You are on page 1of 11

Journal of Cleaner Production 143 (2017) 1094e1104

Contents lists available at ScienceDirect

Journal of Cleaner Production


journal homepage: www.elsevier.com/locate/jclepro

An input-output simulation model for assessing production and


environmental waste in construction
Hamed Golzarpoor a, *, Vicente Gonza
lez a, Mehdi Shahbazpour b, Michael O’Sullivan c
a
Dept. of Civil and Environmental Engineering, The University of Auckland, 20 Symonds Street, Auckland 1010, New Zealand
b
Dept. of Mechanical Engineering, The University of Auckland, 20 Symonds Street, Auckland 1010, New Zealand
c
Dept. of Engineering Science, The University of Auckland, 70 Symonds Street, Auckland 1010, New Zealand

a r t i c l e i n f o a b s t r a c t

Article history: Traditionally, the focus of lean construction has been on production waste (a component of production
Received 19 July 2016 that does not add value to the system) while environmental waste (unnecessary use of resources or a
Received in revised form substance released into the air, water, or land) has been the focus of sustainable construction. Production
2 December 2016
and environmental wastes are dependent. However, they are separately assessed in construction.
Accepted 3 December 2016
Available online 9 December 2016
Developing methodologies to simultaneously assess production and environmental performance is still a
significant challenge in construction. This paper explores the impact of lean production on the envi-
ronmental performance of construction projects to propose a framework for simultaneous management
Keywords:
Lean construction
of production and environmental waste. A hypothetical project is illustrated by simulation, which in-
Production waste tegrates a Discrete-Event Simulation (DES) model of construction operations and an Input/Output (I/O)
Sustainable construction framework for environmental loads. Preliminary results show that the DES-I/O framework is capable to
Environmental waste not only reduce project time and cost with better resource utilization, but also to demonstrate energy
Discrete-event simulation savings and a decrease in greenhouse gas emissions.
© 2016 Elsevier Ltd. All rights reserved.

1. Introduction dependent. However, they are separately assessed in construction.


Due to the fact that both lean and sustainable construction methods
Lean production is a management philosophy that results in focus on the minimization of waste, mixing these approaches can
elimination of waste (see Section 2.1). The implementation of lean enable lean construction to adopt an environmental dimension
production in construction is known as lean construction. One of (Carneiro et al., 2012). Despite the synergy between lean con-
the main goals of lean construction is to eliminate production waste struction and sustainable construction, lean construction does not
(Koskela, 1992). Production waste is a component of production explicitly incorporate environmental waste, where a blind spot is
that does not add value to the system (see Section 2.2). Apart from created with respect to the environmental risk and life cycle impact
the production waste, the increased concern on environmental (EPA, 2011). Based on the potential benefits of using a mixed
sustainability, has generated a new form of waste called environ- approach to manage waste, the aim of this paper is to explore the
mental waste (Belayutham et al., 2016). Environmental waste is an impact of lean production on the environmental performance of
unnecessary use of resources/substances released into the air, wa- construction projects. The effect of improving production perfor-
ter, or land that could harm human health or the environment (EPA, mance on minimization of waste, a common concept in both lean
2011). Reducing environmental waste is one of the main goals of and sustainable construction, is discussed. A simulation model of a
sustainable construction. Sustainable construction is the applica- hypothetical construction project, which integrates a Discrete-
tion of the principles of sustainable development in construction Event Simulation (DES) model of construction operations and an
(see Section 2.2). In fact, production and environmental wastes are Input/Output (I/O) framework for environmental loads is proposed.
DES and I/O concepts were investigated in order to develop this
model. They were found to be compatible approaches for analyzing
and managing both production and environmental waste in con-
* Corresponding author.
E-mail addresses: hgol431@aucklanduni.ac.nz (H. Golzarpoor), v.gonzalez@ struction. Lean-based management methods or strategies were
lez), m.shahbazpour@auckland.ac.nz (M. Shahbazpour),
auckland.ac.nz (V. Gonza implemented in the DES-I/O simulation model in order to reduce
michael.osullivan@auckland.ac.nz (M. O’Sullivan).

http://dx.doi.org/10.1016/j.jclepro.2016.12.010
0959-6526/© 2016 Elsevier Ltd. All rights reserved.
H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104 1095

