You are on page 1of 18

Page 1

Page 2

Construction case tracker—2015

The Construction case tracker 2015 is a list of key decisions in 2015 relevant to construction lawyers. It
covers and collates cases from 1 June 2015 (in reverse chronological order).
Public procurement cases of particular relevance to construction lawyers are included in this tracker. For
public procurement cases more generally, see: UK public procurement case tracker and EU public
procurement case tracker.
To keep up-to-date with the status of cases on appeal, see: Construction future developments tracker—
Appeal cases.
See also:

1  Construction case tracker—2017


2  Construction case tracker—2016

December 2015
Case Judgment date Key facts
Fulton Shipping Inc of Panama v 21 December 2015 Repudiation/damages: The Court
Globalia Business Travel SAU of Appeal, allowed an appeal
(formerly Travelplan SAU) of regarding the measure of damages
Spain to be assessed following the ship
[2015] EWCA Civ 1299 charterers' repudiatory breach of
contract. The court held that if a
claimant adopted by way of
mitigation, a measure which arose
out of the consequences of the
breach and was in the ordinary
course of business and such
measure benefited the claimant,
that benefit was normally to be
brought into account in assessing
the claimant's loss unless the
measure was wholly independent
of the relationship of the claimant
and defendant. See News Analysis:
Court of Appeal—reduction in
damages where claimant benefits
in mitigating loss (Fulton Shipping v
Globalia).
C&S Associates UK Ltd v 21 December 2015 Repudiation: The Commercial
Enterprise Insurance Company Court gave judgment on seven
plc preliminary issues concerning the
[2015] EWHC 3757 (Comm) termination of a contract, pursuant
to which the claimant had provided
claims handling services to the
defendant insurance company. The
preliminary issues concerned,
among other things, repudiation
Page 3

and variation of the contract. See


News Analyses: When does the
cumulative effect of breaches
amount to repudiation? (C&S
Associates v Enterprise Insurance)
and Tactical strategy leads to
irrecoverable costs (C&S
Associates v Enterprise Insurance
Company).
RMP Construction Services Ltd v 21 December 2015 Adjudication enforcement: The
Chalcroft Ltd TCC held that although the
[2015] EWHC 3737 (TCC) adjudicator decided that he had
jurisdiction under one contract,
when actually he had jurisdiction
under a different contract, this did
not stop the decision being
enforced. This was so even when
the choice of contract would have
led to a different factual outcome.
See News Analysis: Adjudication
enforcement—wrong conclusion
under the wrong contract (RMP
Construction Service v Chalcroft).
Counted4 Community Interest 18 December 2015 Public procurement/interim
Company v Sunderland City order: The TCC refused an
Council application under the Public
[2015] EWHC 3898 (TCC) Contracts Regulations 2015, (PCR
2015) SI 2015/102, reg 96(1) of for
an interim order to lift the automatic
suspension of a contract awarded
following a procurement process
which is subject to a challenge by
an unsuccessful bidder. Although
this case essentially turns on its
facts, construction lawyers should
note this application of the
principles set out in American
Cyanamid to PCR 2015, SI
2015/102, reg 96. See News
Analysis: In brief—Lifting of
automatic suspension of contract
refused (Counted4 Community
Interest v Sunderland City Council).
Fahstone Limited v Biesse Group 18 December 2015 Adjudication enforcement: The
UK Limited TCC refused to grant summary
[2015] EWHC 3650 (TCC) judgment to enforce an
adjudicator’s decision. It held that
there was a triable issue as to
whether a structure formed part of
land and so fell within the definition
of a ‘construction operation’ under
section 105 of Housing Grants,
Construction and Regeneration Act
1996 (HGCRA 1996). See News
Analysis: Adjudication
Page 4

