6 Kevin is presenting the Quality is the Quality is the degree that the
project quality plan to degree which product meets the
the stakeholder meeting. the product requirements. Grade is the
One of the stakeholders fulfills the technical characteristics. A
asks what the difference requirements low-grade example is a basic
is between grade and while grade is cellphone meets the need to
quality. What is your technical make phone calls. A high-
best response? characteristics grade example would be an
of the product. advanced smartphone with
extra features.
Num Mock Question Correct Answer Answer Justification
10 You are into the third Forming Since they will be adding new
phase of a project and members, the best choice is
your core project team forming as storming is not an
will be taking on four option.
new members. What
stage of the Tuckman
ladder will they be on
when they start this
phase?
Num Mock Question Correct Answer Answer Justification
18 The project team have Hire a mediator Having a mediator is the best
had a number of to help resolve course of action without
problems with the the issue. having to enter into a formal
vendor and it has been legal proceeding.
decided and supported
by senior management to
terminate the contract.
The vendor is demanding
full payment but the
deliverables were not
completed. What is the
next best action?
Num Mock Question Correct Answer Answer Justification
19 The company is being Begin the close Early termination starts the
bought out and the project process. close project process. PMBOK
project that was just p.101
started has been
terminated. What
should the next step be
by the project manager?
20 You are managing a You should buy To calculate this, The break
project that involves a the website if it even cost is at 12 months. If
new website. If you build will be used less it is used less than 12 months
the website, it will cost than 12 months it will be cheaper to buy from
$240,000 to build and the vendor. A. Total cost of
$9,000 per month to the project if the website is
maintain. If you go to an created in-house and
outside vendor, it will maintained for 12 months @
cost $180,000 to build $9000 per month = 240,000 +
and $14,000 to maintain. (12*9000) = 348,000. B. Total
What is your best cost of the project if the
option? website is developed by an
outised vendor and
mainatined for 12 months @
14000 per month = 180,000 +
(12*14000) = 348,000. Hence
if you plan to use the website
for less than 12 months, buy
from the outside vendor.
Num Mock Question Correct Answer Answer Justification
21 The PMO has made you Review the This is the most likely place to
the project manager human resource find that information.
after the previous management
manager left for a new plan from the
position. Your project PMO
has completed a work
package and two
members of your team
are not needed after this.
Where should you get
the information on how
to release them?
25 During the weekly risk Plan a new This would be the next step.
management meeting, response.
your team is reviewing a
high risk situation. They
realize that the original
response will not work as
planned if the risk occurs.
What should the next
step be?
26 Your team has been told Quality audits This is the primary reason for
that they will be audited are to look for quality audits.
by an outside quality inefficiencies in
management firm and the company's
they are concerned. policies.
What do you tell them?
Num Mock Question Correct Answer Answer Justification
27 Your quality team is not Request that The procurements have been
satisfied with the work of they rework the rejected and need to be
the vendor and has parts to the submitted for rework.
rejected the desired
deliverables. You need tolerances.
to do which of the
following with the seller?
39 You are informed that Work with the You will need a charter as
you will be taking over a sponsor and quickly as possible.
poorly managed project. develop a
You discover that a charter.
charter was never
written for this project.
How you should
proceed?
47 Your project has an initial Cost baseline The only change that is
budget of $100,000. A indicated by the question is
couple of months into the new estimate to
the project you perform complete the project, which
a budget analysis. You is the cost baseline.
should have spent
$50,000 and 100 hours
on the project. Upon
review, you discover that
$60,000 has been spent
and that 110 hours have
been completed which
should have cost
$45,000. You reevaluate
the remaining work to be
done and your new
budget is $120,000.
What baselines must be
changed?
Num Mock Question Correct Answer Answer Justification
49 Which of the following is Firm fixed price This is the most common
the most commonly used contract and the seller has to
contract and most deal with any risks
advantageous to the
buyer?
