You are on page 1of 5

October 2006

Construction
Law UAE
Introduction Our third feature – entitled “The UAE’s Accession to the New
York Convention: worth the wait?” – highlights the implications
This, the first edition of Construction Law UAE, looks at three of the recent accession by the UAE to the New York
issues which have emerged from the white heat of the UAE’s Convention on the enforcement of foreign arbitral awards.
construction market. The UAE construction market, although not yet as litigious as
many, will need to consider whether these new developments
First, is the market too hot for traditional lump sum make UAE arbitration more, or less, of a mug’s game.
turnkey procurement? With most mega-schemes
half-completed before the design and specification The aim of Construction Law UAE is to stimulate debate. Please
are finalised, could the market benefit from a move take the time to email your thoughts and comments on what
towards cost reimbursable guaranteed maximum price we have said. We would like to publish the best responses. So,
contracting? We look at some of the pros and cons of this when emailing, please indicate if you are unwilling for us to do
approach in “UAE: Time for GMP Contracting?” so. In future editions we hope to feature guest contributions
from our readers. Please let us know if you would like to be
Second, claims. The FIDIC Fourth Edition remains the contract a guest contributor. Please contact Di McCleland on 04 405
form of choice in the UAE. One of its advantages, of course, 4150 or, alternatively, email her at
is the flexibility it allows for instructing and valuing scope di.mccleland@dentonwildesapte.com.
changes and the consequential re-scheduling. On the other
hand, its antiquated and obscure language can make the Denton Wilde Sapte’s UAE construction group includes lawyers
meaning of key provisions hard to pin down. This is particularly with many years’ experience negotiating and concluding major
the case where notice procedures are to be complied with works contracts and handling all kinds of dispute resolution,
as a precursor to claims for additional time and money. How claims and advisory work in the UAE, across the Middle East
should these sometimes imprecise and conflicting provisions and throughout the developed and developing world. We are,
be understood, particularly when read in the light of relevant in Abu Dhabi: Alistair Hirst and Steven Tee; in Dubai: David
articles of the UAE Civil Code? In “I thought you’d never notice: Courtney-Hatcher, Michael Kerr, Ravinder Bhullar, Andrew
The UAE Civil Code and Claims under the Red Book” we Chegwidden, Ashley Hill, Nick Kramer and Matthew Blycha.
suggest some answers.
UAE: time for GMP Contacting? The incentives usually arise by agreement of a “target cost”
– sometimes an evolution of the GMP agreed between the
Clients who ask us to help them draft forms of guaranteed parties when the design has become sufficiently frozen. In
maximum price (GMP) contracts, have a variety of reasons for other words, once the design target is no longer moving, the
their decision to contract on this basis. Fixed price lump sum target cost can be fixed.
contracting, they point out, assumes that the design will be
more or less complete at the time the contract is signed. The The target cost will work in conjunction with a pain/gain share
Contractor will have had time to assess the “buildability” of regime. So, if actual cost is lower than target cost, the cost
the project, to organise his supply chain and sub-contractors saving is shared on a pre-agreed percentage basis. If on the
and generally to have satisfied himself that the job can be other hand actual cost exceeds target cost, the cost overrun is
completed at a profit, for the contract price and within the only shared between by the Developer and the Contractor to
contract time. the extent of the pre-agreed percentage, with the Contractor
retaining the risk of all cost overruns above the GMP.
In the UAE, of course, precisely the opposite is usually the case.
First, the price and programme are fixed against an outline The advantages are obvious. In order to earn their shares of
design, then a contract of some kind - often just a letter the cost savings or minimise their shares of the cost overruns,
agreement - is signed. Only after that is the design developed both parties will need competent project management,
to a level of detail which enables the Contractor to see exactly efficient design development and drawing issue, tight sub-
what he has committed himself to. The result, not surprisingly, contract procurement and supply chain management and
is a book of variations which quickly runs out of control and a elimination of waste.
completion date without basis in reality.
So much for the underlying principles: what about the
There are signs that the UAE’s major developers are starting to practice? Some alarming consequences have resulted from
realise that they can’t have it both ways. Fixed price and fixed the unshakeable belief, still widespread in the UAE, that any
time mean fixed workscope. If, on the other hand, an instant construction contract should be drafted using the FIDIC Red
start on site really is essential, with construction following hard Book (4th Edition) as its basis. A quick glance should satisfy
on the heels of design development, a procurement method even FIDIC’s most loyal users that it cannot easily be adapted
which is more flexible than the rigid fixed price lump sum for use as a GMP/cost reimbursable/target cost contract.
approach is needed. A number of suitable standard form contracts have been
published. These include the UK’s JCT Prime Cost contract, the
For these reasons, the UAE’s construction industry is seeing NEC Option C, D and E and the ICHEME Green form but none
increasing numbers of contracts awarded on the basis of a of these seems yet to have found favour in the UAE.
GMP. The advantage of GMP contracting, if properly used,
is that it facilitates an early start on site without sacrificing You should, therefore, consider using one of these forms as
reasonable price certainty. It incentivises the Contractor to the basis for your GMP/target cost contract, rather than FIDIC.
be efficient and the Developer to ensure that his design team Or, if you decide to go bespoke remember you will need a
sticks to the design development programme. contract which covers at least the following:
• a way of fixing the target cost (if not already fixed in the
So, how does GMP contracting work? Typically, the Contractor contract);
bids against the Developer’s preliminary or outline design and
specification and the parties agree a guaranteed maximum • the criteria for adjusting the GMP and/or the target cost
price. Interim payment valuations are made on an actual and a procedure for agreeing or fixing those adjustments;
cost, open-book basis. The categories of reimbursable costs • what will constitute changes in the original scope, sufficient
- labour, materials, plant and sub-contractors – are pre- to justify increases in the GMP and/or target cost?
agreed. There is a fee, either a lump sum or a percentage
of the reimbursable cost, to compensate the Contractor for • the admissible categories of reimbursable costs;
overheads, profit and preliminaries. As the design develops, • how is the fee calculated and what does it include and
often with the benefit of the Contractor’s suggestions on exclude?
buildability, the GMP remains fixed, subject only to adjustment
in case of major scope or design concept changes, or the usual • which cost components are fixed at the date of the
Employer’s risk events. contract and which are subject to escalation?
• how will the advance payment, if any, be apportioned not strictly adhered to by the Contractor, the claim will be dead
between cost and fee? in the water - in other words, the Engineer may be entitled to
reject the claim outright. Building and civil works contracts in
• what compensation is payable upon termination? …and so
the UAE are generally governed by UAE law and hence the
on.
UAE Civil Code (the Civil Code) will apply. This article considers
To conclude: GMP/target cost arrangements may be part of how, when express notification procedures are read in the light
the answer to the time/cost/scope tensions which are part of applicable provisions of the Civil Code, a more moderate
and parcel of the UAE’s fast-track mentality. These contracts and fair outcome may emerge.
can be written simply and clearly but FIDIC, particularly the
modified version of the FIDIC Red Book (4th Edition) which is
still widely used in the UAE, is not the place to start.
Entitlement to Claim
The Red Book provides that in certain circumstances a
Contractor’s entitlement to claim may be lost if he fails to give
notice of his intention to claim or fails to provide detailed
claim particulars within the timescales prescribed. There
I Thought You’d Never Notice: are two provisions of the Red Book which state that a failure
to comply with the specified notice or particularisation
The UAE Civil Code and Claims procedures for making a claim will justify the rejection of the
claim.
under the Red Book
First, Clause 44.2, which is concerned with applications for
FIDIC in the UAE extensions of time. This clause provides that in case of non-
For all its innovation and spectacular achievements, the compliance with the time limit to provide notice and/or to
construction industry in the UAE has been slow to move on from provide detailed claim particulars, the Engineer “is not bound
its close relationship with the FIDIC Red Book (4th Edition) (the to make any determination” of a claim for an extension of
Red Book). This was, of course, superseded long ago and it is time. The Engineer, therefore, has a discretion not to make
scarcely used anywhere else in the world, outside of this region. a determination if either the time limit for notice or for
particularisation is not met.
The Red Book provides a number of notoriously tricky
procedures for claim notification and particularisation to be Second, Clause 52.2, which applies to applications for payment
followed by the Contractor. They are not sharply drafted and for variations. This clause states that the varied work will not
their meaning and intent are not always clear. However, it seems be valued unless notice of an intention to claim extra payment
to be implied in some cases that if these procedures are is made within 14 days of the date of the instruction. Strictly
construed, this clause allows for a claim to be disallowed if the
14 day time limit is not complied with.


