You are on page 1of 93

VACONODECK

DOCUMENTATION
Order No. : PR-17440 / 602083
Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
VACONODECK
Directory

1 General Operating
2 Water Test
3 Sealing
4 Project Drawing
5 Part List
6 Installation Manual
7 Type Sheets
8 Calculations

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
VACONODECK
1.General Operating

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
General Operating Instructions
Recommendations for the Use of the VACONODECK

1. General

The object of the VACONODECK is to minimise the loss through evaporation of the stored
product. Though numerous settlings will not damage the VACONODECK, in order to
minimise gas losses, this should be avoided as much as possible. A deck that is not
floating on the liquid is effectively useless.

2. Particular Recommendations

Overfilling of the Tank

The most frequent causes of damage to the VACONODECK are found to have been
caused through the overfilling of a tank. It is therefore to be recommended that overfilling
of a tank be prevented through the use of any one of the numerous overfilling protection
devices available on the market.

Inlet Rate

When tanks are filled at a high rate of inlet there remains the possibility of damage to the
VACONODECK due to the large amount of turbulence caused.

Before installing the VACONODECK it should be confirmed by the tank operator that the
inlet velocity does not exceed 1,0 m/sec. A diffuser should otherwise be installed to reduce
the inlet rate to this figure.

Important note:
The diffuser is not suitable for or designed to allow purging of the feed line with (nitrogen)
gas. Such an action could lead to damage of the floating deck.

Should it subsequently be decided to increase the inlet rate in a tank where a


VACONODECK is installed this should firstly be advised to ourselves that we may
determine whether a diffuser is necessary and if so what size will be required.

General operating_e_b.doc Page 1/ 4 03.08.04


Tank Mixers (if installed)

If a tank has a mixer installed this mixer should be coupled to a level switch.

By the propeller type of mixer the minimum level whereby it should be switched on is when
the liquid level is 2 mtrs over the maximum height of the propeller thereby assuring no
possible contact, and thereby no damage, to the VACONODECK.

By the use of the jet mixer type the liquid level in the tank should be at least 2,5 mtrs
above the height of the jet mixer nozzle thereby avoiding the possibility of a jet stream
hitting the floats or deck sheets of the VACONODECK etc. causing possible damage.

Important note:
We would advise that where a mixer unit exists or is to be installed in a tank with a
VACONODECK VACONO should firstly be consulted in order to advise in each instance at
what liquid height the mixer may be switched on safely!

Floating Suction Unit (if installed)

Floating Suctions of aluminium or steel design are designed bearing in mind the specific
gravity of the product stored. Should the tank be filled with water (S.G. 1.0) or a heavier
product than foreseen this would lead to an increase in the floatability of the floating
suction unit thereby increasing the pressure to the underside of the VACONODECK unit
(to which it is attached by means of guide rails) and thereby leading to the almost certain
result of damage being caused. Therefore should it be decided to fill a tank with water for
cleaning or testing purposes it is important that the floating suction unit's floats be
removed. Further should it be decided to store another product in the tank we should firstly
be consulted in order that we may determine whether the new product and it's specific
gravity will affect the floatability of the floating suction unit to an extent whereby the deck
may be damaged.

Tank Welds

In order to avoid mechanical failure of the deck seal all tank wall welds should be clean
and smooth without burrs and sharp edges.

Water test

If such is to be undertaken please refer to the attached instructions „Procedure for Water
Testing of VACONODECK Internal Aluminium Floating Covers (IFR)“ thereto.

General operating_e_b.doc Page 2/ 4 03.08.04


3. Regular Controls

Antirotation System

The antirotation cables should never be slack and always under tension. This should be
checked from time to time and where necessary the cables should be retensioned .

Antistatic System

The earthing cables are attached to the VACONODECK and the tank roof manhole and
they should be checked from time to time to ensure that they are still safely connected.

4. Operating the VACONODECK

During the tank inspection, cleaning etc. local safety regulations shall be observed.

In tank cleaning operations where water is used, spraying of water on the VACONODECK
topside surface should be avoided as much as possible to avoid increased weight and
stress to the deck sheets profiles and legs.

Tank cleaning systems (such as Butterworth, Blabo, Prosser, Scanjet etc.) that are
operated from the tank roof are not to be used in conjunction with a VACONODECK.

By use of stream to clean tank direct spraying on the deck seals should be avoided.

When carrying out repairs in the tank 'spark free' tools should be used and dropping of
tools onto the VACONODECK or scratching the zinc plated surfaces should be avoided.

5. Hanging Decks (if installed)

Where ‘Hanging decks’ are to be installed the following points are to be noted:
When the VACONODECK is in the hanging position it is only to be walked on by one
person. In the hanging state (during tank modification, cleaning, etc.) no person should be
on top of the deck whilst work is being carried out by others on the underside.

Working on top and below the deck is only permitted when the supplied leg
supports have been installed.

General operating_e_b.doc Page 3/ 4 03.08.04


6. Live load according API 650 APP. H.4.2.2

The internal floating roof shall be designed to safely support at least two men
( 2,2kN = 500 lbf over 0,1 sqm = 1 sqft ) walking anywhere on the roof while
it is floating or resting on its supports without damaging the floating roof and without
allowing product on the roof. If specified by the purchaser, the concentrated load
design criteria may be modified for roofs less than 9 m ( 30ft. ) diameter ( where
internal floating roofs may become unstable ), to account for access needs, and
expected concentrated live loads.

General operating_e_b.doc Page 4/ 4 03.08.04


INSPECTION/ CUSTOMER ACCEPTANCE CERTIFICATE

Customer:________________________________________________________________

Project Description:________________________________________________________

Project Number:___________

VACONODECK Number_____________ for the above project has been assembled and
installed in accordance with the manufactures installation instructions and drawings. All
workmanship has been checked by the customers representative and found to be acceptable.

Have all customer comments and rectification


work been addressed and accepted. _________________________

Have all areas been cleaned and excess


material disposed of. _________________________

Contractors Signature__________________________ Date:________________________

_________________________________________________________________________

Customer acceptance:

Client / Site Engineer:__________________________

Signature:___________________________________ Date:________________________

Name ( Print ): _______________________________

Position ( Print ):______________________________

Copies to: Customer


Contractor
Manufacturer

____________________________________________________________________
Contractor: Upon acceptance by the customer please return a copy of this report by fax to:

Aluminium Rheinfelden
VACONO DEPT
FAX NO. 07623 / 93 547

INSPEC.DOC 24/10/2003 AR39


V A C O N O DECK ®
Maintenance and Repair instructions

VD-E.10/06.05.2010/B 1
MAINTENANCE

The antirotation cables should never be slack and always under tension. This should be checked from time
to time and where necessary the cables should be retensioned.

The earthing cables are attached to the VACONODECK and the tank roof manhole and they should be
checked from time to time to ensure that they are still safely connected.

During the tank inspection, cleaning etc. local safety regulations shall be observed.

In tank cleaning operations where water is used, spraying of water on the VACONODECK topside surface
should be avoided as much as possible to avoid increased weight and stress to the deck sheets profiles
and legs.

Tank cleaning systems (such as Butterworth, Blabo, Prosser, Scanjet etc.) that are operated from the tank
roof are not to be used in conjunction with a VACONODECK.

By use of stream to clean tank direct spraying on the deck seals should be avoided.

When carrying out repairs in the tank ‘spark free’ tools should be used and dropping of tools onto the
VACONODECK or scratching the zinc plated surfaces should be avoided.

Hanging Decks (if installed)

Where ‘Hanging decks’ are to be installed the following points are to be noted:
When the VACONODECK is in the hanging position it is only to be walked on by one person. In the
hanging state (during tank modification, cleaning, etc.) no person should be on top of the deck whilst work
is being carried out by others on the underside.

Working on top and below the deck is only permitted when the supplied leg supports have been
installed.

REPAIR

In case of one or more parts of the Vaconodome will be damaged, our main office in Rheinfelden
(Germany) shall immediately be informed.

VD-E.10/06.05.2010/B 2
VACONODECK & VACONODOME

Storage:
All materials have to be stored dry to avoid fluid retention between the materials.
Especially sealing materials have to be kept away from sunlight.

Transportation:
Transportation has to be done always with special care. Aluminium parts are very sensitive
against damage. Special care has to be taken on VACONODOME sheets and VACONODECK
floats and sheets because of the thin-walled materials.

VACONODOME materials are packed by VACONO onto pallets, transport frames and into
wooden boxes. All packages can be transported by usual fork lifters or hand lifts. The maximum
gross weight of each package does not exceed 2,2 to.

VACONODECK materials are generally delivered partly packed and partly unpacked. Unpacked
materials like floats, channels, butt straps have to be loaded/unloaded by hand for which normally
3-4 working men are working 1-2 hours (depends on size and quality of VACONODECK(s).

