-IHP 163
Feasibility Study Report
700
Capatilized Cost (KUSD/km)
600
500
132kV S/C Wolf
400
132kV DC wolf
300
132 kV SC Bear
200 132 kV DC Bear
100
0
0 20 40 60 80
Installed Capacity (MW)
As seen from the figure 10.1, "132 kV SC Bear" line exhibits the least capitalized cost
for evacuation of 54 MW power at 0.70 capacity factor. Moreover, this option will be
economical for power evacuation of higher plant capacity as well.
The calculation is primarily performed on per km transmission line basis, and is as such
not dependent on the length of the transmission line. The formulas used for the
calculation are given in Figure 10.2 below where,
UM-IHP 164
Feasibility Study Report
a. AC Resistance Values
The AC resistance in a line is dependent on the temperature and thus on the loading.
With high power transfer, the conductor temperature will be high. To be on the safe
side, the ambient temperature is considered as 40°C. For economic optimization, it is
preferred to use conservative resistance values, i.e. resistance at maximum or close to
maximum operating temperature. In this optimization, an operating temperature of
75°C has been selected. For the conductors used in this study, the following value of AC
resistance has been used;
• ACSR Wolf - 0.2187 Ω/km for single cktand 0.1094 Ω/km for doubleckt
• ACSR Bear - 0.131 Ω/km for single cktand 0.0655 Ω/km for doubleckt
c. Energy Cost
The energy cost normally used for the optimisation of the transmission lines is the long
run marginal cost of generation. The average incremental cost of generation better
reflects the real value and is therefore used. The average incremental cost of
generation as per TSMP-1998 is 6.02 USc/kWh.
UM-IHP 165
Feasibility Study Report
10.9.2 Evacuation
Power generated from UMIHP is proposed to be evacuated at the proposed Dana
substation which is approximately 28km away from the powerhouse area
Load flow studies need to be conducted to maintain the permissible voltage variations.
However, the voltage for transmission should be the standard one commonly used
depending upon the amount of power to be transmitted, the length over which the
power is to be transmitted and the existing transmission facilities available at the
nearest point from the Project location. For this Project, the following options have
been studied.
UM-IHP 166
Feasibility Study Report
UM-IHP 167
Feasibility Study Report
existing HT/LT
lines
5 No. of stream 5 6 8
crossing
6 No. of settlement 2 2 5
crossing
7 No. of road No road crossing No road crossing No road crossing
crossing
8 Forest area (km) 16 km 12 km 8km
(62%) (45%) (26%)
9 Marshy and Not seen Not seen Not seen Cannot be
unstable area identified in
map
10 Any other impact None None None Will be
identified in
detail study
11 Any other None None None
permanent
structure
12 Advantages Shortest Length Less Forest, Less Less forest
less forest settlement and affected, slight
cliff access facility
13 Disadvantages Cliff area and high Slightly longer Longer length,
forest than option I, more settlement
area, More stream
14 Order of Priority 2 1 3
Based on the exercise carried out in this study and the comparison made within the
identified alternative routes, it is fair to recommend Route II as final route. Since there
is more less forest and cliff along the proposed line route and not much difference in
line length as compared to shortest line Route I.
UM-IHP 168
Feasibility Study Report
UM-IHP 169
Feasibility Study Report
11.1 General
Feasibility study shows that implementation of this project is technically and financially
viable and worth for implementation. Financial study has been carried out to check the
feasibility of this project. Accordingly the implementation schedule of Project has been
prepared for the construction of the project.
Critical sequences of major project activities following the take-over of the project
implementation are as follows:
Project construction schedule and cost estimate of the project are prepared on the basis
of the present study. It will be refined during the detailed engineering of the project.
UM-IHP 170
Feasibility Study Report
Construction power required will be approximately 1.5 MW at peak load. The number
and capacity of transformer are estimated, as mentioned in the Table below.
For the headworks, the area near the suspension bridge in the left bank of Myagdi River
is selected for construction of a contractor’s camp.For employer’s permanent camps and
office, the area close to the confluence of Mudiand Myagdi River at the leftt bankseems
appropriate. For the construction of headrace tunnel from construction adit, temporary
construction camp will be needed and it will be arranged around Basbot village.For the
powerhouse and surge tank, area around powerhouse site in the left bank of Myagdi
River can be used for a labour camp.
