Professional Documents
Culture Documents
SEM4-ITPM/Case Study
4. Identify key factors which could have contributed to the success of this project
• Technology was successfully tied up to meet the business objectivel the three spheres
of the project (business, organization & technology) where handled effectively
• Experienced (highly qualified) project manager
• A team with the necessary - diverse (complementary) skills & experience
• Use of the standard software tools &:::- in j sq, f
• Proper source selection for equipments & software
• Proper application of project management skills across all key project areas and
processes ego good scope control, cost control
• Ability to interface the system with the international partners' systems
lecturer: Mr.Ragukumar 1
[IDM]
__C_
~"'T--.,
V"-e
,
. ~; ,
-I
••
t,
SEM4·ITPM/Case Study
. 5. List 5 negative risks in this project and suitable strategies to handle those risks
\' ,t, ~ \
'\
,tor'~'
)'"
..J' :,' . '..~
• Requirements changes
r~ \;..
- user involvement, prototyping, incremental development, good change control
Procedures
6. Project communication is key to the success of a large scale project like this. List down
the project communication management processes?
~ 1. Communications
planning
Determining the information and communications needs of
the stakeholders.
2. Infonnation distribution Making needed information available to project
stakeholders in a timely manner.
3. Perfonnance reporting Collecting and disseminating performance information,
including _tus reports, progress measurement, and
. f u.<t:.u. y e.-.;> forecasting. ~(\ive:n d.Ct-t~ 5~\:U.5 ~ljjveh pe ToJ.
14. Managing stakeholders Managing communications to satisfy the needs and
expectations of project stakeholders and to resolve issues.
Lecturer: Mr.Ragukumar 2
~
.una...~c ... e· . SEM4-ITPM/Case Study
.~0
:t;
~?
'1
()..~".)
y
4. Forcin
. Directl face a conflict usin a roblem-solvina approach.
Use a ive-and-take a roach
De-emphasize areas of difference and emphasize areas of
• Brainstorming
• The Delphi Technique
• Interviewing
• SWOT analysis
Contingency plans are predefined actions that the project team will take if an identified
risk event occurs.
Fallback plans are developed for risks that have a high impact on meeting project
objectives, and are put into effect if attempts to reduce the risk are not effective.
12. State what is resource leveling and list the benefits of dOing it
Lecturer: Mr.Ragukumar 3
~.:
-'-" SEM4-ITPMlCase Stud)
13. State what are the different options for acquiring the needed project staff
• Head hunting
• Recruitment
• Internal promotion
• Taking staff by reference
• Campus reach programmesl apprentice
• Contract hire (consultancy)
~6-~ 're\~ A·
Fixed price or lump sum contracts: Involve a fixed total price for a well-defined
product or service.
~C2-V\ce. \ S Cost reimbursable contracts: Involve payment to the seller for direct and indirect
\:> J. L3' '(> c;) • costs.
• Time and material contracts: Hybrid of both fixed price and cost reimbursable
.. contracts, often used by consultants.
Unit price contracts: Require the buyer to pay the seller a predetermined amount
per unit of service.
15. Mention 2 types of documents used to solicit seller response in project procu'rement
Requests for Quotes: Used to solicit quotes or bids from prospective suppliers.
sellers providing pricing for standard items that have been clearly defined by the buyer.
17. What steps you would take in procuring the necessary equipment such as the Hand
held computers IGPS devices?
• Determine how many units what specification and when to be supplied etc
• Describe the requirement ~ identify potential suppliers
• Request seller response from identified suppliers-send a request for quotation
(RFQ)
• Obtain and evaluate quotes according to the evaluation criteria
• Perform technical evaluation with sam pie devices
• Have a final negotiation and make a contract for supply (purchase order for the
units, warranty & maintenance)
• Receive units, perform acceptance testing
• Issue payments & close contract
Lecturer: Mr.Ragukumar 4
JP~,- o· SEM4-ITPM/Case Study
18. What are the characteristics that make up a good project manager?
19. How a project of a large scope like eCourier could be completed successfully even
though some of the members did not possess a complete set of skills?
Project was carried out by the team, and what is important is'the skill set of the team
rather than each individual possessing a complete set of skills.
Success of a project needs a team with an able Project Manager & skillful developers,
(when other conditions are favorable) and it is evident these requirements were met in
the eCourier Project.
It is evident
• eCourier had head hunted and recruited top employees with skills and
experience.
• The staff responsible for project management, business risk management and
systems development were highly qualified.
• Others were with lower and varying skills
Here the individual member skills were not complete but complementary. Thus there
was a team with a blend of skills & experience and the way those staff were acquired
had made it the right blend of skills set.
Further team must have gain more strength through Group Think and synergy
• Market research
• Project plan _ coveriYlC) 0.-1\, o.Yr2c:.n ot -lhe p:rojec. t,
• Technical issues
• Change management
• Stakeholder management
• Risk management
• Communications management
+C,-(;..-t':JrB
*"
lecturer: Mr.Ragukumar 5