Professional Documents
Culture Documents
DOCUMENTATION
Order No. : PR-17440 / 602083
Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank : 39,000m
Deck No. : 4694 / 4695
1 General Operating
2 Water Test
3 Sealing
4 Project Drawing
5 Part List
6 Installation Manual
7 Type Sheets
8 Calculations
1. General
The object of the VACONODECK is to minimise the loss through evaporation of the stored
product. Though numerous settlings will not damage the VACONODECK, in order to
minimise gas losses, this should be avoided as much as possible. A deck that is not
floating on the liquid is effectively useless.
2. Particular Recommendations
The most frequent causes of damage to the VACONODECK are found to have been
caused through the overfilling of a tank. It is therefore to be recommended that overfilling
of a tank be prevented through the use of any one of the numerous overfilling protection
devices available on the market.
Inlet Rate
When tanks are filled at a high rate of inlet there remains the possibility of damage to the
VACONODECK due to the large amount of turbulence caused.
Before installing the VACONODECK it should be confirmed by the tank operator that the
inlet velocity does not exceed 1,0 m/sec. A diffuser should otherwise be installed to reduce
the inlet rate to this figure.
Important note:
The diffuser is not suitable for or designed to allow purging of the feed line with (nitrogen)
gas. Such an action could lead to damage of the floating deck.
If a tank has a mixer installed this mixer should be coupled to a level switch.
By the propeller type of mixer the minimum level whereby it should be switched on is when
the liquid level is 2 mtrs over the maximum height of the propeller thereby assuring no
possible contact, and thereby no damage, to the VACONODECK.
By the use of the jet mixer type the liquid level in the tank should be at least 2,5 mtrs
above the height of the jet mixer nozzle thereby avoiding the possibility of a jet stream
hitting the floats or deck sheets of the VACONODECK etc. causing possible damage.
Important note:
We would advise that where a mixer unit exists or is to be installed in a tank with a
VACONODECK VACONO should firstly be consulted in order to advise in each instance at
what liquid height the mixer may be switched on safely!
Floating Suctions of aluminium or steel design are designed bearing in mind the specific
gravity of the product stored. Should the tank be filled with water (S.G. 1.0) or a heavier
product than foreseen this would lead to an increase in the floatability of the floating
suction unit thereby increasing the pressure to the underside of the VACONODECK unit
(to which it is attached by means of guide rails) and thereby leading to the almost certain
result of damage being caused. Therefore should it be decided to fill a tank with water for
cleaning or testing purposes it is important that the floating suction unit's floats be
removed. Further should it be decided to store another product in the tank we should firstly
be consulted in order that we may determine whether the new product and it's specific
gravity will affect the floatability of the floating suction unit to an extent whereby the deck
may be damaged.
Tank Welds
In order to avoid mechanical failure of the deck seal all tank wall welds should be clean
and smooth without burrs and sharp edges.
Water test
If such is to be undertaken please refer to the attached instructions „Procedure for Water
Testing of VACONODECK Internal Aluminium Floating Covers (IFR)“ thereto.
Antirotation System
The antirotation cables should never be slack and always under tension. This should be
checked from time to time and where necessary the cables should be retensioned .
Antistatic System
The earthing cables are attached to the VACONODECK and the tank roof manhole and
they should be checked from time to time to ensure that they are still safely connected.
During the tank inspection, cleaning etc. local safety regulations shall be observed.
In tank cleaning operations where water is used, spraying of water on the VACONODECK
topside surface should be avoided as much as possible to avoid increased weight and
stress to the deck sheets profiles and legs.
Tank cleaning systems (such as Butterworth, Blabo, Prosser, Scanjet etc.) that are
operated from the tank roof are not to be used in conjunction with a VACONODECK.
By use of stream to clean tank direct spraying on the deck seals should be avoided.
When carrying out repairs in the tank 'spark free' tools should be used and dropping of
tools onto the VACONODECK or scratching the zinc plated surfaces should be avoided.
Where ‘Hanging decks’ are to be installed the following points are to be noted:
When the VACONODECK is in the hanging position it is only to be walked on by one
person. In the hanging state (during tank modification, cleaning, etc.) no person should be
on top of the deck whilst work is being carried out by others on the underside.
Working on top and below the deck is only permitted when the supplied leg
supports have been installed.
