GAWI MAKMUR KALIMANTAN


POME to Energy Plant in Jorong

ID Task Name Duration Start Finish Predecessors Resource


Resource
Names Group Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 Contract Award 0 days Thu 21/08/14 Thu 21/08/14 21/08

2 Design 294 days Thu 21/08/14 Mon 26/10/15


3 Preliminary design 199 days Thu 21/08/14 Tue 09/06/15
4 PFD 2 days Thu 21/08/14 Fri 22/08/14 1 ADB ADI ADB

5 P&IDs 1 wk Mon 25/08/14 Fri 29/08/14 4 ADB ADI ADB

6 PDM 1 wk Mon 25/08/14 Fri 29/08/14 4 ADB ADI ADB

7 Site / Groundwater Survey to 34 wks Thu 21/08/14 Wed 1 GAWI GAWI GAWI
confirm level (by client) 29/04/15
8 Site Layout 4 days Thu 30/04/15 Tue 05/05/15 7
9 Hazardous Area Zoning - Preliminary 4 days Wed 06/05/15 Mon 8 ADB ADI ADB
11/05/15
10 Stage / Gate Review Preliminary 3 days Tue 12/05/15 Thu 14/05/15 5,6,9 NAC ADI NAC
Design
11 Single Line Diagrams 3 days Fri 15/05/15 Tue 19/05/15 10 Electrical
ADITeam Electrical Team

12 Changes following HAZOP - 2 wks Wed 20/05/15 Tue 02/06/15 11


Electrical, Layout, P&IDs, PDM
13 Client Review / Approval 1 wk Wed 03/06/15 Tue 09/06/15 12 GAWI GAWI GAWI

14 ADI design 117 days Wed 06/05/15 Wed 21/10/158


15 Hazardous Area Zoning - Final 4 days Wed 06/05/15 Mon 11/05/15 ADB ADI ADB

16 Prepare Equipment Specifications 4 days Tue 12/05/15 Fri 15/05/15 15


17 Equipment RFQs and Selection 3 wks Mon 18/05/15 Fri 05/06/15 16
18 ADI Civil Requirements Package (to 7 days Mon 08/06/15 Tue 16/06/15
client)
19 Ponds 1 day Mon 08/06/15 Mon 08/06/1517
20 Tanks 1 day Tue 09/06/15 Tue 09/06/15 19
21 Control Building 1 day Wed 10/06/15 Wed 10/06/1520
22 Plinths 1 day Thu 11/06/15 Thu 11/06/15 21
23 Review ADI Civil Requirements 3 days Fri 12/06/15 Tue 16/06/15 22 NAC ADI NAC
Package
24 Mechanical Design 27 days Wed 17/06/15 Wed 29/07/15
25 Pond internals design 2 wks Wed 17/06/15 Tue 30/06/15 23 ADB,CAD
ADITeam ADB,CAD Team

26 Cover design 2 wks Wed 17/06/15 Tue 30/06/15 23 ADB,CAD


ADITeam ADB,CAD Team

27 External liquid pipework design / 2 wks Wed 01/07/15 Tue 14/07/15 26 ADB,CAD
ADI ADB,CAD Team
layout Team
28 Biogas pipework design / layout 2 wks Wed 08/07/15 Mon 27SS+1 wk ADB,CAD
ADI ADB,CAD Team
27/07/15 Team
29 Review Mechanical Design 2 days Tue 28/07/15 Wed 29/07/1522,28 NAC ADI NAC

30 ADI Electrical Requirements Package 107 days Wed 20/05/15 Wed


(to client) 21/10/15
31 Prepare ADI Electrical 8 wks Wed 20/05/15 Tue 14/07/15 11 Electrical
ADI Electrical Team
Requirements Package Team
32 Review Electrical Requirements 1 wk Wed 15/07/15 Mon 31 SDB ADB SDB
Package 27/07/15
33 HAZOP preparation 1 wk Thu 30/07/15 Wed 05/08/1532,29
34 Completion Detailed Design 1 day Thu 06/08/15 Thu 06/08/15 33
35 HAZOP on-site 2 days Tue 20/10/15 Wed 21/10/1534
36 Procurement 187 days Mon 08/06/15 Mon 29/02/16
37 Client Procures Mechanical Contractor 10 wks Mon 08/06/15 Thu 20/08/15 17 GAWI GAWI GAWI

