You are on page 1of 2

REVIEWING

Shop Drawings
Michael A. West, P.E.

A leading engineer gives his approach to the shop drawing review process,
based on standard AIA documents and the AISC Code of Standard Practice.

he review and approval of upon the Contractor’s submittals such as review. Review of such submittals is not

T shop drawings is a careful


and methodical process.
After “checking” structural
steel shop drawings for
nearly 30 years, I have developed my
approach to the procedure, based on
the one that is described in the AIA
Shop Drawings, Product Data and Sam-
ples, but only for the limited purpose of
checking for conformance with information
given and the design concept expressed in
the Contract documents. The Architect’s
action will be taken with such reasonable
promptness as to cause no delay in the
conducted for the purpose of determining
the accuracy and completeness of other de-
tails such as dimensions and quantities, or
for substantiating instructions for installa-
tion or performance of equipment or sys-
tems, all of which remain the responsibility
of the Contractor as required by the Con-
General Conditions of the Contract of Con- Work or in the activities of the Owner, tract documents. The Architect’s review of
struction as follows: Contractor or separate contractors, while the Contractor’s submittals shall not re-
“4.2.7: The Architect will review and allowing sufficient time in the Architect’s lieve the Contractor of the obligations
approve or take other appropriate action professional judgment to permit adequate under Paragraphs 3.3, 3.5 and 3.12. The
Architect’s review shall not constitute ap-
proval of safety precautions or, unless oth-
Definitions from the AISC Code of Standard Practice erwise specifically stated by the Architect,
of any construction means, methods, tech-
Contract documents. The documents that define the responsibilities of the niques, sequences or procedures. The Ar-
parties that are involved in bidding, fabricating and erecting structural steel. chitect’s approval of a specific item shall not
These documents normally include the design drawings, the specifications indicate approval of an assembly of which
and the contract. the item is a component.”
Also, the AISC Code of Standard Prac-
Design drawings. The graphic and pictorial portions of the contract docu- tice provides that shop-drawing review
ments showing the design, location and dimensions of the work. These docu- is a “confirmation that the Fabricator has
ments generally include plans, elevations, sections, details, schedules correctly interpreted the Contract docu-
diagrams and notes. ments in the preparation of the submit-
tals…”
Embedment Drawings. Drawings that show the location and placement of In this context, the goal of the re-
items that are installed to receive structural steel. view is clear: to check for conformity
with the structural design as expressed
Erection Bracing Drawings. Drawings that are prepared by the erector to il- in the contract documents. The pri-
lustrate the sequence of erection, any requirements for temporary supports, mary way to ensure this is to establish
and the requirements for raising, bolting and/or welding. These drawings are that the detailer understands project re-
in addition to the erection drawings. quirements and has applied them to
the shop and erection drawings in a
Erection Drawings. Field-installation or member-placement drawings that clear and orderly way. Given this,
are prepared by the fabricator to show the location and attachment of the in- when I begin a review, my first activity
dividual shipping pieces. is to examine the submittal’s overall
appearance and content by paging
Shop Drawings. Drawings of the individual structural-steel shipping pieces through it.
to be produced in the fabrication shop. Next, I compare the erection plans
with the structural framing plans, eval-

March 2003 • Modern Steel Construction


uating member sizes, building-grid la- Also, just as the detailer finds and re- proved the Connection details shown
bels and dimensions, and top-of-steel ports discrepancies in the contract doc- on the Shop and Erection Drawing,”
elevations. I review the fieldwork de- uments, the reviewer can find errors in submitted in accordance with the re-
tails, and compare them to the struc- the detailer’s work which are beyond quirements of the contract documents.
tural drawings. I review any notes on the reviewer’s scope. These discrepan- The Code requires that the connections
the erection drawings as they relate to cies are reported with the understand- be fully designed in the contract docu-
the drawing notes and project specifi- ing that the reviewer has not used this ments; or, that information as to re-
cations. I also respond to any questions depth of scrutiny throughout the re- stricted connection types, and
that the detailer has written on the view. connection loads (shears, moments,
shop and erection drawings. Some de- In reviewing the piece drawings, the axial forces and transfer forces) is pro-
tailers (or project requirements) do not beginning sheets are reviewed in vided so the detailer can “select and
allow this form of question and re- greater detail to establish a sense of the complete” appropriate connection de-
sponse, but it is common on small- to detailer’s approach to the job and the tails. To satisfy this requirement the re-
intermediate-size projects. Usually the detailer’s grasp of the construction viewer might have to make some
next drawings to be reviewed are the document’s requirements. The follow- shorthand calculations to determine if
embedment plans and associated piece ing is a list of items that must be re- the project requirements have been
drawings. These are reviewed against viewed in detail: met. Since the approaches given in the
the design drawings for such things as ■ Member size and material specifica- Code of Standard Practice limit the de-
anchor rod diameters, other anchor di- tion tailer to AISC-tabulated connections,
ameters, materials, arrangements and ■ Piece mark, plan location and base the process of confirming that the de-
embedments. Since embedded material length tailer understands the loads and tabu-
falls outside the scope of the typical de- ■ Camber, if any lated connection resistances should
tailer’s requirement to “develop” con- ■ Surface preparation and coating, if only take a few in-depth reviews. How-
nections, deviations from the contract any ever, the reviewer should be alert to
documents are rare, but this must be ■ Connections special conditions, such as deep copes
established in the review. •Geometry and layout or top and bottom copes, that could af-
Lastly, the review of the shop draw- •Bolt sizes, type and material speci- fect connection strength. The shop
ings for the individual shipping pieces fication drawing review process also allows the
begins. As the Code of Standard Practice •Hole sizes, types reviewer to reconfirm that the connec-
states, the detailer’s responsibility is •Masking for SC-type connections tion requirements specified are appro-
“The transfer of information from the con- •Weld geometry, fillet size and priate for the piece in question.
tract documents into accurate and complete length, PJP and CJP Lastly, any corrections must be
Shop and Erection Drawings; and, the de- •Connection types transferred to all of the submitted
velopment of accurate, detailed dimen- •Connection material specifications copies. This is not an idle activity. It
sional information to provide for the fit-up •Copes and edge distances gives the reviewer another chance to
of parts in the field.” Just as the fabricator •Bolt and weld material strengths, look through the entire submittal. Per
is not required to discover errors or dis- specifications the Code of Standard Practice, each sheet
crepancies in the contract documents, it ■ Stiffeners must be individually marked with its
is not the reviewer’s responsibility to ■ Openings for other trades disposition. ★
find errors or discrepancies in the de- The Code of Standard Practice re-
tailer’s work beyond what is appropri- quires that the EOR’s review of the Michael A. West, P.E. is vice-president
ate to the goal of establishing Shop Drawings provides confirmation and a principal of Computerized Structural
conformity to the contract documents. that the EOR has “reviewed and ap- Design, S.C., in Milwaukee, WI.

March 2003 • Modern Steel Construction

You might also like