Professional Documents
Culture Documents
On
Submitted to
July 2009
Preamble
With due consideration of the fact of growing wind energy sector in India, a
Technical Working Group was formed by the Ministry of New and Renewable Energy
(MNRE), to formulate guidelines in addressing the technical issues/problems of
power evacuation and grid synchronization related to wind power projects.
The Technical Working Group met twice, first on19-01-2009, secondly on 17-04-2009
with regard to the requirement and development of grid code for wind power
generation in India. As a part of addressing the technical issues/problems of power
evacuation and grid synchronization related to wind power projects, the Technical
Working Group has awarded the task of “Developing of grid code for wind power
generation in India” to M/s Power Research and Development consultants (PRDC)
Pvt. Ltd, Bangalore. PRDC has formulated a draft report on the grid code for wind
power generation in India named as “Indian Wind Grid Code” which will be presented
before the committee.
Chapter 1
INTRODUCTION
The Indian Electricity Grid Code (IEGC) provides the technical rules to facilitate the
operation, maintenance, development and planning of electricity grid. The objective of
IEGC is to maintain safe, reliable and disciplined operation of power system. The IEGC
guidelines and standards are to be followed by the various agencies and participants
of the power grid.
Indian power generation sector is changing its nature like elsewhere in the world with
focus on environmental impacts of conventional sources and need to encourage
renewable energy. More and more renewable energy sources, mainly wind energy, are
being integrated into the grid. Today, wind generation, whose penetration is increasing
have significant impact on Indian power grid. The IEGC as well as the state grid codes
were originally developed considering the synchronous generators generally used in
conventional power plants. Wind turbine generators (WTG) do not have the same
characteristics as synchronous generators and hence a modification or change in the
grid code is necessary. Indian Wind Grid Code (IWGC) has been developed for the
reliable and secure operation of the wind farms and their integration into the Indian
electrical system. This grid code can be used in tandem with the IEGC/State Grid code
or the IEGC and state grid codes can be amended with the provisions.
1.1 Objective
The primary objective of IWGC is to establish the technical rules which all wind
farms must comply with in relation to their planning, connection and operation on
the Indian grid.
1.2 Scope
All grid connected wind farms and those who operate the associated transmission
system are required to abide by the principles defined in the IWGC in so far as they
apply to them. The IWGC (except sections 4.6.6 and 5.10) shall come into effect
from dd/mm/yyyy. The timeline for implementing fault ride through capability
(section 4.6.6) and wind energy forecasting (section 5.10) shall be specified
separately by the concerned authority taking into account the penetration levels of
wind energy, cost of implementation and tariff structure and their usefulness in
terms of grid management strategies.
1.4 Non-compliance
In case of a persistent non-compliance of any of the stipulations of the IWGC by a
constituent or an agency (other than RPC, RLDC and SLDC), the matter shall be
reported by any agency/RLDC to the Member Secretary, RPC or the designated
agency. The Member Secretary, RPC or the designated agency, shall verify and
take up the matter with the defaulting agency for expeditious termination of the
noncompliance. In case of inadequate response to the efforts made by the Member
Secretary, RPC, the non-compliance shall be reported to CERC/SERC.
CERC/SERC, in turn after due process, may order the defaulting agency for
compliance, failing which; the CERC/SERC may take appropriate action. RPC or
the designated agency shall maintain appropriate records of such violations. In
case of a non-compliance of any of the stipulations of the IWGC by RLDC/SLDC or
RPC, the matter shall be reported to the CERC / SERC.
1.5 Exemptions
Any exemption from provisions of IWGC shall become effective only after approval
of the CERC/ SERC, for which the agencies will have to file a petition in advance.
Chapter 2
Chapter 3
This chapter comprises various aspects of transmission system planning for wind
power evacuation. Planning policy, planning criteria for transmission lines evacuating
wind power are discussed in this chapter.