38 Client Procures Electrical Contractor 10 wks Mon 08/06/15 Thu 20/08/15 17 GAWI GAWI GAWI

39 ADI Commence procurement 1 day Mon 17/08/15 Mon 17/08/15


40 Flare / Biogas package 18 wks Tue 18/08/15 Mon 21/12/1539
41 Flare / biogas shipping 24 days Tue 22/12/15 Fri 22/01/16 40
42 ADIs Cover/ Internals 5 wks Tue 01/12/15 Mon 04/01/16 Ecody Ecody

43 Pumps & Mixers & valves 14 wks Mon 07/09/15 Fri 11/12/15
44 Cooling Tower, FRP & water tank 12.6 wks Mon 21/09/15 Wed 16/12/15
45 Scrubber coatings 37 days Mon 02/11/15 Tue 22/12/15
46 Chiller unit 8 wks Mon 07/12/15 Fri 29/01/16
47 Instruments 4.2 wks Mon 26/10/15 Mon 23/11/15
48 Biomedia 8.2 wks Mon 02/11/15 Mon 28/12/15
49 Site delivery allowance in Indonesia 26 days Mon 25/01/16 Mon 29/02/1644,41
50 Construction 185 days Mon 30/11/15 Fri 12/08/16
51 Civil Construction 374 days Mon 30/11/15 Thu 04/05/17
52 CGR and Settlement Ponds 374 days Mon 30/11/15 Thu 04/05/17
53 Dewatering existing ponds and 1 wk Mon 30/11/15 Fri 04/12/15 Civil GAWI Civil
flow diversion (by client)
54 Lagoon excavation (by client) 12 wks Mon 07/12/15 Fri 26/02/16 53 Civil GAWI Civil

55 Install pipework through berms (by 2 wks Mon 29/02/16 Fri 11/03/16 54 Civil GAWI Civil
client)

Project: 500270011 Programme Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 15/03/17 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 1
PT. GAWI MAKMUR KALIMANTAN
POME to Energy Plant in Jorong

ID Task Name Duration Start Finish Predecessors Resource


Resource
Names Group Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
56 Clearing CGR muck 11 wks Thu 19/05/16 Wed 03/08/16
57 Re-install pipework through berms 1 wk Thu 04/08/16 Wed 10/08/1656
58 Install liner - CGR 4 wks Thu 11/08/16 Wed 07/09/1657 Ecody ADI Ecody

59 Internal pipework 12.4 wks Thu 08/09/16 Fri 02/12/16 58


60 Install liner - Settling pond 2 wks Mon 29/02/16 Fri 11/03/16 54 Ecody ADI Ecody

61 Install internal pipework - Settling 1 wk Mon 23/05/16 Fri 27/05/16 60 Ecody ADI Ecody
pond
62 CGR filling 52 days Mon 05/12/16 Tue 14/02/17 59
63 Leak test 1 day Wed 15/02/17 Wed 15/02/1762
64 Leak repairs 21 days Thu 16/02/17 Thu 16/03/17 63
65 Re-fill digester (by client) 5 days Fri 17/03/17 Thu 23/03/17 64 Civil GAWI Civil

66 Install CGR cover 6 wks Fri 24/03/17 Thu 04/05/17 65 Ecody ADI Ecody

67 Construct Mixing / RANS Sumps (by 80 days Mon 29/02/16 Fri 17/06/16 54 Civil GAWI Civil
client)
68 Construct Scrubber Structure (by 80 days Mon 29/02/16 Fri 17/06/16 54 Civil GAWI Civil
client)
69 Scrubber structural and other items 8 wks Mon 20/06/16 Fri 12/08/16 68
70 Concrete curing 24 wks Mon 15/08/16 Fri 27/01/17 69
71 Coat scrubber internals 5 days Mon 30/01/17 Fri 03/02/17 70
72 Construct MCC Control Building and 14 wks Mon 29/02/16 Fri 03/06/16 54 Civil GAWI Civil
Plinths (by client)
73 Mechanical Construction 345 days Mon 30/11/15 Fri 24/03/17
74 Install feed distribution manifold 6 wks Mon 30/11/15 Fri 08/01/16 Ecody ADI Ecody