—'construction operations' and the


impact of hire purchase
agreements (Fahstone v Biesse
Group UK).
Bibby Factors Northwest Limited v 17 December 2015 Equitable set-off/debtor's cross-
HFD Limited and another claim: The Court of Appeal held
[2015] EWCA Civ 1908 that where the factor (funder) had
failed to stipulate with the supplier
that there should be no rebate and
had not requested the debtor to
advise of any rebate, there was no
obligation on the debtor to inform it
as to any such pre-existing
contractual arrangements
concerning the debt. See News
Analysis: Court of Appeal permits
rebate cross-claim by way of
equitable set off in debt-factoring
(Bibby Factors v HFD Limited).
London Borough of Bromley v 10 December 2015 Disclosure: The TCC dismissed
Heckel two applications made by the
[2015] EWHC 3606 (TCC) claimant in relation to defects in a
construction project. The court held
that the application for disclosure of
documents was hopeless, and
there was no justification for
allowing its application to extend
time for service of the particulars of
claim. See News Analysis: Practical
considerations when making
applications (London Borough of
Bromley v Heckel).
Persimmon Homes Ltd v Ove 8 December 2015 Contract interpretation/exclusion
Arup and Partners Ltd & another clauses: The TCC ruled on
[2015] EWHC 3573 (TCC) preliminary issues in relation to the
discovery of asbestos
contamination on a development
site. These related to the key
agreements between the parties,
and an exclusion clause which
related to any claim in relation to
asbestos. See News Analysis: In
brief—interpreting parties'
intentions and exclusion of liability
(Persimmon Homes v Arup).
Marks and Spencer plc v BNP 2 December 2015 Implied terms: The Supreme
Paribas Services Trust Company Court decided that a term that the
(Jersey) Limited & another rent be repaid to the tenant could
[2015] UKSC 72 not be implied into four leases. It
confirmed there are two types of
contractual implied term: (i) those
implied into a particular contract, in
the light of the express terms,
commercial common sense, and
the facts known to both parties at
Page 5

the time the contract was made;


and (ii) implied by the law unless
such a term is expressly excluded
(eg statute or common law). See
News Analysis: Supreme Court
dismisses Marks and Spencer's
appeal for repayment of overpaid
rent following lease break.
MJ Harding trading as MJ Harding 1 December 2015 Adjudication: The Court of Appeal
Contractors v Paice & another held (dismissing the contractor’s
[2015] EWCA Civ 1231 appeal) that where a party fails to
issue a valid pay less notice and
loses an adjudication on that basis,
it can start a fresh adjudication on
the question of valuation. See
News Analysis: Court of Appeal
confirm ability to adjudicate on
valuation despite earlier
adjudications (Harding v Paice).
Wattret & another v Thomas 1 December 2015 Expert evidence: The TCC
Sands Consulting Ltd allowed the defendant’s application
[2015] EWHC 3455 (TCC) to adduce expert evidence in a
professional negligence case
regarding chartered quantity
surveyors advising on construction
disputes. See News Analysis:
Adducing expert evidence in a
professional negligence claim
(Wattret v Thomas Sands
Consulting Limited).

November 2015
Case Judgment date Key facts
Severfield (UK) Ltd v Duro 24 November 2015 Application of
Felguera UK Ltd HGCRA 1996/Construction
[2015] EWHC 3352 (TCC) operations: The TCC refused a
summary judgment application
relating to a hybrid contract
(construction operations and
excluded operations under HGCRA
1996, s 105. The claimant could
not rely on a previous lack of a pay
less notice where the sum now
claimed was not identified in the
original payment application. See
News Analysis: Claiming payment
in hybrid contracts for construction
operations and excluded
operations (Severfield v Duro).
Mi-Space (UK) Ltd v Bridgwater 20 November 2015 Adjudication enforcement: The
Civil Engineering Ltd TCC refused to enforce an
[2015] EWHC 3360 (TCC) adjudicator’s decision, holding that
an agreement reached by email,
Page 6