1/1
TOOL AND PROTECTIVE CLOTHING LIST FOR
VACONODECK - INSTALLATION

1.) 3 No. Power drill, 12,5mm chuck


2.) 15 No. 8,5mm drilling bits
3.) 15 No. 5,0mm drilling bits
4.) Extension cable to allow easy movement of power tools around tank area
5.) Adequate lighting for work inside tank
6.) Up to 60 meters of clear plastic hose 12mm dia., depent on tank diameter !
7.) 2 No. Screw driver
8.) 8 No. 13mm and 1No. 10mm Combination Spanner
9.) 3 No. Tin snip or Scissor
10.) 3 No. 5 meters Tape Measure
11.) 3 No. Hacksaw and 10 spare blades
12.) 5 No. Marker pens
13.) 3 No. Silicon pistol
14.) 2 No. Pop rivet gun to suit 4,8mm rivets
15.) 2 No. Rubber and 2 metal hammer
16.) 1 No. Stanley marking knife
17.) 10 No. 3m Wooden scaffold boards
18.) 3 No. Electric ratchet spanners with 13mm sockets

PROTECTIVE CLOTHING :
1.) Overall
2.) Protective boots
3.) Gloves
4.) Dust mask

Tool list_e.doc 24.03.2005 1/1


VACONODECK
2. Water Test

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
Procedure for - Water Testing - of
Internal Aluminium / Stainless Steel Floating Covers (IFR)
Type ”VACONODECK“

1. General
The relevant API 650 app. H. paragraphs H.6.6 describes in general how the water test
should be carried out and which risks regarding corrosion are to be seen.

API 650 app. H.

H.6.6 Initial Flotation


A flotation test and initial fill inspection shall be conducted by the Purchaser. This test may be performed or
witnessed by the erector, as subject to agreement with the Purchaser. The party performing the flotation test
shall make water connections and supply all tank closures required for testing and remove all water
connections and temporary closures (including gaskets, fasteners, test blanks, etc.) after completion of the
test, unless otherwise specified by the Purchaser.
H.6.6.1 Internal floating roofs in accordance with types H.2.2a, b, c, d, and g shall be given a flotation test on
water. Internal floating roofs in accordance with types H.2.2e and H.2.2f shall be given a flotation test on water
or product at the option of the Purchaser. During this test, the roof and all accessible compartments shall be
checked to confirm that they are free from leaks. The appearance of a damp spot on the upper side of the part
in contact with the liquid shall be considered evidence of leakage.
H.6.6.2 During initial fill the internal floating roof should be checked to confirm that it travels freely to its full
height. The peripheral seal shall be checked for proper operation throughout the entire travel of the internal
floating roof. During the first event of lowering the level from full height, particular attention shall be given for
tanks that contain a floating suction to ensure proper operation.
H.6.6.3 Because of possible corrosive effects, consideration shall be given to the quality of water used and the
duration of the test. Potable water is recommended. For aluminum or stainless steel floating roofs, S.4.10 shall
be followed.
H.6.6.4 The high flotation level shall be evaluated for clearance and the floating suction (if existing) shall be
compensated for the excess buoyancy that will be encountered during hydrostatic testing of the floating roof
system.

If IFR is tested on water the following recommendations can be given by Vacono:

1. Water which is used for testing should be potable. If such water is not available the test
water must be analysed. The water analysis must be submitted to the deck supplier for
approval and further instruction.

2. The water test must be carried out as quickly as possible. If the test is done in less than
three days practically no corrosion will be seen on the aluminium / stainless steel
components.
Vacono recommends that the test should be less than three days but shall never be
longer than one week.

3. After the water test is completed and the tank is drained water free, the tank must be
filled with product within 2 days. If the tank and the IFR stand without product for a longer
period of the following conservation must be carried out on the IFR.

Water testing_f.doc 24.08.15 1/2


All Aluminium / Stainless Steel Floats must be brushed with a soft brush (no metal brush
to be used) and dried from water drops. A thin layer of oil must be applied on them.
This conservation stops possible ongoing pitting corrosion on the floats and on other
parts treated.

4. The tank with the IFR cover is now ready to be filled with product.

Water testing_f.doc 24.08.15 2/2


VACONODECK
3. Sealing

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
INSTALLATION MANUAL
VACONODECK - "Double PE" - SEAL
DRAWINGS: SGB-71141-4 / SGB-71142-4

See attached drawing SGB-71142-4, Sketch 1-5

Before installing the SEAL, the VACONODECK must be in position and centred.
The best method of centring is to use four wooden blocks placed 90° apart under the upper
flange at the circumference of the floating roof, as shown in sketch 2 and 3.

Installation
The seal is laid out on the circumference of the floating roof. One end is positioned at the point
where the installation of the circumferential clamping channel has been started.

As shown in sketch 1, the seal is curved upwards against the tank wall, and the first hole is
made, using a rubber mallet, at a distance of about 35-50 mm from the inner edge.

Further holes are then punched in the seal, taking care at all times that the outer edge is not
under stress and is held snugly against the tank wall.

Once the first 10 to 20 holes have been punched, and the seal have been placed in position,
the first spacer channel is fitted and bolted down finger-tight.

The complete seal is then installed as described. From the second spacer channel onwards, all
components can be firmly bolted to each other.

Once all the holes have been made in the seal, the end is marked accurately to align with the
start point of the joint, it is then cut and trimmed as necessary, and bonded as shown in drawing
SGB-71141-4.

After the seal has been placed over the bolts again, the last spacer channel is adjusted to fit
and then installed. Finally, after the adhesive has cured, all bolts are firmly tightened and the
installation of the lower seal is thus complete.

The upper seal is installed in the same way, but clamping straps segments are used instead of
the spacer channel, see SGB-71142-4 sketch 5.

PE_Doppel_e.doc 05.12.2007
VACONODECK
4. Project Drawing

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
VACONODECK
5. Part List

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
- V A C O N O D E C K -

MATERIAL LIST

TANK DIAMETER : 39000.00 mm

ORDER NUMBER : 602083

DECK NO : 4694 / 4695

ASSEMBLY DRAWING : 602083-10-00 A/-30-00 A

CUSTOMER : MPP JEDINSTVO A.D. SERBIA

VACONO ALUMINIUM COVERS GMBH

PO BOX 1165 D-79601 RHEINFELDEN / BADEN

FRIEDRICHSTRASSE 50 D-79618 RHEINFELDEN / BADEN

TELEFON 07623 / 71786-0

TELEFAX 07623 / 71786-71

EMAIL vacono@vacono.com
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 1 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

TANK HEIGHT 18097.00


DECK HEIGHT 1800.00
OUTER DIAMETER DA 38620.00
INNER DIAMETER DI 38540.00
INNER DIA PE-BUTT STRAP DKI 38555.00
D2 38500.00
DISTANCE DR 190.00
RISE OF PE-ELEMENT SU 14.60
RADIUS OF PE ELEMENT RI 19270.00
RISE OF PE-BUTT STRAP SUK 14.59
RADIUS OF PE-BUTT STRAP RKI 19277.50
SECANT OVER 90-DEGREES SEC 27308.46
CHANNEL DISTANCE 2000.00
MAX. SHEET LENGTH 15000.00
FLOAT DISTANCE 3000.00
ADDITIONAL WEIGHT 0.00
SPEC. BUOYANCY kg/m3 700.00
DECK WEIGHT 4759.62
BUOYANCY 10323.37
TANK WEIGHT (ADDITIONAL) 0.00

DIMENSIONS IN mm
WEIGHT IN kg
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 2 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

POS. QTY TYP A B C WEIGHT

1 34 1 3500.00 0.00 0.00 319.28 PE ELEMENT


2 2 1 1041.58 0.00 0.00 5.59 PE ELEMENT
----------
324.87

3 1 3 4270.00 0.00 0.00 2.53 R-CHANNEL


4 1 4 4270.00 0.00 0.00 2.53 R-CHANNEL
5 2 3 4167.23 0.00 5.96 4.93 R-CHANNEL
6 2 4 4167.23 0.00 5.96 4.93 R-CHANNEL
7 2 3 3852.93 0.00 11.98 4.56 R-CHANNEL
8 2 4 3852.93 0.00 11.98 4.56 R-CHANNEL
9 2 3 3316.19 0.00 18.14 3.92 R-CHANNEL
10 2 4 3316.19 0.00 18.14 3.92 R-CHANNEL
11 2 3 2536.62 0.00 24.53 3.00 R-CHANNEL
12 2 4 2536.62 0.00 24.53 3.00 R-CHANNEL
13 2 3 1479.77 0.00 31.26 1.74 R-CHANNEL
14 2 4 1479.77 0.00 31.26 1.74 R-CHANNEL
15 2 3 5087.51 0.00 38.52 6.01 R-CHANNEL
16 2 4 5087.51 0.00 38.52 6.01 R-CHANNEL
17 2 3 3254.55 0.00 46.60 3.84 R-CHANNEL
18 2 4 3254.55 0.00 46.60 3.84 R-CHANNEL
19 2 3 757.94 0.00 56.13 0.88 R-CHANNEL
20 2 4 757.94 0.00 56.13 0.88 R-CHANNEL
21 2 3 1912.59 0.00 69.08 2.23 R-CHANNEL
22 2 4 1912.59 0.00 69.08 2.23 R-CHANNEL
23 94 2 5000.00 0.00 0.00 278.24 S-CHANNEL
----------
345.50

25 3 6 2021.00 0.00 0.00 3.64 FRAM SPAC +BOLTS


26 39 6 1998.00 0.00 0.00 46.75 FRAM SPAC +BOLTS
27 2 5 2021.00 0.00 0.00 2.43 FRAMING SPACER
28 30 5 1998.00 0.00 0.00 35.96 FRAMING SPACER
29 2 6 1258.00 0.00 0.00 1.51 FRAM SPAC +BOLTS
----------
90.29