The internal floating roof shall be designed to safely support at least two men
( 2,2kN = 500 lbf over 0,1 sqm = 1 sqft ) walking anywhere on the roof while
it is floating or resting on its supports without damaging the floating roof and without
allowing product on the roof. If specified by the purchaser, the concentrated load
design criteria may be modified for roofs less than 9 m ( 30ft. ) diameter ( where
internal floating roofs may become unstable ), to account for access needs, and
expected concentrated live loads.
Customer:________________________________________________________________
Project Description:________________________________________________________
Project Number:___________
VACONODECK Number_____________ for the above project has been assembled and
installed in accordance with the manufactures installation instructions and drawings. All
workmanship has been checked by the customers representative and found to be acceptable.
_________________________________________________________________________
Customer acceptance:
Signature:___________________________________ Date:________________________
____________________________________________________________________
Contractor: Upon acceptance by the customer please return a copy of this report by fax to:
Aluminium Rheinfelden
VACONO DEPT
FAX NO. 07623 / 93 547
VD-E.10/06.05.2010/B 1
MAINTENANCE
The antirotation cables should never be slack and always under tension. This should be checked from time
to time and where necessary the cables should be retensioned.
The earthing cables are attached to the VACONODECK and the tank roof manhole and they should be
checked from time to time to ensure that they are still safely connected.
During the tank inspection, cleaning etc. local safety regulations shall be observed.
In tank cleaning operations where water is used, spraying of water on the VACONODECK topside surface
should be avoided as much as possible to avoid increased weight and stress to the deck sheets profiles
and legs.
Tank cleaning systems (such as Butterworth, Blabo, Prosser, Scanjet etc.) that are operated from the tank
roof are not to be used in conjunction with a VACONODECK.
By use of stream to clean tank direct spraying on the deck seals should be avoided.
When carrying out repairs in the tank ‘spark free’ tools should be used and dropping of tools onto the
VACONODECK or scratching the zinc plated surfaces should be avoided.
Where ‘Hanging decks’ are to be installed the following points are to be noted:
When the VACONODECK is in the hanging position it is only to be walked on by one person. In the
hanging state (during tank modification, cleaning, etc.) no person should be on top of the deck whilst work
is being carried out by others on the underside.
Working on top and below the deck is only permitted when the supplied leg supports have been
installed.
REPAIR
In case of one or more parts of the Vaconodome will be damaged, our main office in Rheinfelden
(Germany) shall immediately be informed.
VD-E.10/06.05.2010/B 2
VACONODECK & VACONODOME
Storage:
All materials have to be stored dry to avoid fluid retention between the materials.
Especially sealing materials have to be kept away from sunlight.
Transportation:
Transportation has to be done always with special care. Aluminium parts are very sensitive
against damage. Special care has to be taken on VACONODOME sheets and VACONODECK
floats and sheets because of the thin-walled materials.
VACONODOME materials are packed by VACONO onto pallets, transport frames and into
wooden boxes. All packages can be transported by usual fork lifters or hand lifts. The maximum
gross weight of each package does not exceed 2,2 to.
VACONODECK materials are generally delivered partly packed and partly unpacked. Unpacked
materials like floats, channels, butt straps have to be loaded/unloaded by hand for which normally
3-4 working men are working 1-2 hours (depends on size and quality of VACONODECK(s).
1/1
TOOL AND PROTECTIVE CLOTHING LIST FOR
VACONODECK - INSTALLATION
PROTECTIVE CLOTHING :
1.) Overall
2.) Protective boots
3.) Gloves
4.) Dust mask
1. General
The relevant API 650 app. H. paragraphs H.6.6 describes in general how the water test
should be carried out and which risks regarding corrosion are to be seen.
1. Water which is used for testing should be potable. If such water is not available the test
water must be analysed. The water analysis must be submitted to the deck supplier for
approval and further instruction.
2. The water test must be carried out as quickly as possible. If the test is done in less than
three days practically no corrosion will be seen on the aluminium / stainless steel
components.
Vacono recommends that the test should be less than three days but shall never be
longer than one week.
3. After the water test is completed and the tank is drained water free, the tank must be
filled with product within 2 days. If the tank and the IFR stand without product for a longer
period of the following conservation must be carried out on the IFR.
4. The tank with the IFR cover is now ready to be filled with product.
Before installing the SEAL, the VACONODECK must be in position and centred.
The best method of centring is to use four wooden blocks placed 90° apart under the upper
flange at the circumference of the floating roof, as shown in sketch 2 and 3.
