You are on page 1of 109

BASIC PRICES

Materials
Trade
Description Unit Basic Price

EXCAVATION Dry hard earth with transport cost cube.

EXCAVATION Quarry dust with transport cost cube.

EXCAVATION 1 1/2" thick plank (class 11) S. ft

EXCAVATION 2" x 4" joist (class 11) L. ft

EXCAVATION 2" x 6" joist (class 11) L. ft

EXCAVATION Wire nails kg.

CONCRETE Cement bag

CONCRETE Sand cube.

CONCRETE Metal 3/4 " cube.

CONCRETE Metal 1 " cube.

CONCRETE Metal 2 " cube.

CONCRETE Water gal.

FORM WORK 1" thick plank class 11 S. ft

FORM WORK 2 " x 4 " class 11 L. ft

FORM WORK 2 " x 2 " class 11 L. ft

FORM WORK 2 " x 1 " class 11 L. ft

FORM WORK Wire nails kg.

FORM WORK Mould oil ltr

FORM WORK 16mm bolt Nr


REINFORCEM
Tor Steel
ENT
REINFORCEM
25mm kg.
ENT
REINFORCEM
20mm kg.
ENT
REINFORCEM
16mm kg.
ENT
REINFORCEM
12mm kg.
ENT
REINFORCEM
10mm kg.
ENT
REINFORCEM
binding wire kg.
ENT
REINFORCEM
Mild steel
ENT
REINFORCEM
10mm kg.
ENT
REINFORCEM
6mm kg.
ENT
RUBBLE &
CEMENT Rubble cube.
BLOCKS
RUBBLE &
CEMENT cement bag
BLOCKS
RUBBLE &
CEMENT sand cube.
BLOCKS
RUBBLE &
CEMENT water gal.
BLOCKS
RUBBLE &
CEMENT 8" thick cemrnt hollow block Nr
BLOCKS
RUBBLE &
CEMENT 6" thick cemrnt hollow block Nr
BLOCKS
RUBBLE &
CEMENT 4" hick cemrnt hollow block Nr
BLOCKS
BRICK WORK Cement bag

BRICK WORK Sand cube.

BRICK WORK Water gal.

BRICK WORK Bricks Nr


WATER
Cement bag
PROOFING
WATER
Sand cube.
PROOFING
WATER
DPC tar ltr
PROOFING
DOORS &
4" X 3" Class 1 timber L. ft.
WINDOWS
DOORS &
4" X 2" Class 1 timber L. ft.
WINDOWS
DOORS &
11/4 thick plank s. ft.
WINDOWS
DOORS &
Ply wood door sash size 3' 0" x 6' 9" Nr
WINDOWS
DOORS &
1" thick plank 6" wide L. ft.
WINDOWS
DOORS &
5mm.glaze sheet. s. ft.
WINDOWS
DOORS &
4" Brush Nr
WINDOWS
DOORS &
Sand paper Nr
WINDOWS
DOORS &
Wood primer ltr.
WINDOWS
DOORS &
Enamel paint ltr.
WINDOWS
DOORS &
4" x 3" Butt hinges pair.
WINDOWS
DOORS &
4" x 2" Butt hinges pair.
WINDOWS
DOORS &
3/4" brass screws Nr
WINDOWS
DOORS &
1/2" brass screws Nr
WINDOWS
DOORS &
6" long barrel bolt Nr
WINDOWS
DOORS &
12" long barrel bolt Nr
WINDOWS
DOORS &
Mortice lock Nr
WINDOWS
DOORS &
Hold fast Nr
WINDOWS
DOORS &
casement fastner Nr
WINDOWS
DOORS &
casement stay Nr
WINDOWS
ROOF 1" thick Ginisapu plank s. ft.
ROOF 3/4" thick Ginisapu plank s. ft.
ROOF Class 1 timber c. ft.
ROOF Calicut tile Nr
ROOF Calicut pattern ridge tile Nr
ROOF Half round tile Nr
ROOF Asbestos roofing sheet s. ft.
ROOF Reepers 2" x 1" l. ft.
ROOF Wire nails kg.
ROOF Colouring powder kg.
ROOF Cement bag
ROOF Sand cube
ROOF Lime kg.
ROOF " J " bolt Nr
ROOF Wood primer ltr
ROOF Enamel paint ltr
ROOF Wood preservative ltr
ROOF 3/4" x 9" timber for valance board S. ft.
ROOF Asbestos close fitting pair
ROOF Roofing screws Nr
ROOF Brass screws 11/2 Nr

FLOOR Lime kg.

FLOOR Cement cube.

FLOOR Sand cube.

FLOOR water gall.

FLOOR Bricks Nr

FLOOR Floor tile 6" x 6" Nr

FLOOR Flor tile 8" x 8" Nr

FLOOR Floor tile 12" x 12" Nr

FLOOR Tile grout kg.

WALL Cement bag

WALL Sand cube

WALL Lime kg.

WALL water gal

WALL Wall tile 6" x 6" Nr

WALL Wall tile 8" x 12" Nr

WALL Wall tile 8" x 8" Nr

WALL Tile grout kg.

CEILING Cement bag

CEILING Sand cube

CEILING Lime kg.

CEILING water gal

CEILING 4" x 2" class 1 timber l. ft.

CEILING 2" x 2" class 1 timber l. ft.

CEILING 2" x 1" class 1 timber l. ft.

CEILING 11/2" x 11/2" cove moulding l. ft.

CEILING 1/2" x 1/2" beading l. ft.


CEILING 3/4 " thick timber ceiling plank (lunumidella ) s. ft.

CEILING Asbestos ceiling sheet s. ft.

CEILING Wire nails kg.

CEILING Emulsion paint ltr

PAINTING Emulsion paint ltr

PAINTING Weathersheild paint ltr

PAINTING Brush 4" Nr

PAINTING Acrylic filler ltr

PAINTING Sand paper Nr

PAINTING Water gal


PVC Pipe Type 400 (12 ft Standard Length
PLUMBING
pipes)
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PVC Pipe Type 600 (12 ft Standard Length
PLUMBING
pipes)
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PVC Pipe Type 1000 (12 ft Standard Length
PLUMBING
pipes)
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Tee
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Bend
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Elbow
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Value socket
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Faucet Socket
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING PVC Pipe fitting - Socket
PLUMBING 20mm dia pipe (1/2 ") Nr
PLUMBING 25mm dia pipe (3/4") Nr
PLUMBING 32mm dia pipe (1") Nr
PLUMBING 40mm dia pipe (11/4") Nr
PLUMBING 50mm dia pipe (11/2") Nr
PLUMBING 63mm dia pipe (2") Nr
PLUMBING 75mm dia pipe (21/2") Nr
PLUMBING 90mm dia pipe (3") Nr
PLUMBING Solvent cement kg.
Labour Plant

Description Unit Basic Price Description Unit Basic Price

Skilled day 1,000.00 Tractor

Un skilled day 600.00

Skilled Labour day 1,000.00 Concrete Mixer

Un Skilled Labour day 600.00 Vibrator

Vibrator Operator day 1,000.00

Concrete Mixer
day 1,000.00
operator

Skilled Labour day 1,000.00

Un Skilled Labour day 600.00

Skilled labour day 700.00

Un skilled labour day 450.00


Skilled labour day 1,000.00

Un skilled labour day 600.00

Skilled Labour day 1,000.00

Un Skilled Labour day 600.00

Skilled Labour day 1,000.00


Un Skilled Labour day 600.00

Painter day 1,000.00

Carpenter day 1,000.00

Skilled labour day 1,000.00

Un skilled labour day 600.00


Skilled Labour day 1,000.00
Un Skilled Labour day 600.00
Skilled Labour per day 1,000.00

Un Skilled Labour per day 600.00

Skilled Labour per day 1,000.00

Un Skilled Labour per day 600.00

Skilled Labour per day 1,000.00

Un Skilled Labour per day 600.00


Skilled Labour per day 1,000.00

Un Skilled Labour per day 600.00

Skilled Labour per day 1,000.00

Un Skilled Labour per day 600.00


Basic Prices

MATERIALS LABOUR PLANT

Item Code Price Item Price Item Price


Description Unit Description Code No. Unit Description Code No. Unit
No. No. ( Rs.) No. ( Rs.) No. ( Rs.)
1 Acid M-001 Gal 254.00 1 Painter L-001 Day 1,200.00 1 Hire of Mixer P-001 Day 1,500.00

2 Anti Corrosive Primer M-002 litre 245.00 2 Plumber L-002 Day 1,200.00 2 Hire of Vibrator P-002 Day 1,000.00

3 Asbestos Corrugated Sheet M-003 Sq.ft 26.00 3 SK Labour L-003 Day 1,200.00 3 Vibrating Rammer P-003 Day 1,000.00

4 Barrel Bolt M-004 No 75.00 4 SK Labour (Vibrator) L-004 Day 1,200.00

5 Binding Wire - 16 BW M-005 Lbs 100.00 5 Tinker L-005 Day 1,200.00

6 Bitumen M-006 Gal 80.00 6 Tiler L-006 Day 1,200.00

7 Blasting Powder M-007 Lbs 200.00 7 U / SK Labourer L-007 Day 700.00

8 Blue M-008 Ozs 10.00 8 Carpenter L-008 Day 1,200.00

9 Boild Lime M-009 Cwt 300.00 9 Mason L-009 Day 1,200.00

10 Bolts 16mm 18" M-010 No 75.00 10 Glazier L-010 Day 1,200.00

11 Brass Fanlight Chtches M-011 No 45.00

12 Brass Nails - 1 1/2" M-012 Lbs 50.00

13 Brass Pannel Pins M-013 Doz 1.00

14 Brass scews - 1" M-014 No 2.50

15 Brass Screws 1 1/2" M-015 No 3.75

16 Brass Screws - 1/2 " M-016 No 1.30

17 Brass Screws - 3/4" M-017 No 1.25

18 Brass Screws - 4" Long M-018 No 7.50

19 Bricks M-019 No 6.00

20 Brush - 3" M-020 No 210.00

21 Brush - 6" M-021 No 495.00

22 Brush 2" M-022 No 165.00

23 Butt Hinges M-023 No 70.00

24 Casement Fasteners M-024 No 55.00

25 Casement Stays M-025 No 55.00

26 Cement M-026 Bag 645.00

27 Clear Glass panes M-027 Sq.ft 25.00

28 Clips and Nails - 1 " M-028 No 7.00

29 Clips and Nails - 1 1/2 " M-029 No 10.50

30 Clips and Nails - 1 1/4 " M-030 No 8.75


31 Clips and Nails - 2 " M-031 No 10.75

32 Clips and Screws - 3 " M-032 No 34.00


33 Clout Nails - 1/4" M-033 Lbs 25.00

34 Coir Brush - 6" M-034 No 45.00

35 Coloured Pigment M-035 Lbs 175.00

36 Colouring Powder M-036 Lbs 175.00

37 Cotton Waste M-037 Lbs 12.50

38 D. D. T. Powder M-038 Lbs 25.00

39 Diesel Fuel M-039 Ltr 70.00

40 Door Closer M-040 No 1,850.00

41 Draw Rings M-041 No 22.50


42 Earth Delivered at Site M-042 Cube 1,500.00

43 Emulsion Paint M-043 litre 280.00

44 Enamel Paint M-044 litre 354.00

45 Fibre / Plastic Plugs M-045 No 1.50

46 Fire Wood M-046 Lbs 250.00

47 Flannel Cloth M-047 Yards 70.00

48 Flat Asbestos Ceiling Sheets M-048 Sq.ft 15.00

49 Floor Brush M-049 No 210.00


50 Fuel Forge M-050 Ltr 100.00

51 Fuse wire M-051 L.ft 10.00

Galvanised iron sheet(8'X4') - 18 B.W.G


52 M-052 No 2,200.00
(1.2 mm)
53 Gravel delivered to site M-053 Cube 2,000.00

54 Gutter Brackets M-054 No

55 Gutter joiner M-055 No

56 Half Round Clay Tiles M-056 No 5.00

57 Hollow Cement Block - 8" thk. M-057 No 30.00


58 Hollow Cement Blocks - 4" thk. M-058 No 38.00

59 Hollow Cement Blocks - 6" thk. M-059 No 60.00

60 Iron Nails - 1 1/2 M-060 Kg. 25.00

61 Iron Screws - 3/4" M-061 No 0.55

62 Jumper Steel M-062 Lbs 65.00

63 Jute Hessian M-063 Sq.ft 3.50

64 Metal - 1 " M-064 Cube 8,000.00

65 Metal - 1 1/2 " M-065 Cube 3,500.00

66 Metal - 3/4 " M-066 Cube 4,000.00

67 Mild Steel Dowels - 5/8" , 4" Long. M-067 No 6.00

68 Mild Steel Rods including transport to site M-068 Kg. 68.00

69 Mineral Turpentine or Thinner M-069 litre 80.00

70 Mortice lock with screws M-070 No 960.00

71 Mould Oil M-071 litre 35.00

72 Nails - 2" M-072 Lbs 50.00

73 Nails - 3/4" M-073 Lbs 20.00

74 Plywood Sash - 6' 9" X 2' 9" M-074 No 2,000.00

75 Primer M-075 litre 180.00


76 PVC Elbows / Bent / Socket - 3/4" M-076 No 15.00
77 PVC Sockets - 1" M-077 No 14.00

78 PVC down pipes - 12' length M-078 No

79 PVC elbow - for rainwater down pipes. M-079 No

80 PVC Elbows / Bent / Socket - 1 1/2" M-080 No 69.00

81 PVC Elbows / Bent / Socket - 1 1/4" M-081 No 42.00

82 PVC Elbows / Bent / Socket - 1" M-082 No 21.00

83 PVC Elbows / Bent / Socket - 1/2" M-083 No 10.50

84 PVC Elbows / Bent / Socket - 2 1/2" M-084 No 350.00


85 PVC Elbows / Bent / Socket - 2" M-085 No 110.00

86 PVC Elbows / Bent / Socket - 3" M-086 No 580.00


87 PVC End cap M-087 No

88 PVC gutter - 12' length M-088 No

89 PVC gutter head - 6" M-089 No


90 PVC joiner - 3 1/2" M-090 No

91 PVC mitre bend 6" dia M-091 No

92 PVC Pipes - 1 1/2" M-092 L.ft 46.00

93 PVC Pipes - 1 1/4" M-093 L.ft 32.00

94 PVC Pipes - 1" M-094 L.ft 21.00

95 PVC Pipes - 1/2" M-095 L.ft 7.50


96 PVC Pipes - 2" M-096 L.ft 79.00

97 PVC Pipes - 3" M-097 L.ft 185.00

98 PVC Pipes - 3/4" M-098 L.ft 14.00

99 PVC Shoe M-099 No

100 PVC Sockets - 1 1/2" M-100 No 29.50

101 PVC Sockets - 1 1/4" M-101 No 19.50

102 PVC Sockets - 2" M-102 No 48.00

103 PVC Sockets - 3" M-103 No 192.00

104 PVC Straps M-104 No

105 Ridge Tiles (calicut) M-105 No 35.00

106 Ridges 3' 8" Long (Asbestos) M-106 Pair 245.00


107 Rim Lock with Screws M-107 No 500.00

108 Roof tiles - calicut M-108 No 16.00

109 Roofing Screws and Washers M-109 No 3.50

110 Roofing Screws or Bolts M-110 No 3.50

111 Rubble - 6" - 9" M-111 Cube 2,500.00

112 Salt M-112 Lbs 10.00


113 Sand M-113 Cube 8,000.00

114 Sand Papers M-114 No 3.50


115 Slaked Lime M-115 Lbs 275.00

116 Soldering Lead M-116 Lbs 13.75

117 Solvent Cement M-117 Grms 1.40

118 Spur Stone M-118 No 15.00


119 Tarnap M-119 Gal 450.00

120 Tee - 1 " Dia M-120 No 31.25

121 Tee - 1 1/2 " Dia M-121 No 102.00

122 Tee - 1/2 " Dia M-122 No 15.50


123 Tee - 2 " Dia M-123 No 165.50

124 Tee - 2 1/2" Dia M-124 No 526.00

125 Tee - 3 " Dia M-125 No 875.00

126 Tee - 3/4 " Dia M-126 No 21.50

127 Tee - Dia 1 1/4 " M-127 No 63.50

128 Tee Hinges M-128 Pair 165.00

129 Tiles Pressed - 12" X 12" M-129 No 180.00

130 Tiles Pressed - 8" X 8" M-130 No 125.00


131 Tiles Terrazzo - 6" X 6" M-131 No 100.00
132 Tiles Terrazzo - 12" X 12" M-132 No 150.00

133 Timber Beading - 1/2" X 1/2" M-133 L.ft 1.50

134 Timber Beadings - 1 1/2"X1/2" (Halmilla) M-134 L.ft 12.00

Timber Ceiling Plank - 6"x3/4"


