OUTLINE

1. What is planning?
2. Nature of Planning
3. Procurement Planning
3.1 Importance of Planning
3.2 Preparing the PPMP
3.3 Preparing the APP
4. Procurement Monitoring
4.1 Importance of Monitoring
4.2 Preparing the PMR

2
3
PHILIPPINE PROCUREMENT PARADIGM

Assess • Review studies • Post/Advertise Procure


• Consolidate into APP opportunity
• Decide procurement • Open and evaluate
method bids
• Approve APP • Post-qualify
• Determine readiness • Award and enter into
contract

Identify • Cost-benefit analysis • Oversee Implement


• Feasibility study implementation
• Market study • Inspect and accept
• PPMP deliveries
• Release payment

Capacity Development Division 4


PLANNING

PLANNING

- refers to predetermined
course/s of action to achieve a
desired end/goal.

Capacity Development Division 5


PROCUREMENT PLANNING

PROCUREMENT PLANNING

“Process of identifying which


project needs can be best met by
procuring products and services
outside the project organization
and should be accomplished
during the project planning
effort”

6
WHY PROCUREMENT PLANNING
 Procurement Planning ensures that the overall goal of a
particular project will be effectively and efficiently
achieved.

 Precludes occasions for unnecessary government


purchases and circumventions of the prescribed
procurement procedures

− advance deliveries
− suki system
− unwarranted resort to alternative methods
procurement

 However, it must be done within budgetary context

7
SECTION 7.1 OF IRR
Procurement Planning and Budgeting Linkage

 Within approved budget of procuring entity


 Judiciously done
 Consistent with government fiscal measures
 Considered crucial to the efficient discharge of
governmental functions
o Required for the day-to-day operations
o In pursuit of the principal mandate of the procuring
entity concerned
 The APP shall include provisions for foreseeable
emergencies based on historical records.
8
SECTION 7.2 OF IRR

• No procurement unless in accordance with the Annual


Procurement Plan (APP)

• Approval of Head of Procuring Entity (HOPE) or


designated second-ranking official

9
ACTORS IN PROCUREMENT
PLANNING

TECHNICAL
END USER WORKING GROUP
BUDGET
OFFICE (TWG)

BIDS AND AWARDS


APPROVING
COMMITTEE (BAC) &
AUTHORITY/HoPE 10
AND BAC SECRETARIAT
PROJECT PROCUREMENT MANAGEMENT
PLAN (PPMP)
 A guide document in the procurement
and contract implementation process, as
well as a vital reference in procurement
monitoring.
 Tool allowing the PE the flexibility to
optimize the utilization of scarce
resources.

 Minimize the practice of doing short-cuts


 Prepared by the end-user unit during the budget preparation to
support the cost estimates in the budget proposal.
 The end-user or implementing units shall be responsible for the
preparation of all documents necessary for the procurement
activity, including but shall not be limited to, the technical
specifications, scope of work, or terms of reference
11
PPMP SAMPLE FORMAT

12
PROJECT PROCUREMENT
MANAGEMENT PLAN (PPMP)

Contracting
Arrangement

Estimated Type and


budget Objective

PPMP
Time
Extent/size
schedule

Procurement
methods

13
IDENTIFYING THE NEED

Suggested basis for identifying needs:

1. Core functions of the end-user unit in the


organization, i.e Accounting, Legal etc.
2. Historical data/Foreseen contingencies;
3. Identified purpose/goals/MFOs;
4. P.E’s Strategic Plans;
5. Current supply inventory;
6. Other maintenance and operating needs.

14
TECHNICAL SPECIFICATIONS, SCOPE
OF WORK, AND TERMS OF REFERENCE
 Consult Stakeholders
 In developing the project requirements and TS/SOW/TOR, the
Procuring Entity may engage the services of technical
experts, whether in-house or consultants, to ensure that the
requirements and the TS/SOW/TOR are adequate to achieve
the objectives of the particular procurement.
 Set clear Specifications:
– Generic and flexible
– Clear and unambiguous
– Reminder on Reference to Brand Names (Section 18)
– Updated, where technology is taken into account
– Fits the actual requirements of the PMO/End-user

15
APPROVED BUDGET FOR THE
CONTRACT (ABC)
 The ABC reflected in the APP and PPMP shall be consistent
with the appropriations for the project authorized in the
GAA, continuing and automatic appropriations, the
corporate budget, and the appropriations ordinance, as the
case may be.
 For multi-year contracts, for which a Multi-Year Obligational
Authority (MYOA) or an equivalent document is required, the
ABC shall be that incorporated in the project cost reflected
in the MYOA or equivalent document
 For Foreign-funded Procurement, the ABC refers to the cost
estimate prepared by the PE and approved by the foreign
government/foreign or international financing institution as
specified in the Treaty or International or Executive Agreement

16
APPROVED BUDGET FOR THE
CONTRACT (ABC)
 End user to conduct market study
 Market price, inflation and cost of money related to the
procurement time table must also be considered.
 In determining the ABC, the end-user unit, with the
assistance of the TWG (when necessary), must consider
the different cost components.

