NED UNIVERSITY OF ENGINEERING & TECHNOLOGY, KARACHI

DEPARTMENT OF COMPUTER SCIENCE & INFORMATION TECHNOLOGY

FYP Progress Report

Reporting Period: April 2017 - July 2017 To: Project Monitoring Committee
Project Name: NEDOC-HUB Date: 17/07/17
From: Project Personnel Names & Roll Numbers
Aasma Abbasi SE-301
Sadia Arshad SE-051
Hira Maqsood

 Overview :
 -Making sketch of user interface.
 -Designing user interface.
 -Finding out tables and relations among them using ERD.
 -Finally implementing database.
 -Integrating database with UI.
 -Making different accounts for user and setting authorities.

Summary On Schedule or Ahead of Schedule? Yes ___ No ___


On Target to Meet Objectives and Requirements? Yes ___ No ___
Any Additional Technology / Software Acquired? Yes ___ No ___

A. CURRENT STATUS

Accomplishments

 Designing UI :
Made a rough sketch of UI. Created UI, different from system which already exist
Complete PHP Tutorials is practiced.

 Implementation of database:
Finding out tables and relationship among them which will be used in our database. We have used
MySQL for creating database. MySQl is an open-source relational database management system. MySQL is one
of the best platform used for developing databases and an easy to use tool.

 Integrating UI with database :

Successfully integrated UI with database, all the changes made on website like storing of files and deletion of
files can easily be seen in the database.
Problem Areas (Challenges):
- Security
- Introducing digital signature on website
.

B. ISSUES

Technical Issues
It was discussed in project meeting to use SharePoint to develop this project but after complete research and
under the supervision of project internal it was finalized to use PHP . By using SharePoint we cannot
customize according to the needs and requirements of NEDUET working body.

Management Issues:
No issues so far .

C. Comments of the Internal Advisor:

____________________________________________________________________________________
__

______________________________________________________________________________________

Marks(out of 20):____________

Date:________________
__ Signature(Internal Advisor):__________________

Task Name Start End Duration(Days) Student


Responsibility
Design Phase 1-03-2017 15-04-2017 45 done
1.Sketching 1-03-2017 2-03-2017 2 done
2..Designing user 3-03-2017 1-04-2017 27 done
Interface
(prototyping)
3.Designing 15-03-2017 14-04-2017 30 done
Database
4.Showing Design to 15-04-2017 15-04-2017 0 done
Internal
Implementation 16-04-2017 30-07-2017 74 done
Phase
1.Front end 16-04-2017 16-05-2017 30 done
programming
2.Backend 20-04-2017 10-05-2017 20 done
programming
3.Implementating 10-05-2017 16-06-2017 36 done
Database
4.Integrating UI with 17-06-2017 30-06-2017 13 done
database
5.Working on UI 1-07-2017 10-07-2017 25 done
6.Making different 10-07-2017 30-07-2017 20
accounts