Installation
The seal is laid out on the circumference of the floating roof. One end is positioned at the point
where the installation of the circumferential clamping channel has been started.
As shown in sketch 1, the seal is curved upwards against the tank wall, and the first hole is
made, using a rubber mallet, at a distance of about 35-50 mm from the inner edge.
Further holes are then punched in the seal, taking care at all times that the outer edge is not
under stress and is held snugly against the tank wall.
Once the first 10 to 20 holes have been punched, and the seal have been placed in position,
the first spacer channel is fitted and bolted down finger-tight.
The complete seal is then installed as described. From the second spacer channel onwards, all
components can be firmly bolted to each other.
Once all the holes have been made in the seal, the end is marked accurately to align with the
start point of the joint, it is then cut and trimmed as necessary, and bonded as shown in drawing
SGB-71141-4.
After the seal has been placed over the bolts again, the last spacer channel is adjusted to fit
and then installed. Finally, after the adhesive has cured, all bolts are firmly tightened and the
installation of the lower seal is thus complete.
The upper seal is installed in the same way, but clamping straps segments are used instead of
the spacer channel, see SGB-71142-4 sketch 5.
PE_Doppel_e.doc 05.12.2007
VACONODECK
4. Project Drawing
MATERIAL LIST
EMAIL vacono@vacono.com
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 1 --
DIMENSIONS IN mm
WEIGHT IN kg
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 2 --
END-R-SHEET POS 74
A = 7420.38
B = 4704.90
C = 20.38
D = 1485.00
E = 0.00
--- A T T E N T I O N P L E A S E ---
1 66.01 CABLE 05 SS
Issue: 01/2014
Email: vacono@vacono.com
Website: www.vacono.com
Contents
1 PRELIMINARIES 1
1.1 SAFETY REGULATIONS, FORMALITIES ................................................................ 1
1.2 MATERIAL STORAGE ........................................................................................ 1
1.3 MATERIAL CONTROL ........................................................................................ 1
1.4 TANK CONTROL............................................................................................... 1
1.5 TORCH-CUTTING AND WELDING ON TANK ........................................................... 1
2 FREE VENTILATION 1
2.1 PERIPHERAL SCOOPS ...................................................................................... 1
2.2 SIDE OVERFLOW ............................................................................................. 1
2.3 CENTRE ROOF VENT ........................................................................................ 2
3 INSTALLING THE VACONODECK 2
3.1 FINDING THE CENTRE-LINE ............................................................................... 2
3.2 DISTRIBUTION OF PERIPHERAL ELEMENTS ......................................................... 2
3.3 PERIPHERAL LEGS .......................................................................................... 2
3.4 FITTING SPACING ELEMENTS ............................................................................ 2
3.5 PREPARATION OF FIRST PERIPHERAL ELEMENT .................................................. 2
3.6 PRE-FITTING OF PERIPHERAL ELEMENTS ........................................................... 2
3.7 ERECTION OF PERIPHERAL RING ....................................................................... 3
3.8 DISPLACEMENT OF LEGS WITH OBSTACLES ........................................................ 3
3.9 POSITIONING AND ASSEMBLY OF FRAME WORK .................................................. 3
3.10 CONNECTING THE FIRST CHANNELS .................................................................. 4
3.11 COMPLETION OF FIRST ROW OF FLOATS ............................................................ 4
3.12 COMPLETION OF THE FRAME WORK .................................................................. 5
3.13 DIFFICULTIES WITH UNEVEN TANK FLOOR .......................................................... 5
3.14 LEVELLING ..................................................................................................... 6
3.15 FIXING THE FIXED LEGS ................................................................................... 7
3.16 FIXING THE UPPER POSITION WITH ADJUSTABLE LEGS ......................................... 7
3.17 FIXING THE LOWER OPERATING POSITION WITH ADJUSTABLE LEGS....................... 8
3.18 BOLTING THE PERIPHERAL ELEMENTS ............................................................... 8
3.19 BOLTING THE PERIPHERAL ELEMENTS ............................................................... 8