Clauses which expressly provide procedures for claim notification and
particularisation are:
6.3 Notice of delay or disruption in case of delayed information or
instructions;
12.2 Notice of adverse physical obstructions or conditions;
30.3 Notice of damage to any bridge or road due to the transport of
Materials or Plant;
38.1 Notice of when any part of the Works or foundation is ready to be 
There is no prescribed form of notice. Clause 1.5 of the Red Book
covered up (compliance required for 38.2 to apply); states that notices must be in writing and that the word “notify” is to
40.3 Notice requesting permission to proceed with work after a suspension be construed accordingly. As such, there is no reason why a monthly
lasting more than 84 days (compliance required for 51.1 to apply); report, for example, could not be construed as a notice. However, it
42.1 Notice containing “reasonable proposals” regarding access and would be prudent for the Contractor to make two things clear. First,
possession (compliance required - arguably - for 42.2 to apply); that the written information is intended to be a notice under the
contract. Second, the clause under which it is given - this will include
44.2 Notice of an application for an extension of time; in every case at least Clause 53.1or Clause 44.2.
52.2 Notice to claim additional payment for varied work; 
The Red Book is silent as to what constitutes “detailed particulars”.
53.1 Notice to claim additional payment “under any clause of these This will vary case-by-case. It would be good policy, wherever possible,
Conditions or otherwise”; for the Contractor to invite the Engineer to confirm that he is satisfied
with the detail provided, or if not, to say so.
65.5 Notice of increased costs arising from Special Risks; and 
Please note that Clause 53.1 states that, “notwithstanding any other
69.4 Notice of suspension by the Contractor due to non-payment by the provision” of the Red Book, all claims for additional payment under
Engineer. the Red Book require 28 days notice from the date of the event giving
These clauses stipulate a range of notice procedures. There are some slight rise to the claim. This would appear to extend the shorter requirement
differences between them. In any case, Clause 44.2 and/or Clause 53.1 of 14 days under Clause 52.2. We would suggest, however, that the
apply to all of them. Contractor should comply with the 14 days notice period.
The Civil Code the Contractor, Engineer or Employer. Contractual provisions
If the Engineer feels inclined to reject an otherwise meritorious which appear to have drastic consequences as written in the
claim solely by reason of non-compliance with strict Red Book (or in any other standard form contract which may
technicalities of the notification procedures it is important for be used in the UAE) may, in fact, have a modified or different
him to consider the provisions of the Civil Code, which might effect when read together with applicable provisions of the
have a bearing on the issue. Civil Code.

