You are on page 1of 3

FIDIC Contracts Update

Edward Corbett
Corbett & Co International Construction Lawyers Ltd, London

F aithful followers of FIDIC (the


International Federation of Consulting
Engineers) gathered in London in December
• A brown-field version of the Gold Book
(Design-Build Operate);
• An update of the Dredging and Reclamation
2009 for their Users’ Conference. (Blue Book);
Below are some of the points of interest • An update of the Short Form;
that emerged. • A subconsultancy agreement;
FIDIC has cleared out its Contracts • A consultants’ JV agreement;
Committee. The chairman is now Philip • A new version of the Pink MDB form,
Jenkinson (UK) of Atkins, Christophe currently being discussed with the multi-
Theune (Germany) and Zoltan Zahoni lateral development banks; and
(Hungary). ICP’s Chris Seppälä continues in • A first edition of the subcontract for use with
his role as legal adviser. the Red Book, the test edition of which was
The Update Task Group has started work on launched at the conference (see below).
revising the 1999 Red, Yellow and Silver contract
books, starting with the Yellow. The task group
Sales of FIDIC contracts
comprises Svend Poulsen (Atkins, Denmark),
Aisha Nadar (Queen Mary University, London) The sales, an unreliable indicator of market
and Zoltan Zahoni (Hungary). share of the various 1999 forms, show that the
The experience of the old guard of Chris Red Book has regained top spot after many
Wade, Michael Mortimer-Hawkins, Nael years of Yellow domination. The decline in
Bunni and Axel Jaegar will not be wasted as recent Yellow sales has been matched by an
they will remain on tap as special advisers. increase in demand for the Silver. If present
As well as updating the 1999 suite, FIDIC is trends continue, Silver will soon be the more
also planning: popular contractor-design contract.

Sales R

1999 2009
A show of hands of the 140 people at the conference demonstrated that very similar
numbers of people were currently working with Red and Yellow contracts, with far fewer
involved with Silver Book projects.

Construction Law International Volume 5 Issue 1 March 2010 23


Fidic contracts update

Update Task Group which led to the harmonised edition was


fading so that each bank now required their
The Group is starting with the Yellow Book
own definitions and provisions for corruption,
because the recent work done on the Gold
audit and arbitration.
Book 2008 applies most naturally to the
Frank Kehlenbach of the EIC (European
Yellow Book. Many of the changes in the Gold
International Contractors) acknowledged
Book, such as ‘Exceptional Risks’ in place of
some aspects of the current 2006 version of
force majeure and contract data in place of the
the MDB as being fairer or otherwise
Appendix to Tender, will be retained. The
improved. He highlighted:
issues that the Task Group is concentrating
• the now mutual confidentiality obligations;
on first are as follows:
• the now clear obligation of the Employer
• whether to retain the Engineer or to stick to
to provide the building permit and special
the Employer’s Representative used in the
rights of way;
Gold Book. It seems likely that the Engineer
• Employer’s claims are subject to 28 day limit
will be retained;
– although no sanction is attached;
• the definition of ‘Works’ is to include design
• the Contractor’s right to reject a nominated
more clearly and the design requirements
subcontractor that will not accept pay-when-
are to be set out more extensively;
paid provisions;
• programming obligations are to be dealt
• conditions that have to be fulfilled by the
with more thoroughly. This is viewed as
Employer before notice to commence
an area where dispute avoidance can be
can be given, including the obtaining of
achieved by better programming provisions;
permits, the granting of access, advance
• standing or ad hoc Dispute Ajudication
payment and evidence of ability to pay.
Board (DAB): the views at the
(Your reporter cannot but comment that
conference were over whelmingly for
it is strange to allow the Contractor to
standing DABs. The Task Group seem likely to
control the commencement date: until it
retain the Gold Book idea of giving the DAB
provides the advance payment guarantee,
a discretion to order the provision of a bond
the advance payment cannot be made so
in exchange for payment of the Decision;
notice to commence cannot be given); and
• ‘may’ and ‘shall’ may (or shall?) be defined
• the performance bond no longer has to
to resolve uncertainty in some parts of the
be from an institution approved by the
world as to their meaning;
Employer provided that it is ‘reputable’.
• the Gold Book definition of ‘Dispute’ is
Surely a source of much future debate.
being reconsidered, presumably because
it assumes a claim, but disputes can arise EIC are less happy with the ability of the
without a claim; Employer unilaterally to replace the Engineer
• the new Yellow Book will make it clearer and with the removal from Clause 4.2 of the
that notices and other contractual list of grounds on which an Employer may call
communications will need to specify the the performance bond. Frank Kehlenbach
clause under which they are given; also noted difficulties with the dispute
• operation and maintenance manuals will resolution clause that distinguished between
be provided for with greater precision; local and foreign contractors, given that many
• extension of time and advance warning foreign contractors are obliged or advised to
provisions will follow the Gold Book; set up local companies.
• the detail of the escalation provision will be Cyril Chern highlighted some common
relegated to a schedule; and and sometimes underhand amendments that
• Clause 20.1 time barring will be subject he has seen in MDB contracts. Some
to the DAB’s discretion to admit late examples were:
notification where just to do so. • Clause 2.4 amended so that the Contractor
has no right to evidence of ability to pay
after the contract is signed;
MDB conditions • in Clause 3.1, the word ‘no’ being removed
Chris Wade said that the majority of the so that a key sentence reads: ‘The Engineer
proposed amendments were minor. However, shall have authority to change the contract’;
he regretted that the authority of the Engineer • Clause 4.10 being amended so that the
was reduced by the Clause 3.1 approval regime Contractor has the obligation to provide
required by the banks. It was also a pity, in all information regarding the site, ground
his view, that the consensus among the banks conditions etc; and