3.1 Introduction
i) The planning code specifies the policy and procedures to be applied in planning
of transmission lines for evacuating wind power.
ii) Role of various organizations in wind farm planning procedure will be same as
planning procedure for conventional generators.
iii) The planning procedure shall be governed by IEGC and “Electricity Act, 2003”
3.2 Objective
The planning code for transmission systems for wind power evacuation shall be
part of bigger plan that encompasses overall grid planning.
The objectives of the planning code are:
i) To specify the principles, procedures and criteria which shall be used in the
planning and development of the transmission system evacuating wind power.
ii) To promote co-ordination between wind farm developers, system operators and
regional constituents in any proposed development of wind farms.
iii) To provide methodology and information exchange amongst regional
constituents and agencies in planning of transmission system for evacuation of
wind power.
3.3 Scope
The planning code applies to transmission licensees, wind farms, SEBs,
CTU/STUs and Distribution licensees involved in developing the transmission/
evacuation system for wind power evacuation.
{Explanation:-
During peak loading condition all the generating units in a region will be
running at or near to its maximum capacity. Power flow through the
transmission network will be at higher level. Evacuation planning of wind
farm shall ensure that power injected by wind farm shall not cause any
overloading/ congestion in the network during peak load condition.
}
{Explanation:-
Here, the aim is to ensure that during system light load condition, all the
available wind power is evacuated.
}
{Explanation:-
Sometimes wind farms can have significant local load near the wind farms.
Here, the aim is to ensure that during local light load condition, all the
available wind power is evacuated to the system. It is to be noted that low
local load and low system load may not coincide in many parts of India due
to geographical diversity.
}
As the wind farms are distributed over large geographical area, the maximum
generation depends on geographical spread.
{Explanation:-
Normally in India, plant load factors of wind farms would lie in the range of 20-
30%.But, capacity factor may go up to 100% in a small wind farm. So, to have
economic viability, transmission planning of wind farms should consider
capacity factor as a parameter.
Wind turbines in a smaller wind farm face similar wind speeds as they are
spread over smaller geographical area. Output of these wind farms can reach
100% of installed capacity during high wind season. As the wind farm size
grows, capacity factor of wind farm decreases due to large geographical
spread.
Normally, higher capacity wind farms are connected at higher voltage levels.
Here, voltage level at the grid connection point is chosen as criteria because
power system behavior can be better categorized with voltage levels than
power.
100%, 90%, 80% values are based on consultation experience and also
available data from the literature.
}
3.5.1.2 Generally there shall be no restriction on the wind farm size and the voltage
level at which it shall be connected to the grid, provided all the requirements in
this IWGC are fulfilled.
{Explanation:-
The relation between evacuating power and voltage level depends on many
parameters, such as:
- Local network and local load
This relation can vary from one area to other. Providing a definite guideline on
evacuating power vs. voltage relationship can restrict setting up of new wind
farms in some areas where wind power can be evacuated reliably in spite of
violating the “evacuating power and voltage” guideline.
}
3.5.1.3 Lower ambient temperatures which are generally associated with higher wind
velocities may be considered for increasing the loadability of transmission
systems planned for evacuating wind power in cases where other alternatives
are prohibitively expensive affecting viability of the renewable energy project.
IEEE Std 738-1993 “IEEE Standard for Calculating the Current-Temperature
Relationship of Bare Overhead Conductors Contingency study " shall be
followed while calculating line loadability with respect to wind speed. A sample
calculation of transmission line loading with respect to wind speed is given in
Appendix B. In Appendix B transmission line loading limits with increasing wind
speeds are given for Zebra and Panther conductors.
3.5.2.2 The upstream network connected from grid substation shall be capable of
withstanding and be secured against the following contingency outages without
necessitating load shedding or rescheduling of generation during steady state
operation as defined in IEGC and State Grid codes
a) Outage of a 132 kV D/C line or,
3.5.3 Any one of the events mentioned in the adequacy and contingency study shall
not cause:
i) Unacceptable high or low voltage
ii) Prolonged operation of the system frequency below and above specified
limits.
iii) System instability
iv) Unacceptable overloading of transmission system elements.
