Professional Documents
Culture Documents
PROTECTION OF
GENERATORS, GENERATOR
TRANSFORMERS AND
220 kV AND 400 kV
NETWORKS
Editors
C.V.J.VARMA
P.K. LAL
_"I- ----__
,SF
S, > ,
7. !>
,-,. \-;c
- ,5,,L, ;; -
</,--./
:,s ',N ... - /-
-
., .
f r
\ .--"--
%. /
Page
Foreword iii
Introduction 1
Section 1 Generator and Generator Transformer Protection 2
Section 2 Line Protection 19
Section 3 Auto Reclosure 23
Section 4 Transformer Protection 26
Section 5 Reactor Protection 29
Section 6 Bus Bar Protection 31
Section 7 Local Breaker Back-up (Breaker fail) Protection 33
Sectiorl 8 Fault Locator, Disturbance Recording and Event Logging Equipment 35
Section 9 Guidelines for Protection System Engineering 38
Section 1 0 CT, CVT Locations 41
Section 11 Commissioning Tests & Maintenance Recommendations
Section 12 Test Equipments
Section 13 Reference Standards
Section 1
GENERATOR AND GENERATOR TRANSFORMER
PROTECTION
1.0 GENERAL
1.1 Generators are designed to run at a high load factor for a large number of years and
permit certain incidences of abnormal working conditions. The machine and its auxiliaries
are supervised by monitoring devices to keep the incidences of abnormal working
conditions down t o a minimum. Despite the monitoring, electrical and mechanical
faults may occur, and the generators must be provided with protective relays, which, in
case of a fault, quickly initiate a disconnection of the machine from the system and, if
necessary, initiate a complete shut down of the machine.
1.2 Recommendations contained herein for electrical protective systems of generator and
generator transformer are intended t o be used for generators of 10 MVA and above. It
describes t h e requirements of various protections, special comments t o help in
determining application of these protections, for units of various types and sizes, setting
criteria and tripping principles.
The protection requirements of machines used in pumped storage schemes need further attention
and the recommendations given below do not cover these details.
1.2.1 Generator can be connected t o the primary transmission system in following two ways:
1. Unit Scheme
In this scheme no switchgear is provided between the generator and generator
transformer which are treated as a unit. A unit auxiliary transformer is tapped off at
the interconnection, for the supply of power to the auxiliary plant.
11. Generator Circuit Breaker Scheme
In this scheme, a generator circuit breaker is provided between the generator and generator
transformer:
1.3 In view of generator unit being a complex system, various electrical hazards require
consideration. These are given below:
- Stator insulation failure
- Overvoltage
- Rotor faults
- Loss of synchronism
- Over/under frequency
- Overload
- Unbalanced loading
- Loss of excitation
- Reverse power
- Inadvertent energisation of generator
1.4 Following a r e the various protections recommended for the generator and generator
transformer protection.
<
Functions Steam/Gas Turbines Hydro Turbines
Small Medium Large Small Medium Large
(< 1 0 (10-100 (> 100 (< 10 (10-100 (> 100
MVA) MVA) MVA) MVA) MVA) MVA)
Differential Y Y Y Y Y Y
95%Stator E/F Y Y Y Y Y Y
100% Stator E/F N Y/N Y N Y/N Y
Interturn Faults Y Y Y Y Y Y
Bacltup Impedance N Y Y N Y Y
Voltage
Controlled O/C Y N N Y N N
Negative Sequence Y Y Y Y Y Y
Field Failure Y Y Y Y Y Y
Reverse Power Y Y Y Y Y Y
Pole Slipping N N Y N N Y
Overload N N N Y Y Y
Over voltage Y Y Y Y Y Y
Under frequency Y Y Y Y Y Y
Dead Machine N N Y N N Y
Rotor Earth Fault Y Y Y Y Y Y
Overfluxing N Y Y N Y Y
I Requirements:
(i) Shall be capable of detecting a power swing which can lead to instability in addition to
being able to detect an actual pole slip
(ii) By varying size of the characteristic it shall be possible to ensure that a trip command is
given to the circuit breakers in such a way that separation of the poles occurs at a
controlled angle at any time.
Setting Recommendations
(a) If the source of oscillation lies within a generatorhransformer unit, the machine has to
be isolated from the network after the first'slip.
Forward reach of relay characteristics shall cover generator/generator transformer. Tripping
in this zone shall be in the first pole slip. The reach of this zone is 0.7 T .
(b) If the source of oscillation lies outside the unit in the network, the generator should not
be switched off or atleast not until several pole slips have occurred.
2.1.9 Low forward power/reverse power interlock relays (32G/37G)
I 1
The low forward power interlock is recommended for thermal machines and reverse power
protection may be used for hydro machines to protect against motoring.
1
When the steam flow through turbine is interrupted by closing the ESVs or the governor valves,
the remaining energy stored in the set is delivered to the system and the machine enters into a
motoring condition drawing power from the system to supply its losses while keeping the turbo
alternator shaft at synchronous speed.
- The low forward power relay detects that the unit is motoring and must therefore be
shutdown
- Tripping for mechanical faults and abnormal conditions
For faults in the turbine or boiler, the turbine protection closes the ESVs. For abnormal
conditions, the generator protection closes the ESVs. When the generator develops low forward
power, the relay after a short time delay trips the generator breaker.
A protection field suppression signal may also be required if the AVR does not have a built-in
facility to reduce the generator field current as the speed decreases, to avoid overfluxing conditions.
Requirements:
(i) Be single phase power measuring type
(ii) Have a' power setting of approximately 0.5% - 1% of rated active power of generator unit
(iii) Have independent time delay relay with setting range of 1-10 seconds and 0-20 seconds
respectively on pick up
(iv) Have one more common timer with a pick up setting range 5-50 seconds for annunciation
that the Turbo generator set has started motoring
(v) Have suitable arrangement for preventing the operation of this protection during start
up and synchronising of the unit
(vi) Shall be provided with possibility of angle correction to facilitate measurement of power
accurately
Setting Recommendations:
- low forward power relay pickup < 0.05 x Pn
- timer t l - 2 seconds, t2 - 2 seconds
2.1.10 Under-frequency protection (81G)
The under frequency protection
- Prevents the steam turbine and generator from exceeding the permissible operating
time at reduced frequencies
- Ensures that the generating unit is separated from the network at a preset value of
frequency that is less than the final stage of system load shedding
- Prevents the AVR from exciting the machine at reduced speeds when some protective
relays may not perform at all
- Prevent over fluxing of the generator. The over fluxing relay is used to protect against
small overfluxing for long periods while the over voltage and under frequency relays also
protect against large over fluxing for short times
The stator under frequency relay measures the frequency of the stator terminal voltage
Though under frequency tripping is recornmended by turbine manufactures, care should be
taken by grid operating personnel in ensuring that machines are not run at lower frequencies
and instead resort to means like load shedding in the event of overload.