135 M-135 Sq.ft 28.00
(Lunumidella)
136 Timber Class I M-136 Cu.ft 1,200.00

137 Timber Class I - 3" x 1'1/2" M-137 L.ft 45.00

138 Timber Class I - 4"X3" M-138 Cu.ft 1,300.00


139 Timber Class I Planks - 1 1/2" M-139 Sq.ft 140.00
139a Timber Class I Planks - 1" M-139a Sq.ft 110.00
140 Timber Class II M-140 Cu.ft 750.00

141 Timber Class II - 1" Thick M-141 Sq.ft 65.00

142 Timber Class II - 2" x 1" M-142 L.ft 12.00

143 Timber Class II - 2" x 2" M-143 L.ft 22.00

144 Timber class II - 4"X 2" M-144 L.ft 65.00

145 Timber Cove Molding - 2"X2" (Halmilla) M-145 Sq.ft 35.00

146 Timber ceiling Joists - 4" x 2" M-146 L.ft 65.00

147 Timber Planks - 1" (Valance board) M-147 Sq.ft 65.00

148 Timber Purlins M-148 L.ft 100.00


149 Timber Reepers - 2"X1" M-149 L.ft 12.00

150 Timber Strips - 2" X 1/4" M-150 L.ft 5.00

151 Timber Wedges M-151 No 5.00

152 Tor Steel Rods including transport to site M-152 Kg. 115.00

153 Tower / Skeleton Brass Bolts M-153 No 145.00

154 Varnish M-154 Ltr 355.00

155 Wall Tiles Glazed 6" x 6" M-155 No 75.00

156 Wall Tiles Glazed 8" x 12" M-156 No 100.00

157 Water M-157 Gal 0.30

158 Wax Polish M-158 Lbs 150.00

159 White Cement/ tile grout M-159 Lbs 17.50

160 Wire Brush M-160 No 65.00

161 Wire Nails M-161 Lbs 50.00


162 Wire Nails 2" Long M-162 Lbs 25.00

163 Wire Nails 6" Long M-163 Lbs 25.00

164 Wirecut Bricks M-164 No 8.75

165 Wood Preservative M-165 Gal 450.00

166 Yellow Ochre M-166 Lbs 15.00


Activity

1 Site Preparation & Excavation

2 Earth work support and Filling

3 Anti Termite Treatment & DPC

4 Random Rubble Masonry Work

5 Concrete Work

6 Formwork Note

7 Reinforcement Rate Break Downs of all trades are accordin


Rate Break Downs of Concrete Works
8 Block Work

9 Brick Work

10 Roof

11 Doors and Windows

12 Plumbing & Drainage

13 Plastering

14 Tiling

15 Ceiling

16 Painting
Downs of all trades are according to the Building Schedule of Rates of the Department of Buildings except the
Downs of Concrete Works
Page 21 Of 109

Excavation in trenches for walls column pits in ordinary soil from 0' 0" to 5' 0" deep and depositing
01.B.03
excavated material not exceeding 30' 0"
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 U / SK Labourer L-007 Day 2.25 700.00 1,575.00

1.02 Allow 2.5% of Items ( 1.01 ) for Tools 39.38

Total for 1 Cube 1,614.38

Rate for 1 Cube 1,614.38

Rate(Say) 1Cube 1,614.38

Rate(Say) 1ft3 16.14

Rate(Say) 1m3 570.00

Excavation in trenches for walls / column pits in hard/dense soil up to a depth of 5' 0" and depositing
01.B.04
excavated material to distance not exceeding 30' 0"
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 U / SK Labourer L-007 Day 3.5 700.00 2,450.00

1.02 Allow 2.5% of Items ( 1.01 ) for Tools 61.25

Total for 1 Cube 2,511.25

Rate for 1 Cube 2,511.25

Rate(Say) 1Cube 2,511.25

Rate(Say) 1ft3 25.11

Rate(Say) 1m3 887.00

Excavation in trenches for walls column pits in mud/wet soil upto the depth of 5' 0" and depositing
01.B.05
excavated material not exceeding 30' 0"
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 U / SK Labourer L-007 Day 3 700.00 2,100.00

1.02 Allow 2.5% of Items ( 1.01 ) for Tools 52.50

Total for 1 Cube 2,100.00

Rate for 1 Cube 2,100.00

Rate(Say) 1Cube 2,100.00

Rate(Say) 1ft3 21.00

Rate(Say) 1m3 742.00

Excavation in trenches for walls column pits in soft disintegrated rock (not requiring blasting)upto
01.B.06
depth of 5' 0" and depositing excavated material to a distance not exceeding 30' 0"
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount

SDS 03/11/2018
Page 22 Of 109

1 U / SK Labourer L-007 Day 2.5 700.00 1,750.00

1.02 Allow 2.5% of Items ( 1.01 ) for Tools 43.75

Total for 1 Cube 1,793.75

Rate for 1 Cube 1,793.75

Rate(Say) 1Cube 1,793.75

Rate(Say) 1ft3 17.94

Rate(Say) 1m3 633.83

Excavation in trenches for walls column pits in Hard rock requiring Blasting upto depth of 5' 0" and
01.B.07
depositing excavated material to a distance not exceeding 30' 0"
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 Blasting Powder M-007 Lbs 0.75 200.00 150.00

1.01 Fuse wire M-051 L.ft 10 10.00 100.00

1.02 Jumper Steel M-062 Lbs 1 65.00 65.00


Allow 20% of Items ( 1, 1.01, 1.02 ) for Steel
1.03 63.00
Fuel and Forge
1.04 SK Labour L-003 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 2,978.00

Rate for 1 Cube 2,978.00

Rate(Say) 1Cube 2,978.00

Rate(Say) 1ft3 29.78

Rate(Say) 1m3 1,052.00

01.B.08 Benching rock in foundation in 3"-6" Steps (Blasting Prohibited)


Analysis for 10 Sq.ft
No Item Description Item Ref Unit Quantity Rate Amount
1 SK Labour L-003 Day 1.5 1,200.00 1,800.00

Allow 25% of Items ( 1 ) for Steel, fuel &


1.01 450.00
forge

1.02 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 10 Sq.ft 2,600.00

Rate for 1 Sq.ft 260.00

Rate(Say) 1 Sq.ft 260.00

Rate(Say) 1m2 2,797.60

01.B.09 Rock Requiring Blasting


Analysis for 1 Cube

SDS 03/11/2018
Page 23 Of 109

No Item Description Item Ref Unit Quantity Rate Amount


1.01 Labour Skilled L-003 Day 3 1,200.00 3,600.00

1.03 Allow 2.5% of Items ( 1.01, 1.02 ) for Tools 90.00

1.04 Fuel Forge etc. M-050 Ltr 0.25 100.00 25.00

1.05 Blasting powder M-007 lbs 0.68 200.00 136.00

1.06 Fuse wire M-051 L.ft 3.05 10.00 30.50

1.07 Steel Jumper M-062 lbs 0.45 46.00 20.70

Total for 1 Cube 3,902.20

Rate for 1 Cube 3,902.20

Rate(Say) 1Cube 3,902.20

Rate(Say) 1ft3 39.02

Rate(Say) 1m3 1,379.00

SDS 03/11/2018
Page 24 Of 109

02. Filling and Earth Work Support


A. Filling
B. Earthwork Support

Backfilling

02.A.01 Backfilling to trenches with selected earth available at site.


Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 U / SK Labourer L-007 Day 1 700.00 700.00

1.02 Allow 2.5% of Items ( 1 ) for Tools 17.50

Total for 1 Cube 717.50

Rate for 1 Cube 717.50

Rate(Say) 1Cube 717.50

Rate(Say) 1 ft3 7.18

Rate(Say) 1m3 254.00

02.A.02 Backfilling to trenches with Imported Material


Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1 Earth Delivered at Site M-042 Cube 1 1,500.00 1,500.00

1.01 Allow 15% of Items ( 1 ) for Compacting 225.00

1.02 U / SK Labourer L-007 Day 1.25 700.00 875.00

Total for 1 Cube 2,600.00

Rate for 1 Cube 2,600.00

Rate(Say) 1Cube 2,600.00

Rate(Say) 1 ft3 26.00

Rate(Say) 1m3 919.00

Filling under floors including levelling, watering & compacting in 3" layers with available and
02.A.03
selected earth at site
Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1.02 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.02 Allow 2.5% of Items ( 1 ) for Tools 35.00

Total for 1 Cube 1,435.00

Rate for 1 Cube 1,435.00

Rate(Say) 1Cube 1,435.00

Rate(Say) 1 ft3 14.35

SDS 03/11/2018
Page 25 Of 109

Rate(Say) 1m3 507.00

SDS 03/11/2018
Page 26 Of 109
03. Anti termite Treatment & DPC

A. Anti Termite Treatment


B. DPC

Anti Termite Treatment

03.A.01 Anti-Termite treatment on excavated foundation and compacted soil under floors.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate
1 D. D. T. Powder M-038 Lbs 16 25.00

1.01 Water M-157 Gal 20 0.30

1.02 U / SK Labourer L-007 Day 0.5 700.00

Total for 1 Sqr

Rate for 1 Sqr

Rate(Say) 1Sqr

Rate(Say) 1ft2

Rate(Say) 1m2

DPC

3/4" thick DPC in cement sand 1:2 finished with 2 coats hot tar and blinded with
03.B.01
sand.
Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate

1.01 Cement M-026 Bag 2.25 645.00

1.02 Sand M-113 Cube 0.11 8,000.00

1.03 Bitumen M-006 Gal 1.5 80.00

1.04 Fire Wood M-046 Lbs 10 250.00

1.05 Water M-157 Gal 10 0.30

1.06 Mason L-009 Day 1.25 1,200.00

1.07 U / SK Labourer L-007 Day 2.5 700.00

Total for 1 Sqr

Rate for 1 Sqr

Rate(Say) 1Sqr
Rate(Say) 1ft2
Rate(Say) 1m2

Road Development Department - North - East Province


Page 27 Of 109

under floors.

Amount
400.00

6.00

350.00

756.00

756.00

756.00

7.56

81.35

ot tar and blinded with

Amount

1,451.25

880.00

120.00

2,500.00

3.00

1,500.00

1,750.00

8,204.25

8,204.25

8,204.00

82.04

882.75

Road Development Department - North - East Province


Page 28 Of 109
04. Random Rubble Masonry Work

04.01 Random Rubble Masonry in cement mortar 1:5 in foundation

Analysis for 1 Cube


No Item Description Item Ref Unit Quantity Rate Amount
1.01 6" - 9" Rubble M-111 Cube 1.3 2,500.00 3,250.00

1.02 Cement M-026 Bag 5 645.00 3,225.00

1.03 Sand M-113 Cube 0.3 8,000.00 2,400.00

1.04 Water M-157 Gal 100 0.30 30.00

1.05 Mason L-009 Day 4 1,200.00 4,800.00

1.06 U / SK Labourer L-007 Day 6 700.00 4,200.00

Total for 1 Cube 17,905.00

Rate for 1 Cube 17,905.00

Rate(Say) 1Cube 17,905.00

Rate(Say) 1ft3 179.05

Rate(Say) 1m3 6,326.86

04.02 Random Rubble Masonry in cement mortar 1:5 in Superstructure


Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1.01 6" - 9" Rubble M-111 Cu 1.3 2,500.00 3,250.00

1.02 Cement M-026 Bag 5 645.00 3,225.00

1.03 Sand M-113 Cu 0.3 8,000.00 2,400.00

1.04 Water M-157 Gal 100 0.30 30.00

1.05 Mason L-009 Day 4.5 1,200.00 5,400.00

1.06 U / SK Labourer L-007 Day 7 700.00 4,900.00


Allow 3% of Items ( 1.05, 1.06 ) for
1.07 - - - - 309.00
Scaffolding
Total for 1 Cube 19,514.00

Rate for 1 Cube 19,514.00

Rate(Say) 1Cube 19,514.00

Rate(Say) 1ft3 195.14

Rate(Say) 1m3 6,895.41


Page 29 Of 109

19,695.50
Page 30 Of 109
05. Concrete Work

A. Mixing Concrete

B. Screed

C. Mass Concrete

D. Column

E. Beam

F. Slab

G. Lintol

Mixing Concrete

05.A.01 Mixing Concrete 1:1-1/2:3(3/4")


Analysis for 1 Cube
No. Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 23 645.00 14,835.00

1.02 Sand M-113 Cube 0.42 8,000.00 3,360.00

1.03 3/4 " Metal M-066 Cube 0.82 4,000.00 3,280.00

1.04 Hire of Mixer P-001 Day 0.333 1,500.00 499.50

1.05 Water M-157 Gal 150 0.30 45.00

1.06 SK Labour L-003 Day 0.333 1,200.00 399.60

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 23,819.10

Rate for 1 Cube 23,819.10

Rate(Say) 1Cube 23,820.00

Rate(Say) 1m3 8,416.96

05.A.02 Mixing Concrete 1:3:6(1 1/2")


Analysis for 1 Cube

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 13 645.00 8,385.00

1.02 Sand M-113 Cube 0.53 8,000.00 4,240.00

1.03 1 1/2 " Metal M-065 Cube 0.92 3,500.00 3,220.00

1.04 Hire of Mixer P-001 Day 0.333 1,500.00 499.50

1.05 Water M-157 Gal 110 0.30 33.00

1.06 SK Labour L-003 Day 0.333 1,200.00 399.60

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 18,177.10

Rate for 1 Cube 18,177.10


Page 31 Of 109
Rate(Say) 1Cube 18,180.00

Rate(Say) 1m3 6,424.03

05.A.03 Mixing Concrete 1:2 1/2 :5 (1")


Analysis for 1 Cube

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 14 645.00 9,030.00

1.02 Sand M-113 Cube 0.6 8,000.00 4,800.00

1.03 1 " Metal M-064 Cube 0.9 8,000.00 7,200.00

1.04 Hire of Mixer P-001 Day 0.333 1,500.00 499.50

1.05 Water M-157 Gal 100 0.30 30.00

1.06 SK Labour L-003 Day 0.333 1,200.00 399.60

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 23,359.10

Rate for 1 Cube 23,359.10

Rate(Say) 1Cube 23,360.00

Rate(Say) 1m3 8,254.42

05.A.04 Mixing Concrete 1:2:4(3/4")


Analysis for 1 Cube

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 18 645.00 11,610.00

1.02 Sand M-113 Cube 0.5 8,000.00 4,000.00

1.03 3/4 " Metal M-066 Cube 0.88 4,000.00 3,520.00

1.04 Hire of Mixer P-001 Day 0.333 1,500.00 499.50

1.05 Water M-157 Gal 120 0.30 36.00

1.06 SK Labour L-003 Day 0.333 1,200.00 399.60

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 21,465.10

Rate for 1 Cube 21,465.10

Rate(Say) 1Cube 21,470.00

Rate(Say) 1m3 7,586.57

05.A.05 Mixing Concrete 1:1:2(3/4")


