You are on page 1of 39

OBLICON 1-9-2018 I ACJUCO 1

COMMON gallons of molasses, and we stated we believe that this is possible


and will do our best to let you have these extra 100,000 gallons
BREACH OF OBLIGATION during the next year the same to be taken by you before
November 1st, 1923, along with the 300,000, making 400,000
CONCEPT gallons in all.

G.R. No. 23769 September 16, 1925 Regarding the payment for our molasses, Mr. Song Fo gave us to
understand that you would pay us at the end of each month for
SONG FO & COMPANY, plaintiff-appellee, molasses delivered to you.
vs.
HAWAIIAN PHILIPPINE CO., defendant-appellant. Hoping that this is satisfactory and awaiting your answer
regarding this matter, we remain.
Hilado and Hilado, Ross, Lawrence and Selph and Antonio T.
Carrascoso, Jr., for appellant. Yours very truly,
Arroyo, Gurrea and Muller for appellee.
HAWAIIAN-PHILIPPINE COMPANY
MALCOLM, J.: BY R. C. PITCAIRN
Administrator.
In the court of First Instance of Iloilo, Song Fo & Company,
plaintiff, presented a complaint with two causes of action for Exhibit G is the answer of the manager of Song Fo & Company to
breach of contract against the Hawaiian-Philippine Co., the Hawaiian-Philippine Co. on December 16, 1922. This letter
defendant, in which judgment was asked for P70,369.50, with reads:
legal interest, and costs. In an amended answer and cross-
complaint, the defendant set up the special defense that since the December 16th, 1922.
plaintiff had defaulted in the payment for the molasses delivered
to it by the defendant under the contract between the parties, the Messrs. HAWAIIAN-PHILIPPINE CO.,
latter was compelled to cancel and rescind the said contract. The Silay, Neg. Occ., P.I.
case was submitted for decision on a stipulation of facts and the
exhibits therein mentioned. The judgment of the trial court DEAR SIRS: We are in receipt of your favours dated the 9th and
condemned the defendant to pay to the plaintiff a total of the 13th inst. and understood all their contents.
P35,317.93, with legal interest from the date of the presentation
of the complaint, and with costs. In connection to yours of the 13th inst. we regret to hear that you
mentioned Mr. Song Fo the one who visited your Central, but it
From the judgment of the Court of First Instance the defendant was not for he was Mr. Song Heng, the representative and the
only has appealed. In this court it has made the following manager of Messrs. Song Fo & Co.
assignment of errors: "I. The lower court erred in finding that
appellant had agreed to sell to the appellee 400,000, and not only With reference to the contents of your letter dated the 13th inst.
300,000, gallons of molasses. II. The lower court erred in finding we confirm all the arrangements you have stated and in order to
that the appellant rescinded without sufficient cause the contract make the contract clear, we hereby quote below our old contract
for the sale of molasses executed by it and the appellee. III. The as amended, as per our new arrangements.
lower court erred in rendering judgment in favor of the appellee
and not in favor of the appellant in accordance with the prayer of (a) Price, at 2 cents per gallon delivered at the central.
its answer and cross-complaint. IV. The lower court erred in
denying appellant's motion for a new trial." The specified errors (b) All handling charges and expenses at the central and at
raise three questions which we will consider in the order the dock at Mambaguid for our account.
suggested by the appellant.
(c) For services of one locomotive and flat cars necessary
1. Did the defendant agree to sell to the plaintiff 400,000 for our six tanks at the rate of P48 for the round trip dock to central
gallons of molasses or 300,000 gallons of molasses? The trial and central to dock. This service to be restricted to one trip for the
court found the former amount to be correct. The appellant six tanks.
contends that the smaller amount was the basis of the agreement.
Yours very truly,
The contract of the parties is in writing. It is found principally in the
documents, Exhibits F and G. The First mentioned exhibit is a SONG FO & COMPANY
letter addressed by the administrator of the Hawaiian-Philippine By __________________________
Co. to Song Fo & Company on December 13, 1922. It reads: Manager.

SILAY, OCC. NEGROS, P.I. We agree with appellant that the above quoted correspondence
December 13, 1922 is susceptible of but one interpretation. The Hawaiian-Philippine
Co. agreed to deliver to Song Fo & Company 300,000 gallons of
Messrs. SONG FO AND CO. molasses. The Hawaiian-Philippine Co. also believed it possible
Iloilo, Iloilo. to accommodate Song Fo & Company by supplying the latter
company with an extra 100,000 gallons. But the language used
DEAR SIRS: Confirming our conversation we had today with your with reference to the additional 100,000 gallons was not a definite
Mr. Song Fo, who visited this Central, we wish to state as follows: promise. Still less did it constitute an obligation.

He agreed to the delivery of 300,000 gallons of molasses at the If Exhibit T relied upon by the trial court shows anything, it is
same price as last year under the same condition, and the same simply that the defendant did not consider itself obliged to deliver
to start after the completion of our grinding season. He requested to the plaintiff molasses in any amount. On the other hand, Exhibit
if possible to let you have molasses during January, February and A, a letter written by the manager of Song Fo & Company on
March or in other words, while we are grinding, and we agreed October 17, 1922, expressly mentions an understanding between
with him that we would to the best of our ability, altho we are the parties of a contract for P300,000 gallons of molasses.
somewhat handicapped. But we believe we can let you have
25,000 gallons during each of the milling months, altho it interfere We sustain appellant's point of view on the first question and rule
with the shipping of our own and planters sugars to Iloilo. Mr. that the contract between the parties provided for the delivery by
Song Fo also asked if we could supply him with another 100,000
OBLICON 1-9-2018 I ACJUCO 2

the Hawaiian-Philippine Co. to song Fo & Company of 300,000 were received by it on January 5, 1923, not later than January 31
gallons of molasses. of that year. Instead, payment was not made until February 20,
1923. All the rest of the molasses was paid for either on time or
2. Had the Hawaiian-Philippine Co. the right to rescind the ahead of time.
contract of sale made with Song Fo & Company? The trial judge
answers No, the appellant Yes. The terms of payment fixed by the parties are controlling. The time
of payment stipulated for in the contract should be treated as of
Turning to Exhibit F, we note this sentence: "Regarding the the essence of the contract. Theoretically, agreeable to certain
payment for our molasses, Mr. Song Fo (Mr. Song Heng) gave us conditions which could easily be imagined, the Hawaiian-
to understand that you would pay us at the end of each month for Philippine Co. would have had the right to rescind the contract
molasses delivered to you." In Exhibit G, we find Song Fo & because of the breach of Song Fo & Company. But actually, there
Company stating that they understand the contents of Exhibit F, is here present no outstanding fact which would legally sanction
and that they confirm all the arrangements you have stated, and the rescission of the contract by the Hawaiian-Philippine Co.
in order to make the contract clear, we hereby quote below our
old contract as amended, as per our new arrangements. (a) Price, The general rule is that rescission will not be permitted for a slight
at 2 cents per gallon delivered at the central." In connection with or casual breach of the contract, but only for such breaches as
the portion of the contract having reference to the payment for the are so substantial and fundamental as to defeat the object of the
molasses, the parties have agree on a table showing the date of parties in making the agreement. A delay in payment for a small
delivery of the molasses, the amount and date thereof, the date quantity of molasses for some twenty days is not such a violation
of receipt of account by plaintiff, and date of payment. The table of an essential condition of the contract was warrants rescission
mentioned is as follows: for non-performance. Not only this, but the Hawaiian-Philippine
Co. waived this condition when it arose by accepting payment of
the overdue accounts and continuing with the contract.
Date of
Thereafter, Song Fo & Company was not in default in payment so
Date of Account and date receipt of Date of
that the Hawaiian-Philippine co. had in reality no excuse for
delivery thereof account payment
writing its letter of April 2, 1923, cancelling the contract. (Warner,
by plaintiff
Barnes & Co. vs. Inza [1922], 43 Phil., 505.)
1922 1923 1923 We rule that the appellant had no legal right to rescind the contract
of sale because of the failure of Song Fo & Company to pay for
Dec. 18 P206.16 Dec. 26/22 Jan. 5 Feb. 20 the molasses within the time agreed upon by the parties. We
sustain the finding of the trial judge in this respect.
Dec. 29 206.16 Jan. 3/23 do Do
3. On the basis first, of a contract for 300,000 gallons of
1923 molasses, and second, of a contract imprudently breached by the
Hawaiian-Philippine Co., what is the measure of damages? We
Jan. 5 206.16 Jan. 9/23 Mar. 7 or Mar. 31 again turn to the facts as agreed upon by the parties.
8
The first cause of action of the plaintiff is based on the greater
Feb. 12 206.16 Mar. 12/23 do Do expense to which it was put in being compelled to secure
molasses from other sources. Three hundred thousand gallons of
Feb. 27 206.16 do do Do molasses was the total of the agreement, as we have seen. As
conceded by the plaintiff, 55,006 gallons of molasses were
Mar. 5 206.16 do do Do delivered by the defendant to the plaintiff before the breach. This
leaves 244,994 gallons of molasses undelivered which the
Mar. 16 206.16 Mar. 20/23 Apr. 2/23 Apr. 19 plaintiff had to purchase in the open market. As expressly
conceded by the plaintiff at page 25 of its brief, 100,000 gallons
Mar. 24 206.16 Mar. 31/23 do Do of molasses were secured from the Central North Negros Sugar
Co., Inc., at two centavos a gallon. As this is the same price
Mar. 29 206.16 do do Do specified in the contract between the plaintiff and the defendant,
the plaintiff accordingly suffered no material loss in having to
make this purchase. So 244,994 gallons minus the 100,000
Some doubt has risen as to when Song Fo & Company was gallons just mentioned leaves as a result 144,994 gallons. As to
expected to make payments for the molasses delivered. Exhibit F this amount, the plaintiff admits that it could have secured it and
speaks of payments "at the end of each month." Exhibit G is silent more from the Central Victorias Milling Company, at three and
on the point. Exhibit M, a letter of March 28, 1923, from Warner, one-half centavos per gallon. In other words, the plaintiff had to
Barnes & Co., Ltd., the agent of the Hawaiian-Philippine Co. to pay the Central Victorias Milling company one and one-half
Song Fo & Company, mentions "payment on presentation of bills centavos a gallon more for the molasses than it would have had
for each delivery." Exhibit O, another letter from Warner, Barnes to pay the Hawaiian-Philippine Co. Translated into pesos and
& Co., Ltd. to Song Fo & Company dated April 2, 1923, is of a centavos, this meant a loss to the plaintiff of approximately
similar tenor. Exhibit P, a communication sent direct by the P2,174.91. As the conditions existing at the central of the
Hawaiian-Philippine Co. to Song Fo & Company on April 2, 1923, Hawaiian-Philippine Co. may have been different than those
by which the Hawaiian-Philippine Co. gave notice of the found at the Central North Negros Sugar Co., Inc., and the Central
termination of the contract, gave as the reason for the rescission, Victorias Milling Company, and as not alone through the delay but
the breach by Song Fo & Company of this condition: "You will through expenses of transportation and incidental expenses, the
recall that under the arrangements made for taking our molasses, plaintiff may have been put to greater cost in making the purchase
you were to meet our accounts upon presentation and at each of the molasses in the open market, we would concede under the
delivery." Not far removed from this statement, is the allegation of first cause of action in round figures P3,000.
plaintiff in its complaint that "plaintiff agreed to pay defendant, at
the end of each month upon presentation accounts." The second cause of action relates to lost profits on account of
the breach of the contract. The only evidence in the record on this
Resolving such ambiguity as exists and having in mind ordinary question is the stipulation of counsel to the effect that had Mr.
business practice, a reasonable deduction is that Song Fo & Song Heng, the manager of Song Fo & Company, been called as
Company was to pay the Hawaiian-Philippine Co. upon a witness, he would have testified that the plaintiff would have
presentation of accounts at the end of each month. Under this realized a profit of P14,948.43, if the contract of December 13,
hypothesis, Song Fo & Company should have paid for the 1922, had been fulfilled by the defendant. Indisputably, this
molasses delivered in December, 1922, and for which accounts
OBLICON 1-9-2018 I ACJUCO 3

statement falls far short of presenting proof on which to make a


finding as to damages.

In the first place, the testimony which Mr. Song Heng would have
given undoubtedly would follow the same line of thought as found
in the decision of the trial court, which we have found to be
unsustainable. In the second place, had Mr. Song Heng taken the
witness-stand and made the statement attributed to him, it would
have been insufficient proof of the allegations of the complaint,
and the fact that it is a part of the stipulation by counsel does not
change this result. And lastly, the testimony of the witness Song
Heng, it we may dignify it as such, is a mere conclusion, not a
proven fact. As to what items up the more than P14,000 of alleged
lost profits, whether loss of sales or loss of customers, or what
not, we have no means of knowing.

We rule that the plaintiff is entitled to recover damages from the


defendant for breach of contract on the first cause of action in the
amount of P3,000 and on the second cause of action in no
amount. Appellant's assignments of error are accordingly found
to be well taken in part and not well taken in part.

Agreeable to the foregoing, the judgment appealed from shall be


modified and the plaintiff shall have and recover from the
defendant the sum of P3,000, with legal interest form October 2,
1923, until payment. Without special finding as to costs in either
instance, it is so ordered.

Avanceña, C.J., Johnson, Street, Villamor, Ostrand, Johns,


Romualdez and Villa-Real, JJ., concur.
OBLICON 1-9-2018 I ACJUCO 4

A motion for reconsideration filed by the defendants-appellants


G.R. No. L-42283 March 18, 1985 was denied.

BUENAVENTURA ANGELES, ET AL., plaintiffs-appellees, As earlier stated, the then Court of Appeals certified the case to
vs. us considering that the appeal involves pure questions of law.
URSULA TORRES CALASANZ, ET AL., defendants-
appellants. The defendants-appellants assigned the following alleged errors
of the lower court:

GUTIERREZ, JR., J.: First Assignment of Error

This is an appeal from the decision of the Court of First Instance THE LOWER COURT ERRED IN NOT HOLDING THE
of Rizal, Seventh Judicial District, Branch X, declaring the CONTRACT TO SELL (ANNEX "A" OF COMPLIANCE) AS
contract to sell as not having been validly cancelled and ordering HAVING BEEN LEGALLY AND VALIDLY CANCELLED.
the defendants-appellants to execute a final deed of sale in favor
of the plaintiffs-appellees, to pay P500.00 attorney's fees and Second Assignment of Error
costs.
EVEN ASSUMING ARGUENDO THAT THE SAID CONTRACT
The facts being undisputed, the Court of Appeals certified the TO SELL HAS NOT BEEN LEGALLY AND VALIDLY
case to us since only pure questions of law have been raised for CANCELLED, THE LOWER COURT ERRED IN ORDERING
appellate review. DEFENDANTS TO EXECUTE A FINAL DEED OF SALE IN
FAVOR OF THE PLAINTIFF.
On December 19, 1957, defendants-appellants Ursula Torres
Calasanz and Tomas Calasanz and plaintiffs-appellees Third Assignment of Error
Buenaventura Angeles and Teofila Juani entered into a contract
to sell a piece of land located in Cainta, Rizal for the amount of THE LOWER COURT ERRED IN ORDERING DEFENDANTS
P3,920.00 plus 7% interest per annum. TO PAY PLAINTIFFS THE SUM OF P500.00 AS ATTORNEY'S
FEES.
The plaintiffs-appellees made a downpayment of P392.00 upon
the execution of the contract. They promised to pay the balance The main issue to be resolved is whether or not the contract to
in monthly installments of P 41.20 until fully paid, the installments sell has been automatically and validly cancelled by the
being due and payable on the 19th day of each month. The defendants-appellants.
plaintiffs-appellees paid the monthly installments until July 1966,
when their aggregate payment already amounted to P4,533.38. The defendants-appellants submit that the contract was validly
On numerous occasions, the defendants-appellants accepted cancelled pursuant to paragraph six of the contract which
and received delayed installment payments from the plaintiffs- provides:
appellees.
xxx xxx xxx
On December 7, 1966, the defendants-appellants wrote the
plaintiffs-appellees a letter requesting the remittance of past due SIXTH.—In case the party of the SECOND PART fails to satisfy
accounts. any monthly installments, or any other payments herein agreed
upon, he is granted a month of grace within which to make the
On January 28, 1967, the defendants-appellants cancelled the retarded payment, together with the one corresponding to the said
said contract because the plaintiffs-appellees failed to meet month of grace; it is understood, however, that should the month
subsequent payments. The plaintiffs' letter with their plea for of grace herein granted to the party of the SECOND PART
reconsideration of the said cancellation was denied by the expired; without the payments corresponding to both months
defendants-appellants. having been satisfied, an interest of 10% per annum will be
charged on the amounts he should have paid; it is understood
The plaintiffs-appellees filed Civil Case No. 8943 with the Court further, that should a period of 90 days elapse, to begin from the
of First Instance of Rizal, Seventh Judicial District, Branch X to expiration of the month of grace herein mentioned, and the party
compel the defendants-appellants to execute in their favor the of SECOND PART has not paid all the amounts he should have
final deed of sale alleging inter alia that after computing all paid with the corresponding interest up to that date, the party of
subsequent payments for the land in question, they found out that the FIRST PART has the right to declare this contract cancelled
they have already paid the total amount of P4,533.38 including and of no effect, and as consequence thereof, the party of the
interests, realty taxes and incidental expenses for the registration FIRST PART may dispose of the parcel of land covered by this
and transfer of the land. contract in favor of other persons, as if this contract had never
been entered into. In case of such cancellation of the contract, all
The defendants-appellants alleged in their answer that the the amounts paid in accordance with this agreement together with
complaint states no cause of action and that the plaintiffs- all the improvements made on the premises, shall be considered
appellees violated paragraph six (6) of the contract to sell when as rents paid for the use and occupation of the above mentioned
they failed and refused to pay and/or offer to pay the monthly premises, and as payment for the damages suffered by failure of
installments corresponding to the month of August, 1966 for more the party of the SECOND PART to fulfill his part of the agreement;
than five (5) months, thereby constraining the defendants- and the party of the SECOND PART hereby renounces all his
appellants to cancel the said contract. right to demand or reclaim the return of the same and obliges
himself to peacefully vacate the premises and deliver the same to
The lower court rendered judgment in favor of the plaintiffs- the party of the FIRST PART. (Emphasis supplied by appellant)
appellees. The dispositive portion of the decision reads:
xxx xxx xxx
WHEREFORE, based on the foregoing considerations, the Court
hereby renders judgment in favor of the plaintiffs and against the The defendants-appellants argue that the plaintiffs-appellees
defendants declaring that the contract subject matter of the failed to pay the August, 1966 installment despite demands for
instant case was NOT VALIDLY cancelled by the defendants. more than four (4) months. The defendants-appellants point to
Consequently, the defendants are ordered to execute a final Deed Jocson v. Capitol Subdivision (G.R. No. L-6573, February 28,
of Sale in favor of the plaintiffs and to pay the sum of P500.00 by 1955) where this Court upheld the right of the subdivision owner
way of attorney's fees. Costs against the defendants. to automatically cancel a contract to sell on the strength of a
OBLICON 1-9-2018 I ACJUCO 5

provision or stipulation similar to paragraph 6 of the contract in obligation; (Ocejo, Perez & Co. v. International Banking Corp., 37
this case. The defendants-appellants also argue that even in the Phil. 631; Republic v. Hospital de San Juan de Dios, et al., 84
absence of the aforequoted provision, they had the right to cancel Phil. 820) since in every case where the extrajudicial resolution is
the contract to sell under Article 1191 of the Civil Code of the contested only the final award of the court of competent
Philippines. jurisdiction can conclusively settle whether the resolution was
proper or not. It is in this sense that judicial action will be
The plaintiffs-appellees on the other hand contend that the necessary, as without it, the extrajudicial resolution will remain
Jocson ruling does not apply. They state that paragraph 6 of the contestable and subject to judicial invalidation, unless attack
contract to sell is contrary to law insofar as it provides that in case thereon should become barred by acquiescence, estoppel or
of specified breaches of its terms, the sellers have the right to prescription.
declare the contract cancelled and of no effect, because it granted
the sellers an absolute and automatic right of rescission. The right to rescind the contract for non-performance of one of its
stipulations, therefore, is not absolute. In Universal Food Corp. v.
Article 1191 of the Civil Code on the rescission of reciprocal Court of Appeals (33 SCRA 1) the Court stated that—
obligations provides:
The general rule is that rescission of a contract will not be
The power to rescind obligations is implied in reciprocal ones, in permitted for a slight or casual breach, but only for such
case one of the obligors should not comply with what is incumbent substantial and fundamental breach as would defeat the very
upon him. object of the parties in making the agreement. (Song Fo & Co. v.
Hawaiian-Philippine Co., 47 Phil. 821, 827) The question of
The injured party may choose between the fulfillment and the whether a breach of a contract is substantial depends upon the
rescission of the obligation, with the payment of damages in either attendant circumstances. (Corpus v. Hon. Alikpala, et al., L-23707
case. He may also seek rescission, even after he has chosen & L-23720, Jan. 17, 1968). ... .
fulfillment, if the latter should become impossible.
The defendants-appellants state that the plaintiffs-appellees
xxx xxx xxx violated Section two of the contract to sell which provides:

Article 1191 is explicit. In reciprocal obligations, either party the SECOND.—That in consideration of the agreement of sale of the
right to rescind the contract upon the failure of the other to perform above described property, the party of the SECOND PART
the obligation assumed thereunder. Moreover, there is nothing in obligates himself to pay to the party of the FIRST PART the Sum
the law that prohibits the parties from entering into an agreement of THREE THOUSAND NINE HUNDRED TWENTY ONLY
that violation of the terms of the contract would cause its (P3,920.00), Philippine Currency, plus interest at the rate of 7%
cancellation even without court intervention (Froilan v. Pan per annum, as follows:
Oriental Shipping, Co., et al., 12 SCRA 276)—
(a) The amount of THREE HUNDRED NINETY TWO only
Well settled is, however, the rule that a judicial action for the (P392.00) when this contract is signed; and
rescission of a contract is not necessary where the contract
provides that it may be revoked and cancelled for violation of any (b) The sum of FORTY ONE AND 20/100 ONLY (P4l.20)
of its terms and conditions' (Lopez v. Commissioner of Customs, on or before the 19th day of each month, from this date until the
37 SCRA 327, and cases cited therein) total payment of the price above stipulated, including interest.

Resort to judicial action for rescission is obviously not because they failed to pay the August installment, despite
contemplated . . . The validity of the stipulation can not be demand, for more than four (4) months.
seriously disputed. It is in the nature of a facultative resolutory
condition which in many cases has been upheld by this Court. The breach of the contract adverted to by the defendants-
(Ponce Enrile v. Court of Appeals, 29 SCRA 504). appellants is so slight and casual when we consider that apart
from the initial downpayment of P392.00 the plaintiffs-appellees
The rule that it is not always necessary for the injured party to had already paid the monthly installments for a period of almost
resort to court for rescission of the contract when the contract nine (9) years. In other words, in only a short time, the entire
itself provides that it may be rescinded for violation of its terms obligation would have been paid. Furthermore, although the
and conditions, was qualified by this Court in University of the principal obligation was only P 3,920.00 excluding the 7 percent
Philippines v. De los Angeles, (35 SCRA 102) where we explained interests, the plaintiffs- appellees had already paid an aggregate
that: amount of P 4,533.38. To sanction the rescission made by the
defendants-appellants will work injustice to the plaintiffs-
Of course, it must be understood that the act of a party in treating appellees. (See J.M. Tuazon and Co., Inc. v. Javier, 31 SCRA
a contract as cancelled or resolved on account of infractions by 829) It would unjustly enrich the defendants-appellants.
the other contracting party must be made known to the other and
is always provisional, being ever subject to scrutiny and review by Article 1234 of the Civil Code which provides that:
the proper court. If the other party denies that rescission is
justified, it is free to resort to judicial action in its own behalf, and If the obligation has been substantially performed in good faith,
bring the matter to court. Then, should the court, after due the obligor may recover as though there had been a strict and
hearing, decide that the resolution of the contract was not complete fulfillment, less damages suffered by the obligee.
warranted, the responsible party will be sentenced to damages;
in the contrary case, the resolution will be affirmed, and the also militates against the unilateral act of the defendants-
consequent indemnity awarded to the party prejudiced. appellants in cancelling the contract.

