BUILDING MANAGEMENT UPDATES AS AT 31/3/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Teamservice was called to check and the


quotation amounted RM30,690.00 was submitted
San Francisco air conditioning not cold with adding another new 5hp of Air Conditioning
Back up air cooled effects was done
enough due to undersized of the air and re-route the distances of existing cooling
by running for another 2 units of
1 conditioning unit and the cooling piping piping.
Lobby air conditioning for temporary
distance is too far that caused loss of
measures.
cooling efficiencies. Managed to deal with Teamservice again on the
quotation for re-route the distances of existing
cooling piping only.

B FIRE FIGHTING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1st floor Hose Reel water pressure too
To call Safety Link for checking the problem and
1 slow and need to check the caused of Water pressure too slow
submit report to Building Management.
problem.
To call Fire Fighter Industries for checking the
Fireman Intercom Call Button at Fire Alarm
2 The button seems looks like faulty. problem and submit report and quotation to
Panel keep buzzing.
Building Management.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The best and cheapest solutions are to change
Level GF, 1, 2, 3, 4 and 5 toilet freshwater
The leaking caused water seepage to the piping materials from ABS to normal water
supply service riser - ABS pipes was
1 the lower floors and Basement pipes (Grey Color) with the most thicknesses.
leaking like puntured at most of the piping
Parking area. Called contractor to submit quotations for piping
routes.
replacement.

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The floor call button between Lift No.2 & 3
The call buttons still not properly To follow up with SIGMA Technical Team on the
1 unabled to holding the user calls. Informed
functioned. repairs job to solve the problem ASAP.
SIGMA top management on this matters.

Draft Contract Agreement (CA) between


SIGMA and HSB was obtained. Already go
2 The CA still not signed. To email SIGMA on amendment in the CA.
thru the CA and will update the correction
and amendment to SIGMA Management.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Electricity Utilities bill was doubled-charged
Reported and emailed to En. Abdul Haris Abd.
by TNB to SHB. The charged are still No any deduction has been made to
Karim, Pengurus Besar (Operasi & Komersil TNB)
1 around the same as before even AEGIS our Main Electricity bills since
for correction on the billings. Waiting for TNB
had install their dedicated Electricity Sub- January 2016.
further actions.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
To repaint the Genset exhaust system and This issues was highlighted by
To purchase the SILVER color oil based paints
1 the Diesel transmission piping from RED to Amanah Raya Reits Management on
and repaint the exhaust and piping.
standard color (SILVER). the last visits.

G HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Informed Rizal and Daya Bersih top


Received a complaint from Angela Ooi management on this issue. The
(Symphony HRS) on 4th April 2016, that Cleaner was admit and returned the Since this issue was brought to Daya Bersih top
1 one of the Daya Bersih Cleaner at 7th floor stuff. Since this kind of behavior was management, they will take immediate actions
was taking resigned employee’s belonging not acceptable, HRS Management and will inform us soonest possible.
stuff. was emailed us that they want Daya
Bersih to replace the cleaner.

Called the vendors and suppliers to submit their


Currently the daily Cleaners
To purchase new Fingerprint Access and quotation for installation of new Fingerprint
2 attendance was monitored using Staff
Attendance System for the Cleaners. System with attendance records and waiting for
Attendance Record Books.
their promp reply.
Draft Contract Agreement (CA) between
Daya Bersih and HSB was obtained. The CA still not signed and return To follow up with Daya Bersih management on the
3
Already go thru the CA and revert to Daya back to SHB. CA.
Bersih Management.
H SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Will made an amendmend on the SOP and
Dell Security and HSB was obtained. The CA still not signed. Dell Security
Process Flows. Will pass to Dell Security
1 Already go thru the CA and will update the SOP was obtained but is was too
Management for approval before the CA will be
correction and amendment to Dell Security simple.
signed.
Management.

Met up and discussed with En. Abd.


They had raised their concerns too and claimed
Emailed and reported this issue to Rahim on 6/4/2016 and show him the
One of AEGIST staff was entered our that our guard was rude and impolite. I had ask
AEGIS Management and was replied CCTV footage of the incident. He had
building without Access Card and also their management to describe the words that
2 with the statement that the necessary agreed that their staff was rude at first
committed misbehaviour acted to our called rude and impolite. They had replied with
disciplinary action against the staff and was re-escalated this issue to their
Security Guards Personnel. this words “Don’t show your arrogance, just write
has been taken. top management for another further
your name”.
action. Waiting for their prompt reply.

I INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
HSB will responsible to buy the
Consequential Loss Insurance but it must
Insurance Policies for Fire and Emailed to Jenny from Puncak Dana
Will follow up with Puncak Dana on the progress be same insurer with FIRE Insurance.
1 Consequential Loss for Dana 13 will be Management for the renewal of the
of insurance renewal. Once the Fire Insurance has been done,
expiring on 31/5/2016. insurance.
we will buy the Consequential Loss
policy.

J CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP Department at
1 Expiry on 14/12/2016
Passenger Lift 4 (PMA 18839) least 1 month before expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
Renewal of certification for another 2 years has
been done online using ECOS System on
2 Electrical Installation (11KV) Expiry on 27/5/2016 To be renew with Energy Commission
9/3/2016. Payment has been made for RM6000
and waiting for the certificates issuance. Department at least 2 months before
expiry.
3 Electrical Installation (GENSET 280KW) 1/6/2017
4 Electrical B0 Chargeman Registration 2/25/2017

Electrical Safety Protection Device To be recalibrate and certificate renew at


5 10/16/2016
Calibration least 1 months before expiry.

Renewal of certification for another 1 year has


been done online using BLESS System on To be renew with BOMBA Department at
6 Fire Certificate Expiry on 5/4/2016
1/3/2016. Waiting for BOMBA confirmation for least 1 months before expiry.
inspection.

To be sent for service and certificate


7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016
renew at least 1 months before expiry.

K ADMINISTRATIVE
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Pending payment by Puncak Dana
1 Quit Rent 2016 To follow up with Jenny from Puncak Dana Payment to be made by 31/5/2016
Mangement
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016)
2nd Half Rate = RM250,736.64
BUILDING MANAGEMENT UPDATES AS AT 31/4/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

San Francisco air conditioning not cold Received a new quotation from Teamservice for
Back up air cooled effects was done
enough due to undersized of the air piping relocation only for RM3,964.40 which is too
by running for another 2 units of
1 conditioning unit and the cooling piping expensive for the said job. Managed to call and
Lobby air conditioning for temporary
distance is too far that caused loss of deal with other vendors on the quotation for re-
measures.
cooling efficiencies. route the distances of existing cooling piping only.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1st floor Hose Reel water pressure too
1 slow and need to check the caused of Water pressure too slow Done.
problem.

Quotation received from Fire Fighter amounted


RM1200.00. Ask Safety Link for quotation and
Fireman Intercom Call Button at Fire Alarm
2 The button seems looks like faulty. was informed that they are not specialized in
Panel keep buzzing.
Fireman Intercom repairs. PO has been issued to
Fire Fighter for repairing purposes.

Investigation has been made and was


understood that the Copper Strip has To get a vendor to supply and reinstall new
Missing of Lightning protector Copper Strip
3 been missing a long time ago and just Copper Strip at Rooftop as normal soonest
at Rooftop.
noticed and highlighted by DTZ on possible.
their last visit.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Since Maju TKK Enterprise was provided


Level GF, 1, 2, 3, 4 and 5 toilet freshwater the best prices with the same specs, they
The leaking caused water seepage to
supply service riser - ABS pipes was Currently, they was completely to replace the will be awarded for the rest of piping
1 the lower floors and Basement
leaking like puntured at most of the piping piping at GF toilets on 23 & 24 April 2016. replacement job with the same price from
Parking area.
routes. level GF until level 5. The job will be
execute floor by floor.

Ground Floor Male toilet was flooded due


The leaking caused flooding inside The burst pipes has been repaired by replace the
2 to busrt of upper ceiling ABS pipes on 13th Done.
the toilet and surrounding area. new piping at the spotted area.
April 2016.

We have understood that the main


piping for Subang area was broken
Temporary water supply disruption due to To provide the notifications sticker for users to
and under repairs by SYABAS Water supply back to normal by 5pm on
3 unscheduled maintenance work by conserve the water consumptions on every toilet
Contractors. They was estimated the the same day. Done.
SYABAS on 22nd April 2016. doors.
water supply will resume back to
normal by 6pm on the same day.

