Assignment 2

Construct an activity on arrow network based on the activity described below. Show all your
work, label activities in the network by their activity letters and node numbers. Remove any
redundant dependencies and label dummy activities.

 Activities H, R2, T1 start the project


 Activity T2 can start when activities H,E1 and S are completed
 Activity E1 also depends on activity R2
 Activity X follow, activity H and precedes activity L
 Activity E is preceded by activities T2,P1
 The predecessors to the activity G are activities L
 The successor to activity T1 are activities E1, S,W and D2
 Activity P1 cannot begin until activity W is finished
 Activity P2 and F follow activities W and D2 and precede activities E and R1
 Activity O2 depends on T2 and P1, and precedes activity L.

NO. Activity name Precedence Duration


1 T1 - 3
2 R2 - 4
3 H - 2
4 D2 T1 6
5 W T1 9
6 S T1 10
7 E1 T1,R2 8
8 X H 6
9 F D2,W 5
10 P2 D2,W 7
11 P1 W 6
12 T2 S,E1,H 3
13 R1 F,P2 7
14 O2 P1,T2 9
15 E F,P2,P1,T2 10
16 L O2,X 11
17 G L 5
Forward path

Calculations
Start of the project (ES) Early finish activity T1 (EF)= Early finish activityR2
 0 ES+d EF=ES+d
 0+3=3  0+4 = 4
 3+0 = 3
Early finish activity H Early finish activity D2 Early finish activity W
EF=ES+d EF=ES+d EF=ES+d
 0+2 = 2  3+6 =9  3+9 =12
 12+0 = 12
Early finish activity S & E1 Early finish activityP1 &T2 Early finish activity O2 & X
EF=ES+d EF=ES+d EF=ES+d
 3+10 = 13  12+6 = 18  9+ 18 = 27
 8+4= 12  13+3 = 16  2+ 6 = 8
 2+0 = 2
Early finish activity L Early finish activity F Early finish activity P2
EF=ES+d EF=ES+d EF=ES+d
 27 + 11 = 38  5+ 12 = 17  17+ 0= 17
 12+7 = 19
Early finish activity Dummy Early finish activity R1, G, E
5 and 6  19 + 10 = 29
EF=ES+d  38 + 5 = 43
 19 + 0= 19  7 + 19 = 26
 18 + 0 = 18
Backward path

Project late finish (LF) Late start activity G Late start activity E
 43 (LS)= LF - d (LS)= LF - d
 43-5=38  43 -10 = 33
Late start activity R1 Late start activity F& P2 Late start activity L
(LS)= LF - d (LS)= LF - d (LS)= LF - d
 43 - 7 = 36  33-5 = 28  38- 11 = 27
 33 - 0 = 33  33 – 7 = 26
Late start activity X , Late start activity O2 Late start activity P1
(LS)= LF - d (LS)= LF - d (LS)= LF - d
 27- 6 =21  27 - 9= 18  18- 6 = 12
 15- 0 = 15  33 - 0 = 33  26- 0 = 26
Late start activity T2 Late start activity E1 Late start activity
(LS)= LF - d (LS)= LF - d D2,S,W,dummy 2
 18 – 3 = 15  15 – 8 = 7  26- 6 = 20
 12- 9= 3
 15 - 10 = 5
 7-0= 7
Late start activity T1,R2,H
(LS)= LF - d
 3-3 = 0
 7- 4= 3
 15 – 2= 13
Float Calculations