{Explanation: -
As per Indian state grid codes, power factor of conventional generators shall lie
between 0.95 leading to 0.85 lagging. Wind grid codes of UK, Germany ask for
0.95 leading to 0.95 lagging power factor. Canadian grid code asks for 0.95
leading to 0.90 lagging power factor.
So, it can be seen than grid codes mainly differ on the lagging power factor
limit. In India, reactive power injection from wind farms is least expected. So, in
IWGC the power factor range is limited between 0.95 leading to 0.95 lagging.
}
3.5.4.2 Planning studies for power evacuation from wind farms through long distance
transmission lines shall include voltage stability studies to investigate the
requirements of dynamic VAr compensation to prevent voltage collapse during
high wind generation. The modeling of WTG shall be based on the actual type
planned to be installed in the area by the developer of wind farm.
Chapter 4
4.1 Introduction
The connection code for wind farms specify the minimum technical and design
criteria which shall be satisfied by any wind farms seeking connection to
ISTSs/STSs/STUs. This shall be pre-requisite for the establishment of an
agreed connection.
4.2 Objective
The objective of the connection code is to ensure that any new or modified
wind farm connections, when established, shall neither suffer unacceptable
effects due to its connections to ISTS/STS nor impose unacceptable effects on
the system or the grid.
4.3 Scope
The connection code applies to all wind farms connected to the grid at any
voltage levels. The wind farms shall satisfy all requirements of connection code.
Voltage (kV)
% Limit of
Nominal Maximum Minimum
variation
400 +5% to -10% 420 360
220 +11% to -9% 245 200
132 +10% to -9% 145 120
110 +10% to -12.5% 121 96.25
66 +10% to -9% 72.5 60
33 +5% to -10% 34.65 29.7
{Explanation: -
The minimum and maximum voltages for 400, 220 and 132 kV buses are taken
from IEGC. The minimum and maximum voltages for 110, 66 and 33 kV buses
are taken from the planning criteria of Revised TNEGC(page 24) “The
permissible voltage at the point of commencement of supply during the steady
state operation is +5% / -10% for system upto 33 kV voltage level…” .
}
4.6.1.2 Resonance
Wind farms shall avoid introducing undue resonance leading to over voltage at
grid connection point. Of particular concerns are torsional interaction, self
excitation of induction machines, transformer ferro-resonance, and the resonant
effects of capacitor additions. Wind farms connected to the grid through series
compensated transmission lines shall investigate the possibility of sub-
synchronous resonance due to torsional interactions.
{Explanation: -
CEA grid standard is followed
}
Voltage (kV)
420 245 145 121
leading lagging
(absorption) (injection)
Power Factor
Figure 4.1: Voltage vs. power factor characteristics of wind farms connected
above 66 kV
{Explanation: -
The voltage vs. power characteristic is based on the principle that wind farms
should not draw/inject large reactive power at lower/higher system voltages. In
general, the allowable power factor range of wind farms is 0.95 lagging to
leading. But, a comparatively higher leading power factor requirement is placed
when the system voltage is lower. Similarly, a lower lagging power factor is
required when the system voltage is higher. In other words, reactive power
drawl/injection shall be minimized at lower/higher voltages. This is depicted in
Figure 4.1. The Voltage vs. power factor characteristics in IWGC is derived
from German grid code of VE-T.
{Explanation: -
The frequency range of 47.5 to 51.5 Hz is also proposed in the draft IS standard
on “Wind turbines - Design requirements”, which is under finalization by BIS -
Wind turbine Sectional Committee – ET 42. Hence it is suggested that the upper
limit may be restricted to 47.5 - 51.5 Hz.
}
{Explanation: -
During system operations, grid operator in extreme conditions may ask the
wind farms to limit the power injection into the grid. The request from grid
cooperator shall be under the conditions elaborated in IWGC section 5.2.6. and
5.2.7. Wind farms connected at 66 kV and above shall be able to respond to
system operator’s request. }
4.6.4.2 Active power output of wind farms shall vary with respect to frequency
as shown in Figure 4.2.