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The Hall Call Riser button between Lift
The Hall Call Riser Button was repaired and SIGMA was agreed to replace the Call
No.2 & 3 unabled to holding the user calls. The call buttons still not properly
1 functioned back to normal. Only GF button need Buttons without any additional costs as
Informed SIGMA top management on this functioned.
to replace due to no lighting. per new Contract Agreement.
matters.

Draft Contract Agreement (CA) between Emailed SIGMA on amendment in the CA and
SIGMA and HSB was obtained. Already go returned back to them. They had replied with the
2 The CA still not signed.
thru the CA and will update the correction some clauses need to reviews by us. Will discuss
and amendment to SIGMA Management. with En. Ashraf on this matters.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Met up with En Shahril and Mr. Ganesh at TNB


PJ, they had ask to send them an official letter for The new bill amounted RM131,777.45
Electricity Utilities bill was doubled-charged this problem. was received and there was an amounts
by TNB to SHB. The charged are still No any deduction has been made to already deducted from the bill, but the
1 around the same as before even AEGIS our Main Electricity bills since The letter has been sent to them via email and over-charged amount still not yet credited
had install their dedicated Electricity Sub- January 2016. phone call followed up has been made. TNB had back to us and the reply letter also not
Meter. agreed to make a deduction form the bills and will yet received. Will follow up again with
refund the over charged amounts. The reply letter them.
from TNB will be issued by end of April.

Reset the Fire Alarm Panel and temporary


Smoke detector inside the ELV Room shutdown power supply for 9th floor to replace the
Burnt and fire of Electrical protection 315
at 9th floor was activated due to burnt breaker. It was burnt due to undersize of the
2 Amp breaker unit inside the 9th floor ELV Done.
smoky effects from burning and fire of breaker itself and was replace with the bigger
Room on 22nd April 2016.
the breaker parts. capacity breaker. System back to normal and well
functioned after replacement.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
To repaint the Genset exhaust system and This issues was highlighted by
The exhaust and Diesel piping has been painted
1 the Diesel transmission piping from RED to Amanah Raya Reits Management on Done.
with Silver paint.
standard color (SILVER). the last visits.

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

ARRM have sent an official letter dated on 10th


April 2015 to Puncak Dana action on the façade
painting and other raising matters. Puncak Dana Notification email was sent by En. Ashraf
This issues was highlighted to
revert on 2nd June 2015, which stating that from SASB to En. Hasrol ARRM for
Amanah Raya Reits Management
façade rectification and painting didn’t fall under suspended of our monthly payments for
since Mr. Menon's time. It's caused
There are hair line cracks on external Puncak Dana's responsibilities. On 17/2/2016, service charge with the sum of
of water seepage into internal wall
façade wall that caused caused of water Puncak DANA and ARRM had meeting to discuss RM10,754.00 and monthly Sinking fund
1 whenever heavy rain with strong
seepage into internal wall whenever heavy further on façade repainting work and strata title. with the sum of RM2,688.50 to Puncak
wind. It's also caused paint peeling off
rain with strong wind. According to Puncak DANA, DANA 13 external dana Sdn Bhd commencing March 2016
recurred on previously painted wall at
façade not fall under common properties. ARRM due to lack of maintenance and
staircase wall and visible fungus on
will bring this matter to higher management. reinstatement work required by Block
walls.
D13.
Latest update from ARRM is they are in the midst
of appointing solicitor to resolve this issue.

Some deep crack found at several place


This issue also highlighted to Amanah
on rooftop surface slabs that caused water
Raya Reits Management since Mr.
leaks into tenants ceiling below the SASB will write an officially to ARRM to inform
2 Menon's time. SASB had noticed
cracked area. It’s happened due to regarding on this matter for further direction.
there are water dripping from upper
frequent of expanding and shrinking effect
slab at level 12 tenanted area.
from weathers conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Informed Rizal and Daya Bersih top


Received a complaint from Angela Ooi management on this issue. The
(Symphony HRS) on 4th April 2016, that Cleaner was admit and returned the
1 one of the Daya Bersih Cleaner at 7th floor stuff. Since this kind of behavior was The new Cleaner has been replced. Done.
was taking resigned employee’s belonging not acceptable, HRS Management
stuff. was emailed us that they want Daya
Bersih to replace the cleaner.

Currently the daily Cleaners The quotation has been submitted to Procurement
To purchase new Fingerprint Access and
2 attendance was monitored using Staff for purchasing purposes and PO has been issued
Attendance System for the Cleaners.
Attendance Record Books. for purchase.
Draft Contract Agreement (CA) between
The contract has been returned and to check on
Daya Bersih and HSB was obtained. The CA still not signed and return
3 the revised clauses and to draft and include the
Already go thru the CA and revert to Daya back to SHB.
SLA contract.
Bersih Management.
I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Emailed DELL Security on amendment in the CA
Dell Security and HSB was obtained. The CA still not signed. Dell Security
and returned back to them. They had replied with
1 Already go thru the CA and will update the SOP was obtained but is was too
some amendment on the clauses. To revise and to
correction and amendment to Dell Security simple.
completed the SLA draft for them.
Management.

Emailed and reported this issue to


One of AEGIST staff was entered our
AEGIS Management and was replied
building without Access Card and also According to En. Azannizam from Aegis, they had
2 with the statement that the necessary
committed misbehaviour acted to our given the Warning Letter to the said staff.
disciplinary action against the staff
Security Guards Personnel.
has been taken.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
SASB will responsible to buy the
Consequential Loss Insurance but it must
Insurance Policies for Fire and Emailed to Jenny from Puncak Dana
Jenny had replied with their insurer will conduct a be same insurer with FIRE Insurance.
1 Consequential Loss for Dana 13 will be Management for the renewal of the
fire risk survey on 9 May 2016 at 11am. Once the Fire Insurance has been done,
expiring on 31/5/2016. insurance.
we will buy the Consequential Loss
policy.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP Department at
1 Expiry on 14/12/2016
Passenger Lift 4 (PMA 18839) least 1 month before expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
The renewal certificate had been obtained from
2 Electrical Installation (11KV) 5/27/2018 Energy Commision and the copy of certificate was Done. New expiry date is 27/5/2018.
updated to ARRM and DTZ via email.

3 Electrical Installation (GENSET 280KW) 1/6/2017 To be renew with Energy Commission


Department at least 2 months before
4 Electrical B0 Chargeman Registration 2/25/2017 expiry.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2016
Calibration least 1 months before expiry.
Renewal of certification for another 1 year has
been done online using BLESS System on To be renew with BOMBA Department at
6 Fire Certificate Expiry on 5/4/2016
1/3/2016. Waiting for BOMBA confirmation for least 1 months before expiry.
inspection.
To be sent for service and certificate
7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016
renew at least 1 months before expiry.
L ADMINISTRATIVE
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Pending payment by Puncak Dana
1 Quit Rent 2016 Still on follow up with Jenny from Puncak Dana Payment to be made by 31/5/2016
Mangement
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016)
2nd Half Rate = RM250,736.64

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Renovation is still carry on but slow


down by the BOMBA compliances.
They would like to appeal for 2 Forward this issue to SASB top management and
1 LemonSky Animation Sdn. Bhd. New rental space is 11,039 sqft.
additional months of free rental and waitng for decission to be made.
service charges for the month of April
and May 2016.

Willing to expand their office space Discussion has been made with AEGIS and SHB
Aegis is scheduled to move to GF and
rental. Interested on 8th floor (SHB) Management. Aegis to provide their costs of
SHB will be move to 2nd floor (R&R).
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also relocation and reassambles. Roughly cost for SHB
Currently HILTI is waiting the final price
willing to pay the costs of relocations relocations and reassembles has been given to
from Aegis for the relocation purposes.
and reassembles. HILTI estimated around RM150K.

Proposed to be rent by Aegis for relocations from


3 Ground Floor Vacant space 7th floor and new child care center. To discuss on
this matter with Azzanizam away soon.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 Citibank - June Ong 30/3/2016 (1 DAY) RM530. Done by Interbank Funds Transfer .
2 UOB Bank - Chris Saw 22/4/2016 (1 DAY) RM530. Done by cash.
BUILDING MANAGEMENT UPDATES AS AT 31/5/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
San Francisco air conditioning not cold
Back up air cooled effects was done Received another quotation from IMK Tech for
enough due to undersized of the air
by running for another 2 units of piping relocation amounting RM4,452.00 which is
1 conditioning unit and the cooling piping Teamservice price is RM3,964.40
Lobby air conditioning for temporary slightly high. To proceed with Teamservice for the
distance is too far that caused loss of
measures. piping relocations.
cooling efficiencies.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Fireman Intercom Call Button at Fire Alarm
2 Done.
Panel keep buzzing.