Analysis for 1 Cube
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Cement M-026 Bag 31 645.00 19,995.00

1.02 Sand M-113 Cube 0.44 8,000.00 3,520.00


Page 32 Of 109
1.03 3/4 " Metal M-066 Cube 0.96 4,000.00 3,840.00

1.04 Hire of Mixer P-001 Day 0.333 1,500.00 499.50

1.05 Water M-157 Gal 200 0.30 60.00

1.06 SK Labour L-003 Day 0.333 1,200.00 399.60

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Cube 29,714.10

Rate for 1 Cube 29,714.10

Rate(Say) 1Cube 29,710.00

Rate(Say) 1m3 10,498.23

Screed Concrete

05.B.01 2" thick Cement Concrete screed 1:3:6 (1 1/2) in foundation at depth not exceed in 5' 0"
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Mixing Concrete 1:3:6(1 1/2") 05.A.02 Cube 0.1667 18,180.00 3,030.61

1.02 SK Labour L-003 Day 0.125 1,200.00 150.00

1.03 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 3,530.61

Rate for 1 Sqr 3,530.61

Rate(Say) 1 Sqr 3,530.00

Rate(Say) 1ft2 35.30

Rate(Say) 1m2 379.83

05.B.02 3" Thick cement concrete 1:3:6(1-1/2") screed in foundation at depths not exceeding 5' 0"
Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Mixing Concrete 1:3:6(1 1/2") 05.A.02 Cube 0.25 18,180.00 4,545.00

1.02 SK Labour L-003 Day 0.125 1,200.00 150.00

1.03 U / SK Labourer L-007 Day 0.75 700.00 525.00

Total for 1 Sqr 5,220.00

Rate for 1 Sqr 5,220.00

Rate(Say) 1 Sqr 5,220.00

Rate(Say) 1ft2 52.20

Rate(Say) 1m2 561.67

Mass Concrete

05.C.01 6" Thick cement concrete 1:2-1/2:5(1") in floor (Mass concrete)


Analysis for 1 Sqr Page 33 Of 109

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Mixing Concrete 1:2 1/2 : 5(1") 05.A.03 Cube 0.5 23,360.00 11,680.00

1.025 Water M-157 Gal 200 0.30 60.00

1.03 SK Labour L-003 Day 0.5 1,200.00 600.00

1.04 U / SK Labourer L-007 Day 1.25 700.00 875.00

Total for 1 Sqr 13,215.00

Rate for 1 Sqr 13,215.00

Rate(Say) 1 Sqr 13,220.00

Rate(Say) 1ft2 132.20

Rate(Say) 1m2 1,422.47

Column Concrete

05.D.01 Cement concrete 1:11/2 : 3(3/4") in 13-1/2" X 13-1/2" columns in ground floor.
Analysis for 0.51 Cube

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Mixed Concrete 1:1 1/2 : 3 (3/4") 05.A.01 Cube 0.51 23,820.00 12,148.20

Allow 5% of Items ( 1.01 ) for Wastage 607.41

1.025 Hire of Vibrator P-002 Day 0.5 1,000.00 500.00

1.03 Mason L-009 Day 0.5 1,200.00 600.00

1.04 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

1.05 SK Labourer (Vibrator) L-004 Day 0.5 1,200.00 600.00

1.06 Jute Hessian M-063 Sq.ft 45 3.50 157.50

1.07 Water M-157 Gal 100 0.30 30.00

1.08 U / SK Labourer (curing) L-007 Day 0.5 700.00 350.00

Total for 0.51 Cube 16,043.11

Rate for 1 Cube 31,457.08

Rate(Say) 1Cube 31,457.00

Rate(Say) 1m3 11,115.55

Ground floor - First Floor 1m3 11,115.55

First Floor - Second Floor 1m3 12,227.10

Second Floor - Third Floor 1m3 13,449.81

Third Floor - Fourth Floor 1m3 14,794.79


Page 34 Of 109

06.A.01 Sawn timber formwork to 9" x 9" cement concrete column in ground floor.
Analysis for 0.15 Sq
No Item Description Item Ref Unit Quantity Rate Amount
Sawn timber formwork to 9" x 9" cement concrete
1.01 06.A.02 1 Use 1 694.00 694.00
column in ground floor - Making Mould
1.02 Bolts 16mm 18" (12 nos 20 uses) M-010 No 0.6 75.00 45.00

1.03 Mould Oil M-071 litre 0.5 35.00 17.50

1.04 Timber props 4" x 2" M-144 L.ft 3.5 65.00 227.50

1.05 Carpenter - assembling L-008 Day 0.25 1,200.00 300.00

1.06 U / SK Labourer - assembling L-007 Day 0.25 700.00 175.00

1.07 Carpenter - dismantling, cleaning & repairing L-008 Day 0.25 1,200.00 300.00
U / SK Labourer - dismantling, cleaning &
1.08 L-007 Day 0.25 700.00 175.00
repairing
Total for 0.15 Sq 1,934.00

Rate for 1 Sq 12,893.33

Rate(Say) 1Sq 12,893.00

Rate(Say) 1ft2 128.93

Rate(Say) 1m2 1,387.29

Ground floor - First Floor 1m2 1,387.29

First Floor - Second Floor 1m2 1,526.02

Second Floor - Third Floor 1m2 1,678.62

Third Floor - Fourth Floor 1m2 1,846.48

06.A.02 Sawn timber formwork to 9" x 9" cement concrete column in ground floor - Making Mould
Analysis for 4 Uses
No Item Description Item Ref Unit Quantity Rate Amount
1.01 1" Thick Class II Timber M-141 Sq.ft 18.15 65.00 1,179.75

1.02 2" x 2" Class II Timber In Yokes M-143 L.ft 17.1 22.00 376.20

1.03 2" x 1" Class II Timber Battens. M-142 L.ft 16.12 12.00 193.44

1.04 Wire Nails M-161 Lbs 1.5 50.00 75.00

1.05 Carpenter L-008 Day 0.5 1,200.00 600.00

1.06 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 4 Uses 2,774.39

Rate for 1 Uses 693.60

Rate(Say) 1 Use 694.00

Beam

SDS 03/11/2018
Page 35 Of 109

06.B.01 Sawn timber formwork for concrete beams in ground floor


Analysis for 0.55 Sq
No Item Description Item Ref Unit Quantity Rate Amount
Sawn timber formwork for 9" x 12" concrete beams
1.01 06.B.02 1 Use 1 2,607.00 2,607.00
in ground floor - Making the mould
Sawn timber formwork for concrete beams in
1.02 06.B.03 1 Use 1 1,568.00 1,568.00
ground floor-Assembling

1.03 Allow 10% of Items ( 1.02 ) for Repairs - - - - 156.80

1.04 Carpenter - Assembling L-008 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer - Assembling L-007 Day 2 700.00 1,400.00

1.06 Mould Oil M-071 litre 0.5 35.00 17.50

1.07 Wire Nails M-161 Lbs 0.5 65.00 32.50

1.08 Carpenter - dismantling, cleaning & repairing L-008 Day 0.5 1,200.00 600.00

U / SK Labourer - dismantling, cleaning &


1.09 L-007 Day 2 700.00 1,400.00
repairing
Total for 0.55 Sq 8,981.80

Rate for 1 Sq 16,330.55

Rate(Say) 1Sq 16,331.00

Rate(Say) 1ft2 163.31

Rate(Say) 1m2 1,757.22

Ground floor 1m2 1,757.22

First Floor 1m2 1,932.94

Second Floor 1m2 2,126.23

Third Floor 1m2 2,338.85

06.B.02 Sawn timber formwork for 9" x 12" concrete beams in ground floor - Making the mould
Analysis for 4 Uses
No Item Description Item Ref Unit Quantity Rate Amount
1.01 1" Thick Class II Timber M-141 Sq.ft 60 65.00 3,900.00

1.02 2" x 1" Class II Timber Battens. M-142 L.ft 24 12.00 288.00

1.03 2" x 2" Class II Timber In Yokes M-143 L.ft 45 22.00 990.00

1.04 4"X2" Timber bearers M-144 L.ft 30 65.00 1,950.00

1.05 Wire Nails M-161 Lbs 2 50.00 100.00

1.06 Carpenter L-008 Day 1.5 1,200.00 1,800.00

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 4 Uses 10,428.00

Rate for 1 Uses 2,607.00

Rate(Say) 1 Use 2,607.00

SDS 03/11/2018
Page 36 Of 109

06.B.03 Sawn timber formwork for concrete beams in ground floor-Assembling - Materials
Analysis for 6 Uses
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Timber props 4" x 2" M-144 L.ft 110 65.00 7,150.00

1.02 2" x 2" Class II Timber for bracings M-143 L.ft 80 22.00 1,760.00

1.03 1" Thick Class II Timber base plate M-141 Sq.ft 6 65.00 390.00

1.04 Timber Wedges M-151 No 22 5.00 110.00

Total for 6 Uses 9,410.00

Rate for 1 Uses 1,568.33

Rate(Say) 1 Use 1,568.00

Slab

06.C.01 Sawn timber formwork for underside of first floor slab


Analysis for 2 Sq
No Item Description Item Ref Unit Quantity Rate Amount
Sawn timber formwork for 20" x 10" concrete slab
1.01 06.C.02 1 Use 1 7,016.00 7,016.00
in ground floor - Making panels
1.02 Allow 20% of Items ( 1.01 ) for Repairs - - - - 1,403.20
Sawn timber formwork for underside of first floor
1.03 06.C.03 Sq 1 8,176.00 8,176.00
slab - assembling
1.04 Allow 20% of Items ( 1.03 ) for Wastage - - - - 1,635.20

1.04 Carpenter - Assembling L-008 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer - Assembling L-007 Day 4 700.00 2,800.00

1.06 Mould Oil M-071 litre 4.54 35.00 158.90

1.07 Wire Nails M-161 Lbs 2 50.00 100.00

1.08 Carpenter - dismantling, cleaning & repairing L-008 Day 0.5 1,200.00 600.00
U / SK Labourer - dismantling, cleaning &
1.09 L-007 Day 2 700.00 1,400.00
repairing
Total for 2 Sq 24,489.30

Rate for 1 Sq 12,244.65

Rate(Say) 1Sq 12,245.00

Rate(Say) 1ft2 122.45

Rate(Say) 1m2 1,317.56

Ground floor 1m2 1,317.56

First Floor 1m2 1,449.32

Second Floor 1m2 1,594.25

Third Floor 1m2 1,753.68

06.C.02 Sawn timber formwork for 20" x 10" concrete slab in ground floor - Making panels
Analysis for 4 Uses
No Item Description Item Ref Unit Quantity Rate Amount

SDS 03/11/2018
Page 37 Of 109

1.01 1" Thick Class II Timber M-141 Sq.ft 220 65.00 14,300.00

1.02 Timber props 4" x 2" M-144 L.ft 121 65.00 7,865.00

1.03 Wire Nails M-161 Lbs 4 50.00 200.00

1.04 Carpenter L-008 Day 3 1,200.00 3,600.00

1.05 U / SK Labourer L-007 Day 3 700.00 2,100.00

Total for 4 Uses 28,065.00

Rate for 1 Uses 7,016.25

Rate(Say) 7,016.00

06.C.03 Sawn timber formwork for underside of first floor slab - Assembling
Analysis for 6 Uses
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Timber props 4" x 2" M-144 L.ft 690 65.00 44,850.00

1.02 2" x 2" Class II Timber In Yokes M-143 L.ft 66 22.00 1,452.00

1.03 Timber Wedges M-151 No 122 5.00 610.00

1.04 1" Thick Class II Timber M-141 Sq.ft 33 65.00 2,145.00

Total for 6 Uses 49,057.00

Rate for 1 Uses 8,176.17

Rate(Say) 8,176.00

SDS 03/11/2018
Page 38 Of 109
07. Reinforcement

Tor steel reinforcement to lintels, slabs, beams or columns bent to shape, laid in position and tied
7.01
with G.I. Wire as directed.
Analysis for 1 Cwt.
No Item Description Item Ref Unit Quantity Rate Amount

1.01 M.S./Tor Steel Rods including transport to site M-152 kg 50 115.00 5,750.00

1.02 Allow 15% of Items ( 1.01 ) for Wastage - - - - 862.50

1.03 16 BWG Binding Wire M-005 Lbs 1.5 100.00 150.00


Allow 1.5% of Items ( 1.01 ) for spaces or
1.04 - - - - 86.25
chairs
1.05 SK Labour L-003 Day 1 1,200.00 1,200.00

1.06 U / SK Labourer L-007 Day 1 700.00 700.00

Total for 1 Cwt. 8,748.75

Rate for 1 Cwt. 8,748.75

Rate(Say) 1Cwt 8,749.00

Rate(Say) 1Kg 174.98

Mild Steel reinforcement to lintels, slabs, beams or columns bent to shape, laid in position and tied
7.02
with G.I. Wire as directed.
Analysis for 1 Cwt.
No Item Description Item Ref Unit Quantity Rate Amount

1.01 M.S./Tor Steel Rods including transport to site M-068 kg 50 68.00 3,400.00

1.02 Allow 15% of Items ( 1.01 ) for Wastage - - - - 510.00

1.03 16 BWG Binding Wire M-005 Lbs 1.5 100.00 150.00

1.04 SK Labour L-003 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 1 700.00 700.00

Total for 1 Cwt. 5,960.00

Rate for 1 Cwt. 5,960.00

Rate(Say) 1Cwt 5,960.00

Rate(Say) 1Kg 119.20


Page 39 Of 109

10,498.80

209.98 10,498.80
Page 40 Of 109

08. Block Work

08.01 8" Thick hollow block work in cement and sand mortar 1:5 in ground floor (Cavities unfilled)
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Hollow Cement Block (16"x 8"x 8") M-057 No 112 30.00 3,360.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 168.00

1.03 Cement M-026 Bag 0.75 645.00 483.75

1.04 Sand M-113 Cube 0.06 8,000.00 480.00

1.05 Mason L-009 Day 1.5 1,200.00 1,800.00

1.06 U / SK Labourer L-007 Day 2.5 700.00 1,750.00

1.07 Allow 3% of Items ( 1.05, 1.06 ) for Scaffolding - - - - 106.50

Total for 1 Sqr 8,148.25

Rate for 1 Sqr 8,148.25

Rate(Say) 1 Sq 8,148.00

Rate(Say) 1ft2 81.48

Rate(Say) 1m2 876.72

Ground floor 1m2 876.72

First Floor 1m2 964.40

Second Floor 1m2 1,060.84

3rd floor 1m2 1,166.92

08.02 6" Thick hollow block work in cement and sand mortar 1:5 with cavities unfilled.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Hollow Cement Blocks (16"x 8"x 6") M-059 No 112 60.00 6,720.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 336.00

1.03 Cement M-026 Bag 0.75 645.00 483.75

1.04 Sand M-113 Cube 0.07 8,000.00 560.00

1.05 Mason L-009 Day 1.5 1,200.00 1,800.00

1.06 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.07 Allow 3% of Items ( 1.05, 1.06 ) for Scaffolding - - - - 96.00

Total for 1 Sqr 11,395.75

Rate for 1 Sqr 11,395.75

Rate(Say) 1 Sq 11,395.75

Rate(Say) 1ft2 113.96


Page 41 Of 109
Rate(Say) 1m2 1,226.18

Ground floor 1m2 1,226.18

First Floor 1m2 1,348.80

Second Floor 1m2 1,483.68

Third Floor 1m2 1,632.05

08.03 4" Thick hollow block work in cement and sand mortar 1:5 with cavities unfilled.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Hollow Cement Blocks (16"x 8"x 4") M-058 No 112 38.00 4,256.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 212.80

1.03 Cement M-026 Bag 0.4 645.00 258.00

1.04 Sand M-113 Cube 0.03 8,000.00 240.00

1.05 Mason L-009 Day 1 1,200.00 1,200.00

1.06 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.07 Allow 5% of Items ( 1.05, 1.06 ) for Scaffolding - - - - 130.00