UM-IHP 171
Feasibility Study Report
Once river diversion work is complete the construction work will commence from the
excavation at the left bank at the intake, flood guide wall areas. After the excavation
the foundation work for upstream flood guide wall, undersluice, right part of diversion
weir and intake will commence. The part of construction of all these structures will be
completed within a single first dry season so that monsoon flow will not affect the
construction at the upper parts of undersluice, intake, etc. Remaining other structures
will be started after the monsoon is over.
The tunnel excavation method will be conventional drilling and blasting or any other
modified method. The tunnel excavation work will be carried out at an average of 60m
per month per face. To meet the construction schedule it is necessary to execute the
excavation work from all work faces at the same time.
Circular tunnel will be partly concrete lined and the finished size will be 4m diameter
section. Shotcrete lining will be carried out simultaneously with the tunnel excavation
and primary support erection. In shear zone or fault zones, steel rib support will be
UM-IHP 172
Feasibility Study Report
provided immediately after full face drill and blast or heading and benching. Total
construction time for the completion of headrace tunnel has been estimated as 30
months.
Total time required for the excavation of surge tank including excavation, rock bolting
and shotcrete lining is estimated about 12 months. Concrete lining will be executed
after completion of excavation works.
Powerhouse works will commence with protection works at the upstream end that will
ensure safety from river flood and seepage to the powerhouse area. Excavation work
will be followed by foundation concrete, installation of sump pits and other hydro-
mechanical items, superstructures, installation of electro-mechanical item and final
finish work. In parallel the work at tailrace canal and switch yard will be carried out.
UM-IHP 173
Feasibility Study Report
Machinery installation and testing work will require further 15 months. Hence, the
Commissioning of the plant may be achieved after 39 months from the date of award of
the electro-mechanical contract. Therefore, acceleration on the civil construction works
will be necessary.
Total quantity of sand required for civil construction works will be about 1,40,000m3.
Total quantity of sand available within 20km range from the construction site is
sufficient for this project. Other borrow areas along the MyagdiRiver in the downstream
UM-IHP 174
Feasibility Study Report
are the potential sources of sand and aggregates from where the deficit quantity of
sand can be extracted.
11.4.2.2 Gravel
Total quantity of aggregates required for civil construction works is estimated about 1,
90000m3. Total quantity of aggregate available from the potential borrow areas within 6
km range from the construction site is sufficient for this project. Other borrow areas
along the MyagdiRiver in the downstream are the potential sources of aggregates from
where deficit quantity can be fulfilled.
Rest of aggregates required shall be obtained from the quarry site and by processing of
the excavated materials.
Rubble stones required for cofferdam, diversion weir intake structure and gabion works
will be collected from the river banks of MyagdiRiver within the project area.
Reinforcement steels available in the local market from the steel factories of Nepal will
be managed to the extent possible. Only the deficit quantity of reinforcement steel and
structural steel should be imported from India and other countries.
11.5.1.3 Explosives
For the underground excavation work, emulsion type explosives should be used for the
better performance. Such explosives will be managed from the Nepal Army and
alternatively imported from Indian market. To achieve better result of tunnelling works
the explosives play vital role. For the surface excavation in rock and boulder blasting,
explosive products of Nepal Army will be utilized. All types of detonators need to be
imported from Indian market.
UM-IHP 175
Feasibility Study Report
UM-IHP 176
Feasibility Study Report
UMIHEP 177
Feasibility Study Report
UMIHEP 178
Feasibility Study Report
Guiding principles for carrying out the scoping process include the followings:
Recognizing scoping is a process rather than a discrete activity or event
Design the scoping process for each proposal, taking into account the affected
UMIHEP 179
Feasibility Study Report
UMIHEP 180
Feasibility Study Report
forest areas and settlements within project affected VDCs laying outside the 500 m
periphery of the construction site
The direct environmental impacts are those impacts caused by project construction or
operation. During construction, these impacts primarily occur in places where key
structures of the project such as dam, desander, headrace tunnel, adit tunnel,
powerhouse, internal access road, quarry site, burrow pit, spoil disposal site, etc are
located. These structures/facilities result into permanent direct impacts in the
placement sites and areas adjacent to them (maximum of 100 m from the site).