In other words, the party who deems the contract violated many We agree with the observation of the lower court to the effect that:
consider it resolved or rescinded, and act accordingly, without
previous court action, but it proceeds at its own risk. For it is only Although the primary object of selling subdivided lots is business,
the final judgment of the corresponding court that will conclusively yet, it cannot be denied that this subdivision is likewise purposely
and finally settle whether the action taken was or was not correct done to afford those landless, low income group people of
in law. ... . realizing their dream of a little parcel of land which they can really
call their own.
We see no conflict between this ruling and the previous
jurisprudence of this Court invoked by respondent declaring that The defendants-appellants cannot rely on paragraph 9 of the
judicial action is necessary for the resolution of a reciprocal contract which provides:
OBLICON 1-9-2018 I ACJUCO 6

NINTH.-That whatever consideration of the party of the FIRST We agree with the plaintiffs-appellees. The contract to sell
PART may concede to the party of the SECOND PART, as not entered into by the parties has some characteristics of a contract
exacting a strict compliance with the conditions of paragraph 6 of of adhesion. The defendants-appellants drafted and prepared the
this contract, as well as any other condonation that the party of contract. The plaintiffs-appellees, eager to acquire a lot upon
the FIRST PART may give to the party of the SECOND PART which they could build a home, affixed their signatures and
with regards to the obligations of the latter, should not be assented to the terms and conditions of the contract. They had no
interpreted as a renunciation on the part of the party of the FIRST opportunity to question nor change any of the terms of the
PART of any right granted it by this contract, in case of default or agreement. It was offered to them on a "take it or leave it" basis.
non-compliance by the party of the SECOND PART. In Sweet Lines, Inc. v. Teves (83 SCRA 36 1), we held that:

The defendants-appellants argue that paragraph nine clearly xxx xxx xxx
allows the seller to waive the observance of paragraph 6 not
merely once, but for as many times as he wishes. ... (W)hile generally, stipulations in a contract come about after
deliberate drafting by the parties thereto. . . . there are certain
The defendants-appellants' contention is without merit. We agree contracts almost all the provisions of which have been drafted
with the plaintiffs-appellees that when the defendants-appellants, only by one party, usually a corporation. Such contracts are called
instead of availing of their alleged right to rescind, have accepted contracts of adhesion, because the only participation of the party
and received delayed payments of installments, though the is the signing of his signature or his "adhesion" thereto. Insurance
plaintiffs-appellees have been in arrears beyond the grace period contracts, bills of lading, contracts of sale of lots on the installment
mentioned in paragraph 6 of the contract, the defendants- plan fall into this category. (Paras, Civil Code of the Philippines,
appellants have waived and are now estopped from exercising Seventh ed., Vol. 1, p. 80.) (Emphasis supplied)
their alleged right of rescission. In De Guzman v. Guieb (48 SCRA
68), we held that: While it is true that paragraph 2 of the contract obligated the
plaintiffs-appellees to pay the defendants-appellants the sum of
xxx xxx xxx P3,920.00 plus 7% interest per annum, it is likewise true that
under paragraph 12 the seller is obligated to transfer the title to
But defendants do not deny that in spite of the long arrearages, the buyer upon payment of the P3,920.00 price sale.
neither they nor their predecessor, Teodoro de Guzman, even
took steps to cancel the option or to eject the appellees from the The contract to sell, being a contract of adhesion, must be
home-lot in question. On the contrary, it is admitted that the construed against the party causing it. We agree with the
delayed payments were received without protest or qualification. observation of the plaintiffs-appellees to the effect that "the terms
... Under these circumstances, We cannot but agree with the of a contract must be interpreted against the party who drafted the
lower court that at the time appellees exercised their option, same, especially where such interpretation will help effect justice
appellants had already forfeited their right to invoke the above- to buyers who, after having invested a big amount of money, are
quoted provision regarding the nullifying effect of the non- now sought to be deprived of the same thru the prayed application
payment of six months rentals by appellees by their having of a contract clever in its phraseology, condemnable in its
accepted without qualification on July 21, 1964 the full payment lopsidedness and injurious in its effect which, in essence, and in
by appellees of all their arrearages. its entirety is most unfair to the buyers."

The defendants-appellants contend in the second assignment of Thus, since the principal obligation under the contract is only
error that the ledger of payments show a balance of P671,67 due P3,920.00 and the plaintiffs-appellees have already paid an
from the plaintiffs-appellees. They submit that while it is true that aggregate amount of P4,533.38, the courts should only order the
the total monthly installments paid by the plaintiffs-appellees may payment of the few remaining installments but not uphold the
have exceeded P3,920.00, a substantial portion of the said cancellation of the contract. Upon payment of the balance of
payments were applied to the interests since the contract P671.67 without any interest thereon, the defendants-appellants
specifically provides for a 7% interest per annum on the remaining must immediately execute the final deed of sale in favor of the
balance. The defendants-appellants rely on paragraph 2 of the plaintiffs-appellees and execute the necessary transfer
contract which provides: documents as provided in paragraph 12 of the contract. The
attorney's fees are justified.
SECOND.—That in consideration of the agreement of sale of the
above described property, the party of the SECOND PART WHEREFORE, the instant petition is DENIED for lack of merit.
obligates himself to pay to the party of the FIRST PART the Sum The decision appealed from is AFFIRMED with the modification
of THREE THOUSAND NINE HUNDRED TWENTY ONLY (P that the plaintiffs-appellees should pay the balance of SIX
3,920.00), Philippine Currency, plus interest at the rate of 7% per HUNDRED SEVENTY ONE PESOS AND SIXTY-SEVEN
annum ... . (Emphasis supplied) CENTAVOS (P671.67) without any interests. Costs against the
defendants-appellants.
The plaintiffs-appellees on the other hand are firm in their
submission that since they have already paid the defendants- SO ORDERED.
appellants a total sum of P4,533.38, the defendants-appellants
must now be compelled to execute the final deed of sale pursuant
to paragraph 12 of the contract which provides:

TWELFTH.—That once the payment of the sum of P3,920.00, the


total price of the sale is completed, the party to the FIRST PART
will execute in favor of the party of the SECOND PART, the
necessary deed or deeds to transfer to the latter the title of the
parcel of land sold, free from all hens and encumbrances other
than those expressly provided in this contract; it is understood,
however, that au the expenses which may be incurred in the said
transfer of title shall be paid by the party of the SECOND PART,
as above stated.

Closely related to the second assignment of error is the


submission of the plaintiffs-appellees that the contract herein is a
contract of adhesion.
OBLICON 1-9-2018 I ACJUCO 7

said period will be subject to our review and confirmation. [Exh.


G.R. No. L-55665 February 8, 1989 "A" and "C"; Exhs. "l" and "2".]

DELTA MOTOR CORPORATION, petitioner, Hector Genuino was agreeable to the offers of Delta hence, he
vs. manifested his conformity thereto by signing his name in the
EDUARDA SAMSON GENUINO, JACINTO S. GENUINO, Jr., space provided on July 17, 1972 and July 24, 1972 for the first
VICTOR S. GENUINO, HECTOR S. GENUINO, EVELYN S. and second letter-quotations, respectively.
GENUINO, and The COURT OF APPEALS, respondents.
It is undisputed that private respondents made initial payments on
Alcasid, Villanueva & Associates for petitioner. both contracts — for the first contract, P13,200.00 and, for the
second, P2,700.00 — for a total sum of P15,900.00 on July 28,
Luna, Puruganan, Sison & Ongkiko for respondents. 1972 (Exhs. "B" and "D"].

Likewise unquestionable are the following. the non-delivery of the


CORTES, J.: iron pipes by Delta; the non-payment of the subsequent
installments by the Genuinos; and the non-execution by the
Petitioner, through this petition for review by certiorari, appeals Genuinos of the promissory note called for by the first contract.
from the decision of respondent appellate court in CA-G.R. No.
59848-R entitled "Eduarda Samson Genuino, et al. v. Delta Motor The evidence presented in the trial court also showed that
Corporation" promulgated on October 27, 1980. sometime in July 1972 Delta offered to deliver the iron pipes but
the Genuinos did not accept the offer because the construction of
The facts are as follows: the ice plant building where the pipes were to be installed was not
yet finished.
Petitioner Delta Motor Corporation (hereinafter referred to as
Delta) is a corporation duly organized and existing under Almost three years later, on April 15, 1975, Hector Genuino, in
Philippine laws. behalf of España Extension Ice Plant and Cold Storage, asked
Delta to deliver the iron pipes within thirty (30) days from its
On the other hand, private respondents are the owners of an receipt of the request. At the same time private respondents
iceplant and cold storage located at 1879 E. Rodriguez Sr. manifested their preparedness to pay the second installment on
Avenue, Quezon City doing business under the name "España both contracts upon notice of Delta's readiness to deliver.
Extension Iceplant and Cold Storage."
Delta countered that the black iron pipes cannot be delivered on
In July 1972, two letter-quotations were submitted by Delta to the prices quoted as of July 1972. The company called the
Hector Genuino offering to sell black iron pipes. T attention of the Genuinos to the stipulation in their two (2)
contracts that the quoted prices were good only within thirty (30)
The letter dated July 3, 1972 quoted Delta's selling price for 1,200 days from date of offer. Whereupon Delta sent new price
length of black iron pipes schedule 40, 2" x 20' including delivery quotations to the Genuinos based on its current price of black iron
at P66,000.00 with the following terms of payment: pipes, as follows:

a. 20% of the net contract price or P13,200.00 will be due and P241,800.00 for 1,200 lengths of black iron pjpes schedule 40, 2"
payable upon signing of the contract papers. x 20' [Exh. "G-1".]

b. 20% of the net contract price or P13,200.00 will be due and P17,550.00 for 150 lengths of black iron pipes schedule 40, 1 1/4"
payable before commencement of delivery. x 20' [Exh. "G-2".]

c. The balance of 60% of the net contract price or P39,600.00 with The Genuinos rejected the new quoted prices and instead filed a
8% financing charge per annum will be covered by a Promissory complaint for specific performance with damages seeking to
Note bearing interest at the rate of 14% per annum and payable compel Delta to deliver the pipes. Delta, in its answer prayed for
in TWELVE (12) equal monthly installment (sic), the first of which rescission of the contracts pursuant to Art. 1191 of the New Civil
will become due thirty (30) days after the completion of delivery. Code. The case was docketed as Civil Case No. Q-20120 of the
Additional 14% will be charged for all delayed payments. [Exh. then Court of First Instance of Rizal, Branch XVIII, Quezon City.
"A"; Exh. 1.]
After trial the Court of First Instance ruled in favor of Delta,the
The second letter-quotation dated July 18, 1972 provides for the dispositive portion of its decision reading as follows:
selling price of 150 lengths of black iron pipes schedule 40, 1 1/4"
x 20' including delivery at P5,400.00 with the following terms of WHEREFORE, premises considered, judgment is rendered:
payment:
1. Declaring the contracts, Annexes "A" and "C" of the complaint
a. 50% of the net contract price or P 2,700.00 will be due and rescinded;
payable upon signing of the contract papers.
2. Ordering defendant to refund to plaintiffs the sum of P15,900.00
b. 50% of the net contract price or P 2,700.00 will be due and delivered by the latter as downpayments on the aforesaid
payable before commencement of delivery. [Exh. "C"; Exh. "2".] contracts;

Both letter-quotations also contain the following stipulations as to 3. Ordering plaintiffs to pay defendant the sum of P10,000.00 as
delivery and price offer: attorney's fees; and,

DELIVERY 4. To pay the costs of suit. [CFI Decision, pp. 13-14; Rollo, pp. 53-
54.]
Ex-stock subject to prior sales.
On appeal, the Court of Appeals reversed and ordered private
xxx xxx xxx respondents to make the payments specified in "Terms of
Payment — (b)" of the contracts and to execute the promissory
Our price offer indicated herein shall remain firm within a period note required in the first contract and thereafter, Delta should
of thirty (30) days from the date hereof. Any order placed after immediately commence delivery of the black iron pipes.* [CA
Decision, p. 20; Rollo, p. 75.]
OBLICON 1-9-2018 I ACJUCO 8

substantial breach, let alone a breach of contract, as would


The Court of Appeals cited two main reasons why it reversed the warrant rescission.
trial court, namely:
Firstly, it is undisputed that a month after the execution of the two
1. As Delta was the one who prepared the contracts and (2) contracts, Delta's offer to deliver the black iron pipes was
admittedly, it had knowledge of the fact that the black iron pipes rejected by the Genuinos who were "not ready to accept delivery
would be used by the Genuinos in their cold storage plant which because the cold storage rooms have not been constructed yet.
was then undergoing construction and therefore, would require Plaintiffs (private respondents herein) were short-funded, and did
sometime before the Genuinos would require delivery, Delta not have the space to accommodate the pipes they ordered" [CFI
should have included in said contracts a deadline for delivery but Decision, p. 9; Rollo, p. 49].
it did not. As a matter of fact neither did it insist on delivery when
the Genuinos refused to accept its offer of delivery. [CA Decision, Given this answer to its offer, Delta did not do anything. As
pp. 16-17; Rollo, pp. 71-72.] testified by Crispin Villanueva, manager of the Technical Service
department of petitioner:
2. Delta's refusal to make delivery in 1975 unless the
Genuinos pay a price very much higher than the prices it Q You stated that you sent a certain Evangelista to the
previously quoted would mean an amendment of the contracts. It España Extension and Cold Storage to offer the delivery subject
would be too unfair for the plaintiffs if they will be made to bear matter of the contract and then you said that Mr. Evangelista
the increase in prices of the black iron pipes when they had reported (sic) to you that plaintiff would not accept delivery, is that
already paid quite an amount for said items and defendant had correct, as a summary of your statement?
made use of the advance payments. That would be unjust
enrichment on the part of the defendant at the expense of the A A Yes, sir.
plaintiffs and is considered an abominable business practice. [CA
Decision, pp. 18-19; Rollo, pp. 73-74.] Q Now, what did you do in the premises (sic)?

Respondent court denied Delta's motion for reconsideration A Yes, well, we take the word of Mr. Evangelista. We could not
hence this petition for review praying for the reversal of the Court deliver the said black iron pipes, because as per information the
of Appeals decision and affirmance of that of the trial court. Ice Plant is not yet finished.

Petitioner argues that its obligation to deliver the goods under Q Did you not report that fact to ... any other defendant-officials of
both contracts is subject to conditions required of private the Delta Motor Corporation?
respondents as vendees. These conditions are: payment of 20%
of the net contract price or P13,200.00 and execution of a A No.
promissory note called for by the first contract; and payment of
50% of the net contract price or P2,700.00 under the second Q And you did not do anything after that?
contract. These, Delta posits, are suspensive conditions and only
upon their performance or compliance would its obligation to A Because taking the word of my Engineer we did not do anything.
deliver the pipes arise [Petition, pp. 9-12; Rollo, pp. 1720.] Thus, [TSN, December 8, 1975, pp. 18-19.]
when private respondents did not perform their obligations; when
they refused to accept petitioner's offer to deliver the goods; and, xxx xxx xxx
when it took them three (3) long years before they demanded
delivery of the iron pipes that in the meantime, great and sudden And secondly, three (3) years later when the Genuinos offered to
fluctuation in market prices have occurred; Delta is entitled to make payment Delta did not raise any argument but merely
rescind the two (2) contracts. demanded that the quoted prices be increased. Thus, in its
answer to private respondents' request for delivery of the pipes,
Delta relies on the following provision of law on rescission: Delta countered:

Art. 1191. The power to rescind obligations is implied in reciprocal Thank you for your letter dated April 15, 1975, requesting for
ones, in case one of the obligors should not comply with what is delivery of Black Iron pipes;.
incumbent upon him.
We regret to say, however, that we cannot base our price on our
The injured party may choose between the fulfillment and the proposals dated July 3 and July 18, 1972 as per the following
rescission of the obligation, with the payment of damages in either paragraph quoted on said proposal:
case. He may also seek rescission, even after he has chosen
fulfillment, if the latter should become impossible. Our price offer indicated herein shall remain firm within a period
of thirty (30) days from the date hereof. Any order placed after
The court shall decree the rescission claimed, unless there be just said period will be subject to our review and confirmation.
cause authorizing the fixing of a period.
We are, therefore, enclosing our re-quoted proposal based on our
This is understood to be without prejudice to the rights of third current price. [Exh. "G".]
persons who have acquired the thing, in accordance with articles
1385 and 1388 and the Mortgage Law. Moreover, the power to rescind under Art. 1191 is not absolute.
"[T]he act of a party in treating a contract as cancelled or resolved
In construing Art. 1191, the Supreme Court has stated that, on account of infractions by the other contracting party must be
"[r]escission will be ordered only where the breach complained of made known to the other and is always provisional, being ever
is substantial as to defeat the object of the parties in entering into subject to scrutiny and review by the proper court." [University of
the agreement. It will not be granted where the breach is slight or the Phils. v. De los Angeles, G. R. No. L-28602, September 29,
casual." [Phil. Amusement Enterprises, Inc. v. Natividad, G.R. No. 1970, 35 SCRA 102, 107; Emphasis supplied.]
L-21876, September 29, 1967, 21 SCRA 284, 290.] Further, "[t]he
question of whether a breach of a contract is substantial depends In the instant case, Delta made no manifestation whatsoever that
upon the attendant circumstances." [Universal Food Corporation it had opted to rescind its contracts with f-he Genuinos. It only
v. Court of Appeals, G. R. No. L-29155, May 13,1970,33 SCRA raised rescission as a defense when it was sued for specific
1, 18]. performance by private respondents.

In the case at bar, the conduct of Delta indicates that the Further, it would be highly inequitable for petitioner Delta to
Genuinos' non-performance of its obligations was not a rescind the two (2) contracts considering the fact that not only
OBLICON 1-9-2018 I ACJUCO 9

does it have in its possession and ownership the black iron pipes,
but also the P15,900.00 down payments private respondents
have paid. And if petitioner Delta claims the right to rescission, at
the very least, it should have offered to return the P15,900.00
down payments [See Art. 1385, Civil Code and Hodges v.
Granada, 59 Phil. 429 (1934)].

It is for these same reasons that while there is merit in Delta's


claim that the sale is subject to suspensive conditions, the Court
finds that it has, nevertheless, waived performance of these
conditions and opted to go on with the contracts although at a
much higher price. Art. 1545 of the Civil Code provides:

Art. 1545. Where the obligation of either party to a contract of sale


is subject to any condition which is not performed, such party may
refuse to proceed with the contract or he may waived performance
of the condition. . . . [Emphasis supplied.]

Finally, Delta cannot ask for increased prices based on the price
offer stipulation in the contracts and in the increase in the cost of
goods. Reliance by Delta on the price offer stipulation is
misplaced. Said stipulation makes reference to Delta's price offer
as remaining firm for thirty (30) days and thereafter, will be subject
to its review and confirmation. The offers of Delta, however, were
accepted by the private respondents within the thirty (30)-day
period. And as stipulated in the two (2) letter-quotations,
acceptance of the offer gives rise to a contract between the
parties:

In the event that this proposal is acceptable to you, please


indicate your conformity by signing the space provided herein
below which also serves as a contract of this proposal. [Exhs. "A"
and "C"; Exhs. "1" and "2".]

And as further provided by the Civil Code:

Art. 1319. Consent is manifested by the meeting of the offer and


the acceptance upon the thing and the cause which are to
constitute the contract.

Art. 1475. The contract of sale is perfected at the moment there


is a meeting of minds upon thing which is the object of the contract
and upon the price.

Thus, the moment private respondents accepted the offer of


Delta, the contract of sale between them was perfected and
neither party could change the terms thereof.

Neither could petitioner Delta rely on the fluctuation in the market


price of goods to support its claim for rescission. As testified to by
petitioner's Vice-President of Marketing for the Electronics,
Airconditioning and Refrigeration division, Marcelino Caja, the
stipulation in the two (2) contracts as to delivery, ex-stock subject
to prior sales, means that "the goods have not been delivered and
that there are no prior commitments other than the sale covered
by the contracts.. . once the offer is accepted, the company has
no more option to change the price." [CFI Decision, p. 5; Rollo, p.
45; Emphasis supplied.] Thus, petitioner cannot claim for higher
prices for the black iron pipes due to the increase in the cost of
goods. Based on the foregoing, petitioner Delta and private
respondents Genuinos should comply with the original terms of
their contracts.

WHEREFORE, the decision of the Court of Appeals is hereby


AFFIRMED.

SO ORDERED.
OBLICON 1-9-2018 I ACJUCO 10

G.R. No. 101762 July 6, 1993 credited to the said condominium unit in favor of the SECOND
PARTY;
VERMEN REALTY DEVELOPMENT CORPORATION,
petitioner, 7. That the SECOND PARTY shall deliver to the FIRST
vs. PARTY said construction materials under the agreed price and
THE COURT OF APPEALS and SENECA HARDWARE CO., conditions stated in the price quotation approved by both parties
INC., respondents. and made an integral part of this document;

Ramon P. Gutierrez for petitioner. 8. That the SECOND PARTY is obliged to start delivering
to the FIRST PARTY all items in the purchase order seven (7)
Adriano Velasco for private respondent. days from receipt of said purchase order until such time that the
whole amount of P552,000.00 is settled;

BIDIN, J.: 9. That the place of delivery shall be Vermen Pines


Condominium at Bakakeng Road, Baguio City;
Petitioner seeks a review of the decision of the Court of Appeals
in CA-G.R. CV No. 15730, which set aside the decision of the 10. That the freight cost of said materials shall be borne fifty
Regional Trial Court of Quezon City, Branch 92 in Civil Case No. percent (50%) by the FIRST PARTY and fifty percent (50%) by
Q-45232. The dispositive portion of the assailed decision reads the SECOND PARTY;
as follows:
11. That the FIRST PARTY pending completion of the
WHEREFORE, the decision a quo is set aside. As prayed for by VERMEN PINES CONDOMINIUM PHASE II which is the subject
plaintiff-appellant, the "Offsetting Agreement" (Exhibit "E" or "2") of this contract, shall deliver to the SECOND PARTY the
is hereby rescinded. Room 601 of Phase I of the Vermen Pines possession of residential condominium, Phase I, Unit Nos. 601
Condominium should be returned by plaintiff-appellant to and 602, studio type with a total area of 76.22 square meters or
defendant-appellee upon payment by the latter of the sum of less, worth P276,000.00;
P330,855.25 to the former, plus damages in the sum of P5,000.00
and P50.00 for the furnishings of Phase I of Condo (sic) Units 12. That after the completion of Vermen Pines
Nos. 601 and 602, and three (3) day rental of Room 402 during Condominium Phase II, the SECOND PARTY shall be given by
the Holy Week of 1982, respectively. In addition, defendant- the FIRST PARTY the first option to transfer from Phase I to
appellee is hereby ordered to pay plaintiff-appellant, who was Phase II under the same price, terms and conditions. (Rollo, pp.
compelled to litigate and hire the services of counsel to protect its 26-28).
interests against defendant-appellee's violation of their Offsetting
Agreement, the sum of P10,000.00 as an award for attorney's fee As found by the appellate court and admitted by both parties,
(sic) and other expenses of litigation. The claim for unrealized private respondent had paid petitioner the amount of
profits in a sum equivalent to 10% to 20% percent or P522,000.00 P110,151.75, and at the same time delivered construction
not having been duly proved, is therefore DENIED. No costs. materials worth P219,727.00. Pending completion of Phase II of
(Rollo, p. 31) the Vermen Pines Condominiums, petitioner delivered to private
respondent units 601 and 602 at Phase I of the Vermen Pines
On March 2, 1981, petitioner Vermen Realty and Development Condominiums (Rollo, p. 28). In 1982, the petitioner repossessed
Corporation, as First Party, and private respondent Seneca unit 602. As a consequence of the repossession, the officers of
Hardware Co., Inc., as Second Party, entered into a contract the private respondent corporation had to rent another unit for
denominated as "Offsetting Agreement". The said agreement their use when they went to Baguio on April 8, 1982. On May 10,
contained the following stipulations: 1982, the officers of the private respondent corporation requested
for a clarification of the petitioner's action of preventing them and
1. That the FIRST PARTY is the owner/developer of their families from occupying condominium unit 602.
VERMEN PINES CONDOMINIUM located at Bakakeng Road,
Baguio City; In its reply dated May 24, 1982, the petitioner corporation averred
that Room 602 was leased to another tenant because private
2. That the SECOND PARTY is in business of construction respondent corporation had not paid anything for purchase of the
materials and other hardware items; condominium unit. Petitioner corporation demanded payment of
P27,848.25 representing the balance of the purchase price of
3. That the SECOND PARTY desires to buy from the Room 601.
FIRST PARTY two (2) residential condominium units, studio type,
with a total floor area of 76.22 square meter (sic) more or less In 1983, the loan application for the construction of the Vermen
worth TWO HUNDRED SEVENTY SIX THOUSAND Pines Condominium Phase II was denied. Consequently,
(P276,000.00) PESOS only; construction of the condominium project stopped and has not
been resumed since then.
4. That the FIRST PARTY desires to but from the
SECOND PARTY construction materials mostly steel bars, On June 21, 1985, private respondent filed a complaint with the
electrical materials and other related items worth FIVE Regional Trial Court of Quezon City (Branch 92) for rescission of
HUNDRED FIFTY TWO THOUSAND (P552,000.00) PESOS the Offsetting Agreement with damages. In said complaint, private
only; respondent alleged that petitioner Vermen Realty Corporation
had stopped issuing purchase orders of construction materials
5. That the FIRST PARTY shall pay the SECOND PARTY after April, 1982, without valid reason, thus resulting in the
TWO HUNDRED SEVENTY SIX THOUSAND (P276,000.00) stoppage of deliveries of construction materials on its (Seneca
PESOS in cash upon delivery of said construction materials and Hardware) part, in violation of the Offsetting Agreement.
the other TWO HUNDRED SEVENTY SIX THOUSAND
(P276,000.00) PESOS shall be paid in the form of two (2) In its Answer filed on August 15, 1985, petitioner alleged that the
residential condominium units, studio type, with a total floor area fault lay with private respondent (plaintiff therein): although
of 76.22 square meter (sic) more or less also worth P276,000.00; petitioner issued purchase orders, it was private respondent who
could not deliver the supplies ordered, alleging that they were out
6. That, for every staggered delivery of construction of stock. (However, during a hearing on January 28, 1987, the
materials, fifty percent (50%) shall be paid by the FIRST PARTY Treasurer of petitioner corporation, when asked where the
to the SECOND PARTY C.O.D. and, fifty percent (50%) shall be purchase orders were, alleged that she was going to produce the
same in court, but the same was never produced (Rollo, p. 30).
OBLICON 1-9-2018 I ACJUCO 11

