12/29/2017 How to Show the Critical Path in P6
Hey! It’s not working! I don’t see any red Critical Path
activities on my project. What gives?
Glad you asked. Maybe your Gantt chart looks like this instead.
Primavera P6, by default, uses Total Float to decide if an Activity is Critical or not.
Activities with a Total Float value of 0 (or less) usually show red on the Gantt. If
you have no red Activities, you may have a Must Finish By date set on your
project. If your project is finishing earlier than the Must Finish By deadline, then
you may not have any activities with 0 or less Float values which means there are
no Critical activities.
If that’s the case, tell P6 to show Critical Path by the Longest Path rather than by
Total Float.
You can always read more about the Critical Path vs Longest Path.
https://www.planacademy.com/show-critical-path-in-p6/ 2/5
12/29/2017 How to Show the Critical Path in P6
3. Turn On a Filter
Using a Filter can also be a quick and effective way to manifest your Critical Path.
Click the Filters button to turn on the Critical Path filter. This will show only the
Critical Activities. There’s also a filter for the Longest Path.
https://www.planacademy.com/show-critical-path-in-p6/ 3/5
12/29/2017 How to Show the Critical Path in P6
Once you have the log file open in Notepad, you’ll have to scroll down to the
section labeled “Exceptions”. But you should see in the log a list of your project’s
Critical Activities.
https://www.planacademy.com/show-critical-path-in-p6/ 4/5
12/29/2017 How to Show the Critical Path in P6
Which method works best for you in Primavera P6? Do you have your own
method for finding your project’s Critical Path? Drop us a line in the comments.