Investigation has been made and was


Received 2 quotations from vendors such as:
understood that the Copper Strip has
Missing of Lightning protector Copper Strip a) Maju TKK Enterprise - RM9540.00
3 been missing a long time ago and just
at Rooftop.
noticed and highlighted by DTZ on
b) IMK Tech Sdn. Bhd. - RM10,070.00
their last visit.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Currently, they was completely to replace the


Level GF, 1, 2, 3, 4 and 5 toilet freshwater piping at GF toilets on 23 & 24 April 2016.
The leaking caused water seepage to
supply service riser - ABS pipes was
1 the lower floors and Basement Ask Maju TKK to provide bulk quotation.
leaking like puntured at most of the piping En. Ashraf was told me to ask for bulk quotation
Parking area.
routes. for the piping replacement which is the price
included level 1st to 5th floor.

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The Hall Call Riser button between Lift
The Hall Call Riser Button was repaired and
No.2 & 3 unabled to holding the user calls. The call buttons still not properly
1 functioned back to normal. GF button was Done.
Informed SIGMA top management on this functioned.
repaired and replaced.
matters.

Draft Contract Agreement (CA) between


Emailed SIGMA on final amendment in the CA and
SIGMA and HSB was obtained. Already go
2 The CA still not signed. returned back to them. Waiting for their reply with
thru the CA and will update the correction
the whole contract agreement for signing.
and amendment to SIGMA Management.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Electricity Utilities bill was doubled-charged
by TNB to SHB. The charged are still No any deduction has been made to The follow up email has been sent to Pn. Nora
1 around the same as before even AEGIS our Main Electricity bills since from TNB PJ and she had promised to follow up New bill for May 2016 is not yet receive.
had install their dedicated Electricity Sub- January 2016. this issue until resolves.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

ARRM have sent an official letter dated on 10th


April 2015 to Puncak Dana action on the façade
painting and other raising matters. Puncak Dana Notification email was sent by En. Ashraf
This issues was highlighted to
revert on 2nd June 2015, which stating that from SASB to En. Hasrol ARRM for
Amanah Raya Reits Management
façade rectification and painting didn’t fall under suspended of our monthly payments for
since Mr. Menon's time. It's caused
There are hair line cracks on external Puncak Dana's responsibilities. On 17/2/2016, service charge with the sum of
of water seepage into internal wall
façade wall that caused caused of water Puncak DANA and ARRM had meeting to discuss RM10,754.00 and monthly Sinking fund
1 whenever heavy rain with strong
seepage into internal wall whenever heavy further on façade repainting work and strata title. with the sum of RM2,688.50 to Puncak
wind. It's also caused paint peeling off
rain with strong wind. According to Puncak DANA, DANA 13 external dana Sdn Bhd commencing March 2016
recurred on previously painted wall at
façade not fall under common properties. ARRM due to lack of maintenance and
staircase wall and visible fungus on
will bring this matter to higher management. reinstatement work required by Block
walls.
D13.
Latest update from ARRM is they are in the midst
of appointing solicitor to resolve this issue.

Some deep crack found at several place


This issue also highlighted to Amanah
on rooftop surface slabs that caused water
Raya Reits Management since Mr. En. Hasrol will coming by this
leaks into tenants ceiling below the Official letter has wrote to ARRM to inform
2 Menon's time. SASB had noticed Wednesday (1st June 2016) to check
cracked area. It’s happened due to regarding on this matter for further direction.
there are water dripping from upper and inspect the defects.
frequent of expanding and shrinking effect
slab at level 12 tenanted area.
from weathers conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Informed Rizal and Daya Bersih top
Received a complaint from Angela Ooi management on this issue. The
(Symphony HRS) on 4th April 2016, that Cleaner was admit and returned the
1 one of the Daya Bersih Cleaner at 7th floor stuff. Since this kind of behavior was The new Cleaner has been replced. Done.
was taking resigned employee’s belonging not acceptable, HRS Management
stuff. was emailed us that they want Daya
Bersih to replace the cleaner.

Currently the daily Cleaners The quotation has been submitted to Procurement
To purchase new Fingerprint Access and
2 attendance was monitored using Staff for purchasing purposes and PO has been issued
Attendance System for the Cleaners.
Attendance Record Books. for purchase.
Draft Contract Agreement (CA) between
The contract has been returned and to check on
Daya Bersih and HSB was obtained. The CA still not signed and return
3 the revised clauses and to draft and include the
Already go thru the CA and revert to Daya back to SHB.
SLA contract.
Bersih Management.
I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Emailed DELL Security on amendment in the CA
Dell Security and HSB was obtained. The CA still not signed. Dell Security
and returned back to them. They had replied with
1 Already go thru the CA and will update the SOP was obtained but is was too
some amendment on the clauses and still on
correction and amendment to Dell Security simple.
review for the scope of work and SLA.
Management.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Both of Fire and Consequential Loss Insurance


Insurance Policies for Fire and Emailed to Jenny from Puncak Dana
was obtained and forward to ARRM. The insurer Waiting for the revise cover note from
1 Consequential Loss for Dana 13 will be Management for the renewal of the
then was advised to revise the Consequential insurer.
expiring on 31/5/2016. insurance.
Loss sum insured from RM75Mil to RM78Mil.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP Department at
1 Expiry on 14/12/2016
Passenger Lift 4 (PMA 18839) least 1 month before expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
2 Electrical Installation (11KV) 5/27/2018 11 months to go. Done. New expiry date is 27/5/2018.
3 Electrical Installation (GENSET 280KW) 1/6/2017 4 months to go. To be renew with Energy Commission
Department at least 2 months before
4 Electrical B0 Chargeman Registration 2/25/2017 6 months to go. expiry.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2016 3 months to go.
Calibration least 1 months before expiry.
Renewal of certification for another 1 year has
been done online using BLESS System on To be renew with BOMBA Department at
6 Fire Certificate Expiry on 5/4/2016
1/3/2016. Waiting for BOMBA confirmation for least 1 months before expiry.
inspection.
To be sent for service and certificate
7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016 1 month to go.
renew at least 1 months before expiry.
L ADMINISTRATIVE
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Pending payment by Puncak Dana
1 Quit Rent 2016 Still on follow up with Jenny from Puncak Dana Payment to be made by 31/5/2016
Mangement
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) 3 month to go.
2nd Half Rate = RM250,736.64

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Renovation is still carry on but slow


Replied their request by email which is SASB had
down by the BOMBA compliances.
generously to extend the waived for 2 weeks
They would like to appeal for 2
1 LemonSky Animation Sdn. Bhd. Service Charge for the month of May 2016 which New rental space is 11,039 sqft.
additional months of free rental and
is RM1.40/sqft, which comes to approx.
service charges for the month of April
RM6,979.50 (11,039sf x RM1.40 x 14/31).
and May 2016.

Willing to expand their office space


rental. Interested on 8th floor (SHB) En. Azannizam was verbally revert their moving
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also price to Andrea from HILTI. Waiting for HILTI's To follow up with Andrea on this issue.
willing to pay the costs of relocations Management decissions.
and reassembles.
3 Ground Floor Vacant space Still no tenants occupying.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 UOB Bank 3/5/2016 (1 DAY) RM530. Paid by cash .
2 Maybank 24-25/5/2016 (2 DAYS) RM1060. Paid by cash.
BUILDING MANAGEMENT UPDATES AS AT 310/6/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
San Francisco air conditioning not cold
Back up air cooled effects was done
enough due to undersized of the air
by running for another 2 units of
1 conditioning unit and the cooling piping KIV
Lobby air conditioning for temporary
distance is too far that caused loss of
measures.
cooling efficiencies.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Received revised quotation from vendors such as:


Investigation has been made and was a) Maju TKK Enterprise - RM9,858.00
I then was asked by Procurement
understood that the Copper Strip has
Missing of Lightning protector Copper Strip Department (Shafinas) to ask Maju TKK
3 been missing a long time ago and just b) IMK Tech Sdn. Bhd. - RM9,540.00
at Rooftop. to reduce the price same as IMK Tech
noticed and highlighted by DTZ on
since they are our preferred vendors.
their last visit. The quotations then was submitted to
Procurement Department.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Level GF, 1, 2, 3, 4 and 5 toilet freshwater


The leaking caused water seepage to The job was proceed with the bulk price as per
supply service riser - ABS pipes was
1 the lower floors and Basement requested by MA. Currently, they was completely
leaking like puntured at most of the piping
Parking area. to replace the piping at 1st to 4th floor toilets.
routes.