Moreover, private respondent quoted higher prices for the Standard Vacuum Oil Co., 101 Phil. 1262 [1957]). Under the
construction materials which were available. Thus, petitioner had agreement, private respondent shall deliver to petitioner
to resort to its other suppliers. Anent the query as to why Unit 602 construction materials worth P552,000.00 under the conditions
was leased to another tenant, petitioner averred that this was set forth in the Offsetting Agreement. Petitioner's obligation under
done because private respondent had not paid anything for it. the agreement is three-fold: he shall pay private respondent
P276,000.00 in cash; he shall deliver possession of units 601 and
As of December 16, 1986, private respondent had paid petitioner 602, Phase I, Vermen Pines Condominiums (with total value of
P110,151.75 in cash, made deliveries of construction materials P276,000.00) to private respondent; upon completion of Vermen
worth P219,727.00, leaving a balance of P27,848.25 representing Pines Condominiums Phase II, private respondent shall be given
the purchase price of unit 601 (Rollo, p. 28). The price of one option to transfer to similar units therein.
condominium unit was P138,000.00.
Article 1191 of the Civil Code provides the remedy of rescission
After conducting hearings, the trial court rendered a decision in (more appropriately, the term is "resolution") in case of
dismissing the complaint and ordering the plaintiff (private reciprocal obligations, where one of the obligors fails to comply
respondent in this petition) to pay defendant (petitioner in this with that is incumbent upon him.
petition) on its counterclaim in the amount of P27,848.25
representing the balance due on the purchase price of The general rule is that rescission of a contract will not be
condominium unit 601. permitted for a slight or causal breach, but only for such
substantial and fundamental breach as would defeat the very
On appeal, respondent court reversed the trial court's decision as object of the parties in executing the agreement. The question of
adverted to above. whether a breach of contract is substantial depends upon the
attendant circumstances (Universal Food Corp. vs. Court of
Petitioner now comes before us with the following assignment of Appeals, 33 SCRA 1, [1970]).
errors:
In the case at bar, petitioner argues that it was private respondent
I who failed to perform its obligation in the Offsetting Agreement. It
averred that contrary to the appellate court's ruling, the mere
THE RESPONDENT COURT OF APPEALS ERRED, AND ITS stoppage of the loan for the construction of Phase II of the Vermen
ERROR IS REVIEWABLE BY THIS HONORABLE COURT, Pines Condominiums should not have had any effect on the
WHEN IT SUPPLANTED CONTRARY TO THE EVIDENCE ON fulfillment of the obligations set forth in the Offsetting Agreement.
RECORD, THE TRIAL COURT'S CONCLUSIONS THAT Petitioner moreover stresses that contrary to private respondent's
PETITIONER DID NOT VIOLATE THE "OFFSETTING averments, purchase orders were sent, but there was failure to
AGREEMENT" IT ENTERED INTO WITH THE SENECA deliver the materials ordered because they were allegedly out of
HARDWARE CO., INC. WITH ITS TOTALLY BASELESS stock. Petitioner points out that, as admitted by private
"PERCEPTION" THAT IT WAS PETITIONER WHICH respondent's witness, petitioner had the discretion to order or not
DISCONTINUED TO ISSUE PURCHASE ORDERS DUE TO to order constructions materials, and that it was only after
THE STOPPAGE OF THE CONSTRUCTION OF PHASE II OF petitioner approved the price, after making a canvass from other
THE CONDOMINIUM PROJECT WHEN THE LOAN ON THE suppliers, that the latter would issue a purchase order. Petitioner
SAID PROJECT WAS STOPPED. argues that this was the agreement, and therefore the law
between the parties, hence, when no purchase orders were
II issued, no provision of the agreement was violated.

THE RESPONDENT COURT OF APPEALS ERRED, AND ITS Private respondent, on the other hand, points out that the subject
ERROR IS REVIEWABLE BY THIS HONORABLE COURT, of the Offsetting Agreement is Phase II of the Vermen Pines
WHEN IT CONCLUDED THAT IT WAS PETITIONER WHICH Condominiums. It alleges that since construction of Phase II of
BREACHED THE "OFFSETTING AGREEMENT" BECAUSE IT the Vermen Pines Condominiums has failed to begin (Rollo, p.
DID NOT SEND PURCHASE ORDERS TO PRIVATE 104), it has reason to move for rescission of the Offsetting
RESPONDENT AND DISCONTINUED THE CONSTRUCTION Agreement, as it cannot forever wait for the delivery of the
OF THE CONDOMINIUM PROJECT DESPITE THE FACT THAT condominium units to it.
THE EXHIBITS ATTESTING TO THIS FACT WAS FORMALLY
OFFERED IN EVIDENCE IN COURT AND MENTIONED BY IT It is evident from the facts of the case that private respondent did
IN ITS DECISION. not fail to fulfill its obligation in the Offsetting Agreement. The
discontinuance of delivery of construction materials to petitioner
III stemmed from the failure of petitioner to send purchase orders to
private respondent. The allegation that petitioner had been
THE RESPONDENT COURT OF APPEALS ERRED, AND ITS sending purchase orders to private respondent, which the latter
ERROR IS REVIEWABLE BY THIS HONORABLE COURT, could not fill, cannot be given credence. Perhaps in the beginning,
WHEN IT CONCLUDED THAT IT WAS PETITIONER WHICH it would send purchase orders to private respondent (as
BREACHED THE "OFFSETTING AGREEMENT" DESPITE THE evidenced by the purchase orders presented in court), and the
ADMISSION MADE BY PRIVATE RESPONDENT'S OWN latter would deliver the construction materials ordered. However,
WITNESS THAT PETITIONER HAD THE DISCRETION TO according to private respondent, after April, 1982, petitioner
ORDER OR NOT TO ORDER THE CONSTRUCTION stopped sending purchase orders. Petitioner failed to refute this
MATERIAL (SIC) FROM THE FORMER. (Rollo, p. ) allegation. When petitioner's witness, Treasurer of the petitioner
corporation, was asked to produce the purchase orders in court,
The issue presented before the Court is whether or not the the latter promised to do so, but this was never complied with.
circumstances of the case warrant rescission of the Offsetting
Agreement as prayed for by Private Respondent when he On the other hand, petitioner would never able to fulfill its
instituted the case before the trial court. obligation in allowing private respondent to exercise the option to
transfer from Phase I to Phase II, as the construction of Phase II
We rule in favor of private respondent. There is no controversy has ceased and the subject condominium units will never be
that the provisions of the Offsetting Agreement are reciprocal in available.
nature. Reciprocal obligations are those created or established at
the same time, out of the same cause, and which results in a The impossibility of fulfillment of the obligation on the part of
mutual relationship of creditor and debtor between parties. In petitioner necessitates resolution of the contract for indeed, the
reciprocal obligations, the performance of one is conditioned on non-fulfillment of the obligation aforementioned constitutes
the simultaneous fulfillment of the other obligation (Abaya vs. substantial breach of the Offsetting Agreement. The possibility of
OBLICON 1-9-2018 I ACJUCO 12

exercising the option of whether or not to transfer to condominium


units in Phase II was one of the factors which were considered by
private respondent when it entered into the agreement. Since the
construction of the Vermen Pines Condominium Phase II has
stopped, petitioner would be in no position to perform its obligation
to give private respondent the option to transfer to Phase II. It
would be the height of injustice to make private respondent wait
for something that may never come.

WHEREFORE, the petition is DENIED for lack of merit. Costs


against petitioner.

SO ORDERED.
OBLICON 1-9-2018 I ACJUCO 13

MODES OF BREACH On October 9, 1984, the petitioner sent a letter to each of the
private respondents demanding that they vacate the subject
premises and to pay the back rentals for the months of July,
DELAY OR MORA August and September, 1984, within fifteen (15) days from the
receipt thereof. Immediately upon the receipt of the said demand
i. MORA SOLVENDI letters on October 10, 1984, the private respondents paid their
respective arrearages in rent which were accepted by the
G.R. No. 77648 August 7, 1989 petitioner subject to the unilateral condition that the acceptance
was without prejudice to the filing of an ejectment suit.
CETUS DEVELOPMENT, INC., petitioner, Subsequent monthly rental payments were likewise accepted by
vs. the petitioner under the same condition.
COURT OF APPEALS and ONG TENG, respondents.
For failure of the private respondents to vacate the premises as
G.R. No. 77647 August 7, 1989 demanded in the letter dated October 9, 1984, the petitioner filed
with the Metropolitan Trial Court of Manila complaints for
CETUS DEVELOPMENT, INC., petitioner, ejectment against the manner, as follows: (1) 105972-CV, against
vs. Ederlina Navalta (2) 105973-CV, against Jose Liwanag; (3)
COURT OF APPEALS and EDERLINA NAVALTA, 105974-CV, against Flora Nagbuya; (4) 105975-CV, against
respondents. Leandro Canlas; (5) 105976-CV, against Victoria Sudario and (6)
105977-CV, against Ong Teng.
G.R. No. 77649 August 7, 1989
In their respective answers, the six (6) private respondents
CETUS DEVELOPMENT, INC., petitioner, interposed a common defense. They claimed that since the
vs. occupancy of the premises they paid their monthly rental regularly
COURT OF APPEALS and JOSE LIWANAG, respondents. through a collector of the lessor; that their non-payment of the
rentals for the months of July, August and September, 1984, was
G.R. No. 77650 August 7, 1989 due to the failure of the petitioner (as the new owner) to send its
collector; that they were at a loss as to where they should pay
CETUS DEVELOPMENT, INC., petitioner, their rentals; that sometime later, one of the respondents called
vs. the office of the petitioner to inquire as to where they would make
COURT OF APPEALS and LEANDRO CANLAS, respondents. such payments and he was told that a collector would be sent to
receive the same; that no collector was ever sent by the petitioner;
G.R. No. 77651 August 7, 1989 and that instead they received a uniform demand letter dated
October 9, 1984.
CETUS DEVELOPMENT, INC., petitioner,
vs. The private respondents, thru counsel, later filed a motion for
COURT OF APPEALS and VICTORIA SUDARIO respondents. consolidation of the six cases and as a result thereof, the said
cases were consolidated in the Metropolitan Trial Court of Manila,
G.R. No.77652 August 7, 1989 Branch XII, presided over by Judge Eduardo S. Quintos, Jr. On
June 4, 1985, the trial court rendered its decision dismissing the
CETUS DEVELOPMENT, INC., petitioner, six cases, a pertinent portion of which reads, as follows:
vs.
COURT OF APPEALS and FLORA NAGBUYA respondents. The records of this case show that at the time of the filing of this
complaint, the rentals had all been paid. Hence, the plaintiff
cannot eject the defendants from the leased premises, because
MEDIALDEA, J.: at the time these cases were instituted, there are no rentals in
arrears.
This is a petition for review on certiorari of the decision dated
January 30, 1987 of the Court of Appeals in CA-GR Nos. SP- The acceptance of the back rental by the plaintiff before the filing
07945-50 entitled, "Cetus Development, Inc., Petitioner vs. Hon. of the complaint, as in these case, the alleged rental arrearages
Conrado T. Limcaoco, Presiding Judge, Regional Trial Court of were paid immediately after receipt of the demand letter, removes
Manila, Branch Ederlina Navalta, et. al., respondents. its cause of action in an unlawful detainer case, even if the
acceptance was without prejudice.
The following facts appear in the records:
x x x.
The private respondents, Ederlina Navalta, Ong Teng, Jose
Liwanag, Leandro Canlas, Victoria Sudario, and Flora Nagbuya Furthermore, the court has observed that the account involved
were the lessees of the premises located at No. 512 Quezon which constitutes the rentals of the tenants are relatively small to
Boulevard, Quiapo, Manila, originally owned by the Susana which the ejectment may not lie on grounds of equity and for
Realty. These individual verbal leases were on a month-to month humanitarian reasons.
basis at the following rates: Ederlina Navalta at the rate of P80.50;
Ong Teng at the rate of P96.10; Jose Liwanag at the rate of Defendants' counterclaim for litigation expenses has no legal and
P40.35; Leandro Canlas at the rate of P80.55; Victoria Sudario at factual basis for assessing the same against plaintiff.
the rate of P50.45 and Flora Nagbuya at the rate of P80.55. The
payments of the rentals were paid by the lessees to a collector of WHEREFORE, judgment is hereby rendered dismissing these
the Susana Realty who went to the premises monthly. cases, without pronouncement as to costs.

Sometime in March, 1984, the Susana Realty sold the leased Defendants' counterclaim is likewise dismissed.
premises to the petitioner, Cetus Development, Inc., a corporation
duly organized and existing under the laws of the Philippines. SO ORDERED. (pp. 32-33, Rollo, G.R. No. 77647)
From April to June, 1984, the private respondents continued to
pay their monthly rentals to a collector sent by the petitioner. In Not satisfied with the decision of the Metropolitan Trial Court, the
the succeeding months of July, August and September 1984, the petitioner appealed to the Regional Trial Court of Manila and the
respondents failed to pay their monthly individual rentals as no same was assigned to Branch IX thereof presided over by Judge
collector came. Conrado T. Limcaoco (now Associate Justice of the Court of
OBLICON 1-9-2018 I ACJUCO 14

Appeals).lâwphî1.ñèt In its decision dated November 19, 1985, the rent due if the tenant fails to comply with the said demand with
the Regional Trial Court dismissed the appeal for lack of merit. the period provided, his possession becomes unlawful and the
landlord may then bring the action for ejectment. (p. 28, , G.R. No.
In due time, a petition for review of the decision of the Regional 77647)
Trial Court was filed by the petitioner with the Court of Appeals.
Said petition was dismissed on January 30, 1987, for lack of merit. We hold that the demand required and contemplated in Section
2, aforequoted, is a jurisdictional requirement for the purpose of
Aggrieved by the decision of the Court of Appeals, petitioner now bringing an unlawful detainer suit for failure to pay rent or comply
comes to Us in this petition, assigning the following errors: with the conditions of lease. It partakes of an extrajudicial remedy
that must be pursued before resorting for judicial action so much
ASSIGNMENT OF ERRORS so that when there is full compliance with the demand, there
arises no necessity for court action.
I
As to whether this demand is merely a demand to pay rent or
RESPONDENT COURT OF APPEALS COMMITTED A GRAVE comply with the conditions of the lease or also a demand to
ABUSE OF DISCRETION, AMOUNTING TO LACK OF vacate, the answer can be gleaned from said Section 2. This
JURISDICTION, WHEN IT ERRED IN HOLDING THAT THE section presupposes the existence of a cause of action for
CAUSE OF ACTION FOR UNLAWFUL DETAINER IN THESE unlawful detainer as it speaks of "failure to pay rent due or comply
CASES DID NOT EXIST WHEN THE COMPLAINTS WERE with the conditions of the lease." The existence of said cause of
FILED BECAUSE PRIVATE RESPONDENTS TENDERED, AND action gives the lessor the right under Article 1659 of the New Civil
PETITIONER ACCEPTED, THE PAYMENT OF THE THREE (3) Code to ask for the rescission of the contract of lease and
MONTHS RENTAL IN ARREARS WITHIN THE FIFTEEN (15) indemnification for damages, or only the latter, allowing the
DAY PERIOD FROM PRIVATE RESPONDENTS' RECEIPT OF contract to remain in force. Accordingly, if the option chosen is for
PETITIONER'S DEMAND LETTERS TO VACATE THE specific performance, then the demand referred to is obviously to
SUBJECT PREMISES AND TO PAY THE RENTALS IN pay rent or to comply with the conditions of the lease violated.
ARREARS. However, if rescission is the option chosen, the demand must be
for the lessee to pay rents or to comply with the conditions of the
II lease and to vacate. Accordingly, the rule that has been followed
in our jurisprudence where rescission is clearly the option taken,
RESPONDENT COURT OF APPEALS COMMITTED A is that both demands to pay rent and to vacate are necessary to
GRAVEABUSE OF DISCRETION, AMOUNTING TO LACK OF make a lessee a deforciant in order that an ejectment suit may be
JURISDICTION COMMITTED A GRAVE WHEN IT ERRED IN filed (Casilan et al. vs. Tomassi, L-16574, February 28,1964, 10
AFFIRMING THE DISMISSAL OF THE COMPLAINTS IN THESE SCRA 261; Rickards vs. Gonzales, 109 Phil. 423, Dikit vs.
CASES NOTWITHSTANDING THE EXISTENCE OF VALID Icasiano, 89 Phil. 44).lâwphî1.ñèt
GROUNDS FOR THE JUDICIAL EJECTMENT OF PRIVATE
RESPONDENT. Thus, for the purpose of bringing an ejectment suit, two requisites
must concur, namely: (1) there must be failure to pay rent or
III comply with the conditions of the lease and (2) there must be
demand both to pay or to comply and vacate within the periods
RESPONDENT COURT OF APPEALS COMMITTED A GRAVE specified in Section 2, Rule 70, namely 15 days in case of lands
ABUSE OF DISCRETION, AMOUNTING TO LACK OF and 5 days in case of buildings. The first requisite refers to the
JURISDICTION, WHEN IT ERRED IN HOLDING THAT THESE existence of the cause of action for unlawful detainer while the
CASES ARE CLASSIC EXAMPLES TO CIRCUMVENT THE second refers to the jurisdictional requirement of demand in order
RENT CONTROL LAW. (pp. 164-165, Rollo, G.R. No. 77647) that said cause of action may be pursued.

The Court of Appeals defined the basic issue in this case as It is very clear that in the case at bar, no cause of action for
follows: whether or not there exists a cause of action when the ejectment has accrued. There was no failure yet on the part of
complaints for unlawful detainer were filed considering the fact private respondents to pay rents for three consecutive months. As
that upon demand by petitioner from private respondents for the terms of the individual verbal leases which were on a month-
payment of their back rentals, the latter immediately tendered to-month basis were not alleged and proved, the general rule on
payment which was accepted by petitioner. necessity of demand applies, to wit: there is default in the
fulfillment of an obligation when the creditor demands payment at
In holding that there was no cause of action, the respondent Court the maturity of the obligation or at anytime thereafter. This is
relied on Section 2, Rule 70 of the Rules of Court, which provides: explicit in Article 1169, New Civil Code which provides that
"(t)hose obliged to deliver or to do something incur in delay from
Sec. 2. Landlord to proceed against tenant only after demand. the time the obligee judicially or extrajudicially demands from
— No landlord or his legal representative or assign, shall be such them the fulfillment of their obligation." Petitioner has not shown
action against a tenant for failure to pay rent due or to comply with that its case falls on any of the following exceptions where
the conditions of his lease, unless the tenant shall have failed to demand is not required: (a) when the obligation or the law so
pay such rent or comply with such conditions for a period of fifteen declares; (b) when from the nature and circumstances of the
(15) days or five (5) days in case of building, after demand obligation it can be inferred that time is of the essence of the
therefor, made upon qqqm personally, or by serving written notice contract; and (c) when demand would be useless, as when the
of such demand upon the person found on the premises, or by obligor has rendered it beyond his power to perform.
posting such notice on the premises if no persons be found
thereon. The demand required in Article 1169 of the Civil Code may be in
any form, provided that it can be proved. The proof of this demand
It interpreted the said provision as follows: lies upon the creditor. Without such demand, oral or written, the
effects of default do not arise. This demand is different from the
.....the right to bring an action of ejectment or unlawful detainer demand required under Section 2, Rule 70, which is merely a
must be counted from the time the defendants failed to pay rent jurisdictional requirement before an existing cause of action may
after the demand therefor. It is not the failure per se to pay rent as be pursued.
agreed in the contract, but the failure to pay the rent after a
demand therefor is made, that entitles the lessor to bring an action The facts on record fail to show proof that petitioner demanded
for unlawful detainer. In other words, the demand contemplated the payment of the rentals when the obligation matured. Coupled
by the above-quoted provision is not a demand to vacate, but a with the fact that no collector was sent as previously done in the
demand made by the landlord upon his tenant for the latter to pay past, the private respondents cannot be held guilty of mora
OBLICON 1-9-2018 I ACJUCO 15

solvendi or delay in the payment of rentals. Thus, when petitioner


first demanded the payment of the 3-month arrearages and
private respondents lost no time in making tender and payment,
which petitioner accepted, no cause of action for ejectment
accrued. Hence, its demand to vacate was premature as it was
an exercise of a non-existing right to rescind.

In contradistinction, where the right of rescission exists, payment


of the arrearages in rental after the demand to pay and to vacate
under Section 2, Rule 70 does not extinguish the cause of action
for ejectment as the lessor is not only entitled to recover the
unpaid rents but also to eject the lessee.

Petitioner correctly argues that acceptance of tendered payment


does not constitute a waiver of the cause of action for ejectment
especially when accepted with the written condition that it was
"without prejudice to the filing of an ejectment suit". Indeed, it is
illogical or ridiculous not to accept the tender of payment of rentals
merely to preserve the right to file an action for unlawful detainer.
However, this line of argument presupposes that a cause of action
for ejectment has already accrued, which is not true in the instant
case.

Petitioner likewise claims that its failure to send a collector to


collect the rentals cannot be considered a valid defense for the
reason that sending a collector is not one of the obligations of the
lessor under Article 1654. While it is true that a lessor is not
obligated to send a collector, it has been duly established that it
has been customary for private respondents to pay the rentals
through a collector. Besides Article 1257, New Civil Code
provides that where no agreement has been designated for the
payment of the rentals, the place of payment is at the domicile of
the defendants. Hence, it could not be said that they were in
default in the payment of their rentals as the delay in paying the
same was not imputable to them. Rather, it was attributable to
petitioner's omission or neglect to collect.

Petitioner also argues that neither is its refused to accept the


rentals a defense for non-payment as Article 1256 provides that
"[i]f the creditor to whom the tender of payment has been made
refuses without just cause to accept it, the debtor shall be
released from responsibility by the consignation of the thing due."
It bears emphasis that in this case there was no unjustified refusal
on the part of petitioner or non-acceptance without reason that
would constitute mora accipiendi and warrant consignation. There
was simply lack of demand for payment of the rentals.

In sum, We hold that respondent Court of Appeals did not commit


grave abuse of discretion amounting to lack of jurisdiction in its
conclusion affirming the trial court's decision dismissing
petitioner's complaint for lack of cause of action. We do not agree,
however, with the reasons relied upon.

ACCORDINGLY, the petition for review on certiorari is hereby


DENIED for lack of merit and the decision dated January 30, 1987
of respondent Court of Appeals is hereby AFFIRMED.

SO ORDERED.
OBLICON 1-9-2018 I ACJUCO 16

G.R. No. 108129 September 23, 1999


PCIB selling rate at the time of payment at least five (5) days prior
AEROSPACE CHEMICAL INDUSTRIES, INC., petitioner,
vs. to shipment date.
COURT OF APPEALS, PHILIPPINE PHOSPHATE
FERTILIZER, CORP., respondents. F. Shipping Conditions

QUISUMBING, J.: 1. Laycan : July

This petition for review assails the Decision 1 dated August 19, 2. Load port: Cotcot, Basay, Negros Or. and
1992, of the Court of Appeals, which set aside the judgment of the
Regional Trial Court of Pasig, Branch 151. The case stemmed Atlas Pier, Sangi, Cebu
from a complaint filed by the buyer (herein petitioner) against the
seller (private respondent) for alleged breach of contract. xxx xxx xxx
Although petitioner prevailed in the trial court, the appellate court
reversed and instead found petitioner guilty of delay and therefore 11. Other terms and Conditions: To be mutually agreed
liable for damages, as follows: upon.

WHEREFORE, the Decision of the court a quo is SET ASIDE and Very truly yours,
a new one rendered, dismissing the complaint with costs against
the plaintiff (herein petitioner) and, on the counterclaim, ordering Philippine Phosphate Fertilizer Corp.
the plaintiff Aerospace Chemical Industries, Inc. to pay the
defendant, Philippine Phosphate Fertilizer Corporation the sum of Signed: Herman J. Rustia
P324,516.63 representing the balance of the maintenance cost
and tank rental charges incurred by the defendant for the failure Sr. Manager, Materials & Logistics
of the plaintiff to haul the rest of the rest of the sulfuric acid on the
designated date. CONFORME:

Costs against plaintiff-appellee. 2 AEROSPACE INDUSTRIES, INC.