production waste and its impact on environmental waste. The use 2.2. Production and environmental waste
of this simulation model was illustrated and tested through a hy-
pothetical construction project. In construction, waste is commonly interpreted as physical
waste that includes material waste (Golzarpoor and Gonza lez,
2. Background 2013). However, the concept of waste in construction is broader
than material or physical waste. Production waste represents
2.1. Lean production components of production that do not add value to the system
(Koskela, 1992). Transportation (movements that are not required
Lean production is a management philosophy focused on adding to perform a process), inventory (large numbers of material in
value from raw materials to finished product. It is grounded on the store), motion (equipment or people moving more than necessary),
Toyota Production System (TPS) principles focused mainly on the waiting (waiting of any resources that cause gaps and delays be-
elimination of waste. From a lean standpoint, waste is a component tween activities), overproduction (producing more than required),
of production that does not add value to the system. TPS originally over processing (additional steps in processes that are not required)
addressed the seven types of production waste that were subse- and defects (extra effort involved in fixing problems) are catego-
quently adopted by lean production, namely: transport, inventory, rized as lean production waste (Ohno, 1988). As lean construction is
motion, waiting, overproduction, over processing and defects a process focused performance improvement concept and has
(Ohno, 1988) (see Section 2.2). Lean thinking can be summarized in mostly been used to reduce production waste, it does not explicitly
five fundamental goals (Womack and Jones, 2010): eliminate include environmental waste. Instead, environmental waste is the
waste; establish value stream; encourage flow; pull production; focus of sustainable construction. Sustainable construction is the
and pursue perfection. From these goals, a number of principles, application of the principles of sustainable development to the
strategies and management methods have been developed. comprehensive construction cycle from the extraction of raw ma-
Following is a description of the strategies and management terials, through the planning, design and construction of buildings
methods that are used in this research. and infrastructure, until their final deconstruction and manage-
ment of the resultant waste (Tan et al., 2011). Sustainable con-
 Just-In-Time: Inventory is parts or materials on hand, needed for struction refers to the integration of environmental, social and
the manufacturing process. The way to maintain the absolute economic considerations into construction business strategies and
minimum level of inventory of a part is to coordinate deliveries practices (Tan et al., 2011). Considering the environmental dimen-
with use in the production process. JIT can be defined as zero sion (environmental sustainability), minimization of environ-
inventories what lean production is aimed at (Hopp and mental waste is the key component of sustainable construction
Spearman, 2011). (EPA, 2011). EPA (2011) defines environmental waste as ‘unnec-
 Reducing Work-In-Process: Work-In-Process (WIP) is that part essary use of resources or a substance released into the air, water, or
of a manufacturer’s inventory that is in the production process land that could harm human health or the environment’. Excessive
and has not yet been completed and transferred to the finished energy/water consumption, emissions and effluents are examples
goods inventory. Despite the JIT theoretical goal of zero in- of environmental waste. Lean and sustainable construction natu-
ventory, it is not possible to operate a manufacturing system rally share a common goal: to eliminate as much waste as possible
with zero WIP since it would imply zero throughput. In practice, (Nahmens, 2009). They share many of the same best practices to
lean production aims to minimize WIP meanwhile the system reduce their respective waste (Martínez et al., 2009). The U.S. EPA
keeps producing throughput (Reinertsen, 2009). confirms that the performance improvement of production systems
 Reduction of Cycle Time: Lean defines cycle time as the period can lead to the reduction of environmental waste (EPA, 2011).
required to complete one cycle of an operation from start to However, in any production system there are trade-off relation-
finish. Lean production places a tremendous emphasis on ships between production and environmental variables (e.g.
reducing cycle time as it is the key operational metric used to reducing time/cost increases fuel consumption/carbon emission or
determine performance/productivity (Reinertsen, 2009). vice versa) (Shahbazpour and Seidel, 2006). Including environ-
Reduction of cycle time is known as a lean strategy with a huge mental waste (which is the focus of sustainable construction) in the
potential in reducing production waste. list of production waste categories (which is the focus of lean
 Reduction of Batch Size: A batch is the unit of work that passes construction) can encourage the simultaneous assessment of pro-
from one stage to the next stage in a production process. In lean duction and environmental variables. It enables decision makers to
production systems, the batch size should be kept as small as arrive at a maximized level of production performance while
possible in order to ensure a smooth and rapid flow of materials. minimizing the impact on the environment. Inclusion of environ-
Reducing batch size drives down not only cycle time but WIP mental waste in the list of production waste categories has been
(Reinertsen, 2009). confirmed by Rosenbaum et al. (2012). Rosenbaum et al. (2012)
 Kaizen: Kaizen is an approach that seeks improvement in pro- argue that current lean and sustainable construction approaches
ductivity as a gradual and methodical process. It is the practice exhibit a disconnect between production and environmental waste
of continuous improvement with the aim of eliminating waste management. Developing a comprehensive waste reduction model
(Hopp and Spearman, 2011). Examples of Kaizen are produc- for the implementation of both practices into one coordinated
tivity improvement and process optimization. effort is desirable.

Productivity is an average measure of the efficiency of produc- 2.3. Life cycle assessment and life cycle inventory data
tion. It can be expressed as the ratio of output to inputs used in the
production process. LCA is a methodology for evaluating the environmental impacts.
Process optimization is the discipline of adjusting a process so as It is carried out in four distinct phases. In the first phase the goal
to optimize some specified set of parameters without violating and scope of the investigation and the resulting system boundaries
some set of constraints. When optimizing a process, the goal is to are defined. Life Cycle Inventory (LCI), the second phase, involves
maximize one or more of the process specifications, while keeping creating an inventory of Input and Output flows for a production
all others within their constraints. system. Inventory flows include inputs of water, energy and raw
1096 H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104

materials; and outputs to air, land and water. LCI is followed by Life the environmental and production parameters are assessed
Cycle Impact Assessment (third phase) and Life Cycle Interpretation simultaneously to allow the main decision makers to arrive at an
(final phase) (ISO14040, 2006). optimized level of production performance while minimizing the
It is clear that successful LCA is dependent upon reliable LCI impact on the environment (Gonza lez and Echaveguren, 2012). A
data. However, current LCI based approaches for environmental common trade-off example in construction is between time and
analysis in construction have two main modeling limitations: (1) cost. Construction managers are often faced with situations where
LCI does not include proper quantitative analysis of the uncertain, operations should be finished ahead of time (either the project has
complex and dynamic nature of production systems, (2) LCI lacks fallen behind, or the completion date has been moved up). In such
simultaneous assessment of environmental and production per- case, duration of a series of activities on the critical path should be
formance (Golzarpoor and Gonza lez, 2013). reduced (Aminbakhsh and Sonmez, 2016). As this usually increases
One of the main aims of LCA is to quantify the environmental overall cost of resources, time-cost trade-off analysis is applied (to
impact of a given production system, and as a result there is a large Critical Path Method) in order to determine the most optimum
emphasis on the data aspect of LCI. LCI data is basically categorized scenario which allows meeting the deadlines while keeping the
into ‘material LCI data also known as material I/O data’ and ‘process imposed cost at minimum (Sonmez et al., 2015). As the environ-
LCI data also known as process I/O data’. In order to overcome the mental performance is gaining more and more significance, this
LCI limitations for construction management purposes, the process research highlights the need for developing frameworks that sup-
I/O date (known as ‘I/O framework’ in this research) needs to be port trade-off analyses between production and environmental
complemented with a modeling approach that is able to effectively parameters.
represent the complex and dynamic nature of production processes The structure and nature of both DES and the I/O framework are
in construction. This research proposes a dynamic modeling compatible and provide an opportunity for integration, allowing
approach based on the integration of Discrete-Event Simulation life-cycle environmental factors to be considered in decision mak-
and the I/O framework. €fgren and Tillman, 2011). This integration
ing at a detailed level (Lo
allows causes and effects of various scenarios to be analyzed where
2.4. Discrete-event simulation time, resources, location and stochasticity affect the outcome
(Johansson et al., 2009).
Discrete-Event Simulation (DES) is an event-driven simulation A number of studies have revealed positive effects on the eval-
approach in which a real dynamic process is imitated as it pro- uation of environmental metrics while integrating DES and I/O
gresses over time (Lo€ fgren and Tillman, 2011). DES models describe framework in the manufacturing industry. Table 1 summarizes the
time-driven systems, where state variables change instantaneously Integration of DES and I/O framework in Manufacturing.
at separate points in time (Law, 2007). The main goals of DES are to: In the last three decades, DES modeling in construction has been
1) identify problematic areas in a current or proposed system, 2) given a significant amount of attention, and several researchers
implement ‘what if’ experiments, and 3) optimize (production) have developed simulation tools and engines to model and opti-
system performance. Optimization is achieved by changing model mize construction operations (Marzouk and Moselhi, 2003).
input parameters such as: work shifts, routes for material, and However, the study of a project’s environmental impacts has not
available storage, to improve performance metrics that may yet received much attention in construction, except for some recent
include: throughput under average and peak loads, utilization of studies that have focused on the analysis of emissions in con-
resources, queue lengths at work locations, and work-in-process struction projects using DES and environmental models (Gonza lez
(Lind et al., 2009). DES is not only able to model complex systems and Echaveguren, 2012). The integration of DES and the I/O
with highly dynamic decision rules and relationships between framework has not been applied for environmental analysis of an
different entities and resources, but can also explicitly address entire construction product (road, building, bridge, etc.). By
system uncertainty (Law, 2007). The value of DES lies in its ability to learning from the manufacturing industry, this research can fill the
capture the variability of events instead of using mean values as gap in the construction literature by developing an integrated DES-
model inputs, restricting the need for assumptions. DES has also I/O simulation model specific to the production setting in
been recognized as a powerful technique for the quantitative construction.
analysis of complex construction operations (Martínez, 2010).
3. Research scope
2.5. Integration of DES and I/O framework
Fig. 1(1a) illustrates all life cycle phases of construction products
Reuter and Schaik (2004) state that even though the purpose of and components. Fig. 1(b) shows a scheme of the processes in each
LCA is clear, it is developed under a static approach without of the life cycle phases. Process 1, Process 2 and Process 3 represent
involving statistical and/or probabilistic analyses of measures that activities in each of the three phases. The corresponding inputs of
consider the complex and dynamic nature of production systems. each process are resources and energy, and the outputs are emis-
Production systems in construction include a large number of sions, residuals and the product or semi-product (which is trans-
variables and processes, complex and dynamic relationships be- ferred to the next phase). The sub-index indicates the process and
tween entities and resources, and high levels of uncertainty the process number.
(Gonzalez et al., 2012). Due to DES’s capability to analyze stochastic In order to simplify the model and better demonstrate the
scenarios and its ability to quantitatively analyze the complex and linkages between environmental and production performance pa-
dynamic nature of production systems, an integrated DES-I/O rameters, the scope of this research is limited to the process anal-
simulation framework that adds stochasticity to the produced I/O ysis in the construction phase (phase 1 in Fig. 1). Although
data should provide substantial benefits. processes in the other life cycle phases are excluded, they could be
The DES and I/O approaches could be separately applied in modeled based on the same simulation modeling framework
construction, without the need for integration. However, explained in Section 5. Key production variables such as time and
Shahbazpour and Seidel (2006) argue that in any production sys- cost were considered for process analysis in this research. The
tem there are trade-off relationships between environmental pa- environmental variables considered for process analysis were en-
rameters and production performance. It is therefore critical that ergy consumption and carbon emission (associated with energy
H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104 1097

