Professional Documents
Culture Documents
1 Overview of Forecasting
2 Setups Required for Forecasting
3 Process Flow Using Examples
4 Useful Additional information
5 Q&A
• Preventive Maintenance
– Reduces the probability of failure or degradation of
assets
– Ensures that maintenance work is done on a timely
basis
– The work orders are automatically raised based on
meter readings, run time intervals and calendar days.
• Requirements :
– Activities are created for the work required on an asset. You can
associate a Bill of Materials (BOM) and a routing to the activity.
– Meters are created to allow rules to be created for generating work
orders based on certain readings (e.g a service every 15000 miles).
–Preventive Maintenance Schedules are created for an asset to hold the
rules and criteria for generating the work orders and specify the work
required (activities)
• Business Process :
– Once the PM Schedules are created, the Generate PM Maintenance
Work Orders Concurrent Program is scheduled to run on a regular basis
to create the work orders in a unreleased status.
– One can then use the Maintenance Workbench to view these work
orders and release them using the Implement button or use Mass
Release (the PM Scheduler is launched when using implement).
–Maintenance Workbench allows the following functionality also : You
can generate forecasts and see what work orders are suggested. This is
required for planning purposes. These WOs can then be implemented.
Copyright © 2015 Oracle and/or its affiliates. All rights reserved. | 11
SETUPS
• PM Engine will not look at the work order dates and will not look at the last service readings.
• PM Engine will look at the base meter and base meter reading.
• Let’s look at an example :
• Base Meter Reading =1
Interval = 100 (hence work orders to be suggested at meter readings of 101, 201, 301, 401, 501,601, 701, 801,901,1001 etc)
Usage Rate = 5
Latest Meter Reading = 1000 (hence the work order for 901 is due) .
Latest Meter Reading Date = 10 Oct 2014
• Calculation :
Days Left = Latest Meter Reading – Due Reading /Usage Rate
= 1000 – 901/ 5 = 19.8
WO Suggestion Date = Latest Meter Reading Date + Days Left = 10 Oct 2014 + 19.8 = 29 October 2014
1.Set 'no of past readings' >999999 and 'rate per day' = 1 in meters Form.
2.Uncheck 'Implement from Horizon Start Date' parameter in eAM Parameter window.
3.Now when you run the forecast, then suggestions falling between last service date and
latest meter reading date are forecasted with suggestion date = sysdate.
Number of past readings is a parameter that says how many readings are required in
order to recalculate the usage rate. (how many readings from the past are used in the
formula) If that number of readings is never reached then the usage rate is not
recalculated. The above setup ensures that usage rate always remains at 1 and hence
the meter readings will be used to generate the suggestions.
• You can use a meter rule or a date or you can use BOTH.
• If you use BOTH a date rule and a meter rule, then the system will simply look at whichever rule comes
first.
• However, you can choose Last Due Date in the Scheduling Based On region. In this case, even if rule 1
reaches its due reading, the service is not scheduled until rule 2 has also reached its due reading.
• The following page shows an example date rule which creates a work order for the activity every 90
days.
• The calculation is as follows - last date was 27-Nov-2014 as shown on PM.
Next Date = Actual Start Date + Base Interval*Interval Multiple
Next Date = 27/11/2014 + (1 x 90) = 25 Feb 2015
• Ensure that you have defined accounting periods for the entire horizon
otherwise there will be errors in the log file and correct WOs will not be
suggested.
Overview of Forecasting
Looked at setups required
Look at the process flow using
some examples.
On Twitter:
• @COLLAB_OAUG
• #C15LV