settling the claim, made prior to the


adjudication meant that the
decision had no effect. See News
Analysis: In brief—Settlement
reached by email exchange (Mi-
Space v BCE).
Seeney & another v Gleeson 16 November 2015 Agreement of variations: The
Developments Ltd and another TCC granted summary judgment
[2015] EWHC 3244 (TCC) on part of the claimant’s claim
holding that a binding agreement
had been made by email as to the
total value of additions/variations
payable by the claimants. See
News Analysis: In brief—Binding
agreement on variations (Seeney v
Gleeson).
Van Oord UK Ltd & another v 12 November 2015 Ground conditions/obtaining
Allseas UK Ltd permissions: The TCC considered
[2015] EWHC 3074 (TCC) whether the contractor on an
energy project should have
foreseen the ground conditions that
it encountered and the employer's
liability where it failed to procure
permission for the contractor's
temporary works and delayed in
obtaining permission relating to the
contract works. See News Analysis:
In brief—Ground conditions and
obtaining permissions (Van Oord v
Allseas).
The TCC considered Part 36 offers
and gave an order for costs in a
separate hearing ([2015] EWHC
3385 (TCC)). See News Analysis:
When is a Part 36 offer on a
counterclaim not a claimant's Part
36 offer for CPR 36.17 costs
consequences? (Van Oord UK v
Allseas UK).
Cavendish Square Holding BV v 4 November 2015 Penalty clauses: The Supreme
Talal El Makdessi Court reviewed the development of
ParkingEye Limited v Beavis the law of penalties in two
[2015] UKSC 67 associated cases, and clarified a
broader test in assessing whether a
clause is an unenforceable penalty
(rather than the traditional
dichotomy between a penalty and a
genuine pre-estimate of the
innocent party’s loss). The
questions to be asked under the
new test are: (i) whether the
penalty rule is engaged at all, (ii)
whether there is a legitimate
interest served and protected by
the clause, and (iii) whether the
Page 7

provision purporting to serve that


interest is out of proportion (by
being extravagant, exorbitant or
unconscionable)? If the answer to
all of these questions is 'yes', then
the clause is likely to be an
unenforceable penalty. See News
Analysis: ParkingEye and El
Makdessi—Supreme Court clarifies
penalty rule.
Chliaifchtein v Jessop 2 November 2015 Transferring to the TCC: The
[2015] EWHC 3167 (TCC) TCC refused to transfer a claim
from the Central London County
Court to the High Court,
emphasising the guidance in West
Country [2012] EWHC 307 (TCC).

October 2015
Case Judgment date Key facts
Harlequin Property (SVG) Ltd and 29 October 2015 ATE Insurance: The TCC
another v Wilkins Kennedy (a dismissed an application by the
Firm) claimants to vary an order for
[2015] EWHC 3050 (TCC) security for costs to take account of
the claimants' increased
disbursements—holding that it had
no power to do so where the
parties had amended an after-the-
event (ATE) policy offered by the
claimants as security following an
earlier judgment. The court also
ordered inspection of documents
previously withheld on public
interest and confidentiality grounds.
See News Analysis: Court
considers varying security for costs
by ATE and withholding confidential
documents from inspection
(Harlequin Property v Wilkins
Kennedy).
GBM Minerals Engineering v GB 28 October 2015 Costs/Amendment to pleadings:
Minerals Holdings (No. 2) The TCC held that each party
[2015] EWHC 3091 (TCC) would have to bear its own costs of
the hearing, issuing a warning to
parties who engage in persistent
and ‘opportunistic litigation’ that
they may find the court decides not
to award costs. See News Analysis:
Costs warning to ‘opportunistic
litigants’ (GBM Minerals
Engineering Consultants v GB
Minerals Holding).
Page 8