Requirements:
(i) Have one alarm stage and two tripping stages
(ii) Shall have setting of range of 4 5 Hz - 55 Hz with a least count of 0.1 Hz for each stage
(iii) Timer for alarm stage have a range of 0 . 5 to 5 second with a least count of 0.5 second.
Timers for each tripping stage shall have range of 1 to 1 0 seconds with a least count of
0 . 1 second
(iv) Shall have undervoltage blocking
Setting Recommendations
- Stator under frequency relay pick up level = 48.5 Hz
- Time delay for alarm - 2 Sec.
For time delay setting of tripping stages recommendations of turbine manufacturers may be followed.
2.1.11 Inter turn fault protection (95G)
It is generally considered difficult to obtain reliable protection against short circuit of one turn
if the stator winding has large number of turns per phase.
Inter turn fault protection is recommended only for machines where there is a split winding and
all the six terminals are brought out on the neutral side.
For generator with split neutrals, conventional inter-turn fault protective scheme comprises a
time delayed low set over-current relay which senses the current flowing in the connection
between the neutrals of the stator winding.
Alternatively a split phase differential protection may be used.
Requirements
(i) Over current relay with time delay
(ii) Over current relay shall have built in filters t o reject higher harmonics
(iii) Range of over current shall be selected depending on maximum spill current for external
fault
Setting Recommendation
Overcurrent relay shall be set t o maximum unbalanced current in case of external fault.
Time delay 0.2 - 0 . 4 seconds
2.1.12 Generator Transformer Over Fluxing Protection (99 GT)
Overfluxing protection is provided to safeguard the generator, generator transformer and unit
auxiliary transformer against operation at flux densities which may cause accumulative damage
to the core.
From the fundamental equation V = 4.44 x f x n x 4, the level of flux is proportional t o the
ratio of terminal voltage to frequency (v/f). This ratio is monitored by the protective relay.
An over fluxing condition is more likely t o occur while the generator is separated from the
system and the speed is allowed t o drop, but it can also happen with the machine on load if the
tap changer of the generator transformer (HV side) is on a low tap position and the excitation
of the generator is manually increased. In this case the increased generator terminal voltage
knay cause over fluxing tripping at nominal frequency.
The over fluxing protection operates with a time delay after which the tripping functions are
executed.
This protection must b e provided for generator-transformers of size 1 0 MVA and above.
Requirements
(i) Shall be phase to phase connected.
(ii) Shall operate o n the principle of measurement of voltage io frequency ratio.
(iii) Have inverse time characteristics compatible with generator transformer over fluxing
withstand capability for tripping.
(iv) Provide an independent alarm with a definite time delay of value of V/f between 100%
t o 130% of rated value.
(v) Have a high resetting ratio of 98% or better.
Setting Recommendations:
The overfluxing capability of the transformer must be checked and the characteristic matched
accordingly for both alarm and trip.
2.1.13 Generator Over Voltage Protection (59G)
An over voltage on the terminals of the generator can damage the insulation of the generator,
bus ducting, breakers, generator transformer and auxiliary equipment such as voltage
transformers, excitation transformer etc.
This should be provided for machines of all sizes, hydro and thermal
Requirements:
(i) Be single pole type/or triple pole type
(ii) Shall have two separately adjustable stages
(iii) Have a continuously adjustable setting range of 1 0 0 - 140% of rated voltage
(iv) Have a drop off to pick up ratio greater than 95%
(v) Have a continuously variable time delay setting range of 0.5 - 5 seconds for one relay
and 2 to 2 0 seconds for the other relay.
Setting Recommendations:
Stage 1 - Over voltage relay pick up - 1.15 x Vn
Timers t 1 - 1 0 seconds
Stage 2 - Over voltage relay pick up - 1.3 x Vn
Timer t 2 - 0 . 5 seconds
2.1.14 Dead machine protection (27/50G)
Despite existence of interlocking schemes, a number of generators have been inadvertently
energized while at stand still or on turning gear. The generator and rotor may get damaged
beyond repair under this condition. Other protective relays like loss of excitation, back up
impedance, reverse power would operate with delays and this is not admissible. The dead
machine protection permits fast tripping.
This should be installed in switchyard panel rather than in generator panel to ensure that
protection is available during maintenance periods when the generator protection can be rendered
inoperative by switching off the DC supply to the panel.
This protection is recommended for all-machines of size 1 0 0 MVA and above. The protection
is connected to trip generator breakers, generator transformer breaker and the HV Bus.
Requirements:
(i) Shall consist of 3 high speed over current relays of range (0.02 - 20 In) to initiate
instantaneous tripping if generator terminal voltage is below set value.
(ii) Shall have under voltage relays of range (0.2-1 Un) to permit operation of over current
relays when voltage is low
(iii) Shall have timers with adjustable range (0-605) to avoid operation of protection for
nearby fault when the machine is in service.
(iv) Shall be secure against voltage transients at closing
Setting Recommendations:
For Weak System For Strong System
Overcurrent relay 1-2 pu 3-4 pu
Under voltage relay 20% to 40% rated voltage 50% to 70% of rated voltage
Activation of relay 2 0 Seconds after dead time 2 0 Seconds after dead time
2.1.15 Generator VT fuse failure monitoring (60G)
This has t o be provided for all the machines since it is required for blocking of relays which can
mal-operate in the event of PT fuse blowing in primary side or secondary side.
Requirements:
(i) Be triple pole type
(ii) Be able to detect fuse failure in both primary and secondary side of VT
(iii) Have a fixed setting of 70% of rated voltage and have a time delay of 4 0 t o 5 0 milli-
seconds o n pick up
(iv) Be of voltage balance or equivalent type
(v) Have sufficient contacts t o block tripping of those relays which are voltage dependent
and give alarm
2.1.16 Rotor ground fault protection
This protection shall be provided for machines of all sizes. It is recommended that the protection
is connected only for alarm and the operator may take the machine out at the earliest opportunity
after the first earth fault has occurred. The tripping logic should also include unit tripping in
case field circuit breaker opens when the machine is running.
Requirements:
(i) Shall be based on DC injection principle or low frequency AC injection principle
(ii) Shall be single stage or two stages
(iii) Shall have built-in time delay t o prevent unwanted operation of the relay
Alternatively
A sensitive voltage function operating on bridge measuring basis with auxiliary equipment.
This shall have two levels, one for alarm and one for trip.
Setting r a n g e s : Alarm s t a g e 1 0 0 o h m t o 2 5 k o h m , Time delay 2 - 6 0 S e c o n d s
Trip stage 100. ohm to 2 5 K ohm, Time delay 2-60 Seconds
Setting Recommendations:
- alarm level - 2 5 K ohm
- pick up level - 5 K ohm
- timer t l - 1 seconds
- timer t 2 - 5 seconds
2.2 Generator-Transformer Protection
For short circuit protection, transformer-differential relay and over-current relay connected to
different groups are recommended. For ground faults, earth fault o/c relays and restricted
earth fault relay connected to different groups are recommended.