Table 1
Integration of DES and I/O framework in manufacturing.

Authors Positive effect

Solding and Petku (2005), Solding and Conducted a few case studies of the Swedish foundry industry in which electricity use was simulated using DES
Thollander (2006)
Wohlgemuth et al. (2006) Developed a method to include both economic and ecological factors and applied the method to model a
semiconductor lithography process
Ingvarsson and Johansson (2006) Linked a company’s food processing, which was modeled using DES, with static environmental background data on
upstream processes
Reinhard and Motsch, 2007 Provided an understanding of the relationship between electricity and material usage and identified energy saving
potentials
Huang et al. (2007) Developed a model to predict the long term environmental consequences of different urban water management
strategies
Persson and Karlsson (2007), Alvemark and Used DES as a tool for environmental measurements in food production
Persson (2007)
Johansson et al. (2008) Combined DES with I/O data to improve a juice manufacturing system
Heilala et al. (2008) Presented the I/O framework to the DES community to assess the automation level, ergonomics and environment of
manufacturing systems
Guidosh (2009) Combined the I/O framework with DES to assess the environmental impact of diapers (a standard model was
translated into a DES environment)
Dietmair and Verl (2009) Developed a specific DES method for detailed modeling of energy use for machine operations
€ fgren and Tillman (2011)
Lo Described how DES can be combined with I/O to measure in detail the environmental performance of a company’s
manufacturing system
Andersson et al. (2012b) Evaluated methods used for life-cycle assessments in DES
Andersson et al. (2012a) Proposed a framework for eco-labeling using DES
Cao and Li (2014) Proposed a DES-based approach to model carbon emissions dynamic characteristics of manufacturing systems
Aughney and O’Donnell (2015) Proposed a structured approach to save energy from non-value added manufacturing activities
Sproedt et al. (2015) Proposed a DES-based decision support system for eco-efficiency improvements in production systems
Stiel et al. (2016) Enhanced manufacturing and transportation decision support systems with LCA add-ins
Uluer et al. (2016) Proposed a framework for energy reduction in manufacturing process chains
Wilson et al. (2016) Proposed an energy usage toolkit from manufacturing simulation data

were developed by modifying the base model defined in this study.


For each model, a number of simulation runs were developed to
achieve estimates with 95% confidence and a relative error of less
than 5% (Law, 2007). Simulation output analysis focuses on
assessing the improvements achieved by comparing the environ-
mental and production performance of each of the improved
models with the base model.

5. Input/output simulation modeling framework

Fig. 1. Life cycle phases of construction products and components (Res ¼ Resources,
5.1. Conceptual modeling framework
En ¼ Energy, Em ¼ Emissions, Re ¼ Residuals, P ¼ Process).
The hypothetical project illustrated by simulation in this study
consists of earthmoving and foundation operations. The project
consumption). Since the scope of decision making in the hypo- consists of three work sites (Site 1, Site 2 and Site 3) where trucks
thetical illustration presented in this paper was limited to choice of are loaded by excavators and concrete is deposited by mixers, a
machinery and sequence of movements, I/O data related to mate- truck site which the trucks are parked in, a dumping site which
rials used in the construction process were regarded as out of scope. enables excavated material to be dumped at, and a batching plant
The I/O framework in this research is defined as the process I/O where mixers are filled with concrete. Initial number of loaders,
data. trucks and mixers were considered 1, 3 and 2 at each site.
At each work site two operations take place: an excavation
4. Research method operation (O1) and a foundation operation (O2). Each operation
consists of several processes. Fig. 2 shows a logical representation
The research method is based on developing the DES-I/O of both O1 and O2. The O1 includes the movement of trucks from
simulation model. ExtendSim v8, a DES modeling software pack- the truck site to each of the sites (T Move), loading of trucks by the
age was used to model the project operations as it enables visual- loaders available onsite (L/T Excavate), hauling the excavated ma-
ization and copes with highly dynamic, complex systems. Modeling terial to the dumping site (T Haul), the dumping process (T Dump)
assumptions and the simulation framework are explained in Sec- and finally returning back to the truck site (T Return). When the O1
tion 6. This is followed by implementation of lean-based manage- is finished, the O2 starts with filling mixers at the batching plant (M
ment methods/strategies in the DES-I/O model and simulation Fill), followed by hauling the concrete to the sites (M Haul),
output analysis. A number of simulation settings (explained in dumping concrete to fill the excavated volume (M Dump) and
section: Sustainable Lean Experiments), were proposed, where returning back to the batching plant (M Return). Fig. 3 shows the
several lean improvements were considered for implementation in conceptual model of the behavior of truck, soil (excavated material)
the project. The key research goal was to implement lean and loader in O1. Similar figure could be drawn for the behavior of
improvement into the system and, assess production and envi- mixers and concrete in O2. Both Figs. 2 and 3 resulted from the
ronmental performance simultaneously. The improved models application of a new conceptual modeling framework for
1098 H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104

