LABOR ESTIMATE: 26) Installation of Wood Jalousies 1 man install 2 pcs.

30”x 45” or
Windows 18.75 ft.2/day
1) Concreting of plain flooring 2 men pour 1.20 cu.m. conc./day DOORS WINDOWS:
2) Concreting of reinforcement
flooring 2 men pour 0.84 cu.m. conc./day
3) Concreting of col. & beam 2 men pour 0.50 cu.m. conc./day 1) Panel Door (Narra) 1m.x 2.10m.
4) Finishing of flooring (rough) 2 men finishes 72 sq.m./day 2) Panel Type Door (Tanguile) 1m. x 2.10m
5) Finishing of CHB joints 2 men finishes 420 pcs./day 3) Flush Type Door 1m. x 2.10m.
6) Plastering of CHB 2 men plasters 8 sq.m./day 4) Aluminum sliding Door 1.80m. x 2.10m.
7) Laying of CHB 2 men lay 200 pcs./day (w/ 1/4 ” thick glass panel)
8) braking old R-C Flooring 2 men break 0.30 cu.m./day 5) Steel Window, Casement Type 1/8” thk.glass panels
9) Laying of Glazed Tile 4”x 4” 2 men lay 100 pcs./day ( measure reg’d area)
10) Laying of Glazed tile 6”x 6” 2 men lay 72 pcs./day 6) Jalousie Window
11) Installation of Water Closet 2 men install 1-set WC/ 2days (w/ Alum. Frames & glass blades)
12) Instillation of Lavatory 2 men install 1-set Lav./ 1 ½ days (w/ wooden frames and blades)
13) Installation of GI sheets 32”x 8” 2 men install 11 sheets/day 7) Sliding Windows
on steel frames (w/ Alum.& 1/4" thin glass panels)
14) Installation of GI sheets 32”x 8” 2 men install 20 sheets/day 8) Wrought Iron Grills
on wooden frames
15) Installation of GI sheets 32”x12” 2 men install 10 sheets/day
on steel frames EXCAVATION:
16) Installation of GI sheets 32”x 12” 2 men install 15 sheets/day
on wooden frames Soil Hand Excavation MH/m3
17) Fabricating & Installation of 2 men fabricated 5 sheets 32”x 12” Soft Clay Dry Excavation 2.50/m3
Gutter Downspout, Rider Roll install GI sheets/ day Wet Excavation 3.51/m3
18) Installation of GI pipe 1/2 x 20” 2 men install 20 lights/day Hard Medium Dry Excavation 4.90/m3
19) Installation of Doors & Window Jamb 1 man install 3 pcs.2”x5”x16” Wet Excavation 8.59/m3
or 40 bd.ft./day Hard Adobe Dry Excavation 13.50/ m3
20) Installation of Door (Complete of 1 man install 2 pcs. door/day Wet Excavation 13.50/m3
Hinges and Knob)
21) Fabrication of Doors(Excluding 1 man makes 3 pcs./day CONSTRUCTION WORK CAPACITIES IN MANHOURS
Planning of Frames)
22) Planning Rough Lumber 1 man planes 4 pcs. 2’x 4’x 8’or I. Earthwork:
( Including Alignment) 48 bd. ft./day
23) Planning Rough Lumber 1 man planes 10 pcs. 2”x 4”x a) Excavation 1.82 to 2.89 mh/m3
18” or b) Backfill 134 mh/m3
(No Alignment) 120 bd. ft./day II. Formwork:
24) Installation of Plywood Board 2 men install 15 sheets 4”x 8”/ a) Footing, grade, column 2.5 mh/m2
day b) Beams, bond beams, floor slab 2.8 mh/m2
25) Installation of Wooden Post 2 men installs 6 pcs. 4”x 4”x12” c) Roof beams & bond beams 3.01 mh/m2
or 96 bd. ft./day d) Roof slab 3.34 mh/m2
e) retaining walls 2.4 mh/m2 Backfill 3.87 m3/md
f) Stairs & Landing 2.48 mh/m2 Disposal of spoils 4.70 m3/md
g) Form Oil application 6.0 mh/10m2 Form work 2.70
Steel work 10 kg./md
III. Reinforcement Concreting 0.91 m3/md
Ceil Framing 44 bf/md
a) Reinforcement of footing up to roofing average 9.0 mh/ 100 kls. Roof Framing 33bf/md
b) Grade slab EWP 13 mh/100m2 Ground Floor slab
c) Floor membrane 15 mh/100m2 (Concreting) 1.00 m3/md
d) Roof beams & bond beams 2.88mh/m3 Inst. Steel Sliding Door 10 ft2/md
e) Stairs 2.6 mh/cu.m. Place metal Nosing 3 steps/md
f) Roof slab 2.91 mh/cu.m. GI gutter( Cut & shape) 50 bf/md
g) Curing (water) 2.0 mh/day for 7
days DOORS & WINDOWS:
h) Equipment:
1) Vibrator 16 min./m3 Inst. Wooden Windows 30 ft.2/md
2) Crane w/ concrete bucket 4 cu.m./mh Inst. Sash Glass 75 ft.2/md
Inst. Steel Window 17 ft.2/md
CAPABILITIES OF MANUAL LABOR PER HOUR Inst. Wood Panel Doors 22 ft.2/md
Inst. Lock Set 5 set/md
Unit Type of Work Capability Inst. Wod Flush Doors 20 ft.2/md
Inst. Flush Bolts 2 pairs/md
1) Man a) Excavating Loam or Sand 0.76 m3 Inst. Astragal 80 lf/md
b) Excavating Clay or Heavy Soil 0.61 m3 Vitrified the Wall Fin. 1.34 m2/md
c) Excavating Rock 0.38 m3 Painting 100-300 ft.2/md
d) Backfilling 1.22 m3 Door Hardener 2 m2/md
e) Spreading tamping & Grading 2.09 m3 Copper H2O Stop & Shape 60 lf/md
f) Planning escombro fill 2.0 m3 Copper H2O Stop Install 38/md
g) placing binders 4.0 m3
h) Cleaning undergrownd & Small blush 20 m2 CABINETS
i) Cleaning underground & Brush 12” 20 m2
Framing 30-60 bf/md
2) 1 Mason & a) Laying of CBH 7 Adobe 22 pcs. Boarding 40-80 bf/md
1 Helper b) Cement finish 28 m2 Plywood Sheathing 75-150 ft.2/md
Cabinet & doors 40-80 ft.2/md
3) 1 Carpenter & a) Erecting Forms 1.86 m2
1 Helper b) Removing forms 1.86 m2 TRUSSES:

