Professional Documents
Culture Documents
GT2012
June 11-15, 2012, Copenhagen, Denmark
GT2012-70072
dN Discharge Conditions
P Pcompr Pfrict PGT, resid T N J N (1) Pressure (bara) 4.453 4.453 0.000
dt Temperature (ºC) 112.7 110.587 1.875
Compressibility (Z2) 0.967 0.967 0.000
Solving Eq. 1 for steady-state power and speed at the
initial operating point and assuming a constant Q/N Eq. 1 yields Reported Compressor Operating Conditions
the following expression for the speed decay: Polytropic Head (KJ/Kg) 92.8 92.8 0.045
Polytropic Efficiency (%) 73 72.7 0.411
3 Speed (RPM) 10739.1 10739.1 0.000
J No
N (t ) (2) Power (Kw) 338.7 344.3 1.662
J N o Po t
2
Average Relative Difference ‐ All Parameters (%) 0.562
The normal and upset condition pressures, temperatures,
flows, and gas compositions were included. A complete
compressor map was prepared and input to the model for the
1 n
ொೌ
ܱܲ ൌ │ேୀ௦௧ (5)
ொೞ
DYNAMIC SIMULATION ANALYSIS
Simulations of the compressor were focused on various
ொೌ ିொೄಹ
operational conditions identified to be of interest for the ܶ ܦൌ │ுୀ௦௧ (6)
ொೞ
performance improvement study. Transient sequences were
initiated from design, minimum, and other normal flow
conditions, since they represented the most critical scenarios for Different levels of ESD events were simulated for both of
a compressor shutdown. Unit emergency shutdown (ESD) the compressor train systems since different valves delay times
sequences were simulated to determine if the units go through (to begin opening and closing) existed for the various types of
surge and also how stable they were while they were ESDs. The main differences between the ESD sequences were
undergoing coast down. In addition, anti-surge control logic in the delay to open a specific recycle valve in the entire train
function and parameters were programmed into the model and the depressurization of a particular stage or all stages. In
logic. Thus, typical process upset conditions such as sudden addition, four other variations in the ESD sequence were
loss of a separator or flow and pressure changes were considered in order to find solutions to the surging of the
simulated. A very critical situation occurs when centrifugal compression system during an ESD event: 1) Varying the valve
compressors go through surge, which is the flow reversal within delays and opening times, 2) delaying the coast down of the
the compressor that originates high fluctuating loads and compressors, 3) adding an additional line and valve on the
vibrations that could damage the compressor [9, 10, and 11]. So second and third stage recycle lines (referred to as hot bypass),
the main objective of the simulations is to find out how the and 4) combining the coast down delay and hot bypass on the
compressors behave during critical upset conditions such as second stage.
ESD. In addition, it is very important to verify that the
compressors’ surge margins during normal operation are CASE RESULTS
sufficient to avoid any surge phenomenon. However, if the Since it was very critical to evaluate, understand, and
surge margin reaches a stipulated value of 10%, it is expected quantify the existing system’s issues and their effect on the
that the anti-surge control opens the recycle valve; thus, the process, a series of simulation analyses were conducted first for
flow through the compressor increases and the pressure ratio the existing configuration. In addition, it was vital to
decreases. understand how the different stages and their diverse
components were acting as a whole system, since any minor
Several emergency shutdown simulations were completed change in operation of one stage anti-surge valve (such as
on the model of the multi-stage compressor and piping systems. opening time, or relocation of the check valve) would affect the
These were simulated at the provided operating conditions. The behavior of the entire train. The system dynamics was very
same starting operating conditions were used for all sensitive to changes; for example a minor modification of
simulations. The simulations investigated the sensitivity of approximately 5% in the flow coefficient of the third stage
various parameters in the surge control systems, such as recycle (MP) anti-surge valve would cause the fourth stage (HP) to
valve opening times, recycle valve sizes, delay of opening of surge during an ESD. Similarly, increasing the flow coefficient
recycle valves, and the effects of the opening time of the of the anti-surge valve would allow more flow through its
blowdown valve. Thus, the anti-surge system control recycle line during the initial few milliseconds of opening,
parameters were built into the simulation as well as the ESD which would cause a sudden decrease in the suction flow of the
of the system will affect the initial reaction of any stage, since
the pressure waves that originate when the machine is 40
Surge Margin (%)
shutdown travel in the system based on its impedance. Thus,
the system’s impedance can affect the initial dH/dQ behavior of 30
the compressor until the system flow resistance starts
dominating the movement of the gas flow [2, 12]. 20
Existing System
SM_S1:VAL
10
An ESD event was simulated for the existing configuration SM_S2:VAL
SM_S3:VAL
in which the compressor started to shutdown (speed ramped SM_S4:VAL
0
down) at 0 seconds. The valves opened and closed according to 0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5 2.75 3 3.25 3.5
their specified timing. The anti-surge valve opening events are Time (s)
shown in Figure 2. The surging of the compressor occurs within
the first 1 to 2 seconds after shutdown, and the blow down and Figure 3. Surge Margin Values during an ESD Event for the
Existing Configuration
isolation valves do not start to actuate until after this time.
