In order to write new parameters on DUS, the existing cells need to be locked.
I) Adding 1 new carrier with 3 Radios. No modification on existing carrier (only lock/unlock).
The hardware for new carrier can be pre-install. New Radios can be plugin and turn on before
integration. Digital Unit has the ports enable only for existing Radios.
IF THE HARDARE UNITS WILL BE INSTALLED AND POWERED , NO TECHNICIAN WILL BE REQUIRED ON SITE.
a) If the Radios will be cascade, repeat steps from I) Adding 1 new carrier with 3 Radios. (the process
will be similar but the line commands(integrator) will create 3 extra Radios)
b) If the Radios will be stand alone ( they should be connected all in the Digital unit) XMU needed in
this case in order to support more then 6 Radios.
IF THE HARDARE UNITS WILL BE INSTALLED AND POWERED , NO TECHNICIAN WILL BE REQUIRED ON SITE.
The hardware for new carrier can be pre-install. New Radios can be plugin and turn on before
integration. Digital Unit and the XMU have the ports enable only for existing Radios.
IF THE HARDARE UNITS WILL BE INSTALLED AND POWERED , NO TECHNICIAN WILL BE REQUIRED ON SITE.
a)Existing configuration : 1X Existing carrier with 6 Radios(or Two existing carriers totaling 6
Rarios)
I) Adding 1 new carrier with 3 or 6 Radios. Modification on existing carrier (Radios port
reconfiguration).XMU needed if is not present/defined on site.
1) New XMU required (Existing Digital unit can be use(Need to check existing sites with 3 carrier for a
single DUS capacity)
Radios can be installed and connected to new XMU . The link between XMU and DUS can NOT be
installed before integration.
TECHNICIAN WILL BE REQUIRED ON SITE IN ORDER TO ADJUST THE NEW CPRI PORTS CONFIGURATION.(DUS
AND XMU PORTS)
Radios can be installed and connected to new XMU . The link between XMU and DUS can NOT be
installed before integration. New DUS will be mirrored(cascaded) with existing one(I'm not yet familiar
with this process) We will required a TEST site in order to not lose too much time on the first one and in
the worst case, to roll-back the integration.
TECHNICIAN WILL BE REQUIRED ON SITE IN ORDER TO ADJUST THE NEW CPRI PORTS CONFIGURATION.(DUS
AND XMU PORTS) AND BETWEEN THE DIGITAL UNITS.
a) On sites where the actual configuration will support increase of capacity (We need to check if
the Digital Unit and/or license will let us to define other 3 cell/increase the output power.
1) Define 3 new cells( Radios can be cascaded or stand alone for each cell)
I)Cascated Radios will