You are on page 1of 6

DATE:

JOB HAZARD ANALYSIS (JHA)


JHA No:

EPCM: BPJV CONTRACTOR NAME:SAIF BIN DARWISH


PROJECT: Al TAWEELAH WORK LOCATION: Al Taweelah Refinery site
JOB DESCRIPTION:
Use of mobile Crane or HIAB crane for loading and unloading of HDPE pipes at site/ storage yard and laying inside the excavation

EMERGECY PLAN (include First Response):


Make the area safe , Inform EGA emergency response team (02-5092111) , Follow site emergency protocol

PERMITS
Confined Space Excavation Floor/Wall opening Hot Work HV Access Isolation (LOTO) Lift Study NDT Workbox Working at heights
PLANNED HIGH RISK CONSTRUCTIONACTIVITIES
Confined Space Entry Excavation <1.2m Isolation (LOTO) Road Work Work at Heights
Crane Activities Flammable / Contaminated atmosphere Mobile Plant Movement Tilt Up / Precast Installation NDT
Energised Electrical Work Gas / Chemical Fuel Line Work Pressure testing Vertical Rebar Other:

ADDITIONAL PPE PLANT, TOOLS & EQUIPMENT BARRICADE / SIGNS


Goggles Sun Screen Compactor Hand Tools Excavator Barrier Mesh
Face Shield Welding Jacket Drill Ladder Backhoe Yellow & Black Chain
Hearing Protection Welding Helmet Extension Leads Scaffold Crane Concrete Barriers
Safety Harness Other- Fans Power Source EWP / Scissor Lift Hard Barricade
Respirator Other - Fire Extinguisher Welding Machine Shade Red & White
Other - Other - Other – Telehandler , Other -
Hand Protection Grinder
flatbed trailer
JHA DEVELOPED BY: JHAAPPROVAL:
No Name Signature Position Date No Name Signature Position Date
1 1
2 2
3 3
4 4
5 5
EPCM ESHMANAGERREVIEW:
Name: Signature: Position: Date //
EPCM AREA SUPERINTENDENT REVIEW:(work shall not proceed until the JHA is signed &dated by the EPCMESH and Area Superintendent other designees)

25875-000-GFX-GHX-00040 Page 1 of 6 Rev 000


14 June 2014
Name: Signature: Position: Date://
RISK SCORE CALCULATOR
CONSEQUENCES
1 2 3 4 5
Minor Medium Serious Major Catastrophic
Medical Treatment Multiple Fatalities or
Single Fatality or
`1C1 First Aid Injury Injury or restricted Lost Time Injury Multiple Permanent
Permanent Impairment
work day case Impairment
Low level
Major environmental Catastrophic
environmental Minor effects on Moderate short-term
RISK impact, biological or physical environmental impact,
event, e.g. pollution - environmental event,
impact that is e.g. pollution – impact
CRITERIA e.g.pollution– environment, e.g. e.g. pollution – near
unconfined &requiring that is widespread,
Environment Near source pollution – near source source confined &
long term recovery, unconfined &requiring
confined & confined &short-term medium term recovery
leaving residual long term recovery,
promptly reversible impact. impact.
damage. leaving major residual
reversible impact.
damage.
Minor damage to Major damage; loss of Serious problems with
Easily fixed up Loss of less than one
Operational/Economic equipment; no loss of less than six months future operation of the
straight away weeks production
Impact production production facility
<$10k $100k - $1M
$10k - $100k $1M - $10M >$10M

Occurs several times per


year at similar
Very projects/reasonably
A Moderate High High High High
likely expected to occur under
normal operating
conditions
Has occurred several
LIKELIHOOD

times / likely to occur at


B Likely some time under normal
Moderate Moderate High High High
operating conditions

Has occurred/may occur


C Possible under normal operating Low Moderate Moderate High High
conditions
Known to have occurred
in the construction
D Rare industry/unlikely to occur Low Low Moderate Moderate High
under normal operating
conditions