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Followed up by call to Aida from SIGMA on 13th
SIGMA and HSB was obtained. Already go
2 The CA still not signed. June 2016 but still no any finalized from their top
thru the CA and will update the correction
management.
and amendment to SIGMA Management.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Electricity Utilities bill was doubled-charged
by TNB to SHB. The charged are still No any deduction has been made to The follow up email has been sent to Pn. Nora on
New bill for June 2016 was received and
1 around the same as before even AEGIS our Main Electricity bills since 13th June 2016 and she had promised to follow
still no any refund was stated.
had install their dedicated Electricity Sub- January 2016. up this issue until resolves.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

This issues was highlighted to


Amanah Raya Reits Management
since Mr. Menon's time. It's caused
There are hair line cracks on external
of water seepage into internal wall
façade wall that caused caused of water ARRM was in the midst of dealing with their En.Hasrol was advised us to continue the
1 whenever heavy rain with strong
seepage into internal wall whenever heavy lawyer on the repairing of the hairline craks. sinking fund payment as well.
wind. It's also caused paint peeling off
rain with strong wind.
recurred on previously painted wall at
staircase wall and visible fungus on
walls.

Some deep crack found at several place


This issue also highlighted to Amanah
on rooftop surface slabs that caused water
Raya Reits Management since Mr. ARRM was replied with making an arrangement
leaks into tenants ceiling below the
2 Menon's time. SASB had noticed for the repairing after Hari Raya festive. The date
cracked area. It’s happened due to
there are water dripping from upper will be set later.
frequent of expanding and shrinking effect
slab at level 12 tenanted area.
from weathers conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Draft Contract Agreement (CA) between
Followed up by phone call was made to Pn.
Daya Bersih and HSB was obtained. The CA still not signed and return
3 Asmahani and she was promised to get it done as
Already go thru the CA and revert to Daya back to SHB.
soon as possible.
Bersih Management.
I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Draft Contract Agreement (CA) between
Dell Security and HSB was obtained. The CA still not signed. Dell Security Followed up by phone call was made to En. Shah
1 Already go thru the CA and will update the SOP was obtained but is was too and he was promised to get it done before Hari
correction and amendment to Dell Security simple. Raya festive.
Management.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Insurance Policies for Fire and Emailed to Jenny from Puncak Dana Received both policies from insurer and the
1 Consequential Loss for Dana 13 will be Management for the renewal of the payment has been made to Puncak Dana and MIT Done
expiring on 31/5/2016. insurance. Insurance Broker.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP
1 Expiry on 14/12/2016 4 months to go. Department at least 1 month before
Passenger Lift 4 (PMA 18839) expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
2 Electrical Installation (11KV) 5/27/2018 10 months to go. Done. New expiry date is 27/5/2018.
3 Electrical Installation (GENSET 280KW) 1/6/2017 4 months to go. To be renew with Energy Commission
Department at least 2 months before
4 Electrical B0 Chargeman Registration 2/25/2017 5 months to go. expiry.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2016 2 months to go.
Calibration least 1 months before expiry.
Renewal of certification for another 1 year has
been done online using BLESS System on To be renew with BOMBA Department at
6 Fire Certificate Expiry on 5/4/2016
1/3/2016. Waiting for BOMBA confirmation for least 1 months before expiry.
inspection.
Will start getting quotations by this month from the To be sent for service and certificate
7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016
vendors for renewal of the certificates. renew at least 1 months before expiry.
L ADMINISTRATIVE
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Paid by Puncak Dana on 10th March
1 Quit Rent 2016 Done.
2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) 2 months to go.
2nd Half Rate = RM250,736.64

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Renovation is still carry on but slow


down by the BOMBA compliances.
Renovation was done, but they are still request to
They would like to appeal for 2
1 LemonSky Animation Sdn. Bhd. meet up with DHSM to appeal of the rental rate for
additional months of free rental and
May 2016.
service charges for the month of April
and May 2016.

Willing to expand their office space HILTI was sent an email to discuss on the early
rental. Interested on 8th floor (SHB) termination of the contract. They had been
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also informed by email that the management has Waiting for their reply.
willing to pay the costs of relocations decided to remain firm on the clause on fixed
and reassembles. period til October 2017.

To put a banner for the two sides of Symphony


3 Ground Floor Vacant space Building as per requested by DHSM. Called the
vendor to submit their quotations.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 UOB Bank 8/6/2016 (1 DAY) RM530. Paid by online transfer.
2 AEGIS - Standard Chartered Bank 29/6/2016 (1 DAY) RM530. Paid
3 Bank Rakyat 30/6/2016 (1 DAY) RM530. Paid by online transfer.
BUILDING MANAGEMENT UPDATES AS AT 31/7/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Investigation has been made and was


understood that the Copper Strip has
Missing of Lightning protector Copper Strip PO was issued to the vendor Maju TKK and
3 been missing a long time ago and just
at Rooftop. waiting for them to do installation.
noticed and highlighted by DTZ on
their last visit.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Level GF, 1, 2, 3, 4 and 5 toilet freshwater


The leaking caused water seepage to
supply service riser - ABS pipes was
1 the lower floors and Basement The job was completed. Done.
leaking like puntured at most of the piping
Parking area.
routes.

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


The signed agreement was courier to us and
SIGMA and HSB was obtained. Already go
2 The CA still not signed. received on 20th July 2016. The agreement was
thru the CA and will update the correction
passed to our Legal Department for further action.
and amendment to SIGMA Management.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Followed up by phone call has been made on 29th


Electricity Utilities bill was doubled-charged
July 2016 and was told that she only can approve
by TNB to SHB. The charged are still No any deduction has been made to
refund amounts below RM50K. Currently they also
1 around the same as before even AEGIS our Main Electricity bills since New bill for July 2016 not yet received.
using new system for billing that caused delaying.
had install their dedicated Electricity Sub- January 2016.
She had promised to follow up with her superior
Meter.
and revert to us soonest possible.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

This issues was highlighted to


Amanah Raya Reits Management
since Mr. Menon's time. It's caused
There are hair line cracks on external Followed up was made on 20th July 2016 and was
of water seepage into internal wall
façade wall that caused caused of water informed that ARRM still in the midst of dealing En.Hasrol was advised us to continue the
1 whenever heavy rain with strong
seepage into internal wall whenever heavy with their lawyer on the repairing hairline craks sinking fund payment as well.
wind. It's also caused paint peeling off
rain with strong wind. issues.
recurred on previously painted wall at
staircase wall and visible fungus on
walls.

Some deep crack found at several place


This issue also highlighted to Amanah
on rooftop surface slabs that caused water ARRM contractor was came to conduct repairing
Raya Reits Management since Mr.
leaks into tenants ceiling below the job using PU Grouting and cement patching
2 Menon's time. SASB had noticed
cracked area. It’s happened due to method inside the ATES Office at level 12 and
there are water dripping from upper
frequent of expanding and shrinking effect Roof Top. So far no any leakages was reported.
slab at level 12 tenanted area.
from weathers conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Meeting have been conducted within SASB and


Draft Contract Agreement (CA) between Daya Bersih for SLA issues on 19th July 2016.
Daya Bersih and HSB was obtained. The CA still not signed and return They were highlighted some issues on our SLA
3 Waiting for their proposal.
Already go thru the CA and revert to Daya back to SHB. commitment level and was discussed accordingly.
Bersih Management. They will proposed their SLA Commitment Level
as per their existing contract with another clients.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Drafted agreement was agreed by both parties
Dell Security and HSB was obtained. The CA still not signed. Dell Security
and was printed out by us for signing purposes.
1 Already go thru the CA and will update the SOP was obtained but is was too
The agreement was passed to our Legal
correction and amendment to Dell Security simple.
Department for further action.
Management.
Emailed to HRS on our proposed of selling our
existing installed CCTV, Access Card and Checked with MA on the existing
Selling of CCTV, Access Card and Our existing installed CCTV, Access Magnetic Door equipment by 50% less from new installation prices but found not much
2 Magnetic Door equipment to HRS due to Card and Magnetic Door equipment prices obtained. Meeting has been conducted info due to existing price was shown in
separation of operations. to be sell as where as basis to HRS. between SASB and HRS. They had requested our lump sump for the whole projects.Will
existing installation cost before to compare with update them accordingly.
the new price obtained.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Fire and Consequential Loss Insurance. Expiry on31/5/2017 10 months to go.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP
1 Expiry on 14/12/2016 3 months to go. Department at least 1 month before
Passenger Lift 4 (PMA 18839) expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
2 Electrical Installation (11KV) 5/27/2018 9 months to go.
To be renew with Energy Commission
3 Electrical Installation (GENSET 280KW) 1/6/2017 4 months to go. Department at least 2 months before
expiry.
4 Electrical B0 Chargeman Registration 2/25/2017 4 months to go.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2016 1 month to go.
Calibration least 1 months before expiry.

