DAILY PROGRESS REPORT (DPR) OF GCU-2-MECHANICAL

From 0500 Hrs 7 Feb 2018 to 0500 Hrs 08/Feb/2018


Reported Date: 08/Feb/2018
(A) Equipment Installed Details
S No Equipment Type Total Running Standby Total PM PM Cumulative PM Remarks
Equipment Due Done PM Done Remaining

1 Centrifugal Compressor 3 3 0 0 0 0 0 0
2 Expander Compressor 2 2 0 0 0 0 0 0
3 Reciprocating Compressor 4 2 2 1 0 1 0 0
4 Dosing Pump 55 20 35 22 1 9 13 0
5 Centrifugal Pump 126 47 79 44 2 16 28 0
6 Screw Pump 14 3 11 2 0 0 2 0
7 Gear Pumps 8 3 5 3 0 2 1 0
8 Steam Turbine 12 12 0 1 0 0 1 0
9 Agitator 16 4 12 1 0 2 -1 0
10 ID Fan 3 2 1 1 0 0 1 0
11 HVAC System Equipment 13 5 8 4 0 0 4 0
12 Spare Rotor 15 0 15 3 0 0 3 0
Total 271 103 168 82 3 30 52
(B) Critical Equipment Details
S No Equipment Description Tag No. Run Time (Hrs) Down Time (Hrs) Remarks
1 Furnace-1 FF-110 Cell-A 24 0 CRACKING
FF-110 Cell-B 24 0 CRACKING
2 Furnace-2 FF-120 Cell-A 0 24 SHUTDOWN
FF-120 Cell-B 0 24 SHUTDOWN
3 Furnace-3 FF-130 Cell-A 24 0 CRACKING
FF-130 Cell-B 24 0 CRACKING
4 CG Compressor 110-KA-300 24 0 RUNNING
5 C2R Compressor 110-KA-600 24 0 RUNNING
6 C3R Compressor 110-KA-650 24 0 RUNNING
7 Expander Compressor-A 110-KA-400A 24 0 RUNNING
8 Expander Compressor-B 110-KA-400B 24 0 RUNNING
9 BFW Pump-A 110-PA-904A 24 0 RUNNING
10 BFW Pump-B 110-PA-904B 24 0 RUNNING
11 BFW Pump-C 110-PA-904C 0 0 STAND BY
(C ) Work in Progress
1 PA-955 A MECH. MAINT. JOB U/P.
2 FF-120 CLEANING AND PAINTING JOB U/P.
3 FF-120 Deblinding job U/P
4 0
5 0
6 0
7 0
8 0
9 0
10 0
(D) GCU-2-Mech Other Remark
1 PM OF PA-950B,PA-550B,PA-925B
2 RB-380 HP Fuel gas I/V valve attended
3 FF-120 CELL A&B mahole boxed up
4 Strainer welding U/S of steam trap (FV-14913) completed .
5 0
6 0
7 0
8 0
9 0
10 0