In case a overhang protection is required, the same may be combined with REF protection o n
HV side of generator transformer.
2.2.1 Generator Transformer Oifferential Protection (87 GT/87 T)
Requirements:
(i) Be triple pole with individual phase indication
(ii) Have unrestricted instantaneous high set over current units which shall not operate
during inrush
(iii) Have an adjustable or multi bias setting
(iv) Have second harmonic or other inrush proof features and also shall be stable under
normal over fluxing conditions. Magnetising inrush proof feature shall not be achieved
through any intentional time delay e.g. use of timers to block relay operation or using
disc operated relays.
(v) Have one bias winding per phase and per C.T. input
(vi) Have an adjustable operating current
(vii) Have an operating time not greater than 30 milli seconds at 5 times of setting
(viii) Shall have facility for ratio and phase angle correction either through auxiliary transformer
or through in built provisions.
2.2.2 Generator Transformer Backup Overcurrent Protection (51 GT)
Requirements:
(i) Be triple pole type
(ii) Be of definite time over current type
(iii) Have an adjustable setting range of 50-200% of rated current and 0.5 - 5 seconds time
delay
2.2.3 Generator Transformer Back Up Earth Fault Protection (51 NGT)
This relay monitors the current in the generator transformer neutral. It can detect faults in the
transformer HV side or in the adjacent network.
Requirements:
(i) Be of single pole type
(ii) Be of definite time characteristic
(iii) Have an adjustable setting range of 1 0 to 100% of rated current
(iv) Have a timer setting range of 0.5 to 5 seconds
2.2.4 HV winding cum overhang differential protection (87 HV/87 NT)
This is a unit type protection which operates for earth faults on the generator transformer HV
side and also covers a large portion of the HV winding and the HV terminals upto the HV
current transformers.
Requirements:
(i) Be triple pole type (Single pole if used as Restricted E/F Protection)
(ii) Have operating time less than 30 milliseconds at 2 times setting
(iii) Be high impedance or low impedance type
(iv) Operating current shall be 0.1 - 0.4 In
(v) High stability against maximum through fault condition, CT saturation, harmonics and
DC transients
(vi) Be provided with suitable non linear resistors across the relay to limit the peak voltage
to 1000 volts, in case of high impedance type
(vii) Be provided with faulty phase identification
2.3 Unit Auxiliary Transformer Protections
For short circuit protection, unit auxiliary transformer differential relay, overload relay for alarm
and over current relay connected to different groups are recommended. However a utility may
carry out an application check and decide not to have a separate differential relay for UAT.
For ground faults residual O/c relay and Restricted E/F relays connected to different groups
shall be provided. The type of connection may be either current based or voltage based depending
on the grounding system.
2.3.1 Unit Transformer Differential Protection (87 UAT)
This is a unit type protection covering the unit transformer and the cable connection to the unit
board.
This protection operates for phase faults, but not for single phase to earth faults as this current
is limited by the neutral earthing resistance.
The unit transformer differential relay initiates a general trip and unit shutdown.
Requirements:
(i) Be triple pole with individual phase indication
(ii) Have unrestricted instantaneous high set over current unit which shall not operate during
inrush
(iii) Have an adjustable or multi bias setting
(iv) Have second harmonic or other inrush proof features and also should be stable under
normal over fluxing conditions, magnetising inrush proof feature shall not be achieved
through any intentional time delay e.g. use of timers to block relay operation or using
disc operated relays.
(4 Have one bias winding per phase and per C.T. input
(vi) Have an adjustable operating current
(vii) Have an operating time not greater than 3 0 milli seconds at 5 times of setting
(viii) Shall have facility for ratio and phase angle correction either through auxiliary transformer
or through in built provisions.
2.3.2 Unit Transformer back up over current protection (51UAT) Relay
(i) Be triple pole type
(ii) Be of definite time over current type
(iii) Have an adjustable setting range of 50-200% of rated current and 0 . 5 to 5 seconds time
delay
2.3.3 Unit Transformer back-up earth fault protection (51NUAT)
(i) Be single pole type
(ii) Be of definite time over current type
(iii) Have a setting rage of 10-100% of rated current and time setting range of 0.5-5 seconds
3. ENGINEERING RECOMMENDATIONS
3.1 Redundancy
The protection functions shall be subdivided into two groups each being independent and
capable of providing uninterrupted protection even in the event of one of the protection groups
failing. Given below is recommendation for dividing the protections in two groups:
GROUP A GROUP B
Generator
Generator differential Over-all differential
Minimum impedance
(or alternatively over 95% stator earth fault
current/under voltage) Loss of excitation
Negative sequence protection Pole slip
Over load protection Under frequency
100% stator earth-fault
Rotor earth fault
Reverse Power Reverse power
Over voltage Over fluxing
Inter-turn fault
(1 ~ e n e i a t o rTransformer 1I
Transformer differential Over current
Earth fault over current Restricted earth fault
HV winding cum overhang differential
I I Unit Auxiliary Transformer 1I
II Transformer differential
II Over current
I1
1 Ground fault over current Restricted earth fault
I
3.2 Tripping Principles
In general, it is best if generator protection relays initiate non-sequential trip mode (Class-A)for
unit isolation. However sequential tripping (Class B) provides a better means of tripping a
steam turbine generator on some abnormal operating conditions where delayed tripping of the
generator will not result in increased damage to the turbine, generator or other electrical
equipment. The reason for sequentially tripping a steam turbine generator is to avoid the over-
speed condition that results when the generator main breaker is tripped while steam is applied
to the turbine.
Proper control logic is critical to the design of a sequential tripping scheme and requires some
sort of mechanical "Turbine Tripped" indication (i.e. steam stop valve limit switches, trip oil
system pressure switches etc.) which is supervised by an electrical reverse power relay. This
relay is normally set to detect very low power levels and incorporates a brief time delay of the
order of several seconds for added security.
It has been recommended that generator protective relays, initiate non-sequential trip mode for
isolation of the unit due t o electrical faults. Only devices protecting unit from 'an abnormal
mechanical operating condition or an abnormal (not faulted) electrical condition or normal shut
down should initiate a sequential trip.
Section 2
LINE PROTECTION
1.0 GENERAL
The line protection relays are required to protect the line and clear all type of faults on it within
shortest possible time with reliability, selectivity and sensitivity. The line protection relays shall
be suitable for use with capacitive voltage transformers having passive damping and transient
. response as per IEC 186.
Recommendation for provisions of line protection at different voltage levels are as follows:
There should be two independent high speed main protection schemes called Main-I and Main-
I1 with at least one of them being carrier aided non-switched three zone distance protection.