50%
0%
47.5 50.3 51.5 Hz
Frequency
Figure 4.2: Variation of active power output of wind farms with respect to
frequency of wind farm
{Explanation: -
The objective is to utilize wind power at its maximum. This characteristic is
derived from Irish grid code.
The upper limit of 50.3 is derived from recent amendment of IEGC in 2009.
}
4.6.5.2 Wind farms connected below 66 kV can get disconnected from the grid during
system faults (fault ride through capability is not mandatory).
{Explanation: -
Normally, wind farms connected below 66 kV are smaller in size. The
requirement of fault ride through can affect the economics of smaller wind
farms at present scenario. }
4.6.6 Situations where wind turbines must remain connected to the grid
4.6.6.1 Wind farms shall remain connected to the grid during normal system
operation.
4.6.6.2 Wind farms connected at 66 kV and above shall remain connected to the grid
during system fault. Reactive power compensation equipment must also remain
connected during system fault.
Wind farms connected at 66 kV and above shall have the operating region as
shown in Figure 4.3 during system faults. Wind farms can be disconnected if
the operating point falls below the line in Figure 4.3.
During fault ride through, the WTGs in the wind farm shall have the capability to
meet the following requirements:
a) Shall minimize the reactive power drawl from the grid.
b) The wind turbine generators shall provide active power in proportion to
retained grid voltage as soon as the fault is cleared.
Vpf
Vf
0 T 3000
Time (ms)
Where,
Vf = 15% of Nominal System voltage
Vpf = Minimum voltages mentioned in IWGC section 4.6.1.1
The fault clearing time for various system nominal voltage levels is given in the
following Table 4.3:
Higher fault clearance times for the wind farms may be agreed to with the
SEBs/STUs. In such case, the SEBs/STUs shall specify to the wind farm
operators the required opening times of circuit breakers at various locations.
{Explanation: -
With increasing penetration, wind farms will have major impact in Indian power
system. So, the behavior of wind farms should tend to be same as conventional
power plants. Staying connected during system fault is a step towards that
direction. Today’s wind turbine technology has matured enough to provide this
requirement. All the international grid codes demand this criterion from wind
farms. The Fault ride through requirements in IWGC resembles to international
practice. The fault clearing time is taken from IEGC, state grid codes.
However, it may be advised that this facility may be provided for the future wind
farms development with due consideration of the cost impact.
}
{Explanation: -
In India, the occurrence of faults in sub-transmission system is frequent. Hence,
the wind turbines may be thermally stressed. In such cases the machines shall
withstand the repetitive faults or shall disconnect from the grid. Similar
requirement is presented in Danish grid code.
}
4.6.8 Protection
All the grid connected wind farms must have protection systems to protect the
wind farm equipment as well as the grid, such that no part system shall remain
unprotected during faults.
4.6.8.1 The protection schemes for the wind farms shall be developed in coordination
with the grid protection schemes and this shall be carried out keeping in mind
the wind turbine manufacturing capabilities such as fault ride through capability,
voltage and frequency operational ranges etc.
4.6.8.2 The faults on the wind farm and/or its apparatus shall be cleared without any
time delay and in any event shall be cleared within in the fault clearing times
mentioned in IWGC section-4.6.6.3 with reliability, selectivity and sensitivity.
The protection co-ordination for the wind farms shall be monitored by the
SEBs/STUs/ISTSs.
4.6.8.3 The following are the minimum protection schemes that shall be installed for
wind farm protection:
i) under/over voltage protection
ii) under/over frequency protection
iii) over current and earth fault protection
iv) load unbalance (negative sequence) protection
v) differential protection for the grid connecting transformer
vi) capacitor bank protection
vii) tele-protection channels (for use with distance protection) between the grid
connection point circuit breaker and user connection point circuit
breaker
4.6.8.5 The protection requirements for the wind farm substation and for the
transmission system evacuating the wind power shall be as per the
specifications of STUs/SEBs/ISTSs.
4.6.11.2 Earthing
Wind turbine grounding systems shall follow the recommendations of IEC TR
61400-24 (section 9).