Total for 1 Sqr 7,696.80

Rate for 1 Sqr 7,696.80

Rate(Say) 1 Sq 7,696.80

Rate(Say) 1ft2 76.97

Rate(Say) 1m2 828.18

Ground floor 1m2 828.18

First Floor 1m2 910.99

Second Floor 1m2 1,002.09

Third Floor 1m2 1,102.30


Page 42 Of 109

4,491.75

8,099.75

2,500.00

10,599.75

125.00

10,724.75 643.49 11,368.24

2,681.19 2,842.06

13,405.94 14,210.29
Page 43 Of 109

9,043.74
Page 44 Of 109
09. Brick Work

09.01 Brick Work in cement sand 1:5 in 4-1/2" thick walls in ground floor
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Bricks M-019 No 550 6.00 3,300.00
1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 165.00

1.03 Cement M-026 Bag 1.3 645.00 838.50

1.04 Sand M-113 Cu 0.1 8,000.00 800.00

1.05 Water M-157 Gal 50 0.30 15.00

1.06 Mason L-009 Day 1.5 1,200.00 1,800.00

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00


Allow 5% of Items (1.06, 1.07 ) for
1.08 - - - - 160.00
Scaffolding
Total for 1 Sqr 8,478.50

Rate for 1 Sqr 8,478.50

Rate(Say) 1 Sq 8,479.00

Rate(Say) 1ft2 84.79

Rate(Say) 1m2 912.34

Ground floor 1m2 912.34

First Floor 1m2 957.96

Second Floor 1m2 1,005.86

Third Floor 1m2 1,056.15

09.02 9" thick brick wall cement sand 1:5 in ground floor

Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 1090 6.00 6,540.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 327.00

1.03 Cement M-026 Bag 3 645.00 1,935.00

1.04 Sand M-113 Cu 0.2 8,000.00 1,600.00

1.05 Water M-157 Gal 115 0.30 34.50

1.06 Mason L-009 Day 2.25 1,200.00 2,700.00

1.07 U / SK Labour L-007 Day 3.75 700.00 2,625.00


Allow 3% of Items (1.06, 1.07 ) for
1.08 - - - - 159.75
Scaffolding
Total for 1 Sqr 15,921.25

Rate for 1 Sqr 15,921.25

Rate(Say) 1 Sq 15,921.00
Page 45 Of 109
Rate(Say) 1ft2 159.21

Rate(Say) 1m2 1,713.10

Ground floor 1m2 1,713.10

First Floor 1m2 1,798.75

Second Floor 1m2 1,888.69

Third Floor 1m2 1,983.13

09.03 Brick work in cement sand 1:5 in foundation upto D. P. C

Analysis for 1 Cube


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 1450 6.00 8,700.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 435.00

1.03 Cement M-026 Bag 4 645.00 2,580.00

1.04 Sand M-113 Cu 0.25 8,000.00 2,000.00

1.05 Water M-157 Gal 150 0.30 45.00

1.06 Mason L-009 Day 3 1,200.00 3,600.00

1.07 U / SK Labourer L-007 Day 4 700.00 2,800.00

Total for 1 Cube 20,160.00


Rate for 1 Cube 20,160.00
Rate(Say) 1 Cu 20,160.00

Rate(Say) 1ft3 201.60

Rate(Say) 1m3 7,123.67

09.04 Brick Work in cement sand 1:8 in foundation upto D. P. C

Analysis for 1 Cube

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 1450 6.00 8,700.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 435.00

1.03 Cement M-026 Bag 2.333 645.00 1,504.79

1.04 Sand M-113 Cu 0.375 8,000.00 3,000.00

1.05 Water M-157 Gal 150 0.30 45.00

1.06 Mason L-009 Day 3 1,200.00 3,600.00

1.07 U / SK Labourer L-007 Day 4 700.00 2,800.00

Total for 1 Cube 20,084.79

Rate for 1 Cube 20,084.79

Rate(Say) 1 Cu 20,085.00
Page 46 Of 109
Rate(Say) 1ft3 200.85

Rate(Say) 1m3 7,097.17

09.05 Brick Work 13 1/2" thick in cement sand 1:5 in superstructure in ground floor

Analysis for 1 Sqr


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 1630 6.00 9,780.00

1.02 Allow 5% of Items ( 1.01 ) for wastage - - - - 489.00

1.03 Cement M-026 Bag 4.5 645.00 2,902.50

1.04 Sand M-113 Cu 0.3 8,000.00 2,400.00

1.05 Water M-157 Gal 170 0.30 51.00

1.06 Mason L-009 Day 3.5 1,200.00 4,200.00

1.07 U / SK Labourer L-007 Day 5.5 700.00 3,850.00


Allow 2% of Items (1.06, 1.07 ) for
1.08 - - - - 161.00
Scaffolding
Total for 1 Sqr 23,833.50

Rate for 1 Sqr 23,833.50

Rate(Say) 1 Sq 23,834.00

Rate(Say) 1ft2 238.34

Rate(Say) 1m2 2,564.54

Ground floor 1m2 2,564.54

First Floor 1m2 2,820.99

Second Floor 1m2 3,103.09

Third Floor 1m2 3,413.40

09.06 9" Brick Walls in cement sand 1:8 in superstructure in ground floor

Analysis for 1 Sqr


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 1090 6.00 6,540.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 327.00

1.03 Cement M-026 Bag 1.75 645.00 1,128.75

1.04 Sand M-113 Cu 0.3 8,000.00 2,400.00

1.05 Water M-157 Gal 115 0.30 34.50

1.06 Mason L-009 Day 2.25 1,200.00 2,700.00

1.07 U / SK Labourer L-007 Day 3 700.00 2,100.00


Allow 3% of Items ( 1.06, 1.07 ) for
1.08 - - - - 144.00
Scaffolding
Total for 1 Sqr 15,374.25
Page 47 Of 109
Rate for 1 Sqr 15,374.25

Rate(Say) 1 Sq 15,374.00

Rate(Say) 1ft2 153.74

Rate(Say) 1m2 1,654.24

Ground floor 1m2 1,654.24

First Floor 1m2 1,819.67

Second Floor 1m2 2,001.63

Third Floor 1m2 2,201.80

4 1/2" Thick Brick Walls (wire cut) in cement sand 1:5 in superstructure in ground floor (facing to
09.07
brickwork measured separately)
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Wire cut Bricks M-164 No 550 8.75 4,812.50

1.02 Allow 2% of Items ( 1.01 ) for Wastage - - - - 96.25

1.03 Cement M-026 Bag 1.2 645.00 774.00

1.04 Sand M-113 Cu 0.08 8,000.00 640.00

1.05 Water M-157 Gal 30 0.30 9.00

1.06 Mason L-009 Day 1.5 1,200.00 1,800.00

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00


Allow 3% of Items (1.06, 1.07 ) for
1.08 - - - - 96.00
Scaffolding
Total for 1 Sqr 9,627.75

Rate for 1 Sqr 9,627.75

Rate(Say) 1 Sq 9,628.00

Rate(Say) 1ft2 96.28

Rate(Say) 1m2 1,035.97

Ground floor 1m2 1,035.97

First Floor 1m2 1,139.57

Second Floor 1m2 1,253.53

Third Floor 1m2 1,378.88

09.08 9" Thick in Cement and Sand 1:5 with wire cut Bricks (Facing to brickwork measured separately)

Analysis for 1 Sq
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Wire cut Bricks M-164 No 1060 8.75 9,275.00

1.02 Allow 4% of Items ( 1.01 ) for Wastage - - - - 371.00

1.03 Cement M-026 Bag 2.5 645.00 1,612.50


Page 48 Of 109
1.04 Sand M-113 Cu 0.18 8,000.00 1,440.00

1.05 Water M-157 Gal 100 0.30 30.00

1.06 Mason L-009 Day 2.25 1,200.00 2,700.00

1.07 U / SK Labourer L-007 Day 3.75 700.00 2,625.00


Allow 3% of Items ( 1.06, 1.07 ) for
1.08 - - - - 159.75
Scaffolding
Total for 1 Sq 18,213.25

Rate for 1 Sq 18,213.25

Rate(Say) 1 Sq 18,213.00

Rate(Say) 1ft2 182.13

Rate(Say) 1m2 1,959.72

Ground floor 1m2 1,959.72

First Floor 1m2 2,155.69

Second Floor 1m2 2,371.26

Third Floor 1m2 2,608.39

13 1/2" Thick Brick wall (wire cut) in cement and sand 1:5 in ground floor (Facing to brickwork
09.10
measured separately)
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Wire cut Bricks M-164 No 1630 8.75 14,262.50

1.02 Allow 2% of Items ( 1.01 ) for Wastage - - - - 285.25

1.03 Cement M-026 Bag 4.5 645.00 2,902.50

1.04 Sand M-113 Cu 0.3 8,000.00 2,400.00

1.05 Water M-157 Gal 50 0.30 15.00

1.06 Mason L-009 Day 3.75 1,200.00 4,500.00

1.07 U / SK Labourer L-007 Day 5.5 700.00 3,850.00


Allow 2% of Items (1.06, 1.07 ) for
1.08 - - - - 167.00
Scaffolding
Total for 1 Sqr 28,382.25

Rate for 1 Sqr 28,382.25

Rate(Say) 1 Sq 28,382.00

Rate(Say) 1ft2 283.82

Rate(Say) 1m2 3,053.90

Ground floor 1m2 3,053.90

First Floor 1m2 3,359.29

Second Floor 1m2 3,695.22

Third Floor 1m2 4,064.75


Page in
49 ground
Of 109
Extra over for facing including raised pointing 1/8" thick in cement and sand 1:1 mixture
09.11
floor
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.5 645.00 322.50

1.02 Sand M-113 Cu 0.01 8,000.00 80.00

1.03 Acid M-001 Gal 0.1 254.00 25.40

1.04 Water M-157 Gal 10 0.30 3.00

1.05 Mason L-009 Day 5 1,200.00 6,000.00

1.06 U / SK Labourer L-007 Day 3.5 700.00 2,450.00

Total for 1 Sqr 8,880.90

Rate for 1 Sqr 8,880.90

Rate(Say) 1 Sq 8,881.00

Rate(Say) 1ft2 88.81

Rate(Say) 1m2 955.60

09.12 3" Thick floor paved in lime mortar 2:5 in ground floor

Analysis for 1 Sqr


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 350 6.00 2,100.00

1.02 Slaked Lime M-115 Lbs 1.2 275.00 330.00

1.03 Sand M-113 Cu 0.11 8,000.00 880.00

1.04 Water M-157 Gal 45 0.30 13.50

1.05 Mason L-009 Day 1.25 1,200.00 1,500.00

1.06 U / SK Labourer L-007 Day 2.5 700.00 1,750.00

Total for 1 Sqr 6,573.50

Rate for 1 Sqr 6,573.50

Rate(Say) 1 Sq 6,574.00

Rate(Say) 1ft2 65.74

Rate(Say) 1m2 707.36

Steps 1' -1 1/2" x 0' 6" in brick in cement and sand 1:5 with 1/2" thick cement and sand 1:2
09.13
rendering including necessary excavation.
Analysis for 10 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 120 6.00 720.00

1.02 Cement M-026 Bag 0.5 645.00 322.50

1.03 Sand M-113 Cu 0.05 8,000.00 400.00


Page 50 Of 109
1.04 Water M-157 Gal 15 0.30 4.50

1.05 Mason L-009 Day 0.5 1,200.00 600.00

1.06 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 10 L.ft 2,397.00

Rate for 1 L.ft 239.70

Rate(Say) 1 ft 239.70

Rate(Say) 1m 786.22

Brick Drain in cement and sand 1:5 mix, 9" wide and 6"-9" average depth including cement
09.14
rendering 1/2" thick 1:2 to exposed faces with 1' 6" ramp including necessary excavation.
Analysis for 10 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 140 6.00 840.00

1.02 Cement M-026 Bag 0.8 645.00 516.00

1.03 Sand M-113 Cu 0.05 8,000.00 400.00

1.04 Water M-157 Gal 20 0.30 6.00

1.05 Mason L-009 Day 1.25 1,200.00 1,500.00

1.06 U / SK Labourer L-007 Day 1.25 700.00 875.00

Total for 10 L.ft 4,137.00

Rate for 1 L.ft 413.70

Rate(Say) 1 ft 413.70

Rate(Say) 1m 1,356.94

Brick Drain in cement and sand 1:5 mix, 9" wide and 6"-9" average depth including cement
09.15
rendering 1/2" thick 1:2 to exposed faces without ramp including necessary excavation.
Analysis for 10 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Bricks M-019 No 110 6.00 660.00

1.02 Cement M-026 Bag 0.7 645.00 451.50

1.03 Sand M-113 Cu 0.04 8,000.00 320.00

1.04 Water M-157 Gal 15 0.30 4.50

1.05 Mason L-009 Day 1 1,200.00 1,200.00

1.06 U / SK Labourer L-007 Day 1.25 700.00 875.00

Total for 10 L.ft 3,511.00

Rate for 1 L.ft 351.10

Rate(Say) 1 ft 351.10

Rate(Say) 1m 1,151.61
Page 51 Of 109

17,513.10
Page 52 Of 109
10. Roof Covering and Ceiling

A. Roof Frame & Roof Covering


B. Roof Plumbing

Roof frame & Roof Covering

Timber framework for culicut pattern tile hip roof in single storey building consisting of wall plate ,
10.A.01
beam, ridge plate, rafters etc.(Preservative treatment to be measured separately)
Analysis for 6 Sqrs
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Timber Class I M-136 Cu.ft 34 1,200.00 40,800.00

1.02 Allow 10% of Items ( 1.01 ) for Wastage - - - - 4,080.00

1.03 2"X1" Reepers M-149 L.ft 660 12.00 7,920.00

1.04 Allow 5% of Items ( 1.03 ) for Wastage - - - - 396.00

1.05 Wire Nails 6" Long M-163 Lbs 8 25.00 200.00

1.06 Wire Nails 2" Long M-162 Lbs 2 25.00 50.00

1.07 Carpenter L-008 Day 7 1,200.00 8,400.00

1.08 U / SK Labourer L-007 Day 8 700.00 5,600.00

Total for 6 Sqrs 67,446.00

Rate for 1 Sqrs 11,241.00


Rate(Say) 11,241.00

10.A.02 Roof Covering With calicut pattern clay tiles in single storeyed building

Analysis for 6 Sqrs


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Tiles M-108 No 750 16.00 12,000.00

1.02 Carpenter L-008 Day 3 1,200.00 3,600.00

1.03 U / SK Labourer L-007 Day 3 700.00 2,100.00

Total for 6 Sqrs 17,700.00

Rate for 1 Sqrs 2,950.00


Rate(Say) 2,950.00

10.A.03 Timber framework for corrugated asbestos sheet roof in single storeyed building

Analysis for 3.6 Sqrs


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Timber Class I M-136 Cu.ft 13.25 1,200.00 15,900.00

1.02 Allow 10% of Items ( 1.01 ) for Wastage - - - - 1,590.00


Page 53 Of 109
1.03 Carpenter L-008 Day 2.5 1,200.00 3,000.00

1.04 U / SK Labourer L-007 Day 3 700.00 2,100.00

Total for 3.6 Sqrs 22,590.00

Rate for 1 Sqrs 6,275.00


Rate(Say) 6,275.00

Roof covering with corrugated asbestos sheets (Timber frame work and ridge covering measured
10.A.04
separately)
Analysis for 3.6 Sqrs
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Asbestos Corrugated M-003 Sq.ft 420 26.00 10,920.00

1.02 Roofing Screws and Washers M109 No 72 3.50 252.00

1.03 Carpenter L-008 Day 1 1,200.00 1,200.00

1.04 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 3.6 Sqrs 13,772.00

Rate for 1 Sqrs 3,825.56


Rate(Say) 3,826.00

10.A.05 One layer half round clay tiles over corrugated asbestos roof covering

Analysis for 1 Sqr


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Half Round Clay Tiles M-056 No 650 5.00 3,250.00