adjudicator: The TCC refused to


order delivery up, where an
adjudicator had declared that ICI
was entitled to documents but
made no order for delivery up. See
News Analysis: Party ‘entitled’ to
documents, but no order for
delivery up, in TCC adjudication
enforcement proceedings (ICI v
Merit Merrell).
Amey Birmingham Highways v 22 October 2015 Drafting guidance: The TCC
Birmingham City Council (No 2) provided some guidance on the
[2015] EWHC 2994 (TCC) drafting of statements of agreed
facts, whose purpose was to
reduce the weight of evidence and
documentation provided to the
court. See News Analysis: TCC
gives guidance on producing
statements of agreed facts (Amey
Birmingham Highways v
Birmingham CC).
The Dorchester Group Limited v 21 October 2015 Admissions made after
Kier Construction Limited commencement of proceedings:
[2015] EWHC 3051 (TCC) The TCC declined to give judgment
in favour of the claimant on the
basis of an open offer made by the
defendant which the claimant
argued was a formal admission
pursuant to CPR 14.1. See News
Analysis: Admissions made after
commencement of proceedings
(The Dorchester Group Limited v
Kier Construction Limited).
Science and Technology Facilities 21 October 2015 Adjudication
Council v MW High Tech Projects enforcement/jurisdiction of
[2015] EWHC 2889 (TCC) adjudicator: The TCC enforced an
adjudication decision, dismissing
arguments that the GC/Works/1
standard form of contract with
Amendment 1 (2000) was non-
compliant with the HGCRA 1996.
See News Analysis: TCC rejects
defendant ‘scrabbling around’ to
avoid adjudication enforcement
(Science and Technology Facilities
Council v MW High Tech Projects).
GBM Minerals Engineering v GB 21 October 2015 Amendments to pleadings: The
Minerals Holdings TCC allowed applications from both
[2015] EWHC 2954 (TCC) parties to amend their pleadings at
a very late stage, causing the trial
date to be vacated. See News
Analysis: In brief—Late
amendments to pleadings allowed
(GBM Minerals Engineering v GB
Minerals Holdings).
Page 9

William Clark Partnership Limited 16 October 2015 Particularisation of losses: Claim


v Dock St PCT Limited for damages for professional
[2015] EWHC 2923 (TCC) negligence. TCC considered law
relating to abatement and global
claims and found inadequate
particularisation of losses in
claimant's case. See News
Analysis: In brief—Inadequate
particularisation of losses (William
Clark Partnership Limited v Dock St
PCT Limited).
Bloomberg LP v Sandberg (a firm) 16 October 2015 Contribution claim: An application
[2015] EWHC 2858 (TCC) to strike out Part 20 proceedings,
or to obtain summary judgment,
was dismissed by the TCC where it
was argued that a limitation clause
in a collateral warranty prevented
the claim for contribution being
made pursuant to the Civil Liability
(Contribution) Act 1978 (CL(C)A
1978). See News Analysis: In brief
—Part 20 claim permitted under
warranty (Bloomberg v Sandberg).
Husband and Brown v Mitch 16 October 2015 Definition of 'construction
Developments contract': The TCC refused to
[2015] EWHC 2900 (TCC) allow recovery of adjudication costs
on the basis that the agreement in
question was not a construction
contract for the purposes of the
application of the HGCRA 1996 or
the Scheme for Construction
Contracts (England and Wales)
Regulations 1998, SI 1998/649
under which the adjudication had
taken place. See News Analysis:
Recoverability of adjudication costs
(Husband and Brown v Mitch
Developments).
Wilson & Sharp Investments Ltd v 13 October 2015 Winding-up/interim payments:
Harbour View Developments Ltd The Court of Appeal confirmed that
[2015] EWCA Civ 1030 (i) the JCT provisions comply with s
111(10), (ii) the absence of a pay
less notice does not prevent an
employer from later arguing that
the valuation in an interim
certificate was wrong, and (iii) a
winding-up petition should not be
used to enforce an interim payment
obligation, where the employer
challenges the valuation or has a
genuine cross claim. See News
Analysis: Enforcing interim
payments—winding-up or TCC?
Lloyds Bank v McBains Cooper 2 October 2015 Contributory negligence: The
Consulting TCC considered allegations of
Page 10

[2015] EWHC 2372 (TCC) negligence against a project


monitor, when it was clear that the
bank should never have agreed the
loan in the first place. See News
Analysis: In brief—Negligent
project monitoring (Lloyds Bank v
McBains Cooper).