{Explanation: -
The purpose of prohibiting delta connection on the high voltage side of the grid
connecting transformer is to block the harmonics current and to detect the earth
faults on the grid side.
}
Chapter 5
The operating code specifies the operating conditions that the wind farms shall comply
with for safety and reliable operation of the grid and shall be applicable to the wind
farms connected to the grid, and the SEBs/STUs/SSLDCs/SLDCs/RLDCs.
Voltage (kV)
% Limit of
Nominal Maximum Minimum
variation
400 +5% to -10% 420 360
220 +11% to -9% 245 200
132 +10% to -9% 145 120
110 +10% to -12.5% 121 96.25
66 +10% to -9% 72.5 60
33 +5% to -10% 34.65 29.7
{Explanation: -
This requirement is as mentioned in IEGC. This requirement can be met by all
the WTGs.
}
5.2.2.2 The wind farm operator shall endeavor to minimize the VAr drawl from the grid
when the voltage at the grid connection point is below 95% of rated, and shall
not supply to the grid VAr when the voltage is above 105%. As such to control
the VAr exchange, the wind farm operator shall provide the VAr compensation
or request SLDC/RLDC to change the taps of the grid connecting transformer.
{Explanation: -
The WTG manufacture provides VAr compensation facility for each WTG
(switch able capacitor banks). So using this facility the wind farm operator can
control the VAr exchange depending on the grid connection point voltage.
Varying the grid connecting transformer taps also controls the VAr exchange
with the grid.
}
5.2.2.3 The charge/payment for VAr exchange from the grid shall be at nominal paise
per kVArh as specified by CERC/SERC and the transaction will be between the
wind farm owner and the state utility.
{Explanation: -
Although not uniform, all the SERCs have fixed a nominal charge for the VAR
drawl by the WTG from the grid. For e.g., in Tamil Nadu, Rs 0.25/kVArh if the
ratio of kVArh drawn to KWh exported is upto 10%and Rs0.50/ kVArh for more
than 10%.
}
5.2.2.4 Not withstanding the above, SSLDC/SLDC/RLDC may direct a wind farm to
curtail its VAr drawl/injection in case the security of grid or safety of any
equipment is endangered.
{Explanation: -
Ramp control facility regulates the active power generated from the WTG and
also minimizes the variations in the generated power that may arise because of
wind variations. The performance is similar to that of governor control in case of
synchronous machines The system operator may ask the wind farm operator to
curtail the generated power due to increasing wind speed, turbines returning to
service after some outage or to increase the generated power due to increase
in system demand etc.
}
5.2.3.1 The WTGs shall have two ramp rates
a) 10 minute maximum ramp rate
b) 1 minute maximum ramp rate
5.2.3.2 The ramp rate limits shall be applicable for all ranges of operation including
start up, normal operation and shut down of the WTGs. An exception to this can
be situations where there is fall in wind speeds.
5.2.3.3 The wind farm operator shall inform SLDC/RLDC, the maximum and minimum
ramp rates of the WTGs at the time of commissioning. Any changes made to
the ramp rate limits shall be informed to the SLDC/RLDC and shall be done as
per their instructions.
5.2.3.4 Ramp limits for wind farms at the grid connection point shall be as given below
(Table 5.2) depending on the wind farm installed capacity.
{Explanation: -
This is in line with international practice. As per Irish wind grid code grid the
ramp rate averaged over 1 minute should not exceed 3 times the average ramp
rate over 10 minutes.
}
5.2.3.5 The ramping up/down of the wind power generation shall be done by the wind
farm operator as instructed by the system operator. On case to case basis, the
maximum ramp limits mentioned in IWGC section 5.2.3.4 may be changed on
the mutual consent between the system operator and the wind farm operator
provided the WTGs ramp limits are not exceeded.
{Explanation: -
Power quality in relation to a wind turbine describes the influence of a wind
turbine on the power and voltage quality of the grid. The main influences of
wind turbines on the grid concerning power quality are the voltage flicker,
harmonics (for wind turbines with power electronic equipment), voltage
changes & fluctuations and the in-rush currents.