Received a letter from BOMBA dated 14/7/2016


6 Fire Certificate Expiry on 5/4/2016 on 20th July 2016 for inspection. Inspection date
was set on 18 August 2016 at 2.30pm.

Quotations was obtained from several vendors.


Fire Fighter Industries was awarded and PO was To be sent for service and certificate
7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016
issued. Collection of Fire Extinguisher for servicing renew at least 1 months before expiry.
will be starts on 3rd August 2016.
L ADMINISTRATIVE AND OTHERS
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Paid by Puncak Dana on 10th March
1 Quit Rent 2016 Done.
2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) 2 months to go.
2nd Half Rate = RM250,736.64

Some of Gym equipment was found


Proposed to engage with Fitness Concept on
broken and out of order such as
advise, maintenance and repairs. Some of steel
Treadmills, Rower Machines,
Some of Gymnasium equipment was wire rope found worn out and can snap anytime
4 Standing Bikes, Upright Bike,
broken and out of order. and caused injuries to users. Fitness Concept was
Recumbent Bike, Gym Station and
called and they will revert on the visiting time and
some others. All the equipment need
date.
some maintenance and repairs.

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Meeting was conducted between SASB and


Renovation is still carry on but slow Lemonsky on 20th July 2016 and several issues
down by the BOMBA compliances. has been highlighted such as Security, Building
They would like to appeal for 2 Cleanliness, Credit Hours of Air-Cond. Services,
1 LemonSky Animation Sdn. Bhd.
additional months of free rental and Fire System Drawing and Air Cond Ducting
service charges for the month of April Management. All the highlighted issues was noted
and May 2016. and replied to them accordingly. Swift action was
taken to address the matter.

Willing to expand their office space HILTI was informed by email about the Symphony
rental. Interested on 8th floor (SHB) HRS willing to relocate and we are furthering the
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also process of getting the buy-in from Aegis and HRS Still waiting for their reply.
willing to pay the costs of relocations to reasonably relocate from Level 7, to allow for
and reassembles. the whole area to be available for them .

Several vendors was called and came for site


3 Ground Floor Vacant space
visit. Waiting for their quotation submission.

To get the estimation costs of


Estimate of reinstatement costs for Several vendors was called and came for site
4 Symphony Group reinstatement as
Symphony Group Office spaces. visit. Waiting for their quotation submission.
soon as possible.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 Kenangan Investment 13,14 and 15/7/2016 (3 DAYS) RM1,590.00 Paid by online transfer.
2 HSBC Bank 28 and 29/7/2016 (2 DAYS) RM1,060. Paid by online transfer.
BUILDING MANAGEMENT UPDATES AS AT 31/8/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Investigation has been made and was


understood that the Copper Strip has
Missing of Lightning protector Copper Strip
3 been missing a long time ago and just The job was completed. Done.
at Rooftop.
noticed and highlighted by DTZ on
their last visit.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

D VERTICAL TRANSPORTATION SYSTEM (LIFT)


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


All the amendment was done and agreed by both
SIGMA and HSB was obtained. Already go
1 The CA still not signed. parties. We will sign the agreement and pass to
thru the CA and will update the correction
SIGMA for sign and to make duty stamping.
and amendment to SIGMA Management.

Emailed to SIGMA, Takaful Insurance and ARRM


on the incident notify. SIGMA was conducted
action taken on repairing the damaged equipment
It was happened during Guide roller assembly as this is a non-
Lift No.1 was found over shooted to top on the lift such as replacement of:
troubleshooting the problems lift stock item, it is none wear and tear item.
floor and caused the lift to hit the top floor
2 brake and the incident happened due SIGMA have placed other and it requires
slab while counterweight runs to buffer on - Guide Roller Assemble
to human mistakes and procedure about 7-10 days to be delivered, plus 2
17th August 2016 about 6.30pm. - Car top railing
violation. days delivery.
- Car top fan
- Guide rail resurfacing
- Oil buffer replacement

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Electricity Utilities bill was doubled-charged


by TNB to SHB. The charged are still No any deduction has been made to The follow up call has beenmade to Pn. Nora on
1 around the same as before even AEGIS our Main Electricity bills since and she had promised to follow up this issue until
had install their dedicated Electricity Sub- January 2016. resolves.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

This issues was highlighted to


Amanah Raya Reits Management
since Mr. Menon's time. It's caused
There are hair line cracks on external Followed up was made on16th August 2016 and
of water seepage into internal wall
façade wall that caused caused of water was informed that ARRM still in the midst of En.Hasrol was advised us to continue the
1 whenever heavy rain with strong
seepage into internal wall whenever heavy dealing with their lawyer on the repairing hairline sinking fund payment as well.
wind. It's also caused paint peeling off
rain with strong wind. craks issues.
recurred on previously painted wall at
staircase wall and visible fungus on
walls.

Some deep crack found at several place


This issue also highlighted to Amanah
on rooftop surface slabs that caused water
Raya Reits Management since Mr.
leaks into tenants ceiling below the
2 Menon's time. SASB had noticed The job was completed. Done.
cracked area. It’s happened due to
there are water dripping from upper
frequent of expanding and shrinking effect
slab at level 12 tenanted area.
from weathers conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Meeting have been conducted within SASB and


Draft Contract Agreement (CA) between Daya Bersih for SLA issues on 19th July 2016.
Daya Bersih and HSB was obtained. The CA still not signed and return They were highlighted some issues on our SLA
3 Waiting for their proposal.
Already go thru the CA and revert to Daya back to SHB. commitment level and was discussed accordingly.
Bersih Management. They will proposed their SLA Commitment Level
as per their existing contract with another clients.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Draft Contract Agreement (CA) between
Dell Security and HSB was obtained. The CA still not signed. Dell Security
Our Legal Department was amended the CA
1 Already go thru the CA and will update the SOP was obtained but is was too
andsent to Dell for revision.
correction and amendment to Dell Security simple.
Management.

Selling of CCTV, Access Card and Our existing installed CCTV, Access
They were choose to buy new unit and already We have taken down the existing unit
2 Magnetic Door equipment to HRS due to Card and Magnetic Door equipment
installed. and kept as spare parts.
separation of operations. to be sell as where as basis to HRS.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Fire and Consequential Loss Insurance. Expiry on31/5/2017 9 months to go.

Invited Takaful Ikhlas personel for discussion on


To purchase the Machinery Breakdown the insurance matters and was give them our
2 Not yet purchase.
insurance. machinery details. They will come out with their
proposalfor the insurance and coverages.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP
1 Expiry on 14/12/2016 2 months to go. Department at least 1 month before
Passenger Lift 4 (PMA 18839) expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
2 Electrical Installation (11KV) 5/27/2018 8 months to go. To be renew with Energy Commission
Department at least 2 months before
3 Electrical Installation (GENSET 280KW) 1/6/2017 3 months to go. expiry.
25/2/2017. Jeyapalan has been
Interviews for new B0 Chargeman was conducted The new Chargeman B0 will be report to
4 Electrical B0 Chargeman Registration resigned and his last working day will
with HR and new candidate was choose. start works on 9th September 2016.
be on 14 September 2016.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2017 13 months to go.
Calibration least 1 months before expiry.
Bomba was succesfully conducted an inspection
To pay sum of RM200 of renewal fees
on 18 August 2016. They have fully satisfied on
6 Fire Certificate Expiry on 5/4/2016 and PR has been submitted to
our Fire Protection System. The Fire Certificate
Procurement for payment process.
was ready for collection.

