You are on page 1of 27

Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site

WEEKLY PROGRESS REPORT


LOT-I WWTP1 Date: 25 November 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No meeting conducted and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Footing Pad Excavation and lean concrete pouring for PTU
-lean concrete pouring and form work fixing for base slab at Aeration Sludge Tank
-Backfilling with suitable material under base slab of Areation sludge
tank and gravity thickners
-Base Slab formwork and water stop fixing at Biological
treatment unit -Top tie beam and roof slab form work
fixing at Control Building
6 E-M Installation Activities: NA
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological
treatment, Aeration Sludge Tank and Control Building, water stop for Chilorination tank,
embeded pipes for gravity thickners
-No sufficient stock of fine and course aggregates at site.

12 Any Other Remarks: NA

Signature Mesfin D.
minium Site

esfin Derbew

b at Aeration Sludge Tank


lab of Areation sludge

ing at Biological
nd roof slab form work

ebar for Biological


Chilorination tank,

urse aggregates at site.


Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 04 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: Meeting conducted on 24/11/2017 and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Footing Pad C-30 Concrete pouring and Foundation Column Formwork fixingfor PTU
-Backfilling with suitable material and lean concrete pouring
under base slab at Gravity Thickener
-Base Slab formwork and
water stop fixing at Biological treatment unit -Top tie beam
and roof slab form work fixing at Control Building
6 E-M Installation Activities: NA-X-stop Water stop positioning on chilorination tank
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment,
Aeration Sludge Tank and Control Building, water stop for Chilorination tank, embeded pipes for
gravity thickners
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for reinforcement supply.
accordingly we have issued an instruction letter to deliver sufficient quantity of construction
materials which is affecting the quality and progress of works.
12 Any Other Remarks: NA

Signature Mesfin D.
minium Site

Mesfin Derbew

work fixingfor PTU


al and lean concrete pouring

-Base Slab formwork and


-Top tie beam

ebar for Biological treatment,


on tank, embeded pipes for

ting for reinforcement supply.


quantity of construction
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 18 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Backfilling under PTU seat and around foundation columns completed -Masonary work under gra
beam -C
Pouring for 1/9th porition of the Biological treatment unit base slab

-Top tie beam and roof slab form work fixing at Control Building
-Water stop and wall form work positioning and fixing on chilorination tan
6 E-M Installation Activities: NA -HCB block work placing for chemical building

7 Testing and Commissioning: NA


8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment, A
Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for
reinforcement supply.
12 Any Other Remarks:
-Diameter 20mm bars has supplied on Saturday 16 December 2017 and Contractor requested to
rebar bending and placing for porition of Biological treatment unit paused b/c of 20mm diam
parallel to taking samples for quality tests. The Contractor's representative informed by letter tha
will be failure up on test results, they will take the risk and will remove from site accordingly.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

ed -Masonary work under grade


-Concrete

rol Building
and fixing on chilorination tank
uilding

ebar for Biological treatment, Aeration

rse aggregates at site.


ete level and are waiting for
and Contractor requested to continue
t paused b/c of 20mm diameter bars
entative informed by letter that if there
e from site accordingly.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 25 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Lean Concrete pouring under PTU seat, C-30 Concrete pouring under PTU seat below ground le
Ground Elevation columns of PTU unit are completed
-Concrete Pouring for Chilorination tank wall

-HCB block work


for chemical building
6 E-M Installation Activities: NA
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment, A
Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for
reinforcement supply.
12 Any Other Remarks: -Supplied Diameter 20mm bars has failed to satisfy the minimum ASTM A615 requirements and h
Contractor didn't started any activity on Biological treatment unit.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

der PTU seat below ground level and

-HCB block work placing

ebar for Biological treatment, Aeration

rse aggregates at site.


ete level and are waiting for

STM A615 requirements and hence the


Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 01 January 2018 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Concrete pouring for above ground PTU seat and first intermidiate beam
- second lift wall formwork preparation on
chilorination tank

-Plastering of HCB block wall for chemical building

6 E-M Installation Activities: NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biologic
treatment, Aeration Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggre
site. -Most of units are on lean concrete level
waiting for reinforcement supply.
12 Any Other Remarks: -We have forwarded EOT Approval to the Employer with Completion date 13 July 2018
Contractor has been requested to submit Master work schedule according to the EOT. He
Contractor has submitted Guant chart Master schedule on Saturday 30 December 2017.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

beam
wall formwork preparation on

einforcement rebar for Biological


ng.
tock of fine and course aggregates at
ts are on lean concrete level and are
mpletion date 13 July 2018 and the
e according to the EOT. Hence, the
30 December 2017.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 10 January 2018 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: a health and Safety Meeting was held and No accident yet
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Formwork placing and fixing of Biological Treatment unit on portion of poured base slab concrete
-Rebar cutting, bending and fixing on portion of base slab p
due to shortage of dia. 20mm bars -Formwork fixing of second elevation column for PTU unit
-Second lift wall for
preparation on chilorination tank -C
buldged concrete on 1st lift walls of Chilorination Tank
6 E-M Installation Activities: NA
-Plastering of HCB block wall for chemical building
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: The Contractor has submitted IPC #3 and is under evaluation
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biologic
treatment, Aeration Sludge Tank, Gravity thickner and Control Building.
-Fine and coarse aggregates are now suppl
site but still waiting for quality tests due to late request for joint sampling.
-Most of units are still on lean concrete level and are
for reinforcement supply.
12 Any Other Remarks: -Failed reinforcement has been removed by the contractor from site and other new dia. 20m
supplied to site. A joint sample was taken from the newly supplied and the test result is satisfacto
the specification. Accordingly, they have started cutting, bending and placing of the rebar on port
BT unit which was paused due to shortage of 20mm bars.
-The contractor has supplied new quality form work and his staffs has been tra
foreigner proffessional formwork Engineer. Accordingly, they have started placing and fixing of
form work for Biological Treatment unit first lift wall on portion of poured base slab.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