1.02 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 1 Sqr 4,650.00

Rate for 1 Sqr 4,650.00


Rate(Say) 1 Sqr 4,650.00

10.A.06 Asbestos close fittings ridging fixed complete with roofing screws or bolts (hook)

Analysis for 13.33 L.ft.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Ridges 3' 8" Long - Asbestos M-106 Pair 4 245.00 980.00

1.02 Roofing Screws or Bolts M-110 No 16 3.50 56.00

1.03 Carpenter L-008 Day 0.25 1,200.00 300.00

1.04 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 13.33 L.ft. 1,511.00

Rate for 1 L.ft. 113.35


Rate(Say) 1 L.ft 113.00
Page 54 Of 109

10.A.07 Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar 1:1:4

Analysis for 12 L.ft.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Ridge Tiles M-105 No 9 35.00 315.00

1.02 Cement M-o26 Bag 0.333 645.00 214.79

1.03 Sand M-113 Cu 0.02 8,000.00 160.00

1.04 Slaked Lime M-115 Lbs 15 275.00 4,125.00

1.05 Colouring Powder M-036 Lbs 0.5 175.00 87.50

1.06 Mason L-009 Day 0.25 1,200.00 300.00

1.07 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 12 L.ft. 5,377.29

Rate for 1 L.ft. 448.11


Rate(Say) 448.00

10.A.08 3/4" X 9" high valance board fixed with brass screws to ends of rafters (For tile roofing)

Analysis for 100 L.ft.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 1" Planks M-147 Sq.ft 75 65.00 4,875.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 243.75

1.03 Brass Screws 1 1/2" M-015 No 100 3.75 375.00

1.04 Carpenter L-008 Day 3 1,200.00 3,600.00

1.05 U / SK Labourer L-007 Day 3 700.00 2,100.00

1.06 Allow 5% of Items ( 1.04, 1.05 ) for Wastage - - - - 285.00

Total for 100 L.ft. 11,478.75

Rate for 1 L.ft. 114.79


Rate(Say) 115.00

10.A.09 3/4" X 9" high barge board fixed with brass screws at 2 ft. 0"centres to side of rafters

Analysis for 100 L.ft.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 1" Planks M-147 Sq.ft 75 65.00 4,875.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 243.75

1.03 Brass Screws 1 1/2" M-015 No 50 3.75 187.50

1.04 Carpenter L-008 Day 3 1,200.00 3,600.00

1.05 U / SK Labourer L-007 Day 3 700.00 2,100.00


Allow 5% of Items ( 1.04, 1.05 ) for Page 55 Of 109
1.06 - - - - 285.00
Scaffolding
Total for 100 L.ft. 11,291.25

Rate for 1 L.ft. 112.91


Rate(Say) 113.00

Roof Plumbing

18 B.W.G (1.2 mm) galvanised iron sheet valley gutter 3' 0" girth over all once bent with end laps
10.B.01 not less than 9" width including 3/4" tongued and grooved planks laid to slope and profile on timber
members.
Analysis for 15 L.ft.
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Sheet (8'X4') M-052 Sheet 2 2,200.00 4,400.00

1.02 Wood Preservative M-165 Gal 0.25 450.00 112.50

1.03 Cement M-026 Bag 0.1 645.00 64.50

1.04 Slaked Lime M-115 Lbs 0.05 275.00 13.75

1.05 Sand M-113 Cu 0.01 8,000.00 80.00

1.06 1" Thick Class II Timber M-141 Sq.ft 50 65.00 3,250.00

1.07 2" Nails M-072 Lbs 2 50.00 100.00

1.08 Carpenter L-008 Day 1 1,200.00 1,200.00

1.09 U / SK Labourer L-007 Day 1 700.00 700.00

1.10 Tinker L-005 Day 0.5 1,200.00 600.00

1.11 U / SK Labourer L-007 Day 0.5 700.00 350.00

1.12 Mason L-009 Day 0.25 1,200.00 300.00

1.13 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 15 L.ft. 11,345.75

Rate for 1 L.ft. 756.38


Rate(Say) 756.00

18 B.W.G (1.2 mm) GI Flashing 1' 6" girth overall 3 thies bent with end laps not less than 6",
10.B.02 soldered, turned and tucked up to not less than 6" into chase cut in wall and pointed in 1:2 mortar,
lower end dressed over roof covering not less than 1' 0" wide
Analysis for 15 L.ft.
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Sheet (8'X4') M-052 Sheet 1 2,200.00 2,200.00

1.02 Cement M-026 Bag 0.05 645.00 32.25

1.03 Sand M-113 Cu 0.01 8,000.00 80.00

1.04 Soldering Lead M-116 Lbs 1 13.75 13.75

1.05 Tinker L-005 Day 0.5 1,200.00 600.00


Page 56 Of 109
1.06 Mason L-009 Day 0.125 1,200.00 150.00

1.07 U / SK Labourer L-007 Day 0.75 700.00 525.00

Total for 15 L.ft. 3,601.00

Rate for 1 L.ft. 240.07


Rate(Say) 240.00

6" half round PVC eave gutter fixed to timber valance board including gutter joiner and brackets
10.B.03
fixed at 18" centres (other specials paid seperately)
Analysis for 24 L.ft.
No Item Description Item Ref Unit Quantity Rate Amount
1.01 6" eave gutter lengths (12' each) M-088 No 2 0.00 -

1.02 Joiner M-055 No 1 0.00 -

1.03 gutter brackets M-054 No 17 0.00 -

1.04 3/4" brass screws M-017 No 34 1.25 42.50

1.05 Solvent cement M-117 grms 20 1.40 28.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

1.07 U / SK Labourer L-007 Day 0.5 700.00 350.00


Allow 5% of Items ( 1.06, 1.07) for
1.08 47.50
Scaffolding
Total for 24 L.ft. 1,068.00

Rate for 1 L.ft. 44.50


Rate(Say) 1 L.ft. 45.00

10.B.04 6" dia PVC gutter head

Analysis for 1 No.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 6" dia PVC gutter head M-089 No 1 0.00 -

1.02 Gutter Joiner M-055 No 2 0.00 -

1.03 gutter brackets M-054 No 2 0.00 -

1.04 3/4" brass screws M-017 No 4 1.25 5.00

1.05 Solvent cement M-117 grms 12 1.40 16.80

1.06 Plumber L-002 Day 0.125 1,200.00 150.00

1.07 U / SK Labourer L-007 Day 0.125 700.00 87.50


Allow 5% of Items ( 1.06, 1.07) for
1.08 11.88
Scaffolding
Total for 1 No. 271.18

Rate for 1 No. 271.18


Rate(Say) 1 No. 271.00
Page 57 Of 109

10.B.05 6" dia PVC mitres

Analysis for 1 No.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 6" dia PVC mitre bend M-091 No 1 0.00 -

1.02 Gutter Joiner M-055 No 2 0.00 -

1.03 gutter brackets M-054 No 2 0.00 -

1.04 3/4" brass screws M-017 No 4 1.25 5.00

1.05 Solvent cement M-117 grms 12 1.40 16.80

1.06 Plumber L-002 Day 0.125 1,200.00 150.00

1.07 U / SK Labourer L-007 Day 0.125 700.00 87.50


Allow 5% of Items ( 1.06, 1.07) for
1.08 11.88
Scaffolding
Total for 1 No. 271.18

Rate for 1 No. 271.18


Rate(Say) 1 No. 271.00

10.B.06 6" dia PVC end caps

Analysis for 1 No.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 end cap M-087 No 1 0.00 -

1.05 Solvent cement M-117 grms 12 1.40 16.80

1.06 Plumber L-002 Day 0.0625 1,200.00 75.00

1.07 U / SK Labourer L-007 Day 0.0625 700.00 43.75


Allow 5% of Items ( 1.06, 1.07) for
1.08 5.94
Scaffolding
Total for 1 No. 141.49

Rate for 1 No. 141.49


Rate(Say) 1 No. 141.00

3 1/2" PVC rain water down pipes fixed to brick wall with wooden plugs buried in wall (other
10.B.07
specials paid seperately)
Analysis for 24 L.ft.
No Item Description Item Ref Unit Quantity Rate Amount
1.01 3 1/2" down pipe lengths (12' each) M-078 No 2 0.00 -

1.02 3 1/2" Joiner M-090 No 1 0.00 -

1.03 PVC straps M-104 No 4 0.00 -

1.04 1" brass screws M-014 No 8 2.50 20.00

1.05 Solvent cement M-117 grms 30 1.40 42.00


Page 58 Of 109
1.06 Plumber L-002 Day 0.33 1,200.00 400.00

1.07 U / SK Labourer L-007 Day 0.33 700.00 233.33


Allow 5% of Items ( 1.06, 1.07) for
1.08 31.67
Scaffolding
Total for 24 L.ft. 727.00

Rate for 1 L.ft. 30.29


Rate(Say) 1 L.ft. 30.00

10.B.08 3 1/2" dia PVC elbow

Analysis for 1 No.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 elbow M-079 No 1 0.00 -

1.05 Solvent cement M-117 grms 32 1.40 44.80

1.06 Plumber L-002 Day 0.0625 1,200.00 75.00

1.07 U / SK Labourer L-007 Day 0.0625 700.00 43.75


Allow 5% of Items ( 1.06, 1.07) for
1.08 5.94
Scaffolding
Total for 1 No. 169.49

Rate for 1 No. 169.49


Rate(Say) 1 No. 169.00

10.B.09 3 1/2" dia PVC Shoe

Analysis for 1 No.


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Shoe M-099 No 1 0.00 -

1.05 Solvent cement M-117 grms 15 1.40 21.00

1.06 Plumber L-002 Day 0.0625 1,200.00 75.00

1.07 U / SK Labourer L-007 Day 0.0625 700.00 43.75

Allow 5% of Items ( 1.06, 1.07) for


1.08 5.94
Scaffolding
Total for 1 No. 145.69

Rate for 1 No. 145.69


Rate(Say) 1 No. 146.00
Page 59 Of 109
Page 60 Of 109

valance board

barge board
Page 61 Of 109
Page 62 Of 109

11. Doors & Windows

A. Doors & Windows


B. Ironmongery

Doors & Windows

Door Single Hung 3' 3" X7' 0" high overall with frame having 1 1/4" thick sash and 3
11.A.01
1/4" X 2 1/4 ft. timber frame(glazing, ironmongery & painting measured separately)

Analysis for 22.75 Sq.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 4"X3" Timber M-138 Cu.ft 1.5 1,300.00 1,950.00

1.02 Spur Stone M-118 No 2 15.00 30.00

1.03 Fibre / Plastic Plugs M-045 No 6 1.50 9.00

1.04 4" Long Brass Screws M-018 No 6 7.50 45.00

1.05 5/8" Mild Steel Dowels 4" Long. M-067 No 2 6.00 12.00

1.06 1 1/2" Planks M-139 Sq.ft 14 140.00 1,960.00

1.07 1" Planks M-139a Sq.ft 5 110.00 550.00

1.08 Carpenter L-008 Day 5 1,200.00 6,000.00

1.09 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

Total for 22.75 Sq.ft 11,606.00

Rate for Sq.ft 510.15


Rate(Say) 510.00

Door glazed and paneled double hung 4' 0" x 7' 0" high overall with frame including
11.A.02 1 1/4" thick sash and 3 1/4 x 2 1/4" frame (Glazing, Ironmongory and painting
measured separately)
Analysis for 28 Sq.ft

No Item Description Item Ref Unit Quantity Rate Amount

1.01 4"X3" Timber M-138 Cu.ft 1.66 1,300.00 2,158.00

1.02 Spur Stone M-118 No 2 15.00 30.00

1.03 Fibre / Plastic Plugs M-045 No 6 1.50 9.00

1.04 4" Long Brass Screws M-018 No 6 7.50 45.00

1.05 5/8" Mild Steel Dowels 4" Long. M-067 No 2 6.00 12.00

1.06 1 1/2" Planks M-139 Sq.ft 16 140.00 2,240.00

1.07 1" Planks M-139a Sq.ft 7 110.00 770.00


Page 63 Of 109
1.08 Carpenter L-008 Day 6 1,200.00 7,200.00

1.09 U / SK Labourer L-007 Day 2 700.00 1,400.00

Total for 28 Sq.ft 13,864.00

Rate for Sq.ft 495.14


Rate(Say) 495.00

Plywood door single hung 3' 1-1/2" x 6' 11-1/2" overall with frame having 1-1/4"
11.A.03 thick sash and 3 1/4" x 2 1/4" frame (Glazing, Ironmongory and painting measured
separately)
Analysis for 21.75 Sq.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 4"X3" Timber M-138 Cu.ft 1.8 1,300.00 2,340.00

1.02 Spur Stone M-118 No 2 15.00 30.00

1.03 Fibre / Plastic Plugs M-045 No 6 1.50 9.00

1.04 4" Long Brass Screws M-018 No 6 7.50 45.00

1.05 6' 9" X 2' 9" Plywood Sash M-074 No 1 2,000.00 2,000.00

1.06 Carpenter L-008 Day 0.75 1,200.00 900.00

1.07 U / SK Labourer L-007 Day 0.375 700.00 262.50

1.08 Mason - fixing frame L-009 Day 0.25 1,200.00 300.00

1.09 U / SK Labourer - fixing frame L-007 Day 0.25 700.00 175.00

Total for 21.75 Sq.ft 6,061.50

Rate for Sq.ft 278.69


Rate(Say) 279.00

Door Ledged, braced and battened single hung 2' 6" x 6' 6" overall,with frame
11.A.04 having 7/8" thick tongued & Grooved planks and 3-1/4" x 2-3/4"frame (Glazing,
Ironmongory and painting measured separately)
Analysis for 16.25 Sq.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 4"X3" Timber M-138 Cu.ft 1.7 1,300.00 2,210.00

1.02 Spur Stone M-118 No 2 15.00 30.00

1.03 Fibre / Plastic Plugs M-045 No 6 1.50 9.00

1.04 4" Long Brass Screws M-018 No 6 7.50 45.00

1.05 5/8" Mild Steel Dowels 4" Long. M-067 No 2 6.00 12.00

1.06 1" Planks M-139a Sq.ft 21 110.00 2,310.00

1.07 Brass Screws 1 1/2" M-015 No 36 3.75 135.00

1.08 Carpenter L-008 Day 2.25 1,200.00 2,700.00

1.09 U / SK Labourer L-007 Day 1 700.00 700.00


Page 64 Of 109
1.10 Mason - fixing frame L-009 Day 0.25 1,200.00 300.00

1.11 U / SK Labourer - fixing frame L-007 Day 0.25 700.00 175.00

Total for 16.25 Sq.ft 8,626.00

Rate for Sq.ft 530.83


Rate(Say) 531.00

window, Glazed 7'. 0" x 4' 0" High overall with frame comprising 3 No openable
11.A.05 sashes and 3 1/4" x 2 1/4" frame and mullions (Glazing, Ironmongory and painting
measured separately)
Analysis for 28 Sq.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 4"X3" Timber M-138 Cu.ft 3.2 1,300.00 4,160.00

1.02 4" Long Brass Screws M-018 No 4 7.50 30.00

1.03 Fibre / Plastic Plugs M-045 No 4 1.50 6.00

1.04 1 1/2" Planks M-139 Sq.ft 9.25 140.00 1,295.00

1.05 Carpenter L-008 Day 6 1,200.00 7,200.00

1.06 U / SK Labourer L-007 Day 2.5 700.00 1,750.00

1.07 Mason - fixing frame L-009 Day 0.5 1,200.00 600.00

1.08 U / SK Labourer - fixing frame L-007 Day 0.5 700.00 350.00

Total for 28 Sq.ft 15,391.00

Rate for Sq.ft 549.68


Rate(Say) 550.00

1/8" clear sheet glass panes exceeding 1' 0" but not exceeding 4 squere feet cut
11.A.06
and fixed with timber beadings to doors and windows.
Analysis for 9 Sq.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Glass panes M-027 Sq.ft 9 25.00 225.00

