Professional Documents
Culture Documents
Roger E.
Ferch, P.E.,
is a Vice
President
with The
Herrick
Corporation. tures that housed the aircraft gates were
Patrick M.
Hassett,
S.E., P.E.,
T he architects for the San
Francisco International Terminal
constructed before the new terminal
building. The center truss section spans
the existing ten-lane airport entrance
described their design as a dramatic 860’ road. This roadway had to remain open
has 12 years long “winglike” roof that presents its pro- during construction and the contract was
experience file to cars arriving on the access road very restrictive on activities in the vicini-
as a consul- while soaring 60 to 90’ above the floor of ty. Any total road closure had to be lim-
tant on the a cavernous ticketing hall. Couple this ited to a maximum of five minutes
architectural statement with the high between the hours of midnight and 5:00
fabrication
seismic design requirements of northern AM.
and erection California, and the result was the massive
of major structural steel bid documents for the Below the trusses were two floors of
new terminal. AISC-member Herrick conventional beam and column framing.
structural
Corporation was the successful bidder on The existing airport terminals and park-
steel con- ing structure blocked access from the
the 30,000-ton project and signed the
struction pro- east. New construction was already in
contract with the airport in May of 1996.
jects and cur- place on both the north and south sides
rently heads The main roof structure, with a total at the beginning of roof construction.
weight of 4,200 tons, included five sets of Therefore, the only access to the site was
up his own consulting engineering
trusses at 40’ centers. Each truss incor- from the west and the steel had to be
firm. This article is based on their porated two 320’ long double cantilever erected from this side.
scheduled presentation at the 2000 one-way sections resting atop spherical
North American Steel Construction bearings and a two-way 180’ long three-
Conference in Las Vegas. chord center section. The tubular truss Erection of Support Trusses
members range from 12 to 20” in diame- Double cantilever trusses support the
ter and with wall thickness from 7/8 to center span three-chord “football”
2”. All joints were complete penetration shaped trusses. The middle sections were
welds. The final erection tolerance was erected first, followed by the outside can-
one inch in any direction. tilever and the inside cantilever trusses.
Nylon Kevlar slings were used to cradle
The project site contributed to the top chord pipe sections at designated
project challenges. The new 2,000,000- pick points rather than welding lifting
sq. ft. facility provides 26 gates for Boeing lugs to the API pipe and having to grind
747 and 777 jumbo aircraft. The struc-