3.20 BOLTING THE FLOATS WITH LEGS ...................................................................... 9
3.21 RE-CENTERING OF LEVELLED FRAME WORK ....................................................... 9
3.22 FITTING OF SOCKETS AND BOTTOM ANGLES FOR ANTIROTATION CABLES .............. 9
3.23 ALIGNING THE FRAMING SPACER .....................................................................10
3.24 FITTING THE ASSEMBLY SPACERS ....................................................................10
3.25 ALIGNING THE FIRST CHANNEL LINE .................................................................11
3.26 POSITIONING THE FIRST COVER SHEET .............................................................11
3.27 DRILLING THE BUTT STRAPS ............................................................................12
3.28 TRANSFER OF ASSEMBLY SPACERS .................................................................13
3.29 POSITIONING THE FIRST COVER SHEET .............................................................13
3.30 BOLTING THE SHEETS TO PERIPHERY AND POSITIONING THE FOLLOWING SHEETS 13
3.31 METHOD OF MOUNTING SHEET FOR DIFFERENT VACONODECK DIAMETERS .....14
3.32 TIGHTENING THE BUTT STRAPS ON THE CHANNELS ............................................16
I Issue: 09/2012
3.33 COMBINATION AIR VALVE-MANHOLE .................................................................16
4 FITTING THE NEGOTIATING DEVICES 17
4.1 PLUMBING THE FITTING POSITIONS IN THE VACONODECK ..............................17
4.2 ANTIROTATION SYSTEM ..................................................................................17
4.3 FUNNELS ......................................................................................................18
4.4 PIPE-, ROOF COLUMN- AND LADDER NEGOTIATING DEVICES ...............................18
4.5 NEGOTIATING DEVICES FOR AUTOMATIC GAUGING .............................................19
5 FITTING THE SEAL 19
6 FITTING THE ANTISTATIC SYSTEM 19
7 FITTING FLOATS ON PERIPHERY 19
8 ANTISTATIC PAINT 20
9 DRAIN PIPES 20
10 TOOL AND PROTECTIVE CLOTHING LIST
FOR VACONODECK - INSTALLATION 21
11 VACONODECK - INSTALLATION CHECKLIST- 22
II Issue: 09/2012
1 Preliminaries
2 Free ventilation
1 Issue: 09/2012
2.3 Centre roof vent
The centre roof vent can be fitted by welding the steel sockets directly to the tank roof,
see drawing 23541-00D or by mounting it on an existing roof socket no longer required.
2 Issue: 09/2012
3.7 Erection of peripheral ring
Place first peripheral element at the tank wall and then connect the other peripheral
elements. Preferably proceed in a clock-wise direction and screw up hand-tight.
Fig. 1
Points M1 and M2 are marked at the centres of the peripheral elements and then a cord is
stretched tightly from M1 to M2. Points T1 and T2 are then marked on the peripheral ring.
The centre is marked on the centre float (23872 8" AL / 23769 10" SS) and a leg sleeve
fitted hand tight at both ends with leg. See Fig.1. The float length can be obtained from
assembly drawing and the appendent partlist.
3 Issue: 09/2012
3.10 Connecting the first channels
R-channels are connected with at least two framing spacers 1521mm (23510) /
2021mm (23571) and screw clamps to form a frame, see Fig.2. Instead of the framing
spacers, spacing devices are used if available. This frame is drilled, boring Ø9mm,
together with the peripheral element at points T1 and T2 and bolted hand-tight. The
centre float is then set with its centre mark under the cord. The two R-channels are set
exactly parallel to the cord and secured with float brackets (23517 8" AL / 23604 10" SS)
to the float. The hole spacing in the lower flange of channel is 240mm for 8" AL float or
290mm for 10" SS float, refer to drawing 53357-20-04M or 53357-20-05M.
T1
T2
Frame
Screw Clamps
Fig. 2
=
= Framing Spacer
ca.1,5m
L1
Fig. 3
4 Issue: 09/2012
The float line L1 is set up and channels secured on the periphery in this way, regardless
of the size of the VACONODECK, as shown in Fig.3.
IT IS IMPORTANT, THAT THE CHANNELS ARE PARALLEL TO THE CENTRE LINE
AND ARE ALWAYS EXACTLY SPACED !
If it is found that the R-channels-, cannot be connected to the peripheral elements it must
be checked whether they are really too short or whether they are not parallel. The actual
length must then be compared with the value specified in the appendent partlist. In the
event of complaints, the differences should be reported to VACONO Aluminium Covers
GMBH.
Fig. 4
5 Issue: 09/2012
3.14 Levelling
Before levelling, the cover height shown in the assembly drawing must be marked on a
leg at the tank manhole. The marking is suitably made on the lower edge of the sleeve.