30 1 8 4277.50 0.00 0.00 1.99 R-BUTT STRAP


31 1 9 4277.50 0.00 0.00 1.99 R-BUTT STRAP
32 2 8 4174.77 0.00 5.96 3.88 R-BUTT STRAP
33 2 9 4174.77 0.00 5.96 3.88 R-BUTT STRAP
34 2 8 3860.59 0.00 11.98 3.59 R-BUTT STRAP
35 2 9 3860.59 0.00 11.98 3.59 R-BUTT STRAP
36 2 8 3324.08 0.00 18.13 3.09 R-BUTT STRAP
37 2 9 3324.08 0.00 18.13 3.09 R-BUTT STRAP
38 2 8 2544.86 0.00 24.52 2.36 R-BUTT STRAP
39 2 9 2544.86 0.00 24.52 2.36 R-BUTT STRAP
40 2 8 1488.54 0.00 31.25 1.38 R-BUTT STRAP
41 2 9 1488.54 0.00 31.25 1.38 R-BUTT STRAP
42 2 8 5097.09 0.00 38.50 4.73 R-BUTT STRAP
43 2 9 5097.09 0.00 38.50 4.73 R-BUTT STRAP
44 2 8 3265.45 0.00 46.57 3.02 R-BUTT STRAP
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 3 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

POS. QTY TYP A B C WEIGHT

45 2 9 3265.45 0.00 46.57 3.02 R-BUTT STRAP


46 2 8 771.37 0.00 56.10 0.70 R-BUTT STRAP
47 2 9 771.37 0.00 56.10 0.70 R-BUTT STRAP
48 2 8 1933.48 0.00 69.02 1.77 R-BUTT STRAP
49 2 9 1933.48 0.00 69.02 1.77 R-BUTT STRAP
50 94 7 5000.00 0.00 0.00 218.55 S-BUTT STRAP
----------
271.57

51 49 10 2500.00 0.00 0.00 56.96 PE-BUTT STRAP


52 42 11 1967.00 0.00 0.00 40.24 T-BUTT STRAP
53 2 12 1265.50 0.00 0.00 1.18 R-T-BUTT STRAP
54 49 13 0.00 0.00 0.00 2.25 SEALING BLOCK
----------
100.64

55 24 14 15000.00 15000.00 0.00 1009.80 S-SHEET


56 2 15 4510.74 102.91 110.74 25.02 R-SHEET
57 2 16 4510.74 102.91 110.74 25.02 R-SHEET
58 2 15 4408.39 312.06 8.39 23.86 R-SHEET
59 2 16 4408.39 312.06 8.39 23.86 R-SHEET
60 2 15 4097.55 531.73 197.55 21.50 R-SHEET
61 2 16 4097.55 531.73 197.55 21.50 R-SHEET
62 2 15 3567.93 771.03 167.93 17.85 R-SHEET
63 2 16 3567.93 771.03 167.93 17.85 R-SHEET
64 2 15 2800.37 1043.25 150.37 12.78 R-SHEET
65 2 16 2800.37 1043.25 150.37 12.78 R-SHEET
66 2 15 1763.02 1370.48 113.02 6.05 R-SHEET
67 2 16 1763.02 1370.48 113.02 6.05 R-SHEET
68 2 15 15403.48 1795.49 3.48 81.38 R-SHEET
69 2 16 15403.48 1795.49 3.48 81.38 R-SHEET
70 2 15 13632.19 2419.89 232.19 69.69 R-SHEET
71 2 16 13632.19 2419.89 232.19 69.69 R-SHEET
72 2 15 11290.60 3590.07 140.60 53.27 R-SHEET
73 2 16 11290.60 3590.07 140.60 53.27 R-SHEET
74 2 18 7420.38 4704.90 20.38 20.70 END-R-SHEET
75 2 19 7420.38 4704.90 20.38 20.70 END-R-SHEET
----------
1673.97

76 117 23 0.00 0.00 0.00 15.21 CON.BUTT STRAP


77 73 24 0.00 0.00 0.00 7.30 CHANNEL CON
78 36 25 0.00 0.00 0.00 6.12 CONNECTION F. PE
79 1 48 126.00 0.00 0.00 292.32 VACONOSEAL PE Db
80 4 64 0.00 0.00 0.00 19.72 CABLE GUIDE
81 4 65 0.00 0.00 0.00 26.08 ANTIROTATION SYS
82 4 66 0.00 0.00 0.00 0.32 CABLE 05 SS
83 3 67 0.00 0.00 0.00 2.40 ANTISTATIC SYS
84 2 68 0.00 0.00 0.00 34.22 MANHOLE VII AL
86 1 86 0.00 0.00 0.00 9.49 NEG DEV PIPE 2”
87 1 1576 0.00 0.00 0.00 27.80 DBL NEG DEV PIPE 6”/6”
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 4 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

POS. QTY TYP A B C WEIGHT

88 1 1122 0.00 0.00 0.00 11.70 FLOATG.AUTOGAUG.ENRAF


89 64 96 0.00 0.00 0.00 0.64 DRAIN PIPE
----------
453.32

98 44 21 5600.00 0.00 0.00 580.98 FLOAT Al


99 4 21 4560.00 0.00 0.00 43.56 FLOAT Al
100 4 21 4080.00 0.00 0.00 39.29 FLOAT Al
101 4 21 3080.00 0.00 0.00 30.39 FLOAT Al
102 8 21 3540.00 0.00 0.00 68.96 FLOAT Al
103 4 21 4790.00 0.00 0.00 45.61 FLOAT Al
104 8 21 3260.00 0.00 0.00 63.98 FLOAT Al
106 2 21 2250.00 0.00 0.00 11.50 FLOAT Al
107 16 21 1920.00 0.00 0.00 80.26 FLOAT Al
108 4 21 2280.00 0.00 0.00 23.27 FLOAT Al
109 8 21 1770.00 0.00 0.00 37.46 FLOAT Al
110 4 21 2390.00 0.00 0.00 24.25 FLOAT Al
111 8 21 1290.00 0.00 0.00 28.91 FLOAT Al
112 4 21 2610.00 0.00 0.00 26.20 FLOAT Al
113 116 22 0.00 0.00 0.00 19.72 FLOAT ADAPTER
114 200 26 0.00 0.00 0.00 19.20 FLOAT BRACKET
----------
1143.53

116 34 57 2160.00 0.00 0.00 94.18 P-ADJ.LEG+PLUG A


117 64 61 2160.00 0.00 0.00 174.08 F-ADJ.LEG+PLUG A
118 2880 31 0.00 0.00 0.00 35.42 BOLT M8*20
119 310 32 0.00 0.00 0.00 5.64 BOLT M8*35
120 230 33 0.00 0.00 0.00 5.38 BOLT M8*55
121 8010 34 0.00 0.00 0.00 14.90 NUT M8
123 550 36 0.00 0.00 0.00 16.39 BOLT M8*65
124 300 37 0.00 0.00 0.00 0.48 RIVET 4.8*14.8
----------
346.48
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 5 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

END-R-SHEET POS 74
A = 7420.38
B = 4704.90
C = 20.38
D = 1485.00
E = 0.00

--- A T T E N T I O N P L E A S E ---

PART LIST ON NEXT PAGES

THESE PARTS ARE ALREADY INCLUDED IN ABOVE POSITIONS


THE MATERIAL MENTIONED UNDER NB, DEPENDS ON 1. PC OF POS.
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 6 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

QTY TYP DRAWING TEXT WEIGHT


1 6.01 SGB-03267-3 U-PROFILE 58,5x25x A 0.525
1 .02 SGB-00837-4 S-T- CONNECTOR 0.075
1 .03 TYP 38 HEX.BOLT M8 x 35 18.2

1 21.01 SGB-02586-3 PIPE 203x1,3x A-10 2.225


1 .02 COVER 0.27
1 .03 COVER 0.27
2 .04 FLOAT CONNECTION 0.13
1 .05 RIVET 4,8x8,3

1 57.01 SGB-02456-2 P-SLEEVE ADJ LOW.PART 0.59


1 .02 SGB-02455-3 SLEEVE ADJ. UPP.PART 0.20
1 .03 SGB-02589-3 LEG ADJ. -A- AL 0.98
1 .04 SGB-00840-4 PLUG 0.04

1 61.01 SGB-02457-2 F-SLEEVE ADJ.LOW.PART 0.54


1 .02 SGB-02455-3 SLEEVE ADJ. UPP.PART 0.20
1 .03 SGB-02589-3 LEG ADJ. -A- AL 0.98
1 .04 SGB-00840-4 PLUG 0.04

1 64.01 SGB-02545-3 CABLE GUIDE 1.47


2 .02 SGB-02607-2 FRAMING SPACER -A-

1 65.01 SGB-00468-4 BOTTOM ANCHOR 0.20


1 .02 SGB-00351-4 SOCKET 3 INCHES 1.00
1 .03 SGB-00352-4 SCREW CAP 3 INCHES 0.75
1 .04 SGB-00245-4 SPRING 1.20
1 .05 SGB-00353-4 EYE BOLT 0.58
3 .06 DIN 934 HEX.NUT M16 GALV. 0.10
4 .07 CABLE CLAMP 05 SS 0.14
1 .08 SGB-03820-4 REINFORCING RING 2.05