50 Your project has an initial CPI = .75, SPI = CPI = EV/AC = $45,000 /
budget of $100,000. A 1.1 $60,000 = .75 SPI = EV/PV =
couple of months into 110/100 = 1.1
the project you perform
a budget analysis. You
should have spent
$50,000 and 100 hours
on the project. Upon
review, you discover that
$60,000 has been spent
and that 110 hours have
been completed which
should have cost
$45,000. You reevaluate
the remaining work to be
done and your new
budget is $120,000.
What is the CPI and SPI?
Num Mock Question Correct Answer Answer Justification
55 At the end of the first Critical path This is the proper term for
month of a six month method what the project manager is
project, the project doing.
manager is reanalyzing
the schedule. She is
putting together a
sequence of activities
with the least amount of
scheduling flexibility.
What is this called?
Num Mock Question Correct Answer Answer Justification
60 One of the key functions Communicate This is the main activity for
of the project manager the project manager.
during directing and
managing the project is
to do what?
Num Mock Question Correct Answer Answer Justification
72 The virtual project team Well defined These will be the most critical
consists of people communications tools for success.
located in the seven and people
different countries. skills
What will be the the
most critical tools for a
successful project?
74 You are meeting with the Executing Acquiring the project team
human resources process group takes place during the
department about executing process group.
acquiring the project
team. What process
group are you in?
77 Due to severe quality Permit the cost Since quality is the main
problems, the project to increase to issue, costs can increase if
sponsor has told the correct the root the root cause is corrected.
project manager that cause of the
quality is the most problem.
important issue now. If a
problem occurs with
quality, what is the best
course of action?
Num Mock Question Correct Answer Answer Justification
80 The project you have Set up new New ground rules for
been managing has been ground rules for meetings would be beneficial
hard with a large number meetings. for the team.
of approved changes.
The team has been
struggling to keep up and
meetings are uncivil.
Two team members will
only attend by webcam
and the rest of the team
gets upset over the latest
change. What is the best
step to take?
81 One of the inputs to the The stakeholder This is the most appropriate
plan the risk register allows answer.
management process is the project
the stakeholder register. manager to see
What is the best reason what the roles
this is needed in planning are of each
for risks? stakeholder.
Num Mock Question Correct Answer Answer Justification
83 The team wants to know It allows the This is the key benefit of
why they need to project manager managing stakeholder
maintain to increase engagement.
communications with the support and
stakeholders all the way decrease
through the project. resistance in
What is the key benefit order to achieve
of stakeholder success.
engagement?
Num Mock Question Correct Answer Answer Justification
86 During a meeting with Keep them The project sponsor has high
the project management satisfied power but low interest due to
team, the project this new priority. Review the
sponsor mentions that he power/interest grid on
has to focus on a higher PMBOK p. 397.
priority project. Your
project is running
smoothly but you still
need some support.
Your strategy should be
to do what with the
sponsor?
90 The computer upgrade Emails with the This is not the best way to
project you are managing stakeholders to handle stakeholders.
is very complex and was review all
difficult to get approval. rejected
A lot of stakeholders requests to
wanted everything remind them
customized for their not to request it
department but this was again.
not possible. As you are
now four months into
the project, change
requests are starting to
come in. What will not
help you in rejecting
change requests for
items refused during the
project initiation?
Num Mock Question Correct Answer Answer Justification
97 The project team has Critical chain The critical chain method
developed a project method allows the team to place
schedule. However, they buffers on the project
find out that a number of schedule path to account for
key resources will be limited resources.
limited during the
project. What method of
scheduling should they
consider using to help
with this?
100 Three point estimating Triangular These are the proper terms
has two common distribution and for these estimating
formulas. These are Beta techniques.
known as which? distribution
109 When are risk responses Control risks Risk responses are
implemented? implemented during control
risks. PMBOK p.309
Num Mock Question Correct Answer Answer Justification
111 Peter is asking what a Positive risks Positive risks those risks that
positive risk is as he says are those risks would have a positive effect
risks are all negative. where the on the project, such as too
You tell him what? project would many orders.
benefit from an
event.