Renewal of Portable FE's certificate was To be sent for service and certificate
7 Portable Fire Extinguisher Certificates Expiry on 20/8/2016
completed and new expiry date was on 5/8/2017. renew at least 1 months before expiry.

L ADMINISTRATIVE AND OTHERS


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Paid by Puncak Dana on 10th March
1 Quit Rent 2016 Done.
2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) Done. Paid on 8/8/2016
2nd Half Rate = RM250,736.64

Some of Gym equipment was found


Proposed to engage with Fitness Concept on
broken and out of order such as
advise, maintenance and repairs. Some of steel
Treadmills, Rower Machines,
Some of Gymnasium equipment was wire rope found worn out and can snap anytime
4 Standing Bikes, Upright Bike,
broken and out of order. and caused injuries to users. Fitness Concept was
Recumbent Bike, Gym Station and
called and they will revert on the visiting time and
some others. All the equipment need
date.
some maintenance and repairs.

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

They were still asking for the credits from Service


Charges for July 2016. Their new CFO willing to
1 LemonSky Animation Sdn. Bhd. Renovation was completed. meet us for appeal on the Service Charges
deductions. The meeting date will be set later by
them.

Willing to expand their office space


rental. Interested on 8th floor (SHB) HILTI was emailed us on their officially move out.
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also They will starts moves from 29th September 2016
willing to pay the costs of relocations onwards.
and reassembles.
DU TA Printing was awarded the job for supply
and installation of the banner. Currently workout
3 Ground Floor Vacant space
on the wording type and colour design and to get
your approval.

2 of invited vendors was submitted their prices for


the reintatement cost such as:
Air Conditioning compressors
To get the estimation costs of
Estimate of reinstatement costs for a) U Jin Engineering Works - RM3,521,956.00 reinstatement cost was submitted by
4 Symphony Group reinstatement as
Symphony Group Office spaces. (Included of GST) Team Service Sdn. Bhd. For the sum of
soon as possible.
RM1,125,137.00
b) Central Trafalgar Sdn. Bhd. - RM1,765,945.00
(Included of GST)

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
MNH GLOBAL ASSETS MANAGEMENT
1 3/8/2016 (1 DAY) Paid RM530.00
SDN BHD
2 Citibank 15/8/2016 (1 DAY) Paid RM530.00
3 Hatten Group Sdn Bhd 16,17 & 18/8/2016 (3 DAYS) Paid RM1,590.00
4 GC Event Hub - RHB Credit Card 22 & 23/8/2016 (2 DAYS) Paid RM1,060.00
GC Event Hub - Standard Chartered Credit
5 25 & 26/8/2016 (2 DAYS) Paid RM1,060.00
Card
6 Haewaytian Food Industries Sdn Bhd 29/8/2016 (1 DAY) Paid RM530.00
BUILDING MANAGEMENT UPDATES AS AT 30/9/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.
C PLUMBING & SANITARY SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The Male Toilet Mirror at 9th floor was Several vendors was called to do site
1 badly rusted inside the mirror reflector and visit and submit their quotation for
need to replace. replacement.
D VERTICAL TRANSPORTATION SYSTEM (LIFT)
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


All the amendment was done and agreed by both
SIGMA and HSB was obtained. Already go Waiting for their original Letter Head for
1 The CA still not signed. parties. We will sign the agreement and pass to
thru the CA and will update the correction Agreement.
SIGMA for sign and to make duty stamping.
and amendment to SIGMA Management.

The lift was completely restore to normal


It was happened during operation but we have yet to received the
Lift No.1 was found over shooted to top
troubleshooting the problems lift structural engineer to certify that there is no
floor and caused the lift to hit the top floor
2 brake and the incident happened due structural damage to the building from the incident
slab while counterweight runs to buffer on
to human mistakes and procedure and update on the items no. 1,3,4 and 5 as
17th August 2016 about 6.30pm.
violation. highlighted before. Followed up email was sent to
SIGMA on 14 September 2016.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Electricity Utilities bill was doubled-charged


by TNB to SHB. The charged are still No any deduction has been made to The follow up call has beenmade to Pn. Nora on
1 around the same as before even AEGIS our Main Electricity bills since and she had promised to follow up this issue until
had install their dedicated Electricity Sub- January 2016. resolves.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

The Standby Power Generator (Genset)


Last servicing date that was stated on
was overdue for general servicing and
the genset was made on 3/9/2013.
need to get it done soonest possible to To call several vendors for site visit and submit
1 According to the OEM manuals, the
avoid any power interruption or breakdown their quotation for general service.
genset sould be service at least once
to the genset itself when running on power
a year.
failure situations.

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

This issues was highlighted to


Amanah Raya Reits Management
since Mr. Menon's time. It's caused
There are hair line cracks on external Followed up was made on16th August 2016 and
of water seepage into internal wall
façade wall that caused caused of water was informed that ARRM still in the midst of En.Hasrol was advised us to continue the
1 whenever heavy rain with strong
seepage into internal wall whenever heavy dealing with their lawyer on the repairing hairline sinking fund payment as well.
wind. It's also caused paint peeling off
rain with strong wind. craks issues.
recurred on previously painted wall at
staircase wall and visible fungus on
walls.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Received their proposal and waiting for SASB
Daya Bersih and HSB was obtained. The CA still not signed and return
3 representative to sign the agreement before return
Already go thru the CA and revert to Daya back to SHB.
back to Daya Bersih for stamping.
Bersih Management.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Dell Security and HSB was obtained. The CA still not signed. Dell Security
The agreement was signed by En. Muhammad
1 Already go thru the CA and will update the SOP was obtained but is was too
Ashraf and was returned to DELL for stamping.
correction and amendment to Dell Security simple.
Management.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Fire and Consequential Loss Insurance. Expiry on31/5/2017 8 months to go.

Invited Takaful Ikhlas personel for discussion on


To purchase the Machinery Breakdown the insurance matters and was give them our Looking for another insurer to submit
2 Not yet purchase.
insurance. machinery details. They will come out with their their proposal.
proposal for the insurance and coverages.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) To be renew with DOSH/JKKP
1 Expiry on 14/12/2016 1 month to go. Department at least 1 month before
Passenger Lift 4 (PMA 18839) expiry
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)
2 Electrical Installation (11KV) 5/27/2018 7 months to go. To be renew with Energy Commission
Department at least 2 months before
3 Electrical Installation (GENSET 280KW) 1/6/2017 2 months to go. expiry.
25/2/2017. Jeyapalan has been
New B0 Chargeman En. Rahmad was report for
4 Electrical B0 Chargeman Registration resigned and his last working day will
duty on 9/9/2016.
be on 14 September 2016.
Electrical Safety Protection Device To be recalibrate and certificate renew at
5 10/16/2017 12 months to go.
Calibration least 1 months before expiry.
6 Fire Certificate Expiry on 28/8/2017 New FC was obtained.
To check and renew the certificate at
7 Portable Fire Extinguisher Certificates Expiry on 5/8/2017 9 months to go.
least 1 months before expiry.
L ADMINISTRATIVE AND OTHERS
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Paid by Puncak Dana on 10th March
1 Quit Rent 2016 Done.
2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) Done. Paid on 8/8/2016
2nd Half Rate = RM250,736.64

Some of Gym equipment was found


broken and out of order such as
Treadmills, Rower Machines,
Some of Gymnasium equipment was No any updates from Fitness Concept and will
4 Standing Bikes, Upright Bike,
broken and out of order. follow up again.
Recumbent Bike, Gym Station and
some others. All the equipment need
some maintenance and repairs.

M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

No any updates from LemonSky for new meeting


1 LemonSky Animation Sdn. Bhd. Renovation was completed.
date on appeal for service charge credits.

Willing to expand their office space HILTI was officially move out on 2nd September
rental. Interested on 8th floor (SHB) 2016 but are yet to received their office keys. The
2 Hilti Asia IT Services Sdn. Bhd. and 7th floor (Aegis). They also office reinstate also pending no any progress. We
willing to pay the costs of relocations will made due diligence inspection with them after
and reassembles. the office reinstate was completed.

