Professional Documents
Culture Documents
Management to Project
Formulation
A Survey of Policy and
Strategy for Execution
Sam Padgett
Agenda
The Question
Why Do We Care?
Policy
Common Sense
Terminology
Conclusions
Is it Practical (Feasible)?
If so, Is it Practicable (Benefit > Cost)?
What are the Relevant Considerations or ?
The Question
“Should We Be Doing EVM In Project
Formulation?”
What Do Typical Project-centric Entities (Agencies
And Professional Associations) Require In Terms
Of Policy? (Did Not Survey Individual Companies)
What Structures Can Serve As A Viable Framework
For Formulation-phase Baselines?
What Considerations Or Attributes Make A
Formulation Effort Amenable To EVM?
What Do We Mean By “Formulation”?
QuickTime™ and a
TIFF (LZW) decompressor
are needed to see this picture.
What Do We Mean By “Formulation”?
Formulation Implementation
QuickTime™ and a
TIFF (LZW) decompressor
are needed to see this picture.
Policy: NASA
Program And Project Management
Requirements (NPR 7120.5D)
Requires Application Of EVM Only To
“Implementation Phase” Project Work
Not Required Prior To Key Decision Point C
(Roughly PDR) Or For Operations
Policy: No Mention
EIA-748-B
The Federal Acquisition Certification For Program And
Project Managers (FAC-P/PM) April 25, 2007
Dod - Integrating-se-acquisition-
contracts_guide_121106.Doc
Understanding And Leveraging A Supplier’s CMMI ®
Efforts: A Guidebook For Acquirers CMMI Guidebook
For Acquirers Team March 2007 TECHNICAL
REPORT CMU/SEI-2007-TR-004 ESC-TR-2007-004
Summary of Policy Regarding EVM in
Formulation
OMB - Yes, If It’s DME
Implementers
Somewhat Ambiguous in Writings
Usually Neither Discourages Nor Requires
May Well Differ From Facts On The Ground
Why Do We Care?
The Formulation of Large Projects May
Cost Much
Take Several Years
Have Complex Internal Interdependencies
If the Completion Criteria for Formulation are Clear,
Progress Assessment May Not Be Optional
A Viable Preliminary Design
A Complete Risk Register
A Date Certain
If We ’ve Really Thought Hard About It
We’ve
And Decided We Really Need EVM …
EVM…
What Do We Use For A
WBS?
In Implementation Phase It’s Straightforward;
Product-oriented Prime Mission Equipment Branch
Common Elements For Each PME Node
But In Formulation Phase It May Not Be So
Straightforward
There May Be Multiple Competing Architectures
Until The Winning Concept Is Chosen
The Prime Mission Equipment Branch Is Only
Specified As The Culmination Of Formulation
During Formulation, There May Not Be A Single
PME Tree On Which To “Hang” Common Elements
What Course To Choose?
The Simplest Approach
Assume Formulation Effort Is All Part Of An Undifferentiated
PM&SE Node At The Project Level
Not Well Suited To Quantifying Progress
Another Approach
Create A WBS Peculiar To The Task At Hand
Based On The Systems Engineering Products That Dominate
Formulation
Provides For The Application Of Technical Processes To
Concrete Products
But What About Earlier Work?
•Briefings
•Final Report Defense Acquisition Guidebook, 3.3.1
Completing Work Definitions
Technical Processes Should Be Technical Processes
Applied To Each End Product In Requirements
The WBS Hierarchy Development
Those Processes Require That Logical Analysis
Tasks Be Performed Specifically Design Solution
For Each WBS Element Implementation
Perform Requirements Allocation Integration
Prepare Subsystem Spec Verification
Perform Component Testing Validation
Issue Purchase Order Transition
The Process Applied To Each (Defense Acq. Guidebook, 4.2.2)
End Product Element (WBS)
Represents The Work Definition
Candidates For
Formulation-phase Common
Element Definitions
The Draft Acquisition Plan
The Draft Systems Engineering Plan
Others
Will Make Up The Equivalent Of The
Common Elements Task Definitions For
Concept Refinement
In Total,
It’s good practice to “…derive schedule and
cost baselines from normal systems
engineering products.
That will likely improve the quality of the
PMB and
increase acceptance and reduce
reluctance by the systems engineering
community”
Normal systems engineering products can
provide useful structures for assessing
physical progress
If You Decide You Should Do
EVM in Formulation…
What considerations or attributes make it
worthwhile?
What Considerations make it “doable”?
What Considerations Or Attributes
Make Formulation-phase EVM Worth
Considering?
Period Of Performance – ~Authorization To PDR –
More Than One Year?
Hard Date For Pdr (Implementation Authorization)
Complexity
Multiple Business Entities
Multiple Geographic Locations
Unfamiliar Cultures
Multiple Immature Technologies
Visibility To Important Stakeholders
…
What Considerations Make It “Doable”?