ID Task Task Name Duration Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr

on Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 Pembangunan GI 150 KV JATIRANGON - 0151.PJ/DAN.02.02/UIP JBT 122 wks?
II/2017
2 Contract mile stone 122 wks Contract mile stone
3 Contact sign date 0 wks Contact sign date
4 Contract efffective date 0 wks Contract efffective date
5 Project Kick Off Meeting 0 wks Project Kick Off Meeting
6 Issued Perfomance Bond 0 wks Issued Perfomance Bond
7 Issued Advance Payment Bond 0 wks Issued Advance Payment Bond
8 IMB (by PLN) 0 wks IMB (by PLN)
9 60MVA Transformer (by PLN) on site 0 wks 60MVA Transformer (by PLN) on site
10 BAST 1 0 wks BAST 1
11 BAST 2 0 wks BAST 2
12 Contract Duration 89.83 wks?
13 Engineering & Design 18.83 wks
14 PMT Document 3.5 wks
19 Site Survey 2 days Site Survey
20 Soil Test & Topography 5 wks
24 Basic design 8 wks
39 Detailed Design 8 wks
40 Civil 6 wks
58 Electrical & Electromechanical 8 wks
92 Procurement, Manufacturing & Shipment 43.5 wks
93 PO Placement 5.5 wks
94 LLI Material 2.5 wks
106 Non-LLI Material 3 wks
116 Fabrication 40 wks
117 LLI Material 40 wks
129 Non-LLI Material 15 wks
139 FAT 23.5 wks
151 Delivery Material On site 33.5 wks
152 LLI Material 11 wks
163 Non-LLI Material 11 wks
173 Contruction & Installation Work 71 wks?
174 Preliminary Work 3 wks
177 Civil Work 51 wks
178 Preparation Work 2 wks
181 Switchyard Area 49 wks
204 Control Building 20 wks
247 Pos Jaga 6 wks
273 Electrical & Mechanical Work 45 wks?
274 Switchyard Area 45 wks
289 Steel Structure Works 5 wks
292 Lighting Work 2 wks Lighting Work
293 Control Building Area 10 wks?
300 Testing & Comissioning 40 wks
301 Protection Setting Proposed 1 wk Protection Setting Proposed
302 Cable Continuity Check 4 wks Cable Continuity Check
303 Cable Insulation Test 2 wks Cable Insulation Test
304 Mechanical Testing (bolt tighening) 2 wks Mechanical Testing (bolt tighening)
305 Grounding & Earthing System Test 1 wk Grounding & Earthing System Test
306 Individual Test 14 wks
312 Joint Test for Power Transformer 1 wk Joint Test for Power Transformer
313 System Test 5 wks
317 Substation Energize 3 wks Substation Energize

Task External Tasks Manual Task Finish‐only Manual Progress


Split External Milestone Duration‐only Deadline
Project: Project Schedule
Date: 26 Jan '18 Milestone Inactive Task Manual Summary Rollup Critical
Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start‐only Progress

Page 1