Thus, it was found that the first few milliseconds were very Figure 3 shows the surge margin of the four stages of the
decisive for the existing anti-surge configuration. compressor during the ESD. In this figure, it is clear that both
the second and third stages surged. The ESD is shown to have
Anti‐Surge Valves Opening versus Time during an ESD
little effect on the operating point of the first stage. This is most
110
likely due to two factors: 1) the recycle valve of the first stage
100
was already opened to a fraction of 31% at the beginning of the
90 ESD event, and 2) the first stage recycle valve is the first valve
80 that opens during an ESD event and has the quickest opening
time. All of these factors reduce the effect of the compressor
Valve Opening (%)
70
60
shutdown on the surging of the first stage. The first stage had a
minimum surge margin of 18.4% during the transient
50
simulation, which is considered acceptable.
40
30
The second and third compressor stages experienced a
surge event during the simulated ESD for the existing anti-
20 ASV‐Stage 1
ASV‐Stage 2
surge configuration. Those two stages presented the slowest
10 ASV‐Stage 3 opening time and the longest signal delay. Thus, they did not
ASV‐Stage 4
0
0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5 2.75 3 3.25 3.5
have sufficient flow to recover from the rapid speed reduction
Time (s) that originated during the ESD. Moreover, as soon as the fourth
stage started drawing more flow it affected the dH/dQ behavior
Figure 2. Anti-Surge Valves Opening during an ESD Event for the of the second and third stages, since the dQ component
Existing Configuration
decreased rapidly. Thus, the compressors move to the surge
condition quickly.
Contrary to the other stages, the flow and head in the
second and third stages reduced rapidly bringing the
compressors to a surge condition. It was observed that the anti-
surge valves of both units were not able to divert sufficient flow
to the suction of the compressor stage during the transient.
Moreover, the second stage valve has the slowest travel time
and the third stage valve has the longest delay time. Thus, those
conditions affect the behavior of the system, since the high
pressure energy is maintained in the discharge of both units for
a longer period of time during the coast-down of the unit.
Therefore, the lack of enough flow in the suction side and the
high energy present at the discharge (head) during the transient
event cause a harsh surge condition in both compressor stages,
which are not acceptable even for a small period of time.