DU TA Printing that we have awarded the job for


Vacant Space Banner installation was sent an
3 Ground Floor Vacant space email for surrender. However, we will proceed with
the new vendor that submitted second lowest
price.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 Citibank Credit Card Promotion 21/9/2016 (1 DAY) Paid RM530.00
2 HSBC Credit Card Promotion 23/9/2016 (1 DAY) Paid RM530.00
3 AIA Insurance Promotion 30/9/2016 (1 DAY) Paid RM530.00
4
5
6
BUILDING MANAGEMENT UPDATES AS AT 31/10/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.
C PLUMBING & SANITARY SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The Male Toilet Mirror at 9th floor was Several vendors was called to do site
PO had been issued to Maju TKK Enterprise and
1 badly rusted inside the mirror reflector and visit and submit their quotation for
waiting for replacement.
need to replace. replacement.
D VERTICAL TRANSPORTATION SYSTEM (LIFT)
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


SIGMA and HSB was obtained. Already go The CA was signed by both parties and was sent
1 The CA still not signed.
thru the CA and will update the correction for stamping by SIGMA.
and amendment to SIGMA Management.

The lift was completely restore to normal


It was happened during operation but we have yet to received the
Lift No.1 was found over shooted to top
troubleshooting the problems lift structural engineer to certify that there is no
floor and caused the lift to hit the top floor To proceed withnext coming JKKP Inspection as the PMA
2 brake and the incident happened due structural damage to the building from the incident
slab while counterweight runs to buffer on Certification will expire on 14/12/2016.
to human mistakes and procedure and update on the items no. 1,3,4 and 5 as
17th August 2016 about 6.30pm.
violation. highlighted before. Followed up email was sent to
SIGMA on 14 September 2016.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Electricity Utilities bill was doubled-charged


Received an email on 28/10/2016 for Credit Note
by TNB to SHB. The charged are still No any deduction has been made to
amounting RM216,601.15 from TNB for period of
1 around the same as before even AEGIS our Main Electricity bills since
1/2/2016 to 1/4/2016 and should appear in the
had install their dedicated Electricity Sub- January 2016.
next coming bills.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

The Standby Power Generator (Genset)


Last servicing date that was stated on
was overdue for general servicing and Received several quotation and Edi Services Sdn.
the genset was made on 3/9/2013.
need to get it done soonest possible to Bhd. was awarded the job with the lowest
1 According to the OEM manuals, the
avoid any power interruption or breakdown submitted price RM5000.00. Waiting for the PO to
genset sould be service at least once
to the genset itself when running on power issue.
a year.
failure situations.

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Received their proposal and waiting for SASB
Daya Bersih and HSB was obtained. The CA still not signed and return
3 representative to sign the agreement before return
Already go thru the CA and revert to Daya back to SHB.
back to Daya Bersih for stamping.
Bersih Management.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Dell Security and HSB was obtained. The CA still not signed. Dell Security
The CA was signed by both parties and was sent
1 Already go thru the CA and will update the SOP was obtained but is was too
for stamping by Dell Security.
correction and amendment to Dell Security simple.
Management.
Chronology of complaint received from tenants since
August 2016 until now such as:

1) 26/8/2016 - Guard failed to identify the stranger


without Staff ID Pass.

2) 20/9/2016 - Guard failed to identify the stranger


Sent many warning email to the Dell Security without Staff ID Pass and caused stranger loitering
Management and keep received an excused and around inside building area.
We had received many complaints
same explanation. Will proceed with the SLA
complete with photos proofs from
Penalties as the Contract Agreement was 3) 25/9/2016 - Guard that stationed at Security Counter
tenants regarding our Security
2 Repeated offences by Security personel. completely signed and agreed by both parties. and Basement was deep sleeping around 12.30am.
Services had done repeated offences
Latest comment received from Ms. Evan Woo
during working time within very short
from OS HRS on yesterday night regarding our 4) 30/9/2016 - Guard that stationed at Basement was
period of time.
Security Personel that stationed at Basement was deep sleeping around 1.00am.
deep sleeping around 9.30pm.
5) 12/10/2016 - Guard failed to identify the stranger
without Staff ID Pass and caused stranger loitering
around inside building area (2nd Case) and manage to
get some money from one of Aegis’ staff.

6) 31/10/2016 - Guard that stationed at Basement was


deep sleeping around 9.30pm.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Fire and Consequential Loss Insurance. Expiry on31/5/2017 7 months to go.

Invited Takaful Ikhlas personel for discussion on


To purchase the Machinery Breakdown the insurance matters and was give them our
2 Not yet purchase. Looking for another insurer to submit their proposal.
insurance. machinery details. They will come out with their
proposal for the insurance and coverages.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838)
1 Expiry on 14/12/2016 1 month to go. Proceed for applying online with JKKP.
Passenger Lift 4 (PMA 18839)
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)

To be renew with Energy Commission Department at


2 Electrical Installation (11KV) 5/27/2018 6 months to go.
least 2 months before expiry.

3 Electrical Installation (GENSET 280KW) 1/6/2017 2 months to go. Proceed for applying online with Energy Commision.

25/2/2017. Jeyapalan has been


New B0 Chargeman En. Rahmad was report for
4 Electrical B0 Chargeman Registration resigned and his last working day will
duty on 9/9/2016.
be on 14 September 2016.

2 units of Earth Leakage Relay (ELR) at Electrical


Electrical Safety Protection Device Swithcboards was out of order and need to replace.
5 10/16/2017 12 months to go.
Calibration Called some vendor to obtain the quotation for
replacement.

6 Fire Certificate Expiry on 28/8/2017 10 months to go.


To check and renew the certificate at least 1 months
7 Portable Fire Extinguisher Certificates Expiry on 5/8/2017 9 months to go.
before expiry.
L ADMINISTRATIVE AND OTHERS
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Quit Rent 2016 Done. Paid by Puncak Dana on 10th March 2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) Done. Paid on 8/8/2016
2nd Half Rate = RM250,736.64
M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

DU TA Printing was surrendered to proceed the


job and we had reawarded the job to the second
1 Ground Floor Vacant space Ads.
lowest price submitted (DCC Trading). PO has
been issued and waiting for installation.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS
1 Citibank Credit Card Promotion 25/10/2016 (1 DAY) Paid RM530.00
2 HSBC Credit Card Promotion 26-27/10/2016 (2 DAYS) Paid RM1,060.00
BUILDING MANAGEMENT UPDATES AS AT 30/11/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

1 No any big issues. All in order and working conditions.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Quotation obtained from Safety Link and Fire Fighter for
Fire Panel always shows Alarm Fault To get a Fire Alarm Vendor for checking and
1 Zone 1 Alarm Fault issue checking. Safety Link was selected for checking the Fire
Signal. repair.
Alarm Fault Issue.

In the midst of preparing all the fire equipment, invitation


To conduct Fire Drill Exercise on Conducted Fire Drill Talk with Bomba and ERT
2 Fire Drill Exercise and documentations to all related vendors and ERT
22nd December 2016 Team at RNR on 30th Nov 2016.
Team.
C PLUMBING & SANITARY SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
The Male Toilet Mirror at 9th floor was Several vendors was called to do site
Maju TKK was completely replaced the mirror on
1 badly rusted inside the mirror reflector and visit and submit their quotation for Done.
12th Nov 2016.
need to replace. replacement.
D VERTICAL TRANSPORTATION SYSTEM (LIFT)
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


SIGMA and HSB was obtained. Already go
1 The CA was sign by both parties. Done.
thru the CA and will update the correction
and amendment to SIGMA Management.

The lift was completely restore to normal


It was happened during operation but we have yet to received the
Lift No.1 was found over shooted to top
troubleshooting the problems lift structural engineer to certify that there is no
floor and caused the lift to hit the top floor To proceed with next coming JKKP Inspection as the
2 brake and the incident happened due structural damage to the building from the incident
slab while counterweight runs to buffer on PMA Certification will expire on 14/12/2016.
to human mistakes and procedure and update on the items no. 1,3,4 and 5 as
17th August 2016 about 6.30pm.
violation. highlighted before. Followed up email was sent to
SIGMA on 14 September 2016.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Electricity Utilities bill was doubled-charged


by TNB to SHB. The charged are still All the overpaid amounts of
1 around the same as before even AEGIS RM216,601.15 was credited in Nov Done.
had install their dedicated Electricity Sub- and Dec 2016 bills.
Meter.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

The Standby Power Generator (Genset)


was overdue for general servicing and
The Standby Genset was completely
need to get it done soonest possible to
1 serviced by Edi Serviceson 26th Nov Done.
avoid any power interruption or breakdown
2016.
to the genset itself when running on power
failure situations.