Fig. 2. Logical representation of the excavation and the foundation operations e base model (T ¼ Truck, L ¼ Loader, M ¼ Mixer).

proposed conceptual modeling framework for DES). This frame-


work is independent of the DES package used to model the oper-
ations. The process of transferring the conceptual model of Fig. 3
into any DES package (like ExtendSim that is used in this study)
is discussed in the remainder of Section 5. The purpose of both the
conceptual model and the implemented model in ExtendSim is to
simulate construction operations to assess production and envi-
ronmental performance at the same time. It is highlighted that the
criteria used to evaluate production performance are total time
(total time is the time it takes to complete the project) and total cost
(total cost is calculated by adding up hiring cost and fuel cost); and
the criteria used to evaluate environmental performance are total
fuel consumption (consumed by all types of machinery to complete
the project) and total carbon emission (emitted by all types of
machinery from start to finish of the project).

5.2. Modeling assumptions

In this study, the model’s input is process data and the output is
quantitative measurements of production and environmental per-
formance (e.g. total time, total cost, fuel consumption, carbon
emission). Input data such as distances and costs represent the
assumptions made by the authors using their own experience of
Fig. 3. Conceptual model of the behavior of truck, soil and loader in excavation road construction operations. In order to assume more realistic
operation. duration data for the proposed hypothetical case, an expert with
years of experience in earthmoving operations were asked to es-
timate duration data. Triangular distributions were then fitted to
simulation (Furian et al., 2015). Furian et al. (2015) suggest pre- the duration data. This is based on the heuristic approaches pro-
paring structural view (Fig. 2) and behavioral view (Fig. 3) of the posed by Law (2007) for choosing a distribution in the absence of
modeling scenario. Structural view is the logical/physical repre- data. In triangular approach, used in this research, experts are
sentation of the scenario, while behavioral views represent the asked for their most optimistic, the most pessimistic and the most
behavior of each of active entities (active entities in the hypothet- likely estimates of the time to perform the tasks. Environmental
ical example of this study are truck, loader and soil) (see Furian data including fuel consumption of machinery and the equivalent
et al., 2015 for detailed information about developing the amount of carbon emissions were obtained from the machinery’s
H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104 1099

catalogues and online reports and linked to the model. For instance, Hiring Cost ð$Þ ¼ Operation Time ðhÞ  Hiring Cost per Time ð$=hÞ
a loader consumes up to 0.4 l/km (diesel fuel) in normal conditions
 Number of Machinery
(asphalt road, standard road slope, standard traffic and so on) and
emits up to 1.08 kg CO2 eq. depending on type and model (Ministry (4)
for the Environment, 2015). Table 2 shows required input data
including distance, duration, expected fuel consumption and car- Fuel Cost ð$Þ ¼ Fuel Consumption ðlÞ  Fuel Cost per Volume ð$=lÞ
bon emission of the project processes for building up the base (5)
model. Carbon emission was calculated based on fuel consumption
and emission factor as follows:
Total Cost ð$Þ ¼ Hiring Cost ð$Þ þ Fuel Cost ð$Þ (6)
Carbon Emission ðkg CO2 eq:Þ ¼ Fuel Consumption ðlÞ Fig. 2 explains the distances that are presented in the second
 Emission Factor ðkg CO2 eq:=lÞ column of Table 2. For example, Fig. 2 clarifies that three distances
should exist for the ‘T Move’ process (the distance between truck
(1) site and site 1 which is 24 km, the distance between truck site and
Carbon emission in this study is the equivalent amount which site 2 which is 13 km, and the distance between truck site and site 3
covers the six direct Kyoto gases: CO2, CH4, N2O, HFCs, PFCs and SF6. which is 12 km).
Emissions from other gases considered are too small to be reported
and therefore excluded. The six gases have also been the basis for 5.3. Simulation framework
calculating equivalent emission factor of 2.7 kg CO2 eq./l (transport
fuel: diesel) applied in the DES-I/O model. Guidance for voluntary Fig. 4 shows how the conceptual model can be transferred into a
corporate greenhouse gas reporting (Ministry for the Environment, DES package as ExtendSim in this study. The blocks used and their
2015) was used in this study to ensure data accuracy. functions are shown in Table 3. As illustrated on Fig. 4, the resource
Depending on the nature of the involved processes, fuel con- blocks ‘Initialize Truck, Initialize Excavation Volume and Initialize
sumption of different types of machinery is calculated based on Loader’ hold and provide the resources to be used in the simulation.
distance (movement of machinery from one place to another) or Volume of excavated material, initial number of loaders, and initial
waiting time (duration of the processes) as follows: number of trucks are defined as items in these blocks. In Exten-
dSim, items flow throughout the system (blocks). The number of
Fuel Consumption T1ðlÞ ¼ Waiting Time ðhÞ units of excavated material (defined as items) is calculated based on
the volume of excavated material and the capacity of trucks. As an
 Consumption per Time ðl=hÞ (2)
example, 130 units were defined in the resource block ‘Initialize
Excavation Volume’ as follows:
Fuel Consumption T2 ðlÞ ¼ Distance ðkmÞ
 Consumption per Distance ðl=kmÞ 300 m3 ðExcavation VolumeÞ  1:3 ðSwelling Factor of SoilÞ

(3) ¼ 390 m3 ðVolume of Excavated MaterialÞ

Waiting time is defined as the time that machine is waiting in


(7)
queue for an operation. Equation (2) is applied when machine is Swelling factor indicates the increase in volume of earth once it
waiting in queue for an operation, while equation (3) is applied has been excavated from its natural state.
when the machine is travelling from one place to another.
Hiring costs of machinery were assumed $ 10/h, $ 15/h and $ 25/ 390 m3 ðVolume of Excavated MaterialÞ=3 m3 ðTruck Capacity in
h for trucks, mixers and loaders. Diesel fuel cost was assumed $ 0.8/ the Base ModelÞ ¼ 130 units ðExcavated MaterialÞ
l. Total cost is calculated based on adding up hiring cost and fuel
cost.
(8)