}
5.2.4.1Voltage flicker
The IEC 61000-4-15 (IEC, 1997) and IEC 61000-4-15 (IEC, 2003) standards
shall be followed with respect to voltage flicker limits and measurement
techniques.
{Explanation: -
Flicker means the flickering of light caused by fluctuations of the mains voltage,
which can cause distortions or inconvenience to people as well as other
electrical consumers. The flicker measurement is based on measurements of
three instantaneous phase voltages and currents, which are followed by an
analytical determination of Pst (short-term flicker disturbance factor) for different
grid impedance angles.
}
5.2.4.2 Harmonics
Harmonics measurements shall be taken in accordance with methodologies of
IEC 61400-21 or IEEE STD 519-1992. The harmonic content at the grid
connection point shall be as follows:
{Explanation: -
According to the guidelines (IEC 61400-21), harmonic measurements are not
required for fixed-speed wind turbines (Type A), where the induction generator
is directly connected to the grid. Harmonic measurements are required only for
variable-speed turbines with electronic power converters (Types C and D).
}
n = 40
Vn2
VTHD = ∑
n = 2 V1
2
×100
The maximum limits of VTHD shall be as per the following Table 5.3:
I n2
ITHD = ∑ 2 ×100
I1
Where In: nth harmonic of current
I1: fundamental frequency (50 Hz) current
The maximum limits of ITHD shall be as per the following Table 5.4:
{Explanation: -
The limits for VTHD are taken from CEA standards (Grid standards)
Regulations-2006 and the limits for ITHD are taken from IEEE STD-519,
1992.
}
{Explanation: -
The voltage fluctuations in a wind farm can occur because of the switching
operations (capacitor banks, WTG start/stop), inrush currents during WTG
starting etc. Such voltage fluctuations shall be limited to the values mentioned
in the above section.
}
{Explanation: -
This is to necessitate the wind farm owner’s control over the WTG operation.
The system operator may request the wind farm operator to start/stop the
WTGs as the situation demands. So, the WTGs shall respond to the start/stop
command send by wind farm operator without any time delay.
}
5.2.5.2 During the wind generator start-up, the wind farm operator shall ensure that the
reactive power drawl (inrush currents incase of induction generators) shall not
affect the grid performance.
{Explanation: -
Fixed speed WTGs directly connected to the grid directly draws huge inrush
current during starting. This may cause voltage fluctuations and flickering at the
grid connection point.
}
5.2.5.3 The wind farm operator has to ensure that the start up and stopping of the
WTGs comply with the voltage quality requirements.
{Explanation: -
Because, the switching operations and the inrush currents may cause
harmonics, voltage flicker and voltage fluctuations.
}
5.2.5.4 It is recommended that all WTGs in the wind farm shall not start and /or stop
simultaneously owing to high windy conditions.
{Explanation: -
Simultaneous starting/stopping of the WTGs can cause power quality problems.
Also, it can cause large changes in the power injected into the grid.
}
{Explanation: -
Taking into consideration the zero fuel costs and environmental issues, it is
recommended to evacuate all the available wind generated power to the grid.
During transmission congestion, the conventional generation shall be backed
down. Under extreme conditions, when the wind power generated exceeds the
system demand and when the local voltage limits are violated, it shall be the
responsibility of the wind farm operator to back down sufficient amount of the
wind generation, to maintain system security. This shall be done as per the
system operator’s instructions.
}
{Explanation: -
The wind farms shall be operated as an integrated part of the grid. The wind
farm operator shall operate it deriving maximum benefits from the integrated
operation. System security shall not be endangered because of the
substandard/inefficient operational practices of the wind farms. The
contingencies (loss of any of the wind farm equipment, faults within the wind
farms) shall be attended by the wind farm operator, so that there is minimal
damage to the wind farm equipment as well as the grid. For contingencies in
the vicinity of the wind farm, the wind farm operator shall protect the wind farm
equipment from any imminent damage and shall take necessary measures to
mitigate the contingency. The measures can be riding through the fault or
ramping down the generation till the contingency has been remove, running in
island mode to meet the local demand etc. }
{Explanation: -
The demand estimation for operational purposes is done on a
daily/weekly/monthly basis. The wind forecasting data obtained by the day
ahead forecasting can be useful in meeting the estimated demand. The hourly
forecast data can also be used as a part of the scheduling and dispatching.