September 2015
Case Judgment date Key facts
Openview Security Solutions v 28 September 2015 Suspension under Public
London Borough of Merton Contract Regs: The TCC
Council considered lifting a suspension to
[2015] EWHC 2694 (TCC) the contracting process under the
Public Contract Regs, applying the
American Cyanamid principles, and
considered how the public interest
should be taken into account. See
News Analysis: In brief—Lifting a
suspension under the Public
Contract Regulations (Openview v
Merton).
Wycombe Demolition v Topevent Hearing 31 July 2015; Judgment Adjudicator's jurisdiction: The
[2015] EWHC 2692 (TCC) published 28 September TCC enforced an adjudicator’s
decision, dismissing arguments
that multiple disputes had been
referred and that there had been a
breach of natural justice. See News
Analysis: Adjudication enforced,
with sympathy for the adjudicator’s
position (Wycombe Demolition v
Topevent).
Purton (t/a Richwood Interiors) v 16 September 2015 Contract formation/adjudicator's
Kilker Projects jurisdiction: The TCC considered
[2015] EWHC 2624 (TCC) whether a contract had been
formed and examined whether the
court had to satisfied that the
contract was the same as
contended by the claimant. See
News Analysis: In brief—
adjudicator's jurisdiction and an
uncertain contract (Purton v Kilker
Projects).

August 2015
Case Judgment date Key facts
Henia Investments v Beck 14 August 2015 JCT payment/liquidated
Interiors damages: The TCC provided
[2015] EWHC 2433 (TCC) helpful judicial guidance on the
interpretation of the payment
Page 11

provisions in the JCT Standard


Building Contract 2011 (SBC), as
well as the operation of liquidated
damages where the contract
administrator is yet to decide on a
claim for an extension of time. See
News Analysis: In brief—payment,
pay less notices and liquidated
damages under JCT contracts
(Henia Investments v Beck
Interiors).
NH International (Caribbean) v 6 August 2015 Arbitration/FIDIC Red Book: The
National Insurance Property Privy Council allowed two appeals
Development Company from the Trinidad & Tobago Court
[2015] UKPC 37 of Appeal regarding two interim (or
partial) arbitral awards. The dispute
arose out of an agreement
expressed to be subject to the
FIDIC Red Book for the
construction of a hospital in
Tobago. The Privy Council took a
firm stance on respecting party
autonomy and tribunal findings of
fact and considered the application
of clause 2.5 of the Red Book to
set-off and counterclaims. See
News Analysis: Privy Council—
courts should respect party
autonomy and tribunal findings of
fact (NH International (Caribbean) v
National Insurance Property
Development Company).

July 2015
Case Judgment date Key facts
Caterpillar Motoren GmbH & Co 31 July 2015 On-demand bonds: The
K.G. v Mutual Benefits Assurance Commercial Court held, based on
Company the language used by the parties
[2015] EWHC 2304 (Comm) and Paget's presumption, that two
advance payment bonds and two
performance bonds granted for a
project in Liberia were on-demand.
See News Analysis: In brief—
bonds held to be on-demand.
Brit UW v F&B Trenchless 31 July 2015 Insurance: The Commercial Court
Solutions held that an insurer had validly
[2015] EWHC 2237 (Comm) avoided an insurance policy where
a tunnelling sub-contractor failed to
disclose details of settlement of the
ground when settlement caused a
train to derail. See News Analysis:
In brief—failure to disclose facts
allowed insurer to avoid
Page 12

contractor's liability policy.


Cofely Solelec and Others v 28 July 2015 Public
Parliament procurement/abandonment: This
Case T-419/15 (not available in case concerned a challenge by a
English) tenderer against a decision by the
European Parliament to abandon a
public contract award following the
evaluation stage. The applicants
unsuccessfully argued that the
Parliament had failed to state
reasons for its decision, and
committed a manifest error in
arriving at its decision. See News
Analysis: In brief: General Court
reaffirms authorities’ power to
abandon public contract awards
(Cofely Solelec and Others v
Parliament).
Woods Building Services v Milton 14 July 2015 Procurement: Procurement of
Keynes Council framework for asbestos removal.
[2015] EWHC 2011 (TCC) and Claims made regarding unfair
[2015] EWHC 2172 (TCC) conduct of procurement process.
(Remedies) Judge re-evaluated questions in
quality section of the tender. TCC
held that there were manifest errors
in the tender evaluation process,
and instances the duties of
transparency and equality of
treatment were breached. TCC
refused to order Council to award
the contract to the contractor and
held damages the appropriate
remedy. See News Analyses: In
brief—Manifest errors in
procurement exercise (Woods v
Milton Keynes) and Remedies in
Woods v Milton Keynes.
SSE Generation v Hochtief 14 July 2015 Insurance: Scottish case—Outer
Solutions AG and Hochtief (UK) House, Court of Session held that
Constructions CAR insurance policy did not
[2015] CSOH 92 displace parties' liability to each
other under NEC contract. SSE
therefore entitled to bring an action
against Hochtief for damage to
tunnel. See News Analysis: CAR
policy does not supplant parties’
liability under NEC contracts.
Portsmouth City Council v Ensign 14 July 2015 PFI/Deductions/Good faith:
Highways Declarations sought from the court
[2015] EWHC 1969 (TCC) regarding performance of certain
obligations under a PFI
contract. TCC considered whether,
in relation to deductions, a
‘Maximum Event Value’ indicated a
range or a fixed figure. The TCC
Page 13