1.02 1/2" X 1/2" Beading M-133 L.ft 30 1.50 45.00

1.03 Brass Pannel Pins M-013 Doz 4 1.00 4.00

1.04 Glazier L-010 Day 0.5 1,200.00 600.00

1.05 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 9 Sq.ft 1,224.00

Rate for Sq.ft 136.00


Rate(Say) 136.00

Ironmongery
Page 65 Of 109
11.B.01 Butt Hinges 5" X 2 1/2" Brass

Analysis for 1.5 Pair


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Butt Hinges (pairs 1 1/2) M-023 No 3 70.00 210.00

1.02 3/4" Brass Screws M-017 No 24 1.25 30.00

1.03 Carpenter L-008 Day 0.25 1,200.00 300.00

1.04 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 1.5 Pair 715.00

Rate for Pair 476.67


Rate(Say) 477.00

11.B.02 Tee Hinges 6" X 1/2" Brass

Analysis for 1.5 Pair


No Item Description Item Ref Unit Quantity Rate Amount

1.01 Tee Hinges M-128 Pair 1 165.00 165.00

1.02 3/4" Iron Screws M-061 No 18 0.55 9.90

1.03 Carpenter L-008 Day 0.25 1,200.00 300.00

1.04 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 1.5 Pair 649.90

Rate for Pair 433.27


Rate(Say) 433.00

11.B.03 Mortice Lock

Analysis for 1 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Mortice lock with screws M-070 No 1 960.00 960.00

1.02 Carpenter L-008 Day 0.5 1,200.00 600.00

1.03 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 No 1,910.00

Rate for No 1,910.00


Rate(Say) 1,910.00

11.B.04 Casement Stays

Analysis for 4 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Casement Stays M-025 No 4 55.00 220.00

1.02 1/2 " Brass Screws M-016 No 16 1.30 20.80


Page 66 Of 109
1.03 Carpenter L-008 Day 0.25 1,200.00 300.00

1.04 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 4 No 715.80

Rate for No 178.95


Rate(Say) 179.00

11.B.05 Door Closer (Hydraulic)

Analysis for 1 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Door Closer M-040 No 1 1,850.00 1,850.00

1.02 3/4" Brass Screws M-017 No 8 1.25 10.00

1.03 Carpenter L-008 Day 0.25 1,200.00 300.00

1.04 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 1 No 2,335.00

Rate for No 2,335.00


Rate(Say) 2,335.00

11.B.06 Tower / Skeleton Brass Bolts 12"

Analysis for 1 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Tower / Skeleton Brass Bolts M-153 No 1 145.00 145.00

1.02 1/2 " Brass Screws M-016 No 10 1.30 13.00

1.03 Carpenter L-008 Day 0.063 1,200.00 75.60

1.04 U / SK Labourer L-007 Day 0.063 700.00 44.10

Total for 1 No 277.70

Rate for No 277.70


Rate(Say) 278.00

11.B.07 Barrel Bolt 4"

Analysis for 1 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Barrel Bolt M-004 No 1 75.00 75.00

1.02 1/2 " Brass Screws M-016 No 8 1.30 10.40

1.03 Carpenter L-008 Day 0.063 1,200.00 75.60

1.04 U / SK Labourer L-007 Day 0.063 700.00 44.10

Total for 1 No 205.10

Rate for No 205.10


Rate(Say) Page 67205.00
Of 109

11.B.08 Casement Fasteners

Analysis for 6 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Casement Fasteners M-024 No 6 55.00 330.00

1.02 1/2 " Brass Screws M-016 No 24 1.30 31.20

1.03 Carpenter L-008 Day 0.5 1,200.00 600.00

1.04 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 6 No 1,311.20

Rate for No 218.53


Rate(Say) 219.00

11.B.09 Check this item

Analysis for 6 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Brass Fanlight Chtches M-011 No 6 45.00 270.00

1.02 1/2 " Brass Screws M-016 No 24 1.30 31.20

1.03 Carpenter L-008 Day 0.5 1,200.00 600.00

1.04 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 6 No 1,251.20

Rate for No 208.53


Rate(Say) 209.00

11.B.10 Draw Rings

Analysis for 6 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Draw Rings M-041 No 6 22.50 135.00

1.02 1/2 " Brass Screws M-016 No 12 1.30 15.60

1.03 Carpenter L-008 Day 0.125 1,200.00 150.00

1.04 U / SK Labourer L-007 Day 0.125 700.00 87.50

Total for 6 No 388.10

Rate for No 64.68


Rate(Say) 65.00
Page 68 Of 109
Page 69 Of 109
Page 70 Of 109

12. Plumbing & Drainage

12.01 1/2 " Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 10 L.ft

No Item Description Item Ref Unit Quantity Rate Amount

1.01 1/2" PVC Pipes M-095 L.ft 13 7.50 97.50

1.02 1 " Clips and Nails M-028 No 3 7.00 21.00

1.03 Solvent Cement M-117 Grms 2 1.40 2.80

1.04 Plumber L-002 Day 0.125 1,200.00 150.00

1.05 U / SK Labourer L-007 Day 0.125 700.00 87.50

Total for 10 L.ft 358.80

Rate for L.ft 35.88

Rate(Say) 1 L.ft 36.00

12.02 3/4 " Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 10 L.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 3/4" PVC Pipes M-098 L.ft 13 14.00 182.00

1.02 1 " Clips and Nails M-028 No 3 7.00 21.00

1.03 Solvent Cement M-117 Grms 3 1.40 4.20

1.04 Plumber L-002 Day 0.125 1,200.00 150.00

1.05 U / SK Labourer L-007 Day 0.125 700.00 87.50

Total for 10 L.ft 444.70

Rate for L.ft 44.47


Rate(Say) 1 L.ft 44.00

12.03 1 " Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 100 L.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 1" PVC Pipes M-094 L.ft 100 21.00 2,100.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 105.00

1.03 1" PVC Sockets M-077 No 8 14.00 112.00

1.04 Solvent Cement M-117 Grms 32 1.40 44.80

1.05 1 " Clips and Nails M-028 No 35 7.00 245.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

1.07 U / SK Labourer L-007 Day 0.5 700.00 350.00


Page 71 Of 109
Total for 100 L.ft 3,556.80

Rate for L.ft 35.57


Rate(Say) 1 L.ft 36.00

12.04 1 1/4"Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 100 L.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/4" PVC Pipes M-093 L.ft 100 32.00 3,200.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 160.00

1.03 1 1/4" PVC Sockets M-101 No 8 19.50 156.00

1.04 Solvent Cement M-117 Grms 48 1.40 67.20

1.05 1 1/4 " Clips and Nails M-030 No 35 8.75 306.25

1.06 Plumber L-002 Day 0.75 1,200.00 900.00

1.07 U / SK Labourer L-007 Day 0.75 700.00 525.00

Total for 100 L.ft 5,314.45

Rate for L.ft 53.14


Rate(Say) 1 L.ft 53.00

12.05 1 1/2" Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 100 L.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/2" PVC Pipes M-092 L.ft 100 46.00 4,600.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 230.00

1.03 1 1/2" PVC Sockets M-100 No 8 29.50 236.00

1.04 Solvent Cement M-117 Grms 64 1.40 89.60

1.05 1 1/2 " Clips and Nails M-029 No 35 10.50 367.50

1.06 Plumber L-002 Day 0.75 1,200.00 900.00

1.07 U / SK Labourer L-007 Day 0.75 700.00 525.00

Total for 100 L.ft 6,948.10

Rate for L.ft 69.48


Rate(Say) 1 L.ft 69.00

12.06 2" Diameter PVC pipes fixed to walls (Specials paid separately)

Analysis for 100 L.ft


No Item Description Item Ref Unit Quantity Rate Amount

1.01 2" PVC Pipes M-096 L.ft 100 79.00 7,900.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 395.00


Page 72 Of 109
1.03 2" PVC Sockets M-102 No 8 48.00 384.00

1.04 Solvent Cement M-117 Grms 112 1.40 156.80

1.05 2 " Clips and Nails M-031 No 35 10.75 376.25

1.06 Plumber L-002 Day 0.75 1,200.00 900.00

1.07 U / SK Labourer L-007 Day 0.75 700.00 525.00

Total for 100 L.ft 10,637.05

Rate for L.ft 106.37


Rate(Say) 1 L.ft 106.00

12.07 3" Diameter PVC pipes fixed to walls (Specials paid separately) Type 1000

Analysis for 100 L.ft.


No Item Description Item Ref Unit Quantity Rate Amount

1.01 3" PVC Pipes M-097 L.ft 100 185.00 18,500.00


Allow 5% of Items ( 1.01 ) for
1.02 - - - - 925.00
Compaction
1.03 3" PVC Sockets M-103 No 8 192.00 1,536.00

1.04 Solvent Cement M-117 Grms 200 1.40 280.00

1.05 3 " Clips and Screws M-032 No 35 34.00 1,190.00

1.06 Plumber L-002 Day 1 1,200.00 1,200.00

1.07 U / SK Labourer L-007 Day 1 700.00 700.00

Total for 100 L.ft. 24,331.00

Rate for L.ft. 243.31


Rate(Say) 1 L.ft 243.00

Excavation for laying 1/2 " to 3" dia meter PVC pipes in ground not less than 1' 6"
12.08
Deep, Backfilling & Compacting
Analysis for 100 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 U / SK Labourer L-007 Day 2.25 700.00 1,575.00

Total for 100 L.ft 1,575.00

Rate for L.ft 15.75


Rate(Say) 1 L.ft 16.00

Chasing brickwork for laying 1/2" to 1 1/2 " dia PVC pipes and making good average
12.09
depth 2" (Pipes and specials paid separately)
Analysis for 100 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.1 645.00 64.50

1.02 Sand M-113 Cu 0.01 8,000.00 80.00

1.06 Mason L-009 Day 3 1,200.00 3,600.00


Page 73 Of 109
1.07 U / SK Labourer L-007 Day 3 700.00 2,100.00

Total for 100 L.ft 5,844.50

Rate for L.ft 58.45


Rate(Say) 1 L.ft 58.00

Chasing brickwork for laying 1 1/2" to 3 " dia PVC pipes in ground and floor and
12.10
making good. average depth 3" (Pipes and specials measured paid separately)
Analysis for 100 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.2 645.00 129.00

1.02 Sand M-113 Cu 0.03 8,000.00 240.00

1.06 Mason L-009 Day 3.5 1,200.00 4,200.00

1.07 U / SK Labourer L-007 Day 3.5 700.00 2,450.00

Total for 100 L.ft 7,019.00

Rate for L.ft 70.19


Rate(Say) 1 L.ft 70.00

12.11 1/2" dia PVC specials viz-elbow / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1/2" PVC Elbows / Bent / Socket M-083 No 10 10.50 105.00

1.02 Solvent Cement M-117 Grms 20 1.40 28.00

1.06 Plumber L-002 Day 0.25 1,200.00 300.00

Total for 10 No 433.00

Rate for No 43.30


Rate(Say) No 43.00

12.12 3/4" dia PVC specials viz-elbow / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 3/4" PVC Elbows / Bent / Socket M-076 No 10 15.00 150.00

1.02 Solvent Cement M-117 Grms 30 1.40 42.00

1.06 Plumber L-002 Day 0.25 1,200.00 300.00

Total for 10 No 492.00

Rate for No 49.20


Rate(Say) No 49.00

12.13 1" dia PVC specials viz-elbo / Bends / Sockets.


Analysis for 10 No Page 74 Of 109
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1" PVC Elbows / Bent / Socket M-082 No 10 21.00 210.00

1.02 Solvent Cement M-117 Grms 40 1.40 56.00

1.06 Plumber L-002 Day 0.25 1,200.00 300.00

Total for 10 No 566.00

Rate for No 56.60


Rate(Say) No 57.00

12.14 1 1/4" dia PVC specials viz-elbo / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/4" PVC Elbows / Bent / Socket M-081 No 10 42.00 420.00

1.02 Solvent Cement M-117 Grms 60 1.40 84.00

1.06 Plumber L-002 Day 0.25 1,200.00 300.00

Total for 10 No 804.00

Rate for No 80.40


Rate(Say) No 80.00

12.15 1 1/2" dia PVC specials viz-elbo / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/2" PVC Elbows / Bent / Socket M-080 No 10 69.00 690.00

1.02 Solvent Cement M-117 Grms 80 1.40 112.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 1,402.00

Rate for No 140.20


Rate(Say) No 140.00

12.16 2" dia PVC specials viz-elbo / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 2" PVC Elbows / Bent / Socket M-085 No 10 110.00 1,100.00

1.02 Solvent Cement M-117 Grms 140 1.40 196.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 1,896.00

Rate for No 189.60


Rate(Say) No 190.00
Page 75 Of 109

12.17 2 1/2" dia PVC specials viz-elbo / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 2 1/2" PVC Elbows / Bent / Socket M-084 No 10 350.00 3,500.00

1.02 Solvent Cement M-117 Grms 200 1.40 280.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 4,380.00

Rate for No 438.00


Rate(Say) No 438.00

12.18 3" dia PVC specials viz-elbo / Bends / Sockets.

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 3" PVC Elbows / Bent / Socket M-086 No 10 580.00 5,800.00

1.02 Solvent Cement M-117 Grms 240 1.40 336.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 6,736.00

Rate for No 673.60


Rate(Say) No 674.00

12.19 1/2" dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1/2 " Dia Tee M-122 No 10 15.50 155.00

1.02 Solvent Cement M-117 Grms 30 1.40 42.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 797.00

Rate for No 79.70


Rate(Say) No 80.00

12.20 3/4 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 3/4 " Dia Tee M-126 No 10 21.50 215.00

1.02 Solvent Cement M-117 Grms 45 1.40 63.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00


Page 76 Of 109
Total for 10 No 878.00

Rate for No 87.80


Rate(Say) No 88.00

12.21 1" dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 " Dia Tee M-120 No 10 31.25 312.50

1.02 Solvent Cement M-117 Grms 60 1.40 84.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 996.50

Rate for No 99.65


Rate(Say) No 100.00

12.22 1 1/4 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/4 " Dia Tee M-127 No 10 63.50 635.00

1.02 Solvent Cement M-117 Grms 90 1.40 126.00

1.06 Plumber L-002 Day 0.5 1,200.00 600.00

Total for 10 No 1,361.00

Rate for No 136.10


Rate(Say) No 136.00

12.23 1 1/2 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 1 1/2 " Dia Tee M-121 No 10 102.00 1,020.00

1.02 Solvent Cement M-117 Grms 120 1.40 168.00

1.06 Plumber L-002 Day 1 1,200.00 1,200.00

Total for 10 No 2,388.00

Rate for No 238.80


Rate(Say) No 239.00

12.24 2 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount
Page 77 Of 109
1.01 2 " Dia Tee M-123 No 10 165.50 1,655.00

1.02 Solvent Cement M-117 Grms 210 1.40 294.00

1.06 Plumber L-002 Day 1 1,200.00 1,200.00

Total for 10 No 3,149.00

Rate for No 314.90


Rate(Say) No 315.00

12.25 2 1/2 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 2 1/2" Dia Tee M-124 No 10 526.00 5,260.00