25875-000-GFX-GHX-00040 Page 2 of 6 Rev 000


14 June 2014
Unheard of/not known to
E Unlikely have occurred
Low Low Low Moderate Moderate

Inherent Control Methods & Monitoring Residual


Step Hazard Risk Risk Action By
What control measures will be used?
Describe the job step by step What are the hazards of each step?
Score How will the effectiveness of the controls be determined? Score
 All traffic shall be kept to designated roads.
 Load should be secured with guard rails and cargo
belts
 Escort should be in place to guide the vehicle
 Vehicle routes planned to avoid danger to pedestrians
and clear of excavations.
 Roads shall be wetted to suppress dust, as required.
 Collision/Impact  Vehicles will be subject to a planned maintenance Supervisor
programme. Operator
Transporting of HDPE pipes to site/storage
 Overturning High  All heavy equipment must be fitted with reverse Moderate Manual
area by flatbed trailers
audible alarm. workers
 Persons struck by trailers  The maximum allowable speed limit is 30km/hr.,
unless otherwise advised.
 Continues supervision and monitoring the equipment
operation.
 Unloading checklist should be followed for all
delivery vehicles

25875-000-GFX-GHX-00040 Page 3 of 6 Rev 000


14 June 2014
 BPJV approved Traffic controller shall be in place to
control the equipment movement
 Telehandler/ JCB backhoe operational area should be
barricaded with level 2 barricades
 Competent and BPJV authorized banks man in place
to guide the telehandler / JCB backhoe at the time
dumping bedding materials inside the excavation
 Collision/Impact  No personal allowed to stand inside the excavation
Supervisor
 Competent supervision in place
Operator
Placing of Pipe bedding materials (Soft sand)  Overturning  Safe distance should be maintain at the time dumping
High Moderate Manual
inside the excavation by Telehandler / JCB, etc. materials by telehandler / JCB backhoe
workers
 Persons struck by material /  Bedding materials shall be loader <70 percentage
telehandler from the telehandler/ JCB backhoe bucket to avoid
falling materials from bucket
 At the time dumping bedding material telehandler
jacks must be placed in level base
 Proper communication in place between operator and
banks man
 The SWL must be indicated on telehandler / JCB
backhoe bucket and never exceeded
 All lifting operations must be under control of an
‘appointed person’ who will be competent to take
overall responsibility and possess a method statement
for the work activities.
 An assessment of the ground conditions must be
carried out by a competent person.
 Crane must have firm level base with load bearing
checks made on ground to support weight of crane and
Collision/Collapse
load, shock loading, wind stress and slewing torques. Lifting
 Lifting zone should be identified and cordoned off to Supervisor
Overturning of Mobile Crane/ Hiab prevent lifting over people. Crane
crane  Crane out riggers must be placed away from the operator
Unloading and Laying of HDPE pipes High
excavation solid barriers Moderate
wrong slinging, Serious injuries, Rigger
Possible fatality  ASLI’s, radius load indicators and motion limit Manual
switches must be fitted and operational by audio- workers
visual methods. The SWL must be indicated on crane
and never exceeded.
 Oversized loads must be tagline to be guided safely.
 A Plan must be produced that considers weight of
load, radius of lift, overhead clearance, ground
conditions, positioning of crane, and lifting equipment
required.
 lifting zones must be barricaded with red and white
chain
25875-000-GFX-GHX-00040 Page 4 of 6 Rev 000
14 June 2014
 Operation of mobile cranes must be carried out by a
competent and BPJV authorized person
 Competent and BPJV authorized rigger only allowed
the perform the slinging and rigging
 Competent and BPJV authorized lifting supervisor in
place
 Load must be correctly slung and secured.
 Loosed materials must be carried in boxes/containers.
 All lifting equipment must be maintained to
manufactures instructions, generally weekly
inspections by operative required. After 12 months a
thorough examination (T.E.) or For lifting accessories
(chains, slings) must have a thorough examination
after 6 months and weekly inspection. Each rope must
identify SWL
 Lifting equipment and lifting gears must inspected
and colour coded as per RBGY

25875-000-GFX-GHX-00040 Page 5 of 6 Rev 000


14 June 2014
NOTE: If the conditions or controls used to conduct the job changes work group members are together use the re-
STARRT process (for one off changes) or amend and re-sign onto the JHA (for permanent changes).
NOTE: Any significant change requires Contractor & EPCM Management authorisation prior to continuing the job.
PRINCIPAL CONTRACTOR: BPJV CONTRACTOR NAME:SBD
PROJECT: Project Shaheen SUPERVISOR NAME:
JOB DESCRIPTION:

JHA SIGN OFF REGISTER


I have read and understood this JHA …
No. First Name Surname Employer Signature Date
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.

16.

17.
18.
19.
20.
21.
22.
23.
24.
25.

25875-000-GFX-GHX-00040 Page 6 of 6Rev 000 14 June 2014

You might also like