Professional Documents
Culture Documents
Casa sprint tem um resultado que o cliente pode testar, pois ele só descobre o que realmente
quer quando ele tem algo que ele possa usar.
Approaches: abordagens
ROLES
Product owner:
-Responsible for returno n investment (ROI)
-Final arbiter of requirements questions
-Focused more on the what on the how
Scrum Master
-Has no management authority
-Doesn’t have a Project manager role
-Facilitator
-Protege o time de distrações e interrupções
-Facilita o processo
-Ensina as pessoas como usar o SCRUM
-Promove a melhoria das melhores práticas de engenharia
-Força a realização dentro do tempo
-E faz tudo isso sem poder de gerente, apenas com influência.
http://xp123.com/articles/invest-in-good-stories-and-smart-tasks/
Estimation Cards (effort to get a PBI into potentially shippable form): S (Small), M (Medium), L
(Large) and XL (Extra Large).
Propósitos/ Purpose:
-Estimative of effort
-Clarification of requirements
-Decomposition of large PBIs into smaller ones (e.g. epics to user stories).
Product Owner and Development time will agree to Sprint goals (metas) and negotiable which
items from Product Backlog.
Only 60% of the tasks are likely to be identified during the Sprint Planning Meeting.
Part 1: Committing to Product Backlog Items (PBIs). Item que seram feitos no Sprint.
Time Sprint: 30 days, or one calendar month, but one or two weeks is recommended.
Definir todas as tarefas que precisaram ser realizadas para a criação de um incremento
utilizável.
Conseguimos fazer todas essas tarefas dentro do prazo estipulado para o Sprint? Todos devem
estar de acordo.
Principle behind Scrum is Limit Work in Progress (WIP). Humans don´t multitask efficiently. Too
much work in progress actually slows things down.
Sprint forecast
Some Scrum teams who have learned how to define small enough PBIs no longer find tasks
necessary.
A PBI is more about the what than the how. A task is more about the how.
Pair Programming: duas pessoas dividindo uma estação de trabalho, enquanto um programa,
a outra acompanha verificando o código e depois o processo ao inverso.
SideBar: Itens para serem discutidos depois, sem ser no daily scrum.
1 - Product demonstration
4 – Stakeholder feedback
Items that are not done or almost done will be moved in their entirety back to the product
backlog.
The Sprint review meeting is a key inspect and adapt mechanisms in Scrum so we want to
avoid things could interfere with transparency (like applause or praise).
Se o product owner solicitar novas funcionalidades ou qualquer coisa a mais, como um novo
design o scrum master vai adicionar ao product backlog para avaliação futura.
Discordâncias sobre as prioridades ou o que já deveria estar pronto, deve ser resolvido fora da
reunião com o product owner e os outros stakeholders envolvidos.
Feedback from outside stakeholders: the end, after the demonstration and measurement of
which goals were achieved.
4 – Silent Writing
5 – Timeline retrospective
6 – Decisions
http://wiki.c2.com/?TestDrivenDevelopment