As gleaned from the records, the following are the antecedents: Signed: Mr. Melecio Hernandez

On June 27, 1986, petitioner Aerospace Industries, Inc. Manager


(Aerospace) purchased five hundred (500) metric tons of sulfuric
acid from private respondent Philippine Phosphate Fertilizer Initially set beginning July 1986, the agreement provided that the
Corporation (Philphos). The contract 3 was in letter-form as buyer shall pay its purchases in equivalent Philippine currency
follows: value, five days prior to the shipment date. Petitioner as buyer
committed to secure the means of transport to pick-up the
27 June 1986 purchases from private respondent's loadports. Per agreement,
one hundred metric tons (100 MT) of sulfuric acid should be taken
AEROSPACE INDUSTRIES INC. from Basay, Negros Oriental storage tank, while the remaining
four hundred metric tons (400 MT) should be retrieved from Sangi,
203 E. Fernandez St. Cebu.

San Juan, Metro Manila On August 6, 1986, private respondent sent an advisory letter 4
to petitioner to withdraw the sulfuric acid purchased at Basay
Attention:Mr. Melecio Hernandez because private respondent had been incurring incremental
expense of two thousand (P2,000.00) pesos for each day of delay
Manager in shipment.

Subject : Sulfuric Acid Shipment On October 3, 1986, petitioner paid five hundred fifty-three
thousand, two hundred eighty (P553,280.00) pesos for 500 MT of
Gentlemen: sulfuric acid.

This is to confirm our agreement to supply your Sulfuric Acid On November 19, 1986, petitioner chartered M/T Sultan
requirement under the following terms and conditions: Kayumanggi, owned by Ace Bulk Head Services. The vessel was
assigned to carry the agreed volumes of freight from designated
A. Commodity : Sulfuric Acid in Bulk loading areas. M/T Kayumanggi withdrew only 70.009 MT of
sulfuric acid from Basay because said vessel heavily tilted on its
B. Concentration : 98-99% H2SO4 port side. Consequently, the master of the ship stopped further
loading. Thereafter, the vessel underwent repairs.
C. Quantity : 500 MT-100 MT Ex-Basay
In a demand letter 5 dated December 12, 1986, private
400 MT Ex-Sangi respondent asked petitioner to retrieve the remaining sulfuric acid
in Basay tanks so that said tanks could be emptied on or before
D. Price : US$ 50.00/MT-FOB Cotcot, December 15, 1986. Private respondent said that it would charge
petitioner the storage and consequential costs for the Basay
Basay, Negros Or. tanks, including all other incremental expenses due to loading
delay, if petitioner failed to comply.
US$ 54.00/MT-FOB Sangi, Cebu
On December 18, 1986, M/T Sultan Kayumanggi docked at
E. Payment : Cash in Philippine currency Sangi, Cebu, but withdrew only 157.51 MT of sulfuric acid. Again,
the vessel tilted. Further loading was aborted. Two survey reports
payable to Philippine Phosphate conducted by the Societe Generale de Surveillance (SGS) Far
East Limited, dated December 17, 1986 and January 2, 1987,
Fertilizer Corp. (MAKATI) at attested to these occurrences.
OBLICON 1-9-2018 I ACJUCO 17

Later, on a date not specified in the record, M/T Sultan Subject: Sulfuric Acid Ex-Isabel
Kayumanggi sank with a total of 227.51 MT of sulfuric acid on
board.1âwphi1.nêt Gentlemen:

Petitioner chartered another vessel, M/T Don Victor, with a Confirming earlier telcon with our Mr. G.B. Belen, we regret to
capacity of approximately 500 MT. 6 On January 26 and March inform you that we cannot accommodate your request to lift
20, 1987, Melecio Hernandez, acting for the petitioner, addressed Sulfuric Acid ex-Isabel due to Pyrite limitation and delayed arrival
letters to private respondent, concerning additional orders of of imported Sulfuric Acid from Japan. 14
sulfuric acid to replace its sunken purchases, which letters are
hereunder excerpted: On July 25, 1988, petitioner's counsel wrote to private respondent
another demand letter for the delivery of the purchases remaining,
January 26, 1987 or suffer tedious legal action his client would commence.

xxx xxx xxx On May 4, 1989, petitioner filed a complaint for specific
performance and/or damages before the Regional Trial Court of
We recently charter another vessel M/T DON VICTOR who will Pasig, Branch 151. Private respondent filed its answer with
be authorized by us to lift the balance approximately 272.49 MT. counterclaim, stating that it was the petitioner who was remiss in
the performance of its obligation in arranging the shipping
We request your goodselves to grant us for another Purchase requirements of its purchases and, as a consequence, should pay
Order with quantity of 227.51 MT and we are willing to pay the damages as computed below:
additional order at the prevailing market price, provided the lifting
of the total 500 MT be centered/confined to only one safe berth Advanced Payment by Aerospace (Oct. 3, 1986)
which is Atlas Pier, Sangi, Cebu. 7 P553,280.00

March 20, 1987 Less Shipments

This refers to the remaining balance of the above product quantity 70.009 MT sulfuric acid P72,830.36
which were not loaded to the authorized cargo vessel, M/T Sultan
Kayumanggi at your load port — Sangi, Toledo City. 151.51 MT sulfuric acid 176,966.27 (249,796.63)

Please be advised that we will be getting the above product —————— ——————
quantity within the month of April 1987 and we are arranging for
a 500 MT Sulfuric Acid inclusive of which the remaining balance: Balance P303,483.37
272.49 MT an additional product quantity thereof of 227.51 MT. 8
Less Charges
Petitioner's letter 9 dated May 15, 1987, reiterated the same
request to private respondent. Basay Maintenance Expense

On January 25, 1988, petitioner's counsel, Atty. Pedro T. Santos, from Aug. 15 to Dec. 15, 1986
Jr., sent a demand letter 10 to private respondent for the delivery
of the 272.49 MT of sulfuric acid paid by his client, or the return of (P2,000.00/day x 122 days) P244,000.00
the purchase price of three hundred seven thousand five hundred
thirty (P307,530.00) pesos. Private respondent in reply, 11 on Sangi — Tank Rental
March 8, 1988, instructed petitioner to lift the remaining 30 MT of
sulfuric acid from Basay, or pay maintenance and storage from Aug. 15, 1986 to Aug. 15, 1987
expenses commencing August 1, 1986.
(P32,000.00/mo. x 12 mos.) 384,000.00 (628,000.00)
On July 6, 1988, petitioner wrote another letter, insisting on
picking up its purchases consisting of 272.49 MT and an —————— ——————
additional of 227.51 MT of sulfuric acid. According to petitioner it
had paid the chartered vessel for the full capacity of 500 MT, Receivable/Counterclaim (P324,516.63)
stating that:
===========
With regard to our balance of sulfuric acid — product at your shore
tank/plant for 272.49 metric ton that was left by M/T Sultana Trial ensued and after due proceedings, judgment was rendered
Kayumanggi due to her sinking, we request for an additional by the trial court in petitioner's favor, disposing as follows:
quantity of 227.51 metric ton of sulfuric acid, 98% concentration.
WHEREFORE, judgment is hereby rendered in favor of plaintiff
The additional quantity is requested in order to complete the and against defendant, directing the latter to pay the former the
shipment, as the chartered vessel schedule to lift the high grade following sums:
sulfuric acid product is contracted for her full capacity/load which
is 500 metric tons more or less. 1. P306,060.77 — representing the value of the
undelivered 272.49 metric tons of sulfuric acid plaintiff paid to
We are willing to pay the additional quantity — 227.51 metric tons defendant;
high grade sulfuric acid in the prevailing price of the said product.
12 2. P91,818.23 — representing unrealized profits, both
items with 12% interest per annum from May 4, 1989, when the
xxx xxx xxx complaint was filed until fully paid;

By telephone, petitioner requested private respondent's Shipping 3. P30,000.00 — as exemplary damages; and
Manager, Gil Belen, to get its additional order of 227.51 MT of
sulfuric acid at Isabel, Leyte. 13 Belen relayed the information to 4. P30,000.00 — as attorney's fees and litigation
his associate, Herman Rustia, the Senior Manager for Imports expenses, both last items also with 12% interest per annum from
and International Sales of private respondent. In a letter dated date hereof until fully paid.
July 22, 1988, Rustia replied:
OBLICON 1-9-2018 I ACJUCO 18

Defendant's counterclaims are hereby dismissed for lack of merit. RESPONDENT COURT OF APPEALS ERRED IN NOT
HOLDING PRIVATE RESPONDENT TO HAVE COMMITTED A
Costs against defendant. 15 BREACH OF CONTRACT WHEN IT IS NOT DISPUTED THAT
PETITIONER PAID IN FULL THE VALUE OF 500 MT OF
In finding for the petitioner, the trial court held that the petitioner SULFURIC ACID TO PRIVATE RESPONDENT BUT THE
was absolved in its obligation to pick-up the remaining sulfuric LATTER WAS ABLE TO DELIVER TO PETITIONER ONLY
acid because its failure was due to force majeure. According to 227.51 M.T.
the trial court, it was private respondent who committed a breach
of contract when it failed to accommodate the additional order of II.
the petitioner, to replace those that sank in the sea, thus:
RESPONDENT COURT OF APPEALS GRAVELY ERRED IN
To begin with, even if we assume that it is incumbent upon the HOLDING PETITIONER LIABLE FOR DAMAGES TO PRIVATE
plaintiff to "lift" the sulfuric acid it ordered from defendant, the fact RESPONDENT ON THE BASIS OF A XEROX COPY OF AN
that force majeure intervened when the vessel which was ALLEGED AGREEMENT TO HOLD PETITIONER LIABLE FOR
previouly (sic) listing, but which the parties, including a DAMAGES FOR THE DELAY WHEN PRIVATE RESPONDENT
representative of the defendant, did not mind, sunk, has the effect FAILED TO PRODUCE THE ORIGINAL IN CONTRAVENTION
of absolving plaintiff from "lifting" the sulfuric acid at the OF THE RULES ON EVIDENCE.
designated load port. But even assuming the plaintiff cannot be
held entirely blameless, the allegation that plaintiff agreed to a III.
payment of a 2,000-peso incremental expenses per day to
defendant for delayed "lifting has not been proven." . . . RESPONDENT COURT OF APPEALS ERRED IN FAILING TO
CONSIDER THE UNDISPUTED FACTS THAT PETITIONER'S
Also, if it were true that plaintiff is indebted to defendant, why did PAYMENT FOR THE GOODS WAS RECEIVED BY PRIVATE
defendant accept a second additional order after the transaction RESPONDENT WITHOUT ANY QUALIFICATION AND THAT
in litigation? Why also, did defendant not send plaintiff statements PRIVATE RESPONDENT ENTERED INTO ANOTHER
of account until after 3 years? CONTRACT TO SUPPLY PETITIONER 227.519 MT OF
SULFURIC ACID IN ADDITION TO THE UNDELIVERED
All these convince the Court that indeed, defendant must return BALANCE AS PROOF THAT ANY DELAY OF PETITIONER
what plaintiff has paid it for the goods which the latter did not WAS DEEMED WAIVED BY SAID ACTS OF RESPONDENT.
actually receive. 16
IV.
On appeal by private respondent, the Court of Appeals reversed
the decision of the trial court, as follows: RESPONDENT COURT OF APPEALS ERRED IN NOT
CONSIDERING THE LAW THAT WHEN THE SALE INVOLVES
Based on the facts of this case as hereinabove set forth, it is clear FUNGIBLE GOODS AS IN THIS CASE THE EXPENSES FOR
that the plaintiff had the obligation to withdraw the full amount of STORAGE AND MAINTENANCE ARE FOR THE ACCOUNT OF
500 MT of sulfuric acid from the defendant's loadport at Basay THE SELLER (ARTICLE 1504 CIVIL CODE).
and Sangi on or before August 15, 1986. As early as August 6,
1986 it had been accordingly warned by the defendant that any V.
delay in the hauling of the commodity would mean expenses on
the part of the defendant amounting to P2,000.00 a day. The RESPONDENT COURT OF APPEALS ERRED IN FAILING TO
plaintiff sent its vessel, the "M/T Sultan Kayumanggi", only on RENDER JUDGMENT FOR PETITIONER AFFIRMING THE
November 19, 1987. The vessel, however; was not capable of DECISION OF THE TRIAL COURT.
loading the entire 500 MT and in fact, with its load of only 227.519
MT, it sank. From the assigned errors, we synthesize the pertinent issues
raised by the petitioner as follows:
Contrary to the position of the trial court, the sinking of the "M/T
Sultan Kayumanggi" did not absolve the plaintiff from its obligation 1. Did the respondent court err in holding that the petitioner
to lift the rest of the 272.481 MT of sulfuric acid at the agreed time. committed breach of contract, considering that:
It was the plaintiff's duty to charter another vessel for the purpose.
It did contract for the services of a new vessel, the "M/T Don a) the petitioner allegedly paid the full value of its
Victor", but did not want to lift the balance of 272.481 MT only but purchases, yet received only a portion of said purchases?
insisted that its additional order of 227.51 MT be also given by the
defendant to complete 500 MT. apparently so that the vessel may b) petitioner and private respondent allegedly had also
be availed of in its full capacity. agreed for the purchase and supply of an additional 227.519 MT
of sulfuric acid, hence prior delay, if any, had been waived?
xxx xxx xxx
2. Did the respondent court err in awarding damages to
We find no basis for the decision of the trial court to make the private respondent?
defendant liable to the plaintiff not only for the cost of the sulfuric
acid, which the plaintiff itself failed to haul, but also for unrealized 3. Should expenses for the storage and preservation of the
profits as well as exemplary damages and attorney's fees. 17 purchased fungible goods, namely sulfuric acid, be on seller's
account pursuant to Article 1504 of the Civil Code?
Respondent Court of Appeals found the petitioner guilty of delay
and negligence in the performance of its obligation. It dismissed To resolve these issues, petitioner urges us to review factual
the complaint of petitioner and ordered it to pay damages findings of respondent court and its conclusion that the petitioner
representing the counterclaim of private respondent. was guilty of delay in the performance of its obligation. According
to petitioner, that conclusion is contrary to the factual evidence. It
The motion for reconsideration filed by petitioner was denied by adds that respondent court disregarded the rule that findings of
respondent court in its Resolution dated December 21, 1992, for the trial court are given weight, with the highest degree of respect.
lack of merit. Claiming that respondent court's findings conflict with those of the
trial court, petitioner prays that the trial court's findings be upheld
Petitioner now comes before us, assigning the following errors: over those of the appellate court.

I. Petitioner argues that it paid the purchase price of sulfuric acid,


five (5) days prior to the withdrawal thereof, or on October 3, 1986,
OBLICON 1-9-2018 I ACJUCO 19

hence, it had complied with the primary condition set in the sales
contract. Petitioner claims its failure to pick-up the remaining A. Fair, sir. 21
purchases on time was due to a storm, a force majeure, which
sank the vessel. It thus claims exemption from liability to pay Since the third party surveyor was neither petitioner's nor private
damages. Petitioner also contends that it was actually the private respondent's employee, his professional report should carry more
respondent's shipping officer, who advised petitioner to buy the weight than that of Melecio Hernandez, an employee of petitioner.
additional 227.51 MT of sulfuric acid, so as to fully utilize the Petitioner, as the buyer, was obligated under the contract to
capacity of the vessel it chartered. Petitioner insists that when its undertake the shipping requirements of the cargo from the private
ship was ready to pick-up the remaining balance of 272.49 MT of respondent's loadports to the petitioner's designated warehouse.
sulfuric acid, private respondent could not comply with the It was petitioner which chartered M/T Sultan Kayumanggi. The
contract commitment due to "pyrite limitation." vessel was petitioner's agent. When it failed to comply with the
necessary loading conditions of sulfuric acid, it was incumbent
While we agree with petitioner that when the findings of the Court upon petitioner to immediately replace M/T Sultan Kayumanggi
of Appeals are contrary to those of the trial court, 18 this Court with another seaworthy vessel. However, despite repeated
may review those findings, we find the appellate court's demands, petitioner did not comply seasonably.
conclusion that petitioner violated the subject contract amply
supported by preponderant evidence. Petitioner's claim was Additionally, petitioner claims that private respondent's employee,
predicated merely on the allegations of its employee, Melecio Gil Belen, had recommended to petitioner to fully utilize the
Hernandez, that the storm or force majeure caused the vessel, hence petitioner's request for additional order to complete
petitioner's delay and failure to lift the cargo of sulfuric acid at the the vessel's 500 MT capacity. This claim has no probative
designated loadports. In contrast, the appellate court discounted pertinence nor solid basis. A party who asserts that a contract of
Hernandez' assertions. For on record, the storm was not the sale has been changed or modified has the burden of proving the
proximate cause of petitioner's failure to transport its purchases change or modification by clear and convincing evidence. 22
on time. The survey report submitted by a third party surveyor, Repeated requests and additional orders were contained in
SGS Far East Limited, revealed that the vessel, which was petitioner's letters to private respondent. In contrast, Belen's
unstable, was incapable of carrying the full load of sulfuric acid. alleged action was only verbal; it was not substantiated at all
Note that there was a premature termination of loading in Basay, during the trial. Note that, using the vessel to full capacity could
Negros Oriental. The vessel had to undergo several repairs redound to petitioner's advantage, not the other party's. If
before continuing its voyage to pick-up the balance of cargo at additional orders were at the instance of private respondent, the
Sangi, Cebu. Despite repairs, the vessel still failed to carry the same must be properly proved together with its relevance to the
whole lot of 500 MT of sulfuric acid due to ship defects like listing question of delay. Settled is the principle in law that proof of verbal
to one side. Its unfortunate sinking was not due to force majeure. agreements offered to vary the terms of written agreements is
It sunk because it was, based on SGS survey report, unstable and inadmissible, under the parol evidence rule. 23 Belen's purported
unseaworthy. recommendation could not be taken at face value and, obviously,
cannot excuse petitioner's default.
Witness surveyor Eugenio Rabe's incident report, dated
December 13, 1986 in Basay, Negros Oriental, elucidated this Respondent court found petitioner's default unjustified, and on
point: this conclusion we agree:

Loading was started at 1500hrs. November 19. At 1600Hrs. It is not true that the defendant was not in a position to deliver the
November 20, loading operation was temporarily stopped by the 272.481 MT which was the balance of the original 500 MT
vessel's master due to ships stability was heavily tilted to port purchased by the plaintiff. The whole lot of 500 MT was ready for
side, ship's had tried to transfer the loaded acid to stbdside but lifting as early as August 15, 1986. What the defendant could not
failed to do so, due to their auxiliary pump on board does not work sell to the plaintiff was the additional 227.51 MT which said
out for acid. plaintiff was ordering, for the reason that the defendant was short
of the supply needed. The defendant, however, had no obligation
xxx xxx xxx to agree to this additional order and may not be faulted for its
inability to meet the said additional requirements of the plaintiff.
Note. Attending surveyor arrived BMC Basay on November And the defendant's incapacity to agree to the delivery of another
22, due to delayed advice of said vessel Declared quantity loaded 227.51 MT is not a legal justification for the plaintiffs refusal to lift
onboard based on data's provided by PHILPHOS representative. the remaining 272.481.

On November 26, two representative of shipping company arrived It is clear from the plaintiff's letters to the defendant that it wanted
Basay to assist the situation, at 1300Hrs repairing and/or welding to send the "M/T Don Victor" only if the defendant would confirm
of tank number 5 started at 1000Hrs November 27, repairing that it was ready to deliver 500 MT. Because the defendant could
and/or welding was suspended due to the explosion of tank no. 5. not sell another 227.51 MT to the plaintiff, the latter did not send
Explosion ripped about two feet of the double bottom tank. a new vessel to pick up the balance of the 500 MT originally
contracted for by the parties. This, inspite the representations
November 27 up to date no progress of said vessel. 19 made by the defendant for the hauling thereof as scheduled and
its reminders that any expenses for the delay would be for the
While at Sangi, Cebu, the vessel's condition (listing) did not account of the plaintiff. 24
improve as the survey report therein noted:
We are therefore constrained to declare that the respondent court
Declared quantity loaded on board was based on shore tank did not err when it absolved private respondent from any breach
withdrawal due to ship's incomplete tank calibration table. Barge of contract.
displacement cannot be applied due to ship was listing to Stboard
side which has been loaded with rocks to control her stability. 20 Our next inquiry is whether damages have been properly awarded
against petitioner for its unjustified delay in the performance of its
These two vital pieces of information were totally ignored by trial obligation under the contract. Where there has been breach of
court. The appellate court correctly took these into account, contract by the buyer, the seller has a right of action for damages.
significantly. As to the weather condition in Basay, the appellate Following this rule, a cause of action of the seller for damages
court accepted surveyor Rabe's testimony, thus: may arise where the buyer refuses to remove the goods, such that
buyer has to remove them. 25 Article 1170 of the Civil Code
Q. Now, Mr. Witness, what was the weather condition then provides:
at Basay, Negros Oriental during the loading operation of sulfuric
acid on board the Sultana Kayumanggi?
OBLICON 1-9-2018 I ACJUCO 20

Those who in the performance of their obligations are guilty of petitioner's sulfuric acid. It stands to reason that petitioner should
fraud, negligence, or delay and those who in any manner reimburse private respondent's rental expenses of P32,000
contravene the tenor thereof, are liable for damages. monthly, commencing December 15, 1986, up to August 31,
1987, the period of the extended lease. Note further that there is
Delay begins from the time the obligee judicially or extrajudicially nothing on record refuting the amount of expenses abovecited.
demands from the obligor the performance of the obligation. 26 Private respondent presented in court two supporting documents:
Art. 1169 states: first, the lease agreement pertaining to the equipment, and
second a letter dated June 15, 1987, sent by Atlas Fertilizer
Art. 1169. Those obliged to deliver or to do something Corporation to private respondent representing the rental charges
incur in delay from the time the obligee judicially or extrajudicially incurred. Private respondent is entitled to recover the payment for
demands from them the fulfillment of their obligation. these charges. It should be reimbursed the amount of two
hundred seventy two thousand
In order that the debtor may be in default, it is necessary that the (P272,000.00) 29 pesos, corresponding to the total amount of
following requisites be present: (1) that the obligation be rentals from December 15, 1986 to August 31, 1987 of the Sangi,
demandable and already liquidated; (2) that the debtor delays Cebu storage tank.
performance; and (3) that the creditor requires the performance
judicially or extrajudicially. 27 Finally, we note also that petitioner tries to exempt itself from
paying rental expenses and other damages by arguing that
In the present case, private respondent required petitioner to ship expenses for the preservation of fungible goods must be assumed
out or lift the sulfuric acid as agreed, otherwise petitioner would by the seller. Rental expenses of storing sulfuric acid should be
be charged for the consequential damages owing to any delay. at private respondent's account until ownership is transferred,
As stated in private respondent's letter to petitioner, dated according to petitioner. However, the general rule that before
December 12, 1986: delivery, the risk of loss is borne by the seller who is still the
owner, is not applicable in this case because petitioner had
Subject: M/T "KAYUMANGGI" incurred delay in the performance of its obligation. Article 1504 of
the Civil Code clearly states:
Gentlemen:
Unless otherwise agreed, the goods remain at the seller's risk
This is to reiterate our telephone advice and our letter HJR-8612- until the ownership therein is transferred to the buyer, but when
031 dated 2 December 1986 regarding your sulfuric acid vessel, the ownership therein is transferred to the buyer the goods are at
M/T "KAYUMANGGI". the buyer's risk whether actual delivery has been made or not,
except that:
As we have, in various instances, advised you, our Basay wharf
will have to be vacated 15th December 1986 as we are expecting xxx xxx xxx
the arrival of our chartered vessel purportedly to haul our
equipments and all other remaining assets in Basay. This (2) Where actual delivery has been delayed through the
includes our sulfuric acid tanks. We regret, therefore, that if these fault of either the buyer or seller the goods are at the risk of the
tanks are not emptied on or before the 15th of December, we party at fault. (emphasis supplied)
either have to charge you for the tanks waiting time at Basay and
its consequential costs (i.e. chartering of another vessel for its On this score, we quote with approval the findings of the appellate
second pick-up at Basay, handling, etc.) as well as all other court, thus:
incremental costs on account of the protracted loading delay. 28
(Emphasis supplied) . . . The defendant [herein private respondent] was not remiss in
reminding the plaintiff that it would have to bear the said expenses
Indeed the above demand, which was unheeded, justifies the for failure to lift the commodity for an unreasonable length of time.
finding of delay. But when did such delay begin? The above letter
constitutes private respondent's extrajudicial demand for the But even assuming that the plaintiff did not consent to be so
petitioner to fulfill its obligation, and its dateline is significant. bound, the provisions of Civil Code come in to make it liable for
Given its date, however, we cannot sustain the finding of the the damages sought by the defendant.
respondent court that petitioner's delay started on August 6, 1986.
The Court of Appeals had relied on private respondent's earlier Art. 1170 of the Civil Code provides:
letter to petitioner of that date for computing the commencement
of delay. But as averred by petitioner, said letter of August 6th is Those who in the performance of their obligations are guilty of
not a categorical demand. What it showed was a mere statement fraud, negligence, or delay and those who in any manner
of fact, that "[F]for your information any delay in Sulfuric Acid contravene the tenor thereof, are liable for damages.
withdrawal shall cost us incremental expenses of P2,000.00 per
day." Noteworthy, private respondent accepted the full payment Certainly, the plaintiff [herein petitioner] was guilty of negligence
by petitioner for purchases on October 3, 1986, without and delay in the performance of its obligation to lift the sulfuric
qualification, long after the August 6th letter. In contrast to the acid on August 15, 1986 and had contravened the tenor of its
August 6th letter, that of December 12th was a categorical letter-contract with the defendant. 30
demand.
As pointed out earlier, petitioner is guilty of delay, after private
Records reveal that a tanker ship had to pick-up sulfuric acid in respondent made the necessary extrajudicial demand by
Basay, then proceed to get the remaining stocks in Sangi, Cebu. requiring petitioner to lift the cargo at its designated loadports.
A period of three days appears to us reasonable for a vessel to When petitioner failed to comply with its obligations under the
travel between Basay and Sangi. Logically, the computation of contract it became liable for its shortcomings. Petitioner is
damages arising from the shipping delay would then have to be indubitably liable for proven damages.
from December 15, 1986, given said reasonable period after the
December 12th letter. More important, private respondent was Considering, however, that petitioner made an advance payment
forced to vacate Basay wharf only on December 15th. Its Basay for the unlifted sulfuric acid in the amount of three hundred three
expenses incurred before December 15, 1986, were necessary thousand, four hundred eighty three pesos and thirty seven
and regular business expenses for which the petitioner should not centavos (P303,483.37), it is proper to set-off this amount against
be obliged to pay. the rental expenses initially paid by private respondent. It is worth
noting that the adjustment and allowance of private respondent's
Note that private respondent extended its lease agreement for counterclaim or set-off in the present action, rather than by
Sangi, Cebu storage tank until August 31, 1987, solely for another independent action, is encouraged by the law. Such
OBLICON 1-9-2018 I ACJUCO 21

practice serves to avoid circuitry of action, multiplicity of suits,


inconvenience, expense, and unwarranted consumption of the
court's time. 31 The trend of judicial decisions is toward a liberal
extension of the right to avail of counterclaims or set-offs. 32 The
rules on counterclaims are designed to achieve the disposition of
a whole controversy involving the conflicting claims of interested
parties at one time and in one action, provided all parties can be
brought before the court and the matter decided without
prejudicing the right of any party. 33 Set-off in this case is proper
and reasonable. It involves deducting P272,000.00 (rentals) from
P303,483.37 (advance payment), which will leave the amount of
P31,483.37 refundable to petitioner.