1 66.01 CABLE 05 SS

2 67.01 SGB-00467-4 BUTT STRAP 65 0.04


2 .02 TYP 33 HEX. BOLT 0.05
6 .03 DIN 934-SS HEX. NUT M8 0.03
2 .04 DIN 127-SS SPRING WASHER A8
4 .05 DIN 9021-SS WASHER A8,4 0.02
2 .06 SGB-03319-4 GROUND CABLE 03,0 0.60
2 .07 SGB-03409-4 WARNING PLATE 0.01

1 68.01 SGB-53753-3 MANHOLE SHAFT 2.50


1 .03 SGB-03589-2 MANHOLE COVER AL 5.41
2 .04 SGB-03590-4 SPACER 0.02
1 .05 SGB-03591-3 SLEEVE 0.26
1 .06 SGB-01970-4 OPENING ROD 0.
DECKHEIGHT +200 CA 3.00
1 .07 SGB-01993-4 PLUG 0.063
1 .08 SGB-00304-4 PLUG 0.043
1 .09 SGB-00350-4 BUTT STRAP 85 0.04
2 .10 SGB-03760-3 FRAMING SPACER -A- 0.
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 7 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

QTY TYP DRAWING TEXT WEIGHT


2 .11 SGB-03759-3 FRAMING SPACER 608 1.58
12 .12 TYP 31 HEX. BOLT 0.15
12 .13 TYP 34 HEX. NUT 0.02
1 .14 TYP 130 SEALING PASTE 0.
1 .17 SGB-50264-4 TYPE PLATE 0.24
4 .18 TYP 37 POP-RIVET 0.
4 .19 HEX. BOLT M5X10 0.
4 .20 HEX. NUT M5 0.

1 86.01 SGB-03296-1 SHAFT 500 2.76


1 .02 SGB-01506-1 SEALING PLATE PIPE-C- 4.67
4 .03 SGB-01077-4 EARTHING KIT 0.01
8 .04 DIN 9021-SS WASHER 8,4
4 .05 TYP 31 HEX. BOLT 0.02
4 .06 TYP 34 HEX. NUT 0.01
2 .07 SGB-02607-2 FRAMING SPACER -A-
2 .08 SGB-02608-2 FRAMING SPACER -B- = 510

1 96.01 SGB-00521-4 DRAIN PIPE 0.023


2 .02 SGB-03602-4 WASHER 0.005
1 .03 SPRING CLIP 10
VACONODECK D= 39000.00 mm 602083 5. 8.2016 -- 8 --

MPP JEDINSTVO A.D. SERBIA 602083-10-00 A/-30-00 A Deck 4694 / 4695

QTY TYP DRAWING TEXT WEIGHT


2 48.01 SGB-71100-4 PE-SEAL -A- 66.78
504 .02 TYP 28 BUTT STRAP 45.36
0 .03 TYP 34 HEX. NUT M8 3.78
504 .04 DIN 933 HEX. BOLT M8x45 A2 10.08
0 .05 TYP 31 HEX. BOLT M8x20 2.52
51 .06 SGB-70947-3 U-PROFILE 156.24
80/40/3x2500 -C-
51 .07 CONN.-STRIP 5.04
BL. 3x72x200 ALMG3
1008 .08 DIN 125 WASHER 8,4 A2 2.52
48 .09 TYP 29.01 CONNECTION STRAP 0.00

60 . .03 POP-RIVET 3,2 x 25 0.00


VACONODECK
6. Installation Manual

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
VACONODECK
INSTALLATION MANUAL
AL- / MIX-P QE²
AL- / MIX-P QE² CLAD

Issue: 01/2014

VACONO ALUMINIUM COVERS GMBH


Friedrichstrasse 50
79618 Rheinfelden
GERMANY

Tel +49 7623 717 86 0


Fax +49 7623 717 86 71

Email: vacono@vacono.com
Website: www.vacono.com
Contents
1 PRELIMINARIES 1
1.1 SAFETY REGULATIONS, FORMALITIES ................................................................ 1
1.2 MATERIAL STORAGE ........................................................................................ 1
1.3 MATERIAL CONTROL ........................................................................................ 1
1.4 TANK CONTROL............................................................................................... 1
1.5 TORCH-CUTTING AND WELDING ON TANK ........................................................... 1
2 FREE VENTILATION 1
2.1 PERIPHERAL SCOOPS ...................................................................................... 1
2.2 SIDE OVERFLOW ............................................................................................. 1
2.3 CENTRE ROOF VENT ........................................................................................ 2
3 INSTALLING THE VACONODECK 2
3.1 FINDING THE CENTRE-LINE ............................................................................... 2
3.2 DISTRIBUTION OF PERIPHERAL ELEMENTS ......................................................... 2
3.3 PERIPHERAL LEGS .......................................................................................... 2
3.4 FITTING SPACING ELEMENTS ............................................................................ 2
3.5 PREPARATION OF FIRST PERIPHERAL ELEMENT .................................................. 2
3.6 PRE-FITTING OF PERIPHERAL ELEMENTS ........................................................... 2
3.7 ERECTION OF PERIPHERAL RING ....................................................................... 3
3.8 DISPLACEMENT OF LEGS WITH OBSTACLES ........................................................ 3
3.9 POSITIONING AND ASSEMBLY OF FRAME WORK .................................................. 3
3.10 CONNECTING THE FIRST CHANNELS .................................................................. 4
3.11 COMPLETION OF FIRST ROW OF FLOATS ............................................................ 4
3.12 COMPLETION OF THE FRAME WORK .................................................................. 5
3.13 DIFFICULTIES WITH UNEVEN TANK FLOOR .......................................................... 5
3.14 LEVELLING ..................................................................................................... 6
3.15 FIXING THE FIXED LEGS ................................................................................... 7
3.16 FIXING THE UPPER POSITION WITH ADJUSTABLE LEGS ......................................... 7
3.17 FIXING THE LOWER OPERATING POSITION WITH ADJUSTABLE LEGS....................... 8
3.18 BOLTING THE PERIPHERAL ELEMENTS ............................................................... 8
3.19 BOLTING THE PERIPHERAL ELEMENTS ............................................................... 8
3.20 BOLTING THE FLOATS WITH LEGS ...................................................................... 9
3.21 RE-CENTERING OF LEVELLED FRAME WORK ....................................................... 9
3.22 FITTING OF SOCKETS AND BOTTOM ANGLES FOR ANTIROTATION CABLES .............. 9
3.23 ALIGNING THE FRAMING SPACER .....................................................................10
3.24 FITTING THE ASSEMBLY SPACERS ....................................................................10
3.25 ALIGNING THE FIRST CHANNEL LINE .................................................................11
3.26 POSITIONING THE FIRST COVER SHEET .............................................................11
3.27 DRILLING THE BUTT STRAPS ............................................................................12
3.28 TRANSFER OF ASSEMBLY SPACERS .................................................................13
3.29 POSITIONING THE FIRST COVER SHEET .............................................................13
3.30 BOLTING THE SHEETS TO PERIPHERY AND POSITIONING THE FOLLOWING SHEETS 13
3.31 METHOD OF MOUNTING SHEET FOR DIFFERENT VACONODECK DIAMETERS .....14
3.32 TIGHTENING THE BUTT STRAPS ON THE CHANNELS ............................................16
I Issue: 09/2012
3.33 COMBINATION AIR VALVE-MANHOLE .................................................................16
4 FITTING THE NEGOTIATING DEVICES 17
4.1 PLUMBING THE FITTING POSITIONS IN THE VACONODECK ..............................17
4.2 ANTIROTATION SYSTEM ..................................................................................17
4.3 FUNNELS ......................................................................................................18
4.4 PIPE-, ROOF COLUMN- AND LADDER NEGOTIATING DEVICES ...............................18
4.5 NEGOTIATING DEVICES FOR AUTOMATIC GAUGING .............................................19
5 FITTING THE SEAL 19
6 FITTING THE ANTISTATIC SYSTEM 19
7 FITTING FLOATS ON PERIPHERY 19
8 ANTISTATIC PAINT 20
9 DRAIN PIPES 20
10 TOOL AND PROTECTIVE CLOTHING LIST
FOR VACONODECK - INSTALLATION 21
11 VACONODECK - INSTALLATION CHECKLIST- 22

II Issue: 09/2012
1 Preliminaries

1.1 Safety regulations, formalities


Before starting work in the depot check with the depot operator on the safety regulations
and other formalities to be observed or completed.

1.2 Material storage


Unload material as close to the tank as is possible and check for any wich may have
occured damage during transport. If damage is found, request a signature from the
vehicle driver immediately and – if possible – notify a representative of the customer.
Report damage immediately to VACONO Aluminium Covers Gmbh.

1.3 Material control


Check material for completeness according to the material list. Report missing items
immediately to VACONO Aluminium Covers Gmbh.

1.4 Tank control


Check that positions of devices, such as dip hatches, auxiliary dip hatches, automatic
gauging, temperature measurement hatch, etc. on the tank roof correspond with the
drawing. Check whether the centre distance of the fittings from the tank wall is
acceptable. Plumb existing roof columns. Consult tank operator in event of uncertainty.

1.5 Torchcutting and welding on tank


If torch cutting and welding operations have to be performed on the tank, the tank
operator must first be asked about the relevant safety regulations.

2 Free ventilation

2.1 Peripheral air scoops


If a tank is provided with peripheral roof scoops and side overflows, the following
procedure must be adapted.

