Professional Documents
Culture Documents
DRAINAGE
TECHNICAL
55
D E S I G N R E C O M M E N D A T I O N S
Trench Preparation end of the drain, but not more than 4 metre
Ensign may be laid directly into a naturally head at the lower end. If necessary, pipe
trimmed trench allowing 50mm clearance at lines,may be tested in sections.
each joint between coupling and trench AIR TEST - Pipework should withstand a
bottom. The trench bottom should be flat to pressure of 100mm water gauge and this
give continuous support to the pipework. should not fall by more than 25mm in a 5
If the subsoil cannot be accurately minute period. However where traps or
trimmed with a spade. the trench should be gullies are connected they should withstand a
excavated to a depth of 100mm below the pressure of 50mm water gauge and this
pipe invert and a granular bed laid. This also should not fall by more than 12mm in a 5
should allow 50mm clearance at each joint minute period.
between the coupling and the granular bed. It is recommended that pipework
Where Ensign is to be set in concrete, the installations are tested in sections rather than
trench should be prepared as above to allow waiting to complete in one operation.
a minimum of 100mm of concrete under the
Q;@
pipe. Differential Movement
Ensign couplings allow up to 3° deflection
;;;;;;;;;
Fig. 13
Constructional at each joint.
Flexible Joint Pipelines leaving buildings, manholes or
;;;;;;;;;
Q;@Q;
other structures which are likely to be subject
➤
;;;;;;;;;
joints, a maximum of 600mm apart, thereby
allowing a short length of pipe to act as a
;;;;;;;;;
@
“rocker pipe”. The joint nearest the structure
should be as close to it as possible and, in
;;;;;;;;;
areas where large settlement is expected,
more than one “rocker pipe” may be required.
(See fig. 16).
Note: See BS EN 752-1 and relevant building regulations for further information.
D E S I G N R E C O M M E N D A T I O N S
Fig. 14
;; ;;;;;
;;;;;
ENSIGN BURIED
DRAINAGE
;;;; ;;;;
min. 600mm max.
➤ ➤➤ ➤
TECHNICAL
;;;; ;;;;;
;;;;
➤
;;;;;
➤
Flexible Joints
Access Fig. 16
Access is required on all pipelines to
facilitate the rodding and clearing of debris
and can be provided by manholes, chambers,
➤
➤
exceed 90 metres. (See fig. 15) Gully
Fig. 15
➤ 45m ➤ 45m
➤ ➤
Fig. 17 57
MH MH
Below is a table of maximum spacing of drainage access points (in metres). For pipes up to and including
300mm dia.
Access-Fitting Inspection
From To small Large Junction Chamber Manhole
Start of external drain 12 12 - 22 45
Rodding eye 22 22 22 45 45 Reference the building
Access fitting regulation 1985 (2000)
Small 150Ø drainage and waste dis-
150 x 100 12 22 22 posal document H. H1 -
Large 225 x 100 22 45 45 sanitary pipework and
Inspection Chamber 22 45 22 45 45 drainage-table 10.
Manhole 22 45 45 45 90
D E S I G N R E C O M M E N D A T I O N S
Fig. 18
➤
Access Bend
➤
;;;
;;;;;
;;;
;;;;;
Access Branch
;;;;;;
;;;;;; ;;;;;
;;;;;;
;;;;;;;
Use of Bends/Branches
Bends in drains should be kept to a
;;;;;;;
minimum. Wherever possible bends should be
at or near to manholes or in a position which
allow ease of rodding (See fig. 20).
Inspection Chambers At the base of soil and rainwater stacks, it
Inspection chamber branch arm entries are is recommended that long radius bends be
all at 45° to conform with BS EN 12056/4. used (See fig. 19).
Where other angles of entry are Branches or junctions on drains should be
neccessary these can be achieved by the use - where possible - at access points, such as
of standard bends (See fig. 20). manholes, to facilitate rodding.
58
Fig. 20
➤
➤ 1200mm ➤
D E S I G N R E C O M M E N D A T I O N S
for removal is more hygienic. drain between two fixing points reducing the
● Quicker to install reducing installation costs. need for many small bends.
● Construction of manhole brick chambers no ● Fulfils the requirements of BS EN 12056/4
TECHNICAL
➤
➤
➤
Recess in
structural slab
Structural slab
Recess in manhole
➤
A Comparison of Systems 59
T5 T5 T2
T6
T2 T6 T3
T3 T8
T7 T7
T8
T9
T9
T10 T12
T12 T10
T11
T11
T13
T14 T13 T14
PUDDLE FL ANGES INSTALL ATION D E T A I L S
;;;;;;
required. Location which may be below the
water table or in areas liable to flooding or in Bolt on
;;;;;;
areas which may need to be sealed against Puddle ➤
Flange
methane gas coming from made up ground ➤
➤
;;;;;;
etc. Denso ➤
;;;;;;
water entering the building by capillary action Pipe
;;;
onto the pipe once it has been bedded on Figure 24 shows the build in type again,
denso tape or similar. this time one piece (4set screws) for use with
;;;
a 200mm pipe. The ED078 is a compression
Fig. 21 puddle flange which needs to be slipped over
;;;
the end of the pipe and put into position.
100/150
Then it can be tightened up with the rachet
;;;
wrench. The gasket within the unit is
➤
;;;
compressed on to the pipe, therefore no
;;;
denso tape is required.
;;; ;;;
Fig. 24
;;;
200
;;;
➤
;;;
60 is installed after walls have been constructed.
;;;
The areas between the pipe and sleeve is
;;;
sealed using a mastic type sealant.
;;;
Fig. 22
;;;
Figure 25 you can see that four bolts need
;;;;;
Mastic
Sleeve ➤ Sealant to be tightened up equally.
➤
;;;;;
Fig. 25
;;;
;;; ;;;;;
Clamp
;;;;;
➤ Ring
Puddle ➤
Flange
➤
;;;;;
Pipe
➤
Flange
;;;;;
In figure 23 we see how the puddle flange
is fixed and sealed onto the pipe. With
Ensign this type of puddle flange is available
as ED078 in 100mm, 150mm, 250mm and
300mm diameters.