17
PROCUREMENT MILESTONES

18
PROCUREMENT MILESTONES

19
PROCUREMENT MILESTONES

Factors to consider in identifying procurement timelines:


1. Budget rules, i.e. CSE – every quarter;
2. Nature of Procurement Projects, whether simple or
complex
3. For shopping/small value procurement, give at least
two weeks
4. Foreseen/Unforeseen Contingencies, i.e. frequent
change in specifications, etc.
5. Availability in the market.

20
METHOD OF PROCUREMENT

 As a general rule, all procurement should be through


public bidding

 The selection of the method of procurement is


dependent on the presence or absence of specific
conditions of other methods of procurement in Sections
48 to 54 of the revised IRR

21
PPMP vs PR

 Purchase Request (P.R.) – Request for purchase or


requisition of supplies, materials and equipment or its
equivalent shall be duly approved by proper authorities.
(Source: Training Handbook on Government Expenditures)

 In no way that the End-user Unit submit their P.R. ahead


of the approved PPMP item.

22
ANNUAL PROCUREMENT PLAN (APP)

 Legal Basis: Section 7 of the IRR of RA 9184


 Refers to the entirety of the procurement activities that will be
undertaken by the procuring Entity within the calendar year
using the prescribed format required by the GPPB.
 Shall be consolidated by the BAC Secretariat from the PPMPs
of end-user units. The BAC shall take into consideration the
following factors:
 One year planning perspective
 Emergency or Contingency Fund
 Schedule of Activities
 No procurement shall be undertaken unless in accordance
with APP

23
ANNUAL PROCUREMENT PLAN (APP)
 All procurement should be meticulously and judiciously planned
by procuring entity

 APP should be maintained and updated regularly

 In the consolidation of PPMPs, the BAC may adopt a strategy


through where similar items of procurement are packaged into
one procurement undertaking.

 A review and updating of the individual PPMPs and the APP


shall be done regularly, at least once every 6 mos. or as often as
necessary. The end-user or implementing units shall be
responsible for the changes to the PPMPs, while the BAC
Secretariat shall be responsible for the consolidation of these
PPMPs into an APP

24
ANNUAL PROCUREMENT PLAN (APP)

1 2 3 5 7
4 6

Per GPPB Resolution No. 20-2015


1. Name of Procurement 4. Schedule of identified
Project; procurement activities;
2. Procurement Management 5. Source of funds;
Office (PMO)/end- 6. Indicative ABC;
user/implementing unit; 7. Other relevant descriptions
3. Method of Procurement; of the project, if applicable.

25
PREPARATION OF APP

When GAA,
Corporate Budget
or Appropriation
Upon approval Ordinance
of HOPE, Budget becomes final,
Submit Budget Office will PPMPs will be
Proposal to forward PPMPs finalized and
HOPE to BAC submitted to BAC
Submit to
Budget Office Secretariat for Secretariat for
for Consolidation consolidation and
evaluation and Review approval of the
HOPE.
Prepare Project
Procurement
Management
Plan (PPMP)

26
PREPARATION OF APP

Procedure under the 2016 IRR of RA 9184

When GAA, Corporate


Budget or Appropriation
Ordinance becomes
final, PPMPs will be
Submit Indicative finalized and submitted
APP and budget to BAC Secretariat for
proposal to consolidation, to BAC for
Consolidation
HOPE/oversight final recommendation of
of PPMPs to
body for approval modality and final
Indicative APP
by BAC Sec and approval of the HOPE
Submit to
Budget Office recommendatio
for n by BAC of
evaluation modality
Prepare Project
Procurement
Management
Plan (PPMP) During Budget Preparation
27
PPMP CONSOLIDATION

• Checking of • Recommendation of
procurement procurement
methods methods by the
BAC

• Propose
procurement
methods (End-user)