75 Install liquid pipework external to 8 wks Mon 11/01/16 Fri 04/03/16 74 Mechanical
GAWI Mechanical
ponds including valves and supports
(by client)

76 Install biogas pipework including 8 wks Mon 07/03/16 Fri 29/04/16 75 Mechanical
GAWI Mechanical
valves and support (by client)
77 Equipment Installation 160 days Mon 15/08/16 Fri 24/03/17
78 Install Cooling Tower (by client) 12 wks Mon 15/08/16 Fri 04/11/16 72,44,49,69 Mechanical
GAWI Mechanical

79 Install Biogas Dryer (by client) 4 wks Mon 07/11/16 Fri 02/12/16 78 Mechanical
GAWI Mechanical

80 Install Flare (by client) 4 wks Mon 05/12/16 Fri 30/12/16 79 Mechanical
GAWI Mechanical

81 Other tasks 8 wks Mon 02/01/17 Fri 24/02/17 80


82 Install mixers (by client) 1 wk Mon 27/02/17 Fri 03/03/17 67,81 Mechanical
GAWI Mechanical

83 Install pumps (by client) 1 wk Mon 06/03/17 Fri 10/03/17 82 Mechanical


GAWI Mechanical

84 Install Biogas Scrubber 1 wk Mon 13/03/17 Fri 17/03/17 49,71,83 Ecody ADI Ecody
Components
85 Install Instruments (by client) 5 days Mon 20/03/17 Fri 24/03/17 84 Mechanical
GAWI Mechanical

86 Electrical Construction 337 days Fri 01/01/16 Mon 17/04/17


87 Contractor Detailed Electrical Design 4 wks Fri 01/01/16 Thu 28/01/16 30,38 Electrical
GAWI Electrical
(by client)
88 MCC (by client) 28 wks Fri 29/01/16 Thu 11/08/16 87 Electrical
GAWI Electrical

89 Establish Temporary Power Supply at 5 days Fri 05/08/16 Thu 11/08/16 88FF Electrical
GAWI Electrical
Site (if required) (by client)

90 Install MCC (by client) 6 wks Fri 12/08/16 Thu 22/09/16 88 Electrical
GAWI Electrical

91 Install cable trays etc. (by client) 8 wks Fri 23/09/16 Thu 17/11/16 90 Electrical
GAWI Electrical

92 Field cabling (by client) 10 wks Fri 18/11/16 Thu 26/01/17 91 Electrical
GAWI Electrical

93 Terminations (by client) 2 wks Mon 27/03/17 Fri 07/04/17 92,82,83,85 Electrical
GAWI Electrical

94 Install and terminate mains (by 1 wk Mon 10/04/17 Fri 14/04/17 93 Electrical
GAWI Electrical
client)
95 Liven MCC (by client) 1 day Mon 17/04/17 Mon 17/04/1794 Electrical
GAWI Electrical

96 Pre-Commissioning 4 wks Thu 18/08/16 Wed 14/09/16


97 Electrical commissioning (by client) 1 wk Tue 18/04/17 Mon 24/04/1773,86 Electrical
GAWI Electrical

98 Hydro-mechanical commissioning (by 1 wk Tue 25/04/17 Mon 97 Mechanical


GAWI Mechanical
client) 01/05/17
99 ADI Review of pre-commissioning 2 days Tue 02/05/17 Wed 03/05/1798 Commissioning
ADI Team Commissioning Team

100 Biological Commissioning 82 days Fri 05/05/17 Mon 28/08/17


101 Seeding 3 wks Fri 05/05/17 Thu 25/05/17 66,83
102 Wet commisioning 2 wks Fri 26/05/17 Thu 08/06/17 101
103 ADI process commisioning 5 days Fri 26/05/17 Thu 01/06/17 101
104 Process Commissioning/start-up 10 wks Fri 09/06/17 Thu 17/08/17 102 Commissioning
ADI Team Commissioning Team

105 Biogas commisioning 1 wk Fri 11/08/17 Thu 17/08/17 104FF


106 Controls Commissioning 1 wk Fri 18/08/17 Thu 24/08/17 105 Commissioning
ADI Team Commissioning Team

107 Training 2 days Fri 25/08/17 Mon 28/08/17106


108 Plant Operational 0 days Mon 28/08/17 Mon 28/08/17107,104 28/08

Project: 500270011 Programme Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Wed 15/03/17 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress