You are on page 1of 9

Fast-tracking an FCC revamp

The design, detailed engineering and installation of one revamp took just
four-and-a-half months

Michael Whatley Navajo Refining Company


Scott Golden and Tony Barletta Process Consulting Services

I
n 2003, Navajo Refining Company revamped ess, project, mechanical and operating personnel
its FCCU to increase capacity from 18–25 with a vested interest in the successful outcome.
Mbpd. During the previous turnaround, the Other time-consuming activities such as the
reactor-regenerator section had been modified to approval of drawings were done in one or two
meet the 25.Mbpd feed rate, but downstream days versus weeks by an appropriate working-
equipment had not been upgraded. There were level team. Avoiding bureaucratic project
only four-and-a-half months from engineering execution processes eliminates waste, unneces-
kick-off to unit start-up. Everything had to be sary costs and scheduling delays.
done on a fast track. Consequently, identifying Developing a complete scope of work was key
modified or new long lead-time items quickly, to preparing a good estimate and controlling
such as compressor rotor modifications or costs. Fast-track revamps are challenging,
vessels, was a priority. Normal linear engineer- because engineering activities need to be priori-
ing practices prior to issuing bids could not be tised around long lead-time equipment, and
followed. These included finalised simulations, standard engineering practices often have to be
heat and material balances, and equipment spec- ignored as not being necessary. Major equipment
ification. In spite of the challenges, the unit must be specified in sufficient detail to get an
started up on schedule. The unit has been able accurate quote, but details that are not needed
to exceed its design feed rate, and increase gaso- can wait until after the critical activities are
line and LCO product recovery. Payout was less complete. For example, when buying a new
than six months. vessel, process nozzle sizes can be estimated
based on preliminary simulations and finalised
Fast-track execution after the vessel manufacturer has been selected
It is not unusual in today’s business climate for and plate ordered. While there is risk of cost
revamp projects to take two to three years to escalation if a process nozzle changes from, say,
engineer and construct. But with a dedicated 8–10in, waiting until everything is finalised will
project team and experienced revamp group, it is at best ensure a premium is paid for the steel
possible to complete fast-track work on schedule plate or, at worse, the schedule cannot be met.
and within budget. When this project was In many instances, standard engineering prac-
executed, refinery margins were tight and capital tices dictate the equipment specification
was scarce. Hence, the decision to invest was development time, not truly practical require-
made as near as possible to the upcoming ments that ensure equipment deliveries are met,
turnaround. costs are contained and ultimately the unit oper-
However, fast track does not mean wasting ates properly.
money. The proper execution of fast-track Since the schedule was short, sufficient process
revamps avoids the excessive engineering costs simulations and equipment modelling were done
associated with studying options that are not to assess the major system limits such as the wet
practical. In this case, options that did not make gas compressor, condenser system, main column
sense were eliminated by discussions with proc- and feed hydraulics. In parallel, field pressure

