7 Site / Groundwater Survey to 34 wks Thu 21/08/14 Wed 1 GAWI GAWI GAWI
confirm level (by client) 29/04/15
8 Site Layout 4 days Thu 30/04/15 Tue 05/05/15 7
9 Hazardous Area Zoning - Preliminary 4 days Wed 06/05/15 Mon 8 ADB ADI ADB
11/05/15
10 Stage / Gate Review Preliminary 3 days Tue 12/05/15 Thu 14/05/15 5,6,9 NAC ADI NAC
Design
11 Single Line Diagrams 3 days Fri 15/05/15 Tue 19/05/15 10 Electrical
ADITeam Electrical Team
27 External liquid pipework design / 2 wks Wed 01/07/15 Tue 14/07/15 26 ADB,CAD
ADI ADB,CAD Team
layout Team
28 Biogas pipework design / layout 2 wks Wed 08/07/15 Mon 27SS+1 wk ADB,CAD
ADI ADB,CAD Team
27/07/15 Team
29 Review Mechanical Design 2 days Tue 28/07/15 Wed 29/07/1522,28 NAC ADI NAC
38 Client Procures Electrical Contractor 10 wks Mon 08/06/15 Thu 20/08/15 17 GAWI GAWI GAWI
43 Pumps & Mixers & valves 14 wks Mon 07/09/15 Fri 11/12/15
44 Cooling Tower, FRP & water tank 12.6 wks Mon 21/09/15 Wed 16/12/15
45 Scrubber coatings 37 days Mon 02/11/15 Tue 22/12/15
46 Chiller unit 8 wks Mon 07/12/15 Fri 29/01/16
47 Instruments 4.2 wks Mon 26/10/15 Mon 23/11/15
48 Biomedia 8.2 wks Mon 02/11/15 Mon 28/12/15
49 Site delivery allowance in Indonesia 26 days Mon 25/01/16 Mon 29/02/1644,41
50 Construction 185 days Mon 30/11/15 Fri 12/08/16
51 Civil Construction 374 days Mon 30/11/15 Thu 04/05/17
52 CGR and Settlement Ponds 374 days Mon 30/11/15 Thu 04/05/17
53 Dewatering existing ponds and 1 wk Mon 30/11/15 Fri 04/12/15 Civil GAWI Civil
flow diversion (by client)
54 Lagoon excavation (by client) 12 wks Mon 07/12/15 Fri 26/02/16 53 Civil GAWI Civil
55 Install pipework through berms (by 2 wks Mon 29/02/16 Fri 11/03/16 54 Civil GAWI Civil
client)
Project: 500270011 Programme Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 15/03/17 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 1
PT. GAWI MAKMUR KALIMANTAN
POME to Energy Plant in Jorong
61 Install internal pipework - Settling 1 wk Mon 23/05/16 Fri 27/05/16 60 Ecody ADI Ecody
pond
62 CGR filling 52 days Mon 05/12/16 Tue 14/02/17 59
63 Leak test 1 day Wed 15/02/17 Wed 15/02/1762
64 Leak repairs 21 days Thu 16/02/17 Thu 16/03/17 63
65 Re-fill digester (by client) 5 days Fri 17/03/17 Thu 23/03/17 64 Civil GAWI Civil
66 Install CGR cover 6 wks Fri 24/03/17 Thu 04/05/17 65 Ecody ADI Ecody
67 Construct Mixing / RANS Sumps (by 80 days Mon 29/02/16 Fri 17/06/16 54 Civil GAWI Civil
client)
68 Construct Scrubber Structure (by 80 days Mon 29/02/16 Fri 17/06/16 54 Civil GAWI Civil
client)
69 Scrubber structural and other items 8 wks Mon 20/06/16 Fri 12/08/16 68
70 Concrete curing 24 wks Mon 15/08/16 Fri 27/01/17 69
71 Coat scrubber internals 5 days Mon 30/01/17 Fri 03/02/17 70
72 Construct MCC Control Building and 14 wks Mon 29/02/16 Fri 03/06/16 54 Civil GAWI Civil
Plinths (by client)
73 Mechanical Construction 345 days Mon 30/11/15 Fri 24/03/17
74 Install feed distribution manifold 6 wks Mon 30/11/15 Fri 08/01/16 Ecody ADI Ecody
75 Install liquid pipework external to 8 wks Mon 11/01/16 Fri 04/03/16 74 Mechanical
GAWI Mechanical
ponds including valves and supports
(by client)
76 Install biogas pipework including 8 wks Mon 07/03/16 Fri 29/04/16 75 Mechanical
GAWI Mechanical
valves and support (by client)
77 Equipment Installation 160 days Mon 15/08/16 Fri 24/03/17
78 Install Cooling Tower (by client) 12 wks Mon 15/08/16 Fri 04/11/16 72,44,49,69 Mechanical
GAWI Mechanical
79 Install Biogas Dryer (by client) 4 wks Mon 07/11/16 Fri 02/12/16 78 Mechanical
GAWI Mechanical
80 Install Flare (by client) 4 wks Mon 05/12/16 Fri 30/12/16 79 Mechanical
GAWI Mechanical
84 Install Biogas Scrubber 1 wk Mon 13/03/17 Fri 17/03/17 49,71,83 Ecody ADI Ecody
Components
85 Install Instruments (by client) 5 days Mon 20/03/17 Fri 24/03/17 84 Mechanical
GAWI Mechanical
89 Establish Temporary Power Supply at 5 days Fri 05/08/16 Thu 11/08/16 88FF Electrical
GAWI Electrical
Site (if required) (by client)
90 Install MCC (by client) 6 wks Fri 12/08/16 Thu 22/09/16 88 Electrical
GAWI Electrical
91 Install cable trays etc. (by client) 8 wks Fri 23/09/16 Thu 17/11/16 90 Electrical
GAWI Electrical
92 Field cabling (by client) 10 wks Fri 18/11/16 Thu 26/01/17 91 Electrical
GAWI Electrical
93 Terminations (by client) 2 wks Mon 27/03/17 Fri 07/04/17 92,82,83,85 Electrical
GAWI Electrical
94 Install and terminate mains (by 1 wk Mon 10/04/17 Fri 14/04/17 93 Electrical
GAWI Electrical
client)
95 Liven MCC (by client) 1 day Mon 17/04/17 Mon 17/04/1794 Electrical
GAWI Electrical
Project: 500270011 Programme Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 15/03/17 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 2