Table 2
Simulation Modeling Input Data for each activity in the Base Model.
a
Activity Distance (km) Duration (min) triangular distribution Expected fuel consumption Expected CO2 emission

Min. Max. Mode l/km l/h kg/km kg/h

T move 24 (S1) 24 72 43 0.25 e 0.675 e


13 (S2) 13 39 23.5 0.25 e 0.675 e
12 (S3) 12 36 21 0.25 e 0.675 e
L/T excavate e 6 13 10 e L: 9.5 e L: 25.6
e T: 5 e T: 13.5
T haul 39 (S1) 39 117 69.5 0.25 e 0.675 e
14 (S2) 14 42 25 0.25 e 0.675 e
28 (S3) 28 84 50 0.25 e 0.675 e
T dump e 1 3 2 e 5 e 13.5
T return 14 14 43 26 0.25 e 0.675 e
M fill e 5 15 11.5 e 6 e 16.2
M haul and M return 4.5 (S1) 4.5 13.5 8 0.3 e 0.81 e
15 (S2) 15 45 27 0.3 e 0.81 e
10.5 (S3) 10.5 31.5 19 0.3 e 0.81 e
M dump e 10 20 16.5 e 6 e 16.2

Note.
a
Calculated based on the transport fuel emission factor of 2.7 kg CO2 eq./l (diesel), Adopted from Ministry for the Environment (2015), (T ¼ Truck, L ¼ Loader, M ¼ Mixer).
1100 H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104

out based on the process time and arrival time of each item. In
other words, processes are simulated by activity delays. Activity
delays are set by connecting activity blocks to random number
generator blocks. Random number generator blocks generate
random integers or real numbers based on selected distributions
(exponential, triangular, beta, etc.). For instance, a triangular
distribution (which represents processing time of an activity) is
fitted to the activity block ‘T Move’, by connecting it to the
random number generator block. Activity block ‘T Move’ defines
the first process for trucks. The batch block allows items from
several sources to be joined into a single item. One loader, one
truck and one unit of the excavated material are batched into a
single item in this block. One unit of excavated material is 3 m3 in
the base model. However, in case of doubling the truck capacity,
each unit of excavated material should be either increased to
6 m3 or two units should be batched together in this block.
Queue/Wait blocks are used in the model whenever there is an
item waiting to be processed by an activity block. When pro-
cessing an item in the activity block ‘L/T Excavate’ finishes, an
unbatch block is used to return back the loader to the queue
block (wait 1 in the figure). However, the excavated material and
the truck are batched again for the ‘T Haul’ process in a new
activity block. As illustrated in Fig. 4, the ‘T Dump’ and ‘T Return’
processes are performed similarly. Loader and Truck return back
and the excavated volume passed out of the simulation using the
exit/leave block.
In this section, the simulation framework was clarified by
Fig. 4. Implementation of the conceptual model in ExtendSim (T ¼ Truck, L ¼ Loader). explaining a selected potion of the model (only activities related
to the excavation operation in the third site within the base
model). The base model and improved models were built by
The initial number of loaders and trucks were assumed 1 and
applying similar modeling strategies to other operations (e.g.,
3 in the resource blocks ‘Initialize Loader’ and ‘Initialize Truck’.
foundation operation) at different sites (site 1, 2 and 3).
Activity blocks are used to hold one or more items and pass them

Table 3
Blocks used to model O1 at S3 - base model.

Block symbol Block name Block function

Resource item This block holds and provides items (trucks, loaders and mixers) to be used in a simulation. It can be used as part
of an open or closed system.

Activity Holds one or more items and passes them out based on the process time and arrival time for each item.

Random number generator Generates random integers or real numbers based on the selected distribution (exponential, triangular, beta,
etc.).

Queue Queue blocks hold items in queue to be able to simulate the waiting time and release them based on a user
selected queuing algorithm.

Batch Allows items from several sources to be joined as a single item. Useful for combining resources.

Unbatch Produces multiple items from a single input item. Useful for detaching resources.

Exit/leave Passes items out of the simulation. The total number of items absorbed by this block is reported in its dialog and
at the value output connectors.
H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104 1101

5.4. Sustainable lean experiments Note that different project times for O1 at S1, S2 and S3 (in
Fig. 5) are due to differences in duration of activities/processes
Several simulation settings based on lean production man- (as in Table 2).
agement methods/strategies have been developed and applied
to the base model in order to simultaneously assess production  Model 3 (Reduction of Transportation: Capacity of Machinery):
and environmental performance. Removing non-value-adding Reducing construction process waste in transportation was
activities or production waste from the project’s operations achieved in the third model by doubling the truck capacity. In
has been the main mechanism for improving the models per- the base model, 1 loader, 1 truck, and 1 unit of soil (3 m3) are
formance (both production and environmental). The analyses batched together. However, in the third model, as capacity of
are based on the simulation outputs from the following six trucks is doubled, 1 loader, 1 truck and 2 units of soil (6 m3) are
models: batched together. Duration of the truck filling process (L/T
Excavate) is also doubled in Model 3. Another assumption is
 Model 1 (Base Model): Production system of the project as that hiring cost of trucks with the capacity of 6 m3 is twice
defined in this study. more than hiring cost of trucks with the capacity of 3 m3.
 Model 2 (Reduction of Cycle Time and Batch Size): However, same fuel consumption is assumed for both types of
trucks in the simulation model. As stated in Section 2.2,
Reduction of Cycle Time: In this model, cycle time is reduced by ‘transportation’ is categorized as one type of lean production
starting O2 immediately after O1 is finished in each of the sites, waste and is defined as ‘movements that are not required to
rather than starting O2 after O1 is completely finished in all sites. perform a process’.
Reduced cycle time is achieved by minimizing ‘waiting times’  Model 4 (Reduction of Transportation: Routing of Machinery):
which is a lean production waste. Similar to Model 3, transportation is reduced in Model 4 by
Reduction of Batch Size: Reduction of the batch size is also changing the truck routing. In this model, trucks return to the
implemented in the second model. In earthmoving operations, total sites immediately after the dumping process is finished. As
excavation volume is normally considered as a single batch. Thus, the loaders only move between the three sites and the
the next operation (O2 in the model) should be started after dumping site, the ‘T Move’ process is omitted and respective
completing the current operation (O1 in the model). However, in changes on distances and durations are applied. In this model,
case of dividing the total excavation volume into several batches, movement of trucks in excavation operation is illustrated in
O2 could be started before O1 is completely finished. In this model, Fig. 6.
O2 starts while four fifth (maximum executive time saving poten-
tial based on O1 and O2 durations) of O1 is finished. Therefore, the In this experiment, the lean production waste ‘transportation’
cycle time is reduced. The batch sizes or excavation volumes and ‘motion’ are reduced.
represent WIP, which in turn, represents inventory (as mentioned,
inventory is waste from a lean standpoint). In practice, lean is  Model 5 (Multi-Objective Optimization of Resources): Optimi-
aimed at reducing inventory as much as possible, avoiding starva- zation of the number of machinery (loaders, trucks and mixers)
tion of processes at the same time. In this regard, a low level of WIP forms Model 5. Evolutionary Multi-Objective Optimization has
was implemented mimicking a minimum level of inventory as been used in this research to optimize how resources are uti-
proposed by JIT. lized. The reason for applying multi-objective optimization was
Fig. 5 shows how O2’s flexibility helps reducing cycle time the possibility of conflict between the variables (total time, total
and batch size. For each of the sites (S1, S2 and S3), this flexi- cost, fuel consumption and carbon emission) (minimizing one
bility has been demonstrated in three different situations may result in maximizing the other, and vice versa). Therefore,
including: the base case with no improvement/change (O2 e No the number of machinery was expected to be optimized in
Change), the effect of reduced cycle time (O2 e Reduced CT), and presence of trade-offs. An Evolutionary Strategy (ES) belonging
the effect of reduced cycle time and batch size together (O2 e to the class of Evolutionary Algorithms was applied to the
Reduced CT & BS). As shown in Fig. 5, the total project time is simulation model as it is well suited to multi-objective optimi-
reduced directly through reducing the cycle time and indirectly zation problems. As a result, the following equation based on
through reduction of the batch size. Reducing cycle time and calculating the least surface, which results in the minimization
batch size reduces lean production wastes ‘waiting time’ and of total time, total cost, fuel consumption and carbon emission,
‘inventory’. was proposed:

