After the visual inspection has been performed, the next step in the site
acceptance tests is to execute the functional tests. The main purpose of the
functional tests is to make sure that the control circuitry is functioning properly and
as requested. The functional tests cover many aspects of the switchgear design,
because they include checking that the control devices like pushbuttons and
miniature circuit-breakers (MCBs) are working properly, making sure that the signal
devices like the pilot lamps, alarms or horns are working as requested. Functional
tests do not include the testing of the protection relay functions, because they
have their own tests. It is a custom practice to do the functional and mechanical
tests together, because the mechanical motions involve some indication signals.
The first step to do after safety precautions, is to supply the auxiliary (control
voltage) necessary to energize the control circuitry. The supply voltage can be 220
l Dr.Zakir Hussein street, 42 - 11471, 7th district, Cairo, Egypt l ' +20 100 166 1137
l ' +49 157 586 32 990l* ahmedhandoussa@hotmail.com l http://energy-
1/6
technik.com l https://www.linkedin.com/in/ahmed-handoussa-b56412140/
l https://www.xing.com/profile/Ahmed_Handoussa?sc_o=mxb_p
Medium-voltage series
Principles of medium-voltage switchgear testing:
Functional tests
Sunday, November 26, 2017,
10:13:18
Vac or dc, 110 Vac or dc, 24 Vdc, 60 Vdc or another special supply voltage. It can
one should take care that the polarity is correct before energizing the control
circuitry. The necessary hand tools for the functional tests are the digital
(CB) cubicle
breaker cubicle is usually equipped with some signalling and control devices to
schematic of a medium voltage outgoing cubicle and figure 2 is the same with
l Dr.Zakir Hussein street, 42 - 11471, 7th district, Cairo, Egypt l ' +20 100 166 1137
l ' +49 157 586 32 990l* ahmedhandoussa@hotmail.com l http://energy-
2/6
technik.com l https://www.linkedin.com/in/ahmed-handoussa-b56412140/
l https://www.xing.com/profile/Ahmed_Handoussa?sc_o=mxb_p
Medium-voltage series
Principles of medium-voltage switchgear testing:
Functional tests
Sunday, November 26, 2017,
10:13:18
Figure 1 Schematic of a medium-voltage outgoing cubicle equipped with an SF6 crcuit-breaker.
l Dr.Zakir Hussein street, 42 - 11471, 7th district, Cairo, Egypt l ' +20 100 166 1137
l ' +49 157 586 32 990l* ahmedhandoussa@hotmail.com l http://energy-
3/6
technik.com l https://www.linkedin.com/in/ahmed-handoussa-b56412140/
l https://www.xing.com/profile/Ahmed_Handoussa?sc_o=mxb_p
Medium-voltage series
Principles of medium-voltage switchgear testing:
Functional tests
Sunday, November 26, 2017,
10:13:18
Figure 2 Low voltage compartment of an outgoing cubicle equipped with a circuit-breaker.
Before applying the control voltage, the commissioning engineer should make
sure that all MCBs are turned OFF and the fuses are removed. Following the
control wiring, the engineer should start by switching ON the MCB that supplies
control power to the cubicle and observe the relevant indication LEDs.
pressing the CB ON pushbutton, but 1st the MCB for the spring charging motor
must be turned ON to supply it with the necessary voltage. The red pushbutton
should turn OFF the CB. The circuit breaker internal circuit is built with switch-over
contacts that indicate the level of the SF6 gas, so the cubicle is designed to display
the gas level on the low voltage compartment using the relevant LEDs. Another
important design feature is the CB position inside the cubicle, which is indicated
by the CB SERVICE LED, so when the commissioning engineer rotates the crank
and withdraws the CB to the SERVICE position (CB moves outside for
relevant MCB. Another important feature to test is the flipper circuit, which
depends on a limit switch placed on the cubicle roof, in a circuit loop designed to
trip the circuit-breaker when a short-circuit occurs and blows the roof of the cubicle
Figure 3. Space heater placed inside the cubicle to reduce vapour and decrease the risk of an arcing hazard
In the same cubicle, there are signalling LEDs on the mimic diagram that indicate
the CB and earthing switch (ES)1 positions visually. To test the signalling function,
the CB and the ES positions can be switched mechanically using their relevant
cranks.
1
The earthing switch is a safety feature to de-energize the cables connected in the cable
compartment of the cubicle to allow operating inside it safely.
l Dr.Zakir Hussein street, 42 - 11471, 7th district, Cairo, Egypt l ' +20 100 166 1137
l ' +49 157 586 32 990l* ahmedhandoussa@hotmail.com l http://energy-
5/6
technik.com l https://www.linkedin.com/in/ahmed-handoussa-b56412140/
l https://www.xing.com/profile/Ahmed_Handoussa?sc_o=mxb_p
Medium-voltage series
Principles of medium-voltage switchgear testing:
Functional tests
Sunday, November 26, 2017,
10:13:18
Figure 4 The signalling LEDs indicate that the CB is ON and the ES is OFF, they are both displayed in red to emphasize the
hazard, in the opposite positions the LEDs will turn green to indicate safety.
From this application example, it becomes obvious that the functional tests are
basically the same, but might vary a lot in the amount of control and its complexity
In the same cubicle, there are many functional tests and these tests are replicated
meeting before the tests to avoid time loss. Furthermore, the different cubicles,
which are electrically interconnected with control wiring perform certain functions
with control wiring, Ethernet cables or fiber optic communication cables and all of
Conclusion
In this article, functional tests where introduced and presented briefly to give the
reader a taste of the amount of work involved in tests and their nature. An
l Dr.Zakir Hussein street, 42 - 11471, 7th district, Cairo, Egypt l ' +20 100 166 1137
l ' +49 157 586 32 990l* ahmedhandoussa@hotmail.com l http://energy-
6/6
technik.com l https://www.linkedin.com/in/ahmed-handoussa-b56412140/
l https://www.xing.com/profile/Ahmed_Handoussa?sc_o=mxb_p