For instance, the Civil Code makes clear that neither party
to a contract should act in bad faith. Article 246 states that
contracts must be performed in a manner consistent with
the requirements of good faith. This could apply, for example,
The UAE’s Accession to the
where a Contractor points to information given in agreed
minutes of a meeting or a periodic report as written notice
New York Convention: worth
of an intention to claim, as required by the Red Book. If, the wait?
as is sometimes the case, a question arises as to whether
information in a formal minute or a written report is strictly The UAE has ratified the Convention on the Recognition and
“written notice”, consideration of good and bad faith may, as a Enforcement of Foreign Arbitral Awards, know as the New York
matter of UAE law, be relevant. The Contractor may argue, in Convention (the Convention). The date of the UAE’s accession is
such a case, that the Employer and the Engineer have actually likely to be soon. The UAE will then join the 137 states which have
been notified of the existence of the claim, in a written form, already acceded.
within the stipulated time period and, as such, the purpose of
the notification provision has been fulfilled and that it would be Until now the UAE has had only limited arrangements for mutual
an act of bad faith not to accept this. recognition and enforcement of foreign arbitral awards: various
treaties with states in the Gulf, the Middle East and North Africa
The Civil Code also states that neither party may exercise its as well as France and India. Those treaties resulted in easier
rights under a contract in a manner which is oppressive or enforcement in the UAE of awards made in those states (and vice
abusive to the other. Article 106 says that the exercise of a versa), but enforcement of awards from non-treaty states was
right shall be unlawful if, among other things, the interests subject to scrutiny by the UAE courts under local laws. This not
desired are disproportionate to the harm that will be suffered only involved burdensome procedural requirements but also an
by the other party. Thus, if an otherwise valid and meritorious often lengthy court process. That said, even the enforcement of
claim is disallowed solely by reason of purely technical breach purely domestic awards in the UAE is not without its difficulties.
of a notice provision, this may well be unlawful, especially if the
likely financial harm to the Contractor is disproportionate to With the UAE’s accession to the Convention, enforcing foreign
the interests in upholding the Employer’s contractual right to awards from Convention states is likely to become easier. Subject
receive timely notice. to any reservations the UAE makes when it accedes, the UAE
courts will then be required to recognise awards made in other
Furthermore, Articles 318 and 319 of the Civil Code provide Convention states as binding and to enforce them under the
that unjust enrichment is unlawful. If, for example, the Engineer conditions outlined in the Convention. The grounds for objection
rejects a claim for additional payment for varied work purely are limited: mainly, lack of arbitral jurisdiction or procedural
on the grounds that the time limit for notice has not been met, unfairness during the proceedings.
it could, as a matter of UAE law, be the case that the Employer
has been unjustly enriched by benefiting from additional work But what practical impact will this have for the UAE construction
while seeking to avoid payment by relying on a procedural industry? Probably not much. It remains the case that only a
technicality. Consequently, the claim may succeed in the eyes very small number of UAE construction disputes reach a formal
of UAE law even if the notice procedures were not complied dispute resolution process. In such cases the UAE construction
with. industry still tends to prefer a domestic arbitration process.
Dubai government bodies are in any case bound to do so by the
Law of Contracts of Government Departments in Dubai 1997.
Comment It is a very rare contractor who, when tendering for a project in
This article highlights only a few examples of how the Red the UAE, will even consider negotiating different terms for the
Book, when read in the context of the applicable provisions dispute resolution clause (eg. foreign venue, international rules
of the Civil Code, might not have the meaning, or at least the etc.). The UAE construction industry therefore remains far more
effect, suggested by the express words used. There are, of likely to generate domestic UAE awards than foreign ones. The
course, numerous other provisions of the Civil Code which are Convention is, of course, no help in relation to domestic awards: it
likely to be relevant and must be considered when advising applies only to “foreign” awards.
So, does the UAE’s accession to the Convention offer any real For further information, please contact:
benefits to the UAE construction industry at all? The answer,
perversely, may be yes, but only if the UAE construction David Courtney Hatcher
industry is prepared to consider opting for foreign arbitration T +971 4 3310220
venues. These would then generate ‘foreign’ awards. The F +971 4 3310220
obvious benefit is that the Convention would then apply. david.courtney-hatcher@dentonwildesapte.com
Enforcing a foreign award in the UAE under the Convention
may be considerably easier and quicker than enforcing a Michael Kerr
domestic award. Moreover, a party with the benefit of a T +971 4 3310220
UAE award may find it easier to take that award to another F +971 4 3310220
Convention state than to face the hurdles and uncertainties michael.kerr@dentonwildesapte.com
associated with enforcement in the UAE.
Alastair Hirst
These are peculiar and, presumably, unintended T +971 2 6266180
consequences. F +971 2 6266175
alastair.hirst@dentonwildesapte.com
Perhaps the imbalance between these legal regimes will be
corrected in time, leading to a more uniform approach towards
ratification of ‘domestic’ and ‘foreign’ awards.

