Professional Documents
Culture Documents
EPT 09-T-01
Scope
This Engineering Practice Tutorial (EPT) supplements the basic requirements for the design of piping
systems for refineries, petrochemical plants and onshore and offshore production and processing
facilities contained in MP 16-P-01. It covers all piping for onshore and offshore production and
processing facilities.
Version 0
EPT 09-T-01 Facilities Piping July 1998 Draft
Table of Contents
Scope................................................................................................................................................... 1
1. References.................................................................................................................................. 7
2. General ........................................................................................................................................ 9
3. Definitions .................................................................................................................................. 9
© Mobil Oil,1998 2 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
5.1. General...........................................................................................................................30
7. Pipe Supports..........................................................................................................................52
9. Valving .......................................................................................................................................56
9.1. Chokes............................................................................................................................56
© Mobil Oil,1998 3 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 4 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
Table of Figures
Figure 1: Example Flowsheet of a Simplified Production System .................................. 24
Figure 7: Sectional View of a Manifold Valve (Courtesy of National Supply Co.) .......51
© Mobil Oil,1998 5 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
Table of Tables
Table 1: Thread Allowance for Pipe Wall Thickness Calculations, ASME B31.3......... 13
Table 5: Design Factors for Steel Pipe Construction (Courtesy of ASME ) ...................19
Table 6: Summary ASME Pressure Ratings Material Group 1.1 (Source: ASME
B16.5)............................................................................................................................. 22
© Mobil Oil,1998 6 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
1. References
The following publications form a part of this Practice. Unless otherwise specified herein , use the
latest edition.
API RP 14C Recommended Practice for Analysis, Design, Installation, and Testing of
Basic Surface Safety Systems for Offshore Production Platforms Fifth
Edition; Errata - 1994
API RP 14E Recommended Practice for Design and Installation of Offshore Production
© Mobil Oil,1998 7 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
ASTM A106 Standard Specification for Seamless Carbon Steel Pipe for High-
Temperature Service
MSS SP-58 Pipe Hangers and Supports - Materials, Design and Manufacture
MSS SP-69 Pipe Hangers and Supports - Selection and Application
© Mobil Oil,1998 8 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
2. General
The design of piping systems for refineries, petrochemical plants, and onshore and offshore
production and processing facilities contained in MP 16-P-01 shall be in accordance with
requirements of this Tutorial, unless superceded by more stringent local regulations.
3. Definitions
Cold Spring Cold spring is the intentional deformation of piping during assembly to
produce a desired initial dis placement or stress.
Facility A site containing one or more pieces of equipment and interconnecting
piping required to convey, separate, treat, process, pump or compress a
fluid.
Fluid Term used for a gas, liquid, vapor or mixture thereof.
Fluid Service A piping code term that establishes the basis for design of a piping system
and considers the combination of fluid properties, operating conditions and
other factors. ASME B31.3 has fluid service classifications as listed below.
Fluid Service, A fluid service in which all of the following apply:
Category D 1. The fluid handled is nonflammable , nontoxic and not damaging to
human tissues.
2. The design pressure does not exceed 1035 kPa (150 psi).
3. The design temperature is -29–186°C (-20–366°F).
Fluid Service, A fluid service in which the potential for personnelexposure is judged to be
Category M significant and in which a single exposure to a very small quantity of a
toxic fluid, caused by leakage, can produce serious irreversible harm to
persons on breathing or bodily contact, even when prompt restorative
measures are taken.
Fluid Service, A fluid service for which the owner specifies the use of Chapter IX of
High Pressure ASME B31.3 for piping design and construction.
Fluid Service, A fluid service pertaining to most piping covered by ASME B31.3, i.e. not
Normal subject to the rules of Category D, Category M or High Pressure Fluid
© Mobil Oil,1998 9 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 10 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
4. Piping Design
• ASME B31.3 does not require a margin between maximum operating and design
conditions. However, it does not permit continuous operation of a piping system at
conditions exceeding design conditions . Therefore, the design conditions (pressure,
temperature, location of spec. breaks, etc.) shall be carefully determined, considering
cost/risk factors. Short-term (upset) operation above the design conditions is
acceptable within the limitations of ASME B31.3.