}
{Explanation: -
In a power system wind power generation profile and system demand may not
follow the same pattern. For e.g. system demand may be high when there is
least possible wind generation. So, the demand management procedure shall
consider the variations in the wind generation (can be known from the wind
forecast data) to maintain power balance in system operation.
}
{Explanation: -
Periodic reports issued by RLDC give the description of the grid performance
over a week/month. Wind generation in that region can also be included in the
periodic reports, because that gives a picture of wind energy profile, demand
met with wind generated power and also can be useful for evolving good
operational practices in the future.
}
{Explanation: -
Wind farms are through their communication interface shall exchange the
information in relation to operations and/or events with SLDC/RLDC. It is the
mandatory built-in hierarchical function of the RLDC and Regional constituents
including the wind farms, to facilitate quick transfer of information to operational
staff for decision making and actions to be sought.
}.
{Explanation: -
The outage schedules prepared by the RPC Secretariat based on the inputs
from all the SEBs/STUs, CTU and ISGS. Wind farms shall also submit their
outage schedule(s), if any, to the concerned SEB/STU. The wind farm operator
shall also be aware of the planned/maintenance outages taking place around
the vicinity of the wind farm, so that these outages do not have any effect on
the wind power generation.
}
The wind energy forecasting system shall forecast power based on wind flow
data at the following time intervals:
i) Day ahead forecast: Wind power forecast with an interval of one hour for
the next 24 hours for the aggregate wind farms.
ii) Hourly forecast: Wind power forecast with a frequency of one hour and
interval of 30 minutes for the next 3 hours for the aggregate wind
farms.
The day ahead forecasting shall be done to assess the probable wind energy
that can be scheduled for the next day. The hourly forecast is necessary to
minimize the forecasting error that can occur in the day ahead forecasting of
wind power. The SSLDC/SLDC/RLDC shall receive the forecasted wind power
data which shall be used for scheduling.
Wind energy forecasting system shall be implemented within the time specified
by the concerned authority with due consideration of penetration level, cost and
tariff.
{Explanation: -
Wind energy forecast corresponds to an estimate of the expected amount of
power production from wind farms over the forecast period. Evacuation of large
amounts of energy from intermittent sources like wind has considerable effect
on the generation-demand balance of a power system. So, for reliable system
operation wind energy forecasting is necessary for larger wind farms. As the
penetration level increases, it becomes difficult for the system operator to
maintain the correct generation mix. As the system operator is responsible for
maintaining balance between generation and demand, he should know in
advance the amount of wind generated power that can be scheduled and
dispatched from the wind farm, much like the conventional generation
scheduling and dispatching.}
5.10.2 Scheduling
The scheduling of other generators by the SLDC/RLDC shall consider the
available wind generation for the duration. While scheduling generating stations
in a region, system operator shall aim at utilizing available wind energy fully and
the Merit Order dispatch shall not be applied for wind farms. The wind farms
shall be treated as over-flowing reservoir/run of the river hydro power plants as
defined in Tamil Nadu Electricity Grid Code.
{Explanation: -
Keeping a certain amount of energy as spinning reserve/backup generation is
necessary to ensure that sufficient generation can maintained to meet the
demand incase of an unexpected loss of wind generation. Also to meet the
uncertainty in wind energy forecasting (forecasting error) the spinning reserve/
backup generation is necessary.}
APPENDIX A
Planning Data (Wind farm)
The following data are to be made available to the planning wing of CTU/STU
by all the wind farms
Rated slip
Magnetizing reactance of generator p.u
Stator leakage reactance p.u
Stator reactance p.u
Rotor leakage reactance p.u
Rotor reactance p.u
Magnitude of inrush current Ampere
Time duration of inrush current s
In addition to the above mentioned data, the wind farm owner has to provide
dynamic model of wind farm. If all the WTGs in the wind farm are not identical,
the model shall incorporate separate modules to represent each type of WTG.