For fixed legs, the difference of the lower edges of sleeves between the legs at the
periphery and the legs in the inner area is 59mm, for 8“ AL floats, and 34mm for 10“ SS
floats, as shown in Fig.5.
Fig. 5
For adjustable legs, the lower edges are at the same level.
Starting from the selected leg, the height marked is then transferred with the hose
levelling instrument or laser unit to all other legs.
Levelling with the hose levelling instrument is performed as shown in Fig.5.
Levelling with a laser unit is performed as indicated in Fig.6.
Fig. 6
6 Issue: 09/2012
The bracket is placed on the wall of the tank, where it is held by magnets. The rotary table
is set horizontal with the three adjusting screws. The mark on the first leg is transferred to
all the others by turning the laser – as for the hose levelling instrument. It must be
ensured that none of the legs stands in the shadow of another.
When all legs have been marked, they must be fixed at the correct height.
Fig. 7
7 Issue: 09/2012
3.17 Fixing the lower operating position with adjustable legs
The lower operating position must be clarified with the operator in the case of adjustable
legs. It should be ensured in this case that the distance from the highest steel section
extending into the tank ( pipeline, mixer etc.) and the cover section above is not less than
100mm, see Fig. 8
190
assembly position
service position
min.100
tank wall
diffuser
Fig. 8
The service height determined is measured from the lower edge of the leg sleeve
downwards. The leg is drilled at that point and an M8x55 (24006) screw inserted and
tightened.
8 Issue: 09/2012
Fig. 9
It should be noted here that the upper edges of the channels must lie in one plane, that
the bolt spacing is 250mm and that the centreline of the framing spacers is aligned, as
shown in Fig.9.
A connection strap 300mm (23518) is used as an aid to installation. A start is made at the
centre. After tightening, the diameter is measured again over the outer edges of the
peripheral elements, to check whether it coincides with the assembly drawing. If it is too
large, the end-framing spacers must be shortened evenly. If too small, the length of the
other centreline must be established later.
When marking, alignment is taken either from the assembly drawing or – if the points
have to be newly selected- according to the frame work channels, i.e. it must be ensured
9 Issue: 09/2012
that the plumb-bob passes as closely as possible through the centre of a panel and
therefore does not meet a channel or float.
Connecting Screws
Spacer
Centreline
Fig. 10 1
10 Issue: 09/2012
3.25 Aligning the first channel line
The channel line A is then accurately straightened from 1 to 2, see Fig.10, and all float
brackets tightened on the float of this line.
A B
Sheet
1
Centreline-Deck
Fig. 11
If the framing spacer, shown in drawing 53357-20-08M, is displaced to one side or the
other in the direction of the width, so that the screws do not fit the slotted holes, it must be
loosened again at the periphery and set to the correct position.
The sheet is then completely unrolled. If it lies satisfactorily, the channel lines A and B are
screwed tightly at the ends with the peripheral section, see Fig.13. The projecting end of
11 Issue: 09/2012
the sheet is cut off flush at the outside edge of the peripheral section.
With continuous sheets, a start is made in the same way at one end of the centre panel.
Cutt off
Screwed tightly
Fig. 13
Starting mark
ca.50mm A
A-A
90° turned
A
Panel
1
Fig. 14
The pre-drilled and pre-bent PE-butt strap is clamped with screw clamps on the outer
flange of the peripheral element and acts as a drilling template. The start of the first PE-
butt strap is made on the flange of the peripheral element. The PE-butt straps are drilled
successively preferably in the clockwise direction.
Please note:
A distance of 250mm form the last hole of the PE-butt strap to the 1st hole of the next PE-
butt strap, must be maintained. The PE-butt strap make-up section has to be cut and to fit
on site.
12 Issue: 09/2012
3.28 Transfer of assembly spacers
When sheet 1 has been laid and the channels of lines A an B have been tightly screwed
to the peripheral element, the spacers of length 1498mm / 1998mm are placed in the next
panel preferably in the clockwise direction. It must be ensured that the spacers are always
in line with those in the panel already covered. The final spacer should be placed as far
as possible on the peripheral element, see Fig.15.
Fig. 15 A B C D E F
Fig. 16
3.30 Bolting the sheets to periphery and positioning the following sheets
If two sheets are laid in the 1500mm or 2000mm system, the first PE-butt strap is
immediately placed, the sheets drilled through at the edge-with the PE-butt strap again
serving as a drilling template- and screwed tight. The tank wall spacers must then
immediately be securely fitted again, see Fig. 17.