held that a maximum value


indicated the upper limit of a range
of possible values. Also, the court
found that a duty to act in good
faith set out in a particular clause of
the contract did not apply to the
whole contract. See News Analysis:
In brief—Deductions under a PFI
contract and good faith
(Portsmouth CC v Ensign).
A later hearing was heard on costs:
[2015] EWHC 3320 (TCC).
Amec Foster Wheeler Group v Hearing 29 June 2015; Judgment Production of documents in
Morgan Sindall Professional published 14 July 2015 arbitration: The TCC held that the
Services defendants were obliged to deliver
[2015] EWHC 2012 (TCC) documents to AMEC relating to two
arbitrations, despite any obligation
of confidentiality to the other party
to the arbitrations. See News
Analysis: In brief—TCC orders
production of documents (AMEC v
Morgan Sindall & Others).
Obrascon Huarte v AG for 9 July 2015 Termination/Design: The Court of
Gibraltar Appeal considered Obrascon's
[2015] EWCA Civ 712 appeal against the TCC's decision
that it could have foreseen the
amount of contamination it
encountered in undertaking tunnel
works at Gibraltar airport and that
the employer’s termination of the
FIDIC contract was lawful. Court of
Appeal upheld the TCC's decision
and dismissed Obrascon's appeal.
See News Analysis: In brief—
Obrascon Huarte v AG of Gibraltar
—Obrascon's appeal dismissed.
Iliffe & another v Feltham 9 July 2015 Appeal against summary
Construction judgment: The Court of Appeal
[2015] EWCA Civ 715 allowed the appeal by the main
contractor against summary
judgment granted in favour of the
home owners whose house was
destroyed by fire. Although the
Iliffes had a good chance of
success, a full trial will be held as
to quantum and liability of the other
parties joined in the proceedings. It
was therefore inappropriate to give
summary judgment when similar
issues would be later determined in
full proceedings between the other
parties—this therefore constituted a
'compelling reason' not to enter
summary judgment within the
meaning of CPR 24.2(b). See
Page 14

News Analysis: In brief—Appeal


allowed against summary judgment
(Iliffe v Feltham Construction).
Gotch v Enelco 3 July 2015 Adjudication—entitlement to
[2015] EWHC 1802 (TCC) refer: TCC refused to consider an
application for a declaration relating
to the parties’ entitlement to refer a
dispute to adjudication. As neither
party had any current intention to
refer a dispute to adjudication, the
application served no useful
purpose. See News Analysis:
Adjudication declaration refused it
would serve no useful purpose
(Gotch v Enelco).
Bunge SA v Nidera BV 1 July 2015 Damages: Measurement of
[2015] UKSC 43 damages for anticipatory breach
(renunciation). UKSC unanimously
concluded that a default damages
clause, construed on its precise
terms, did not provide a complete
code for assessing damages for
the breach. UKSC confirmed the
compensatory principle identified in
The Golden Victory and that this
'overriding compensatory principle'
was not limited to instalment
contracts as had perhaps
previously been suggested. See
News Analysis: UKSC considers
damages clauses and anticipatory
breach (renunciation) (Bunge SA v
Nidera BV).