1.02 Solvent Cement M-117 Grms 300 1.40 420.00

1.06 Plumber L-002 Day 1.5 1,200.00 1,800.00

Total for 10 No 7,480.00

Rate for No 748.00


Rate(Say) No 748.00

12.26 3 " dia PVC Tee

Analysis for 10 No
No Item Description Item Ref Unit Quantity Rate Amount

1.01 3 " Dia Tee M-125 No 10 875.00 8,750.00

1.02 Solvent Cement M-117 Grms 360 1.40 504.00

1.06 Plumber L-002 Day 1.5 1,200.00 1,800.00

Total for 10 No 11,054.00

Rate for No 1,105.40


Rate(Say) No 1,105.00
Page 78 Of 109

1/2 " 20mm dia pipe

3/4" 25mm dia pipe

1" 32mm dia pipe

11/4" 40mm dia pipe

11/2" 50mm dia pipe

2" 63mm dia pipe

21/2" 75mm dia pipe

3" 90mm dia pipe


Page 79 Of 109
13. Plastering

A. Wall Plastering

B. Rendering

C. Sofit Plastering

D. Skirting

Wall Plastering

13.A.01 5/8" thick plastering to wall in Cement and sand 1:3 including Cement floating
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 1.4 645.00 903.00

1.02 Sand M-113 Cu 0.06 8,000.00 480.00

1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 1.5 700.00 1,050.00


Allow 3% of Items ( 1.04, 1.05 ) for
1.06 - - - - 67.50
Scaffolding
Total for 1 Sqr 3,703.50

Rate for Sqr 3,703.50

Rate(Say) 1Sq 3,704.00

Rate(Say) 1ft2 37.04

Rate(Say) 1m2 398.55

13.A.02 5/8" thick to wall in cement and sand 1:5 finished semi-rough with wooden float.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.8 645.00 516.00

1.03 Sand M-113 Cu 0.07 8,000.00 560.00

1.04 Water M-157 Gal 10 0.30 3.00

1.05 Mason L-009 Day 1 1,200.00 1,200.00

1.06 U / SK Labourer L-007 Day 1.25 700.00 875.00

Total for 1 Sqr 3,154.00

Rate for Sqr 3,154.00

Rate(Say) 1Sq 3,154.00

Rate(Say) 1ft2 31.54

Rate(Say) 1m2 339.37

Ground floor - First Floor 1m2 339.37


Page 80 Of 109
First Floor - Second Floor 1m2 373.31

Second Floor - Third Floor 1m2 410.64

Third Floor - Fourth Floor 1m2 451.70

5/8" thick to wall in lime cement and sand 1:1:5 finished semi-rough with wooden
13.A.03
float.
Analysis for 1 Sq
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.8 645.00 516.00

1.02 Slaked Lime M-115 Lbs 44 275.00 12,100.00

1.03 Sand M-113 Cu 0.07 8,000.00 560.00

1.04 Water M-157 Gal 10 0.30 3.00

1.05 Mason L-009 Day 1 1,200.00 1,200.00

1.06 U / SK Labourer L-007 Day 1.25 700.00 875.00


Allow 3% of Items ( 1.04, 1.05 ) for
1.07 - - - - 62.25
Scaffolding
Total for 1 Sqr 15,316.25

Rate for Sqr 15,316.25

Rate(Say) 1Sq 15,316.00

Rate(Say) 1ft2 153.16

Rate(Say) 1m2 1,648.00

Ground floor - First Floor 1m2 1,648.00

First Floor - Second Floor 1m2 1,812.80

Second Floor - Third Floor 1m2 1,994.08

Third Floor - Fourth Floor 1m2 2,193.49

5/8" thick Plastering to wall in lime cement and sand 1:1:5 finished smooth with
13.A.04
lime putty floating.
Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.8 645.00 516.00

1.02 Slaked Lime M-115 kg 30 275.00 8,250.00

1.03 Sand M-113 Cu 0.07 8,000.00 560.00

1.04 Water M-157 Gal 10 0.30 3.00

1.05 Mason L-009 Day 1.5 1,200.00 1,800.00

1.06 U / SK Labourer L-007 Day 1.5 700.00 1,050.00


Allow 3% of Items ( 1.05, 1.06 ) for
1.07 - - - - 85.50
Scaffolding
Total for 1 Sqr 12,264.50

Rate for Sqr 12,264.50

Rate(Say) 1Sq 12,265.00


Page 81 Of 109
Rate(Say) 1ft2 122.65

Rate(Say) 1m2 1,319.71

Ground floor - First Floor 1m2 1,319.71

First Floor - Second Floor 1m2 1,451.69

Second Floor - Third Floor 1m2 1,596.85

Third Floor - Fourth Floor 1m2 1,756.54

13.A.05 5/8" thick plastering to wall in lime and sand 2:5 including floating with lime putty.
Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Slaked Lime M-115 kg 65 275.00 17,875.00

1.02 Sand M-113 Cu 0.07 8,000.00 560.00

1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 1.75 700.00 1,225.00


Allow 3% of Items ( 1.04, 1.05 ) for
1.06 - - - - 72.75
Scaffolding
Total for 1 Sqr 20,935.75

Rate for Sqr 20,935.75

Rate(Say) 1Sq 20,936.00

Rate(Say) 1ft2 209.36

Rate(Say) 1m2 2,252.71

Rendering

13.B.01 3/4" thick rendering in cement and sand 1:3 finished smooth
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 1.75 645.00 1,128.75

1.02 Sand M-113 Cu 0.08 8,000.00 640.00

1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1.25 1,200.00 1,500.00

1.05 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.06 U / SK Labourer - curing L-007 Day 0.25 700.00 175.00

Total for 1 Sqr 4,846.75

Rate for Sqr 4,846.75

Rate(Say) 1Sq 4,847.00

Rate(Say) 1ft2 48.47

Rate(Say) 1m2 521.54


Page 82 Of 109
Ground floor 1m2 521.54

First Floor 1m2 573.69

Second Floor 1m2 631.06

Third Floor 1m2 694.17

13.B.02 1/2" thick rendering in cement and sand 1:3 finished smooth
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 1.07 645.00 690.15

1.02 Sand M-113 Cu 0.05 8,000.00 400.00

1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

Total for 1 Sqr 3,343.15

Rate for Sqr 3,343.15

Rate(Say) 1Sq 3,343.00

Rate(Say) 1ft2 33.43

Rate(Say) 1m2 359.71

13.B.03 1/2" thick rendering in cement and sand 1:2 in floors, finished smooth
Analysis for 1 Sq
No Item Description Item Ref Unit Quantity Rate Amount

` 1.01 Cement M-026 Bag 1.5 645.00 967.50

1.02 Sand M-113 Cu 0.05 8,000.00 400.00

1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1 1,200.00 1,200.00

1.05 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

1.06 U / SK Labourer - curing L-007 Day 0.25 700.00 175.00

Total for 1 Sq 3,795.50

Rate for Sq 3,795.50

Rate(Say) 1Sq 3,796.00

Rate(Say) 1ft2 37.96

Rate(Say) 1m2 408.45

13.B.04 3/4" thick rendering in cement and sand 1:2 in floors finished smooth
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 2.25 645.00 1,451.25

1.02 Sand M-113 Cu 0.08 8,000.00 640.00


Page 83 Of 109
1.03 Water M-157 Gal 10 0.30 3.00

1.04 Mason L-009 Day 1.25 1,200.00 1,500.00

1.05 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.06 U / SK Labourer - curing L-007 Day 0.25 700.00 175.00

Total for 1 Sqr 5,169.25

Rate for Sqr 5,169.25

Rate(Say) 1Sq 5,169.00

Rate(Say) 1ft2 51.69

Rate(Say) 1m2 556.18

3/4" thick rendering in cement and sand 1:2 in colored cement floors finished
13.B.05
smooth
Analysis for 1 Sqr

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 2.25 645.00 1,451.25

1.02 Sand M-113 Cu 0.08 8,000.00 640.00

1.03 Coloured Pigment M-035 Lbs 5 175.00 875.00

1.04 Water M-157 Gal 10 0.30 3.00

1.05 Mason L-009 Day 1.25 1,200.00 1,500.00

1.06 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.07 U / SK Labourer - curing L-007 Day 0.25 700.00 175.00

Total for 1 Sqr 6,044.25

Rate for Sqr 6,044.25

Rate(Say) 1Sq 6,044.00

Rate(Say) 1ft2 60.44

Rate(Say) 1m2 650.33

Sofit Plastering

3/8" thick plastering to Soffit Slab in Cement and sand 1:3 including floating with
13.C.01
Lime putty
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.8 645.00 516.00

1.02 Slaked Lime M-115 kg 8 275.00 2,200.00

1.03 Sand M-113 Cu 0.05 8,000.00 400.00

1.04 Water M-157 Gal 5 0.30 1.50

1.05 Mason L-009 Day 2.5 1,200.00 3,000.00

1.06 U / SK Labourer L-007 Day 2.5 700.00 1,750.00


Allow 3% of Items ( 1.05, 1.06 ) for
1.07 - - - - 142.50
Scaffolding
Total for 1 Sqr 7,494.00
Page 84 Of 109
Rate for Sqr 7,494.00

Rate(Say) 1Sq 7,494.00

Rate(Say) 1ft2 74.94

Rate(Say) 1m2 806.35

Ground floor 1m2 806.35

First Floor 1m2 886.99

Second Floor 1m2 975.69

Third Floor 1m2 1,073.26

3/8" thick plastering to sides and softfit of beams in Cement and sand 1:3 including
13.C.02
floating with Lime putty
Analysis for 1 Sq

No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.8 645.00 516.00

1.02 Slaked Lime M-115 kg 8 275.00 2,200.00

1.03 Sand M-113 Cu 0.05 8,000.00 400.00

1.04 Water M-157 Gal 5 0.30 1.50

1.05 Mason L-009 Day 2 1,200.00 2,400.00

1.06 U / SK Labourer L-007 Day 2 700.00 1,400.00


Allow 3% of Items ( 1.05, 1.06 ) for
1.07 - - - - 114.00
Scaffolding
Total for 1 Sqr 6,515.50

Rate for Sqr 6,515.50

Rate(Say) 1Sq 6,516.00

Rate(Say) 1ft2 65.16

Rate(Say) 1m2 701.12

Ground floor 1m2 701.12

First Floor 1m2 771.23

Second Floor 1m2 848.36

Third Floor 1m2 933.19

Skirting

1/2" x 6" Skirting in cement and sand 1:3 projected or flush to walls finished with
13.D.01
floating including forming groove
Analysis for 10 L.ft
No Item Description Item Ref Unit Quantity Rate Amount

1.01 Cement M-026 Bag 0.1 645.00 64.50

1.02 Sand M-113 Cu 0.003 8,000.00 24.00

1.03 Coloured Pigment M-035 Lbs 0.25 175.00 43.75

1.04 Mason L-009 Day 0.375 1,200.00 450.00


Page 85 Of 109
1.05 U / SK Labourer L-007 Day 0.312 700.00 218.40

Total for 10 L.ft 800.65

Rate for L.ft 80.07

Rate(Say) 1ft 80.00

Rate(Say) 1m 262.40

Ground floor 1m 262.40

First Floor 1m 288.64

Second Floor 1m 317.50

3rd floor 1m 349.25


Page 86 Of 109
Page 87 Of 109
Page 88 Of 109
Page 89 Of 109
Page 90 Of 109
14. Tilling

A. Wall Tilling

B. Floor Tilling

Wall Tilling

Glazed tiles fixed to walls including bedding in cement mortar 1:2 and raking in ground floor.
14.A.01
(Specials measured separately)
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Glazed Tiles (6''x6") M-155 No 400 75.00 30,000.00

1.02 Allow 10% of Items ( 1.01 ) for Wastage - - - - 3,000.00

1.03 Cement M-026 Bag 2.5 645.00 1,612.50

1.04 Sand M-113 Cu 0.11 8,000.00 880.00

1.05 White Cement M-159 Lbs 1 17.50 17.50

1.06 Mason L-009 Day 4 1,200.00 4,800.00

1.07 U / SK Labourer L-007 Day 4 700.00 2,800.00

1.08 U / SK Labourer L-007 Day 0.25 700.00 175.00

Total for 1 Sqr 43,285.00

Rate for 1 Sqr 43,285.00

Rate(Say) 1Sq 43,285.00

Rate(Say) 1ft2 432.85

Rate(Say) 1m2 4,657.47

Ground floor 1m2 4,657.47

First Floor 1m2 5,123.21

Second Floor 1m2 5,635.53

Third Floor 1m2 6,199.09

Glazed tiles fixed to walls including bedding in cement mortar 1:2 and raking in ground floor.
14.A.02
(Specials measured separately)
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Glazed Tiles (8''x12") M-156 No 150 100.00 15,000.00

1.02 Allow 10% of Items ( 1.01 ) for Wastage - - - - 1,500.00

1.03 Cement M-026 Bag 2.5 645.00 1,612.50

1.04 Sand M-113 Cu 0.11 8,000.00 880.00

1.05 White Cement M-159 Lbs 1 17.50 17.50

1.06 Mason L-009 Day 4 1,200.00 4,800.00

1.07 U / SK Labourer L-007 Day 4 700.00 2,800.00

1.08 U / SK Labourer L-007 Day 0.25 700.00 175.00


Page 91 Of 109
Total for 1 Sqr 26,785.00

Rate for 1 Sqr 26,785.00

Rate(Say) 1Sq 26,785.00

Rate(Say) 1ft2 267.85

Rate(Say) 1m2 2,882.07

Ground floor 1m2 2,882.07

First Floor 1m2 3,170.27

Second Floor 1m2 3,487.30

Third Floor 1m2 3,836.03

Floor Tilling

14.B.01 Terrazzo floor tiles on 1/2" thick cement and sand 1:2 in ground floor
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Terrazzo Tiles 12" X 12" M-132 No 100 150.00 15,000.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 750.00

1.03 Cement M-026 Bag 1.25 645.00 806.25

1.04 Sand M-113 Cu 0.07 8,000.00 560.00

1.05 Coloured Pigment M-035 Lbs 2 175.00 350.00

1.06 Wax Polish M-158 Lbs 0.5 150.00 75.00

1.07 Cotton Waste M-037 Lbs 2 12.50 25.00

1.08 Mason L-009 Day 4 1,200.00 4,800.00

1.09 U / SK Labourer L-007 Day 3 700.00 2,100.00

1.10 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 24,816.25

Rate for 1 Sqr 24,816.25

Rate(Say) 1Sq 24,816.00

Rate(Say) 1ft2 248.16

Rate(Say) 1m2 2,670.20

Ground floor 1m2 2,670.20

First Floor 1m2 2,937.22

Second Floor 1m2 3,230.94

Third Floor 1m2 3,554.04

14.B.02 Pressed floor tiles bedded in 1/2" cement mortar 1:2 and pointing in neat cement in ground floor
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Pressed Tiles 8" X 8" M-130 No 225 125.00 28,125.00

1.02 Allow 5% of Items ( 1.01 ) for Wastage - - - - 1,406.25


Page 92 Of 109
1.03 Cement M-026 Bag 1.25 645.00 806.25

1.04 Sand M-113 Cu 0.07 8,000.00 560.00

1.05 Colouring Powder M-036 Lbs 0.25 175.00 43.75

1.06 Cotton Waste M-037 Lbs 2 12.50 25.00

1.07 Mason L-009 Day 4 1,200.00 4,800.00

1.08 U / SK Labourer L-007 Day 4 700.00 2,800.00

1.09 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 38,916.25

Rate for 1 Sqr 38,916.25


Rate(Say) 1Sq 38,916.00
Rate(Say) 1ft2 389.16

Rate(Say) 1m2 4,187.36

Ground floor 1m2 4,187.36

First Floor 1m2 4,606.10

Second Floor 1m2 5,066.71

Third Floor 1m2 5,573.38


Page 93 Of 109
Page 94 Of 109
15. Ceiling

Timber Framework for 4' 0"x4' 0" flat asbestos ceiling (Sheet Measured separately)
15.01
Comprising of 4"x2" joists and 2"x2" bearers in class 1 timber

Analysis for 1.95 Sqrs


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Timber Class I M-136 Cu.ft 8 1,200.00 9,600.00