Besides, direct impacts of temporary nature occur in sites where activities of
construction operation such as camps for contractors, labours, and support facilities for
storage of construction materials, batching plants, aggregate crushing and washing
plants, mechanical yards for repair and maintenance, etc are located throughout project
construction period. During the operation period changes in river hydrology are the key
impacts influencing a considerable stretch of river. Above direct impacts modifies the
natural and social environment of the areas significantly depending upon the nature of
activities during construction and operation.
Indirect or induced environmental impacts are those impacts which are not directly
caused by project construction or operation. These impacts result from activities
associated with or induced by the project. Indirect impacts can include the degradation
of forests and ecology near the project sites by the project work force, or impacts on
cultural traditions (both positive and negative) and social development in general. The
indirectly impact area of the proposal is defined as the administrative boundary of the
VDCs in which the structures and components of project are located.
There are no active faults and landslide in the project area the rocks quartzite-phyllite
are exposed on both, along upstream as well as downstream of the proposed intake
and weir axis area. Also, proposed surge shaft, pressure shaft, powerhouse and tailrace
area lies in good rock. The slope stability condition of the project area in general seems
to be stable.
UMIHEP 181
Feasibility Study Report
anthropogenic activities contributing to air pollution. Indoor air pollution due to the use
of firewood for cooking is the only source of air pollution in the project area at present.
Natural springs are the main source of drinking water for people and their livestock in
the project area. Water quality of the river seems to be satisfactory. The water of
Myagdi River seems to be free from anthropogenic source of pollution. The water is
clean.
Project area is free from any noise pollution at present. Vibration produced during the
construction period could produce noise. Nature is pristine and no urbanization is in
process in the project area. So, the question of noise and vibration is still irrelevant.
Natural vegetation plays an influential role in the socio-economic condition and life style
of local people. Diverse ethnic groups inhabit the project area. They utilize the local
plant resources for different purposes including timber, firewood, medicine and food.
Main timber yielding plant of the project area is Chilaune (Schimawallichii). Similarly,
the common fodders reported from the project area are Dudhilo (Ficusnerifolia), Painyu
(Prunuscerasoides) and Nemaro (Ficusauriculata).
Ethno botanical study of the project area showed that local people are dependent on
forest and forest based non timber forest products (NTFP) tofulfil their daily needs.
Furthermore, forest products are also the income sources of the local people. Collection
of firewood, wild fruits and vegetables for own consumption is the common practice in
the area. Valuable species like Pinuswallichiana, Betulautilis, Acoroscalamus,
Zanthoxylumarmatum, Dioscoreadeltoidea, Bergeniaciliata, Valerianawallichii,
Swertiachirayita, Daphnebholua, Dactylorhizahatagirea, and few orchids are found in
the forests.
12.4.2.2 Fauna
Project area is situated in the national forest, community forest, cultivated land, and
barren area. According to locals, the potential area for wildlife habitat is located in
headwork site and some part of the tunnel alignment. The forest around the project
UMIHEP 182
Feasibility Study Report
12.4.2.3 Mammals
Local people reported about 15 species of mammals from the project periphery during
the field survey and discussions with the locals. The mammals species recorded from
the project periphery are:Bagh (Pantheratigris), Ban Biralo (Felix chaus), Bhalu (Felix
chaus), Chari Bagh (Prionailurusbengalensis), Chituwa (Pantherapardus), Dumsi
(Pantherapardus), Ghoral (Nemorhacdusghoral), Malsanpro (Martin flavigula), Musa
(Rattusrattus), Nyauri (Herpestisedwardsi), ownt (Lutralutra),Rato-Bandar
(Macacamulata), Ratuwamirga (Macacamulata), Seto Bandar-langur (Presbytis
entellus), and Syal (Canisaureus).
12.4.2.4 Birds
Birds’ species seen during the survey as well as knowledge of sighting in the project
area as answered in interview with locals are: Bakulla(Bubulcus ibis), Ban Kukhura
(Gallus gallus), Bhangera (Passer domesticus), Bhyakura (Turdoides spp.),Chil (Aquila
heliacal), Dhukur(Streptopeliachinensis),Gaunthali(Apusaffinis), Giddha (Gyps
bengalensis), Jureli(Pycnonotuscafer), Kaag(Pycnonotuscafer), Kalchauda
(Myophonuscaeruleus),Kalij(Lophuraleucomelanos), Koili (Cuculuscanorus),
Lahache(Picoidesspp.),Lampuchre (Urocissaerythrorhyncha), and Suga
(Psittaculacyanocephala).