• The design of piping shall provide for the most severe coincident (occurring at the
same time) condition of temperature, pressure and loading. The most severe condition
is that which results in the greatest required component thickness and highest-pressure
rating. When two or more conditions exist, they shall be separately evaluated using
design pressure, design temperature and loadings applicable to each case.
• In determining the operating pressure and temperature of a piping system, variations
may be expected because of operating fluctuations , other than upsets. When
establishing maximum operating conditions, these fluctuations shall be considered as
well as liquid static head, fluid friction losses under clean and fouled conditions, pump
and compressor characteristics and pressure pulsations.
• For design pressures of 3450 kPa (500 psi) or less, the design pressure is generally set
at 10 percent or 210 kPa (30 psi) above the maximum anticipated operating pressure,
whichever is greater.
• For design pressures greater than 3450 kPa (500 psi), setting the design pressure 10
percent higher than the operating pressure may result in unjustifiable costs,
particularly if higher flange ratings are required. For such piping systems, each
system shall be evaluated in order to establish a reasonable design pressure rather than
setting a fixed percentage over the maximum operating pressure. The design of a
centrifugalpump discharge line shall be at least equal to the pump shutoff pressure.
• The design temperature shall be the highest or lowest temperature to which the piping
system is subjected plus a margin to cover uncertainties in temperature predictio n.
The following are examples of conditions that may determine the piping system
design temperature:
− In hot service (above ambient temperature), use the maximum expected operating
temperature plus a minimum of 25°C (45°F) as a safety factor.
− For cold service (below ambient temperature), use the minimum expected
operating temperature minus a minimum of 5°C (10°F) as a safety factor.
− The maximum temperature that can occur when bypassing a heat exchanger or
cooler for cleaning.
© Mobil Oil,1998 11 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 12 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
Pi d o 100
t = t c + t th +
2(S t E L + Pi Y ) 100 - Tol
Where:
Table 1: Thread Allowance for Pipe Wall Thickness Calculations, ASME B31.3
© Mobil Oil,1998 13 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
For ease in picking a pipe wall thickness, tables such as Table 2.5 in API RP
14E are published, giving the maximum allowable working pressure for
standard pipe diameters and wall thickness.
© Mobil Oil,1998 14 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 15 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 16 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 17 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 18 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
1 2 3 4
Div. 1 Div. 2
Pipelines, mains and service lines 0.80 0.72 0.60 0.50 0.40
Crossings of roads, railroads without casing:
a. Private roads 0.80 0.72 0.60 0.50 0.40
b. Unimproved public roads 0.60 0.60 0.60 0.50 0.40
c. Roads, highways or public streets with hard 0.60 0.60 0.50 0.50 0.40
surface and railroads
Crossings of roads , railroads with casing :
a. Private roads 0.80 0.72 0.60 0.50 0.40
b. Unimproved public roads 0.72 0.72 0.60 0.50 0.40
c. Roads, highways or public streets with hard 0.72 0.72 0.60 0.50 0.40
surface and railroads
Parallel encroachment of pipelines and mains on roads and railroads :
a. Private roads 0.80 0.72 0.60 0.50 0.40
b. Unimproved public roads 0.80 0.72 0.60 0.50 0.40
© Mobil Oil,1998 19 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
1 2 3 4
Div. 1 Div. 2
c. Roads, highways or public streets with hard 0.60 0.60 0.60 0.50 0.40
surface and railroads
Fabricated assemblies 0.60 0.60 0.60 0.50 0.40
Pipelines on bridges 0.60 0.60 0.60 0.50 0.40
Compressor station piping 0.50 0.50 0.50 0.50 0.40
Near concentration of people in Location Class 1 0.50 0.50 0.50 0.50 0.40
and 2
ASME B31.4 does not have a temperature derating factor ("T") since it states
that it is only applicable to temperatures -29–121°C (-20–250°F).