www.digitalrefining.com/article/1000115 Revamps 2006 1


and temperature measurements were gathered revamp was complete, a new gas oil hydrotreater
to identify problem areas. Proper simulation and needed to be put in service. Its design basis
equipment modelling are important, but accurate called for additional hot feed to the FCC. As long
measurements are essential to quickly identify as there was capacity to remove this heat else-
problem areas. In this case, field pressure meas- where, it was acceptable. But cold feed was the
urements showed a 15 psi pressure drop from LCO and HCO pumparounds’ major heat sink.
the reactor to the wet gas compressor inlet. The Main fractionator pumparound heat removal was
reactor effluent line had a 5 psi pressure drop therefore a significant constraint that needed to
due to coke build-up at the main column inlet be addressed.
flange. The main column pressure drop was 3 psi
and the main fractionator-to-wet gas compressor Discovering constraints
inlet was 7 psi. Measured pressure was only 3 Preliminary simulations showed that the gas
psig at the suction of the wet gas machine. But plant debutaniser and, to a lesser extent, the
maintaining a 3 psig compressor inlet pressure stripper column diameters were too small to
would have required a new compressor and process all the FCC gasoline. Even using high-
motor. Revamp economics, and capital and capacity trays in the debutaniser required a large
schedule constraints eliminated this option. percentage of the gasoline to be produced as
Another solution had to be found. main fractionator heavy naphtha product to
reduce gas plant liquid loading. Producing heavy
Developing scope naphtha reduces the main fractionator overhead
Process engineering focused on developing major temperature, lowering the condenser system
scope items, not finalising the simulations, heat driving force temperatures, reducing the main
and material balances, and finally equipment fractionator overhead vapour temperature and
specifications. During every FCC revamp, the wet lowering the heavy naphtha pumparound draw
gas compressor, main column heat removal, temperature. These all make heat removal more
main column capacity, gas plant capacity and difficult. In addition, the main fractionator over-
reactor-to-wet gas compressor pressure drop are head temperature could drop to 210°F in the
critical systems that must be evaluated. These worst case, resulting in salt formation on column
are always the focus. For example, preliminary internals. Even though final simulations and
process simulation and equipment modelling equipment evaluations were not complete, many
showed the wet gas compressor suction pressure unit constraints were becoming apparent.
needed to be increased to 10 psig to keep wet gas The existing main column did not have enough
production within the compressor capacity. trays between the products to provide good frac-
Furthermore, additional condenser capacity was tionation. There was a relatively large amount of
needed to reduce the receiver temperature to gasoline in the LCO, and LCO in the slurry prior
less than 105°F to stay within the compressor to the revamp. Furthermore, at revamp charge
size. Preliminary simulation and equipment rates, trays would have generated almost 5 psi
modelling were accurate enough to identify these pressure. But the system pressure drop had to be
constraints. minimised to stay within the existing compressor
A higher FCC feed rate (and higher conversion) capacity. The revamped main column needed to
increases the amount of heat entering the main use packing to reduce the pressure drop to 1 psi
column, so heat removal must increase. Yet heat or less. The vessel needed to be taller to accom-
removed at a given location in the column deter- modate the packed column internals. Based on a
mines product quality and product recovery. For rough layout of the column internals, an estimate
example, increasing the slurry pumparound duty of vessel height and weight was developed so the
increases the total heat removal, but the liquid/ existing foundation could be checked. Since it
vapour ratio throughout the column drops. was adequate to support a taller vessel, a vessel
Fractionation decreases, thereby increasing the section specification was put together to prepare
amount of gasoline in the LCO and LCO in the a cost estimate for this part of the work. The new
slurry. Moreover, sulphur species in the products main column vessel section plus the revamp of
change, making sulphur specifications difficult to the trays to packing was the single biggest
meet in downstream units. Before the FCC investment.

2 Revamps 2006 www.digitalrefining.com/article/1000115


Reactor system pressure drop
Main column Main column
overhead receiver
Components iP, psi (bar)
Reactor vapour line 5 Regenerator Reactor
Main column 3
Condenser and piping 4 Atmosphere
10.2 3.0
Flow metering and valve 3
Total 15 18.0 6.0

Wet gas
compressor
Table 1

Several critical systems were eval-


uated and major equipment work
scope was developed early in the Pressure, psig
engineering phase. Even though Air 13.2 Tray P = 3.0 psi
work scope development was not Air Oil feed
complete, major investment areas blower
were identified, including:
• Wet gas compressor
• Main column vessel and tray Figure 1 Measured reactor-to-wet gas compressor pressure drop
conversion to packing
• Overhead system piping and condensers coke restrictions, column internals, check valves,
• Main column pumparound heat removal condensers, flow metering and other factors.
• Gas plant debutaniser diameter System component pressure losses can vary
• Gas plant stripper performance. dramatically, depending on the original equip-
Engineering work was prioritised to prepare ment design and current operation (Figure 1 and
equipment specifications to meet the delivery on Table 1).
the long lead-time items. Other less critical items As previously noted, the reactor vapour line
such as exchanger bundles and high-capacity pressure loss was 5 psi, because coke formed at
trays for the debutaniser were completed later in the main column inlet nozzle. Other component
the project. pressure losses were not excessive, but the pres-
sure drop had to be reduced from 15 to less than
Wet gas compressor — unit pressure balance 10 psi at a much higher flow rate to avoid costly
Pressure balance is king on an FCC, especially wet gas compressor changes.
during a revamp when existing equipment
constrains an ideal solution. A supplemental air Wet gas compressor
blower was already planned to meet the higher Compressor evaluations are straightforward if
air rates, but the high pressure drop from the there are accurate compressor polytropic head-
reactor to the wet gas compressor inlet had to be flow and polytropic efficiency-flow curves. The
reduced. Since paralleling or replacing the exist- polytropic head-flow curve is similar to a pump
ing wet gas compressor was not possible, curve, except that the fluid is compressible and
lowering the system pressure drop was the only the head generated depends on a number of
practical option to reuse the existing compressor variables. The compressor curve starts at the
with minimum modifications. surge point and ends at stonewall or choke flow.
While calculations are useful tools, it is only Wet gas production needs to be held between
actual measurements that allow true losses to be surge and stonewall flow rates for stable opera-
quickly determined. Measured values are more tion. The curve is flat near the surge point and
accurate than any calculation, because they elim- becomes steeper as flow is increased. Centrifugal
inate unknowns. Reducing the pressure drop compressors develop a fixed head for a given
first requires accurate measurements of the inlet flow rate over the typical ranges of molec-
component pressure drops. A system component ular weight encountered on an FCC. Since gas
pressure drop includes line losses, reactor line is compressible, gas density will affect the