2.2 Side overflow


The total number of peripheral roof scoops and side overflows are distributed regularly
around the periphery. The position must be selected so that no rafter will be damaged
during torchcutting. Determine dimensions from drawing 23540-00D 53456-00D. If the
position of the rafters cannot be clearly determined from above, we would recommend
cutting a small inspection hole in the tankroof and place realign the peripheral air scoops
according. The side overflows are fitted most economically with a mounting basket,
observe the safety regulations. Refer to drawing 23540-00D for installation height.

1 Issue: 09/2012
2.3 Centre roof vent
The centre roof vent can be fitted by welding the steel sockets directly to the tank roof,
see drawing 23541-00D or by mounting it on an existing roof socket no longer required.

3 Installing the VACONODECK


The centre-line in channel longitudinal direction has to be determined before beginning
installation of the VACONODECK. The procedure is as follows:

3.1 Finding the centre-line


Normally a device whose centre must be plumbed down from the tank roof. e.g. automatic
gauging, ladder, funnel, etc. This point has to be marked on the floor of the tank. The
desired centre-line is obtained from here via the tank centre.

3.2 Distribution of peripheral elements


Placed them at the tankwall and complete the ring with peripheral elements (21120). The
alignment of the peripheral elements (21120) shown in the assembly drawing.

3.3 Peripheral legs


An M8x55 (24006) bolt is now inserted hand-tight into the predrilled hole of the leg at the
periphery and the sleeve attached. In the case of adjustable legs, also fit upper part of P-
sleeve hand tight with two M8x55 (24006) bolts. Lay out the legs together with the refer to
drawing 24352-00D / 24353-00D / 24357-00D /24358-00D / 24361-00D or 24362-00D.

3.4 Fitting spacing elements


Bolt a butt strap for peripheral seal (23525) tight as a spacer to each peripheral element
(21120), approx. 300mm from each end. Hole distance as measured from end of butt
strap 190mm + 20mm = 210mm, hole diameter 9mm. Refer to drawing 53357-20-02M.

3.5 Preparation of first peripheral element


Fit a leg sleeve with leg and an PE connector (23526) with M8x20 (24005) bolts at both
ends of the peripheral element first selected, hand tight.

3.6 Pre-fitting of peripheral elements


Provide all other peripheral elements right through to the last one with sleeve, leg and an
PE connector (23526) at one end. Preferably proceed in a clock-wise direction in this
case.

2 Issue: 09/2012
3.7 Erection of peripheral ring
Place first peripheral element at the tank wall and then connect the other peripheral
elements. Preferably proceed in a clock-wise direction and screw up hand-tight.

3.8 Displacement of legs with obstacles


When the ring is closed and a leg meets a pipeline or tank floor recess, the relevant leg
must be displaced far enough to provide a minimum clear spacing of 150mm between the
obstacle and the leg. Only the sleeve with leg is moved, the connection for peripheral
element (23526) remains in position! The sleeve is drilled and bolted at its new position.

3.9 Positioning and assembly of frame work


When the ring is at its required position, assembly of the frame work can commence.





 



Fig. 1
Points M1 and M2 are marked at the centres of the peripheral elements and then a cord is
stretched tightly from M1 to M2. Points T1 and T2 are then marked on the peripheral ring.
The centre is marked on the centre float (23872 8" AL / 23769 10" SS) and a leg sleeve
fitted hand tight at both ends with leg. See Fig.1. The float length can be obtained from
assembly drawing and the appendent partlist.

3 Issue: 09/2012
3.10 Connecting the first channels
R-channels are connected with at least two framing spacers 1521mm (23510) /
2021mm (23571) and screw clamps to form a frame, see Fig.2. Instead of the framing
spacers, spacing devices are used if available. This frame is drilled, boring Ø9mm,
together with the peripheral element at points T1 and T2 and bolted hand-tight. The
centre float is then set with its centre mark under the cord. The two R-channels are set
exactly parallel to the cord and secured with float brackets (23517 8" AL / 23604 10" SS)
to the float. The hole spacing in the lower flange of channel is 240mm for 8" AL float or
290mm for 10" SS float, refer to drawing 53357-20-04M or 53357-20-05M.
T1
T2

Frame
Screw Clamps

Fig. 2
=
= Framing Spacer
ca.1,5m

L1

Fig. 3

3.11 Completion of first row of floats


The external floats (23872 8" AL / 23769 10" SS) are then connected to the centre float
aligned, drilled, boring Ø9mm, and bolted hand-tight to the peripheral element by means
of the float adapter ( 23515 AL / 23601 SS), see Fig.3.
R-channels, are spaced with the aid of framing spacers 1498mm (23511) / 1998mm
(23570) similar to Fig. 2 and connected with peripheral element and external float.

4 Issue: 09/2012
The float line L1 is set up and channels secured on the periphery in this way, regardless
of the size of the VACONODECK, as shown in Fig.3.
IT IS IMPORTANT, THAT THE CHANNELS ARE PARALLEL TO THE CENTRE LINE
AND ARE ALWAYS EXACTLY SPACED !
If it is found that the R-channels-, cannot be connected to the peripheral elements it must
be checked whether they are really too short or whether they are not parallel. The actual
length must then be compared with the value specified in the appendent partlist. In the
event of complaints, the differences should be reported to VACONO Aluminium Covers
GMBH.

3.12 Completion of the frame work


When the first section of the frame work has been erected as shown, the remaining float
lines and channels are fitted as shown in the assembly drawing , until the entire frame
work is closed, see Fig.4.

Fig. 4

3.13 Difficulties with uneven tank floor


If the frame work cannot be closed owing to inclination of the tank floor (convex,
concave), i.e. channels, do no quite reach the peripheral elements or project beyond it for
some reason, levelling must first be performed.

5 Issue: 09/2012
3.14 Levelling
Before levelling, the cover height shown in the assembly drawing must be marked on a
leg at the tank manhole. The marking is suitably made on the lower edge of the sleeve.
For fixed legs, the difference of the lower edges of sleeves between the legs at the
periphery and the legs in the inner area is 59mm, for 8“ AL floats, and 34mm for 10“ SS
floats, as shown in Fig.5.










Fig. 5
For adjustable legs, the lower edges are at the same level.
Starting from the selected leg, the height marked is then transferred with the hose
levelling instrument or laser unit to all other legs.
Levelling with the hose levelling instrument is performed as shown in Fig.5.
Levelling with a laser unit is performed as indicated in Fig.6.

Fig. 6

6 Issue: 09/2012
The bracket is placed on the wall of the tank, where it is held by magnets. The rotary table
is set horizontal with the three adjusting screws. The mark on the first leg is transferred to
all the others by turning the laser – as for the hose levelling instrument. It must be
ensured that none of the legs stands in the shadow of another.

When all legs have been marked, they must be fixed at the correct height.

3.15 Fixing the fixed legs


The leg sleeve is positioned up or down until its lower edge coincides with the correct
mark. The leg is then drilled with the leg sleeve, whereby for the fixed leg the existing hole
in the lower part serves as a template. An M8x55 (24006) screw is then inserted and both
parts screwed together tightly. If the leg projects beyond the upper edge of the sleeve,
which can occur with convex tank floors, the projecting end must be cut off in order to
prevent subsequent damage to the sheet, refer to drawing 53357-20-05M.

3.16 Fixing the upper position with adjustable legs


The height adjustment is made in exactly the same way as for fixed legs, but drilling is
performed in the upper sleeve piece and the screw is only secured hand- tight. An
additional hole has to be drilled just below the compressed upper sleeve piece, later on
when the cover is lowered into the lower service position, shown in Fig.7 and drawing
53357-20-04M.

Fig. 7

7 Issue: 09/2012
3.17 Fixing the lower operating position with adjustable legs
The lower operating position must be clarified with the operator in the case of adjustable
legs. It should be ensured in this case that the distance from the highest steel section
extending into the tank ( pipeline, mixer etc.) and the cover section above is not less than
100mm, see Fig. 8

190

assembly position

service position
min.100

tank wall
diffuser

Fig. 8
The service height determined is measured from the lower edge of the leg sleeve
downwards. The leg is drilled at that point and an M8x55 (24006) screw inserted and
tightened.

3.18 Bolting the peripheral elements


When all legs have been fixed at the correct height, all peripheral elements are first bolted
together securely. It must be ensured that the peripheral elements lie closely together at
the joints and that the legs are vertical.

3.19 Bolting the framing spacer


The framing spacers, shown in drawing 53357-20-08M, are then tightened securely at the
centre of the cover.

8 Issue: 09/2012




  



Fig. 9
It should be noted here that the upper edges of the channels must lie in one plane, that
the bolt spacing is 250mm and that the centreline of the framing spacers is aligned, as
shown in Fig.9.
A connection strap 300mm (23518) is used as an aid to installation. A start is made at the
centre. After tightening, the diameter is measured again over the outer edges of the
peripheral elements, to check whether it coincides with the assembly drawing. If it is too
large, the end-framing spacers must be shortened evenly. If too small, the length of the
other centreline must be established later.

3.20 Bolting the floats with legs


Finally, the floats (23872 8" AL / 23769 10" SS) are tightened, with M8x20 bolts, together
with the leg sleeves, ensuring here too that the legs are vertical.
The R-channel connections and – if present - all other framing spacers are tightened in
the same way.