© Mobil Oil,1998 20 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
B31.3 and a pipeline designed to ASME B31.8 or ASME B31.4. The location of the
transition varies from company to company , but it is usually at the plant fence for an
onshore facility and at the first flange above the water on an offshore platform (see EPT
09-T-05).
© Mobil Oil,1998 21 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
Table 6: Summary ASME Pressure Ratings Material Group 1.1 (Source: ASME
B16.5)
The pressure rating of a piping system is set either by the wall thickness of
the pipe or by the pressure rating of the valves and fittings . Note that in
ASME B31.3 the allowable stress for most commonly used steels in
production facility piping systems is constant through 204.4°C (400°F) and
in ASME B31.8 the temperature derating factor is 1.0 through 121.1°C
(250°F). Thus the pressure rating of a piping system may be set by the wall
thickness of the pipe at low temperatures and by the pressure rating of the
valves and fittings at a higher temperature.
Although ASME Class 400 exists, it shall not be used in production facility
design. Valves and fittings in this class are not readily available and so may
cost more than those in Class 600.
© Mobil Oil,1998 22 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 23 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
4.7.1. Rules
This Section describes a procedure for determining the design pressure for a
specific segment of a piping system.
Consider the case of a well with a shut-in tubing pressure of 69,000 kPa
(10,000 psi) flowing through a choke to a series of successive separators to a
tank as shown in Figure 1. The wellhead shall be designed to withstand
69,000 kPa (10,000 psi) internal pressure, but the tank is incapable of
withstanding pressures much in excess of one atmosphere. Clearly, there
shall be one or more locations in such a system where the design pressure
(that is, the maximum pressure to which the piping can be subjected) is
higher on the upstream side than it is on the downstream side. These
locations , called "pressure breaks" or "spec breaks," occur at valves, control
valves, chokes or other devices which can be shut to isolate one segment of
the piping system from another.
© Mobil Oil,1998 24 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
4.7.1.2. Overpressure
In reality , the pressure in the piping system may exceed relief valve set
pressure for a short period of time while the relief valve is handling its full
design load.
• The ASME Boiler and Pressure Vessel Code allows pressure to build up
to 110–125 percent of set pressure under certain conditions of relief.
© Mobil Oil,1998 25 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
4.7.2. Procedure
To determine the location of pressure breaks, a complete mechanical flow
diagram (sometimes called a process and instrument diagram, or P&ID) is
needed. This diagram shall show schematically the process and the location
of all equipment, valves, controls and instrumentation.
© Mobil Oil,1998 26 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 27 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 28 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 29 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
These examples are shown to help to explain how to apply the rules of
Section 4.7 of this MEP and not to make any point regarding the proper way
to design a specific situation. The important point is that in complex piping
systems, care shall be taken to follow the procedure and rules properly and to
choose the pressure break locations carefully. Often such an analysis leads to
a re-evaluation of the proper location of valves in a piping system.
5.1. General
• Piping shall be run overhead throughout a unit except in freezing climates, where
water, drainage and pumpout lines shall be underground (below the frost line) to the
maximum extent possible . Proper corrosion protection shall be applied to
underground piping.
• Equipment subject to damage by heat, such as motor-operated valves, shall not be
located where heat can exceed the design temperature of the equipment. Avoid
routing lines containing cold high-vapor-pressure fluids near uninsulated hot lines or
equipment, especially suction lines to pumps handling such fluids.
• Avoid routing lines with flanged joints, threaded connections , high radiant heat or
high-pressures near instrument/electrical cable trays.
• Expansion bends shall be located in a horizontal plane and clear of any accessway.
Underground expansion bends require expansion pits. Where expansion pits are
provided, suitable anchors shall be furnished to ensure that the pipe expansion is
contained within the pit dimensions.
• Tank piping shall be designed with adequate loops and offsets to accommodate
expected tank settlement. If this is not possible where large tank settlements are
anticipated, ball joints with fire resistant packing or metal bellows expansion joints
may be considered.