13 Issue: 09/2012
Tank wall spacer
PE-butt strap
Fig. 17
The spacers from panel 2 are moved to panel 4, see Fig.16, after all float brackets of
channel lines C and D had been secured. The fourth sheet is then laid, the corresponding
straight S-butt strap secured hand-tight and the PE-butt strap section positioned and
screwed tight.
Fig. 18
With through going sheets, a start is also made with panel 1, but from the edge and first
closing one half and then the other. If sufficient personnel are available, both sides can be
worked here simultaneously, see Fig.19.
14 Issue: 09/2012
Fig. 19
With large diameters, i.e. over 30m, all 15m long S-sheets are first laid and then
installation continued – as for a cover with sheet panels divided in the middle, see Fig 20.
Fig. 20
15 Issue: 09/2012
3.32 Tightening the butt straps on the channels
When all sheets have been laid, the edge is screwed tight, i.e. the PE-butt straps
compress the sheets to the peripheral elements. The straight S-butt straps inside the
cover on the overlap are only secured hand-tight. These are now tightened firmly. A start
can be made anywhere.
16 Issue: 09/2012
4 Fitting the negotiating devices
A check must be made before installing further fixtures whether the cover is still fixed
firmly at the tank centre. Re-tension tank spacers if necessary.
Fig. 22
17 Issue: 09/2012
4.3 Funnels
When providing gauging funnels, the upper funnel is laid centrally with the mark on the
cover and the internal diameter marked. The circle is neatly cut out, so that no excess
remains inside. The upper funnel is placed on again and aligned with one side of the
square flange parallel to the nearest butt strap. All pre-drilled holes are transferred to the
cover sheet. After drilling, the channels are fitted as described in 4.2 and drilled in a
similar way. Assembly of upper and lower funnels is performed as shown on drawings
23717-00D, 23718-00D and 23719-00D. Where it is planned to include nylon membranes,
it must be ensured that the slots running at 60° do not overlap.
pipe
Fig. 22
sheet cut
sheet cut out
1540/2040
sheet
column
Fig. 23
The sheet is cut open on one side for negotiating devices near the wall of the tank and
sufficient material cut out around the pipe entering to permit the remaining sheet slot is
later sealed with waste sheet, sealing paste (24114) and pop rivets (24018). The sheet is
cut right through for roof supports inside the tank, see Fig. 22, in order to avoid
deformation when further unrolled, Fig.23.
The seal firmly inserted in the sealing plate must be inspected before the two halves of
the plate are riveted together, to check whether it provides an efficient seal. Modify if
necessary. Ensure when riveting together that the rivet heads are on the underside of the
plate.
18 Issue: 09/2012
4.5 Negotiating devices for automatic gauging
In the case of automatic gauges already fitted with guide cables attached to roof and floor,
the cables are removed before fitting the cover. The float is drawn up from the roof for
plumbing, without it slipping out of its strip guide. After fitting the shaft, the cover is
positioned with the measuring tape guide at a negotiating device with guide rods, see
drawing 23722-00D. The measuring tape is released from the float and- after the seal has
been slit at the centre of the cover- drawn through the slit. The float is then reattached.
The two guide rods are then fitted so that there is at least 50mm safety spacing left
between their lower end and the floor of the tank. Warning: This spacing must apply to the
lower service position in the case of adjustable legs.
For floats without eyelet guides, a guide cage, see drawing 23723-00D, riveted to the
shaft, is used and the safety spacing of 50mm must also be observed here.
In the case of automatic gauges suitable for calibration to drawing 23721-00D, the lower
edge of the pipe-shaped shaft must also have a safety spacing of at least 50mm from the
floor.
19 Issue: 09/2012
8 Antistatic paint
The painting work to TRbF 120 if necessary, the areas to be coated are specified on
assembly drawing. The areas indicated are marked and cleaned and then painted with
the green primer,Type 94, (mixing ratio paint to hardener 7:1). The black top coat (mixing
ratio paint o hardener 4:1) is applied when the undercoat has dried.
9 Drain pipes
The drain pipes are mounted as per drawing 23536-00D, 23942-00D, 53363-00D or
53405-00D, 1 pc. per sheet - in the center of the sheets.
