ID Task Name Duration Start Finish Predecessors

1 IMPLEMENTACION DEL AMBIENT55 days Mon 10/02/17 Fri 12/15/17


2 MESA DE CONCRETO 37 days Mon 10/02/17 Tue 11/21/17
3 MESA DE CONCRETO 23 days Mon 10/02/17 Wed 11/01/17
4 CONCRETO F'C=210 3 days Thu 10/26/17 Mon 10/30/17 6
5 ACERO CORRUGADO F' 10 days Mon 10/02/17 Fri 10/13/17
6 ENCOFRADO Y DESE 15 days Thu 10/05/17 Wed 10/25/17 5SS+3 days
7 CONSTRUCCION DE P 5 days Thu 10/26/17 Wed 11/01/17 4SS
8 REVESTIMIENTO 30 days Mon 10/02/17 Fri 11/10/17
9 TARRAJEO EN MESAS 5 days Fri 11/03/17 Thu 11/09/17 4FS+3 days
10 CUBIERTA DE GRANIT 30 days Mon 10/02/17 Fri 11/10/17 5SS
11 CERAMICA 5 days Wed 11/15/17 Tue 11/21/17
12 CERAMICA EN MESA 5 days Wed 11/15/17 Tue 11/21/17 9FS+3 days
13 CONTRAZOCALO DE 5 days Wed 11/15/17 Tue 11/21/17 12SS
14 CARPINTERIA METALICA Y HE 55 days Mon 10/02/17 Fri 12/15/17
15 VENTANAS 45 days Mon 10/16/17 Fri 12/15/17
16 VENTANA CON PERFI 45 days Mon 10/16/17 Fri 12/15/17 5SS+10 days
17 PUERTAS 45 days Mon 10/16/17 Fri 12/15/17
18 PUERTA DE VIDRIO TE 45 days Mon 10/16/17 Fri 12/15/17 5SS+10 days
19 CERRAJERIA 15 days Mon 10/02/17 Fri 10/20/17
20 CHAPA CERRRADURA 1 day Mon 10/16/17 Mon 10/16/17 18SS
21 PICAPORTE PARA SOB 1 day Mon 10/16/17 Mon 10/16/17 18SS
22 MANIJAS DE ACERO I 1 day Mon 10/16/17 Mon 10/16/17 18SS
23 TUBO METALICO 4"X4" 15 days Mon 10/02/17 Fri 10/20/17 5SS
Resource Names
ID Resource name Type Material label Initials Group Max.Units
Std.Rate Ovt.Rate Cost/Use Accrue At Base Calendar Code
Uid Task name Resource name Work Duration