© Mobil Oil,1998 30 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
6.1. Compressors
• Special precaution is necessary in the design of the piping at or near compressors to
reduce fatigue failures. The piping shall have the minimum of overhanging weight.
Braces shall be provided as needed to reduce vibration. Full penetration buttwelds
shall be used wherever feasible , including fittings such as branch connections , etc.
• To avoid damage to centrifugal compressors, a time delay shall be incorporated into
the circuit of centrifugal compressors when needed to ensure that valve closing is not
complete until the compressor has slowed suffic iently to prevent compressor damage
should surge occur during the coastdown period.
© Mobil Oil,1998 31 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 32 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 33 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• Interconnecting oil piping between the compressor, turbine and lube oil
console shall comply with the piping specifications for the console (see
MP 15-P-04). No elastometric or metal hose shall be used for lube or
seal oil piping.
• Low points in the discharge line from an oil-lubricated air compressor
shall be avoided to eliminate the possibility of lube oil being trapped and
subsequently ignited. If low points are unavoidable , they shall be
provided with drains . The recommendations for auxiliary piping
contained in Section 6.2.3 of this MEP are also applicable to centrifugal
compressors.
© Mobil Oil,1998 34 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
expansion joint is frequently needed on the short suction line from the basin. For such
pumps , an expansion joint is generally not needed on the discharge side of the pump if
the piping contains at least one 90 degree elbow before going underground.
© Mobil Oil,1998 35 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 36 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
serious heat buildup may occur at the pump during blocked discharge, or
where the pressure breakdown will liberate gas, the relief valve discharge
line shall be installed to relieve to an unblocked suction source, such as a
tank or an accumulator. The relief valve may only be eliminated if the
pump and the equipment downstream of the pump are designed to
withstand the shutoff or stalling pressure.
• Steam driver piping, including drains , shall be designed to avoid pockets and to
minimize condensation. Inlet piping to turbines and other steam drivers shall branch
from the top of the supply header and contain a block valve in a horizontal run near
and above the header.
• Connections to exhaust headers shall be made to the top of the header unless the line
from the driver is at least one size smaller than the header. If it is smaller, it is
permissible to make a centerline connection to the side of the header, provided that
such routing does not obstruct space in a pipe rack available for future lines.
• Provisions are generally made for bleed warming steam into turbines and other steam
drivers.
• Piping connections for pressure indicators shall be provided in supply and exhaust
piping of turbines driving centrifugal compressors.
© Mobil Oil,1998 37 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 38 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
6.4.1. Arrangement
• Piping at vessel nozzles shall be arranged so that blanks can be readily
installed and valves easily removed for maintenance. Blanks shall be in
accordance with Section 7 of MP 16-P-01.
• For economy and ease of support, piping at towers shall be run parallel to
and as close as feasible to the tower.
• The piping designer shall coordinate piping requirements with the
designers of the instruments, structures and vessels to achieve the
optimum nozzle location so that valves, instruments and blanks are
accessible from grade or platforms and do not obstruct passageways.
• Process requirements usually govern the location of the valves in vessel
piping. However, block valves shall generally be provided at vessel
nozzles for all piping connections , except as follows:
− Connections for vapor and reboiler lines, unless the reboilers are in
parallel and need to be cleaned onstream
− Connections for sidestream drawoff lines (except water drawoffs)
− Furnace transfer lines to vacuum vessels
− Connections to lines containing block valves located within 9 m (30
ft) in a horizontal direction from the vessel nozzle
• Valves, flanged joints and threaded joints shall not be located inside
vessel skirts.
• Piping connections shall not be made to manway covers, other than on
coke drums. (The bottom manway cover [or bottom head] on coke
drums is the preferred location for the main charge, quench and drain
nozzles.)
© Mobil Oil,1998 39 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 40 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
block valve is not required in the second vessel outlet unless the liquid in
the bottom of that vessel exceeds 75 M3 (2000 U.S. gallons).