Num Mock Question Correct Answer Answer Justification
114 There are five tools and Organizational This is one of the tools and
techniques used in the theories techniques in the plan human
plan human resources resources process.
process. Which of the
following is one of these?
Num Mock Question Correct Answer Answer Justification
115 You are in the middle of Set up a This is the best course of
the project when you meeting with action as it presents possible
discover that two key the project workarounds.
materials will not be sponsor to
available as planned. discuss the
Your best course of impact and
action is to do what? possible
workarounds.
117 The buyer has completed Organizational These are part of the
the purchase and Sue is process assets organizational process
putting the final updates updates. The key item is
documents into the lessons learned. PMBOK
closed procurements file. p.389
These include the
procurement file, lessons
learned and the formal
acceptance letter. These
are part of which of the
following?
Num Mock Question Correct Answer Answer Justification
120 There are seven outputs Selected sellers This is an output of the
in the plan procurement conduct procurements
management process. process.
Which of these is not a
output?
121 The project manager Quality This is the plan that will
informs the team that management change.
they need to plan how to plan
implement the quality
policy. If this plan
changes, which plan will
also have to change?
Num Mock Question Correct Answer Answer Justification
122 All of the following are Create the WBS This is a part of planning.
part of the direct and
manage project work
process except?
123 The project charter you Project sponsor The project sponsor will have
are working on is being the primary authority to
changed frequently by allow or refuse changes
two of the before the charter is
stakeholders. Who has complete.
the primary responsibility
to decide if these
changes are necessary?
126 The team is preparing for Quality control This is an input to the
a quality assurance audit measurements perform quality assurance
and they are gathering process.
the materials for this.
What do they need?
129 As the team works on The deliverables While this does occur, it is
closing out the phase, a are accepted. not a key benefit in closing
new intern asks what are the project. PMBOK p.100
the main benefits of a
formal closing when all of
the work has been done.
What is not a key benefit
of closing the project?
130 Your project is on budget Report on the This is the objective of the
and on schedule. Your progress of the status meeting.
team has come up with a demo and
demo for the sales team inform them
to use for making their that it is
presentations to complete.
prospective
customers. You will do
which of the following at
the next stakeholder
project status meeting?
Num Mock Question Correct Answer Answer Justification
132 Which of the following Leads and lags Leads and lags do not affect
tools is the primary work or resources. PMBOK
method to adjust the p.187
start times of a successor
activity without work or
resource impact?
134 The project will involve Enroll the team Since the team is not used to
far more communication in a an elevated requirement for
than your team has been communications communications, a seminar
used to in previous seminar would be best for them to be
projects. What is the trained.
best way to ensure the
best communication with
all stakeholders
throughout the project?
135 The project has a CPI of Put a quality This is the best action to take.
.9 and an SPI of .92 when assurance team
a key stakeholder asks to review the
you about some concerns project and the
she has on the quality of quality
the project standards. standards to
What should you do in demonstrate
this situation? that the project
is meeting the
quality
standards.
Num Mock Question Correct Answer Answer Justification
136 You are approached by a Inform him that This is the ethical thing to do.
key stakeholder who you are unable
offers you a promotion if to do that.
you delay the project by
a few days. What is your
best response?
137 The project had a major Review the This is the best course of
problem and your team communications action. Some stakeholders
is now in crisis. What management may need immediate
should be done with plan. notification while others
communicating the need that information later.
problem?
139 What is the only output The risk This is the only output.
of the plan risk management
management process? plan
Num Mock Question Correct Answer Answer Justification
140 Valerie has been Variance and This is looking for outcomes
comparing the last six trend analysis that may forecast potential
weeks of performance deviations.
data. She notices that
everything is still within
specifications but that
the data appears to be
going up a couple
percentage points each
week. She is involved in
what activity?
141 The project manager is Variance report This is the correct report.
asking for a report which
shows actual results
versus planned results.
Which report will provide
this information?
142 There are three risk Risk register The risk register documents
themes or attitudes that the results of risk analysis and
can affect an risk response planning.
organization and
stakeholders. Which one
of this is not considered
an attitude regarding
risk?
