You are on page 1of 5

Performance and Design Specifications.

The contract specifications will often instruct the contractor to do more than
simply build a particular building element using certain materials. While
sometimes the specifications will simply instruct the contractor to build an
element in a particular fashion, other times the specifications will instruct the
contractor to construct a building element in a manner that achieves certain
objectives. The difference between these two types of specification is important
because it dictates the level of risk a contractor is assuming.

A performance specification sets forth the standard of performance to be


achieved. The contractor is expected to exercise it judgment in how best to
achieve the performance standard. A basic example of a performance
specification is if a specification states that the contractor shall construct a
HVAC system shall maintain a certain level of temperature and humidity level,
but leaves the design of the system necessary to achieve the required
temperature and humidity levels up to the contractor performing the work.

Conversely, a design specification describes in detail the materials and


equipment the contractor must use and the manner in which the work must be
performed. As one court put it, “design specifications state how the contract is
to be performed and permit no deviations. Performance specifications, on the
other hand, specify the results to be obtained, and leave it to the contractor to
determine how to achieve those results.”

This distinction is critical because when a contractor agrees to design a system


to meet a performance specification,
A Tactical Guide To Avoiding Construction Contract Disputes.

21 Copyright Wally Zimolong, Esquire, 2012.


it warrants that the system will perform as promised. Conversely, a contractor
that designs a system simply to meet the design specification guidelines makes
no warranty that the system will perform in any particular way. In fact, under
the so called Spearin Doctrine, which gets its name from a 1918 Supreme Court
decision United States v. Spearin, a contractor who has constructed a system
according to a design specification has a defense to any claim that the system is
not performing as intended.
The Spearin Doctrine applies onto to design specifications. Often, determining
whether a specification is a performance versus design specification is difficult
as a specification may blend elements of both. In order to differentiate between
performance versus design specifications, courts look to the level of discretion
that exists within the given specification. A contractor arguing that a
specification is a design specification – and thus subject to the Spearin Doctrine
– must show that the specification “does not permit meaningful discretion.”
Specifying a certain manufacturer of a product alone is not dispositive of
whether a specification is design rather than performance, especially when a
specification permits substitution of a specified product with “an approved
equal.” In determining whether a specification is design over performance,
courts also look to how much oversight the owner exercised over the contractors
work and whether the specifications lay out the contractors means and methods
of contraction.
Additionally, the difference between design and performance specification and
the liabilities each creates is of
A Tactical Guide To Avoiding Construction Contract Disputes.

22 Copyright Wally Zimolong, Esquire, 2012.

particular importance to design builders because specifications in design-build


contracts are performance specifications. Therefore, design-build contractors
should not only confirm that the system is capable of being constructed to
perform as required, but also that it can be constructed a price acceptable to the
design-build contractor. A design-build contractor that learns after contracting
that although the system is capable of construction, albeit at an exorbitant price,
will not be entitled to an adjustment in the contract price. Moreover, if they are
financially incapable of constructing the system at the price necessary for it to
perform, it is at risk for a bond claim.

A Tactical Guide To Avoiding Construction Contract Disputes.

23 Copyright Wally Zimolong, Esquire, 2012.

G. Change Order Clauses

Even on modestly sized projects changes are inevitable and a project is rarely
constructed exactly as originally designed. The reasons for changes in the work
are as numerous as the stars in the sky. However, one certainty is that
entitlement to additional compensation for changes is a frequent battle ground
for construction disputes.

Several areas of the contract will address changes. Of particular importance is


how a contractor perfects a claim for compensation for a change. Pity the
contractor that has performed work clearly outside the scope of his contract only
to see his claim be lost because he failed to perfect his claim under the contract.
Your lawyer cannot argue a claim for compensation because of a change if the
claim was not perfected. Therefore, it is imperative that a contractor know how
a change claim is perfected.

A contract should state the “who, when, and how” of change claims: Who
is authorized to direct changes? When is the deadline for submitting claims
for changes? How must those claims be submitted?

1. Who is authorized to direct change orders? The contract should state who is
authorized to direct changes in the work. In First General Construction Corp.,
Inc. v. Kasco Construction Co., Inc., the Federal District Court for the Eastern
District of Pennsylvania held that verbal directives
A Tactical Guide To Avoiding Construction Contract Disputes.

24 Copyright Wally Zimolong, Esquire, 2012.

to perform additional work from a person not authorized to approve extra work
are insufficient to support a claim for additional compensation related to that
work. In First General, the Court granted summary judgment in favor of the
defendant on a subcontractor’s claim that it was entitled to compensation for
additional work directed at the behest of defendant’s project superintendent.
The Court held that the only person from defendant that was authorized to direct
such work was the project manager and the directive in question came from the
project superintendent.

Therefore, the contract should be clear as to which persons are authorized to


direct the work. Contractors should follow directives only from those
authorized persons and when the directive comes from a non-authorized person
should confirm the directive from the person that is authorized.

2. When is the deadline for submitting claims?

Contracts will typically require written notification on claims for compensation


to be submitted within a certain time period. The time period can range from
between 7 to 21 days after a contractor is aware of an event giving rise to a
claim. Failure to provide notice within the prescribed time period may result in
a claim being barred. Therefore, contractors should be wary of any such notice
provisions and deadlines for making claims for changes.

3. How must the claims be submitted? Knowing how claims are submitted is
just as important as knowing when they must be made. Typically, the contract
will require claims to be made “in writing.” Contractors
should take care to learn what the written notice must include in order to
validate the claim. Moreover, to whom is the claim being made? Is it to the
architect, the construction manager, the owner, or some combination of them?

Of course there are exceptions to these rules, but why make claims for
entitlement more difficult to prove; especially, when the burden of proof in
demonstrating the exception applies is on the party claiming the exception.

You might also like