3.21 Re-centering of levelled frame work


When bolting has been completed, the distance from the tank wall is checked once again
at the peripheral elements. Since no tank or cover is ever perfectly circular, the cover
must now be centred exactly, i.e. that the spacers described in 3.4- where necessary-
must be exchanged with others having the hole spacing now required. One spacer
should be fitted on each peripheral element. The re-centred cover must be rigidly
tensioned against the wall of the tank.

3.22 Fitting of sockets and bottom angles for antirotation cables


The R 3“ sockets for the anti-rotation cable (21403) see drawing 23712-00D, 23764-00D,
23964-00D or 53384-00D, are marked on the tank roof and welded in after cutting the
openings. The centre of the sockets is then transferred to the tank floor with a plumb-bob,
where the floor angle is then welded.

When marking, alignment is taken either from the assembly drawing or – if the points
have to be newly selected- according to the frame work channels, i.e. it must be ensured

9 Issue: 09/2012
that the plumb-bob passes as closely as possible through the centre of a panel and
therefore does not meet a channel or float.

3.23 Aligning the framing spacer


The framing spacer centreline is then accurately aligned. It may be necessary to remove
the connecting screws between R-channel, and peripheral element in order to move the
channel to the required position.

3.24 Fitting the assembly spacers


Spacers for installation are inserted in the centre panel with an distances from 1500mm.
The entire panel is fitted in the case of continuous sheets, half in the case of divided.

Connecting Screws
Spacer
Centreline

Fig. 10 1

10 Issue: 09/2012
3.25 Aligning the first channel line
The channel line A is then accurately straightened from 1 to 2, see Fig.10, and all float
brackets tightened on the float of this line.

A B
Sheet
1
Centreline-Deck

Fig. 11

3.26 Positioning the first cover sheet


The sheet "1" is then placed at the centre on the screws in the centre framing spacer, see
Fig.11 and 12, and unrolled sufficiently for four or six of the screws of the channels A and
B to enter the slotted holes. A check is then made on angularity of the frame work. The
centres of the slotted holes should coincide as closely as possible with the centres of the
screws. If the layout is as shown in Fig.12, channel line a, the sheet can be unrolled
without difficulty. If the screws of channel line B are in the position shown in b or c,
however, the entire channel line must be moved so that the screws lie at the centre of the
hole.Like in channel line a.

Fig. 12 Centerline of framing spacer a b c

If the framing spacer, shown in drawing 53357-20-08M, is displaced to one side or the
other in the direction of the width, so that the screws do not fit the slotted holes, it must be
loosened again at the periphery and set to the correct position.
The sheet is then completely unrolled. If it lies satisfactorily, the channel lines A and B are
screwed tightly at the ends with the peripheral section, see Fig.13. The projecting end of

11 Issue: 09/2012
the sheet is cut off flush at the outside edge of the peripheral section.
With continuous sheets, a start is made in the same way at one end of the centre panel.

Cutt off

Screwed tightly

Fig. 13

3.27 Drilling the butt straps


Peripheral elements and PE-butt straps, are drilled together parallel with the work
described in 3.24. A start is made at the end of panel 1, as illustrated in Fig. 14.

Starting mark
ca.50mm A
A-A
90° turned
A
Panel
1

Fig. 14

The pre-drilled and pre-bent PE-butt strap is clamped with screw clamps on the outer
flange of the peripheral element and acts as a drilling template. The start of the first PE-
butt strap is made on the flange of the peripheral element. The PE-butt straps are drilled
successively preferably in the clockwise direction.
Please note:
A distance of 250mm form the last hole of the PE-butt strap to the 1st hole of the next PE-
butt strap, must be maintained. The PE-butt strap make-up section has to be cut and to fit
on site.

12 Issue: 09/2012
3.28 Transfer of assembly spacers
When sheet 1 has been laid and the channels of lines A an B have been tightly screwed
to the peripheral element, the spacers of length 1498mm / 1998mm are placed in the next
panel preferably in the clockwise direction. It must be ensured that the spacers are always
in line with those in the panel already covered. The final spacer should be placed as far
as possible on the peripheral element, see Fig.15.

Sheet Sheet Sheet


1 Sheet 3 Sheet 5
2 4

Fig. 15 A B C D E F

3.29 Positioning the first cover sheet


The second sheet is laid out in the same way as described in 3.28. When the sheet has
been unrolled and cut away at the periphery, PE-butt straps of the channel line B are
immediately positioned and tightened as securely as possible by hand, see Fig.16.

Fig. 16

3.30 Bolting the sheets to periphery and positioning the following sheets
If two sheets are laid in the 1500mm or 2000mm system, the first PE-butt strap is
immediately placed, the sheets drilled through at the edge-with the PE-butt strap again
serving as a drilling template- and screwed tight. The tank wall spacers must then
immediately be securely fitted again, see Fig. 17.

13 Issue: 09/2012
Tank wall spacer
PE-butt strap

Fig. 17

The spacers from panel 2 are moved to panel 4, see Fig.16, after all float brackets of
channel lines C and D had been secured. The fourth sheet is then laid, the corresponding
straight S-butt strap secured hand-tight and the PE-butt strap section positioned and
screwed tight.

3.31 Method of mounting sheet for different VACONODECK diameters


For sheet sections divided in the middle, see Fig.18, the first quarter is closed in this way.
A start is then made again at the centre on the other side and the first half closed. The
second half is covered in a corresponding way. If sufficient personnel are available, both
sides can be worked on at the same time.

Fig. 18

With through going sheets, a start is also made with panel 1, but from the edge and first
closing one half and then the other. If sufficient personnel are available, both sides can be
worked here simultaneously, see Fig.19.

14 Issue: 09/2012
Fig. 19

With large diameters, i.e. over 30m, all 15m long S-sheets are first laid and then
installation continued – as for a cover with sheet panels divided in the middle, see Fig 20.

Fig. 20

15 Issue: 09/2012
3.32 Tightening the butt straps on the channels
When all sheets have been laid, the edge is screwed tight, i.e. the PE-butt straps
compress the sheets to the peripheral elements. The straight S-butt straps inside the
cover on the overlap are only secured hand-tight. These are now tightened firmly. A start
can be made anywhere.

3.33 Combination air valve-manhole


The valve-manhole combination (23531) is assembled and set in position prior to placing
the final sheet. The position is either given in the assembly drawing or must be agreed
with the operator though in principle it should be fitted close to a tank shell manhole .
The manhole cover must fold in the direction of the tank wall, see drawing 23531-00D. so
that any cables and / or air hoses required for maintenance and inspection purposes
etc. are not obstructed when drawn through the manhole.

16 Issue: 09/2012
4 Fitting the negotiating devices
A check must be made before installing further fixtures whether the cover is still fixed
firmly at the tank centre. Re-tension tank spacers if necessary.

4.1 Plumbing the fitting positions in the VACONODECK


The centre-lines of all auxiliary fixtures as antirotation cable guides, gauging or sampling
funnel, calibrating datum plates, temperature measuring device, automatic gauge, etc. on
the tank roof are then plumbed-down and marked on the cover.

4.2 Antirotation system


The antirotation system, drawing 23712-00D / 23764-00D / 23964-00D / 53384-00D is
fitted as follows:
A hole is cut in the sheet where the cover has been marked – of diameter slightly larger
than the guide pipe approx. 21mm. The cable guide (23534) is inserted and the square
base plate aligned, with a hole-free side parallel to a straight butt strap. The sheet is then
drilled on the pre-perforated sides of the square. The holes are trimmed from underneath.
The two frame sections are centred under the holes and drilled and screwed up with the
channels. The six holes already present in the sheet are also drilled from above through
the frame sections. The cable guide is replaced on the lower side, provided with sufficient
sealing paste (24114) secured with six M8x20 (24005) screws and riveted along the
transverse sides.
The antirotation cable (21403) is secured to the eyebold – as illustrated – which in turn is
attached to the 3“ cap, secured and lowered through the 3“ socket. The 3“ cap is screwed
as tightly as possible by hand. The cable is drawn through the cable guide in the cover
and then secured on the floor together with the spring. The spring is tensioned to 2/3 its
unloaded length with loose lower cable clamp, the cable is then clamped, the second
cable clamp fitted and the remainder of the cable cut off or neatly coiled. See Fig. 22

Fig. 22

17 Issue: 09/2012
4.3 Funnels
When providing gauging funnels, the upper funnel is laid centrally with the mark on the
cover and the internal diameter marked. The circle is neatly cut out, so that no excess
remains inside. The upper funnel is placed on again and aligned with one side of the
square flange parallel to the nearest butt strap. All pre-drilled holes are transferred to the
cover sheet. After drilling, the channels are fitted as described in 4.2 and drilled in a
similar way. Assembly of upper and lower funnels is performed as shown on drawings
23717-00D, 23718-00D and 23719-00D. Where it is planned to include nylon membranes,
it must be ensured that the slots running at 60° do not overlap.

4.4 Pipe-, roof column- and ladder negotiating devices


The provision of negotiating devices for pipes, roof supports or ladders see drawing
23725-00D, 23727-00D, 23728-00D or 53117-00D, is carried out in basically the same
way as described in 4.2 and 4.3. It must be ensured when laying the sheet, however, that
it is damaged as little as possible.
sheet cut
sheet cut out
1540/2040
sheet

pipe
Fig. 22

sheet cut
sheet cut out
1540/2040
sheet

column

Fig. 23
The sheet is cut open on one side for negotiating devices near the wall of the tank and
sufficient material cut out around the pipe entering to permit the remaining sheet slot is
later sealed with waste sheet, sealing paste (24114) and pop rivets (24018). The sheet is
cut right through for roof supports inside the tank, see Fig. 22, in order to avoid
deformation when further unrolled, Fig.23.
The seal firmly inserted in the sealing plate must be inspected before the two halves of
the plate are riveted together, to check whether it provides an efficient seal. Modify if
necessary. Ensure when riveting together that the rivet heads are on the underside of the
plate.

