Professional Documents
Culture Documents
and Reliability
J. DAUGHTRY and E. TELETZKE,
INEOS GAS/SPEC Technology Group, Freeport, Texas
vibrations, which can cause catastrophic pump failures. Main- Corrections. The following corrections were made:
taining flow above the minimum specified flowrate prevents re- 1. The amine flowrate was increased above 660 gpm,
circulation of the fluid in the pump, which can lead to bubble in both trains, in accordance with the minimum
formation and cavitation. Low liquid flowrates can also cause flowrate required by the pump data sheets.
cavitation if the temperature increase in the liquid across the 2. Equipment limitations, in addition to the chemistry
pump results in vaporization. Typically, the minimum circula- and loading limits of the amine, are now considered
tion rate for a given pump is 50% of the best efficiency point when adjusting the amine circulation rate and other
(BEP)—the operating point at which the pump is most effi- process variables.
cient.14 For this pump, the BEP is 1,270 gpm, more than double 3. In subsequent years of operation, no additional leaks
the 620 gpm flowrate at which the pump had been operating. or failures of the lean amine booster pumps have
The pump curve confirmed that operating below the mini- occurred at this facility.
mum flowrate was resulting in discharge cavitation corrosion.
Upon increasing the circulation rate of the pump above the 660 CASE HISTORY 5: BROKEN PUMP
gpm required by the pump design curve, the rattling sound in- SHAFT—STRESS AND FATIGUE FAILURE
dicative of pump cavitation ceased.
Problem. In 1985, a gas processing plant in Texas treating gas-
Conclusions. After the investigation was completed, the fol- eous-phase ethane and propane experienced an amine pump
lowing conclusions were drawn: failure. The multistage pump shaft experienced a clean and in-
1. The lean amine booster pump was operating below the stantaneous break. While the root cause analysis for the first
minimum flowrate specified on the pump design curve. pump failure was being conducted, a second pump shaft expe-
2. The resulting cavitation caused a pump failure rienced a clean and instantaneous break for an unknown reason.
two months after the pump was put into service.
Background. This facility was using a formulated methyldieth-
Data point 175 13 in. 65 70 anolamine (MDEA) solvent to treat an inlet ethane and propane
Flow: 1,270 US gpm 75
Head: 146 ft 78
78.6
gas stream from 10 mol% CO2 to a pipeline specification of less
Eff.: 79% 150
Power: 59.6 hp 56 pw ~133 ft 78
75
than 2 mol%. The feed to this facility included seven different
NPSHr: 9.74 ft
Design curve
125 70 pipelines with varying CO2 compositions. The amine circula-
Shutoff head:
Shutoff dP:
179 ft
77.5 psi 100 tion rate was fixed to handle the highest possible inlet CO2 com-
9 in.
Head, ft
Min. flow:
SEP:
660 US gpm
79% at 75 position of 10 mol%. Prior to the pump failures, a reduction had
NOL power:
1,270 US gpm
69.8 hp at
65 occurred in the inlet flowrate to the plant, and operations had
50
1,688 US gpm
Max. curve decided to reduce the amine circulation rate in accordance with
Max. power: 69.6 hp at 25 200 400 600 800 1,000 1,200 1,400 1,600 1,800 the rich loading requirements for the formulated MDEA solvent.
1,688 US gpm 15
10 The amine at this gas processing plant was on a routine ana-
5 lytical program, and the sample history was consulted to identify
0 any unusual trends that could be responsible for the pump fail-
200 400 600 800 1,000 1,200 1,400 1,600 1,800
ure. The amine analytical history did not show significant levels
FIG. 11. Pump data sheet for the centrifugal lean amine booster pump.13 of oxygen degradation products or any other contaminants that
would increase the corrosivity of the amine solution. The rich
and lean amine loadings were within the recommended range
for the formulated MDEA solvent.