MISCELLANEOUS LABOR OUTPUT Truss fabrication 46 bf/md


*md- Mondays = 8 hrs. Truss Erection 40 bf/md
Excavation 1.35 m3/md Posts 60-90 bf/md
Girts 50-75 bf/md 6) Excavation Manual
Plates 90-120 bf/md Common Earth 1 man work 1.00 m3/8 hrs 0.125 m3/hr.
Purlins 40-60 bf/md Loam of Sand 1 man work 0.76 M3/HR.
Fascia Boards 25-35 bf/md Clay of Heavy Soil 1 man work 0.61 m3/hr.
Rock 1 man work 0.38 m3/hr.
ROOFING & H2O PROOFING:
7) Mechanical Compaction 7.00 m3/hr.
Insts. Asbestos Roofing 18 shts/day Common earth 0.15 m3/hr.
Insts. Aluminum or GI Roofing 10 shts/day Rock w/ Jackhammer 0.06 m3/hr.
Insts. GI Gutter # 24 16 lf/md
Copper Cladding Roof Deck 52 lf/md 8) Backfilling 1 man work
Install Membrane H2O Proofing 29 m2/md Common Manual 1.24 m3/hr.
Fabricate GI Gutters 2.3 shts/md Gravel Fill Manual 0.20 m3/hr.

9) Mechanical Compaction 7.00 m3Hr.


RATE PER ITEM WORKS: Plate Compaction 18.00 m3/hr.

1) Ceiling: 10) Spreading, Tamping & Grading 1 man work 2.09 m2/hr.
2
Frame Installation 1.33 hr/m 11) Escombro Backfilling 1 man work 4.78 m3/hr.
Plywood Installation 1.00 hr/m2 12) Placing binder- Gravel 1 man work 9.46 m3/hr.