22.5
50
20.0
17.5
40
Surge Margin (%)
15.0
12.5 30
10.0
20
7.5
5.0 10 SM_S1:VAL
LP‐S1 SM_S2:VAL
LP‐S2 SM_S3:VAL
2.5
MP‐S3 SM_S4:VAL
HP‐S4 0
0.0 0 0.5 1 1.5 2 2.5 3 3.5 4
1.50 1.75 2.00 2.25 2.50 2.75 3.00 3.25 Time (s)
2nd Stage Anti‐Surge Valve Opening Time (s)
Figure 4. Parametric Study for the Second Stage Anti-Surge Valve Figure 5. Coastdown Delay and Hot Bypass Option Results
Opening Time including a Coastdown delay of 100 Milliseconds
Results from the different parametric studies indicated the
most critical scenarios to be analyzed for the entire train, as
well as the best direction for any proposed change or
modification. Therefore, modified sequences and alternatives
were simulated and analyzed for the compressor trains. The
first modified sequence involved changing valve delay and
60
surge margins of each compressor stage. The second alternate
50 case investigated the effects of a short valve opening time on
40
the surging of the compressor stages. In all cases simulated, the
ESD sequence with a 0.75 second coast down delay and
30
inclusion of a hot bypass valve on the second stage was used.
Existing ESD Sequence
20
Modified Valve Timing The results of these simulations indicate that the first and
Coastdown Delay
10 Hot Bypass
second stages were not affected by the change of timing on the
Coastdown + Hot Bypass main blowdown valve. This was expected since the valve is
0
4000 6000 8000 10000 12000 14000 16000 18000 20000 22000 located on the blow down line at the suction of the fourth stage
Inlet Flow (am3/hr) compressor. The third stage was slightly affected by the delay
Figure 6. 2nd Stage Compressor Map with Decel Paths for
opening time of the valve. When the valve had a 0.5 second
Different Sequences delay, the surge characteristics of the third stage compressor
slightly improved. The minimum surge margin point increased
Figure 6 and Figure 7 show each of the five sequences to 17.2% from 15.4%. The third stage was not affected by the
discussed above on the compressor maps for the second and short opening time of the valve simulated in the second case.
third stages. Based on the results of these studies, it is The minimum operating point on the fourth stage slightly
recommended that either the hot bypass sequence (use of 6 and decreased when the main blowdown valve opened with a 0.5
3-inch quick opening valves with 1.2 and 1.5 seconds on second delay. However, the decrease experienced (4.3%) was
second and third stages, respectively) or a combination of a not considered significant since the fourth stage has an
coast down delay and hot bypass on the second stage adequate surge margin. The fourth stage was not affected by the
compressor be implemented. In addition, it was observed that short opening time of the valve as simulated in the second case.
the implementation of the hot bypass will affect the neighbor
stages, since it will produce a quick drop of the discharge Additional scenarios were also analyzed for critical process
pressure of one stage as well as the suction pressure of the upset conditions and failure of check and isolation valves. The
following stage as observed in Figure 6 where the coast down existing anti-surge system responded well to mild process
delay and the hot bypass combined effect is in the middle. In upsets, such as lower suction pressure; however, for critical
this case, the hot bypass option of the 2nd stage is diminishing upset conditions, such as a sudden drop of the inlet flow due to
the positive effect of the coast down delay. a loss of a process separator, its response was very marginal
due to the slow response of the second and third stages recycle
Compressor Train 3rd Stage Map with Different Sequences valves. Thus, this confirmed again that the anti-surge logic or
140
sequence for those stages should be adjusted to provide
120
sufficient protection for the entire train.