12.4.2.5 Reptiles
According to the local information the reptiles and amphibians found in the project area
are garden lizard (Calotes versicolor), frog (Rana cyanophlyctus), toad (Bufo
melanostictus) etc.
12.4.2.6 Fisheries
Diversity of fish species is low. The dominant fish species of Myagdi River is Katle
(Acrosssocheilus hexagonolepis), Asala (Schizothorax spp) and Buduna (Garrasp).
UMIHEP 183
Feasibility Study Report
Among recorded plant species, none of them are identified as rare, endangered and
threatened species in the core project area.
Occupation
Agriculture is the main occupation of the project area, which is followed by labour,
foreign employment, business, collection of herbs and other forest products in the
project area. Significant numbers of local people go to Kathmandu and other urban
areas of Nepal. Similarly, many youths are going to India, Malaysia and other gulf
countries to seek employment.
UMIHEP 184
Feasibility Study Report
UMIHEP 185
Feasibility Study Report
13.1 General
In this chapter, we deal about the quantities of various materials, their rate analysis,
costing and BoQ. This cost report describes the methodology used for estimating the
project cost of 53.5 MW Project which is located in Myagdi district,
WesternDevelopment Region of Nepal. The cost of project is calculated based on
quantity estimation of various materials from drawings and the report. The unit rate of
the item is based on existing labour and material cost at current price level.
A key assumption made is that the project management and procurement policy will
stress on competitive bidding and that GON policies will not hinder a cost-effective
construction. Contractors will be free to employ labour from Nepal or neighbouring
countries deemed most cost effective.
UMIHEP 186
Feasibility Study Report
In the application of this approach, the contractor’s overhead and profits markup is
applied during the unit rate development.
Considering the overall construction requirements for the project, hourly rates of labour
will be developed based on prevailing rates of the project site. Since the project site is
accessible, availability of labour in the local area will be considered. The hourly rate of
labour will be calculated with provision of ten percent as project allowances, mark-up of
UMIHEP 187
Feasibility Study Report
ten percent for labour man-power supplier and allowances for forty percent will be
made for labour, who is involved in shift and hazardous work. Calculated rates of
workers on an hour basis will then be developed for the following categories.
UMIHEP 188
Feasibility Study Report
Surface works
Open cut excavation in river bed material = US$2.95 /cum
Open cut excavation in rock = US$ 10.56 /cum
Concrete M25 = US$156.92 /cum
Concrete M20 = US$146.40 /cum
Concrete M15 = US$129.37 /cum
Plum concrete (M 20) = US$107.08 /cum
Reinforcement steel = US$1106.36 /Mtn
Stone masonry = US$90.34 /cum
Formwork plain ordinary = US$7.31 /sqm
Gabions = US$39.89 /cum
Gravel surfacing and gravel bedding = US$41.94 /cum
Underground works
Tunnel excavation = US$41.05/ cum
Concrete M25 = US$ 156.92 / cum
Concrete M20 = US$146.40 /cum
Rock bolt ordinary type 2m long (dia. 25mm) = US$23.35 /m
Shotcrete (10 cm) = US$46.76 /sqm
Shotcrete (5 cm) = US$24.43 /sqm
Wire mesh shotcrete (10 cm) = US$41.38/sqm
Consolidation grouting = US$382.36 /ton
Reinforcement = US$1106.36 / ton
UMIHEP 189
Feasibility Study Report
In the powerhouse area, access road of about 1.5km length will be constructed to
approach surge tank and powerhouse area from nearest accessible road. In the
construction adit location, access road length of 0.5 km will be constructed from the
main proposed road head to the headrace inlet of construction adit 1. Similarly about
10km road id needed to be constructed to access headworks site from powerhouse
area.The estimated cost for the access road for the project is US$1.68 Million.
Employer’s camp is situated at Batase village. Design work of the building consist of
The project envisages the construction of following types of quarters, shades & facilities
to accommodate the project staffs of Upper Myagdi IHydropower project.
UMIHEP 190
Feasibility Study Report
UMIHEP 191
Feasibility Study Report
Water supply system is planned to off take water for the camps at three locations. For
all three locations intake structures with filtration plants will be installed. In the
headwork site and water ways site, separate water supply is planned for the project
staff, contractor’s camp and labour camp. The estimated cost for the water supply
system is approximately US$23,364.