Min: Surface ¼ ðT  FC þ T  CE þ FC  C þ CE  CÞ=2 (9)

where FC ¼ Fuel Consumption, CE ¼ Carbon Emission, T ¼ Total


Time, C ¼ Total Cost.
The objective function optimized the number of machinery in
the case of having total time and total cost as production

Fig. 5. Reduction of cycle time and batch size (CT ¼ Cycle time, BS ¼ Batch size). Fig. 6. Movement of trucks in excavation operation e model 4 (T ¼ Truck, L ¼ Loader).
1102 H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104

6. Result and discussion

As discussed, the radial representation is to visualize multiple


metrics and explore trade-offs (see Fig. 7). A ‘spider web’ plot is
used in Fig. 8 to illustrate results of all the models.
Comparing each of the sustainable lean models with the first
model (base model) reveals the improvements achieved.
Model 1 (Base Model) represents production system of the
project as defined in this study.
In Model 2, batch sizes (excavation volumes) represent WIP. It
was expected that reducing WIP reduces the cycle time. As ex-
pected, total project time was the only variable reduced. The
assumption that reduction of batch size and cycle time does not
affect environmental performance was also confirmed by the result
of the second model. Reducing batch size and cycle time together
reduced total project time by 27 h (from 174 to 147 h).
In Model 3 and Model 4, applying the lean based improvement
reduction of transportation and/or motion, whether by increasing
capacity of machinery or decreasing the distance through changes
on the routing, highly impacts environmental and production var-
Fig. 7. Conceptual Figure of the optimization objective function (FC ¼ Fuel con- iables, simultaneously. The significant effect of reducing construc-
sumption, CE ¼ Carbon emission, T ¼ Total time, C ¼ Total cost). tion process waste in transportation on production and
environmental performance is illustrated in Fig. 8 based on the
results obtained from Models 3 and 4. Model 3 saves 56 h on total
time (from 174 to 118 h), $ 4668 on total cost (from $ 25,773 to $
variables on the X axis and fuel consumption and carbon emis-
21,104), 2430 l on total fuel consumption (from 8658 to 6228) and
sion as environmental variables on the Y axis. The different ob-
6561 kg eq. on total CO2 emission (from 23,377 to 16,815); while
jectives have been combined into a single objective that
Model 4 does not affect the total project time but saves $ 2108 on
minimizes the area of the quadrilateral shown in Fig. 7. The
total cost (from $ 25, 773 to $ 23,664), 1621 l on total fuel con-
trade-off between production and environmental variables is
sumption (from 8658 to 7036) and 4377 kg eq. on total CO2 emis-
captured and visualized.
sion (23,377e18,999). Results from Models 3 and Model 4 show
ES uses mutation, recombination, and selection applied to a
that reduction of transportation and/or motion is the best strategy
population of individuals containing candidate solutions in order to
in terms of combined environmental and production performance
evolve iteratively better and better solutions. ES tuning parameters
improvement. However, increasing the capacity of machinery
were set as follows: m1 ¼ 10, l2 ¼ 20, mutation rate3 ¼ 0.25, se-
(Model 3) resulted in greater savings than changes to the routing of
lection pressure4 ¼ 2. In addition to ES tuning parameters, termi-
machinery (Model 4). Note that some other production and/or
nation rules parameters have the purpose of producing enough
environmental variables can be calculated from the 4 key variables
long simulation runs, which guarantees reliable results avoiding
local convergence and sub-optimal solutions. Termination rules
parameters were set as follows: truncation rate ¼ 0.2, minimum
convergence level ¼ 99.5%, maximum number of generations ¼
1000, maximum sampling by generation (simulation runs) ¼ 100.
Optimization of the number of machinery converged to 99.78%
after 287 simulation runs (Convergence level is an indicator of
improvement in optimization. As the results from successive
simulation runs become closer, convergence level approaches to 1).
Due to the fact that there was a trade-off for minimizing the vari-
ables, the number of loaders, trucks and mixers were optimized
from 1, 3 and 2 to 1, 7 and 5 for each site. Multi-Objective optimi-
zation of resources significantly increased utilization rate of ma-
chinery, which in turn, reduced ‘waiting’ (a production waste
category).

 Model 6 (All Changes Combined): All the previous improve-


ments were applied together into Model 6 to demonstrate the
total waste reduction potential.