WHEREFORE, the petition is hereby DENIED. The assailed


decision of the Court of Appeals in CA G.R. CV No. 33802 is
AFFIRMED, with MODIFICATION that the amount of damages
awarded in favor of private respondent is REDUCED to Two
hundred seventy two thousand pesos (P272,000.00). It is also
ORDERED that said amount of damages be OFFSET against
petitioner's advance payment of Three hundred three thousand
four hundred eighty three pesos and thirty-seven centavos
(P303,483.37) representing the price of the 272.481 MT of sulfuric
acid not lifted. Lastly, it is ORDERED that the excess amount of
thirty one thousand, four hundred eighty three pesos and thirty
seven centavos (P31,483.37) be RETURNED soonest by private
respondent to herein petitioner.1âwphi1.nêt

Costs against the petitioner.

SO ORDERED.
OBLICON 1-9-2018 I ACJUCO 22

G.R. No. 153004 November 5, 2004 properties involved. For its part, petitioner SVHFI, paid P1.5
million to respondent Santos, leaving a balance of P13 million.
SANTOS VENTURA HOCORMA FOUNDATION, INC.,
petitioner, Subsequently, petitioner SVHFI sold to Development Exchange
vs. Livelihood Corporation two real properties, which were previously
ERNESTO V. SANTOS and RIVERLAND, INC., respondents. subjects of lis pendens. Discovering the disposition made by the
petitioner, respondent Santos sent a letter to the petitioner
demanding the payment of the remaining P13 million, which was
DECISION ignored by the latter. Meanwhile, on September 30, 1991, the
Regional Trial Court of Makati City, Branch 62, issued a Decision6
approving the compromise agreement.
QUISUMBING, J.:
On October 28, 1992, respondent Santos sent another letter to
Subject of the present petition for review on certiorari is the petitioner inquiring when it would pay the balance of P13 million.
Decision,1 dated January 30, 2002, as well as the April 12, 2002, There was no response from petitioner. Consequently,
Resolution2 of the Court of Appeals in CA-G.R. CV No. 55122. respondent Santos applied with the Regional Trial Court of Makati
The appellate court reversed the Decision,3 dated October 4, City, Branch 62, for the issuance of a writ of execution of its
1996, of the Regional Trial Court of Makati City, Branch 148, in compromise judgment dated September 30, 1991. The RTC
Civil Case No. 95-811, and likewise denied petitioner's Motion for granted the writ. Thus, on March 10, 1993, the Sheriff levied on
Reconsideration. the real properties of petitioner, which were formerly subjects of
the lis pendens. Petitioner, however, filed numerous motions to
The facts of this case are undisputed. block the enforcement of the said writ. The challenge of the
execution of the aforesaid compromise judgment even reached
Ernesto V. Santos and Santos Ventura Hocorma Foundation, Inc. the Supreme Court. All these efforts, however, were futile.
(SVHFI) were the plaintiff and defendant, respectively, in several
civil cases filed in different courts in the Philippines. On October On November 22, 1994, petitioner's real properties located in
26, 1990, the parties executed a Compromise Agreement4 which Mabalacat, Pampanga were auctioned. In the said auction,
amicably ended all their pending litigations. The pertinent portions Riverland, Inc. was the highest bidder for P12 million and it was
of the Agreement read as follows: issued a Certificate of Sale covering the real properties subject of
the auction sale. Subsequently, another auction sale was held on
1. Defendant Foundation shall pay Plaintiff Santos P14.5 Million February 8, 1995, for the sale of real properties of petitioner in
in the following manner: Bacolod City. Again, Riverland, Inc. was the highest bidder. The
Certificates of Sale issued for both properties provided for the
a. P1.5 Million immediately upon the execution of this agreement; right of redemption within one year from the date of registration of
the said properties.
b. The balance of P13 Million shall be paid, whether in one lump
sum or in installments, at the discretion of the Foundation, within On June 2, 1995, Santos and Riverland Inc. filed a Complaint for
a period of not more than two (2) years from the execution of this Declaratory Relief and Damages7 alleging that there was delay
agreement; provided, however, that in the event that the on the part of petitioner in paying the balance of P13 million. They
Foundation does not pay the whole or any part of such balance, further alleged that under the Compromise Agreement, the
the same shall be paid with the corresponding portion of the land obligation became due on October 26, 1992, but payment of the
or real properties subject of the aforesaid cases and previously remaining P12 million was effected only on November 22, 1994.
covered by the notices of lis pendens, under such terms and Thus, respondents prayed that petitioner be ordered to pay legal
conditions as to area, valuation, and location mutually acceptable interest on the obligation, penalty, attorney's fees and costs of
to both parties; but in no case shall the payment of such balance litigation. Furthermore, they prayed that the aforesaid sales be
be later than two (2) years from the date of this agreement; declared final and not subject to legal redemption.
otherwise, payment of any unpaid portion shall only be in the form
of land aforesaid; In its Answer,8 petitioner countered that respondents have no
cause of action against it since it had fully paid its obligation to the
2. Immediately upon the execution of this agreement (and [the] latter. It further claimed that the alleged delay in the payment of
receipt of the P1.5 Million), plaintiff Santos shall cause the the balance was due to its valid exercise of its rights to protect its
dismissal with prejudice of Civil Cases Nos. 88-743, 1413OR, TC- interests as provided under the Rules. Petitioner counterclaimed
1024, 45366 and 18166 and voluntarily withdraw the appeals in for attorney's fees and exemplary damages.
Civil Cases Nos. 4968 (C.A.-G.R. No. 26598) and 88-45366
(C.A.-G.R. No. 24304) respectively and for the immediate lifting On October 4, 1996, the trial court rendered a Decision9
of the aforesaid various notices of lis pendens on the real dismissing herein respondents' complaint and ordering them to
properties aforementioned (by signing herein attached pay attorney's fees and exemplary damages to petitioner.
corresponding documents, for such lifting); provided, however, Respondents then appealed to the Court of Appeals. The
that in the event that defendant Foundation shall sell or dispose appellate court reversed the ruling of the trial court:
of any of the lands previously subject of lis pendens, the proceeds
of any such sale, or any part thereof as may be required, shall be WHEREFORE, finding merit in the appeal, the appealed Decision
partially devoted to the payment of the Foundation's obligations is hereby REVERSED and judgment is hereby rendered ordering
under this agreement as may still be subsisting and payable at appellee SVHFI to pay appellants Santos and Riverland, Inc.: (1)
the time of any such sale or sales; legal interest on the principal amount of P13 million at the rate of
12% per annum from the date of demand on October 28, 1992 up
... to the date of actual payment of the whole obligation; and (2)
P20,000 as attorney's fees and costs of suit.
5. Failure of compliance of any of the foregoing terms and
conditions by either or both parties to this agreement shall ipso SO ORDERED.
facto and ipso jure automatically entitle the aggrieved party to a
writ of execution for the enforcement of this agreement. Hence this petition for review on certiorari where petitioner
[Emphasis supplied]5 assigns the following issues:

In compliance with the Compromise Agreement, respondent I


Santos moved for the dismissal of the aforesaid civil cases. He
also caused the lifting of the notices of lis pendens on the real
OBLICON 1-9-2018 I ACJUCO 23

WHETHER OR NOT THE COURT OF APPEALS COMMITTED should be deemed to have been included therein.17 This holds
REVERSIBLE ERROR WHEN IT AWARDED LEGAL INTEREST true even if the agreement has not been judicially approved.18
IN FAVOR OF THE RESPONDENTS, MR. SANTOS AND
RIVERLAND, INC., NOTWITHSTANDING THE FACT THAT In the case at bar, the Compromise Agreement was entered into
NEITHER IN THE COMPROMISE AGREEMENT NOR IN THE by the parties on October 26, 1990.19 It was judicially approved
COMPROMISE JUDGEMENT OF HON. JUDGE DIOKNO on September 30, 1991.20 Applying existing jurisprudence, the
PROVIDES FOR PAYMENT OF INTEREST TO THE compromise agreement as a consensual contract became
RESPONDENT binding between the parties upon its execution and not upon its
court approval. From the time a compromise is validly entered
II into, it becomes the source of the rights and obligations of the
parties thereto. The purpose of the compromise is precisely to
WHETHER OF NOT THE COURT OF APPEALS ERRED IN replace and terminate controverted claims.21
AWARDING LEGAL IN[T]EREST IN FAVOR OF THE
RESPONDENTS, MR. SANTOS AND RIVERLAND, INC., In accordance with the compromise agreement, the respondents
NOTWITHSTANDING THE FACT THAT THE OBLIGATION OF asked for the dismissal of the pending civil cases. The petitioner,
THE PETITIONER TO RESPONDENT SANTOS TO PAY A SUM on the other hand, paid the initial P1.5 million upon the execution
OF MONEY HAD BEEN CONVERTED TO AN OBLIGATION TO of the agreement. This act of the petitioner showed that it
PAY IN KIND – DELIVERY OF REAL PROPERTIES OWNED BY acknowledges that the agreement was immediately executory
THE PETITIONER – WHICH HAD BEEN FULLY PERFORMED and enforceable upon its execution.

III As to the remaining P13 million, the terms and conditions of the
compromise agreement are clear and unambiguous. It provides:
WHETHER OR NOT RESPONDENTS ARE BARRED FROM
DEMANDING PAYMENT OF INTEREST BY REASON OF THE ...
WAIVER PROVISION IN THE COMPROMISE AGREEMENT,
WHICH BECAME THE LAW AMONG THE PARTIES10 b. The balance of P13 Million shall be paid, whether in one lump
sum or in installments, at the discretion of the Foundation, within
The only issue to be resolved is whether the respondents are a period of not more than two (2) years from the execution of this
entitled to legal interest. agreement…22 [Emphasis supplied.]

Petitioner SVHFI alleges that where a compromise agreement or ...


compromise judgment does not provide for the payment of
interest, the legal interest by way of penalty on account of fault or The two-year period must be counted from October 26, 1990, the
delay shall not be due and payable, considering that the obligation date of execution of the compromise agreement, and not on the
or loan, on which the payment of legal interest could be based, judicial approval of the compromise agreement on September 30,
has been superseded by the compromise agreement.11 1991. When respondents wrote a demand letter to petitioner on
Furthermore, the petitioner argues that the respondents are October 28, 1992, the obligation was already due and
barred by res judicata from seeking legal interest on account of demandable. When the petitioner failed to pay its due obligation
the waiver clause in the duly approved compromise agreement.12 after the demand was made, it incurred delay.
Article 4 of the compromise agreement provides:
Article 1169 of the New Civil Code provides:
Plaintiff Santos waives and renounces any and all other claims
that he and his family may have on the defendant Foundation Those obliged to deliver or to do something incur in delay from
arising from and in connection with the aforesaid civil cases, and the time the obligee judicially or extrajudicially demands from
defendant Foundation, on the other hand, also waives and them the fulfillment of their obligation. [Emphasis supplied]
renounces any and all claims that it may have against plaintiff
Santos in connection with such cases.13 [Emphasis supplied.] Delay as used in this article is synonymous to default or mora
which means delay in the fulfillment of obligations. It is the non-
Lastly, petitioner alleges that since the compromise agreement fulfillment of the obligation with respect to time.23
did not provide for a period within which the obligation will become
due and demandable, it is incumbent upon respondent Santos to In order for the debtor to be in default, it is necessary that the
ask for judicial intervention for purposes of fixing the period. It is following requisites be present: (1) that the obligation be
only when a fixed period exists that the legal interests can be demandable and already liquidated; (2) that the debtor delays
computed. performance; and (3) that the creditor requires the performance
judicially or extrajudicially.24
Respondents profer that their right to damages is based on delay
in the payment of the obligation provided in the Compromise In the case at bar, the obligation was already due and
Agreement. The Compromise Agreement provides that payment demandable after the lapse of the two-year period from the
must be made within the two-year period from its execution. This execution of the contract. The two-year period ended on October
was approved by the trial court and became the law governing 26, 1992. When the respondents gave a demand letter on
their contract. Respondents posit that petitioner's failure to comply October 28, 1992, to the petitioner, the obligation was already due
entitles them to damages, by way of interest.14 and demandable. Furthermore, the obligation is liquidated
because the debtor knows precisely how much he is to pay and
The petition lacks merit. when he is to pay it.

A compromise is a contract whereby the parties, by making The second requisite is also present. Petitioner delayed in the
reciprocal concessions, avoid a litigation or put an end to one performance. It was able to fully settle its outstanding balance
already commenced.15 It is an agreement between two or more only on February 8, 1995, which is more than two years after the
persons, who, for preventing or putting an end to a lawsuit, adjust extra-judicial demand. Moreover, it filed several motions and
their difficulties by mutual consent in the manner which they agree elevated adverse resolutions to the appellate court to hinder the
on, and which everyone of them prefers in the hope of gaining, execution of a final and executory judgment, and further delay the
balanced by the danger of losing.16 fulfillment of its obligation.

The general rule is that a compromise has upon the parties the Third, the demand letter sent to the petitioner on October 28,
effect and authority of res judicata, with respect to the matter 1992, was in accordance with an extra-judicial demand
definitely stated therein, or which by implication from its terms contemplated by law.
OBLICON 1-9-2018 I ACJUCO 24

Verily, the petitioner is liable for damages for the delay in the
performance of its obligation. This is provided for in Article 117025
of the New Civil Code.

When the debtor knows the amount and period when he is to pay,
interest as damages is generally allowed as a matter of right.26
The complaining party has been deprived of funds to which he is
entitled by virtue of their compromise agreement. The goal of
compensation requires that the complainant be compensated for
the loss of use of those funds. This compensation is in the form
of interest.27 In the absence of agreement, the legal rate of
interest shall prevail.28 The legal interest for loan as forbearance
of money is 12% per annum29 to be computed from default, i.e.,
from judicial or extrajudicial demand under and subject to the
provisions of Article 1169 of the Civil Code.30

WHEREFORE, the petition is DENIED for lack of merit. The


Decision dated January 30, 2002 of the Court of Appeals and its
April 12, 2002 Resolution in CA-G.R. CV No. 55122 are
AFFIRMED. Costs against petitioner.

SO ORDERED.

Davide, Jr. C.J. (Chairman), Ynares-Santiago and Carpio, JJ.,


concur.
Azcuna, J., on leave.
OBLICON 1-9-2018 I ACJUCO 25

G.R. No. 149734 November 19, 2004


3.1.2. The true and complete list, certified by the Secretary and
DR. DANIEL VAZQUEZ and MA. LUIZA M. VAZQUEZ, Treasurer of the Company showing:
petitioners,
vs. xxx
AYALA CORPORATION, respondent.
D. A list of all persons and/or entities with whom the Company
DECISION has pending contracts, if any.

TINGA, J.: xxx

The rise in value of four lots in one of the country's prime 3.1.5. Audited financial statements of the Company as at Closing
residential developments, Ayala Alabang Village in Muntinlupa date.
City, over a period of six (6) years only, represents big money.
The huge price difference lies at the heart of the present 4. Conditions Precedent
controversy. Petitioners insist that the lots should be sold to them
at 1984 prices while respondent maintains that the prevailing All obligations of the BUYER under this Agreement are subject to
market price in 1990 should be the selling price. fulfillment prior to or at the Closing, of the following conditions:

Dr. Daniel Vazquez and Ma. Luisa Vazquez1 filed this Petition for 4.1. The representations and warranties by the SELLERS
Review on Certiorari2 dated October 11, 2001 assailing the contained in this Agreement shall be true and correct at the time
Decision3 of the Court of Appeals dated September 6, 2001 which of Closing as though such representations and warranties were
reversed the Decision4 of the Regional Trial Court (RTC) and made at such time; and
dismissed their complaint for specific performance and damages
against Ayala Corporation. xxx

Despite their disparate rulings, the RTC and the appellate court 6. Representation and Warranties by the SELLERS
agree on the following antecedents:5
The SELLERS jointly and severally represent and warrant to the
On April 23, 1981, spouses Daniel Vasquez and Ma. Luisa M. BUYER that at the time of the execution of this Agreement and at
Vasquez (hereafter, Vasquez spouses) entered into a the Closing:
Memorandum of Agreement (MOA) with Ayala Corporation
(hereafter, AYALA) with AYALA buying from the Vazquez xxx
spouses, all of the latter's shares of stock in Conduit
Development, Inc. (hereafter, Conduit). The main asset of 6.2.3. There are no actions, suits or proceedings pending, or to
Conduit was a 49.9 hectare property in Ayala Alabang, the knowledge of the SELLERS, threatened against or affecting
Muntinlupa, which was then being developed by Conduit under a the SELLERS with respect to the Shares or the Property; and
development plan where the land was divided into Villages 1, 2
and 3 of the "Don Vicente Village." The development was then 7. Additional Warranties by the SELLERS
being undertaken for Conduit by G.P. Construction and
Development Corp. (hereafter, GP Construction). 7.1. With respect to the Audited Financial Statements required to
be submitted at Closing in accordance with Par. 3.1.5 above, the
Under the MOA, Ayala was to develop the entire property, less SELLER jointly and severally warrant to the BUYER that:
what was defined as the "Retained Area" consisting of 18,736
square meters. This "Retained Area" was to be retained by the 7.1.1 The said Audited Financial Statements shall show that on
Vazquez spouses. The area to be developed by Ayala was called the day of Closing, the Company shall own the "Remaining
the "Remaining Area". In this "Remaining Area" were 4 lots Property", free from all liens and encumbrances and that the
adjacent to the "Retained Area" and Ayala agreed to offer these Company shall have no obligation to any party except for billings
lots for sale to the Vazquez spouses at the prevailing price at the payable to GP Construction & Development Corporation and
time of purchase. The relevant provisions of the MOA on this point advances made by Daniel Vazquez for which BUYER shall be
are: responsible in accordance with Par. 2 of this Agreement.

"5.7. The BUYER hereby commits that it will develop the 7.1.2 Except to the extent reflected or reserved in the Audited
'Remaining Property' into a first class residential subdivision of the Financial Statements of the Company as of Closing, and those
same class as its New Alabang Subdivision, and that it intends to disclosed to BUYER, the Company as of the date thereof, has no
complete the first phase under its amended development plan liabilities of any nature whether accrued, absolute, contingent or
within three (3) years from the date of this Agreement. x x x" otherwise, including, without limitation, tax liabilities due or to
become due and whether incurred in respect of or measured in
5.15. The BUYER agrees to give the SELLERS a first option to respect of the Company's income prior to Closing or arising out of
purchase four developed lots next to the "Retained Area" at the transactions or state of facts existing prior thereto.
prevailing market price at the time of the purchase."
7.2 SELLERS do not know or have no reasonable ground to know
The parties are agreed that the development plan referred to in of any basis for any assertion against the Company as at closing
paragraph 5.7 is not Conduit's development plan, but Ayala's or any liability of any nature and in any amount not fully reflected
amended development plan which was still to be formulated as of or reserved against such Audited Financial Statements referred
the time of the MOA. While in the Conduit plan, the 4 lots to be to above, and those disclosed to BUYER.
offered for sale to the Vasquez Spouses were in the first phase
thereof or Village 1, in the Ayala plan which was formulated a year xxx xxx xxx
later, it was in the third phase, or Phase II-c.
7.6.3 Except as otherwise disclosed to the BUYER in writing on
Under the MOA, the Vasquez spouses made several express or before the Closing, the Company is not engaged in or a party
warranties, as follows: to, or to the best of the knowledge of the SELLERS, threatened
with, any legal action or other proceedings before any court or
"3.1. The SELLERS shall deliver to the BUYER: administrative body, nor do the SELLERS know or have
reasonable grounds to know of any basis for any such action or
xxx
OBLICON 1-9-2018 I ACJUCO 26

proceeding or of any governmental investigation relative to the valid because it was incorporated in the MOA and the
Company. consideration therefor was the commitment by Ayala Corporation
to petitioners embodied in the MOA.
7.6.4 To the knowledge of the SELLERS, no default or breach
exists in the due performance and observance by the Company As previously mentioned, the Court of Appeals reversed the RTC
of any term, covenant or condition of any instrument or agreement Decision. According to the appellate court, Ayala Corporation was
to which the company is a party or by which it is bound, and no never informed beforehand of the existence of the Lancer claim.
condition exists which, with notice or lapse of time or both, will In fact, Ayala Corporation got a copy of the Lancer subcontract
constitute such default or breach." only on May 29, 1981 from G.P. Construction's lawyers. The
Court of Appeals thus held that petitioners violated their
After the execution of the MOA, Ayala caused the suspension of warranties under the MOA when they failed to disclose Lancer's
work on Village 1 of the Don Vicente Project. Ayala then received claims. Hence, even conceding that Ayala Corporation was
a letter from one Maximo Del Rosario of Lancer General Builder obliged to develop and sell the four (4) lots in question within three
Corporation informing Ayala that he was claiming the amount of (3) years from the date of the MOA, the obligation was suspended
P1,509,558.80 as the subcontractor of G.P. Construction... during the pendency of the case filed by Lancer.

G.P. Construction not being able to reach an amicable settlement Interpreting the MOA's paragraph 5.7 above-quoted, the
with Lancer, on March 22, 1982, Lancer sued G.P. Construction, appellate court held that Ayala Corporation committed to develop
Conduit and Ayala in the then Court of First Instance of Manila in the first phase of its own amended development plan and not
Civil Case No. 82-8598. G.P. Construction in turn filed a cross- Conduit's development plan. Nowhere does the MOA provide that
claim against Ayala. G.P. Construction and Lancer both tried to Ayala Corporation shall follow Conduit's development plan nor is
enjoin Ayala from undertaking the development of the property. Ayala Corporation prohibited from changing the sequence of the
The suit was terminated only on February 19, 1987, when it was phases of the property it will develop.
dismissed with prejudice after Ayala paid both Lancer and GP
Construction the total of P4,686,113.39. Anent the question of delay, the Court of Appeals ruled that there
was no delay as petitioners never made a demand for Ayala
Taking the position that Ayala was obligated to sell the 4 lots Corporation to sell the subject lots to them. According to the
adjacent to the "Retained Area" within 3 years from the date of appellate court, what petitioners sent were mere reminder letters
the MOA, the Vasquez spouses sent several "reminder" letters of the last of which was dated prior to April 23, 1984 when the
the approaching so-called deadline. However, no demand after obligation was not yet demandable. At any rate, the Court of
April 23, 1984, was ever made by the Vasquez spouses for Ayala Appeals found that petitioners in fact waived the three (3)-year
to sell the 4 lots. On the contrary, one of the letters signed by their period when they sent a letter through their agent, Engr. Eduardo
authorized agent, Engr. Eduardo Turla, categorically stated that Turla, stating that they "expect that the development of Phase I
they expected "development of Phase 1 to be completed by will be completed by 19 February 1990, three years from the
February 19, 1990, three years from the settlement of the legal settlement of the legal problems with the previous contractor."7
problems with the previous contractor."
The appellate court likewise ruled that paragraph 5.15 above-
By early 1990 Ayala finished the development of the vicinity of the quoted is not an option contract but a right of first refusal there
4 lots to be offered for sale. The four lots were then offered to be being no separate consideration therefor. Since petitioners
sold to the Vasquez spouses at the prevailing price in 1990. This refused Ayala Corporation's offer to sell the subject lots at the
was rejected by the Vasquez spouses who wanted to pay at 1984 reduced 1990 price of P5,000.00 per square meter, they have
prices, thereby leading to the suit below. effectively waived their right to buy the same.