At the time of writing, the full text of the instrument of


accession has yet to be released. This may confirm, among
other things, whether awards made before ratification or
accession will be enforceable under the Convention and
whether the UAE has made any reservations regarding
enforcement of awards. These may include only enforcing
awards which are made in other Convention states and/or
which relate to disputes which are “commercial” in nature.
The ratifying decree does not contain any reference to
reservations. We hope to be able to address these questions in
our next edition.

©2006 Denton Wilde Sapte, unless otherwise indicated. All information correct as at time of printing. Consistent with our policy when giving advice on a non-
specific basis, we cannot assume legal responsibility for the accuracy of any particular statement. In the case of a specific problem we recommend that you seek
professional advice.

With effect from 1 November 2006 any references to “Denton Wilde Sapte” should be taken as referring to “Denton Wilde Sapte LLP”.
The term partner is used to refer to a member of Denton Wilde Sapte LLP or an employee or consultant with equivalent standing and qualifications.

Denton Wilde Sapte & Co


Denton Wilde Sapte & Co Legal Consultants
26th Floor  Suite 1204 
API World Tower  Al Ghaith Tower 
Sheikh Zayed Road   Hamdan Street   info@dentonwildesapte.com
PO Box 1756 Dubai PO Box 47656 Abu Dhabi www.dentonwildesapte.com
United Arab Emirates United Arab Emirates
PU18490 09/06

T +971 4 331 0220 T +971 2 6266180


F +971 4 331 0201 F +971 2 6266175
dubai@dentonwildesapte.com abudhabi@dentonwildesapte.com
www.dentonwildesapte.com www.dentonwildesapte.com

You might also like