Professional Documents
Culture Documents
1 Startup Procedures
a. General
CAUTION
Check location, availability and operability of firewater monitors, eyewashes, safety showers, fire
extinguishers, stretchers, first aid kits, H2S monitors, gas masks, air packs, etc.
CAUTION
f. Air Coolers
i. Fired Heaters
2. Testing
3. Duration of Test
k. Records
2.1.1.2 Flushing
a. Steam Piping
b. Process Lines
CAUTION
Remove temporary strainers at the end of flushing if no longer needed (compressor suction strainers).
CAUTION
a. Control Loops
d. Level Instruments
h. Control Valves
i. Thermowells
k. Gas Detectors
l. Analyzers
2.1.2.2 Pumps
a. Centrifugal Pumps
b. Reciprocating Pumps
c. Special Pumps
2.1.2.3 Compressors
a. Purpose
c. Tube Protection
d. Dry-out Procedure
2.1.2.6 Purging
a. Steam-Out
CAUTION
Ensure that a top vent to the atmosphere is open during steamout to avoid pulling a vacuum. do not
open vent to flare as an explosive mixture of hydrocarbons and air may be formed if hydrocarbons
are admitted back from the flare.
CAUTION
b. Gas Purging
1. Flow Purge
By repeating pressuring-and-venting,
oxygen can be reduced progressively.
Dead air spaces in vessels, equipment,
and piping can be purged by pressuring to
about 50 psig and depressurizing to 2~3
psig. Normally, three (3) times is
sufficient. Oxygen content should be
checked after the second depressuring,
and each one after until oxygen content is
1 mol. % or less.
CAUTION
Note that preparation for gas plant start-up (if the Delayed coker unit DCU have a gas plant) should
be underway at the same time DCU is starting up. Full coordination among operating teams is
necessary to assure continuity and to avoid unnecessary delays.
CAUTION
2.1.3.6 Ensure that all utility stations are ready for use.
2.1.3.7 Check to make sure that the flare system is
commissioned and ready for operation.
2.1.3.10 Ensure that all auto modes and cascade controls are
properly activated and functioning at start-up.
2.1.3.11 Ensure that all alarm and trip settings are correct and
all alarms are active and will function properly.
2.1.3.14 Crack vessel drains, pump case drains and other low
point drains in preparation for draining steam
condensate.
Normal start-up DCU take place when the upstream Crude Unit
is already onstream and Vacuum Residue is available to feed the
DCU. The following downstream processing units should also
be onstream to receive and process the DCU products, typically:
Stabilizing Operation
CAUTION
Close all control valves and bypasses, replace any blind flanges or remove plugs. Battery Limit
valves are to be closed.
CAUTION
CAUTION
Pay attention to the low molecular weight of the natural gas during compressor start-up. Inspect for
instability in compressor.
CAUTION
CAUTION
All this procedure have to be taken as example because can change according with unit
design.
CAUTION
This step may precede step 2.1.4.7 to prevent pump cavitation as the sysytem is being heated up.
CAUTION
CAUTION
Do not raise the heater outlet temperature above 700oF.
CAUTION
Do not raise the heater outlet temperature
above 700°F. Temperatures to be controlled
TIC on the heater passes.
CAUTION
Assure proper warm-up of the coke drums during start-up to minimize thermal fatigue that may lead
to potential bulging/cracking of shell/shell welds, leak and fire.
CAUTION