You are on page 1of 3

 PROJECT NAME: BARWA1 S/S 

OWNER: NSPO DAILY REPORT

REPORT (Day) No.6


PROJECT NAME: BARWA1 /66/22kv
CONTRACTOR: CONSORTIUM EET&D /ABB
Shift: 8am to 5pm Date:10 -8-2017 Weather: N Temp: 40

WORK FORCE No. MH LIST OF MAJOR PLANT AND HRS


EQUIPMENT
Manager. & Eng. 1 4 Hilti / Core derail 0
Site Supervision 1 4 Generator 0
Safety Supervision 1 4 Steel Cutter 0
Drivers& equipment operator. 1 4 Welding machine 0
administrator 1 4 Loader 0
Fitter 1 4 Unimog / Crane 0
Welder 0 0 Excavator 0
Electrician 3 12 Hydraulic Trolley 0
Power Cable Electrician 0 0 Plat Compactor 0
Storekeeper 0 0 Scissor Lift 0
Helpers 0 0 Truck 0
Office Boy 1 4 Fork Lift 0
Test/Commissioning 0 0 Vacuum Machine 0
Guard 0 0 Vehicle 8
Banksman 0 0 Oil Treatment 0
Labourers for Laying Cables 1 4 Dilo Machine for SF6 Gas 0
Owner & Consultant 0 0 Witness from EETC (Civil Eng.)
Subcontractor F.F system 0 0
Subcontractor for Civil Work 0 0
Total 10 40 Without M.H. for Owner , Consultant & 0
Visitors

Subcontractors: 0 0 CO. Name / N.A


Scope of Work / N.A

Visitors 0 0 CO. Name /


Reason /
Safety :
- No.of Toll Box \ Safety Talk : ( ) -
- Site Events: - Accident ( ) -First Aid ( ) - Near Miss ( ) - Unsafe act\Unsafe con.( / )
- Inspection Tools & Equipments : ( ) ( ) ( ) ( ) ( )
- Briefing Induction Subject : PTW

Page 1 of 3
 PROJECT NAME: BARWA1 S/S 
*Receiving Materials :
* NON

*Description of Work Performed Today:

1- providing 66KV DS/ES/CB bridges for the mechanism


2- Eathing links REMOVING for CT .
3- Mobilization works continued.

*Description of Work Performed Today Group 2 at Night Shift from pm : am


N/A

* Expected Work Next Day:


* Pre commissioning work
1- providing 66KV DS/ES/CB bridges for the mechanism
2- Eathing links REMOVING for CT .

Site Requirement :
* We need urgently from EET&D to inspect and test the charger in DC panel to obtain DC source
* We need from from EET&D to finish the work of 8 sectionalizing DS and 4 B.C ES to finish our works
* We need from from EET&D to install Bus Coupler and riser Cubicles
* We need from from EET&D to terminate the cables in the transformer panel
*Complete Termination Works in 22KV /66KV & Protection

Site Constraints :

Critical Items :

MV Voltage SWGR Modification + 2*2.5 CABLES Shall be provided +NER Shall be provided

*Missing & Shortage Materials

NOTES:_

Page 2 of 3
 PROJECT NAME: BARWA1 S/S 
Reviewed by: Date: - Reported by: Date:10 -08-
: 2017
ABB :
Mostafa Mansour

Page 3 of 3