Project camp facilities includes the different types of building at camp site, river
protection wall at the site of Upper Myagdi, compound wall as a boundary wall, water
supply scheme & miscellaneous structures. The total cost estimated for the project
camp facilities for Upper Myagdi IHydropower project is approximately US$7,
97,991excluding VAT.
Interpretation of budget prices supplied by potential suppliers, mainly for the larger and
more expensive equipment such as turbines, generators, power transformers and main
UMIHEP 192
Feasibility Study Report
UMIHEP 193
Feasibility Study Report
13.13 Contingencies
Contingencies will be applied to various area of work to cover the changes in physical
scope which cannot be identified at this stage. Following allowances will be applied.
UMIHEP 194
Feasibility Study Report
UMIHEP 195
Feasibility Study Report
UMIHEP 196
Feasibility Study Report
UMIHEP 197
Feasibility Study Report
14.2 Assumptions
Financial evaluation is based on a number of key assumptions and parameters. A
reference or base case for analysis was prepared and then sensitivity cases were
analysed. The principal criteria and parameters are discussed below.
14.7 Depreciation
Depreciation rate applied is 3.33% percent per annum is used.
UMIHEP 198
Feasibility Study Report
14.8 VAT
VAT @ 13% is payable to the government or its bodies have to be considered in the
financial evaluation.
14.13 Disbursement
Major amount of the project cost is disbursed within construction period in the
proportion of 5% in the first year, 15% in the second year, 30% in the third year and
50% in the fourth year. However, annual cost including operation and maintenance cost
is spread over the period of the analysis. Similarly, the project benefits are received
during the operation period only.
UMIHEP 199
Feasibility Study Report
It has been assumed that debt equity ratio will be 70:30 with an interest rate of 10%
on debt. Royalties and taxes have been deducted from the revenue.
Financial Factors
Insurance Charges 0.5% of Total Project Cost
Financial Costs
Total Project Cost without IDC NRs. 8108.18 million
Total Project Cost With IDC NRs. 9331.93 million
Total Project Cost in USD without IDC USD 75.77 million
(1 USD = NRs. 107)
Loan
Debt : Equity 70 : 30
Loan Amount NRs. 5675.73 million
Interest Rate 10%
Loan Repayment (after commercial operation) 10 years
No. of payment per year 4.00
Energy Production
Firm or Dry Season 45.48 GWh
Secondary or Wet Season 261.70 GWh
Energy Prices
Energy Benefit
Dry Season Energy Price 8.40 NRs./kWh
Wet Season Energy Price 4.80 NRs./kWh
Estimated CoD 2020/2021
Escalation of Energy Prices 3%
Number of years for above escalation 8
Income Tax
Till 7thyear of operation 0%
th th
8 -10 year of operation 10%
After 10th year of operation 20%
UMIHEP 200
Feasibility Study Report
Royalty
Upto 15 years - Energy Royalty 2.00%
Upto 15 years - Capacity Royalty / kW installed (in NRs.0.00015
Millions)
After 15 years - Energy Royalty 10.00%
After 15 years - Capacity Royalty / kW installed (in NRs.0.00120
Millions)
Other Assumptions
Growth on Salary and Wages per year 3%
Depreciation (on project cost ) 3.33% (i.e. 30 years of CoD)
Repair and Maintenance (on project cost) 0.5%
R & M escalation per year after commissioning 5%
Insurance cost (after commissioning) 0.5% of project cost
Results
Without IDC With IDC
Project Internal Rate of Return 16.78% 14.66%
Equity IRR 26.89% 22.05%
Project NPV NRs. 2514.39 million NRs1558.15 million
Project Benefit Cost Ratio 1.62 1.33
Average DSCR 1.82 1.57
Project Payback Period 5.40 years 5.10 years
Annual Revenue (Energy Sale) NRs. 1638.19 million
UMIHEP 201
Feasibility Study Report
Results
Project IRR 13.32%
Project NPV NRs. 828.94 million
Project BC Ratio 1.16
Average DSCR 1.42
Project Payback Period 6.6 years
Project’s IRR under this sensitivity test is well above the opportunity cost of capital of
10% and Net Present Value is positive. Average DSCR and Benefit Cost Ratio are more
than one as well. Therefore, the project is economically viable even with 10% increase
in investment cost and IDC.