24 Construction Law International Volume 5 Issue 1 March 2010


• in Clause 20.4, the DAB being given 84 ‘foreclusions’ which prevented a right
days from the final submission of the arising in the first place.
parties to deliver their Decision, potentially Levent Irmak (Turkey) argued persuasively
elongating the DAB process indefinitely. for an Employer’s right of partial termination
in the event of Contractor default. He
pointed out that full termination is often too
DBO Gold Book
drastic to be a practical solution. He was
It was pointed out by Sarah Thomas of Pinsent addressing the Silver Book but made clear
Masons that Clause 4.1 imposed a fitness that the same reasoning applied to all the
for purpose obligation that lasted the full FIDIC forms. He also suggested – to this
duration of the operation period, perhaps listener’s ear, less convincingly – the
20 years. She suggested that this was not involvement of the DAB to confirm or
reasonable. Michael Mortimer-Hawkins, who prevent terminations.
chaired the DBO Task Group, defended the Altogether the Users’ Conference
clause, saying that of course the plant should demonstrated that FIDIC is busy and continues
work properly at all times. to generate much interest.
Jim Perry of PS Consulting, Paris drew
attention to a new law in France, namely
Article 2255 of the Civil Code, introduced
Edward Corbett is the Managing Director of
in June 2008. Although it appeared to say
Corbett & Co International Construction
that parties may not agree to reduce Lawyers Ltd based in London, UK, the Editor-in-
limitation periods to less than one year, it Chief of CLInt, a FIDIC Adjudicator, the author
probably did not nullify the time-barring of FIDIC 4th – A Practical Legal Guide and a
provisions of Clause 20.1 as a distinction was member of the FIDIC Subcontracts Task Group.
to be made between limitation clauses and

Comment

Does a contractor’s delay


always involve its liability?
Mauro Rubino-Sammartano
Bianchi Rubino-Sammartano & Associati, Milan

D elays to the completion of a project


usually result in sanctions against the
contractor, the most common of which is
delay by the owner may override the non-
compliance with the programme by the
contractor. If so, unless it involves other
liquidated damages. It is not suggested that negative impacts on the project, the
concerns about such sanctions be disregarded, contractor may not be held liable for his
but there are certain circumstances in which own delay. In theory the owner might seek to
a delay may not result in sanctions against prove a breach of contract by the contractor
the contractor. in any event, even if this should not result
in any further sanctions, but the contractor
might counterclaim that the owner is itself
Concurrent delays
in breach of contract. The possibility of
Often a delay caused by the contractor these two findings would probably not make
occurs at the same time as a delay caused it worth either party pursuing such a limited
by the owner. In this event, the concurrent course of action.

Construction Law International Volume 5 Issue 1 March 2010 25

You might also like