www.digitalrefining.com/article/1000115 Revamps 2006 3


Equation 1

0OLYTROPICHEAD THOUSANDFT

 Polytropic
3TAGE



Where,
 MW Molecular weight


n Compression coefficient
 Zavg Average compressibility
       P1 Suction pressure, psia
)NLETVOLUME )#&-
T1 Suction temperature, °R
P2 Discharge pressure, psia
Figure 2 Six-stage wet gas compressor curve
In this instance, raising the receiver
pressure from 3–10 psig and lowering
the temperature to 105°F decreased the
amount of wet gas produced to around
 11 200 ICFM, which was within the
 existing compressor’s volumetric capac-
 ity. Although pulling a heavy naphtha
3TAGE cut from the main fractionator decreased
4OTALBRAKE (P


the liquid loading to the gas plant, the

net effect was to increase the molecular
 weight of the gas inlet to the compres-
 sor. Therefore, while raising the
 compressor inlet pressure and lowering
 the temperature decreased the inlet flow
      rate, the reduced volume reduction due
)NLETVOLUME )#&-
to a higher mol weight gas also raised
the compressor discharge pressure, since
Figure 3 Five-stage wet gas compressor curve it develops a fixed polytropic head. The
calculated discharge pressure (P2 in
ability of the compressor to move a given mass Equation 1) from the existing six stages of
of gas. Operating changes that raise gas density compression was well above 350 psig over much
decrease the inlet volume for a given mass of the stable flow rate, which exceeded the maxi-
flow rate. In this case, raising the suction pres- mum allowable working pressure (MAWP) of the
sure from 3–10 psig was essential to stay major equipment in the gas plant. Moreover, the
within the stable operating range of the compressor shaft horsepower would have been
compressor. The existing compressor had a 20% above 5000 HP, requiring replacement of the
operating range between surge and stonewall existing 4400 HP motor. However, replacing a
flow rates prior to the revamp. Navajo’s six- motor is very costly, and often requires new
stage compressor performance curve is shown transformers and motor control centre
in Figure 2. equipment.
Once the compressor suction pressure was Navajo’s design compressor discharge pressure
established to stay within the stable volumetric was 210 psig. The gas plant operating pressure
flow range, the discharge pressure generated should be maintained as close to the equipment’s
by the six-stage compressor was calculated MAWP as possible, because it maximises propyl-
from the polytropic head equation shown ene recovery and minimises fuel gas production.
below: The gas plant operating pressure could be met

4 Revamps 2006 www.digitalrefining.com/article/1000115


by reducing the number of stages in the compres-
sor from six to five. Decreasing the number of Main
stages lowered the compressor polytropic head, column Spillback Gas plant
reducing the shaft horsepower to less than the
4400 HP motor (Figure 3). Increased suction SC FC
pressure combined with reducing the number of
stages enabled the existing compressor rotor to
meet both the volume and system head require- Motor Compressor
ment without changing the motor. Compressor
shaft horsepower is shown below:
C.W. PC
Equation 2
PC

Overhead
receiver

Where, SC Surge control

Hp Polytropic head
SHP Shaft horsepower
m Mass flow rate of gas Figure 4 Compressor controls
np Polytropic efficiency
1.02 includes 2% gear losses