14.15.2 At 90% of project revenue
Results
Annual Sales Revenue (after 1st year of production) NRs. 1474.37 million
Project IRR 13.15%
Project NPV NRs. 657.31 million
Project BC Ratio 1.14
Average DSCR 1.40
Project Payback Period 7.0 years
According to the results obtained, the project is economically viable even with 10%
decrease in revenue.
14.15.3 Interest Rate Increased to 12%
Results
Project IRR 14.65%
Project NPV NRs. 1518.14million
Project BC Ratio 1.33
Average DSCR 1.44
Project Payback Period 6 years
According to the results obtained, the project is economically viable even with interest
rate at 12%.
UMIHEP 202
Feasibility Study Report
UMIHEP 203
Feasibility Study Report
Geologically, proposed project area lies in the Ranimatta Formation of the Lesser
Himalaya, Central Nepal. This formation is comprised of the thick-bedded, fine-grained,
and grey to greenish grey schist and phyllite intercalated with fine to medium grained,
grey to greenish grey quartzite. The dip directions of rocks ranges from 340° to 010°
(northwest to northeast) with dip amount ranging from 25° to 50° .Left bank of Myagdi
Khola within project area has mostly exposed bedrock and thin to thick colluvial deposit.
Exposed rock is Phyllite and phyllite with quartzite make exposure on both bank at weir
area. Proposed settling basin lies on alluvial terrace deposit. Proposed tunnel alignment
encounters different lithology as passes through mostly phyllite, schist, and occasional
bands of thin to thick quartzite. Proposed structures; surge tank, penstock, powerhouse
and tailrace lies on phyllite and schist with quartzite intercalation.
About 12km long access road needs to be built to make access to the headworks site,
powerhouse site and surge tank area of the project.
A 28km long single circuit 132kV Transmission line is required to to evacuate power
from this project’s powerhouse up to proposed Dana Substation of Myagdi district
UMIHEP 204
Feasibility Study Report
Financial analysis is carried out with the assumption that the developer will invest it in
local currency. Developer Company will arrange the required finance through
commercial banks and equity. The project will be developed according to the prevailing
hydropower policy. The entire energy will be sold to Nepal Electricity Authority through
a mutually agreed power purchase agreement.
Total annual energy generation from the plant is 323.88 GWh. However, the annual
energy available for sale excluding outage, station consumption and transmission
losses, totalling 5% comes out to be 307.68 GWh. Out of which 261.46 GWh is the wet
energy and 46.22 GWh is the dry energy.
Cost estimate of Upper Myagdi-I Hydropower Project has been carried out based on
2016 price level. Major cost components are divided into Land and support, Pre-
operating expenses, infra-structure works, main civil works, hydro-mechanical works
and electromechanical works & transmission line works. Cost of value added tax and
contingencies have also been considered in the cost estimate. Total construction cost of
the project without interest during construction as of 2016 is estimated at NRs. 8,108
Million.
Financial analysis of the project is carried out to assess the financial viability of the
project. PPA is expected to follow the prevailing practice in Nepal. i.e. NRs. 8.40/kWh in
the dry season) and NRs. 4.80/kWh in wet season with annual escalation of 3% for five
times from the commercial operation date.
Internal rate of return of the project works out to be 16.78%. Likewise, benefit cost
ratio is 1.62 and NPV is NRs. 2,514 million. Average debt service coverage ratio is 1.82
as summarised below.
UMIHEP 205
Feasibility Study Report
15.3 Conclusions
Proposed run-of-river project of 53.5MW on the Myagdi River, located on Myagdi
district, is not only technically feasible but also financially attractive. Based on the
feasibility study, this project is recommended for implementation at the earliest.
15.4 Recommendations
Following are the recommendations made during this stage of the study:
Hydrological review is necessary to confirm the design discharge and low flows. With
the measurement started by fixing gauge station some year back, data measurement
shall be continued and re-analysis is necessary based on recent measured data.
Efficiency of the hydraulic structures largely depends on the quantity of sediment flow
in the river. The effective way of estimation of the sediment is the measurement during
the monsoon periods. It is recommended for the daily sediment measurements during
next monsoon.
Energy rate for the projects bigger than 25MW is fixed on the negotiation. So the actual
financial & economic analysis shall be done after the negotiated rate with NEA.
UMIHEP 206