1 IMPLEMENTACION DEL AMBIENT55 days Mon 10/02/17 Fri 12/15/17
2 MESA DE CONCRETO 37 days Mon 10/02/17 Tue 11/21/17 3 MESA DE CONCRETO 23 days Mon 10/02/17 Wed 11/01/17 4 CONCRETO F'C=210 3 days Thu 10/26/17 Mon 10/30/17 6 5 ACERO CORRUGADO F' 10 days Mon 10/02/17 Fri 10/13/17 6 ENCOFRADO Y DESE 15 days Thu 10/05/17 Wed 10/25/17 5SS+3 days 7 CONSTRUCCION DE P 5 days Thu 10/26/17 Wed 11/01/17 4SS 8 REVESTIMIENTO 30 days Mon 10/02/17 Fri 11/10/17 9 TARRAJEO EN MESAS 5 days Fri 11/03/17 Thu 11/09/17 4FS+3 days 10 CUBIERTA DE GRANIT 30 days Mon 10/02/17 Fri 11/10/17 5SS 11 CERAMICA 5 days Wed 11/15/17 Tue 11/21/17 12 CERAMICA EN MESA 5 days Wed 11/15/17 Tue 11/21/17 9FS+3 days 13 CONTRAZOCALO DE 5 days Wed 11/15/17 Tue 11/21/17 12SS 14 CARPINTERIA METALICA Y HE 55 days Mon 10/02/17 Fri 12/15/17 15 VENTANAS 45 days Mon 10/16/17 Fri 12/15/17 16 VENTANA CON PERFI 45 days Mon 10/16/17 Fri 12/15/17 5SS+10 days 17 PUERTAS 45 days Mon 10/16/17 Fri 12/15/17 18 PUERTA DE VIDRIO TE 45 days Mon 10/16/17 Fri 12/15/17 5SS+10 days 19 CERRAJERIA 15 days Mon 10/02/17 Fri 10/20/17 20 CHAPA CERRRADURA 1 day Mon 10/16/17 Mon 10/16/17 18SS 21 PICAPORTE PARA SOB 1 day Mon 10/16/17 Mon 10/16/17 18SS 22 MANIJAS DE ACERO I 1 day Mon 10/16/17 Mon 10/16/17 18SS 23 TUBO METALICO 4"X4" 15 days Mon 10/02/17 Fri 10/20/17 5SS Resource Names ID Resource name Type Material label Initials Group Max.Units Std.Rate Ovt.Rate Cost/Use Accrue At Base Calendar Code Uid Task name Resource name Work Duration