After trial, the court a quo rendered its decision, the dispositive In the instant Petition, petitioners allege that the appellate court
portion of which states: erred in ruling that they violated their warranties under the MOA;
that Ayala Corporation was not obliged to develop the "Remaining
"THEREFORE, judgment is hereby rendered in favor of plaintiffs Property" within three (3) years from the execution of the MOA;
and against defendant, ordering defendant to sell to plaintiffs the that Ayala was not in delay; and that paragraph 5.15 of the MOA
relevant lots described in the Complaint in the Ayala Alabang is a mere right of first refusal. Additionally, petitioners insist that
Village at the price of P460.00 per square meter amounting to the Court should review the factual findings of the Court of
P1,349,540.00; ordering defendant to reimburse to plaintiffs Appeals as they are in conflict with those of the trial court.
attorney's fees in the sum of P200,000.00 and to pay the cost of
the suit." Ayala Corporation filed a Comment on the Petition8 dated March
26, 2002, contending that the petition raises questions of fact and
In its decision, the court a quo concluded that the Vasquez seeks a review of evidence which is within the domain of the Court
spouses were not obligated to disclose the potential claims of GP of Appeals. Ayala Corporation maintains that the subcontract
Construction, Lancer and Del Rosario; Ayala's accountants between GP Construction, with whom Conduit contracted for the
should have opened the records of Conduit to find out all claims; development of the property under a Construction Contract dated
the warranty against suit is with respect to "the shares of the October 10, 1980, and Lancer was not disclosed by petitioners
Property" and the Lancer suit does not affect the shares of stock during the negotiations. Neither was the liability for Lancer's claim
sold to Ayala; Ayala was obligated to develop within 3 years; to included in the Audited Financial Statements submitted by
say that Ayala was under no obligation to follow a time frame was petitioners after the signing of the MOA. These justify the
to put the Vasquezes at Ayala's mercy; Ayala did not develop conclusion that petitioners breached their warranties under the
because of a slump in the real estate market; the MOA was afore-quoted paragraphs of the MOA. Since the Lancer suit
drafted and prepared by the AYALA who should suffer its ended only in February 1989, the three (3)-year period within
ambiguities; the option to purchase the 4 lots is valid because it which Ayala Corporation committed to develop the property
was supported by consideration as the option is incorporated in should only be counted thence. Thus, when it offered the subject
the MOA where the parties had prestations to each other. lots to petitioners in 1990, Ayala Corporation was not yet in delay.
[Emphasis supplied]
In response to petitioners' contention that there was no action or
Ayala Corporation filed an appeal, alleging that the trial court proceeding against them at the time of the execution of the MOA
erred in holding that petitioners did not breach their warranties on April 23, 1981, Ayala Corporation avers that the facts and
under the MOA6 dated April 23, 1981; that it was obliged to circumstances which gave rise to the Lancer claim were already
develop the land where the four (4) lots subject of the option to extant then. Petitioners warranted that their representations under
purchase are located within three (3) years from the date of the the MOA shall be true and correct at the time of "Closing" which
MOA; that it was in delay; and that the option to purchase was shall take place within four (4) weeks from the signing of the
OBLICON 1-9-2018 I ACJUCO 27

MOA.9 Since the MOA was signed on April 23, 1981, "Closing" Likewise, petitioners aver that although Ayala Corporation may
was approximately the third week of May 1981. Hence, Lancer's change the sequence of its development plan, it is obliged under
claims, articulated in a letter which Ayala Corporation received on the MOA to develop the entire area where the subject lots are
May 4, 1981, are among the liabilities warranted against under located in three (3) years.
paragraph 7.1.2 of the MOA.
They also assert that demand was made on Ayala Corporation to
Moreover, Ayala Corporation asserts that the warranties under comply with their obligation under the MOA. Apart from their
the MOA are not just against suits but against all kinds of liabilities reminder letters dated January 24, February 18 and March 5,
not reflected in the Audited Financial Statements. It cannot be 1984, they also sent a letter dated March 4, 1984 which they claim
faulted for relying on the express warranty that except for billings is a categorical demand for Ayala Corporation to comply with the
payable to GP Construction and advances made by petitioner provisions of the MOA.
Daniel Vazquez in the amount of P38,766.04, Conduit has no
other liabilities. Hence, petitioners cannot claim that Ayala The parties were required to submit their respective memoranda
Corporation should have examined and investigated the Audited in the Resolution12 dated November 18, 2002. In compliance with
Financial Statements of Conduit and should now assume all its this directive, petitioners submitted their Memorandum13 dated
obligations and liabilities including the Lancer suit and the cross- February 14, 2003 on even date, while Ayala Corporation filed its
claim of GP Construction. Memorandum14 dated February 14, 2003 on February 17, 2003.

Furthermore, Ayala Corporation did not make a commitment to We shall first dispose of the procedural question raised by the
complete the development of the first phase of the property within instant petition.
three (3) years from the execution of the MOA. The provision
refers to a mere declaration of intent to develop the first phase of It is well-settled that the jurisdiction of this Court in cases brought
its (Ayala Corporation's) own development plan and not to it from the Court of Appeals by way of petition for review under
Conduit's. True to its intention, Ayala Corporation did complete Rule 45 is limited to reviewing or revising errors of law imputed to
the development of the first phase (Phase II-A) of its amended it, its findings of fact being conclusive on this Court as a matter of
development plan within three (3) years from the execution of the general principle. However, since in the instant case there is a
MOA. However, it is not obliged to develop the third phase (Phase conflict between the factual findings of the trial court and the
II-C) where the subject lots are located within the same time frame appellate court, particularly as regards the issues of breach of
because there is no contractual stipulation in the MOA therefor. It warranty, obligation to develop and incurrence of delay, we have
is free to decide on its own the period for the development of to consider the evidence on record and resolve such factual
Phase II-C. If petitioners wanted to impose the same three (3)- issues as an exception to the general rule.15 In any event, the
year timetable upon the third phase of the amended development submitted issue relating to the categorization of the right to
plan, they should have filed a suit to fix the time table in purchase granted to petitioners under the MOA is legal in
accordance with Article 119710 of the Civil Code. Having failed to character.
do so, Ayala Corporation cannot be declared to have been in
delay. The next issue that presents itself is whether petitioners breached
their warranties under the MOA when they failed to disclose the
Ayala Corporation further contends that no demand was made on Lancer claim. The trial court declared they did not; the appellate
it for the performance of its alleged obligation. The letter dated court found otherwise.
October 4, 1983 sent when petitioners were already aware of the
Lancer suit did not demand the delivery of the subject lots by April Ayala Corporation summarizes the clauses of the MOA which
23, 1984. Instead, it requested Ayala Corporation to keep petitioners allegedly breached when they failed to disclose the
petitioners posted on the status of the case. Likewise, the letter Lancer claim:
dated March 4, 1984 was merely an inquiry as to the date when
the development of Phase 1 will be completed. More importantly, a) Clause 7.1.1. – that Conduit shall not be obligated to anyone
their letter dated June 27, 1988 through Engr. Eduardo Turla except to GP Construction for P38,766.04, and for advances
expressed petitioners' expectation that Phase 1 will be completed made by Daniel Vazquez;
by February 19, 1990.
b) Clause 7.1.2. – that except as reflected in the audited financial
Lastly, Ayala Corporation maintains that paragraph 5.15 of the statements Conduit had no other liabilities whether accrued,
MOA is a right of first refusal and not an option contract. absolute, contingent or otherwise;

Petitioners filed their Reply11 dated August 15, 2002 reiterating c) Clause 7.2. – that there is no basis for any assertion against
the arguments in their Petition and contending further that they Conduit of any liability of any value not reflected or reserved in the
did not violate their warranties under the MOA because the case financial statements, and those disclosed to Ayala;
was filed by Lancer only on April 1, 1982, eleven (11) months and
eight (8) days after the signing of the MOA on April 23, 1981. d) Clause 7.6.3. – that Conduit is not threatened with any legal
Ayala Corporation admitted that it received Lancer's claim before action or other proceedings; and
the "Closing" date. It therefore had all the time to rescind the
MOA. Not having done so, it can be concluded that Ayala e) Clause 7.6.4. – that Conduit had not breached any term,
Corporation itself did not consider the matter a violation of condition, or covenant of any instrument or agreement to which it
petitioners' warranty. is a party or by which it is bound.16

Moreover, petitioners submitted the Audited Financial Statements The Court is convinced that petitioners did not violate the
of Conduit and allowed an acquisition audit to be conducted by foregoing warranties.
Ayala Corporation. Thus, the latter bought Conduit with "open
eyes." The exchanges of communication between the parties indicate
that petitioners substantially apprised Ayala Corporation of the
Petitioners also maintain that they had no knowledge of the Lancer claim or the possibility thereof during the period of
impending case against Conduit at the time of the execution of negotiations for the sale of Conduit.
the MOA. Further, the MOA makes Ayala Corporation liable for
the payment of all billings of GP Construction. Since Lancer's In a letter17 dated March 5, 1984, petitioner Daniel Vazquez
claim was actually a claim against GP Construction being its sub- reminded Ayala Corporation's Mr. Adolfo Duarte (Mr. Duarte) that
contractor, it is Ayala Corporation and not petitioners which is prior to the completion of the sale of Conduit, Ayala Corporation
liable. asked for and was given information that GP Construction sub-
contracted, presumably to Lancer, a greater percentage of the
OBLICON 1-9-2018 I ACJUCO 28

project than it was allowed. Petitioners gave this information to responsibility "for the payment of all billings of the contractor GP
Ayala Corporation because the latter intimated a desire to "break Construction & Development Corporation after the first billing and
the contract of Conduit with GP." Ayala Corporation did not deny any payments made by the company and/or SELLERS shall be
this. In fact, Mr. Duarte's letter18 dated March 6, 1984 indicates reimbursed by BUYER on closing which advances to date is
that Ayala Corporation had knowledge of the Lancer subcontract P1,159,012.87."22
prior to its acquisition of Conduit. Ayala Corporation even
admitted that it "tried to explore…legal basis to discontinue the The billings knowingly assumed by Ayala Corporation necessarily
contract of Conduit with GP" but found this "not feasible when include the Lancer claim for which GP Construction is liable. Proof
information surfaced about the tacit consent of Conduit to the sub- of this is Ayala Corporation's letter23 to GP Construction dated
contracts of GP with Lancer." before "Closing" on May 4, 1981, informing the latter of Ayala
Corporation's receipt of the Lancer claim embodied in the letter
At the latest, Ayala Corporation came to know of the Lancer claim dated April 30, 1981, acknowledging that it is taking over the
before the date of Closing of the MOA. Lancer's letter19 dated contractual responsibilities of Conduit, and requesting copies of
April 30, 1981 informing Ayala Corporation of its unsettled claim all sub-contracts affecting the Conduit property. The pertinent
with GP Construction was received by Ayala Corporation on May excerpts of the letter read:
4, 1981, well before the "Closing"20 which occurred four (4)
weeks after the date of signing of the MOA on April 23, 1981, or …
on May 23, 1981.
In this connection, we wish to inform you that this morning we
The full text of the pertinent clauses of the MOA quoted hereunder received a letter from Mr. Maximo D. Del Rosario, President of
likewise indicate that certain matters pertaining to the liabilities of Lancer General Builders Corporation apprising us of the
Conduit were disclosed by petitioners to Ayala Corporation existence of subcontracts that they have with your corporation.
although the specifics thereof were no longer included in the They have also furnished us with a copy of their letter to you dated
MOA: 30 April 1981.

7.1.1 The said Audited Financial Statements shall show that on Since we are taking over the contractual responsibilities of
the day of Closing, the Company shall own the "Remaining Conduit Development, Inc., we believe that it is necessary, at this
Property", free from all liens and encumbrances and that the point in time, that you furnish us with copies of all your
Company shall have no obligation to any party except for billings subcontracts affecting the property of Conduit, not only with
payable to GP Construction & Development Corporation and Lancer General Builders Corporation, but all subcontracts with
advances made by Daniel Vazquez for which BUYER shall be other parties as well…24
responsible in accordance with Paragraph 2 of this Agreement.
Quite tellingly, Ayala Corporation even attached to its Pre-Trial
7.1.2 Except to the extent reflected or reserved in the Audited Brief25 dated July 9, 1992 a copy of the letter26 dated May 28,
Financial Statements of the Company as of Closing, and those 1981 of GP Construction's counsel addressed to Conduit
disclosed to BUYER, the Company as of the date hereof, has no furnishing the latter with copies of all sub-contract agreements
liabilities of any nature whether accrued, absolute, contingent or entered into by GP Construction. Since it was addressed to
otherwise, including, without limitation, tax liabilities due or to Conduit, it can be presumed that it was the latter which gave
become due and whether incurred in respect of or measured in Ayala Corporation a copy of the letter thereby disclosing to the
respect of the Company's income prior to Closing or arising out of latter the existence of the Lancer sub-contract.
transactions or state of facts existing prior thereto.
The ineluctable conclusion is that petitioners did not violate their
7.2 SELLERS do not know or have no reasonable ground to know warranties under the MOA. The Lancer sub-contract and claim
of any basis for any assertion against the Company as at Closing were substantially disclosed to Ayala Corporation before the
of any liability of any nature and in any amount not fully reflected "Closing" date of the MOA. Ayala Corporation cannot disavow
or reserved against such Audited Financial Statements referred knowledge of the claim.
to above, and those disclosed to BUYER.
Moreover, while in its correspondence with petitioners, Ayala
xxx xxx xxx Corporation did mention the filing of the Lancer suit as an obstacle
to its development of the property, it never actually brought up nor
7.6.3 Except as otherwise disclosed to the BUYER in writing on sought redress for petitioners' alleged breach of warranty for
or before the Closing, the Company is not engaged in or a party failure to disclose the Lancer claim until it filed its Answer27 dated
to, or to the best of the knowledge of the SELLERS, threatened February 17, 1992.
with, any legal action or other proceedings before any court or
administrative body, nor do the SELLERS know or have We now come to the correct interpretation of paragraph 5.7 of the
reasonable grounds to know of any basis for any such action or MOA. Does this paragraph express a commitment or a mere
proceeding or of any governmental investigation relative to the intent on the part of Ayala Corporation to develop the property
Company. within three (3) years from date thereof? Paragraph 5.7 provides:

7.6.4 To the knowledge of the SELLERS, no default or breach 5.7. The BUYER hereby commits that it will develop the
exists in the due performance and observance by the Company 'Remaining Property' into a first class residential subdivision of the
of any term, covenant or condition of any instrument or agreement same class as its New Alabang Subdivision, and that it intends to
to which the Company is a party or by which it is bound, and no complete the first phase under its amended development plan
condition exists which, with notice or lapse of time or both, will within three (3) years from the date of this Agreement….28
constitute such default or breach."21 [Emphasis supplied]
Notably, while the first phrase of the paragraph uses the word
Hence, petitioners' warranty that Conduit is not engaged in, a "commits" in reference to the development of the "Remaining
party to, or threatened with any legal action or proceeding is Property" into a first class residential subdivision, the second
qualified by Ayala Corporation's actual knowledge of the Lancer phrase uses the word "intends" in relation to the development of
claim which was disclosed to Ayala Corporation before the the first phase of the property within three (3) years from the date
"Closing." of the MOA. The variance in wording is significant. While
"commit"29 connotes a pledge to do something, "intend"30
At any rate, Ayala Corporation bound itself to pay all billings merely signifies a design or proposition.
payable to GP Construction and the advances made by petitioner
Daniel Vazquez. Specifically, under paragraph 2 of the MOA
referred to in paragraph 7.1.1, Ayala Corporation undertook
OBLICON 1-9-2018 I ACJUCO 29

Atty. Leopoldo Francisco, former Vice President of Ayala amended development plan within three (3) years from the
Corporation's legal division who assisted in drafting the MOA, execution of the MOA, there was no parallel commitment made
testified: as to the timeframe for the development of the third phase where
the subject lots are located.
COURT
Lest it be forgotten, the point of this petition is the alleged failure
You only ask what do you mean by that intent. Just answer on of Ayala Corporation to offer the subject lots for sale to petitioners
that point. within three (3) years from the execution of the MOA. It is not that
Ayala Corporation committed or intended to develop the first
ATTY. BLANCO phase of its amended development plan within three (3) years.
Whether it did or did not is actually beside the point since the
Don't talk about standard. subject lots are not located in the first phase anyway.

WITNESS We now come to the issue of default or delay in the fulfillment of


the obligation.
A Well, the word intent here, your Honor, was used to emphasize
the tentative character of the period of development because it Article 1169 of the Civil Code provides:
will be noted that the sentence refers to and I quote "to complete
the first phase under its amended development plan within three Art. 1169. Those obliged to deliver or to do something incur in
(3) years from the date of this agreement, at the time of the delay from the time the obligee judicially or extrajudicially
execution of this agreement, your Honor." That amended demands from them the fulfillment of their obligation.
development plan was not yet in existence because the buyer had
manifested to the seller that the buyer could amend the However, the demand by the creditor shall not be necessary in
subdivision plan originally belonging to the seller to conform with order that delay may exist:
its own standard of development and second, your Honor,
(interrupted)31 (1) When the obligation or the law expressly so declares; or

It is thus unmistakable that this paragraph merely expresses an (2) When from the nature and the circumstances of the obligation
intention on Ayala Corporation's part to complete the first phase it appears that the designation of the time when the thing is to be
under its amended development plan within three (3) years from delivered or the service is to be rendered was a controlling motive
the execution of the MOA. Indeed, this paragraph is so plainly for the establishment of the contract; or
worded that to misunderstand its import is deplorable.
(3) When demand would be useless, as when the obligor has
More focal to the resolution of the instant case is paragraph 5.7's rendered it beyond his power to perform.
clear reference to the first phase of Ayala Corporation's amended
development plan as the subject of the three (3)-year intended In reciprocal obligations, neither party incurs in delay if the other
timeframe for development. Even petitioner Daniel Vazquez does not comply or is not ready to comply in a proper manner with
admitted on cross-examination that the paragraph refers not to what is incumbent upon him. From the moment one of the parties
Conduit's but to Ayala Corporation's development plan which was fulfills his obligation, delay by the other begins.
yet to be formulated when the MOA was executed:
In order that the debtor may be in default it is necessary that the
Q: Now, turning to Section 5.7 of this Memorandum of Agreement, following requisites be present: (1) that the obligation be
it is stated as follows: "The Buyer hereby commits that to develop demandable and already liquidated; (2) that the debtor delays
the remaining property into a first class residential subdivision of performance; and (3) that the creditor requires the performance
the same class as New Alabang Subdivision, and that they intend judicially or extrajudicially.33
to complete the first phase under its amended development plan
within three years from the date of this agreement." Under Article 1193 of the Civil Code, obligations for whose
fulfillment a day certain has been fixed shall be demandable only
Now, my question to you, Dr. Vasquez is that there is no dispute when that day comes. However, no such day certain was fixed in
that the amended development plan here is the amended the MOA. Petitioners, therefore, cannot demand performance
development plan of Ayala? after the three (3) year period fixed by the MOA for the
development of the first phase of the property since this is not the
A: Yes, sir. same period contemplated for the development of the subject lots.
Since the MOA does not specify a period for the development of
Q: In other words, it is not Exhibit "D-5" which is the original plan the subject lots, petitioners should have petitioned the court to fix
of Conduit? the period in accordance with Article 119734 of the Civil Code. As
no such action was filed by petitioners, their complaint for specific
A: No, it is not. performance was premature, the obligation not being
demandable at that point. Accordingly, Ayala Corporation cannot
Q: This Exhibit "D-5" was the plan that was being followed by GP likewise be said to have delayed performance of the obligation.
Construction in 1981?
Even assuming that the MOA imposes an obligation on Ayala
A: Yes, sir. Corporation to develop the subject lots within three (3) years from
date thereof, Ayala Corporation could still not be held to have
Q: And point of fact during your direct examination as of the date been in delay since no demand was made by petitioners for the
of the agreement, this amended development plan was still to be performance of its obligation.
formulated by Ayala?
As found by the appellate court, petitioners' letters which dealt
A: Yes, sir.32 with the three (3)-year timetable were all dated prior to April 23,
1984, the date when the period was supposed to expire. In other
As correctly held by the appellate court, this admission is crucial words, the letters were sent before the obligation could become
because while the subject lots to be sold to petitioners were in the legally demandable. Moreover, the letters were mere reminders
first phase of the Conduit development plan, they were in the third and not categorical demands to perform. More importantly,
or last phase of the Ayala Corporation development plan. Hence, petitioners waived the three (3)-year period as evidenced by their
even assuming that paragraph 5.7 expresses a commitment on agent, Engr. Eduardo Turla's letter to the effect that petitioners
the part of Ayala Corporation to develop the first phase of its
OBLICON 1-9-2018 I ACJUCO 30

agreed that the three (3)-year period should be counted from the road to our property and the development of Phase I will be
termination of the case filed by Lancer. The letter reads in part: completed.41

I. Completion of Phase I At best, petitioners' letters can only be construed as mere


reminders which cannot be considered demands for performance
As per the memorandum of Agreement also dated April 23, 1981, because it must appear that the tolerance or benevolence of the
it was undertaken by your goodselves to complete the creditor must have ended.42
development of Phase I within three (3) years. Dr. & Mrs. Vazquez
were made to understand that you were unable to accomplish this The petition finally asks us to determine whether paragraph 5.15
because of legal problems with the previous contractor. These of the MOA can properly be construed as an option contract or a
legal problems were resolved as of February 19, 1987, and Dr. & right of first refusal. Paragraph 5.15 states:
Mrs. Vazquez therefore expect that the development of Phase I
will be completed by February 19, 1990, three years from the 5.15 The BUYER agrees to give the SELLERS first option to
settlement of the legal problems with the previous contractor. The purchase four developed lots next to the "Retained Area" at the
reason for this is, as you know, that security-wise, Dr. & Mrs. prevailing market price at the time of the purchase.43
Vazquez have been advised not to construct their residence till
the surrounding area (which is Phase I) is developed and The Court has clearly distinguished between an option contract
occupied. They have been anxious to build their residence for and a right of first refusal. An option is a preparatory contract in
quite some time now, and would like to receive assurance from which one party grants to another, for a fixed period and at a
your goodselves regarding this, in compliance with the determined price, the privilege to buy or sell, or to decide whether
agreement. or not to enter into a principal contract. It binds the party who has
given the option not to enter into the principal contract with any
II. Option on the adjoining lots other person during the period designated, and within that period,
to enter into such contract with the one to whom the option was
We have already written your goodselves regarding the intention granted, if the latter should decide to use the option. It is a
of Dr. & Mrs. Vazquez to exercise their option to purchase the two separate and distinct contract from that which the parties may
lots on each side (a total of 4 lots) adjacent to their "Retained enter into upon the consummation of the option. It must be
Area". They are concerned that although over a year has elapsed supported by consideration.44
since the settlement of the legal problems, you have not
presented them with the size, configuration, etc. of these lots. In a right of first refusal, on the other hand, while the object might
They would appreciate being provided with these at your earliest be made determinate, the exercise of the right would be
convenience.35 dependent not only on the grantor's eventual intention to enter
into a binding juridical relation with another but also on terms,
Manifestly, this letter expresses not only petitioners' including the price, that are yet to be firmed up.45
acknowledgement that the delay in the development of Phase I
was due to the legal problems with GP Construction, but also their Applied to the instant case, paragraph 5.15 is obviously a mere
acquiescence to the completion of the development of Phase I at right of first refusal and not an option contract. Although the
the much later date of February 19, 1990. More importantly, by no paragraph has a definite object, i.e., the sale of subject lots, the
stretch of semantic interpretation can it be construed as a period within which they will be offered for sale to petitioners and,
categorical demand on Ayala Corporation to offer the subject lots necessarily, the price for which the subject lots will be sold are not
for sale to petitioners as the letter merely articulates petitioners' specified. The phrase "at the prevailing market price at the time
desire to exercise their option to purchase the subject lots and of the purchase" connotes that there is no definite period within
concern over the fact that they have not been provided with the which Ayala Corporation is bound to reserve the subject lots for
specifications of these lots. petitioners to exercise their privilege to purchase. Neither is there
a fixed or determinable price at which the subject lots will be
The letters of petitioners' children, Juan Miguel and Victoria offered for sale. The price is considered certain if it may be
Vazquez, dated January 23, 198436 and February 18, 198437 determined with reference to another thing certain or if the
can also not be considered categorical demands on Ayala determination thereof is left to the judgment of a specified person
Corporation to develop the first phase of the property within the or persons.46
three (3)-year period much less to offer the subject lots for sale to
petitioners. The letter dated January 23, 1984 reads in part: Further, paragraph 5.15 was inserted into the MOA to give
petitioners the first crack to buy the subject lots at the price which
You will understand our interest in the completion of the roads to Ayala Corporation would be willing to accept when it offers the
our property, since we cannot develop it till you have constructed subject lots for sale. It is not supported by an independent
the same. Allow us to remind you of our Memorandum of consideration. As such it is not governed by Articles 1324 and
Agreement, as per which you committed to develop the roads to 1479 of the Civil Code, viz:
our property "as per the original plans of the company", and that
Art. 1324. When the offeror has allowed the offeree a certain
1. The back portion should have been developed before the front period to accept, the offer may be withdrawn at any time before
portion – which has not been the case. acceptance by communicating such withdrawal, except when the
option is founded upon a consideration, as something paid or
2. The whole project – front and back portions be completed by promised.
1984.38
Art. 1479. A promise to buy and sell a determinate thing for a price
The letter dated February 18, 1984 is similarly worded. It states: certain is reciprocally demandable.