The other protection may be a phase segregated current differential (this may require digital
communication) phase comparison, directional comparison type or a carrier aided non-switched
distance protection. Further, if Main-I and Main-I1 are both distance protection schemes, then
they should be preferably of different types. However, they need not necessarily be of different
make. Both the protections should be suitable for single and three phase tripping. In addition
to above following shall also be provided:
(i) Two stage over-voltage protection. However in such cases where system has grown
sufficiently or in case of short lines, utilities on their discretion may decide not to provide
this protection.
(ii) Auto reclose relay suitable for 1 ph/3 ph (with deadline charging and synchro check
facility) reclosure.
(iii) Sensitive IDMT directional E/F relay
2.0 REQUIREMENTS
2.1 Distance Protection
Distance Protection scheme shall have the following attributes:
(i) Three independent zones
(ii) Non-switched type with separate measurements for a!l phase to phase and phase to
ground faults.
(iii) Capable of single and three phase tripping
(iv) Directional (mho or quadrilateral or other suitably shaped) characteristics for zone 1,
zone 2 and zone 3
(v) Capable of operation for close-up three phase faults and switch on to faults
(vi) Adjustable characteristic angle to match line angle wherever applicable
(vii) Accuracy of better than or equal to 5% of set value for reach measurement in zone 1
and better than or equal to 10% of set value for zone 2 and zone 3
(viii) Accuracy of better than or equal to 5% of set value for time measurement of zone 2 and
zone 3
(ix) Variable residual compensation
(x) Shall include power swing detection feature for selectively blocking, as required.
(xi) Shall include suitable fuse-failure protection to monitor all types of fuse failure and block
the protection.
(xii) Maximum operating time under given set of condition shall be as follows:
SIR 4 15
Relay setting 1 0 Ohms 2 Ohms
Fault location (as % of relay setting) 60% 60%
Trip duty Contacts per phase* 4 4
Fault resistance Zero Ohms Zero Ohms
Max. Operating Times 45 ms 4 5 ms for 3 phase faults
Including trip relays (if any) for all faults 6 0 ms for other faults
and with CVT
*
These trip duty contacts can be provided either in-built in the distance relay or through
additional relay. Making capacity of trip contracts shall be 3 0 A for 0.25 S with an
inductive load of L/R > 1 0 ms
, 1 1 I
I
I I ]
A Zone-I1 timing of 0.3 second is recommended. However, if a long line is followed by a short
' , / I line, then a higher setting (say 0.5 sec) may be adopted on long line to avoid indiscriminate
, tripping through Zone-I1 operation on both lines.
Zone-I11 timer should be set so as to provide discrimination with the operating time of relays
provided in subsequent sections with which Zone-111 reach of relay being set overlaps.
4.3 O/V Protection
4.3.1 Low set stage may be set at 110% with a typical time delay of 5 seconds. However, a
time grading of 1 second may be provided between relays of different lines at a station.
Longest time delay should be checked with expected operating time of overfluxing relay
of the transformer to ensure disconnection of fine before tripping of transformer.
4.3.2 High set stage may be set at 150% with a time delay of 100 m.second.
4.4 Power Swing Blocking Function Associated with Distance Relays
Decisions pertaining to allowing which Zone to trip and which to block should be taken based
on system studies oil case to case basis.
Section 3
AUTO-RECLOSING
1.0 GENERAL
The auto-reclosing of power lines has become a generally accepted practice. Reports from
different parts of the world show that in certain networks in regions subject to a high lightning
intensity only about 5 per cent of the faults are permanent. Auto-reclosing therefore provides
significant advantages. Outage times will be short compared to where station personnel have
to re-energise the lines after a fault. Additionally, in interconnected networks auto-reclosing
helps in maintaining system stability.
Following different arrangements of auto-reclosing are possible:
High speed single pole reclosing (HSAR)
High speed three pole reclosing (HTAR)
Delayed three pole reclosing (DAR)
DAR with dead line (DL) and synchronism check(SC)
HTAR with DL and S C
HTAR with parallel line check (PC)
In case of HSAR and HTAR without check, the two ends can be reclosed at about the same instant.
In case of DAR and HTAR with DL and SC the C.B. at one end recloses first after the set dead
time and with a check of dead line condition. After a successful line re-energization from one
end the voltage, phase angle and possibly frequency on the line and station side are compared.
At acceptable synchronous in-phase conditions the C.B. at the second end is reclosed.
1.1 Recommendations for provisions of auto-reclosing.
Presently 1 phase high speed auto-reclosure (HSAR) at 400 kV and 220 kV level is widely
practised including on lines emanating from Generating Stations and the same is recommended
for adoption. If 3-phase auto-reclosure is adopted in future the application of the same on lines
emanating from generating stations should be studied and decision taken on case to case basis.
2.0 REQUIREMENTS
It shall have the following attributes:
(i) Have single phase and/or three phase reclosing facilities.
(ii) Have a continuously variable single phase dead time.
(iii) Have continuously variable three phase dead time.
(iv) Have continuously variable reclaim time.
(4 Incorporate a facility of selecting single phase/three phase/single and three phase auto-
reclose and non-auto reclosure modes.
(vi) Have facilities for selecting check synchronising or dead line charging features.
(vii) Be of high speed single shot type
(viii) Suitable relays for S C and DLC should be included in the overall auto-reclose scheme.
(ix) Should allow sequential reclosing of breakers in one and half breaker or double breaker
arrangement.
3.0 SPECIAL COMMENTS
3.1 Fast simultaneous tripping of the breakers at both ends of a faulty line is essential for
successful auto-reclosing. Therefore, availability of protection signalling equipment is a
pre-requisite.
3.2 Starting and Blocking of Auto-reclose Relays:
Some protections start auto-reclosing and others block. Protections which start A/R are Main-
I and Main-11 line protections.
Protections which block A/R are:
- Breaker Fail Relay
- Line Reactor Protections
- O/V Protection
- Received Direct Transfer trip signals
- Busbar Protection
- Zone 2/3 of Distance Protection
- Carrier Fail Conditions
- Circuit Breaker Problems.
When a reclosing relay receives start and block A/R impulse simultaneously, block signal
dominates. Similarly, if it receives 'start' for 1-phase fault immediately followed by multi-phase
fault the later one dominates over the previous one.
.3.3 Following comn~entsare for multi-breaker arrangements of one and half breaker or
double breaker arrangement
3.3.1 In a mu.lti-C.B. arrangement one C.B. can be taken out of operation and the line still be
kept in service. After a line fault only those C.Bs which were closed before the fault.
shall be reclosed.
3.3.2 In multi-C.B. arrangement it is desirable to have a priority arrangement so as to avoici
closing of both the breakers in case of a permanent fault. This will help in avoiding
unnecessary wear and tear.
A natural priority is that the C.B. near the busbar is reclosed first. In case of faults
on two lines on both sides of a tie C.B. the tie C.B. is reclosed after the outer C.Bs.
The outer C.Bs. do not need a prioritin3 with respect to each other.