18 Issue: 09/2012
4.5 Negotiating devices for automatic gauging
In the case of automatic gauges already fitted with guide cables attached to roof and floor,
the cables are removed before fitting the cover. The float is drawn up from the roof for
plumbing, without it slipping out of its strip guide. After fitting the shaft, the cover is
positioned with the measuring tape guide at a negotiating device with guide rods, see
drawing 23722-00D. The measuring tape is released from the float and- after the seal has
been slit at the centre of the cover- drawn through the slit. The float is then reattached.
The two guide rods are then fitted so that there is at least 50mm safety spacing left
between their lower end and the floor of the tank. Warning: This spacing must apply to the
lower service position in the case of adjustable legs.
For floats without eyelet guides, a guide cage, see drawing 23723-00D, riveted to the
shaft, is used and the safety spacing of 50mm must also be observed here.
In the case of automatic gauges suitable for calibration to drawing 23721-00D, the lower
edge of the pipe-shaped shaft must also have a safety spacing of at least 50mm from the
floor.

5 Fitting the seal


Installation procedures for VACONOSEAL are described in the separate project
documentation.

6 Fitting the Antistatic system


The antistatic cables, see drawing 23713-00D, are usually taken from a roofmanhole
hatch to the cover.
The cables are first firmly secured to the screws in the roofmanhole hatch. A metallic
connection must be provided, i.e. paint and rust must be removed, so that the spring
washer can grip the hatch material. Check with an ohmmeter if possible.
The attachment points on the cover must be selected so that the cables are not
obstructed by any other vertical tank fitting. The lower service position must be taken into
account during installation in the case of adjustable legs.

7 Fitting floats on periphery


The floats are finally fitted on the periphery according to assembly drawing and drawing
53357-20-05M.

19 Issue: 09/2012
8 Antistatic paint
The painting work to TRbF 120 if necessary, the areas to be coated are specified on
assembly drawing. The areas indicated are marked and cleaned and then painted with
the green primer,Type 94, (mixing ratio paint to hardener 7:1). The black top coat (mixing
ratio paint o hardener 4:1) is applied when the undercoat has dried.

9 Drain pipes
The drain pipes are mounted as per drawing 23536-00D, 23942-00D, 53363-00D or
53405-00D, 1 pc. per sheet - in the center of the sheets.

20 Issue: 09/2012
10 TOOL AND PROTECTIVE CLOTHING LIST
FOR VACONODECK - INSTALLATION

1.) 3 No. Power drill, 12,5mm chuck


2.) 15 No. 8,5mm drilling bits
3.) 15 No. 5,0mm drilling bits
4.) Extension cable to allow easy movement of power tools around tank area
5.) Adequate lighting for work inside tank
6.) Up to 60 m. of clear plastic hose 12mm dia., depent on tank diameter!
7.) 2 No. Screw driver
8.) 8 No. 13mm and 1No. 10mm Combination Spanner
9.) 3 No. Tin snip or Scissor
10.) 3 No. 5 meters Tape Measure
11.) 3 No. Hacksaw and 10 spare blades
12.) 5 No. Marker pens
13.) 3 No. Silicon pistol
14.) 2 No. Pop rivet gun to suit 4,8mm rivets
15.) 2 No. Rubber and 2 metal hammer
16.) 1 No. Stanley marking knife
17.) 10 No. 3m Wooden scaffold boards
18.) 3 No. Electric ratchet spanners with 13mm sockets

PROTECTIVE CLOTHING :
1.) Overall
2.) Protective boots
3.) Gloves
4.) Dust mask

21 Issue: 09/2012
11 VACONODECK - INSTALLATION CHECKLIST-

1. DECK BOTTOM SIDE Check Mark

1.1 Frame work,


53357-20-03M
Screw joints, complete and tight

1.2 Floats,
53357-20-06M
Blind rivets, upwards
Brackets, complete and tight

1.3 Support legs,


53357-20-04M, 53357-20-05M
Vertically installed
Screw joints tight
Nylon plugs complete
Support legs do not extend above the upper rim
of the fixed leg sleeve _____

1.4 Pipe,Ladder, Column negotiating devices,


23725-00D, 23727-00D, 23728-00D, 53117-00D
Screw joints tight
Rivet joints tight
Sealing correct

22 Issue: 09/2012
1.5 Automatic gauging devices,
23722-00D, 23723-00D
Screw joints tight
Rivet joints tight
Sealing correct
Distance between lowest edge and tank bottom min.50mm

1.6 Manhole valve combination, Vacuum-valve,


23531-00D, 23545-00D
Screw joints tight
Rivet joints tight
Sealing correct
Nylon plug for opening rod inserted

1.7 Gauging funnel,


23717-00D, 23718-00D, 23719-00D
Screw joints tight
Rivet joints tight

1.8 Antirotation cable guide,


23712-00D, 23764-00D, 23964-00D, 53384-00D
Screw joints tight
Rivet joints tight

1.9 Drain pipes,


23536-00D, 23942-00D, 53363-0D, 53405-00D
Pipes well sealed
Spring clips tight

23 Issue: 09/2012
2. TANK BOTTOM Check Mark

2.1 Anti-rotation system,


23712-00D, 23764-00D, 23964-00D, 53384-00D
Bottom anchor completely fillet welded
Cable clamps tight
Spring strained to approx. 90 mm

2.2 Diffuser
Diffuser is installed pointing to tank centre
Diffuser horizontally installed
Support welded to diffusor
No welding between support and tank bottom

24 Issue: 09/2012
3. DECK TOP SIDE Check Mark

3.1 Clamping channels,


53357-20-03M
Peripheral clamping channels tight
Sealing blocks inserted
Straight clamping channels tight
Additional bolts inserted at the ends of the clamping channels
Connection butt straps at channel joints installed

3.2 Adjustable legs,


53357-20-04M
Screws ( 4 each ) are upper sleeves tight
Additional drilling to 80 mm under leg tip
Legs easily movable in the leg sleeves

3.3 Valve - Manhole combination


23531-00D
Hinge bolted tight
Sealing at cover installed
Well corners sealed
Cover lifts to 150 mm at it's lowest deck position

3.4 Vacuum-valve
23545-00D
Cover plate lock nuts are tight
Cover plate lifted for 150 mm in the lowest deck position
Opening road easily movable in the sleeve

25 Issue: 09/2012
3.5 Pipe, Ladder, Column negotiation devices
23725-00D, 23727-00D, 23728-00D, 53117-00D
Well flange sealed
Rivet joints tight
Sealing plate riveted ( Heads downward )
Antistatic cables installed

3.6 Automatic gauging device


23722-0D, 23723-00D
Well flange sealed
Cover secured with two rivets

3.7 Gauging funnel,


23717-00D, 23718-00D, 23719-00D
Nylon diaphragm installed

3.8 Antistatic system,


23713-00D
Deck connection tight
Tape or cable or automatic gauge is not impeded
by antistatic cables

3.9 PE seal, 23709-00D, SGB-71117-4


Double PE seal, 23710-00D, SGB-71142-4
Lip fitted well into tank shell in up and downward position
Lip seal is showing downwards
Butt straps tight

3.10 Teflon T seal, 23701-00D


Double T seal, 23705-00D
RTS seal, 23708-00D
Lip is fitting well to tank shell
Seal joint is sewn and sealed
Butt straps tight

26 Issue: 09/2012
4. TANK ROOF Check Mark

4.1 Antirotation-system,
23712-00D, 23764-00D, 23964-00D, 53384-00D
Socket and reinforcing flange completely fillet welded

4.2 Antistatic-system,
23713-00D
Cable clamping bolts tight
Resistance test executed ( reading: Zero Ohm )

27 Issue: 09/2012
VACONODECK
7. Type Sheets

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
Klemmprofil, U-K
butt strap, peripheral
22001

M8
24016

Dichtstück
sealing block
24207

Umfangselement
peripheral profile
21120
M8x65 M8
24025

M8x20
24005

Verbinder - U
PE connector
23526
-
This article replaces type

Randbereich AL-P QE² Artikel Nr.


rim section AL-P QE² Item No. 53357
Doc. No: 53357-20-07-M
Vacono Aluminium Covers Ref. DWG:
Subject to change withaut notice
This document is our property and given for personal use only. It may not be copied or made available to others without our permission. The receiver is responsible for any misuse. This drawing and the information contained herein is for documentation
purposes only. Although care has been taken to ensure the accuracy, completeness and reliability of the information provided, VACONO assumes no responsibility therefore.
IN NO EVENT SHALL VACONO BE LIABLE FOR ANY DIRECT, INDIRECT, SPECIAL OR INCIDENTAL DAMAGE RESULTING FROM, ARISING OUT OF OR IN CONNECTION WITH THE USE OF THE INFORMATION.
Deck sheet Framing spacer
for accessories (2x)

Guide tube 12"


AL-P QE Channel

Bottom plate

Top funnel 12"


A ( 1 : 10 ) #23813

Frame cross Bolted connections


profile (2x) Hex bolt M8x20 (#24005)
Hex nut M8 (#24016)

Schwimmerf hr. Autopeilung ENRAF 12" Artikel Nr.