In this regard, we would like to remind you of Articles 5.7 and 5.9 An accepted unilateral promise to buy or to sell a determinate
of our Memorandum of Agreement which states respectively:…39 thing for a price certain is binding upon the promissor if the
promise is supported by a consideration distinct from the price.
Even petitioner Daniel Vazquez' letter40 dated March 5, 1984
does not make out a categorical demand for Ayala Corporation to Consequently, the "offer" may be withdrawn anytime by
offer the subject lots for sale on or before April 23, 1984. The letter communicating the withdrawal to the other party.47
reads in part:
In this case, Ayala Corporation offered the subject lots for sale to
…and that we expect from your goodselves compliance with our petitioners at the price of P6,500.00/square meter, the prevailing
Memorandum of Agreement, and a definite date as to when the market price for the property when the offer was made on June
OBLICON 1-9-2018 I ACJUCO 31

18, 1990.48 Insisting on paying for the lots at the prevailing


market price in 1984 of P460.00/square meter, petitioners
rejected the offer. Ayala Corporation reduced the price to
P5,000.00/square meter but again, petitioners rejected the offer
and instead made a counter-offer in the amount of
P2,000.00/square meter.49 Ayala Corporation rejected
petitioners' counter-offer. With this rejection, petitioners lost their
right to purchase the subject lots.

It cannot, therefore, be said that Ayala Corporation breached


petitioners' right of first refusal and should be compelled by an
action for specific performance to sell the subject lots to
petitioners at the prevailing market price in 1984.

WHEREFORE, the instant petition is DENIED. No


pronouncement as to costs.

SO ORDERED.
OBLICON 1-9-2018 I ACJUCO 32

ii. MORA ACCIPIENDI possession, as the same rate that the defendant company used
to pay.

G.R. No. L-10394 December 13, 1958 Thereafter, when the United States Army finally gave up the
occupancy the premises, the Manila Motor Co., Inc., through their
CLAUDINA VDA. DE VILLARUEL, ET AL., plaintiffs-appellees, branch manager, Rafael B. Grey, decided to exercise their option
vs. to renew the contract for the additional period of five (5) years,
MANILA MOTOR CO., INC. and ARTURO COLMENARES, and the parties, agreed that the seven months occupancy by the
defendants-appellants. U. S. Army would not be counted as part of the new 5-year term.
Simultaneously with such renewal, the company sublet the same
Hilado and Hilado for appellees. buildings, except that used for the residence of the branch
Ozaeta, Gibbs and Ozaeta for appellant company. manager, to the other defendant, Arturo Colmenares.
Jose L. Gamboa and Napoleon Garcia for appellant Arturo
Colmenares. However, before resuming the collection of rentals, Dr. Alfredo
Villaruel, who was entrusted with the same, consulted Atty. Luis
Hilado on whether they (the lessors) had the right to collect, from
REYES, J. B. L., J.: the defendant company, rentals corresponding to the time during
which the Japanese military forces had control over the leased
Manila Motor Co., Inc., and Arturo Colmenares interpose this premises. Upon being advised that they had such a right, Dr.
appeal against the decision of the Court of First Instance of Villaruel demanded payment thereof, but the defendant company
Negros Occidental, in its Civil Case No. 648, ordering the refused to pay. As a result, Dr. Villaruel gave notice seeking the
defendant Manila Motor Co., Inc. to pay to the plaintiffs Villaruel rescission of the contract of lease and the payment of rentals from
the sum of (a) P11,900 with legal rest from May 18, 1953, on June 1, 1942 to March 31, 1945 totalling P11,900. This was also
which date, the court below declared invalid the continued rejected by the defendant company in its letter to Villaruel, dated
operation of the Debt Moratorium, under the first cause of action; July 27, 1946.
(b) P38,395 with legal interest from the date of filing of the original
complaint on April 26, 1947, on the second cause of action; and Sometime on that same month of July, Rafael B. Grey offered to
against both the Manila Motor Co., Inc. and its co-defendant, pay to Dr. Villaruel the sum of P350, for which, tenderer requested
Arturo Colmenares, the sum of P30,000 to be paid, jointly and a receipt that would state that it was in full payment for the said
severally, with respect to the third cause of action. month. The latter expressed willingness to accept the tendered
amount provided, however, that his acceptance should be
On May 31, 1940, the plaintiffs Villaruel and the defendant Manila understood to be without prejudice to their demand for the
Motor Co., Inc. entered into a contract (Exhibit "A") whereby, the rescission of the contract, and for increased rentals until their
former agreed to convey by way of lease to the latter the following buildings were returned to them. Later, Dr. Villaruel indicated his
described premises; willingness to limit the condition of his acceptance to be that
"neither the lessee nor the lessors admit the contention of the
(a) Five hundred (500) square meters of floor space of a other by the mere fact of payment". As no accord could still be
building of strong materials for automobile showroom, offices, and reached between the parties as to the context of the receipt, no
store room for automobile spare parts; payment was thereafter tendered until the end of November,
1946. On December 4, 1946 (the day after the defendant
(b) Another building of strong materials for automobile company notified Dr. Villaruel by telegram, that it cancelled the
repair shop; and power of attorney given to Grey, and that it now authorized Arturo
Colmenares, instead, to pay the rent of P350 each month), the
(c) A 5-bedroom house of strong materials for residence of Manila Motor Co., Inc. remitted to Dr. Villaruel by letter, the sum
the Bacolod Branch Manager of the defendant company. of P350.00. For this payment, the latter issued a receipt stating
that it was "without prejudice" to their demand for rents in arrears
The term of the lease was five (5) years, to commence from the and for the rescission of the contract of lease.
time that the building were delivered and placed at the disposal of
the lessee company, ready for immediate occupancy. The After it had become evident that the parties could not settle their
contract was renewable for an additional period of five (5) years. case amicably, the lessors commenced this action on April 26,
The Manila Motor Company, in consideration of the above 1947 with the Court of First Instance of Negros Occidental against
covenants, agreed to pay to the lessors, or their duly authorized the appellants herein. During the pendency of the case, a fire
representative, a monthly rental of Three Hundred (P300) pesos originating from the projection room of the City Theatre, into which
payable in advance before the fifth day of each month, and for the Arturo Colmenares, (the sublessee) had converted the former
residential house of its branch manager, a monthly rental not to repair shop of the Manila Motor Co. Inc., completely razed the
exceed Fifty (P50) pesos "payable separately by the Manager". building, engulfing also the main building where Colmenares had
opened a soda fountain and refreshment parlor, and made
The leased premises were placed in the possession of the lessee partitions for store spaces which he rented to other persons.
on the 31st day of October, 1940, from which date, the period of
the lease started to run under their agreement. Because of the aforesaid occurrence, plaintiffs demanded
reimbursement from the defendants, but having been refused,
This situation, the Manila Motor Co., Inc. and its branch manager they filed a supplemental complaint to include as their third cause
enjoying the premises, and the lessors receiving the of action, the recovery of the value of the burned buildings.
corresponding rentals as stipulated, continued until the invasion
of 1941; and shortly after the Japanese military occupation of the Defendants filed their amended answer and also moved for the
Provincial Capital of Bacolod the enemy forces held and used the dismissal of the plaintiffs' first and second causes of action
properties leased as part of their quarters from June 1, 1942 to invoking the Debt Moratorium that was then in force. The
March 29, 1945, ousting the lessee therefrom. No payment of dismissal was granted by the trial court on February 5, 1951, but
rentals were made at any time during the said period. hearing was set as regards the third cause of action.

Immediately upon the liberation of the said city in 1945, the On August 11, 1952, the defendant company filed a motion for
American Forces occupied the same buildings that were vacated summary judgment dismissing the plaintiffs, third cause of action,
by the Japanese, including those leased by the plaintiffs, until to which plaintiffs registered objection coupled with a petition for
October 31, 1945. Monthly rentals were paid by the said reconsideration of the order of the court dismissing the first and
occupants to the owners during the time that they were in second causes of action. Pending the resolution of this incident,
plaintiffs, on October 2, 1953, called the court's attention to the
OBLICON 1-9-2018 I ACJUCO 33

decision in the case of Rutter vs. Esteban (93 Phil., 68; 49 Off.
Gaz. [5] 1807) invalidating the continued effectivity of the ART. 1554. It shall be the duty of the lessor;
Moratorium Law (R. A. 342). On November 25, 1953, the trial
court denied the defendant company's motion for summary 1. To deliver to the lessee the thing which is the subject
judgment and set aside its previous order dismissing the first and matter of the contract;
second causes of action. The case was accordingly heard and
thereafter, judgment was rendered in plaintiffs' favor in the terms 2. To make thereon, during the lease, all repairs necessary
set in the opening paragraph of this decision. Thereafter, the in order to keep it in serviceable condition for the purpose for
defendants regularly appealed to this Court. which it was intended;

The defendants-appellants raise a number of procedural points. 3. To maintain the lessee in the peaceful enjoyment of the
The first of these relates to their contention that the supplemental lease during the entire term of the contract.
complaint which included a third cause of action, should not have
been admitted, as it brought about a change in the original theory ART. 1560. The lessor shall not be liable for any act of
of the case and that it raised new issues not theretofore mere disturbance of a third person of the use of the leased
considered. This argument cannot be sustained under the property; but the lessee shall have a direct action against the
circumstances. This action was inceptionally instituted for the trespasser.
rescission of the contract of lease and for the recovery of unpaid
rentals before and after liberation. When the leased buildings It the third person, be it the Government or a private individual,
were destroyed, the plaintiffs-lessors demanded from the has acted in reliance upon a right, such action shall not be
defendants-lessees, instead, the value of the burned premises, deemed a mere act of disturbance. (Emphasis supplied)
basing their right to do so on defendants' alleged default in the
payment of post-liberation rentals (which was also their basis in Under the first paragraph of article 1560 the lessor does not
formerly seeking for rescission). This cannot be considered as answer for a mere act of trespass ( perturbacion de mero hecho)
already altering the theory of the case which is merely a change as distinguished from trespass under color of title ( perturbacion
in the relief prayed for, brought about by circumstances occurring de derecho). As to what would constitute a mere act of trespass,
during the pendency of the action, and is not improper. (Southern this Court in the case of Goldstein vs. Roces (34 Phil. 562), made
Pacific Co. vs. Conway, 115 F. 2d 746; Suburban Improvement this pronouncement:
Company vs. Scott Lumber Co., 87 A.L.R. 555, 59 F. 2d 711). The
filing of the supplements complaint can well be justified also under Si el hecho perturbador no va acompañado ni precedido de nada
section 2, Rule 17 of the Rules of Court (on amendments) "to the que revele una intencion propiamente juridica en el que lo realiza,
end that the real matter in dispute and all matters in the action in de tal suerte que el arrendatario solo pueda apreciar el hecho
dispute between the parties may, as far as possible be completely material desnudo de toda forma o motivacion de derecho,
determined in a single proceedings". It is to be noted furthermore, entendemos que se trata de una perturbacion de mero hecho.
that the admission or rejection of this kind of pleadings is within
the sound discretion of the court that will not be disturbed on Upon the basis of the distinction thus established between the
appeal in the absence of abuse thereof (see Sec. 5, Rule 17, perturbacion de hecho and the perturbacion de derecho, it is
Rules of Court), especially so, as in this case, where no demonstrable that the ouster of the appellant by the Japanese
substantial procedural prejudice is caused to the adverse party. occupying forces belongs to the second class of disturbances, de
derecho. For under the generally accepted principles of
It is urged that the dismissal of the first and second causes of international law (and it must be remembered that those principles
action on February 5, 1951 had the effect of a dismissal "with are made by our Constitution a part of the law of our nation 1) a
prejudice" as the court did not make any qualification in its belligerent occupant (like the Japanese in 1942-1945) may
dismissal order. Appellants, apparently, lost sight of the fact that legitimately billet or quarter its troops in privately owned land and
the dismissal was premised on the existence of the "Debt buildings for the duration of its military operations, or as military
Moratorium" which suspended the enforcement of the obligation necessity should demand. The well known writer Oppenheim,
up to a certain time. The reference thereto by the lower court discoursing on the laws of war on land, says upon this topic;
amounted to a dismissal "without prejudice", since in effect it ruled
that the plaintiffs could not, at the time they sought it, enforce their Immovable private enemy property may under no circumstances
right of action against the defendants, but plaintiffs must wait until or conditions be appropriated by an invading belligerent. Should
the moratorium was lifted. In this way, the court qualified its he confiscate and sell private land or buildings, the buyer would
dismissal. acquire no right whatever to the property. Article 46 of the Hague
Regulations expressly enacts that "private property may not be
Taking up the case on its merits, it is readily seen that the key to confiscated." But confiscation differs from the temporary use of
the entire dispute is the question whether the defendant-appellant private land and building for all kinds of purposes demanded by
Manila Motor Co., Inc. should be held liable for the rentals of the the necessities of war. What has been said above with regard to
premises leased corresponding to the lapse of time that they were utilization of public buildings applied equally to private buildings.
occupied as quarters or barracks by the invading Japanese army, If necessary, they maybe converted into hospital barracks, and
and whether said appellant was placed in default by its refusal to stables without compensation for the proprietors, and they may
comply with the demand to pay such rents. For if the Motor also be converted into fortifications. A humane belligerent will not
Company was not so liable, then it never was in default nor was drive the wretched inhabitants into the street if he can help it. But
it chargeable for the accidental lose of the buildings, nor for any under the pressure of necessity he may be obliged to do this, and
damages except the rental at the contract rate from its he is certainly not prohibited from doing it. (Emphasis supplied)
reoccupation of the premises leased until the same were (Oppenheim & Lauterpach, International Law, Vol. II, p. 312, 1944
accidentally destroyed by fire on March 2, 1948. Ed.)

The appellees contended, and the court below has held, that the The view thus expressed is concurred in by other writers. Hyde
ouster of the least company by the Japanese occupation forces (International Law, Vol. 3, p. 1893, 2nd Rev. Ed.) quotes the U. S.
from 1942 until liberation, while operating to deprive the lessee of War Department 1940 Rules of Land Warfare (Rule No. 324) to
the enjoyment of the thing leased, was, nevertheless, a mere act the effect that —
of trespass ("perturbacion de mero hecho") that, under the
Spanish Civil Code of 1889 (in force here until 1950), did not The measure of permissible devastation is found in the strict
exempt the lessee from the duty to pay rent. We find that necessities of war. As an end in itself, as a separate measure of
contention and ruling erroneous and untenable. war, devastation is not sanctioned by the law of war. There must
be some reasonably close connection between the destruction of
The pertinent articles of the Civil Code of Spain of 1889 provide: property and the overcoming of the enemy's army. Thus the rule
OBLICON 1-9-2018 I ACJUCO 34

requiring respect for private property is not violated through


damage resulting from operations, movements, or combats of the Considerando que sobre tales bases de hecho es de desestimar
army; that is, real estate may be utilized for marches, camp sites, el primer motivo del recurso: violacion de los articulos 1.254,
construction of trenches, etc. Buildings may be used for shelter 1.278 y 1.091 del Codigo civil, que sancionan, en terminos
for troops, the sick and wounded, for animals, for reconnaissance, generales, la eficacia de los contratos, puesto que en el presente
cover defense, etc. Fence, woods, crops, buildings, etc., may be caso de los que se trata en definitiva es de determinar si por virtud
demolished, cut down, and removed to clear a field of fire, to de fuerza mayor, la requisa a que se hace referencia, ajena, por
construct bridges, to furnish fuel if imperatively needed for the lo tanto, a culpa, asi del arrendatario como del arrendador, se vio
army. (Emphasis supplied) aquel privado del posible disfrute de la finca arrendada, y de si
por virtud de esta circunstancia esta o no exento de la obligacion
Reference may also be made to Rule 336: de abonar la renta pactada durante el tiempo que subsistio la
incautacion; y es indudable la afirmativa en cuanto al primer
What may be requisitioned. — Practically everything may be extremo, puesto que la sentencia recurrida establece que el
requisitioned under this article (art. LII of the regulations above hecho de que no funcionase la industria y estuvieran los locales
quoted) that is necessary for the maintenance of the army and not cerrados no actuo como causa de la requisa de estos por el
of direct military use, such as fuel, food, forage, clothing, tobacco, Ejercito.
printing presses, type, leather, cloth, etc. Billeting of troops for
quarters and subsistence is also authorized. (Emphasis supplied) Considerando que la sentencia recurrida, en cuanto no da lugar
al pago de las rentas correspondientes al tiempo que duro la
And Forest and Tucker state: incautacion, lejos de infringir, por aplicacion indebida, el art. 1.568
del Codigo civil, se ajusta la orientacion marcada en el mismo,
The billegerent occupant may destroy or appropriate public puesto que este precepto legal dispone que el arrendatario tiene
property which may have a hostile purpose, as forts, arms, accion contra el tercero perturbador de mero hecho en la
armories, etc. The occupying force may enjoy the income from posesion de la finca arrendada, pero no contra la Administracion
the public sources. Strictly private property should be inviolable, o contra los que obran en virtud de un derecho que les
except so far as the necessity of war requires contrary action. corresponde; y aqui la perturbacion que experimento el
(Forest and Tucker, International Law, 9th Ed., p. 277) (Emphasis arrendador en su posesion, como consecuencia de la requisa, no
supplied) puede calificarse como de mero hecho, conforme al citado
articulo, puesto que la finca fue requisada por la autoridad militar
The distinction between confiscation and temporary sequestration para fines de guerra, de donde se sigue que el arrendatario tenia
of private property by a belligerent occupant was also passed que soportar la privacion de su tenencia material a traves del
upon by this Court in Haw Pia vs. China Banking Corporation, 80 arrendador, con quien ha de entenderse la requisa de la cosa
Phil. 604, wherein the right of Japan to sequester or take arrendada.
temporary control over enemy private property in the interest of
its military effort was expressly recognized. In addition, the text of Art. 1560, in its first paragraph ( jam quot.)
assumes that in case of mere disturbance ( perturbacion de mero
We are thus forced to conclude that in evicting the lessee, Manila hecho) "the lessee shall have a direct action against the
Motor Co., Inc. from the leased buildings and occupying the same trespasser." This assumption evidently does not contemplate the
as quarters for troops, the Japanese authorities acted pursuant to case of dispossession of the lessee by a military occupant, as
a right recognized by international and domestic law. Its act of pointed out by Mr. Chief Justice Paras in his dissenting opinion in
dispossession, therefore, did not constitute perturbacion de Reyes vs. Caltex (Phil.) Inc., 84 Phil. 669; for the reason that the
hecho but a perturbacion de derecho for which the lessors lessee could not have a direct action against the military
Villaruel (and not the appellants lessees) were liable (Art. 1560, occupant. It would be most unrealistic to expect that the
supra) and for the consequences of which said lessors must occupation courts, place under the authority of the occupying
respond, since the result of the disturbance was the deprivation belligerent, should entertain at the time a suit for forcible entry
of the lessee of the peaceful use and enjoyment of the property against the Japanese army. The plaintiffs, their lawyers, and in all
leased. Wherefore, the latter's corresponding obligation to pay probability, the Judge and court personnel, would face "severest
rentals ceased during such deprivation. penalties" for such defiance of the invader.

The Supreme Court of Spain, in its Sentencia of 6 December The present case is distinguishable from Lo Ching vs. Archbishop
1944, squarely declared the resolutory effect of the military of Manila (81 Phil., 601) in that the act of the Japanese military
sequestration of properties under lease upon the lessee's involved in the latter case clearly went beyond the limits set by the
obligation to pay rent (Jurisprudencia Civil, Segunda Serie, Tomo Hague Conventions, in seizing the property and delivering it to
8, pp. 583, 608):. another private party; and from Reyes vs. Caltex (Phil.) Inc., 84
Phil. 654, in that the rights of the military occupant under
Considerando que para resolver acerca de la procedencia del international law were not raised or put in issue in said case; and
presente recurso es preciso partir de las bases de hecho moreover, the lessee there, by failing to rescind the lease upon
sentadas en la sentencia recurrida, y no impugnadas al amparo seizure of the premises by the Japanese military, despite the
del numero 7. del articulo 1.692 de la Ley de Enjuiciamiento civil, stipulated power to do so, resumed business and decided to hold
es decir, de que hallandose vigente el contrato de arrendamiento unto the long term lease for the balance of its 20-year period,
celebrado entre actor y demandada, en fecha que no se precisa, starting from December 23, 1940. In the case before us, the
entre los dias del 18 al 31 de julio de 1936, los locales objeto de occupation of the leased property by the Japanese army covered
dicho contrato de arrendamiento, y en los que no funcionaba de the major portion of the five-year contractual period, without any
tiempo anterior la industria para cuyo ejercicio se arrendaron, option to rescind by the lessee.
fueron requisados por el Ejercito Nacional, con motivo de la
guerra civil, para que se instalara en los mismos la Junta de The lessor's position is not improved by regarding the military
Donativos al Ejercito del Sur, aun cundo en dicha incautacion, seizure of the property under lease as a case of force majeure or
que se hizo a la propiedad de la finca, no se observaron las fortuitous event. Ordinarily, a party may not be held responsible
formalidades legales, a causa de las circunstancias therefor, despite the fact that it prevented compliance of its
extraordinarias por que a la sazon atravesaba Sevilla, hecho que obligations. But lease being a contract that calls for prestations
no consta se hiciera saber por los arrendatarios demandados al that are both reciprocal and repetitive (tractum successivum), the
actor, pero que fue notorio en aquella capital, donde residia el obligations of either party are not discharged at any given
actor, que de el debio tener conocimiento. Se estima igualmente moment, but must be fulfilled all throughout the term of the
por la Sala que el hecho de que la industria no funcionara en el contract. As a result, any substantial failure by one party to fulfill
local no tuvo influencia alguna sobre su incautacion por el its commitments at any time during the contract period gives rise
Ejercito. to a failure of consideration (causa) for the obligations of the other
OBLICON 1-9-2018 I ACJUCO 35