20 Issue: 09/2012
10 TOOL AND PROTECTIVE CLOTHING LIST
FOR VACONODECK - INSTALLATION
PROTECTIVE CLOTHING :
1.) Overall
2.) Protective boots
3.) Gloves
4.) Dust mask
21 Issue: 09/2012
11 VACONODECK - INSTALLATION CHECKLIST-
1.2 Floats,
53357-20-06M
Blind rivets, upwards
Brackets, complete and tight
22 Issue: 09/2012
1.5 Automatic gauging devices,
23722-00D, 23723-00D
Screw joints tight
Rivet joints tight
Sealing correct
Distance between lowest edge and tank bottom min.50mm
23 Issue: 09/2012
2. TANK BOTTOM Check Mark
2.2 Diffuser
Diffuser is installed pointing to tank centre
Diffuser horizontally installed
Support welded to diffusor
No welding between support and tank bottom
24 Issue: 09/2012
3. DECK TOP SIDE Check Mark
3.4 Vacuum-valve
23545-00D
Cover plate lock nuts are tight
Cover plate lifted for 150 mm in the lowest deck position
Opening road easily movable in the sleeve
25 Issue: 09/2012
3.5 Pipe, Ladder, Column negotiation devices
23725-00D, 23727-00D, 23728-00D, 53117-00D
Well flange sealed
Rivet joints tight
Sealing plate riveted ( Heads downward )
Antistatic cables installed
26 Issue: 09/2012
4. TANK ROOF Check Mark
4.1 Antirotation-system,
23712-00D, 23764-00D, 23964-00D, 53384-00D
Socket and reinforcing flange completely fillet welded
4.2 Antistatic-system,
23713-00D
Cable clamping bolts tight
Resistance test executed ( reading: Zero Ohm )
27 Issue: 09/2012
VACONODECK
7. Type Sheets
M8
24016
Dichtstück
sealing block
24207
Umfangselement
peripheral profile
21120
M8x65 M8
24025
M8x20
24005
Verbinder - U
PE connector
23526
-
This article replaces type
Bottom plate
Floater
Tube 1,3 mm AlMn1Mg1 3004
End Cap 2,5 mm Al Mg 3 5754
Floater end brackets 2,0 mm Al Mg 3 5754
alternative:
Cover Sheets 0,5 mm
Core Al Mn Cu (hh) 3003-H26
Cladding min. 5 % each side Al Zn 1 7072
Extruded Sections
Rim profile 2,5 mm AlMgSi0,5 F25 6063
Crossing profile (lower) 1,8 mm (3,0 mm) AlMgSi0,5 F25 6063
Crossing-profile (upper) 3,0 mm (2,0 mm) AlMgSi0,5 F25 6063
Negotiation Devices
Gauging 1-1,5 mm(flange 1,5 mm) Al Mg 3 5754
1,0 mm (flange 1,5 mm) 1.4301 (stainless steel)
Manhole 1,5 mm (cover 5 mm) Al Mg 3 5754
1,0 mm (cover 3 mm) 1.4301 (stainless steel)
Nuts M8 Al Mg Si 1 F 23 6082
(stainless steel optional)
issued 02.11.2016
Content:
Remark
Accessories as per parts list are included
Unit weight fluid g = 700 kg/m³ (6,867 kN/m³ ) as per API 650 12th Add. H 4.2.1.1 6,87 kN/m³
Reduced Ration Dead Weight/Buoyancy 2 Floats defective compl. API 650 App H 4.2.1.3
* two biggest floaters are considerd
Length of longest floater [mm]
1 5600
2 5600
The calculation situation of valve-manhole combination is considered open. Usually hatch is closed, except
when landing on bottom plate. (150mm open, when on ground)
Assessment of boundary conditions
Qty of vent units n= 2 pcs.
Max. discharge velocity 11,21 m/s equals 8 mmWC per API 2000
Gapping Area = 0,33 m²
specified pumping out rate of 1000 m³/h complies to API 650 by 2 vents
specified pumping in rate of 1000 m³/h complies to API 650 by 2 vents
Note: This calculation is set up in compliance to API 650 H.5.2.1
LEG (BUCKLING) Check Vacono Project: 17440
in reference to API 650 12th ed. Appendix H, § 4.2.1.2 / 32-SAMSS-005 H 4.2.1
Issued: 02.11.2016
in reference to
Conc.LL = kN/0.1m² 2,2 API H 4.2.1.4
Utilisation
Buckling
48,93%
Remark : Utilisation for buckling must be lower than 100%
Note: Requirement is met!
page 3