1.02 2" Nails M-072 Lbs 1 50.00 50.00

1.03 Fibre / Plastic Plugs M-045 No 26 1.50 39.00

1.04 Cement M-026 Bag 0.23 645.00 148.35

1.05 Sand M-113 Cu 0.02 8,000.00 160.00

1.06 Brush 2" M-022 No 0.25 165.00 41.25

1.07 Tarnap M-119 Gal 0.333 450.00 149.85

1.08 Carpenter L-008 Day 2.5 1,200.00 3,000.00

1.09 Mason L-009 Day 0.5 1,200.00 600.00

1.10 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

Allow 3% of Items ( 1.08, 1.09,


1.11 - - - - 139.50
1.10 ) for Scaffolding

Total for 1.95 Sqrs 14,977.95

Rate for 1 Sqrs 7,681.00


Rate(Say) 7,681.00

Horizontal ceiling lining using 4' 0"x4' 0" flat asbestos cement sheets fixed with and including
15.02
beading and cove mouldings on timber framework(Timber, framework, painting m/separately)

Analysis for 1.95 Sqrs


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Flat Asbestos Sheets M-048 Sq.ft 210 15.00 3,150.00

1.02 2"X2" halmilla Cove Moulding M-145 Sq.ft 60 35.00 2,100.00

1.03 1 1/2"X1/2" Halmilla Beadings M-134 L.ft 125 12.00 1,500.00

1.04 1/4" clout Nails M-033 lbs 0.25 25.00 6.25

1.05 Brass Screws 1 1/2" M-015 No 96 3.75 360.00


1.06 Carpenter L-008 Day 1.5 1,200.00 1,800.00

1.07 U / SK Labourer L-007 Day 2 700.00 1,400.00


Allow 3% of Items ( 1.06, 1.07 ) for
1.08 - - - - 96.00
Scaffolding
Total for 1.95 Sqrs 10,412.25

Rate for 1 Sqrs 5,339.62


Rate(Say) 5,340.00

3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on 4"X2" class I
15.03
timber Joists at 2' 0" centres with 1 1/2 " Brass Nails

Analysis for 1.95 Sqrs


No Item Description Item Ref Unit Quantity Rate Amount
1.01 4" x 2" Timber Joists M-146 L.ft 115 65.00 7,475.00
6" x 3/4" Lunumidella Ceiling
1.02 M-135 Sq.ft 215 28.00 6,020.00
Planks.
1.03 Cement M-026 Bag 0.027 645.00 17.42

1.04 Sand M-113 Cu 0.04 8,000.00 320.00

1.05 1 1/2 brass Nails M-012 lbs 9 50.00 440.53


Mason - making holes, fixing joists &
1.06 L-009 Day 1 1,200.00 1,200.00
making goods
Carpenter - making holes, fixing
1.07 L-008 Day 1 1,200.00 1,200.00
joists & making goods
U / SK Labourer - making holes,
1.08 L-007 Day 3 700.00 2,100.00
fixing joists & making goods
1.09 Carpenter - Fixing ceiling boards L-008 Day 3 1,200.00 3,600.00
U / SK Labourer - Fixing ceiling
1.10 L-007 Day 4 700.00 2,800.00
boards
Allow 3% of Items (1.06, 1.07, 1.08,
1.11 - - - - 327.00
1.09, 1.10) for Scaffolding
Total for 1.95 Sqrs 25,499.94

Rate for 1 Sqrs 13,076.89


Rate(Say) 13,077.00

3/4" X 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of roof
15.04
rafters. (Existing) with 1 1/2" brass nails including levelling with timber strips where necessary

Analysis for 1.8 Sq


No Item Description Item Ref Unit Quantity Rate Amount
6" x 3/4" Lunumidella Ceiling
1.01 M-135 Sq.ft 220 28.00 6,160.00
Planks.
1.02 2" X 1/4" Timber Strips M-150 L.ft 40 5.00 200.00

1.03 3/4" Nails M-073 Lbs 4.5 20.00 90.00

1.04 1 1/2" Brass Nails M-012 Lbs 9 50.00 440.53

1.05 Carpenter L-008 Day 3 1,200.00 3,600.00

1.06 U / SK Labourer L-007 Day 6 700.00 4,200.00


Allow 3% of Items ( 1.05, 1.06 ) for
1.07 - - - - 234.00
Scaffolding
Total for 1.8 Sq 14,924.53

Rate for 1 Sq 8,291.40


Rate(Say) 8,291.00
Page 99 Of 109

16. Painting

A. Wall

B. Sofit

C. Wood

D. Steel

Wall

16.A.01 Preparing and apply one coat of Alkali resistant primer and two coats of emulsion paint to walls.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Primer M-075 litre 0.9 180.00 162.00

1.02 Emulsion Paint M-043 litre 1.4 280.00 392.00

1.03 Water M-157 Gal 0.1 0.30 0.03

1.04 6" Brush M-021 No 0.1 495.00 49.50

1.05 Sand Papers M-114 Sheet 2 3.50 7.00

1.06 Painter L-001 Day 1.25 1,200.00 1,500.00

1.07 Allow 3% of Items (1.06) for Scaffolding - - - - 45.00

Total for 1 Sqr 2,155.53

Rate for 1 Sqr 2,155.53

Rate(Say) 1 Sq 2,156.00

Rate(Say) 1ft2 21.56

Rate(Say) 1m2 231.99

Ground floor 1m2 231.99

First Floor 1m2 255.18

Second Floor 1m2 280.70

Third Floor 1m2 308.77

16.A.02 Painting walls with emulsion paint (2 Coats)


Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Emulsion Paint - first coat M-043 litre 0.757 280.00 211.96

1.02 Emulsion Paint - Second coat M-043 litre 0.649 280.00 181.72

1.03 6" Brush M-021 No 0.1 495.00 49.50

1.04 Water M-157 Gal 0.1 0.30 0.03

1.05 Painter L-001 Day 0.75 1,200.00 900.00

1.06 Allow 3% of Items (1.05 ) for Scaffolding - - - - 27.00

Total for 1 Sqr 1,370.21

Rate for 1 Sqr 1,370.21


Page 100 Of 109
Rate(Say) 1 Sq 1,370.00

Rate(Say) 1ft2 13.70

Rate(Say) 1m2 147.41

Ground floor 1m2 147.41

First Floor 1m2 162.15

Second Floor 1m2 178.37

Third Floor 1m2 196.21

16.A.03 White or colourwashing two coats in single storey


Analysis for 10 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Boild Lime M-009 Cwt 0.5 300.00 150.00

1.02 Salt M-112 Lbs 2 10.00 20.00

1.03 Yellow Ochre M-166 Lbs 0.5 15.00 7.50

1.04 Blue M-008 Ozs 2 10.00 20.00

1.05 6" Brush M-021 No 0.333 495.00 165.83

1.06 Water M-157 Gal 10 0.30 3.00

1.07 Painter L-001 Day 2.5 1,200.00 687.50

1.08 U / SK Labourer L-007 Day 2.5 700.00 500.00

1.09 Allow 3% of Items (1.07, 1.08 ) for Scaffolding - - - - 35.63

Total for 10 Sqr 1,589.46

Rate for 1 Sqr 158.95

Rate(Say) 1 Sq 159.00

Rate(Say) 1ft2 1.59

Rate(Say) 1m2 17.11

16.A.04 White or colourwashing two coats in two storeyed building


Analysis for 10 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Boild Lime M-009 Cwt 0.5 300.00 150.00

1.02 Salt M-112 Lbs 2 10.00 20.00

1.03 Yellow Ochre M-166 Lbs 0.5 15.00 7.50

1.04 Blue M-008 Ozs 2 10.00 20.00

1.05 6" Brush M-021 No 0.333 495.00 164.84

1.06 Water M-157 Gal 10 0.30 3.00

1.07 Painter L-001 Day 3 1,200.00 3,600.00

1.08 U / SK Labourer L-007 Day 3 700.00 2,100.00

1.09 Allow 3% of Items (1.07, 1.08 ) for Scaffolding - - - - 171.00

Total for 10 Sqr 6,236.34


Page 101 Of 109
Rate for 1 Sqr 623.63

Rate(Say) 1 Sqr 624.00

Rate(Say) 1ft2 6.24

Rate(Say) 1m2 67.14

16.A.05 Cement washing to walls of single storyed building 2 coats


Analysis for 10 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Cement M-026 Bag 0.625 645.00 403.13

1.02 6" Coir Brush M-034 No 1 45.00 45.00

1.03 Water M-157 Gal 5 0.30 1.50

1.04 Painter L-001 Day 2 1,200.00 2,400.00

1.05 U / SK Labourer L-007 Day 2 700.00 1,400.00

1.06 Allow 3% of Items ( 1.04, 1.05 ) for Scaffolding - - - - 114.00

Total for 10 Sqr 4,363.63

Rate for 1 Sqr 436.36

Rate(Say) 1 Sq 436.00

Rate(Say) 1ft2 4.36

Rate(Say) 1m2 46.91

Ground floor 1m2 46.91

First Floor 1m2 51.60

Second Floor 1m2 56.77

Third Floor 1m2 62.44

Soffit

Preparing and apply one coat of alkali resistant primer and two coats of emulsion paint to soffit of
16.B.01
slabs
Analysis for 1 Sq
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Primer M-075 litre 0.9 180.00 162.00

1.02 Emulsion Paint M-043 litre 1.5 280.00 420.00

1.03 Water M-157 Gal 0.1 0.30 0.03

1.04 6" Brush M-021 No 0.1 495.00 49.50

1.05 Painter L-001 Day 1.75 1,200.00 2,100.00

1.06 Allow 3% of Items (1.05 ) for Scaffolding - - - - 63.00

Total for 1 Sq 2,794.53

Rate for 1 Sq 2,794.53

Rate(Say) 1 Sq 2,795.00

Rate(Say) 1ft2 27.95


Page 102 Of 109
Rate(Say) 1m2 300.74

Ground floor 1m2 300.74

First Floor 1m2 330.82

Second Floor 1m2 363.90

Third Floor 1m2 400.29

Wood

Prepare and apply one coat of preservative (oil type) to structural timber including touching up cut
16.C.01
ends etc. after fixing.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Wood Preservative M-165 Gal 0.605 450.00 272.25

1.02 3" Brush M-020 No 0.1 210.00 21.00

1.03 Painter L-001 Day 0.75 1,200.00 900.00

1.04 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 1,543.25

Rate for 1 Sqr 1,543.25

Rate(Say) 1 Sq 1,543.00

Rate(Say) 1ft2 15.43

Rate(Say) 1m2 166.03

16.C.02 Painting new timber work with two coats wood preservative
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Wood Preservative M-165 Gal 0.5 450.00 225.00

1.02 Brush 2" M-022 No 0.2 165.00 33.00

1.03 Painter L-001 Day 0.5 1,200.00 600.00

Total for 1 Sqr 858.00

Rate for 1 Sqr 858.00

Rate(Say) 1 Sq 858.00

Rate(Say) 1ft2 8.58

Rate(Say) 1m2 92.32

16.C.03 Preparing and painting wood work with primer and 2 coats Enamel paint
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Primer M-075 litre 0.75 180.00 135.00

1.02 Enamel Paint M-044 litre 2.5 400.00 354.00

1.03 Brush 2" M-022 No 0.1 60.00 165.00

1.04 Sand Papers M-114 No 2 3.50 7.00


Page 103 Of 109
1.05 Painter L-001 Day 1.5 1,200.00 1,800.00

1.06 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 2,811.00

Rate for 1 Sqr 2,811.00

Rate(Say) 1 Sq 2,810.00

Rate(Say) 1ft2 28.10

Rate(Say) 1m2 302.36

16.C.04 Varnishing two coats with copal varnish after sandpapering


Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Varnish M-154 litre 1.8 355.00 639.00

1.02 3" Brush M-020 No 0.33 210.00 70.00

1.03 Painter L-001 Day 0.5 1,200.00 600.00

1.04 U / SK Labourer L-007 Day 0.5 700.00 350.00

Total for 1 Sqr 1,659.00

Rate for 1 Sqr 1,659.00

Rate(Say) 1 Sq 1,660.00

Rate(Say) 1ft2 16.60

Rate(Say) 1m2 178.62

16.C.05 Wax polishing to timber in panals & floors


Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Wax Polish M-158 Lbs 0.75 150.00 112.50

1.02 Sand Papers M-114 Sheet 6 3.50 21.00

1.03 Floor Brush M-049 No 0.1 210.00 21.00

1.04 Flannel Cloth M-047 Yards 0.5 70.00 35.00

1.05 U / SK Labourer L-007 Day 0.375 700.00 262.50

Total for 1 Sqr 452.00

Rate for 1 Sqr 452.00

Rate(Say) 1 Sq 450.00

Rate(Say) 1ft2 4.50

Rate(Say) 1m2 48.42

Steel

16.D.01 Prepare surface of steel trusses and apply two coats of anticorrosive primer.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
Page 104 Of 109
1.01 Anti Corrosive Primer M-002 litre 2.25 245.00 551.25

1.02 Mineral Turpentine or Thinner M-069 litre 0.15 80.00 12.00

1.03 Wire Brush M-160 No 1 65.00 65.00

1.04 Brush 2" M-022 No 0.125 165.00 20.63

1.05 Painter L-001 Day 1.5 1,200.00 1,800.00

1.06 U / SK Labourer L-007 Day 1.5 700.00 1,050.00

Total for 1 Sqr 3,498.88

Rate for 1 Sqr 3,498.88

Rate(Say) 1 Sq 3,500.00

Rate(Say) 1ft2 35.00

Rate(Say) 1m2 376.60

Apply one coat of anti-Corrosive primer and two coat enamel paint on already shop primed and
16.D.02
erected steel roof truss.
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Anti Corrosive Primer M-002 litre 0.2 245.00 49.00

1.02 Enamel Paint M-044 litre 1.33 354.00 470.82

1.03 Mineral Turpentine or Thinner M-069 litre 0.2 80.00 16.00

1.04 Brush 2" M-022 No 0.2 165.00 165.00

1.05 Painter L-001 Day 2.5 1,200.00 687.50

1.06 U / SK Labourer L-007 Day 1 700.00 200.00

1.07 Allow 3% of Items (1.05, 1.06 ) for Scaffolding - - - - 26.63

Total for 1 Sqr 1,614.95

Rate for 1 Sqr 1,614.95

Rate(Say) 1 Sq 1,610.00

Rate(Say) 1ft2 16.10

Rate(Say) 1m2 173.24

16.D.03 Prepare and apply two coats primer and finishing soat of enamel paint to mild steel (angle/flat) gate.

Analysis for 50 Sq.ft


No Item Description Item Ref Unit Quantity Rate Amount
1.01 Anti Corrosive Primer M-002 litre 1.5 245.00 367.50

1.02 Enamel Paint M-044 litre 0.67 354.00 237.18

1.03 Mineral Turpentine or Thinner M-069 litre 0.2 80.00 16.00

1.04 Wire Brush M-160 No 0.5 65.00 32.50

1.05 Brush 2" M-022 No 0.2 165.00 33.00

1.06 Painter L-001 Day 0.5 1,200.00 600.00

1.07 U / SK Labourer L-007 Day 0.75 700.00 525.00


Page 105 Of 109
Total for 50 Sq.ft 1,811.18

Rate for 1 Sq.ft 36.22

Rate(Say) 1 Sq. ft 40.00

Rate(Say) 1ft2 40.00

Rate(Say) 1m2 430.40

16.D.04 Painting steel in new work with 2 coats of anti-corrosive paint


Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
1.01 Anti Corrosive Primer M-002 litre 0.667 245.00 163.42

1.02 Brush 2" M-022 No 0.2 165.00 33.00

1.03 Painter L-001 Day 1.5 1,200.00 1,800.00

Total for 1 Sqr 1,996.42

Rate for 1 Sqr 1,996.42

Rate(Say) 1 Sqr 2,000.00

Rate(Say) 1ft2 20.00

Rate(Say) 1m2 215.20


Page 106 Of 109
Page 107 Of 109
Page 108 Of 109
Page 109 Of 109

You might also like