Since the compressor revamp reduced the


stable operating range from 20–8%, a robust, 10.2
Piping 6.6
fast-acting surge control system was needed. The
main column overhead receiver pressure and gas Inlet
6.3 nozzle
plant pressure control are essential. The main
column overhead receiver pressure is maintained
by throttling the compressor suction. The throt- FI
Wet gas
Outlet compressor
tle valve pressure drop controls the overhead nozzle 6.0
receiver pressure so that the reactor pressure is 3.0
Piping Overhead
stable (Figure 4). receiver
The receiver pressure is controlled by the Pressure, psig
compressor suction throttle valve position. Since
the compressor discharge pressure is held
constant by the gas plant pressure controller, the Figure 5 Main column overhead system
compressor suction pressure will vary and follow
the flow-head curve. When the gas rate leaving with suction pressure determined by the poly-
the overhead receiver is higher than the flow at tropic head generated at the minimum flow
the surge point, the compressor spillback is control point. Since the amount of gas leaving
closed. The compressor suction pressure will ride the overhead receiver depends on the reactor
up and down the flow-head curve as long as the effluent composition and overhead receiver
throttle valve is generating a pressure drop and conditions, the compressor suction pressure is a
is not fully open. As the compressor inlet flow variable. As long as the suction throttle valve is
rate approaches the surge point, the spillback not fully open, the compressor has unused capac-
valve opens, recycling gas to ensure sufficient ity. However, once the valve goes wide open, the
inlet flow into the machine. When the spillback compressor discharge pressure will drop. At this
is open, the spillback flow rate determines the point, the FCC feed rate must be reduced to
operating point on the curve. The flow rate must maintain the gas plant pressure and avoid flaring
always be maintained above the surge point, from the overhead receiver.

www.digitalrefining.com/article/1000115 Revamps 2006 5


transfer coefficient was only 22 btu/hr-ft2-°F,
Two-phase resulting in a receiver temperature 12ºF higher
stream
than with a properly designed exchanger. The
New bundle
with baffles trim condenser bundle needed to be replaced.
Designing the bundles with a higher pressure
drop would increase the heat-transfer coefficient,
but the resultant exchanger outlet temperature
must reduce the wet gas rate. Otherwise, a higher
pressure drop and higher heat-transfer coeffi-
cient have no practical benefit. Ultimately, both
the overhead receiver temperature and pressure
determine wet gas production, so they must be
balanced. A good rule of thumb is that for every
1.4 psi increase in receiver pressure, wet gas
production decreases by 10% when the receiver
pressure is 6 psig. And for every 10ºF reduction
Figure 6 Bundle modification in temperature, wet gas production will drop by
approximately 10%. After evaluating various
possible designs, a double segmental vertical
Main column overhead system baffle design was selected to raise the heat-trans-
The main column overhead system pressure drop fer coefficient from 22–50 Btu/hr-ft2-°F, while
and heat exchange capacity set the receiver pres- increasing the pressure drop from 0.6–1 psi
sure and temperature, which control the amount (Figure 6). The bundle design would reduce the
of wet gas produced. The pressure drop from the overhead receiver temperature from 117–103ºF,
main fractionator to the compressor inlet (Figure which would lower wet gas production by about
5) had to be reduced and condensing capacity 7%, factoring in the higher pressure drop. Four
had to be increased. A fourth fin-fan exchanger new bundles were designed.
was being added as part of a previous project.
However, this still did not provide the condens- Main column
ing capacity to meet the targeted overhead The existing main column did not have sufficient
receiver temperature of 105°F or less. Adding the height to fractionate between products and allow
fourth fin-fan bundle helped reduce the pressure the installation of the packing and internals
drop, but the 10 psig compressor inlet pressure needed to reduce the pressure drop. While struc-
that was required still would not have been met, tured packing has been used for more than 20
because the piping losses would have been too years to reduce pressure drop and increase
high. capacity, packed columns only work well if the
The overhead line from the main column to distributors and collectors are designed properly.
the fin-fans was increased from 24–30in. In But properly designed internals require more
addition, the orifice plate in the suction of the vessel height than poorly designed ones. The
wet gas compressor was removed because it was existing foundation allowed vessel height to be
not needed. The existing trim condenser bundles increased by about 20ft without modifications.
were TEMA H-shell exchangers designed for a There were two options. The first would add a
very low pressure drop by eliminating the verti- section to the top of the column, but required
cal baffles. Even though the series exchangers extensive turnaround work to install new nozzles
generated only a 0.6 psi pressure drop, they had and manways in the existing vessel. A better
a very low heat-transfer coefficient. Trim solution was to cut the vessel just below the HCO
condenser bundle designs need to balance pres- pumparound section and install a new vessel
sure drop and the resultant heat-transfer section. Existing vessel modifications would be
coefficient. Outlet temperature and pressure minimised. Even though this solution signifi-
should be optimised so that wet gas production cantly increased the cost for the new vessel
is minimised. Rigorous exchanger modelling section, it reduced turnaround work, resulting in
with HTRI software showed the service heat- a negligible cost difference between the two