© Mobil Oil,1998 41 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 42 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 43 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 44 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 45 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• Utility stations (including hose requirements) for service water, steam, air and
nitrogen shall be in accordance with EPT 04-T-10. Each steam and nitrogen hose
outlet shall be provided with a steel gate valve. Air and water outlets shall have
bronze or aluminum-bronze ball valves.
• Steam piping systems shall meet the requirements of EPT 04-T-06. Condensate
collection systems shall meet the requirements of EPT 04-T-06.
• Utility stations shall remain in service at all times, except when isolated for repairs.
Steam shall be supplied by a source that will not be closed off during shutdowns.
• The steam supply for smothering, snuffing, space heating and protective heating shall
be connected to a source that will not be shut off during shutdowns or when the steam
to a piece of equipment is shut off.
• Whenever steam is exhausted to the atmosphere, the line shall be fitted with an
exhaust head with a drain to a sewer. The exhaust system shall be reviewed to ensure
that sound levels and flow induced vibration levels are within acceptable limits.
• The ends of steam mains and all low points in steam lines (except steam tracer lines)
shall be provided with drip legs. The maximum distance between drip legs shall be 90
m (300 ft).
• Steam traps shall be provided for the removal of condensate from collection points.
Each trap shall serve only one collection point. Whenever possible , the steam trap
shall be installed below and close to the equipment or piping.
• Hot oil and steam tracing systems shall conform to MP 00-P-04. Cooling water
systems shall conform to the requirements of EPT 04-T-09.
• All water piping shall be located or protected to prevent freezing. In cold climates,
headers and branches that are outdoors and in intermittent service (but not below the
frost line) shall be traced and/or insulated. Tracing and insulating water lines with
low continuous flowrates shall also be considered.
• Low point drains shall be provided so that any water line located above the frost line
can be drained when it is shut down. A vent shall be provided for each high point
between block valves on large water mains. These vents shall be protected from
mechanical damage and from freezing, as required.
• Provisions shall be made to ensure that water is available for sanitary facilities, safety
showers and eyewash fountains during unit shutdowns.
• Fuel gas systems shall conform to the requirements of EPT 04-T-13. Instrument air
and plant air systems shall conform to EPT 04-T-18.
• Plant air piping shall either slope downward toward dry drums and moisture traps or
shall be horizontal. Branch connections on all air headers shall be into the top of the
pipe. Block valves shall be provided in all branch lines from air headers.
© Mobil Oil,1998 46 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 47 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 48 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
6.11.1. Velocities
Typically , the velocities in manifold piping are high and therefore erosional
flow can be a problem. For this reason target tees are usually installed, and
headers may be looped to reduce velocities. Each inlet source shall have a
check valve installed and the manifold shall be pressure rated for the shut-in
pressure of the source. Also, the inlet sources shall be spaced far enough
apart to allow the valves to be actuated without interference. For 51–102
mm (2–4 in) lines the spacing shall be 38–51 mm (11 /2 –2 in) center to center.
To minimize the length of the manifold , it is possible to arrange headers in a
vertical plane and enter from both sides on a staggered pattern.
© Mobil Oil,1998 49 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
the nominal diameter of the input lines is chosen because the operating
company's piping specifications will not allow weld-o-lets to be installed
where the inlet is more than half the diameter of the header. If there are any
plans for future expansion, weld-o-lets, flanges and blind flanges can be pre-
installed on the header.
Specially designed valves and connections may minimize the space required
and reduce costs. Figure 7 shows one such valve arrangement.
• Flow enters the inlet that contains a block valve and a check valve and is
directed either up to a test header or down to one or more group headers.
• A divert valve with an actuator can be used as shown in the figure for
automatic well test (AWT).
• Such valve arrangements have the drawback of having non-standard
dimensions , requiring the use of a single supplier for parts.