2) Flush Door 3’x 7’ 21 sf. FORMULA FOR ESTIMATING THE COST OF A HOUSE/ BUILDING
Frame 32.5 bf.
Board 2 bf. * Multiply: Floor Area x P 3,500.00 + P 5,000.00
Glue 0.10 gal. Min. cost = P 5,000/m2
Fabrication 1 man work 12 hr./pc/
13) Trenching & Backfilling of underground piping using
3) Door Jamb 2’ x 6‘ lumber Excavation materials manual
Fabrication 1 carpenter 4.5 bf./hr.
Installation 2 carpenter 6.0 bf./hr. From 0 to 2 m. depth 0.80 L.M./hr.
2 to 3 m. depth 0.60 L.M./ hr.
4) Metal Doors 3’ x 7’ 3 to 4 m. depth 0.40 L.M./hr.
Steel door w/ #16 Cladding & 4 to 5 m. depth 0.30 L.M./hr.
LCS C Frames # 12 of SOLF 14) Placing Concrete
Fabrication 2 steel man/ welder 24 hr./pc. Slab on Fill 0.20 m3/hr.
Equipmemt 1 welding machine 8 hr./pc. Slip form 0.04 m3//hr.
Floor Finishing Unhardened 1.00 m2/hr.
5) Manual Cleaning & Grabbing Conc. Fin. Hhardened 0.70 m2/hr.
Cleaning Underground & trees 12”dia. 20 m2/hr/
Cleaning Underground & shrubs 40 m2/hr. 15) Water Stop Installation 1 man work 1.50 L.M./hr.
16) Caulking-sag joint 1 man work 5.00 L.M./hr.
17) Asphalting 1 man work 1.25 m2/hr.
18) Pebble Finish 1 man work 0.70 m2/hr.
19) Marble Slab- Installation 1 man work 0.50 m2/hr. 32) Installation of Alum. Or
20) 1/4 x 2 x 8 Red Bricks 1 man works 0.20 m2/hr. GI Sheet 10 Sheet/man days
21) Glazed Tiles 1 mason,1 helper 0.19 m2/hr. 33) Installation of Asbestos
22) Unglazed Tiles 1 mason, 1 helper 0.23 m2/hr. Roofing 08 sht./man days
23) Reinforcing Bars: 34) Fabrication of Wooden Trusses 47 bf./md
Fabrication 1 steel man 10 kg./hr. 35) Fabrication of GI Gutter 2.3 sht./md
Installation 2 steel men 10 kg./hr. 36) Installation of Wooden Post 40 bf./md
37) Erection of Wooden Post 40 bf./md
24) steel Window 38) Girts 50-75 bf./md
Installation 2 men work 01 pc./hr. 39) Plates 90-120 bf./md
25) Door Lockset 1 carpenter 5 set/ 8hrs. 40) Fascia Board 25-35 bf./md
26) CBH Laying 41) Ceiling Framing 44 bf. /md
6” CHB 1 mason,1 helper 1.25 m2/hr. 42) Ceiling Plywood 60 sf../md
4” CHB 1 mason, 1 helper 1.50 m2/hr. 43) T & G Flooring 112 bf./md
8” CHB 1 mason, 1 helper 1.00 m2/.hr. 44) Plywood Partition 80 sf./md
27) W- Panel 45) Roof Framing 33 bf./md
Installation 2 men work 5 pcs./hr. 46) Formworks 2.50 m2/md
28) Tinsmitting:
Corr. GI Sheet lifting, 4 men 0.27 hr./sq.m.
Corr. GI Sheet Installation, 2 Tinsmith 1.22 sq.m./hr.
Gutter Cut & Shape, 1 Tinsmith 6.25 LM/hr.
Gutter Installation 2 Tinsmith 2.25 LM/hr.
Downspout Cut & Shape, 1 Tinsmith 3.30 LM/hr.
Downspout Installation, 1 Tinsmith 7.50 LM/hr.

29) PAINTING WORKS:

Any Paint 1 Painter 3.48 sq.m./hr.


Varnishing 1 Varnisher 2.32 sq.m./hr.
Structural Steel Frame:

1 Painter 20 hr./mt. Ton

30) Concrete Demolition, 5 Men 0.31 cu.m./hr.


31) CHB Laying:
6” CHB 1 Mason,1 Helper 1.25 sq.m./hr.
4” CHB 1 Mason,1 Helper 1.50 sq.m./hr.
8” CHB 1 Mason,1 Helper 1.00 sq.m./hr.