June 2015
Case Judgment date Key facts
Medicure v The Minister for the 29 June 2015 Procurement: Procurement of
Cabinet Office framework for supply of locum
[2015] EWHC 1854 (TCC) doctors. Tender process was
challenged and claims made
regarding operation of the
framework agreement. TCC held
that both tender process and
framework agreement had been
properly and fairly operated. See
News Analysis: In brief—Medicure
Ltd v The Minister for the Cabinet
Office.
Calendonian Modular v Mar City 29 June 2015 Enforcement of adjudication
Developments decision/Payment: Judge
[2015] EWHC 1855 (TCC) considered substantive issue at
enforcement hearing. Question
regarding validity of documents
Page 15

claimed to be application for interim


payment or valid payee's notice.
TCC held documents were not
valid application for interim
payment/valid payee's notice
therefore no sums due under
adjudicator’s decision. See News
Analysis: Incorrect adjudicator’s
decision not enforced (Caledonian
Modular v Mar City).
Severfield UK Ltd v Duro 25 June 2015 Enforcement of adjudication
Felguara UK Ltd decision/construction
[2015] EWHC 2975 (TCC) operations: The TCC refused to
enforce an adjudicator’s decision,
where the decision arguably
included operations that were not
‘construction operations’ as defined
by the HGCRA 1996. See News
Analysis: No enforcement of
adjudicator’s decision where it
arguably included excluded
operations (Severfield UK Ltd v
Duro Felguara UK Ltd).
Swynson v Lowick Rose 24 June 2015 Damages/Mitigation: Concerned
[2015] EWCA Civ 629 level of damages recoverable by an
innocent party where its loss was
avoided not as a consequence of
its own attempts to mitigate loss,
but due to the intervention of a third
party. Court of Appeal held
intervention of third party did not go
to reduce the damages recoverable
(appeal dismissed). See News
Analysis: Court of Appeal—
substance triumphs over form in
avoided loss appeal (Swynson v
Lowick Rose).
Martifer UK v Lend Lease 19 June 2015 Contract documents/Programme
Construction (EMEA) for works: Was an information
[2015] CSOH 81 release schedule the programme
for the sub-contract in question and
was it a contract document?
Scottish case (Outer House of the
Court of Session). Held that the
IRS was a sub-contract document
but did not impose an obligation on
the parties to complete the works in
accordance with the programme in
it. See News Analysis: In brief—
information release schedule
programme not binding (Martifer v
Lend Lease).
Page 16

an unfavourable adjudicator's
decision to have the dispute finally
determined and recover money
paid out. Is it the time limit applying
to the original claim, or does a new
period of six years run from the
date of payment? Supreme Court
overturned Court of Appeal
decision. Held that party seeking
repayment of an adjudication
award is entitled to the full limitation
period (from date of payment),
even if a dispute on the underlying
facts would have been time barred.
See News Analysis: Supreme
Court gives one-way decision on
limitation and adjudication (Aspect
Contracts v Higgins).
IMI v Delta Limited 16 June 2015 Part 20/Civil Liability
[2015] EWHC 1676 (Ch) (Contribution) Act 1979:
Court's interpretation of the
operation of CL(C)A 1978, s 1(4)
meant that Part 20 defendant was
precluded from asserting that it was
not liable for a contribution on the
basis that the main claim was time-
barred. See News Analysis: Part 20
defendant precluded in contribution
proceedings from relying on
limitation arguments which could
have been raised in main claim (IMI
v Delta).
Transformers and Rectifiers v 12 June 2015 Costs: Two costs orders made
Needs against the defendant by Edwards-
[2015] EWHC 1687 (TCC) Stuart J following defendant's
unsuccessful attempt to adjourn a
preliminary issues trial. Further
costs order against defendant later
made by Coulson J, also in relation
to the adjournment. Issue was
whether Coulson J had jurisdiction
under the CPR to undertake
summary assessment of all three
costs orders or whether
assessment should be undertaken
by same judge that made the costs
orders. TCC held that where a
costs order is made following an
interim application, those costs
may be the subject of summary
assessment at a later date by a
different judge. See News Analysis:
Summary costs assessment—
which judge should undertake the
assessment? (Transformers and
Page 17

Rectifiers v Needs).

You might also like