3.3.3 In multi-breaker arrangement it is necessary to trip two C.Bs. to clear a line fault and
also auto reclose these two. Basically two types of arrangement for C.B. associated
relays are possible i.e.
- C.B. Oriented
- Line Oriented
With C.B. oriented arrangement co-operation between C.Bs, Synchrocheck relay etc. is straight
forward and autoreclose mode can be selected separately for each breaker. With line oriented
arrangement interconnections between line relays and reclosure relay is simpler, but cooperation
with circuit breakers schemes becomes complicated. For the above reasons C.B. oriented
arrangement is recommended.
3.4 In case of bus bar configuration arrangement having a transfer breaker, a separate auto-
reclosure relay for transfer breaker is recommended.
The recommended operating cycle at 400 kV and 220 kV is as per the IEC standard. Therefore,
reclaim time of 2 5 Sec. is recommended.
Section 4
TRANSFORMER PROTECTION
1.0 GENERAL
A Power Transformer is a very valuable and vital link in a Power Transmission system. Reliable,
secure and fast protection system for the transformer is essential to minimise the damage in
case of an internal fault with suitable back up protection scheme to take care of uncleared
system faults.
Faults occur in Transformer due to insulation breakdown, ageing of insulation, overheating due
to over excitation, oil contamination and leakage or reduced cooling. To give an early warning
and to minimise the damage in case of a fault it is necessary to equip it with monitors and
Protective relays.
Recommendations for provision of protective and monitoring equipment for transformers of
400 kV and 220 kV class are as follows:
1.1 Following are the various protections recommended for the transformer protection:
Transformer differential protection
Overfluxing protection
Restricted earth-fault protection
Back up directional O/C + E/F protection on HV side
Back up directional O/C + E/F protection on LV side
Protection and monitors built in to Transformer (Buchholz relay, Winding and Oil
Temperature Indicators, Oil Level Indicator and Pressure Relief Device)
Protection for Tertiary winding
Overload Alarm
2.0 REQUIREMENTS
Differential Protection
(i) Triple pole with individual phase indication
(ii) Have unrestrained instantaneous high set over-current units which should not operate
during inrush.
Have an adjustable or multi bias setting
Have second harmonic or other inrush proof features and also should be stable under
normal overfluxing conditions, Magnetising inrush proof feature shall not be achieved
through any intentional time delay e.g. use of timers to block relay operation or using
disc operated relays.
(4 Have one bias winding per phase and per C.T. input
(vi) Have an adjustable operating current
(vii) Have an operating time not greater than 30 milli seconds at 5 times of setting
(viji) The scheme shall have facility for ratio and phase angle correction either through auxiliary
transformer or through in-built provisions.
2.2 Overfluxing Protection
(i) Overfluxing protection shall be phase to phase connected.
26
(ii) Operate on the principle of measurement of voltage to frequency ratio.
(iii) Have inverse time characteristics compatible with transformer overfluxing.
(iv) Provide an independent alarm with a definite time delay at value of v/f between 100%
t o 130% of rated value.
(v) Have a high resetting ratio of 98% or better.
2.3 REF Protection
(i) Shall be single pole
(ii) Have an operating current sensitivity of at least 10% of nominal current
(iii) Be tuned to the system frequency
(iv) Have a suitable non-linear resistor t o limit the peak voltage during in-zone faults in case
of high impedance type
(v) Shall be high or low impedance principle type.
2.4 Back-up overcurrent protection relay (on HV side and MV side)
(i) Be 3 pole type
(ii) Have IDMT characteristic (directional on MV side)
(iii) Have a variable setting range of 50-200% of rated cilrrent
(iv) Have a characteristic angle, 30(/45( degrees lead
(v) Shall include high unit having low transient over-reach and variable setting range typically
500-2000% of rated current
(vi) Include hand reset indicators per phase
2.5 Back up earth-fault protection relay
(i) Shall be single pole type
(ii) Have IDMT characteristic (directional on MV side)
(iii) Have a variable setting range of typically 20-80% of rated current
(iv) Shall have a characteristic angle of 45/60 degree lag
(v) Shall include high set instantaneous unit having low transient over-reach and variable
setting range of typically 200-800% of rated current
(vi) Shall include hand reset indicators
2.6 0;erload Alarm relay
(i) Shall be of single pole type
(ii) Shall be of definite time overcurrent type
(iii) Shall have a continuously variable current range of 50-200% of rated current and
continuously variable timer setting range of 1-10 sec.
(iv) Shall have a drop off t o pick up ratio of 95% or better.
2.7 Tertiary Winding Protection
There are variations in the practices adopted for bringing out the tertiary terminals of ICTs.
Therefore, depending upon the type of connections, adequate protection scheme may be adopted
in consultation with the manufacturer of the transformer.
3.0 Special Comments
3.1 Duplication of transformer protection is not considered necessary but the protection
and monitors shall be divided in two groups viz. Gr A and Gr B at 400 kV. At 2 2 0 k ~
level this is recommended depending on the importance of the substation and where it
is decided to go for two groups of protection with two station batteries.
Given below is one possible way of grouping these protections:
Group A Group B
Transformer biased R.E.F. Protection
differential relay Buchholz Protection
Back up Protection (HV) Back up Protectior, (MV)
Overfluxing Protection (HV) Overfluxing Protection (MV)
Oil temperature high tripping Overload protection (Alarm only) winding
temperature high tripping
Pressurn relief tripping OLTC Buchholz tripping
Delta winding protection Oil level high/low tripping
Group A and B protections shall be connected to separate DC source/separately fused supplies.
DC sources shall be supervised.
Both Gr A and Gr B protections shall give out tripping impulses to liV, MV and LV (if applicable),
circuit breakers.
3.2 The transformer overfluxing protection has been recommended on both sides for
interconnecting transformers. This is to cover all possible operating conditions, e.g.
the transformer may remain energised from either side. For other transformers
overfluxing relay shall be provided on the untapped winding of the ~ransformer.
3.3 In case of breaker and half switching schemes, the differential protection C.Ts. associated
with Main and Tie breakers should be connected to separate bias windings and these
should not be paralleled in order to avoid false operation due to dissimilar C.T. transient
response.
3.4 Whenever separate phase-wise C.Ts are available on neutral side of transformer, triple
pole high impedance relay may be provided instead of single pole R.E.F. relay.
1.0 GENERAL
Shunt Reactors are used in EHV systems to limit the overvoltages due to capacitive VAR
Generation in Long Transmission Lines.
The shunt reactors are normally connected
(a) Through isolators to a line
(b) Through circuit breakers to a busbar
(c) Through circuit breakers to the tertiary of a Interconnecting transformer.
Faults occur in shunt reactors due to insulation breakdown, ageing of insulation, overheating
due to overexcitation, oil contamination and leakage. To give an early warning and to minimize
the damage in case of a fault it is necessary to equip it with monitors and protective relays.