of poured base slab concrete


xing on portion of base slab paused
levation column for PTU unit
-Second lift wall formwork
-Correcting

r chemical building

einforcement rebar for Biological


ng.
se aggregates are now supplied to
ling.
on lean concrete level and are waiting
site and other new dia. 20mm bar is
nd the test result is satisfactory as per
d placing of the rebar on portion of the

rk and his staffs has been trained by a


started placing and fixing of the new
red base slab.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 10 January 2018 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Formwork placing and fixing of Biological Treatment unit on portion of poured base slab concrete
-Rebar cutting, bending and fixing on portion of base slab p
due to shortage of dia. 20mm bars -Formwork fixing of second elevation column for PTU unit
-Second lift wall reb
formwork preparation on chilorination tank

-Plastering of HCB
6 E-M Installation Activities: NA
wall for chemical building
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: The Contractor has submitted IPC #3 and forwarded for Client's approval
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biologic
treatment, Aeration Sludge Tank, Gravity thickner and Control Building.
-Fine and coarse aggregates are now suppl
site but quality testb results are not yet submitted.
-Most of units are still on lean concrete level and are waiting for reinforceme
supply.
12 Any Other Remarks: -Pouring of C-30 concrete for porition of Base slab scheduled for Sunday 21 January 2018 has p
to Tuesday 23 January 2018 due to extended holiday on the way between batching plant and th
site.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

of poured base slab concrete


xing on portion of base slab paused
levation column for PTU unit
-Second lift wall rebar and

-Plastering of HCB block

roval

einforcement rebar for Biological


ng.
se aggregates are now supplied to

nd are waiting for reinforcement


unday 21 January 2018 has postponed
between batching plant and the project
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 29 January 2018 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -C-30 Concrete pouring for Biological Treatment unit base slab (one portion out of nine)
-Formwork placing and fixing of Biological Treatment unit on portion of previously poured base sla
-Formwork fixing and C-30 Concrete pouring of seco
elevation column for PTU unit
-Second lift wall form work and reinforcement bars preparation on chilorination tank ba
comments given.

-Plastering of HCB block wall for chemical b


-FormW
checking (due to work paused for long time after fixing) and roof slab reinforcemewnt bending and
6 E-M Installation Activities: control
NA building

7 Testing and Commissioning: NA


8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biologic
treatment, Aeration Sludge Tank, Gravity thickner and Control Building.
- The Contractor has submitted quality test r
fine and coarse aggregates and hence results show that coarse aggregate and sand sample no. 2
minimum specification requirement.
-Most of units are still on lean concrete level and are waiting for reinforcement supply.
12 Any Other Remarks: -The Contractor has supplied Diameter 16 and 10mm reinforcement bars, jointly sampled for te
results are not yet submitted.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

portion out of nine)


of previously poured base slab
-30 Concrete pouring of second

ration on chilorination tank based on

HCB block wall for chemical building


-FormWork
b reinforcemewnt bending and fixing at

einforcement rebar for Biological


ng.
or has submitted quality test results of
regate and sand sample no. 2 satisfy

for reinforcement supply.


nt bars, jointly sampled for testing but
Employer: AAWSA - WSDR PO, Consultant: SWS Consult, Contractor: Tsemex Global Enterprise PLC.

Construction of Decentralized Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
Date: 05 February to 10 February 2018
LOT-I WWTP1 Prepared By: Mesfin Derbew and Michael Haile
1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community:
NA
4 Contractual Issues:
LC still pending and the contractor has submitted CV for EM expert
5 Civil Construction Activities: Biological Treatment unit - Formwork placing and fixing of on portion of poured base slab 1 completed,
Formwork fixing on a section of base slab 2 commenced with local formwork,
- Rebar cutting, bending and fixing on the rest of the
structure paused due to shortage of dia. 20mm bars
Pretreatment unit - Intermediate beam concrete casted, -
Formwork, rebar fixing and concrete casted for 4 members of 3 rd elevation columns which will not have a
relation to E-M works.
Chlorination Building -Second lift wall concrete casted
Aerated storage sludge tank (SST) - No activity due to shortage of 20 mm Reinforcement bars,
Final Clarification tank - excavation commenced on 10 b, Hard Rock encountered
Sludge dewatering building (DWB) - Foundation excavation commenced and 14 pits completed
6 E-M Installation Activities: NA
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: N/A
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biological
treatment, Aeration Sludge Tank, Gravity thickener and Control Building.

-Most of units are still on lean concrete level and are waiting for reinforcement supply.

12 Any Other Remarks: Contractor has requested change of wall reinforcement bar for SST unit from 20mm to 16mm on the lower
half of the wall. Accordingly, we have checked and rejected it because the upper half reinforcement bars dia.
12c/c 170 will not align with the lower half reinforcement bars on placing dia. 16c/c 110mm.
Also Contractor has requested Change of reinforcement bar for footing bad of Dewatering Building (DWB)
from dia. 12 mm to 10 mm with equivalent area and request approved,
Also Contractor has requested change of reinforcement bar for SST wall from dia. 20 mm c/c 170mm on
lower half and 12 mm c/c 170 mm on upper half to 16 mm c/c 110 throughout the wall for the 2nd time.

Prepared by : Michael Haile

You might also like