© Mobil Oil,1998 50 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
© Mobil Oil,1998 51 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• Where there is a control valve, block valves are often provided so the control valve
can be maintained without having to drain or bleed the pressure from the vessel and
downstream piping. Typically , a safety-systems analysis also would call for a check
valve at this point to prevent backflow. Drain or vent valves shall be installed to drain
liquid or bleed pressure out of the system so that the control valve can be maintained.
• Bypass valves are sometimes installed to allow the control valve to be repaired
without shutting in production. On large, important streams the bypass could be
another control valve station. Manual bypass valves are more common in smaller
facilities. The bypass valve could be a globe valve if it is anticipated that flow will be
throttled through the valve manually during the bypass operation, or it could be an
on/off valve such as a ball, plug or gate valve, if the flow is to be cycled. Because
globe valves do not provide positive shutoff, sometimes there is a ball or other on/off
valve piped in series with the globe bypass valve.
• The piping system for any facility, other than the straight pipe connecting the
equipment, is made up primarily of a series of control stations . Flow from one vessel
goes through a control station and into a piece of pipe that goes to another vessel. In
addition to considering the use of block valves, check valves, etc., all control stations
shall be designed so that the control valve can be removed.
• Any bypass valve shall be located above or on a level with the main control valve. If
the bypass is below the control valve, it provides a dead space for water accumulation
and corrosion.
7. Pipe Supports
• The layout and design of piping and its supporting elements shall meet the objectives of ASME
B31.3, Paragraph 321. Suggested pipe support spacing tables are listed in MP 16-P-01, Appendix
C. If the contractors' tables are used, they shall be reviewed and approved by Mobil.
• When it is anticipated that a line will deflect vertically as a result of thermal expansion or
contraction (which could thereby unload some supports and overload others), spring supports
shall be provided.
• Supports shall be designed so they will not be disengaged by movement of the supporting pipe or
structure. Unless approved otherwise by Mobil, all supports shall be designed to withstand the
added load resulting from testing, erection and shipping, if applicable . This is particularly
important for piping on offshore platforms that shall be shipped by water.
• Spacing of overhead pipe supports shall be based on the piping size mix to secure maximum
economy. Where support spacing exceeds allowable spans for small lines (NPS 2 and smaller),
the lines shall be grouped (when feasible ) to simplify supporting methods. To eliminate an
intermediate support for a small line, it may be economical to increase line sizes.
• Supports for piping near equipment shall be designed so that excessive forces and moments
caused by temperature changes shall not be transmitted to the equipment. Piping entering vessels
shall be supported from brackets attached to the vessel if vertic a l expansion of either the vessel or
the pipe will cause excessive loads on the vessel nozzle.
© Mobil Oil,1998 52 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• Piping sections requiring frequent dismantling for maintenance, such as for installation of blanks,
shall be provided with permanent supports for the dismantled condition to maintain proper
alignment.
• Process and auxiliary piping shall be arranged and supported so that a minimum number of joints
shall have to be disconnected (when removing equipment or components) and so that temporary
supports shall not be required. Areas of particular concern are:
− Auxiliary piping at pumps (arranged to facilitate removal of rotating elements)
− Burner piping
− Piping at control valves
− Exchanger channels
• MSS SP-58 support types 1, 2, 5, 6, 7, 9, 10, 11, 12, 15, 16, 19, 20, 23, 28, 29, 30, 41, 43 and 49
shall not be used. Guidance for selection and application of pipe hangers and supports can be
found in MSS SP-69.
• Pipe supports elements (for example , clamps, turnbuckles, U-bolts, saddles, etc.) are provided in
carbon steel, ductile iron or malleable iron. The following limitations apply to these materials:
© Mobil Oil,1998 53 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• Piping requiring mechanical cleaning for removal of solids buildup shall employ flanged fittings
(such as tees and crosses) at changes in direction in lieu of pipe bends and buttwelding elbows. If
pipe bends are used, they shall be of a radius suitable for the cleaning tool. The run of pipe
between cleanout points shall be a maximum of 12 m (40 ft) if cleaned from one end, and 24 m
(80 ft) if cleaned from both ends. Flanged removable spools shall be provided at cleanout points
on long straight runs.