Recommendations for provision of protection and monitoring equipment for Reactors are as follows:
(a) Reactor differentialProtection
(b) Reactor REF Protection
(c) Reactor-backup protection (Impedance type or definite time o/c & E/F)
(d) Protections and monitors built into reactor (buchholz, winding temperature, oil
temperature,. pressure relief, oil level, Fire protection)
2.0 REQUIREMENTS
2.1. Differentia1 Protection
(i) Shall be triple pole type
(ii) Have an operating current sensitivity of atleast 10% of nominal current.
(iii) Be tuned to system frequency
(iv) Have operating time not greater than 30 ms at 5 times of setting
(v) Have suitable non-linear resistors to limit peak voltage during in-zone faults in case of
high impedance type
(vi) Shall be high or low impedance type.
2.2 Restricted earthfauIt protection
(i) Shall be 'single pole
(ii) Have an operating current sensitively of atleast 10% of nominal current
(iii) Be tuned to system frequency
(iv) Have suitabhnon-linear resistors to limit peak voltage during in-zone faults
(v) Shall be high or low impedance type
2.3 Backup protection ReIay
Either
(i) Shall be triple pole type
(ii) Shall be single step polarised 'mho' or impedance distance relay suitable for measuring
phase to ground and phase to phase faults.
(iii) Shall grounds a characteristic angle between 60-80 degrees
(iv) Shall have an adjustable definite time delay relay with setting range of 0.2. to 2.0 Sec.
(v) Shall have a suitable range for covering 60% of reactor impedance
(i) Shall be a single stage definite time 3 pole, overcurrent relay with adjustable current and
time.
(ii) Shall be connected for 2 O/C and 1 E/F connection and shall be non-directional with
high reset ratio and low transient overreach.
1.0 GENERAL
Bus bar protection is required to be provided for high speed sensitive clearance of bus bar faults
by tripping all the circuit breakers connected to faulty bus.
Recommendations for providing bus bar protection at different voltage levels are as follows:-
(i) Bus bar protection must be provided in all new 400 kV and 220 kV substations as well
as generating station switchyards.
(ii) For existing substations, provision of bus bar protection is considered a must at 400 KV
level and at 220 KV level it is essential at substations having multiple feed. In case of
radially fed 220 KV substations, having more than one bus it is desirable to have bus bar
protection but is not a must.
2.0 REQUIREMENTS
Bus bar protection shall have following features.
(i) It shall be of 3 phase type and operate selectively for each bus bar section.
(ii) It shall operate on differential principle and provide independent zones of protection for
each bus.
(iii) It shall provide zone indication.
(iv) It shall be stable for through faulf conditions upto maximum 40 kA fault level.
(4 For applications where bus differential protection sensitivity has to be set below load
current, as may be a case with use of concrete structures, it is recommended that a
separate check zone is provided otherwise provision of separate check zone is not
essential. Check zone, if provided, shall be of high impedance type.
It shall incorporate continuous supervision for C,T. secondaries against any possible
open circuits. In case of detection of any open circuiting of C.T. secondaries, after a
time delay, the affected zone of protection shall be rendered inoperative and an alarm
will be initiated.
(vii) It shall include D.C. supply supervision
(viii) Include adequate number of high speed tripping relays.
(ix) Whenever C.T. switching is involved the scheme shall include necessary C.T. switching
relays and have provision for C.T. switching incomplete alarm.
It shall include IN/OUT switching facility for each zone.
1.0 GENERAL
In the event of any circuit breaker failing to trip on receipt of trip command from protection
relays, all circuit breakers connected to the bus section to which the faulty circuit breaker is
connected are required to be tripped with minimum possible delay through LBB protection.
This protection also provides coverage for faults between C.B and C.T. which are not cleared
by other protections.
Recommendations for providing LBB protection at different voltage levels are as follows:
(i) In all new 400 kV and 220 kV substations as well as generating stations switchyards, it
must be provided for each circuit breaker.
(ii) For existing switchyards, it is considered a must at 400 kV level and also at 220 kV
switchyards having multiple feed. In case of radjally fed 220 kV substations, provision
of LBB protection is desirable but not essential.
2.0 REQUIREMENTS
LBB protection shall have following features:
(i) Have short operation and drop off times.
(ii) Have three phase current elements with facility for phase wise initiation.
(iii) Have current setting range such that these can be set at minimum 200 mA for line and
5 0 mA for generators (for 1A C.T. Secondary).
(iv) Have one common associated timer with adjustable setting.
1.0 GENERAL
1.1 Disturbance Recorder
- Provides better understanding of the behaviour of Power network after a disturbance
- Gives useful information to improve existing equipment and in planning/designing new
installations
Disturbance recorder shall be microprocessor based and shall be used to record the graphic
form of instantaneous values of voltage and current in all three phases, open delta voltage and
neutral current, open or closed positions of relay contacts and breaker during the system
disturbances.
Disturbance recorders are recommended for all the 400 kV lines. At 220 kv level also they are
recommended for all interconnecting lines. In other cases utilities may decide depending on
their need.
It is also recommended that all the disturbance recorders in the station are synchronised with
GPS
1.2 Fault Locator
Distance to fault locator is recommended to be provided as a standard for all 400 kV and 220
kV lines on both ends. However for short lines of length upto 2.0 kms, fault locator can be
provided at one end only.
1.3 Event Logger
The Event logger is used to record the state of switchyard equipment and relays and occurrences
of alarms. The equipment also records events recorded by disturbance recorder, as also changes
in digital inputs, i.e operation and resetting of relay contact and switching of primary plant
within the substation.
In case all required events can be accommodated in disturbance recorder no separate event
logging equipment is recommended.
2.0 . REQUIREMENTS
2 . 1 Disturbance Recorder
Recording capacity
- Record minimum eight analogue inputs (8)and minimum 16 binary signals per bay or
circuit.
Memory capacity
- Minimum 5 sec of total recording time
Recording times
- Minimum prefault recording time of 100 ms
- Minimum Post fault recording time of 1 0 0 0 ms
Trigger
- Any of digital signals can be programmed to act as trigger
- Analogue channels should have programmable threshold levels for triggers. Selectior
of over or under levels should be possible.
Time Tagging
- Has built in real time clock and calendar to time tag recorded disturbances. Drift of thc
in built clock shall not be more then 0 . 5 sec per day.
Sampling Rate
- 1 KHz
Recording band width
, - 5-250 Hz
Voltage Channel
- Dynamic range 0.01-2 x Nominal Voltage
- Resolution 0.1%
Current Channel
- Dynamic range with full DC offset
- .01-60 x Nominal Current
Printer
-- Printer shall be suitable for taking print on plane paper
From Line VT
From Aux. VT
vo
1.0 GENERAL
Some broad guidelines for Engineering of Protection System in addition to engineering
recommendations made in various sections, are given below and could be refined if felt necessary
by the Utility according to its specific needs and practices.