6 Revamps 2006 www.digitalrefining.com/article/1000115


options. Furthermore, it reduced the shutdown
schedule.
Once the correct option was selected, the avail-
able vessel height was optimised to meet overall
processing objectives. Whereas the existing
Light LCO (LLCO)
vessel had a wash section between the HCO and
slurry pumparounds, when grid is used in the LLCO/HLCO
fractionation
slurry pumparound section reactor effluent cata-
lyst fines are completely removed. Therefore, a
wash section is not needed. Furthermore, Navajo Heavy LCO (HLCO)
was considering undercutting LCO (post ULSD HLCO/HCO
specification) to optimise the hydrotreater run fractionation
length, and wanted the flexibility to produce
light and heavy LCO streams (Figure 7). The
HCO PA
column was also going to produce a large
percentage of gasoline as heavy naphtha.
Therefore, the overhead temperature might be
reduced as low as 210°F to reduce the gas plant
liquid loading to maximise the feed rate. Hence,
an on-line water wash system needed to be
installed for reliable operation at very low over-
head temperatures. Figure 7 Heavy LCO draw
Main column bottom product is used as carbon
black feed. Therefore, undercutting the heavy Even though this temperature is above the water
portion of the LCO to slurry product would raise dewpoint, localised cold temperatures cause salts
gravity above specification. The new vessel to deposit on the column internals, eventually
section was designed with both a light LCO draw, causing flooding. Hence, as noted, the main
where most of the product is produced, and a column was designed with on-line water wash
heavy LCO product draw yielding the boiling features. Ammonium chloride salts deposit after
range material containing the refractory sulphur the condensed water has absorbed the ammonia
compounds. Segregating the heavy LCO would and HCl. Subsequently, the water vapourises as
allow the hydrotreater run length to be opti- the temperatures increase lower in the column.
mised. Figure 8 shows the 4,6 DMDBT sulphur When salts form inside structured packing, they
in an LCO product produced from hydrotreated restrict the vapour flow area, causing the column
feed from moderate sulphur crude blends. Most to flood. To ensure these salts can be removed
4,6 DMDBT begins to distil in the 630–
640°F TBP cut and peaks at 650–660°F.
Very little is present in the 680°F-plus
cut, apart from other substituted sterically

hindered sulphur compounds.
Gas plant major equipment capacity 
00-WT

could not process 25 Mbpd FCC feed 


without producing heavy naphtha from
the main column. The debutaniser column 

diameter was the first limit, but the high- 


pressure receiver cooling, stripper charge

pump capacity and stripper column diam-            
eter were also limits. Thus, the main            
           
           
column was designed to produce as much #UTBOILINGPOINT o&
as 25 vol% of the total FCC gasoline as
heavy naphtha, resulting in a column
overhead temperature as low as 210°F. Figure 8 LCO 4,6 DMDBT distribution by boiling range

www.digitalrefining.com/article/1000115 Revamps 2006 7


with little disturbance to normal operation, an
Condenser on-line water wash system was added (Figure 9).
Main features include an active tray that heats
the cold reflux from receiver temperature to
about 190°F, and a collector tray to remove
water. Water can be intermittently injected into
Reflux the reflux stream to dissolve the salts, removing
Water-
them from the water draw collector tray. Salt
intermittent forms on the top tray, keeping it out of the pack-
use ing. Additionally, the top tray and collector are
Oil made from AL6XN to ensure the rate of corro-
Oil and water sion is low.
to overhead
condensers-
Packing intermittent Main column heat removal
The reactor effluent heat is removed by the main
column pumparounds and condenser system.
Otherwise, vapour entering the column leaves
Figure 9 Water wash system the overhead receiver as wet gas, adding to the
compressor load. Furthermore, heat not removed
Condenser by the pumparounds becomes condenser system
load. Increasing the condenser duty raises the
overhead receiver temperature, which increases
wet gas production by approximately 1% for each
Reflux
1°F rise in receiver temperature. As a conse-
quence, pumparound and condenser duty
Water draw
constraints influence the FCC feed rate (and
Light naphtha
Heavy naphtha conversion) when the compressor capacity is
limited. The wet gas compressor capacity was
Heavy naphtha PA and remains a significant unit limit, as are
Heavy naphtha pumparound and condenser heat removal.
product Heat removal was identified as a major unit
Heavy naphtha/
light LCO constraint. The main column had four pumpa-
LCO PA rounds: heavy naphtha, LCO, HCO and slurry.
Light LCO
Prior to the revamp, the heavy naphtha pumpa-
Light LCO/ product round system was not operating. It needed to be
heavy LCO put back in service, with other pumparounds’
Heavy LCO heat removal maximised without large invest-
product ment, because capital was limited. System and
Heavy LCO/
slurry equipment sizing were pushed, with marginal
operation being deemed adequate. As an exam-
HCO PA ple, an existing LCO product rundown cooler
was converted to heavy naphtha product and
lean sponge oil cooling. An existing out-of-serv-
ice fin fan located near the LCO rundown line to
Slurry PA tankage was used when product goes to tankage.
Since lean sponge oil cooling actually helps
remove heat from the main column, part of the
Slurry duty from the converted LCO product cooler
product removes the main column heat. Increasing the
lean sponge oil circulation to the hydraulic, cool-
ing or sponge absorber capacity constraint
Figure 10 Main column pumparounds reduces the main column overhead temperature

