Addition omission/cost variations

GENERAL COMMENT WELENCHITI AND SHENO (where applicable)


Unit rate analysis
1. The index shall not be beyond 25% as the CSA inflation and labor index never
released to be above 25%. What is indicated in the labor analysis as 60% is not
accepted!!!!
2. The labor rate shall be the monthly salary divide by 30 days and not 26 days.
Other costs are covered somewhere!!!!
3. The output rates are
4. The profit margin for Contractor class 1 is 25% and not 35%. Other costs as
overhead are 10%. This shall be corrected
5. The original preforma shall be attached from the firms you stated, Geosynthetic,
Belt, etc. with appropriate stamps and due dates.
6. All doors and sheet metal thicknesses are correctly stated as 1mm. but the tiles
and details in the BoQ are stated as 1.25mm. Not acceptable. All sheet metals
shall be 1mm as per the original contract.
7. The table for labor hourly output and equipments are highly reduced to
exaggerate the unit rate. Please provide a separate table for the same.
8. You shall maintain sizes of all doors of appropriate sizes and cost as indicated
in the original contract for public toilet and buildings.
9. All reservoir chemical paints shall be omitted no further work is to be approved.

PLEASE REFER DETAILS IN PRECEDING PAGES!!!

Bill No 07: Reservoirs

1. The reservoirs are perfectly casted and so the client shall require additional water
proofing material

It is the contractor responsibility if the quality is checked and found leakage to correct
it with water proofing material

So delete
”Provide and apply two coats of water proofing chemical over the
plastered surface of internal walls inclusive top surface of top slab” in all
reservoirs

Valve chambers:
What wall material is proposed for such high cost of building a valve chamber to all
reservoirs?

So correct and include the wall material type approved


“Construction of 2000x2800x2000 outlet valve chambers with
concrete manhole cover 600x600x10”

Amen Consulting Plc 1


Addition omission/cost variations

What PN is recommended for all inlets and outlets DCI pipes for all reservoirs?
Drainage ditch

Stone masonry canal of hard basalt or equivalent impermeable, non-weathered and


non-fractured stone bedded and joined in 1:3 cement mortar For SDB. Why here
1500birr/m3 not stating the thickness and associated works?

What is the difference?


4.9.1 (Operator building) Stone pitched drainage ditch m 80 120.00

The is exaggerated so to compensate the mortar shall be 1:2 ratio

Supply and installation of HDPE Pipes & fittings (PN10). Price includes butt welding
OD 160mm pipe for draining the waste water to soak away pit

Public Toilets and other buildings


All doors and windows
Why is the door 1.25mm? It has no special benefit, in fact the more heavier the fastest to be
non-functional. It is unusual to make the sheet metal such thickness …to be changed. The
cost is twice exaggerated!!!!!! How about the original sizes where correctly to be
maintained?? Say 1x2.1m2, 0.9x2.1m2
So: Delete the thickness as 1.25mm and replace with the original thickness 1mm
Also maintain the original sizes and cost of all doors with sizes 2.1 height but give
additional costs for the 50cm panel section only!!!!!
Who gave the order to change the thickness of the door sheet metal?

SLF and SDB

SLF
Why the contractor quoted 1birr for the following

1.4 Excavation soft rock m³ 1,534.00


1.5 Excavation of hard rock m³ 1,534.00
How about the depth and thickness of the overload soil against the thickness of the
pipe proposed HDPE for the wastewater. At some point the depth might be above
1500mm or so.
So

Amen Consulting Plc 2


Addition omission/cost variations

Delete the new addition quotations for the same work or shall talk with the Client
on the matter!!!!!
SDB
Why the access road is separately included in the SDB?
So
“Delete in all places where indicated” and
Also Omit:
Access road From the Drilling Bill No 2 and
Add
” the same in the “Bill no 1 General to serve for all Total 3km”. please keep the
same unit rate for the lump sum(which is understood as 1km for Welenchity and
sheno case during the bid)

ACCESS ROAD FOR NBH3 369.24


ACCESS ROAD FOR NBH1 & NBH2 1804.54
ACCESS ROAD FOR SANITARY LAND FILL 665.66
Total 2839.44
Why is the following material omitted from the original contract in SDB?

15m3 Prefab Polyethylene Tank pcs 1.00

3m3 Prefab Polyethylene Tank pcs 1.00

Why is this omitted? From SDB

5 Fence and gate work unit Qty Unit rate


Provide and install entrance gate with
(40*40*2.6) mm RHS grilled vertical door
frame, and horizontal frame shall be
(30*30*2) mm, inner verticals (25*25*2) mm
@ 100 mm c/c welded all round at the
profile and all necessary ironmongery, locks
of the best quality. The gate shall be painted
with one coat of anti-rust and two coats of
5.3 synthetic paint as given in the specification No. 1.00 10.00

So do not omit this item it shall be correct to be executed!!!!

Amen Consulting Plc 3


Addition omission/cost variations

Comments No: 2 Details


A. No “cart way” item hall be omitted in all bills
B. The pipe works distribution depth is 800x800mm in some case the depth is 600mm.
the bedding over quantity(~3000m3) shall be corrected in accordance with the OD of
each HDPE pipes
C. The new testing and commissioning cost is 200% of the original contract. Why?
D. The new disinfection cost is 800% of the original contract value. Why?
E. The cost of new HDPE pipes even if all are produced in Ethiopia has shown
exaggerated unit rate”
a. OD 75mm 221% of the original contract rate
b. OD 63mm 193% of the original contract price
c. OD 50mm 157% of the original contract price
F. Please no “valve chamber “original contract items of size 800x800x1000mm shall be
omitted and replaced by 1200x1200x1000mm new sizes. Why and what materials?
G. In addition no “item” in the original contract for which unit rates are birr1.00” shall be
omitted. The client shall decide first.

Comments No: 3 Details


Details

A. Why this items and others to come so assigned to have exaggerated unit rate
B. Is it a reservoir why not state in details?

Pipes and fittings for new village water


supply around Sheno Boreholes
Ground Reservoir 50m3 with GS inlet
column GS outlet Column and Overflow-
Complete LS 0 1 1,062,792.20
Reservoir elevated 10m3 with GS inlet
column GS outlet Column and Overflow-
Complete LS 0 1 127,343.25

Water Point No. 0 3 40,000.00

Amen Consulting Plc 4