The main objective of the check valves in the gas system is
100
to stop reverse flow through the compressor stages. A high
Polytropic Head (kJ/kg)
Anti-Surge Valve
Out Flow Discharge
Cooler Header
Suction Check
Header Valve
Scrubber
Flare
Pressure (bara) 1.02 1.02 0.000 4.164 4.164 0.000 4.263 4.263 0.000 9.85 9.85 0.000 9.93 9.93 0.000 32.25 32.25 0.000 31.88 31.88 0.000
42.78 42.78 0.000 39.87 39.87 0.000 29.89 29.89 0.000 39.93 39.93 0.000 29.94 29.94 0.000 39.93 39.93 0.000 29.94 29.94 0.000
Temperature (ºC)
45.21 45.21 0.000 30.73 30.73 0.000 29.24 29.24 0.000 30.39 30.39 0.000 28.95 28.95 0.000 28.11 28.11 0.000 26.91 26.91 0.000
Molecular Weight (kg/kmol)
Specific Gravity (‐) 1.561 1.561 0.008 1.061 1.061 0.000 1.010 1.010 0.000 1.049 1.048 0.116 1.000 0.999 0.050 0.971 0.970 0.052 0.929 0.929 0.008
0.985 0.985 0.000 0.975 0.975 0.000 0.975 0.985 1.026 0.943 0.943 0.000 0.944 0.944 0.000 0.84 0.84 0.000 0.841 0.841 0.000
Compressibility (Z1)
5381 5466 1.572 16241 16281 0.245 15647 15907 1.659 9588 9560 0.292 9328 9443 1.229 2105 2076 1.368 1981 2004 1.181
Inlet Actual Volume (m3/h)
Inlet Actual Volume (ft3/min) 3167 3217 1.572 9559 9583 0.245 9209 9362 1.659 5643 5627 0.292 5490 5558 1.229 1239 1222 1.368 1166 1180 1.181
5025.4 5004.0 0.426 63136.9 62680.0 0.724 64324.8 64875.0 0.855 91145.2 89860.0 1.410 92242.5 92570.0 0.355 73550.2 71430.0 2.883 70594.7 70590.0 0.007
Standard Flow (SCMH)
4.259 4.241 0.426 53.512 53.125 0.724 54.519 54.985 0.855 77.250 76.161 1.410 78.180 78.458 0.355 62.338 60.541 2.883 59.833 59.829 0.007
Standard Flow (MMSCFD)
Density (kg/m3) 1.782 1.778 0.245 5.043 5.026 0.337 5.074 5.065 0.184 12.195 12.130 0.535 12.085 12.049 0.297 41.462 41.034 1.031 40.481 40.191 0.717
0.111 0.111 0.245 0.315 0.314 0.337 0.317 0.316 0.184 0.761 0.757 0.535 0.754 0.752 0.297 2.588 2.562 1.031 2.527 2.509 0.717
Density (lbm/ft3)
Mass Flow Rate (kg/s) 2.66 2.70 1.323 22.75 22.73 0.092 22.05 22.38 1.472 32.48 32.21 0.825 31.31 31.60 0.928 24.24 23.67 2.385 22.28 22.38 0.456
Discharge Conditions
4.453 4.453 0.000 10.39 10.39 0.000 10.41 10.41 0.000 32.55 32.548 0.006 32.15 32.15 0.000 102.5 102.499 0.001 102 101.993 0.007
Pressure (bara)
Temperature (ºC) 112.7 110.587 1.875 94.4 96.261 1.971 85 83.253 2.055 122.8 125.549 2.239 113.2 110.657 2.246 146.7 150.28 2.440 139.1 136.36 1.970
Compressibility (Z2) 0.967 0.967 0.000 0.965 0.964 0.104 0.966 0.966 0.000 0.92 0.92 0.000 0.923 0.923 0.000 0.871 0.871 0.000 0.877 0.877 0.000
Reported Compressor Operating Conditions
92.8 92.8 0.045 81.6 81.9 0.357 81.4 81.6 0.185 107.7 108.1 0.401 108.2 108.5 0.252 105.6 107.8 2.095 108.7 110.6 1.728
Polytropic Head (KJ/Kg)
73 72.7 0.411 83.1 83.2 0.120 83 83 0.000 74.7 74.4 0.402 75.3 74.9 0.531 58 58.2 0.345 58.5 58.7 0.342
Polytropic Efficiency (%)
Speed (RPM) 10739.1 10739.1 0.000 10802.3 10802.3 0.000 10739.1 10739.1 0.000 10802.3 10802.0 0.003 10739.0 10739.0 0.000 10802.3 10802.0 0.003 10739.1 10739.0 0.001
Power (Kw) 338.7 344.3 1.662 2234.0 2236.7 0.118 2163.0 2199.1 1.672 4682.9 4824.5 3.025 4499.5 4717.0 4.834 4414.0 4518.0 2.356 4136.0 4343.0 5.005