8 Revamps 2006 www.digitalrefining.com/article/1000115


when other heat-removal services
are limited. The sponge absorber
Main Column Main column
was retrayed to maximise capacity overhead receiver
and main column cooling.
Regenerator Reactor
Pumparound duty depends on
pump capacity, draw temperature Atmosphere
17.0 10.0
and heat sink temperatures. Ideally,
a portion of the main column 20.0 12.0

pumparound heat should be Wet gas


compressor
exchanged with utilities so that
dependence on a fixed heat sink is
avoided. Steam, BFW preheat, fin
fan and cooling water are all varia-
ble heat sinks. As noted, other heat 18.0 Pressure, psig
sinks, such as gas plant reboilers Air Packing P = 1.0 psi
and cold feed, are fixed by these Air Oil feed
sinks’ temperatures and flow rates. blower
Navajo’s main column heat-
removal system had a small fin fan Figure 11 Revamp pressure profile
on the heavy naphtha pumparound
as well as a steam generator on the slurry pump- design, detailed engineering and installation took
around. Other sinks were cold feed and gas plant just four-and-a-half months. Capital investment
reboiler duty, with cold feed representing a large was targeted only on critical areas, such as the
portion of the main column total heat removal. reactor-to-wet-gas-compressor inlet pressure
Since cold feed was a major heat sink for the drop (Figure 11). While some major changes
LCO and HCO pumparounds (Figure 10), main- were made, such as the main column vessel
taining both the cold feed rate and keeping its section and overhead piping, others, including
temperature down were important. But Navajo the wet gas compressor and overhead condenser
was installing a new gas oil hydrotreater that system modific ations, were minimised.
was slated to increase the amount of hot feed to Throughout front-end and detailed engineering,
the FCC and raise the temperature of the cold the focus was on minimising changes. Where
feed. Since the cold feed rate and temperature existing equipment was deemed marginal but
were dependent on the gas oil hydrotreater adequate, no changes were made. Based on
rundown cooling, the hydrotreater operation was refinery margins since the revamp, the project
adjusted to maximise main column heat removal paid out in less than six months.
to cold feed. Two additional fin-fans were added
to the gas oil product from the hydrotreater to Michael Whatley is the engineering manager for Holly
ensure feed temperature going to the FCC was Corporation’s Navajo refinery in New Mexico, USA.
130°F. LCO pumparound heat removal was Scott Golden is a chemical engineer with Process Consulting
improved by installing a new reboiler bundle on Services in Houston, Texas, USA. Email: sgolden@revamps.com
Tony Barletta is a chemical engineer
the stripper column to raise the heat-transfer
with Process Consulting Services in Houston, Texas, USA.
coefficient, allowing more reboiler duty for this
Email: tbarletta@revamps.com
service. This allowed better C2 and H2S removal
from the LPG product. Main column heat
removal was maximised through judicious low-
cost modifications only. But main column heat Links
removal remains a constraint.
More articles from: Process Consulting Services
Conclusions More articles from the following categories:
Navajo’s FCC revamp has been operating since Revamps, Shutdowns and Turnarounds
late 2003, meeting its feed rate, product FCC
recovery and product quality objectives. The

www.digitalrefining.com/article/1000115 Revamps 2006 9

You might also like