Professional Documents
Culture Documents
Construction of Deep
Excavation With Case
Studies - KVMRT in KL
Limestone
Gue See Sew
G&P Professionals Sdn Bhd
www.gnpgroup.com.my
20 July 2016
CONTENTS
INTRODUCTION
SOIL PARAMETERS
NUMERICAL ANALYSES
CASE HISTORIES
3 Underground Stations for KVMRT
Circular Shaft for Launching of TBM
Hydraulic Failure @ Penang
CONCLUSIONS
INTRODUCTION
0 0 0
Stage 1
Stage 2
Excavate to R.L.35.0m
-10 -10
-10
Stage 3
Excavate to R.L.31.0m
Depth(m)
Depth (m)
-20
Depth (m)
-30 -30
WALL A -30
-40 -40
Wall Relative Lateral Displacement (mm) Wall Relative Lateral Displacement (mm) Wall Relative Lateral Displacement (mm)
-10 0 10 20 30 40 -10 0 10 20 30 40 -10 0 10 20 30 40 -50
0 0 0
Stage 4
Stage 4
-20 -20
Stage 6 -20
Depth (m)
Depth (m)
Depth (m)
Excavate to R.L.22.5m
Excavate to R.L.18.5m
-30 -30 -30
Excavate to R.L.16.7m
-40 -40 -40
Limestone
Cavity in the Bedrock Highly fractured
Pinnacle
bedrock
Typical Karstic Feature :
Typical Karstic Feature :
Typical Karstic Feature :
(Note: Rock slope strengthening indicated is provisional only. Actual locations and
extent of rock slope strengthening are determined after geological mapping works
and kinematic analysis).
Conchrane Underground Station
Subsoil Bedrock
Average 5m 5m below
depth
Unit weight 18 kN/m3 24 kN/m3
SPT N 2-4 -
RQD - 0 – 100%
Average - 50 MPa
UCS
Effective c’= 1 kPa c’= 400 kPa
shear ɸ’= 29º ɸ’= 32º
strength
Elastic 4000 - 1.0E6 –
Modulus, 12000 1.0E7
E' (kPa)
Hydraulic 1.0E-5 0 – 31
conductivity, m/s Lugeon
k
Conchrane Station Bedrock Contour
Secant Pile Wall
Secant Pile Wall
Typical Secant Pile Wall Elevation View
Temporary Ground Anchor Support System
Description Properties
Working loads (kN) 212; 424; 636; 848
No. of strand 2; 4; 6; 8
Strand diameter 15.24mm
Breaking load 260.7 kN
Factor of safety 1.6
Strand U-turn radius 47.5mm
Reduction factor 0.65
Drill hole diameter 175mm
Allowable bond 400 kPa (limestone)
stress
Free length Varies (until
bedrock)
Bond length (m) 3; 3; 4.5; 6
Curtain & Base Grouting to seal the Limestone
Karstic Features
Grouted Layer
Typical Curtain & Base Grouting Holes Layout
Construction Sequence
1 2
3 4
Constrution Sequence (con’t)
5 6
7 8
Exposed Vertical Rock Face of the Excavation
<
Case History 3 :
Hydraulic Failure @ Penang
100 Years Ago
The Site
Subsoil Profile
Original Design
Original Retaining Wall (Insufficient Depth)
Original Retaining Wall (Insufficient Depth)
Thickness of Clay
insufficient to resist
Water Uplift Pressure
4
Ground level
0
Ground water level from Piezometer
(Days from the date of investigation)
(28 days) PZ 7
(49 days)
-2
(84 days)
Ground Level
-4 PZ 5 PZ 8
PZ 4
PZ 3
PZ 2
PZ 1
-6
0 5 10 15 20 25
Distance from Excava tion / Depth of Excavation
Additional Settlement
Excavation
Distance from Excavation (m)
Side Retained
0 Side 20 40 60 80 100 120 140
-5
Additional Settlement (mm)
-10
0 2 4 6 8 10 12
Distance from Excavation / Depth of Excavation
Remedial Works
HYDRAULIC FAILURE
Base instability caused by piping
Seepage due to high groundwater level
Available methods
Terzaghi’s method
Critical hydraulic gradient method
HYDRAULIC FAILURE CHECKS
HYDRAULIC FAILURE
Terzaghi’s method recommended
Based on latest research by Tanaka &
Verruijt (1999)
Factor of safety required – 1.2 to 1.5
HEAVING DUE TO ARTESIAN PRESSURE
HYDRAULIC FAILURE
ACKNOWLEDGEMENT
The input from the following team
members for KVMRT and in this
presentation are very much appreciated:-
- Ir. TAN Yean Chin
- Ir. CHOW Chee Meng
- Ir. KOO Kuan Seng
- TIONG Chiong Ngu
- Ir. Dr. GUE Chang Shin
THANK YOU
Q&A
G&P Professionals Sdn Bhd
www.gnpgroup.com.my