DAF 1 OF 11
CONTENT:
This General Instruction prescribes the roles and responsibilities between the Inspection Department (ID) and
Project Management (PM) during the various project phases under the Capital Program.
1. Purpose
2. References
3. Definitions
4. Commitment
5. Team Organization Structure
6. Roles and Responsibilities for Major Projects
7. Roles and Responsibilities for Small Projects
8. Attachments
9. Approval Authority
1.0 PURPOSE:
This instruction defines the roles and responsibilities of the organizations and personnel directly
responsible for the quality of the facilities being provided to the Company under the Capital Budget for
all projects managed by Project Management.
2.0 REFERENCES:
2.1 SAEP-1023 "Contractor Quality Assurance And Quality Control Requirements"
2.2 SAEP-303 "Engineering Reviews of Project Proposal And Detailed Design Documentation"
3.0 DEFINITIONS:
3.1 Functional Reporting: For the purposes of this document, when the ID Representative
functionally reports to the Project Manager, he is empowered to report and resolve all quality
issues, concerns and violations directly with the Project Manager or his representative in
accordance with SAEP-1023. In addition, the Project Manager will communicate all project
quality documentation review/approval requests directly to the ID Representative.
3.2 Administrative Reporting: For the purposes of this document, the ID representative will
continue to report to his Project Inspection Unit on his daily inspection activities and
assignments. In addition, all of his personnel records, promotions, evaluations and all other
personnel activities will be retained by Inspection Department.
3.3 Major projects: Any project with a capital value more than $50MM, or any group of small
projects agreed to by Project Management and Inspection Department.
3.4 Small projects: Any project with capital value less than $50MM.
4.0 COMMITMENT:
4.1 Engineering and Operations Services (E&OS) is committed to providing facilities that are fit for
purpose and designed, procured and built to the highest quality in accordance with Saudi
Aramco Mandatory Engineering Requirements (SAMERs), Project Specifications and Contract
requirements.
4.2.1 As the Company Representative leading the project delivery effort, Project Management,
through Project Management Teams (PMT's), is responsible for the overall quality of the
projects in the capital program. Each Project Manager is responsible for implementation
of quality systems that will effectively deliver the project per Saudi Aramco specified
quality requirements.
4.2.2 Project Management will provide the leadership, management systems, and resources
required to effectively design, procure, construct and mechanically complete the
projects. In addition, Project Management will provide on site qualified PMT
supervision to insure that the Contractor adheres to all procedures and standards and the
built facilities meet with Saudi Aramco Mandatory Engineering Requirements
(SAMERs), Project Specifications and Contract requirements.
4.3 INSPECTION DEPARTMENT
4.3.1 Inspection Department is charged with the corporate responsibility to assure that an
effective quality management system is in place, so that materials and equipment
purchased, and equipment and facilities constructed for and by Saudi Aramco comply
with Saudi Aramco specified quality requirements.
4.3.2 Inspection Department will participate actively in the development of effective quality
systems, and monitor and assess capital program execution to ensure the project meets
specified quality requirements.
4.3.3 Inspection Department will provide the resources required to effectively support and
assess quality systems throughout all phases of the project: design, procurement,
construction and pre-commissioning. In addition, Inspection Department will provide
on site inspection in sufficient quality, quantity and detail to insure, through the Project
Manager, that the Contractor effectively and efficiently enforces the Saudi Aramco
Mandatory Engineering Requirements (SAMERs), Project Specifications and Contract
requirements.
5.2 The same concept will be adopted for a group of medium and small size projects.
At this stage of the project, Inspection Department SPC will assign a VID
coordinator over the SAIRs to coordinate all the Design and Procurement
inspection activities. At the Design and Procurement office, the SAIR located
at that Design offices will still functionally report to the most senior PMT
Representative (Sr. Project Manager, Project Manger. Sr. PE, PE) located at
the design office, and administratively to the VID coordinator.
6.1.1.4 Construction phase: the arrangement outlined in 6.1.1.3 will still apply; how-
ever, the PID Supervisor will report functionally to the Project Managers and
administratively to the SPC. Also, the VID coordinator and all the SAIRs will
move to the respective sites and continue their procurement phase inspection
activities. They will functionally report to the senior PMT member and admin-
istratively to the SPC. Once all materials have arrived on site, the VID coordi-
nator and SAIRs will report to VID.
6.1.2 Manning Level and Mobilization Plan
6.1.2.1 Immediately after Contract(s) award, the SPC will work with Projects Inspec-
tion Division (PID) Superintendent, Vendors Inspection Division (VID) Su-
perintendent and Project Manager(s) to determine the required ID QA/QC
manning level. He will assign Saudi Aramco Inspection Representatives
(SAIRs), PID Supervisor(s) and discipline inspectors to each site and/or con-
tract in sufficient numbers to effectively monitor the Contractor's quality sys-
tem and insure that all procedures and critical systems are inspected to
SAMERs, Project Specifications and Contract requirements.
6.1.2.2 The SPC will continue to work with PID & VID Superintendents and Project
Manager(s) to determine the ID inspectors Mobilization Plan during the vari-
ous phases of the project.
6.1.3 Responsibilities
6.1.3.1 Prior to Contract Award
a. The SPC or his representative(s) will actively work with Project
Manager(s) in the development of the project overall QA/QC plans.
6.3.1 Provide guidance and support to the Project Manager as needed to assure project quality
goals are met.
6.3.2 Set department quality objectives and provide means to achieve them.
6.3.3 Review project and departmental QA/QC programs and performance to insure effective
implementation of corporate objectives.
6.3.4 Periodically review project QA/QC results, and make appropriate policy adjustments to
achieve the desired results.
6.3.5 Interface with Inspection Department Manager as necessary.
6.3.6 Resolve ID/PMT disagreements or refer them to senior management.
6.4.1 Develop and maintain Quality Performance Indices to assess the status of the project and
benchmark at the Corporate level as a whole.
6.4.2 Monitor quality compliance performance indicators and take corrective actions when
deviations from plan start to appear.
6.4.3 Assign qualified ID Single Point Contacts (SPCs).
6.4.4 Call for and implement quality assessments to ensure compliance.
6.4.5 Assign an individual or a team to conduct spot assessments of work progress. The
objective of these assessments is to evaluate the effectiveness of the Contractor QA/QC
coverage of a project.
6.4.6 Provide feedback to executive management on quality issues as necessary.
7.1.1 The Project Inspection Unit Supervisor will be the Single Point Contact (SPC) for the
project.
7.1.2 All other roles and responsibilities assigned to other Inspection Department
Representatives listed in Section 6.1 are applicable.
8.0 ATTACHMENTS:
The following attachments are provided with this General Instruction:
Approved By:
Senior Vice President E&OS