1
Number of parents involved in the procreation of an offspring (see Beyer, 2007
for more information).
2
Number of offspring created in each iteration (see Beyer, 2007 for more
information).
3
The probability that individuals are randomly altered (see Beyer, 2007 for more
information). Fig. 8. Environmental and production performance (key variables) (TPT ¼ Total project
4
Indicates how much the best individual is better than the worst (see Beyer, time, TPC ¼ Total project cost, TFC ¼ Total fuel consumption, TCE ¼ Total carbon
2007 for more information). emission).
H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104 1103

illustrated in Fig. 8. Fig. A.1 is presented as an extended version of Appendix


Fig. 8 in case further discussion on results is required (e.g. it shows
Models 3 and Model 4 also save 398 and 48 h on total machinery
working time; $ 1944 and $ 1297 on total machinery fuel cost; and $
2724 and $ 811 on total machinery hiring cost).
In Model 5, multi-objective optimization of resources enabled
another lean based improvement by reducing over processing and
unnecessary motion. As expected, results from Model 5 proved that
optimization of the number of machinery do not affect the envi-
ronmental performance, but noticeably affects production perfor-
mance (Fig. A.1 shows multi-objective optimization significantly
reduced the total project time; however, the total machinery
working time has remained almost constant. It also noticeably af-
fects the hiring cost but not fuel cost. The savings on total cost is
mainly due to reduction of machinery’s hiring cost in this model).
One interesting finding from this model is the significant effect of
multi-objective optimization on the utilization rate of machinery.
The optimization model results in the highest utilization rate for
almost all the processes defined.
The results of Model 6 indicate that improving production per-
formance not only reduces the production waste but also envi-
ronmental waste. In cases of production and environmental trade-
off between the models, further research is expected to propose a
suitable decision making mechanism. Model 6 demonstrates the
total waste reduction potential and is the best model in terms of Fig. A.1. Environmental and production performance (all variables). (TPT ¼ Total
combined environmental and production performance. In general, Project Time, TMWT ¼ Total Machinery Working Time, TPC ¼ Total Project Cost,
the lean-based management methods/strategies applied to this TMFC ¼ Total Machinery Fuel Cost, TMHC ¼ Total Machinery Hiring Cost, TFC ¼ Total
Fuel Consumption, TCE ¼ Total Carbon Emission).
hypothetical project reduced total project time by 75% (from 174 to
43), total machinery working time by 39% (from 1123 to 679), total
cost of machinery by 38% (from 25,773 to 15,803), total fuel con-
sumption by 41% (from 8658 to 5127) and total CO2 eq. emission by References
41% (from 23,377 to 13,843).
Alvemark, O., Persson, F., 2007. Flow Simulation of Food Production; Cultured Dairy
7. Conclusion Products (MSc Thesis, Department of Product and Production Development).
Chalmers University of Technology, Gothenburg, Sweden.
Aminbakhsh, S., Sonmez, R., 2016. Pareto front particle swarm optimizer for discrete
From the theoretical standpoint, by exploring the relationship time-cost trade-off problem. J. Comput. Civ. Eng. 04016040.
between lean and environment, this study proposed a sustainable Andersson, J., Berglund, J., Skoogh, A., 2012a. Framework for ecolabeling using
discrete event simulation. In: Emerging Applications of M&S in Industry and
lean approach for simultaneous assessment of environmental and Academia Symposium, Orlando, Florida, p. 9.
production waste in construction using an integrated DES-I/O Andersson, J., Skoogh, A., Johansson, B., 2012b. Evaluation of methods used for life-
simulation framework. The integration of DES and I/O framework cycle assessments in discrete event simulation. In: Proceedings of the 44th
Winter Simulation Conference, Berlin, Germany, p. 156.
has been proved to be effective and efficient in manufacturing.
Aughney, N., O’Donnell, G.E., 2015. The energy saving opportunity in targeting non-
However, it has not been applied to construction. This research value added manufacturing activities e a structured approach. J. Clean. Prod.
provides a proof of concept for the applicability of the proposed 86, 191e200.
Beyer, H.G., 2007. Evolution strategies. Scholarpedia 2 (8), 1965.
methodology through the illustration of a hypothetical project. The
Belayutham, S., Gonz alez, V.A., Yiu, T.W., 2016. Cleanelean administrative pro-
DES-I/O simulation model indicates that improving production cesses: a case study on sediment pollution during construction. J. Clean. Prod.
performance not only reduces production waste but also environ- 126, 134e147.
mental waste. In case of trade-off between production and envi- Cao, H., Li, H., 2014. Simulation-based approach to modeling the carbon emissions
dynamic characteristics of manufacturing system considering disturbances.
ronmental variables (e.g. reducing time/cost increases fuel J. Clean. Prod. me 64, 572e580.
consumption/carbon emission), the DES-I/O integration method- Carneiro, S.B.M., Campos, I.B., Oliveira, D.M., Barros, N.J.P., 2012. Lean and green: a
ology helps decision makers to arrive at an optimized level of relationship matrix. In: Annual Conference of the International Group for Lean
Construction, San Diego, CA, USA.
production performance while minimizing the impact on the Dietmair, A., Verl, A., 2009. A generic energy consumption model for decision
environment. Further research is expected to identify areas with making and energy efficiency optimisation in manufacturing. Int. J. Sustain. Eng.
significant trade-off relationships between production and envi- 2 (2), 123e133.
EPA, 2011. Lean Manufacturing and Environment e Environmental Benefits and
ronmental variables. Shortcomings. Environmental Protection Agency, USA.
From a practical standpoint, the DES-I/O simulation framework Furian, N., O’Sullivan, M., Walker, C., Vo €ssner, S., Neubacher, D., 2015. A conceptual
could serve as a basis for building a generic model able to simul- modeling framework for discrete event simulation using hierarchical control
structures. J. Simul. Model. Pract. Theory 56. ISSN 1569e190X.
taneously assess production and environmental performance of Golzarpoor, H., Gonza lez, V., 2013. A green-lean simulation model for assessing
construction operations. The DES-I/O simulation model has the environmental and production waste in construction. In: 21st Annual Confer-
potential to propose a decision support tool able to assess the ence of the International Group for Lean Construction, Fortaleza, Brazil.
Gonza lez, V., Echaveguren, T., 2012. Exploring the environmental modeling of road
impact of managerial decisions (such as the lean based improve-
construction operations using discrete-event simulation. Autom. Constr. 24,
ments applied to the model) on production and environmental 100e110.
performance of construction projects. The environmental analyses, Gonza lez, V., Yiu, T.W., Martínez, P., 2012. Towards a dynamic modelling framework
proposed in this study, contribute to the development of more for assessing the sustainable degree of construction materials. In: 37th Annual
Conference of the Australasian Universities Building Educators Association,
sustainable projects that explicitly consider environmental aspects Sydney, Australia.
in the planning phase or even during the construction phase. Guidosh, J.A., 2009. The Use of Life Cycle Assessment through an Objective
1104 H. Golzarpoor et al. / Journal of Cleaner Production 143 (2017) 1094e1104