144 The project sponsor Power / Interest The power / interest grid
wants a list of key grid groups stakeholders based on
stakeholders along with their power and interest in
their level of authority the project.
and their concern about
the upcoming project.
This is known as what?
146 The project is nearing Have the This keeps them most
completion but there is stakeholders involved at this late stage.
one last milestone to review the
reach. The initial requirements
excitement of the that remain to
stakeholders is long gone be met.
and you need to keep
them involved. What
would be the best way to
do this?
Num Mock Question Correct Answer Answer Justification
147 Victoria is collecting the Tell the This is the best course of
requirements for the stakeholder action as this request had
project scope and a key that the already been evaluated.
stakeholder asks to requirement
include a requirement was denied
which was denied in the while
charter. What should developing the
she do next? project charter.
151 You are in charge of a Speak with the Since you have spoken to the
small team working with project manager other team's leader before,
others on a large project. and the leader this has proven to be
Another team has missed of the other ineffective. The best choice
several deadlines which team. now is to have a meeting
your team depends on. between you, the team
You have spoken to the leader and the project
manager of the other manager. This gets the
team several times yet project manager involved and
they have missed keeps communications open
another deadline and with the other team leader.
your team will have to
work through the
weekend. What is your
best course of action?
152 During the project work, Submit the Any changes need to be
the team realizes that requested approved before being
some changes need to be changes to the worked on.
made but time is short. change control
What is the best step? board.
Num Mock Question Correct Answer Answer Justification
153 You are working with the Stakeholder Gathering information about
PMO office to gather analysis stakeholders is a part of
information about why a stakeholder analysis.
stakeholder is opposed
to the possbile project.
This is known as what?
154 You are taking over a The latest This would give you the latest
project that has been progress report information in a short
going on for the last 6 summary.
months. You have to
assess the project quickly
for your first meeting
with the project team.
What document should
you request first?
Num Mock Question Correct Answer Answer Justification
157 You and the project Detailed The project charter only
sponsor are developing timeline includes a broad view of the
requirements for an project timeline such as
internal project. The milestones.
charter will include all
EXCEPT the following?
Num Mock Question Correct Answer Answer Justification
163 During contract Sally only needs The contract is the final
negotiations, Jim makes to do what is in authority.
some detailed notes the contract.
which Sally signs. The
contract is signed.
However, while the work
is being performed, Sally
says she does not have to
do the work in the notes
because those were not
included in the contract.
What is required for Sally
to do?
164 The phase has now been These Since this is a multi-phase
ended and what happens deliverables can project, the deliverables from
to the deliverables that be used in the one phase would most likely
were accepted? next phase. be used in the next phase.
165 Which statement is true The expeditor Expeditors are only assistants
about the difference works as an and communicators. They do
between a project assistant and not have the authority to
coordinator and a project communications make any decisions.
expediter? coordinator
Num Mock Question Correct Answer Answer Justification
169 Your project has an initial The project is The CPI is below 1, meaning
budget of $100,000. A over budget, the project is over budget.
couple of months into ahead of the The SPI is over 1, meaning it
the project you perform schedule, and is ahead of schedule. The
a budget analysis. You more expensive new EAC is higher than the
should have spent than originally original budget meaning it is
$50,000 and 100 hours planned. more expensive than
on the project. Upon planned.
review, you discover that
$60,000 has been spent
and that 110 hours have
been completed which
should have cost
$45,000. You reevaluate
the remaining work to be
done and your new
budget is $120,000.
What are the conditions
of the project?
170 You are a project The project Although ABC will be doing
manager for XYZ. You sponsor at XYZ. the work and they will have a
are working on a project project manager for the
to expand the construction, the sponsoring
manufacturing capacity organization is XYZ The
for your charter will be approved by
department. The the sponsor at XYZ.`
construction of the new
facility will be outsourced
to ABC. Who approves
the project charter for
this project?
171 You are working for a Each project has Each project has its own staff
projectized PMO. What its own staff. for the project that reports
is the best description of only to the project manager.
this?