2.1 Gr. A and Gr. B Protection
Wherever two sets of DC sources are available, to obtain redundancy and to be able to take
protection out for maintenance, while equipment is in service, the relays are electrically and
physically segregated into two groups. Grouping is done to the extent possible in such a way
that each group can independently carry out protective functions with near equal redundancy.
Interconnection between these two groups shall not generally be attempted. However if found
absolutely necessary such interconnection shall be kept to the bare minimum.
Even in cases when only one set of battery source is available segeration of protections and trip
circuits in two groups may be considered by giving DC supplies through separate fuses.
2.2 Trip Unit
In case of segregation being made as indicated above, scheme associated with each circuit
breaker is provided with two sets of trip units, one in Gr A and one in Gr.B. Each set consists
of one unit for 1/3 phase tripping and another for 3 phase tripping only. 1/3 phase tripping
unit and 3 phase tripping units are initiated by functions as described below. However, in case
the protection relay itself is having sufficient number of trip duty contacts, then separate trip
units will not be necessary.
2.2.1 1 ph & 3 ph trip (Protections which,start auto recloser)
- Main I Line Protection
- Main I1 Line Protection
These units shall be applicable for line circuits only and shall be with self reset type contacts
2.2.2 3 ph trip (Protections which block auto reclosure)
- Direct trip receive
- Line reactor protection
- Bus bar protection
- Transformer protection
- Overvoltage protection
- Back up protections
These units shall be hand reset type
2.2.3 Direct trip of remote end breaker
In line with the present 400 KV practice it is recommended that direct trip signal is sent to
remote end under following conditions.
(i) When LBB relay operates
(ii) Reactor protection and O/V protection
2.3 DC Distribution
Since the availability of even the best engineered protection depends upon the integrity of the
DC auxiliary supply, considerable care has to be given to the design of a system which will
retain the reliability of the protection system as a whole, under all conditions. Secondly from
an operational point of view, it is essential that it is possible to work on any part of the protection
system with full security, while not disturbing the rest of the protective system.
Arising out of these considerations, following guidelines for designing a suitable DC distribution
system have been set forth.
2.3.1 For 400 kV stations there shall be two separate battery systems available for protection,
control and tripping/closing operations. For 220 kV stations where only one set of
battery source is available segregation of protection and trip circuits in two groups may
be considered by giving DC supplies through separate fuses.
2.3.2 Distribution of DC supply shall be done bay wise to feed the following
(a) Protection
(b) CB functions
(c) Isolator/earth switch functions
(d) Annunciation/Indications
(e) Monitoring functions(DisturbanceRecorder, Fault Locator, Event Logger etc.) when these
are not integral part of protection
2.3.3 (a) Protection Function
For each group of protection(ie Group A and Group B relays) separate DC sources
are recommended.
(b) CB Functions
Trip coil 1&2 shall be fed from separate sources. Closing coil can be from either of
these two sources.
(c) Isolator/Earth switch
These associated with any one circuit shall be fed from one of the two DC sources.
In the case of a 1& 1/2 CB arrangement, the Isolator/Earth switch associated with
the tie CB can be fed from either Source 1 or 2.
(d) Annunciation & Indication
For each bay, these functions can be fed from either one of the 2 sources. Each
function shall be fed however through separate feeds.
(e) Monitoring Functions
These shall be grouped in 3 groups
(i) Disturbance Recorders
(ii)- Fault Locators
(iii) Event Loggers
All the three groups shall be fed through separate teeds from either of the two
sources. This is to enable the full availability of these equipment irrespective
of that of the protections.
2.3.4 General Notes:
1. A s to how the separate D.C. feeds are to be taken from the sources, there are two
alternatives.
(a) Through separate feeds from the board to each circuit panel
(b) Through a limited no of feeds to a separate panel of the relay or control board
(Exclusively meant for marshalling the DC circuits for the various relay panels).
The choice between (a) or (b) is left to the utilities as per their individual practices.
2. Sub-fusing of the DC circuits shall be done with care since blowing of the fuse will have
to be monitored. Also such sub-fusing shall be kept to the minimum and can be augmented
with isolating links as required.
3. Selection of sources in the event of one supply to a function failing is to be done with
care, because if the fault lies downstream one may lose both supplies.
4. As a rule every DC supply going through fuse should be supervised with a no-volt relay.
For trip circuits where separate trip circuit supervision relays are provided it is not
necessary to provide separate DC supervision relays.
5. MCBs of adequate break-up capacity can also be used instead of fuses.
2.4 Cabling
It is recommended that:
(i) Separate cables are used for AC & DC circuit
(ii) Separate cables are used for DC 1 & DC 2 circuits
(iii) For different cores of CT & CVT separate cables shall be used.
Section 10
LOCATION OF CTS AND VTS IN SUB-STATIONS
1.0 GENERAL
Instrument transformers (CTs and VTs) are used to obtain measured quantities of current and
voltage in appropriate form for use in control, protection and measuring equipment such as
Energy meters, indicating instruments, protective relays, fault locators, fault recorders,
synchronizers. These are installed in different bays such as line, transformer, bus coupler bays
and also at the busbar.
i WWW
3-Phase
Bus Sectionolizer
Tr
1 www
1
-
3-Phase
7-/ o - m - . . /
\
c;c-
--
h
--
Fig. 4 : One and a half breaker arrangement
Fig. 5 : One and a half breaker arrangement (alternative arrangement with 5 CTs)
Fig. 7 : Typical Protective Relaying Scheme for one and a half breaker busbar arrangement
2.2 Current Transformers
Some explanatory notes and comments with reference to above are given below regarding
location of CTs.
2.2.1 Double Bus Arrangement (Ref. Fig.4)
The CTs shall be placed near the circuit breakers (CBs) and on the line side. The detection
zones of line relays and busbar relays start at the CTs. It is advantageous if these two points are
close to each other. In the improbable case of a fault between the CT and CB the busbar
protection will detect and clear the fault.
2.2.2 Double Main and Transfer Bus Arrangement (Ref:Fig.5)
It is advantageous to locate the CTs on the line side of the disconnectors for Line and Transformer
bays. In this way the protective relay connected to the CT will remain connected to the line or
Transformer when it is switched over to the transfer busbar.
A separate CT is required to be provided in the Transfer bus coupler bay to obtain selective
tripping for faults on Transfer bus.
2.2.3 Bus Coupler and Bus Sectionalizer.Bays (Ref. Fig.4 and Fig.5)
A set of CT is necessary to enable different busbar protection zones to be formed. The protection
can be arranged to give complete fault clearing with a short time-delay (L.B.B. time) for faults
between CB and CT. Sometimes CTs on the two sides of CB are employed by some utilities but
are usually not considered necessary. Therefore, only one set of CTs is recommended.
2.2.4 Double Breaker Station (Ref: Fig. 1)
It is usual to locate the CTs on the line side after the CBs. The two CTs shall be identical. To
get the line current the secondary currents of the two CTs are summated.