28
REVISIONS ON APP

End-User Update
/Supplement
PPMP

Consolidate
PPMP to
BAC & BAC Sec Updated/
Supplemental
APP

Approve
Updated
HOPE /Supplemental
APP
29
ANNUAL PROCUREMENT PLAN (APP)
Procurement Short of Award
 To facilitate the immediate implementation of procurement ,
even pending approval of the GAA, corporate budget or
appropriations ordinance, as the case may be, the PE may
undertake the procurement activities short of award
 For a contract with a period not exceeding one (1) year,
the ABC shall be based on the amount in the approved
indicative APP as included in the proposed national budget
(NEP) submitted by the President to Congress; on budget
levels as proposed to the governing board for GOCCs
 No award of contract shall be made until the GAA or
corporate budget has been approved
30
APP vis-a-vis APP-CSE

 APP being referred to in the IRR of RA 9184 is different from


the APP-CSE

 APP-CSE serves as basis of DBM – PS in projecting its


inventory requirements, scheduling of activities, and over-all
management of the central procurement of common-use
goods (DBM Circular Letter 2011-6 & 2011-6a)

 Common-use supplies – refers to those supplies and materials


and equipment included in the price list of the PS which are
necessary in the transaction of the official business of the
procuring entity and consumed in its day-to-day operations

31
APP-CSE

32
TIPS IN CONSOLIDATING PPMPS

Sort by Type of Procurement


Goods Infra Consulting

Check for Items which can be merged


i.e: IT Equipment, Design and Build projects, Office Furniture, etc

Common Use Supplies


CSE NON-CSE

Mode of Procurement

Sources of Funds

33
5 RIGHTS IN PUBLIC PROCUREMENT

Source
Value for Money

Time/
Quantity
Delivery

Procurement

Price Quality

34
POSSIBLE CONSEQUENCES

1. Possible COA AOMs/Disallowances

2. Wastage of Government Funds

3. Suspension of Officials

4. Possible administrative/criminal liabilities

5. Project Delays

6. Project Failures

35
36
WHAT IS MONITORING?

Defined as:

• Tracking of inputs, activities, outputs, and outcomes of


the procurement activity; and

• Tracking results of current operations on a regular basis.

37
MONITORING AND EVALUATION

 It is the BAC who shall be responsible for ensuring that the


procuring entity abides by the standards set forth under R.A. 9184
and its IRR.

 BAC is required to prepare a PROCUREMENT MONITORING


REPORT (PMR) in the form prescribed by the GPPB.

 The PMR shall cover all procurement activities specified in the APP,
whether on-going and completed from holding of the pre-
procurement conference to the issuance of the notice of award and
approval of the contract, including the actual time for each major
procurement activity.

 The PMR shall be approved and submitted by the Head of the


Procuring Entity (HOPE) the GPPB in printed and electronic format
within 14 cd after the end of each semester.
( Executive Orders 662, 662-A and 662-B, series of 2007)

38
WHY MONITOR?

 Compliance to R.A. 9184 and its IRR

 Performance
– Efficiency
– Effectiveness

 Aid GPPB in crafting policies that address weaknesses


and uphold strengths of the Philippine Procurement
System

39
PROCUREMENT MONITORING REPORT (PMR)

40
MONITORING AND EVALUATION

 Monitoring entails tracking of inputs, activities,


outputs, and outcomes of the procurement activity

 Ex-post evaluation examines the project outcomes and


impacts. It is a determination of the benefits derived
from the project, the attainment of specific targets for
key indicators, and the sustainability of the project.

41
SUBMISSION & POSTING
REQUIREMENTS
• APP
– Submission to the GPPB (AO 222) and posting in the procuring
entity's website of its APP for CY 2012 (Section 1.1 of the IRR of
EO 662), following the form and format downloadable from the
GPPB website
– Changes in the APP, if any, for the budget year shall be submitted to
the GPPB in July of the current budget year, and in January of the
following budget year

• PMR
– Submission to the GPPB (Section 12.2 of IRR of RA 9184) and
posting in the procuring entity's website of its approved
Procurement Monitoring Report every semester, following the
form and format downloadable from the GPPB website (Section
1.2 of the IRR of EO 662)

42
THANK YOU!!

Contact us at:

Unit 2506 Raffles Corporate Center


F. Ortigas Road, Ortigas Center
Pasig City, Philippines 1605

TeleFax: (632)900-6741 to 44
Email Address: gppb@gppb.gov.ph

43

You might also like