Num Mock Question Correct Answer Answer Justification
173 While negotiations are The project This is the key role of the
important for the project manager should project manager in
manager, what is the be available to negotiations.
best statement regarding provide
a project manager's role assistance and
in negotiations? any needed
information.
Num Mock Question Correct Answer Answer Justification
176 Your time will be limited The head of the This is the key stakeholder
to spend with the department that you need to engage to
stakeholders. Which that will be improve their interest.
stakeholder would be using the
most important to work product. He is
with? not actively
engaged in the
project.
178 Your project team is The Stakeholder The matrix indicates the
working on a Engagement current engagement level
Stakeholders Assessment and the desired engagement
Engagement Assessment Matrix helps level of each stakeholder. If
Matrix. The project determine there is a gap, it can indicate
sponsor asks what this is communication a communication gap.
used for and you explain gaps.
which of the following?
179 Which two management The stakeholder These are the two
plans do you need to management management plans to
manage the plan and the manage stakeholder
stakeholders? communication engagement.
management
plan
Num Mock Question Correct Answer Answer Justification
181 The quality control team Performing both Although controlling the
and the scope validation in parallel is a quality is normally done
group, which includes a reasonable before scope validation, the
team member of the practice. two can be performed in
client, are working on parallel. PMBOK p.134
control quality and scope
validation at the same
time. A team member
objects to this stating
that they are two
different processes.
What is the next best
course of action?
182 The project team is Agile These terms are from an agile
having their approach. Although not
retrospective review and discussed in detail, the
determing the current PMBOK p. 187 does mention
velocity. What type of agile.
approach are they using?
Num Mock Question Correct Answer Answer Justification
183 The team wants to Submit the Even though these are
update the schedule with requested project documents and not
some key changes. What changes to the work on the project
is the best course of change control deliverables, these changes
action for this task? board. still need to be submitted.
184 The quality standard for They are precise The value all are very close
the parts needs to be 4 but not accurate together but not close to the
inches. A sample of parts desired measurement.
is 4.33, 4.29, 4.34, 4.31
and 4.30. What can be
said about the parts?
Num Mock Question Correct Answer Answer Justification
185 The key benefit of a cost- They provide This is the key benefit for a
reimbursable contract is flexibility to cost reimbursable contract.
which of the following? redirect a seller
when the scope
of the project
cannot be
defined or there
are high risks
involved.
189 The team is reviewing This links the See PMBOK p.134
the requirements various
traceability matrix while requirements to
validating the scope. their origin and
What is this used for? tracks them
through the
project.
190 What important cost and Cost variance These are calculations that
schedule forecast and Schedule are derived from the project
calculations are Performance baselines and show the
important in monitor and Index variance from the baseline.
control project work?
192 The team is discussing Focus the team Problem solving is the best
who should take with a solution in this instance.
responsibility for each brainstorming
WBS when a couple of session to get
team members disagree multiple
about some of the work possible
packages. One member solutions and
says that one work then work with
package needs to be the team to
decomposed further, select one.
while another says that
another work package
should be put in a
different category. Your
best option is to do
which of the following?
193 You get an urgent call Check the email This is the best next step.
from a manager on the that you used Checking the
electrical portion of the and compare it communications plan will see
project. He has not to the if something was changed.
received a progress communications
report for the last two plan.
weeks. You email him a
copy right away but what
should you do next?
Num Mock Question Correct Answer Answer Justification
194 The building has passed Update the The stakeholder register
the final fire inspection. stakeholder should be updated when a
What should the next register and stakeholder is no longer
step be? mark the fire impacted by the project.
warden as no
longer actively
involved.
195 The project manager is Mark these She should not be making
reviewing a schedule changes as a these changes as approved
diagram and removes a proposal and without a change request.
step required to submit a change
complete another task. request.
She then changes that
task to include the
activities for the previous
task. What should she
do next?
Num Mock Question Correct Answer Answer Justification
200 How often may scope Multiple times The scope validation can
validation occur? occur a number of times.