Float Guide ENRAF 12" (CUSTOM PART) Item No.
Doc. No: CUSTOM PART
Vacono Aluminium Covers Ref. DWG: CUSTOM PART
Subject to change without notice
This document is our property and given for personal use only. It may not be copied or made available to others without our permission. The receiver is responsible for any misuse. This drawing and the information contained herein is for documentation
purposes only. Although care has been taken to ensure the accuracy, completeness and reliability of the information provided, VACONO assumes no responsibility therefore.
IN NO EVENT SHALL VACONO BE LIABLE FOR ANY DIRECT, INDIRECT, SPECIAL OR INCIDENTAL DAMAGE RESULTING FROM, ARISING OUT OF OR IN CONNECTION WITH THE USE OF THE INFORMATION.
VACONODECK - Material List “AL-P QE²”

Parts Dimensions Material Designations


(Material Thickness) DIN AA/AISI
------------------------------------------------------------------------------------------------------------------------
Seal Polyurethane, Polyethylene
PTFE (Teflon)

Floater
Tube 1,3 mm AlMn1Mg1 3004
End Cap 2,5 mm Al Mg 3 5754
Floater end brackets 2,0 mm Al Mg 3 5754

Cover Sheets 0,5 mm Al Mn Cu (hh) 3003-H16

alternative:
Cover Sheets 0,5 mm
Core Al Mn Cu (hh) 3003-H26
Cladding min. 5 % each side Al Zn 1 7072
Extruded Sections
Rim profile 2,5 mm AlMgSi0,5 F25 6063
Crossing profile (lower) 1,8 mm (3,0 mm) AlMgSi0,5 F25 6063
Crossing-profile (upper) 3,0 mm (2,0 mm) AlMgSi0,5 F25 6063

Cover Supports 42 ø x 3,0 mm AlMgSi0,5 F25 6063

Negotiation Devices
Gauging 1-1,5 mm(flange 1,5 mm) Al Mg 3 5754
1,0 mm (flange 1,5 mm) 1.4301 (stainless steel)
Manhole 1,5 mm (cover 5 mm) Al Mg 3 5754
1,0 mm (cover 3 mm) 1.4301 (stainless steel)

Uni. Brackets 1,5 mm 1.4571 316 Ti

Bolts M 8 x 20 1.4301 (stainless steel)


M 8 x 35 (cross-profile) 1.4301 (stainless steel)
M 8 x 55 (supports) 1.4301 (stainless steel)

Nuts M8 Al Mg Si 1 F 23 6082
(stainless steel optional)

VACONODECK Material list_e 01-2014.doc 28.01.14


VACONODECK
8. Calculations

Order No. : PR-17440 / 602083


Customer : MPP Jedinstvo a.d.
Location : Novi Sad / Serbia
Tank No. : A-5505 / A-5506
Tank  : 39,000m
Deck No. : 4694 / 4695
“Report to be found on CD”

Vacono Aluminium Covers GmbH


Postfach 11 65 D 79601 Rheinfelden
Friedrichstr. 50 D 79618 Rheinfelden

Tel.: +49 (0) 7623 71786-0


Fax: +49 (0) 7623 71786-71
vacono@vacono.com
www.vacono.com
FACT SHEET
Customer: MPP Jedinstvo a.d.

Vacono Project 17440


Reference drawing (VAC): 602083-10-00 A / 602083-30-00 A

Material List Deck No. 4694 / 4695


Tank Diameter 39,000 m
Vacono DECK 38,620 m

Tank: A-5505 / A-5506

Tank height: 18,097 m

MAX. DECK CLEARANCE


(under skin)
AT LOWEST POINT IN TANK : 1,800 m

Product density 700,00 kg/m³

issued 02.11.2016

Deck Calculation compliant API 650 Appendix H (12th ed)

Content:

1. Calculation of Ratio Buoyancy / Weight (Page 2)

2. Calculation of Deck Ventilation (Pages 3)

3.Leg Check (Page 4)

Remark
Accessories as per parts list are included

Rev No Date Description DRWN CHKD REVD APPD


Calculation of Ratio Buoyancy / Weight Vacono Project 17440
Mechanical Calculation, Document Code: 4694 / 4695 -DECK-Calkulation
Vacono Internal Floating Roof :
Reference drawing (VAC): 602083-10-00 A / 602083-30-00 A
Customer: MPP Jedinstvo a.d.
Issued: 02.11.2016

Total Floater Length [mm] = 455.660 mm

Diameter Buoyant Elements ('Floats')


ø= 203 mm = 8,0 inches
Net Hollow Cross Section Area = ø ² / 4 * P = 203,00 mm² / 4 * P = 0,0324 m²
4759,62 kg
Total Dead Weight of Deck = 46,692 kN equ. 1,729 m³ of AL
Seal friction 0,61 kN 5 N/m
Total required Lift force 94,00 kN 2xDead weight +1x seal friction
Hollow Measure (Volume [m³])

V = total length * Net. Sec. Area = 455,660 m * 0,0324 m² = 14,7477 m³

Unit weight fluid g = 700 kg/m³ (6,867 kN/m³ ) as per API 650 12th Add. H 4.2.1.1 6,87 kN/m³

(1)Hollow Buoyant Lift Force = g * V, void = 101,272 kN (Hollow) 14,748 m³


(2)Solid Buoyant Lift Force = g * V,solid 11,875 kN (solid) 1,729 m132

total buoyancy = 113,15 kN

Ratio Dead Buoyancy/Weight = 120,374%

Note 1: a.m. ratio MUST exceed 100%


(API 650 12th ed. Appendix H, § 4.2.1.2)

Note: Requirement is met!

Reduced Ration Dead Weight/Buoyancy 2 Floats defective compl. API 650 App H 4.2.1.3
* two biggest floaters are considerd
Length of longest floater [mm]
1 5600
2 5600

Floater length excl. 2 longest floaters 444,46 m 14,385 m³


Ratio Dead Buoyancy/Weight = 212% 98,783 kN

Note: Requirement is met


Calculation of Valve-Manhole-Combination Vacono Project 17440

Mechanical Calculation, Document Code: 4694 / 4695


Vacono Internal Floating Roof :
Reference drawing (VAC): 602083-10-00 A / 602083-30-00 A
Customer: MPP Jedinstvo a.d.
Issued: 02.11.2016

The calculation situation of valve-manhole combination is considered open. Usually hatch is closed, except
when landing on bottom plate. (150mm open, when on ground)
Assessment of boundary conditions
Qty of vent units n= 2 pcs.

Gapping Area = n * ( 2 * 1/2*0.500 * 0.150 + 0.600*0.150) [see sketch above]

Max. discharge velocity 11,21 m/s equals 8 mmWC per API 2000
Gapping Area = 0,33 m²

Q = 4/5 * √( 1600 * p) * A 0,8 coefficent for orifice flow friction


in reference to EC1; BS EN 1991-4: 2005+A1:2010; based on DIN 1055
a. outstream rate
b. instream rate
add. a
Deck has a loading capacity of 0,25 kN/m² thus this pressure difference furnishes in-stream:
Discharge velocity 11,21 m/s (fluid emptying mode)

Q= 2,958 m³/sec = 10649,909 m³/hour


Utilisation ratio η = 0,117 or 11,737 %
add. b
Deck has a distributed dead weight of 0,040 kN/m² thus this pressure difference furnishes out-stream:
Discharge velocity 7,99 m/s (fluid filling mode)

Q= 2,108 m³/sec = 7589,792 m³/hour


Utilisation ratio η = 0,165 or 16,469 %

specified pumping out rate of 1000 m³/h complies to API 650 by 2 vents
specified pumping in rate of 1000 m³/h complies to API 650 by 2 vents
Note: This calculation is set up in compliance to API 650 H.5.2.1
LEG (BUCKLING) Check Vacono Project: 17440
in reference to API 650 12th ed. Appendix H, § 4.2.1.2 / 32-SAMSS-005 H 4.2.1

Customer: MPP Jedinstvo a.d.


Vacono Internal Floating Roof :
Reference drawing (VAC): 602083-10-00 A / 602083-30-00 A

Issued: 02.11.2016

Capacity Compressive Load[kN] of Legs | Eulerian Case : ß= 2


in reference to DIN EN 1999-1-1:2014-03 (E) EC 9 Part 1-1; 6.3

leg material ALU


Buckling resistance [kN/cm²] 7000
leg diameter ø [mm] 42
wall thickness t [mm] 3
 3
I
moment of inertia
for leg section size I-y[cm ] 4
8,728 td
length of leg l [m] 1,485 8
 2 EI
allowable
kN 6,836
buckling load
Fb  2 2
Qty of Legs [-] 98 l
Dead Weight kN 46,692
per Leg kN/Leg 0,476

Area of Deck m² 1171,425 in reference to


Unit Load kN/m² 0,240 API H 4.4.2.1
Conc. Load per leg kN 2,869

in reference to
Conc.LL = kN/0.1m² 2,2 API H 4.2.1.4

Active Load kN 3,345

Utilisation
Buckling
48,93%
Remark : Utilisation for buckling must be lower than 100%
Note: Requirement is met!

page 3

You might also like