You are on page 1of 2

IED - PCE - 001Rev.

project : Roof Painting


owner : PPA
subject : COST ESTIMATES
DESCRIPTION PRODUCTIVITY Qty
Mobilization/Demob 1.00
Labor 0.14573 md/sq.m. 4.00
Eqpt
Truck 0.05360 hr/sq.m. 8.00
Painting Works 1,623.96
Materials
Lacquer Thinner Premium 50.00000 sq.m./gal. 47.00
1 coat Epoxy Primer 30.00000 sq.m./gal. 140.00
1 coat ac 25.00000 sq.m./gal. 96.00
1 coat topcoat (epoxy enamel) 25.00000 sq.m./gal. 96.00
1 coat Oxide Primer option/ lesser u-cost
1 coat Paint Thinner option/ lesser u-cost
Labor
Painter 0.05894 md/sq.m. 96.00
Removal of Rust& Old Paint 0.03700 md/sq.m. 61.00
Consumables
Brittle Brush or Steel Brush 0.00120 pcs/sq.m. 2.00
Brush Paint #4 0.01101 pcs/sq.m. 18.00
Brush Paint #2 0.02202 pcs/sq.m. 36.00
Brush Cup 3" M10x1.25 0.00340 pcs/sq.m. 6.00
Pad waste Cotton 0.00380 kl/sq.m. 7.00
Roller Brush 0.02020 pcs/sq.m. 33.00
Baby Brush 0.02020 pcs/sq.m. 33.00
JFC
gas respirator 12.00
Machine Time
Compressor with Complete Accs 0.16081 hrs/sq.m.
Angle Grinder 0.05360 hrs/sq.m. 87.05
Safety
Labor 0.03266 md/sq.m. 23.00
JFC
Caution Tape 0.00670 roll/sq.m. 2.00
Blue sheet 2.00
Consumables-PPE's
Hard Hat 0.02010 pcs/sq.m. 12.00
Uniform 0.06700 pcs/sq.m.
Safety Goggles 0.04020 pcs/sq.m.
Gas Test 0.03350 hr/sq.m.
Scaffolding Works
Labor 16.00
Universal Swivel Clamp 45.00
Planks 240.00
Pipe 1½ Ø sch. 40 rentals 35.00

TOTAL PROJECT BARE COST


MARK – UP
SELLING PRICE (VAT INCLUSIVE)
PRICE PER UNIT

Prime bare metal Epoxy Red Oxide Epoxy Primer Gray. Let dry eight (8) hours before recoating. Topcoat with
Consumables for power tools
Power tooling
Scaffolding
PPR
Mar-18
ROOF FRAMING PLAN 1
CANOPY, ROOF BEAM & VERT. TRUSSES
Blue Sheet PAINT in gal.

1 coat topcoat
rolls (2.4m Lacquer Thinner 1 coat Epoxy
ITEM PARTICULARS DESCRIPTION Total Le. qty unit S. Area UNIT 1 coat ac (epoxy REMARKS
x100m) Premium (325) Primer (650)
enamel)

A ROOF FRAMING PLAN-1 m 50.00 30.00 25.00 25.00


Canopy 59.47 sq.m. 1.00 - 1.98 2.38 2.38
1 1.2mm x50mmx100mm C-Purlins Canopy C100mmx50mmx1.2mm ### 10.00 set 52.75 sq.m. 1.06 1.76 2.11 2.11
2 HT Half Truss@Canopy 2L2x2x3mm 7.45 4.00 set 38.04 sq.m. 0.76 1.27 1.52 1.52
3 VT-4 Canopy VT-4 2L2x2x5mm ### 5.00 set 66.71 sq.m. 1.33 2.22 2.67 2.67
4 VT-2 Vertical Truss-2 C-100mm x50mm ### 7.00 set 151.19 sq.m. 3.02 5.04 6.05 6.05
5 VT-1 Vertical Truss-1 C-100mm x50mm ### 6.00 set 309.83 sq.m. 6.20 10.33 12.39 12.39
6 VT-3 Vertical Truss-3 C-100mm x50mm ### 4.00 set 23.17 sq.m. 0.46 0.77 0.93 0.93
7 PRB 12mm Sag Rod PRB 12mm ### 79.00 set 2.98 sq.m. 0.06 0.10 0.12 0.12
8 PRB 16mm Tie Rod PRB 16mm ### 50.07 set 2.52 sq.m. 0.05 0.08 0.10 0.10
9 With Stud Turnbuckle Pcs. Turnbuckle ### ### set 1.08 sq.m. 0.02 0.04 0.04 0.04
-
B ROOF FRAMING PLAN-2
1 Roof Framing 702.21 sq.m. 3.00 14.04 23.41 28.09 28.09
2 1.2mm x50mmx100mm C-Purlins Roof Framing C100mmx50mmx1.2mm ### ### set ### sq.m. 6.89 11.49 13.79 13.79
3 Rafter Roof Framing C-150mm x50mm ### 36.00 set 207.74 sq.m. 4.15 6.92 8.31 8.31
4 VT-4 Vertical Truss-4 2L2x2x5mm ### 8.00 set 360.32 sq.m. 7.21 12.01 14.41 14.41
5 PRB 16mm Tie Rod PRB 16mm ### 56.00 set 24.23 sq.m. 0.48 0.81 0.97 0.97
6 PRB 12mm Sag Rod PRB 12mm ### 241.00 set 9.06 sq.m. 0.18 0.30 0.36 0.36
7 With Stud Turnbuckle Pcs. Turnbuckle ### 112.00 set 3.36 sq.m. 0.07 0.11 0.13 0.13
8 Inner Gutter Framing Welded to VT-1 L25x25mm ### 5.00 set 26.30 sq.m. 0.53 0.88 1.05 1.05

1,623.96 sq.m. 47.00 80.00 96.00 96.00