2.2.5 One and a Half Breaker Station (Ref. Fig. 2 and Fig.3)
Like the double breaker station, the CTs are located close to the CBs. At the central CB (Tie
CB) two CT sets are shown. This arrangement utilizes 4 CTs however it is also possible to use
a single set of C.T. with the tie CB thus reducing number of CTs to 3 per diameter. The centre
CT in this case will have to be a non-standard one and therefore 3 CT arrangement is not
recommended at present but can be reviewed at a later date.
Fig.3 shows alternative way of locating the CTs. This arrangement requires 5 CTs. The
advantages with this arrangement are:
- Paralleling of two CTs to the main line protection is not required. This gives better
transient response.
- Separate stub protection can be connected
Presently there are many installations with 4 CT arrangement and performance has been
satisfactory. Therefore, it is recommended that 4 CT arrangement is continued to be adopted.
2.3 Voltage Transformers
2.3.1 Line CVTs
CVTs are used for metering, protection and synchronization. Located at the line entry they
also enable indication of voltage on a line energized from the opposite end. CVTs can also be
used as coupling capacitors for power line carrier (PLC). They are then to be located at the line
side of the line traps and line earthing switches, as shown in Fig. 5.
For 400 kV level it is recommended that each line bay is provided with CVTs all the three
phases. Even for 220 kV substations it is preferable to provide three phase CVTs in each
phase for each line bay. However, depending on utility practice CVTs in one phase may also
be provided in which case protections will have to be connected to Bus VTs.
2.3.2 Bus CVTs
Three phase VTs/CVTs on the busbars provide input for directional relays and reference voltage
for synchronization. These VTs will have to be selected by using voltage selection scheme.
1.5 Listed below are some of the more usual tests, with comments:
1.5.1 Insulation Resistance Tests
These tests should be done with 500 V D.C. Megger. Each circuit should be tested in turn
whilst all the others are earthed to ensure that there is no connection between two supposedly
separate circuits.
It is difficult to qualify in general, what value of insulation resistance should be obtained. On
panel and other indoor wiring one would expect a figure in excess of 100 M.ohms. On outdoor
wiring in a medium-sized substation, with wiring loops into many auxiliary switches and junction
boxes, 1 M.ohm would not be unreasonable. The weather can also affect the results. A warm
humid day tends to lower the value where as a cold dry day gives high values. It is recommended
that items like space heater and illuminating lamps are discounted during meggering.
1.5.2 Secondary Injection Tests
These tests consist of AC injection into the relay to ensure that its calibration is correct. In
general, high-accuracy secondary injection tests on site are not necessary. What is needed is a
set of figures, reproducible later from time to time on routine tests, which bear a known
relationship to accurate figure previously obtained. Guidance should be taken from the
manufacturer recommendation in this regard.
1.5.3 Polarity Tests
Much of the preliminary checking can be done with the aid of a 1.5 V battery and a centre zero
voltmeter. All the CTs in a group should be checked in turn to prove that they are connected
to the protection with correct polarity.
1.5.4 Primary Injection Tests
I
Primary Injection Tests are required to prove that CTs are correctly connected to relays. These
tests should include a check of the polarity of the three CTs in a group, and often the comparison
of the group with another.
I
1.5.5 Tripping and Closing Tests
II
1
Trip circuit supervision relays should be proved and it should be checked that the alarm supply
is not fed from the same supply as being supervised, otherwise no alarm could be given if the
supervised supply failed. Trip-healthy lamps and resistors should be proved.
1.5.6 Indications and Alarms
I These tests should involve checking each indication and alarm function correctly.
1.5.7 Tests on Commissioning of Carrier Protection
Apart from the tests recommended on the carrier equipments itself, check should be made to
ensure correct connection and implementation of logic between relay panels and carrier
equipment.
1.5.8 Phasing Tests
It is necessary to prove correct phasing before a new piece of equipment can be put in parallel
with existing equipment.
When a circuit is being paralleled for the first time, the VT associated with that circuit must be
energised from a known source and outputs should be compared with outputs of already proven
VTs to prove that the VT connections are correct.
1.5.9 On-load Tests
(i) Standing Current in Relays
Having got the new equipment on load it is essential to do on load tests. It should be checked
that there is negligible spill current in any residually connected relays and in any protection
working on the differential principle. Appearance of current in differential circuit should also
be chekced either by reversing or shorting and disconnecting one of the C.T. connections.
Before measuring current in the CT circuits of differential relays care should be taken to remove
the appropriate trip link.
(ii) Directional Relays
On load tests are also required to prove the polarity of the VT connection with respect to CT
connection. This will ensure that the schemes/relays are looking in proper direction. The
manufacturers instructions are to be followed to conduct this test. The types of relays that need
to be tested this way are directional relays and distance relays/schemes.
1.0 GENERAL
In order to ensure healthiness and maximum availability of protective relays it is necessary to
carry out periodic testing. Presently, manual as well as microprocessor based automatic testing
kits are available. While the manual kits have been in use by utility engineers in past, automatic
test kits are relatively recent introduction. Apart from automatic testing capability, these kits
are also capable of replaying the fault recordings captured by disturbance recorders as well as
transient simulation done using Electro Magnetic Transient Programme (EMTP). Also, it is
possible to do comprehensive end to end testing of line protections including protection signalling
with use of these automatic kits in conjunction with Time synchronising equipment. Utilities
may decide on requirement of manual or automatic kits depending on size of their network and
testing practices.
2.0 REQUIREMENTS
2.1 Manual Test Kits
(a) Portable over current relays testing equipment. The input rating shall be between 200-
250 V. 5 0 Hz, AC supply and the current output range shall be 0.05-200 amps. with
negligible harmonic distortion of less than 1%. A time interval meter shall be fitted to
read and display 0-10 seconds with an accuracy of + 10 milliseconds.
(b) Portable test equipment for testing distance relays comprising supply unit, control unit
and fault impedance unit. Suitable for Ac voltage from 380-440 V, three phase, 3 wire
system 2 0 Ampere (short time rated) with built in safety devices.
2.2 Automatic Test Kits
It shall be suitable to test all types of distance, overcurrent, ground relays, synchronising,
transformer, reactor and busbar protection relays of major manufacturers in automatic as well
as manual mode.
It shall include all the accessories required for making the complete test set up.
It shall have three phase current output range 0-30 amps. (rms) and three phase voltage range
0- 11 0 voltage (PH-G).
It shall work on single phase 240 V, 5 0 Hz + 10% supply
Shall include necessary software and hardware
(a) To accept fault recordings available from fault data recorder/numerical relay/EMTP
simulation and replay these on the relay under test.
(b) To draw the relay characteristics
The accuracy of relay test kit shall be as follows:
1% for voltage aid current output and resolution of time measurement of 1ms or better.
REFERENCE STANDARDS