• Permanent blanks shall be in accordance with MP 16-P-01, Section 7.
• Thin plate blanks (maintenance isolation blanks) shall be used only for lines that are not under
pressure and which shall be sealed off to permit inspection or welding during shutdowns.
© Mobil Oil,1998 54 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
Flange protectors shall not be used in H 2 S service. They may trap small leaks of sour gas
and keep them from being dispersed in the atmosphere. Also, many companies do not use
flange protectors on lines containing flammable liquids . Liquids from a leaking flange
can accumulate under the protective cover, producing a fire hazard.
© Mobil Oil,1998 55 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
9. Valving
• Valve stems and handles shall not project into passageways or be installed with the stem inclined
below the horizontal. See MP 16-P-01 for clearance and accessibility requirements.
• Valves that are open to the atmosphere shall have their outboard connection either blinded or
plugged.
• Drain and bypass connections may be positioned in a valve body, where necessary, to simplify
piping or to ensure complete drainage. The connection type (flanged, threaded, etc.) shall be
consistent with those allowed by the governing piping line classification.
9.1. Chokes
Fluid flows from a choke in a high-velocity jet. For this reason, it is desirable to have a
straight run of pipe of at least 10–15 pipe diameters downstream of any choke, so that the
jet does not impinge on the side of the pipe.
Often, on high-pressure wells, two chokes are installed in the flow line: one a positive
choke and the other an adjustable choke. The adjustable choke is used to control the flow
rate. If it were to erode (cut out), the positive choke then would act to restrict the flow out
of the well and keep the well from damaging itself. Where there are two chokes, it is good
piping practice to separate the chokes by 10 pipe diameters to keep the jet of flow formed
by the first choke from cutting out the second choke. In practice, this separation is not
often done because of the expense of separating two chokes by a spool of pipe rated for
well shut-in pressure. It is much less expensive to bolt the flanges of the two chokes
together. No data have been collected to prove whether the separation of chokes is
justified from maintenance and safety considerations.
Whenever a choke is installed, it is good piping practice to install block valves within a
reasonable distance upstream and downstream so that the choke bean or disc can be
changed without having to bleed down a long length of pipeline. A vent valve for
bleeding pressure off the segment of the line containing the choke is also needed. This is
particularly true in instances where a positive choke is installed at the wellhead and an
adjustable choke is installed hundreds of feet away in a line heater. If block valves are not
installed downstream of the positive choke and upstream of the adjustable choke, it would
be necessary to bleed the entire flow line to atmosphere to perform maintenance on either
choke .
© Mobil Oil,1998 56 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
12. Models
• When a plastic modelis used for a project, it shall be built to a minimum scale of 3/8 in:1 ft or
1:33 metric. Before the model is built , a detailed model specification shall be prepared by the
contractor for Mobil approval.
© Mobil Oil,1998 57 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
• When a 3D computer model is used for a project, the software to be used requires Mobil
approval. The system shall include clash/interference checking and walk-through capabilities.
• As a minimum, the following items shall be shown on the model:
− Piping NPS 2 and larger, with flanges and insulation as required. Piping shall be labeled with
the line number and specification.
− All valves, including handwheels or operators.
− Critical pipe supports, guides, restraints and anchors.
− Instrument support stanchions and all instruments, including transmitters labeled for ready
identification.
− Drain hubs, catch basins, manholes and cleanouts.
− Ladders, platforms and stairs.
− Lighting equipment and electrical boxes.
− Fixed hose reels.
− Fixed fire water spray systems.
© Mobil Oil,1998 58 of 59
EPT 09-T-01 Facilities Piping July 1998 Draft
provided for protection against hydrocarbon spillage. If the temperature exceeds 480°C (900°F),
insulation is usually provided to protect against contact with combustible gas.
13.3. H2S
In the presence of H2 S, flanges shall not be insulated. This is to prevent the H 2 S from
concentrating around the bolts and causing stress corrosion cracking of the bolt materials.
© Mobil Oil,1998 59 of 59