Appropriate data and parameter values must be provided for each model. The
dynamic model must represent the features and phenomena likely to be
relevant to angular and Voltage stability. These features include but may not be
limited to:
i) Generator model
ii) Blade pitch control
iii) Model of drive train
iv) Model of converter (if any)
APPENDIX B
Conductor ampacity calculation and variation with wind speed
B.2 Calculation: -
The natural convection heat loss is calculated by means of equation (1):
Convected heat loss, qc = 0.283ρ 0.5
f D
0.75
(Tc − Ta )1.25 W/ft ---------------------------- (1)
Where,
Conductor diameter, D =1.108 in
Ambient temperature, Ta =40o C
Conductor temperature, Tc =65o C
Air film temperature (°C) T film = (Tc + Ta)/2 = 52.5 °C
Density of air, ρ f =0.06775 lb/ft3 (from Table1 of IEEE Std. 738 at 52.5 o C)
Therefore, substituting the above values in equation (1) gives, qc = 4.48 W/ft
Since the wind velocity is greater than 0 ft/s, the forced convection heat loss for
perpendicular wind is calculated according to both equations (2) and (3) corrected
for wind direction, and compared to the natural convection heat loss. The larger of
the heat losses due to both natural and forced convection is then used in
calculating the thermal rating:
D ρ f VW
0.52
qc1 = 1.01 + 0.371 k f (Tc − Ta ) ---------------------------- (2)
µf
0.6
D ρ f VW
qc 2 = 0.1695
µf k f (Tc − Ta ) ----------------------------- (3)
Where,
D = 1.108 in
Velocity of air stream, VW = (2 ft/s) · 3600 (s/h)
Tc =65o C
Ta =40o C
Absolute viscosity of air,
µf = 0.04775 lb/h (ft) (Table1 of IEEE Std. 738 at 52.5 °C)
Density of air, ρ f =0.06775 lb/ft3 (from Table1 of IEEE Std. 738 at 52.5 o C)
Thermal conductivity of air at temperature,
kf = 0.00858 W/ft (°C) (from Table1 of IEEE Std. 738 a t 52.5 °C)
Therefore, substituting the above values in equation (2) and (3), gives
qc1 = 10.421 W/ft
qc2 = 9.837 W/ft
Since the wind is perpendicular to the axis of the conductor, the wind direction
multiplier, Kangle, is 1.0, and the forced convection heat loss is greater than the
natural convection heat loss. Therefore, the forced convection heat loss will be
used in the calculation of thermal rating.
(T + 273) 4 (T + 273) 4
qr = 0.138 Dε c −
a
----------------------------- (4)
100 100
Where,
D = 1.108 in
∈ = 0.5
Tc = 65 °C
Ta = 40 °C
Radiated heat loss, qr = 2.64 W/ft of conductor
Where,
Solar absorptivity, α = 0.5
Projected area of conductor, A' =D/2= 0.092 ft
R(75) − R(20)
R(65)=R(20)+ ( 65 − 20 )
75 − 20
= 2.313 x 10–5 Ω /ft
qc + qr − qs
The steady state thermal loading is given by, I = ---------------------- (7)
R ( 65 )
Further, the relation between conductor ampacity and ambient temperature mentioned in
CBIP Technical Report 77 of May 1991 is furnished in Table B2 [2].
References:
[1] IEEE Std 738-1993 “IEEE Standard for Calculating the Current-Temperature
Relationship of Bare Overhead Conductors”, by Transmission and Distribution
Committee of the IEEE Power Engineering Society.
[2] S.K.Sonee, “Assessment of Transfer Capability in the Indian Bulk Electric
Power System”, GSIOAR07, 8th – 9th August 2007, IT-BHU, Varanasi.