Framework Constructed by Simulation (MSc Thesis, Industrial and Systems Productivity Press, New York, USA.
Engineering). Youngstown State University, Youngstown, Ohio, USA. Persson, D., Karlsson, J., 2007. Flow Simulation of Food Industry Production: Kiviks
Heilala, J., Vatanen, S., Tonteri, H., Montonen, J., Lind, S., Johansson, B., Stahre, J., Musteri AB (In Swedish) (MSc Thesis, Department of Product and Production
2008. Simulation-based sustainable manufacturing system design. In: Pro- Development). Chalmers University of Technology, Gothenburg, Sweden.
ceedings of the 40th Winter Simulation Conference, Miami, FL, pp. 1922e1930. Reinertsen, D.G., 2009. The Principles of Product Development Flow: Second Gen-
Hopp, W.J., Spearman, M.L., 2011. Factory Physics. Waveland Press, Waveland Press. eration Lean Product Development, vol. 62. Celeritas, Redondo Beach.
Huang, D.B., Scholz, R.W., Gujer, W., Chitwood, D.E., Loukopoulos, P., Reinhard, J., Motsch, S., 2007. Material Flow Management in a Motor Fabrication.
Schertenleib, R., Siegrist, H., 2007. Discrete event simulation for exploring Information Technologies in Environmental Engineering, Springer,
strategies: an urban water management case. Environ. Sci. Technol. 41 (3), pp. 409e415.
915e921. Reuter, M., Schaik, A.V., 2004. Optimization of the Resource Cycle: Linking Research
Ingvarsson, A., Johansson, C., 2006. Flow Simulation of Food Industry Production: and Teaching in Recycling at the Delft University of Technology. International
Ingemar Johansson i Sverige AB (In Swedish) (MSc Thesis, Department of Conference on Engineering Education in Sustainable Development, Barcelona,
Product and Production Development). Chalmers University of Technology, Spain.
Gothenburg, Sweden. Rosenbaum, S., Toledo, M., Gonz alez, V., 2012. Green-lean approach for assessing
ISO14040, 2006. ISO 14040: Environmental Management - Life Cycle Assessment - environmental and production waste in construction. In: Proceedings for the
Principles and Framework. International Organization for Standardisation. 20th Annual Conference of the International Group for Lean Construction, San
Johansson, B., Skoogh, A., Mani, M., Leong, S., 2009. Discrete event simulation to Diego, USA.
generate requirements specification for sustainable manufacturing systems Shahbazpour, M., Seidel, R., 2006. Using sustainability for competitive advantage.
design. In: Proceedings of the 9th Workshop on Performance Metrics for In: 13th CIRP International Conference on Life Cycle Engineering, Flanders,
Intelligent Systems, Gaithersburg, Maryland, pp. 38e42. Belgium.

Johansson, B., Stahre, J., Berlin, J., Ostergren, K., Sundstro €m, B., Tillman, A.M., 2008. Solding, P., Petku, D., 2005. Applying energy aspects on simulation of energy-
Discrete Event Simulation with Lifecycle Assessment Data at a Juice intensive production systems. In: Proceedings of the 37th Winter Simulation
Manufacturing System. FOODSIM. Conference, Orlando, Florida, pp. 1428e1432.
Koskela, L., 1992. Application of the New Production Philosophy to Construction Solding, P., Thollander, P., 2006. Increased energy efficiency in a Swedish iron
(Technical Report No. 72, Center for Integrated Facility Engineering, Depart- foundry through use of discrete event simulation. In: Proceedings of the 38th
ment of Civil Engineering). Stanford University, Stanford, CA. Winter Simulation Conference, Monterey, California, pp. 1971e1976.
Law, A.M., 2007. Simulation Modeling and Analysis. McGraw-Hill, Boston. Sonmez, R., Iranagh, M.A., Uysal, F., 2015. Critical sequence crashing heuristic for
Lind, S., Johansson, B., Stahre, S., Berlin, C., Fath, A., Heilala, J., Helin, K., Kiviranta, S., resource-constrained discrete timeecost trade-off problem. J. Constr. Eng.
Krassi, B., Montonen, J., 2009. SIMTER e a Joint Simulation Tool for Production Manag. 142 (3), 04015090.
Development. VTT Working Paper 125, Espoo, Finland. Sproedt, A., Plehn, J., Scho €nsleben, P., Herrmann, C., 2015. A simulation-based de-
€fgren, B., Tillman, A.-M., 2011. Relating manufacturing system configuration to
Lo cision support for eco-efficiency improvements in production systems. J. Clean.
life-cycle environmental performance: discrete-event simulation supple- Prod. 105, 389e405.
mented with LCA. J. Clean. Prod. 19 (17), 2015e2024. Stiel, F., Michel, T., Teuteberg, F., 2016. Enhancing manufacturing and transportation
Martínez, J.C., 2010. Methodology for conducting discrete-event simulation studies decision support systems with LCA add-ins. J. Clean. Prod. me 110, 85e98.
in construction engineering and management. J. Constr. Eng. Manag. 136 (1), Tan, Y., Shen, L., Yao, H., 2011. Sustainable construction practice and contractors’
3e16. competitiveness: a preliminary study. Habitat Int. 35 (2), 225e230.
Martínez, P., Gonzalez, V., Da Fonseca, E., 2009. Green-lean conceptual integration Uluer, M.U., Unver, H.O., Gok, G., Unver, N.F., Kilic, S.E., 2016. A framework for energy
in project design, planning and construction. Rev. Ing. Constr. 24 (1), 5e32. reduction in manufacturing process chains (E-MPC) and a case study from the
Marzouk, M., Moselhi, O., 2003. Object-oriented simulation model for earthmoving Turkish household appliance industry. J. Clean. Prod. 112 (Part 4), 3342e3360.
operations. J. Constr. Eng. Manag. 129 (2), 173e181. Wilson, J., Arokiam, A., Belaidi, H., Ladbrook, J., 2016. A simple energy usage toolkit
Ministry for the Environment, 2015. Guidance for Voluntary Corporate Greenhouse from manufacturing simulation data. J. Clean. Prod. 122, 266e276.
Gas Reporting: Data and Methods for the 2013 Calendar Year. Ref. ME 1194, Wohlgemuth, V., Page, B., Kreutzer, W., 2006. Combining discrete event simulation
Wellington, New Zealand. and material flow analysis in a component-based approach to industrial envi-
Nahmens, I., 2009. From lean to green construction: a natural extension. In: Pro- ronmental protection. Environ. Model. Softw. 21 (11), 1607e1617.
ceedings of the 2009 Construction Research Congress, Seattle, WA, Womack, J.P., Jones, D.T., 2010. Lean Thinking: Banish Waste and Create Wealth in
pp. 1058e1067. Your Corporation. Simon and Schuster, New York.
Ohno, T., 1988. Toyota Production System: beyond Large-scale Production.

You might also like