party and excuses the latter from the correlative performance, law the lessor is under no implied covenant to repair, or even that
because the causa in lease must exist not only at the perfection the premises shall be fit for the purpose for which they are leased.
but throughout the term of the contract. No lessee would agree to Fowler vs. Bott, 6 Mass. 63; 3 Kent, Com. 465, 466; Broom, Legal
pay rent for premises he could not enjoy. As expressed by Marcel Maxims, 3d ed. 213, 214; Doupe vs. Genin, 45 N. Y. 119;
Planiol (quoted in 4 Castan, Derecho Civil, 7th Edition, p. 264) — Kingbury vs. Westfall, 61 N. Y. 356. Naumberg vs. Young, 15
Vroom, 331; Bowe vs. Hunking, 135 Mass. 380; Manchester
Como la obligacion del arrendador es sucesiva y se renueva Warehouse Co. vs. Carr, L.R. 5 C.P.D. 507.
todos los dias, la subsistencia del arrendamiento se hace
imposible cuando, por cualquier razon, el arrendador no puede The civil law, on the other hand, regards a lease for years as a
ya procurar al arrendatario el disfrute de la cosa. mere transfer of the use and enjoyment of the property; and holds
the landlord bound, without any express covenant, to keep it in
This effect of the failure of reciprocity appears whether the failure repair and otherwise fit for use and enjoyment for the purpose for
is due to fault or to fortuitous event; the only difference being that which it is leased, even when the need of repair or the unfitness
in case of fault, the other party is entitled to rescind the contract is caused by an inevitable accident, and if he does not do so, the
in toto, and collect damages, while in casual non-performance it tenant may have the lease annulled, or the rent abated. Dig. 19,
becomes entitled only to a suspension pro tanto of its own 2, 9, 2; 19, 2, 15, 1, 2; 19, 2, 25, 2; 19, 2, 39; 2 Gomez, Variae
commitments. This rule is recognized in par. 2 of Art. 1558, Resolutiones c. 3, secs. 1-3, 18, 19: Gregorio Lopez in 5 Partidas,
authorizing the lessee to demand reduction of the rent in case of tit. 8, 11. 8, 22; Domat, Droit Civil, pt. 1, lib. 1, tit. 4, sec. 1, no. 1;
repairs depriving him of the possession of part of the property; sec. 3 nos. 1, 3, 6, Pothier, Contract de Louage, nos. 3, 6, 11, 22,
and in Art. 1575, enabling the lessee of rural property to demand 53, 103, 106, 139-155.
reduction of the rent if more than one-half of the fruits are lost by
extraordinary fortuitous event. Of course, where it becomes It is accordingly laid down in the Pandects, on the authority of
immediately apparent that the loss of possession or enjoyment Julian, "If anyone has let an estate, that, even if anything happens
will be permanent, as in the case of accidental destruction of a by vis major, he must make it good, he must stand by his
leased building, the lease contract terminates. contract," si quis fundum locaverit, ut, etiamsi quid vi majore
accidisset, hoc ei praestaretur, pacto standum esse; Dig. 19, 2, 9,
Applying these principles, the Sentencia of December 1944, 2; and on the authority of Ulpian, that "A lease does not change
already adverted to, ruled as follows: the ownership," non solet locatio dominiun mutare; Dig. 19, 2, 39;
and that the lessee has a right of action, if he cannot enjoy the
Considerando que privado el arrendador, por tal hecho, del thing which he has hired, si re quam conduxit frui non liceat,
disfrute de esta, es manifiesta la imposibilidad en que se vio de whether because his possession, either of the whole or of part of
cumplir la tercera de las obligaciones que el impone el articulo the field, is not made good, or a house, or stable or sheepfold, is
1.554 del Codigo Civil, obligacion (la de mantener al arrendatario not repaired; and the landlord ought to warrant the tenant,
en el disfrute de la cosa arrendada) que ha de entenderse dominum colono praestare debere, against every irresistible
reciproca de la de pago de renta pactada, que impone al force, omnim vim cui resisti non potest, such as floods, flocks of
arrendatario el numero primero del art. 1.555 de dicho Cuerpo birds, or any like cause, or invasion of enemies; and if the whole
legal, y por ello no puede ser exigida. crop should be destroyed by a heavy rainfall, or the olives should
be spoiled by blight, or by extraordinary heat of the sun, solis
Considerando que, aunque no sean estrictamente aplicables al fervore non assueto, it would be the loss of the landlord, damnum
caso los articulos 1.124, 1.556 y 1.568, que se citan como domini futurum; and so if the field falls in by an earthquake, for
infringidos por el recurrente, suponiendo que a ellos ha entendido there must be made good to the tenant a field that he can enjoy,
referirse la Audiencia (lo que impediria, en todo caso, la oportere enim agrum praestari conductori, ut frui possit; but if any
estimacion del recurso por este motivo, ya que dichos articulos loss arises from defects in the thing itself, si qua tamen vitia ex
no se citan en la sentencia de instancia), es evidente que ellos ipsa re oriantur, as if wine turns sour, or standing corn is spoiled
proclaman la reciprocidad de las obligaciones entre arrendatario by worms or weeds, or if nothing extraordinary happens, si vero
y arrendador, y en este sentido, tratandose de un incumplimiento nihil extra consuetudinem acciderit, it is the loss of the tenant,
inculpable decontrato, pueden servir, como tambien el 1.558, en damnum coloni esse. Dig. 19, 2; 15, 1, 2. (Emphasis supplied)
cuanto preven la reduccion de rentas o posible restriccion del
contrato cuando el arrendatario se ve privado, por obras In short, the law applies to leases the rule enunciated by the
realizadas en la finca arrendada, del disfrute de este, de Canonists and the Bartolist School of Post glossatorse, that
fundamento, con los demas preceptos invocados, a una "contractus qui tractum successivum habent et dependentiam de
extencion de renta mientras subsiste la imposibilidad de utilizar la futuro, sub conditione rebus sic stantibus intelliguntur," they are
cosa arrendada, sobre todo cuando los articulos 157 y 158 del understood entered subject to the condition that things will remain
Reglamento de Requisas de 13 de enero de 1921 estatuyen as they are, without material change.
claramente que las requisas de edificio se hacen a la propiedad,
y es el propietario el que puede pedir indemnization, uno de cuyos It is also worthy of note that the lessors, through Dr. Javier
elementos es el precio del alquiler que le sea satisfecho por el Villaruel, agreed after liberation to a renewal of the contract of
inmueble incautado. lease for another five years (from June 1, 1946 to May 31 of 1951)
without making any reservation regarding the alleged liability of
We are aware that the rule in the common law is otherwise, due the lessee company for the rentals corresponding to the period of
to its regarding a lease as a conveyance to the lessee of a occupancy of the premises by the Japanese army, and without
temporary estate or title to the leased property so that loss of insisting that the non-payment of such rental was a breach of the
possession due to war or other fortuitous event leaves the tenant contract of lease. This passivity of the lessors strongly supports
liable for the rent in the absence of stipulation. The fundamental the claim of the lessees that the rentals in question were verbally
difference between the common law and the civil law concepts waived. The proffered explanation is that the lessors could not
has been outlined by the United States in Viterbo vs. Friedlander, refuse to renew the lease, because the privilege of renewal had
30 L. Ed. (U.S.) pp. 776, 778, in this wise: been granted to the lessees in the original contract. Such excuse
is untenable: if the lessors deemed that the contract had been
But as to the nature and effect of a lease for years, at a certain breached by the lessee's non-payment of the occupation rents
rent which the lessee agrees to pay, and containing no express how could they admit the lessee's right to renew a contract that
covenant on the part of the lessor, the two systems differ the lessee itself had violated?
materially. The common law regards such a lease as the grant of
an estate for years, which the lessee takes a title in, and is bound But this is not all. The lessors accepted payment of current rentals
to pay the stipulated rent for, notwithstanding any injury by flood, from October 1945 to June 1946. It was only in July 1946 that they
fire or external violence, at least unless the injury is such a insisted upon collecting also the 1942-1945 rents, and refused to
destruction of the land as to amount to an eviction; and by that accept further payments tendered by the lessee unless their right
OBLICON 1-9-2018 I ACJUCO 36

to collect the occupation rental was recognized or reserved. After risk of loss that lay upon them. (3 Castan, Der. Civ., 8th Ed., p.
refusing the rents from July to November 1946, unless the lessee 145; 4 Puig Peña, Der. Civ., part. 1, p. 234; Diaz Pairo, Teoria
recognized their right to occupation rentals, the appellees Gen. de las Obligaciones [3rd Ed.], Vol. 1, pp. 192-193).
(lessors) demanded rescission of the contract and a rental of
P1,740 monthly in lieu of the stipulated P350 per month. (Exhibit In view of the foregoing, we hold:lawphil.net
"C").
(a) That the dispossession of the lessee from the premises
This attitude of the lessors was doubly wrongful: first, because as by the Japanese army of occupation was not an act of mere
already shown, the dispossession by the Japanese army trespass ( perturbacion de mero hecho) but one de derecho
exempted the lessee from his obligation to pay rent for the period chargeable to the lessors;
of its ouster; and second, because even if the lessee had been
liable for that rent, its collection in 1946 was barred by the (b) That such dispossession, though not due to fault of
moratorium order, Executive Order No. 32, that remained in force lessors or lessee, nevertheless resulted in the exemption of the
until replaced by Rep. Act 342 in 1948. To apply the current lessee from its obligation to pay rent during the period that it was
rentals to the occupation obligations would amount to enforcing deprived of the possession and enjoyment of the premises
them contrary to the moratorium decreed by the government. leased;

Clearly, then, the lessor' insistence upon collecting the occupation (c) That the insistence of the lessors to collect such rentals
rentals for 1942-1945 was unwarranted in law. Hence, their was unwarranted;
refusal to accept the current rentals without qualification placed
them in default (mora creditoris or accipiendi) with the result that (d) That the lessors were not justified in refusing to accept
thereafter, they had to bear all supervening risks of accidental the tender of current rentals unless the lessee should recognize
injury or destruction of the leased premises. While not expressly their right to the rents corresponding to the period that the lessee
declared by the Code of 1889, this result is clearly inferable from was not in possession;
the nature and effects of mora, and from Articles 1185, 1452 [par.
3] and 1589). (e) That by their improper refusal to accept the current rents
tendered by the lessee, the lessors incurred in default (mora) and
ART. 1185. When the obligation to deliver a certain and they must shoulder the subsequent accidental loss of the
determinate thing arises from the commission of a crime or premises leased;
misdemeanor the obligor shall not be exempted from the payment
of its value, whatever the cause of its loss may have been, unless, (f) That the mora of the lessors was not cured by the failure
having offered the thing to the person entitled to receive it, the of the lessee to make the consignation of the rejected payments,
latter should have refused without reason to accept it. but the lessee remained obligated to pay the amounts tendered
and not consigned by it in court.
Art. 1452. ....
Consequently, it was reversible error to sentence the appellants
If fungible things should be sold for a price fixed with relation to to pay P2,165 a month as reasonable value of the occupation of
weight, number, or measure, they shall not be at the purchaser's the premises from July 1946, and the value of the destroyed
risk until they have been weighed, counted, or measured, unless buildings amounting to P30,000.
the purchaser should be in default.
Wherefore, the decision appealed from is modified in the sense
ART. 1589. If the person who contracted to do the work that the appellant Manila Motor Company should pay to the
bound himself to furnish the materials, he shall bear the loss in appellees Villaruel only the rents for the leased premises
case of the destruction of the work before it is delivered, unless corresponding to the period from July up to November 1946, at
its acceptance has been delayed by the default of the other party. the rate of P350 a month, or a total of P1,750. Costs against
appellees in both instances. So ordered.
While there is a presumption that the loss of the thing leased is
due to the fault of the lessee (Civil Code of 1889, Art. 1563), it is Paras, C. J., Bengzon, Padilla, Montemayor, Bautista Angelo,
noteworthy that the lessor have not invoked that presumption Labrador, Concepcion and Endencia, JJ., concur.
either here or in the court below. On the contrary, the parties and
the trial court have all proceeded and discussed the issues taking
for granted that the destruction of the leased buildings was purely
fortuitous. We see no reason for departing from that assumption
and further prolonging this litigation..

That the lessee and sublessee did not consign or deposit in court
the rentals tendered to and improperly rejected by the lessors, did
not render the debtor liable for default (mora solvendi) nor
answerable for fortuitous events because, as explained by the
Supreme Court of Spain in its Sentencia of 5 June 1944 —

Al exigir el art. 1176 del Codigo Civil la consignacion para liberar


al deudor no quiere decir que necesariamente haya de
practicarse, y no baste el ofrecimiento de pago que de aquella no
fuere seguido, a efectos de exclusion de las consecuencias de la
mora solvendi. (8 Manresa, Comentarios, 5th Ed., Vol. 1, p. 136).

In other words, the only effect of the failure to consign the rentals
in court was that the obligation to pay them subsisted (P.N.B. vs.
Relativo, 92 Phil., 203) and the lessee remained liable for the
amount of the unpaid contract rent, corresponding to the period
from July to November, 1946; it being undisputed that, from
December 1946 up to March 2, 1948, when the commercial
buildings were burned, the defendants-appellants have paid the
contract rentals at the rate of P350 per month. But the failure to
consign did not eradicate the default (mora) of the lessors nor the
OBLICON 1-9-2018 I ACJUCO 37

G.R. No. 126486 February 9, 1998 credit term, vis-a-vis the various sales invoices and/or delivery
receipts;
BARONS MARKETING CORP., petitioner,
vs. 2. 25% of the preceding obligation for and as attorney's
COURT OF APPEALS and PHELPS DODGE PHILS., INC. fees;
respondents.
3. P10,000.00 as exemplary damages;

KAPUNAN, J.: 4. Costs of suit.3

The instant petition raises two issues: (1) whether or not private Both parties appealed to respondent court. Private respondent
respondent is guilty of abuse of right; and (2) whether or not claimed that the trial court should have awarded it the sum of
private respondent is entitled to interest and attorney's fees. P3,802,478.20, the amount which appeared in the body of the
complaint and proven during the trial rather than P3,1081000.00
The facts are undisputed: The latter amount appears in petitioner's prayer supposedly as a
result of a typographical error.
On August 31, 1973, plaintiff [Phelps Dodge, Philippines, Inc.
private respondent herein] appointed defendant [petitioner On the other hand, petitioner reiterated its claims for damages as
Barons Marketing, Corporation] as one of its dealers of electrical a result of "creditor's abuse." It also alleged that private
wires and cables effective September 1, 1973 (Exh. A). As such respondent failed to prove its cause of action against it.
dealer, defendant was given by plaintiff 60 days credit for its
purchases of plaintiff's electrical products. This credit term was to On 25 June 1996, the Court of Appeals rendered a decision
be reckoned from the date of delivery by plaintiff of its products to modifying the decision of the trial court, thus:
defendant (Exh. 1).
WHEREFORE, from all the foregoing considerations, the Court
During the period covering December 1986 to August 17, 1987, finds Phelps Dodge Phils., Inc. to have preponderantly proven its
defendant purchased, on credit, from plaintiff various electrical case and hereby orders Barons Marketing, Inc. to pay Phelps
wires and cables in the total amount of P4,102,438.30 (Exh. B to Dodge the following:
K). These wires and cables were in turn sold, pursuant to previous
arrangements, by defendant to MERALCO, the former being the 1. P3,802,478.20 constituting the unpaid balance of
accredited supplier of the electrical requirements of the latter. defendant's purchases from plaintiff and interest thereon at 12%
Under the sales invoices issued by plaintiff to defendant for the per annum computed from the respective expiration of the 60 day
subject purchases, it is stipulated that interest at 12% on the credit term, vis-a-vis the various sales invoices and/or delivery
amount due for attorney's fees and collection (Exh. BB).1 On receipts; and
September 7, 1987, defendant paid plaintiff the amount of
P300,000.00 out of its total purchases as above-stated (Exh. S), 2. 5% of the preceding obligation for and as attorney's
thereby leaving an unpaid account on the aforesaid deliveries of fees.
P3,802,478.20. On several occasions, plaintiff wrote defendant
demanding payment of its outstanding obligations due plaintiff No costs.4
(Exhs. L, M, N, and P). In response, defendant wrote plaintiff on
October 5, 1987 requesting the latter if it could pay its outstanding Petitioner Barons Marketing is now before this Court alleging that
account in monthly installments of P500,000.00 plus 1% interest respondent court erred when it held (1) private respondent Phelps
per month commencing on October 15, 1987 until full payment Dodge not guilty of "creditor's abuse," and (2) petitioner liable to
(Exh. O and O-4). Plaintiff, however, rejected defendant's offer private respondent for interest and attorney's fees.
and accordingly reiterated its demand for the full payment of
defendant's account (Exh. P).2 I

On 29 October 1987, private respondent Phelps Dodge Phils., Petitioner does not deny private respondent's rights to institute an
Inc. filed a complaint before the Pasig Regional Trial Court against action for collection and to claim full payment. Indeed, petitioner's
petitioner Barons Marketing Corporation for the recovery of right to file an action for collection is beyond cavil.5 Likewise,
P3,802,478.20 representing the value of the wires and cables the private respondent's right to reject petitioner's offer to pay in
former had delivered to the latter, including interest. Phelps installments is guaranteed by Article 1248 of the Civil Code which
Dodge likewise prayed that it be awarded attorney's fees at the states:
rate of 25% of the amount demanded, exemplary damages
amounting to at least P100,000.00, the expenses of litigation and Art. 1248. Unless there is an express stipulation to that
the costs of suit. effect, the creditor cannot be compelled partially to receive the
prestations in which the obligation consists. Neither may the
Petitioner, in its answer, admitted purchasing the wires and debtor be required to make partial payments.
cables from private respondent but disputed the amount claimed
by the latter. Petitioner likewise interposed a counterclaim against However, when the debt is in part liquidated and in part
private respondent, alleging that it suffered injury to its reputation unliquidated, the creditor may demand and the debtor may effect
due to Phelps Dodge's acts. Such acts were purportedly the payment of the former without waiting for the liquidation of the
calculated to humiliate petitioner and constituted an abuse of latter.
rights.
Under this provision, the prestation, i.e., the object of the
After hearing, the trial court on 17 June 1991 rendered its obligation, must be performed in one act, not in parts.
decision, the dispositive portion of which reads:
Tolentino concedes that the right has its limitations:
WHEREFORE, from all the foregoing considerations, the Court
finds Phelps Dodge Phils., Inc. to have preponderantly proven its Partial Prestations. — Since the creditor cannot be compelled to
case and hereby orders Barons Marketing, Inc. to pay Phelps accept partial performance, unless otherwise stipulated, the
Dodge the following: creditor who refuses to accept partial prestations does not incur
in delay or mora accipiendi, except when there is abuse of right
1. P3,108,000.00 constituting the unpaid balance of or if good faith requires acceptance.6
defendant's purchases from plaintiff and interest thereon at 12%
per annum computed from the respective expiration of the 60 day
OBLICON 1-9-2018 I ACJUCO 38

Indeed, the law, as set forth in Article 19 of the Civil Code, in accordance with the purpose for which it was established, and
prescribes a "primordial limitation on all rights" by setting certain must not be excessive or unduly harsh; there must be no intention
standards that must be observed in the exercise thereof.7 Thus: to injure another. Ultimately, however, and in practice, courts, in
the sound exercise of their discretion, will have to determine all
Art. 19. Every person must, in the exercise of his rights and in the facts and circumstances when the exercise of a right is unjust,
the performance of his duties, act with justice, give everyone his or when there has been an abuse of right.11
due, and observe honesty and good faith.
The question, therefore, is whether private respondent intended
Petitioner now invokes Article 19 and Article 218 of the Civil Code, to prejudice or injure petitioner when it rejected petitioner's offer
claiming that private respondent abused its rights when it rejected and filed the action for collection.
petitioner's offer of settlement and subsequently filed the action
for collection considering: We hold in the negative. It is an elementary rule in this jurisdiction
that good faith is presumed and that the burden of proving bad
. . . that the relationship between the parties started in 1973 faith rests upon the party alleging the same.12 In the case at bar,
spanning more than 13 years before the complaint was filed, that petitioner has failed to prove bad faith on the part of private
the petitioner had been a good and reliable dealer enjoying a good respondent. Petitioner's allegation that private respondent was
credit standing during the period before it became delinquent in motivated by a desire to terminate its agency relationship with
1987, that the relationship between the parties had been a fruitful petitioner so that private respondent itself may deal directly with
one especially for the private respondent, that the petitioner Meralco is simply not supported by the evidence. At most, such
exerted its outmost efforts to settle its obligations and avoid a suit, supposition is merely speculative.
that the petitioner did not evade in the payment of its obligation to
the private respondent, and that the petitioner was just asking a Moreover, we find that private respondent was driven by very
small concession that it be allowed to liquidate its obligation to legitimate reasons for rejecting petitioner's offer and instituting the
eight (8) monthly installments of P500,000.00 plus 1% interest per action for collection before the trial court. As pointed out by private
month on the balance which proposal was supported by post- respondent, the corporation had its own "cash position to protect
dated checks.9 in order for it to pay its own obligations." This is not such "a lame
and poor rationalization" as petitioner purports it to be. For if
Expounding on its theory, petitioner states: private respondent were to be required to accept petitioner's offer,
there would be no reason for the latter to reject similar offers from
In the ordinary course of events, a suit for collection of a sum of its other debtors. Clearly, this would be inimical to the interests of
money filed in court is done for the primary purpose of collecting any enterprise, especially a profit-oriented one like private
a debt or obligation. If there is an offer by the debtor to pay its respondent. It is plain to see that what we have here is a mere
debt or obligation supported by post-dated checks and with exercise of rights, not an abuse thereof Under these
provision for interests, the normal response of a creditor would be circumstances, we do not deem private respondent to have acted
to accept the offer of compromise and not file the suit for in a manner contrary to morals, good customs or public policy as
collection. It is of common knowledge that proceedings in our to violate the provisions of Article 21 of the Civil Code.
courts would normally take years before an action is finally settled.
It is always wiser and more prudent to accept an offer of payment Consequently, petitioner's prayer for moral and exemplary
in installment rather than file an action in court to compel the damages must thus be rejected. Petitioner's claim for moral
debtor to settle his obligation in full in a single payment. damages is anchored on Article 2219 (10) of the Civil Code which
states:
xxx xxx xxx
Art. 2219. Moral damages may be recovered in the
. . . Why then did private respondent elect to file a suit for following and analogous cases:
collection rather than accept petitioner's offer of settlement,
supported by post-dated checks, by paying monthly installments xxx xxx xxx
of P500,000.00 plus 1% per month commencing on October 15,
1987 until full payment? The answer is obvious. The action of (10) Acts and actions referred to in articles 21, 26, 27, 28,
private respondent in filling a suit for collection was an abuse of 29, 30, 32, 34, and 35.
right and exercised for the sole purpose of prejudicing and injuring
the petitioner.10 xxx xxx xxx

Petitioner prays that the Court order private respondent to pay Having ruled that private respondent's acts did not transgress the
petitioner moral and exemplary damages, attorney's fees, as well provisions of Article 21, petitioner cannot be entitled to moral
as the costs of suit. It likewise asks that it be allowed to liquidate damages or, for that matter, exemplary damages. While the
its obligation to private respondent, without interests, in eight amount of exemplary damages need not be proved, petitioner
equal monthly installments. must show that he is entitled to moral, temperate or compensatory
damages before the court may consider the question of whether
Petitioner's theory is untenable. or not exemplary damages should be awarded.13 As we have
observed above; petitioner has failed to discharge this burden.
Both parties agree that to constitute an abuse of rights under
Article 19 the defendant must act with bad faith or intent to It may not be amiss to state that petitioner's contract with private
prejudice the plaintiff. They cite the following comments of respondent has the force of law between them.14 Petitioner is
Tolentino as their authority: thus bound to fulfill what has been expressly stipulated therein.15
In the absence of any abuse of right, private respondent cannot
Test of Abuse of Right. — Modern jurisprudence does not permit be allowed to perform its obligation under such contract in parts.
acts which, although not unlawful, are anti-social. There is Otherwise, private respondent's right under Article 1248 will be
undoubtedly an abuse of right when it is exercised for the only negated, the sanctity of its contract with petitioner defiled. The
purpose of prejudicing or injuring another. When the objective of principle of autonomy of contracts16 must be respected.
the actor is illegitimate, the illicit act cannot be concealed under
the guise of exercising a right. The principle does not permit acts II
which, without utility or legitimate purpose cause damage to
another, because they violate the concept of social solidarity Under said contract, petitioner is liable to private respondent for
which considers law as rational and just. Hence, every abnormal the unpaid balance of its purchases from private respondent plus
exercise of a right, contrary to its socio-economic purpose, is an 12% interest. Private respondent's sales invoices expressly
abuse that will give rise to liability. The exercise of a right must be provide that:
OBLICON 1-9-2018 I ACJUCO 39

. . . Interest at 12% per annum will be charged on all overdue


account plus 25% on said amount for attorney's fees and
collection. . . .17

It may also be noted that the above stipulation, insofar as it


provides for the payment of "25% on said amount for attorney's
fees and collection (sic)," constitutes what is known as a penal
clause.18 Petitioner is thus obliged to pay such penalty in addition
to the 12% annual interest, there being an express stipulation to
that effect.

Petitioner nevertheless urges this Court to reduce the attorney's


fees for being "grossly excessive," "considering the nature of the
case which is a mere action for collection of a sum of money." It
may be pointed out however that the above penalty is supposed
to answer not only for attorney's fees but for collection fees as
well. Moreover:

. . . the attorneys' fees here provided is not, strictly speaking, the


attorneys' fees recoverable as between attorney and client
spoken of and regulated by the Rules of Court. Rather, the
attorneys' fees here are in the nature of liquidated damages and
the stipulation therefor is aptly called a penal clause. It has been
said that so long as such stipulation does not contravene law,
morals, or public order, it is strictly binding upon defendant. The
attorneys' fees so provided are awarded in favor of the litigant, not
his counsel. It is the litigant, not counsel, who is the judgment
creditor entitled to enforce the judgment by execution. 19

Nonetheless, courts are empowered to reduce such penalty if the


same is "iniquitous or unconscionable." Article 1229 of the Civil
Code states thus:

Art. 1229. The judge shall equitably reduce the penalty


when the principal obligation has been partly or been irregularly
complied with by the debtor. Even if there has no performance,
the penalty may also be reduced by the courts if it is iniquitous or
unconscionable. (Emphasis supplied.)

The sentiments of the law are echoed in Article 2227 of the same
Code:

Art. 2227. Liquidated damages, whether intended as an


indemnity or a penalty, shall be equitably reduced if they are
iniquitous or unconscionable.

It is true that we have upheld the reasonableness of penalties in


the form of attorney's fees consisting of twenty-five percent (25%)
of the principal debt plus interest.20 In the case at bar, however,
the interest alone runs to some four and a half million pesos
(P4.5M), even exceeding the principal debt amounting to almost
four million pesos (P4.0M). Twenty five percent (25%) of the
principal and interest amounts to roughly two million pesos (P2M).
In real terms, therefore, the attorney's fees and collection fees are
manifestly exorbitant. Accordingly, we reduce the same to ten
percent (10%) of the principal.

Private respondent, however, argues that petitioner failed to


question the award of attorney's fees on appeal before
respondent court and raised the issue only in its motion for
reconsideration. Consequently, petitioner should be deemed to
have waived its right to question such award.

Private respondent's attempts to dissuade us from reducing the


penalty are futile. The Court is clothed with ample authority to
review matters, even if they are not assigned as errors in their
appeal, if it finds that their consideration is necessary in arriving
at a just decision of the case.21

WHEREFORE, the decision of the Court of Appeals is hereby


MODIFIED in that the attorney's and collection fees are reduced
to ten percent (10%) of the principal but is AFFIRMED in all other
respects.

SO ORDERED.

You might also like