Any diesel storage in building must have


Diesel permits and it should be obtained
In the midst of preparation all the related
from KPDNHEP under Seksyen 5 Akta Symphony House Building doesn't
2 documentations for applying the Diesel Storage
Kawalan Bekalan 1961 and stipulated in have Diesel Storage Permit
Permit before submission.
Table 1 Peraturan-Peraturan Kawalan
Bekalan 1974.

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Daya Bersih and HSB was obtained.
3 The CA was sign by both parties. Done. Done.
Already go thru the CA and revert to Daya
Bersih Management.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Draft Contract Agreement (CA) between


Dell Security and HSB was obtained.
1 Already go thru the CA and will update the The CA was sign by both parties. Done. Done.
correction and amendment to Dell Security
Management.
We had received many complaints
complete with photos proofs from
tenants regarding our Security The penalized of RM800 was charged to Dell Dell Security was issued a Credit Note of RM800 for the
2 Repeated offences by Security personel.
Services had done repeated offences Security using the SLA commitment charges. penalty purposes.
during working time within very short
period of time.

J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Fire and Consequential Loss Insurance. Expiry on31/5/2017 7 months to go.

Invited Takaful Ikhlas personel for discussion on


To purchase the Machinery Breakdown the insurance matters and was give them our
2 Not yet purchase. Looking for another insurer to submit their proposal.
insurance. machinery details. They will come out with their
proposal for the insurance and coverages.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) Application was submitted to JKKP for renewal
1 Expiry on 14/12/2016 JKKP to deal with SIGMA for the inspection date.
Passenger Lift 4 (PMA 18839) and waiting for inspection date.
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)

To be renew with Energy Commission Department at


2 Electrical Installation (11KV) 5/27/2018 5 months to go.
least 2 months before expiry.

1 months to go. Submitted online application with


3 Electrical Installation (GENSET 280KW) 1/6/2017 Energy Commision and the payment was paid to
ST. Waiting for the cedrtificate issuance.

Waiting for the certificate issuance from


New B0 Chargeman En. Rahmad
4 Electrical B0 Chargeman Registration Suruhajaya Tenaga for new B0 registration with
was report for duty on 9/9/2016.
ST.

2 units of Earth Leakage Relay (ELR) at Electrical


Electrical Safety Protection Device Swithcboards was out of order and need to replace.
5 10/16/2017 11 months to go.
Calibration Some quotation was obtained from vendors. To get
another quotaton from another vendors.

6 Fire Certificate Expiry on 28/8/2017 9 months to go.


To check and renew the certificate at least 1 months
7 Portable Fire Extinguisher Certificates Expiry on 5/8/2017 8 months to go.
before expiry.
L ADMINISTRATIVE AND OTHERS
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Quit Rent 2016 Done. Paid by Puncak Dana on 10th March 2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) Done. Paid on 8/8/2016
2nd Half Rate = RM250,736.64
M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Get a new price from new vendor Life Style Sdn.


Bhd. Final artwork was submitted to them for
printing. Due to sharing cost for the installation, Managed to discuss again with Symphony Life and they
1 Ground Floor Vacant space Ads.
there are an issues with Symphony Life which are were confirmed the installation will be on next week..
the banner will install on January 2016 and it was
too long wasting time.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS

1 Standard Chartered Credit Card Promotion 9&22/11/2016 (2 DAYS) Paid RM1,060.00

2 HSBC Credit Card Promotion 30/11/2016 (1 DAY) Paid RM530.00


BUILDING MANAGEMENT UPDATES AS AT 31/12/2016

A AIR CONDITIONING SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

1 No any big issues. All in order and working conditions.

B FIRE PROTECTION SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Safety Link was came and reprogramme the Fire
Fire Panel always shows Alarm Fault
1 Zone 1 Alarm Fault issue Alarm Panel and reset the system. All system Done.
Signal.
back to normal.

To conduct Fire Drill Exercise on Fire Drill was succesfully conducted on 22nd Dec
2 Fire Drill Exercise We got 90% marks from BOMBA. Done.
22nd December 2016 2016.

C PLUMBING & SANITARY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Unpleasant smeel was coming from Building Management team managed to buy the
Unpleasant smell at 1st floor walkway to Currently was completed at Female Toilets. To continue
1 the toilets floor trap that doesn't have piping parts and modified the existing piping
Tan Sri Azman Office. for Male Toilets ASAP.
U Trap system. system.
D VERTICAL TRANSPORTATION SYSTEM (LIFT)
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

1 No any big issues. All in order and working conditions.

E ELECTRICAL SYSTEM
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

1 No any big issues. All in order and working conditions.

F ESSENTIAL/ BACK UP POWER SUPPLY SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

Any diesel storage in building must have


Diesel permits and it should be obtained
In the midst of preparation all the related
from KPDNHEP under Seksyen 5 Akta Symphony House Building doesn't
1 documentations for applying the Diesel Storage
Kawalan Bekalan 1961 and stipulated in have Diesel Storage Permit
Permit before submission.
Table 1 Peraturan-Peraturan Kawalan
Bekalan 1974.

G CIVIL& STRUCTURAL SYSTEM


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 No any big issues. All in order and working conditions.

H HOUSEKEEPING & CLEANING SERVICES


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

1 No any big issues. All in order and working conditions.

I SECURITY SERVICES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Buy the laminate papers, clips and hole puncher.
The existing Visitor Passes were To make a new design according to Symphony
1 To make new Vendor and Visitor Passes. Done.
damaged and too basic. Building and getting approval from top
management.
J INSURANCES
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
Renewal of insurance was submitted to insurer
Public Liability Insurance was expired
1 Public Liability Insurance. and waiting for the new certificate issuance and
and to renew ASAP.
payment.

K CERTIFICATION AND AUTHORITY COMPLIANCE


NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
BOMBA Lift 1 (PMA 18836)
Passenger Lift 2 (PMA 18837)
Passenger Lift 3 (PMA 18838) Application was submitted to JKKP for renewal
1 Expiry on 14/12/2016 The inspection date was set on 11th January 2017.
Passenger Lift 4 (PMA 18839) and waiting for inspection date.
Passenger Lift 5 (PMA 18840)
Passenger Lift 6 (PMA 18841)

To be renew with Energy Commission Department at


2 Electrical Installation (11KV) 5/27/2018 4 months to go.
least 2 months before expiry.

Submitted online application with Energy


3 Electrical Installation (GENSET 280KW) 1/6/2017 Commision and the payment was paid to ST.
Waiting for the cedrtificate issuance.

Obtained the certificate from Suruhanjaya Tenaga


To be renew with Energy Commission Department at
4 Electrical B0 Chargeman Registration Issued by Suruhanjaya Tenaga. and was succesfully registered to Suruhanjaya
least 2 months before expiry.
Tenaga.

Electrical Safety Protection Device Replaced 2 units of Earth Leakage Relay (ELR) at
5 10/16/2017 10 months to go.
Calibration Electrical Swithcboards . Done.

To check and renew the certificate at least 3 months


6 Fire Certificate Expiry on 28/8/2017 8 months to go.
before expiry.
To check and renew the certificate at least 1 month
7 Portable Fire Extinguisher Certificates Expiry on 5/8/2017 7 months to go.
before expiry.
L ADMINISTRATIVE AND OTHERS
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS
1 Quit Rent 2016 Done. Paid by Puncak Dana on 10th March 2016.
Payment to be made by 28/2/2016
2 Assesment (1st half 2016) Done. Paid on 3/2/2016
1st Half Rate = RM250,736.64
Payment to be made by 31/8/2016
3 Assesment (2nd half 2016) Done. Paid on 8/8/2016
2nd Half Rate = RM250,736.64
M TENANCY
NO. ISSUE CURRENT STATUS ACTION TO BE TAKEN/ TAKEN REMARKS

The banner was succesfully hanged outside the


1 Ground Floor Vacant space Ads. Done.
Symphony Building at 8th foor.

N BOOTH RENTAL
NO. COMPANY/PERSON IN-CHARGE DATE/DAYS PAYMENT STATUS REMARKS

1 HSBC Credit Card Promotion 1&2/12/2016 (2 DAYS) Paid RM1,060.00