An unusual light lavender color was observed in the transpar-
ent amine solution. A purple tint to the amine solution indicates
the presence of chromium (Cr), a component of 300 and 400
series stainless steel. The presence of Cr dissolved in the amine
solution suggested corrosion to stainless steel equipment in the
plant. Interestingly, the amine was analyzed for soluble metals
using inductively coupled plasma mass spectrometry (ICP-
MS). Less than 1 ppmw of dissolved Cr was detected. It was later
discovered that strips of denim blue jeans had been used in a
filter canister, and the indigo dye had leached into the amine,
resulting in the light lavender color.
pellers, the number of stages used and the speed at which the While the issues with the RO H2O system were being inves-
impellers are turning. The diameter of the impellers is usually tigated, the amine solvent began to form degradation products,
not trimmed to achieve the required conditions. resulting from oxygen (O2 ) contamination. These degradation
The appearance of the damaged or broken shaft can be used products—known as heat-stable amine salts (HSAS)—bind
to speculate the cause of failure. A clean break indicates an “in- with the amine in a reaction that cannot be reversed in the re-
stantaneous” fracture caused by sudden overload or imbalance generator. As these salts were formed, the concentration quickly
(FIG. 12). If the broken shaft is discolored (usually blue), the increased to 9 wt% in the amine solvent, with acetate, formate
damage was gradual, indicating excessive heat buildup before and oxalate accounting for most of the HSAS.
the shaft broke (FIG. 13). Six months after startup, a pump failed unexpectedly. The
The failure in FIG. 11 between where the shaft diameter changed operations team began investigating the cause of the failure.
is the exact location of the actual failure. With an instantaneous When the pump was taken apart, a solid, salt-like material was
pump shaft failure suspected, the next course of action was to de- found coating the bearing surface (FIG. 14). While the plant was
termine why the instantaneous break in the pump shaft occurred. shut down for inspection, similar deposits were found plug-
An instantaneous break indicates the pump shaft was overloaded ging 40% of the reboiler tubes. Samples of the solids from both
with unbalanced forces. Pumps are designed to be balanced when the pump and the reboiler were collected and were identified
operating within a safe range of their BEP. As the pump flowrate as calcium oxalate (C2CaO4 ). This event was the first instance
moves farther from the BEP, the pounds of unbalanced thrust on of fouling resulting from calcium oxide that operations had ob-
the pump increase. Further review of the pump operations re- served in any of the company’s plants.
vealed that the pump was operating at less than 50% of the BEP. The cause of the fouling and pump failure was two-fold.
First, the RO unit allowed Na, K and Ca salts to enter the amine
Conclusions. The following conclusions were observed: system. Second, the O2 contamination in the inlet natural gas
1. The clean break indicates an instantaneous fracture resulted in degradation of the amine solvent to form oxalate.
caused by a sudden overload or imbalance on the When strong base cations like Na, K and Ca are present in the
pump shafts that experienced failures. amine solution, they will replace the amine molecule in the
2. Operating the pumps too far from the BEP specified HSAS and form an inorganic heat-stable salt (IHSS). TABLE 2
for each pump resulted in unbalanced thrust being
applied to the pump shafts. TABLE 1. H2O quality standards for amine systems14
Property Specific values ASTM test method
Corrections. The following corrections were made:
1. The multi-stage pumps that experienced failures Total solids, ppmw 100 max. D1888
were replaced. Total hardness, ppmw 50 max. D1126
2. Flowrates were maintained within a safe operating Chloride (CL), ppmw 2 max. D512, D4327
range of the BEP for each pump. No additional pump
Sulfate (SO4 ), ppmw 3 max. D516, D4327
shaft failures have occurred since the operating range
was adjusted. Sodium (Na), ppmw 3 max. D516, D4327
Potassium (K), ppmw 3 max. D516, D4327
CASE HISTORY 6: PUMP BEARING FOULING Iron (Fe), ppmw 10 max. D516, D4327
AND SEIZURE—HARD WATER (H2O) DEPOSITS pH 7–7.7 D1293
74 DECEMBER 2017 | HydrocarbonProcessing.com