You are on page 1of 17

Project: Construction of 2-Storey Commercial Building Company: PBT Construction and Trading

Location: Brgy. Bantug, Science City of Muñoz, N.E. Manager: Engr. Paulino B. Tomas Jr.
Owner: Mrs. Amor A. Manalili
Apprentice: Fernando D. Gagelonia Jr.
Charles Kevin G. Valdez
Marverick Paolo W. Yarcia

WEEK 7
March 12-16, 2018

EQUIPMENT PERSON/S INVOLVED


DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The masons are


plastering the left
outer wall.
Engr. Marvin Quilanlan 75% finished
Plastering of outer Field Engineer (whole day)
left side wall. 4 span(4x1.6m)
12-Mar-18 Rebar works on Portal lift Wilson Baltazar 1-mason/span
(Monday) staircase. One-bagger concrete Foreman
Formworks for mixer
beams.(3rd floor) Laborers
Formworks for Steelman The laborers are
staircase. Mason fixing and tying the
Carpenters rebars on staircase.
EQUIPMENT PERSON/S INVOLVED
DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

Foreman Wilson is
levelling the forms
on staircase.

Engr. Marvin Quilanlan


Plastering of outer Field Engineer
left side wall.
12-Mar-18 Rebar works on Portal lift Wilson Baltazar
(Monday) staircase. One-bagger concrete Foreman
Formworks for mixer
beams.(3rd floor) Laborers
Formworks for Steelman
staircase. Mason
Carpenters The laborers are
installing forms on
beams.
EQUIPMENT PERSON/S INVOLVED
DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The foreman is

removing forms on

staircase.
Stripping of forms
on staircase. Engr. Marvin Quilanlan
Plastering of outer Field Engineer
left side wall.
14-Mar-18 Preparation for Portal lift Wilson Baltazar
(Wednesday) plastering of One-bagger concrete Foreman The masons are
columns. 1st floor mixer plastering the left
Formworks on Welding Machine Laborers outer wall (lower
beams. Steelman row of wall).
Laying of Mason
steeldecks. Welder
Carpenter

The masons are


leveling the plaster.
EQUIPMENT PERSON/S INVOLVED
DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The laborers are


installing forms on
corner of beam.

Stripping of forms
on staircase. Engr. Marvin Quilanlan
Plastering of outer Field Engineer
left side wall.
14-Mar-18 Preparation for Portal lift Wilson Baltazar
(Wednesday) plastering of One-bagger concrete Foreman The mason is
columns. 1st floor mixer preparing the
Formworks on Welding Machine Laborers columns for
beams. Steelman plastering.
Laying of Mason (15mins/col)
steeldecks. Welder (.15+.4+.15)*4.15
Carpenter

The welder and


helper are installing
steeldecks.
EQUIPMENT PERSON/S INVOLVED
DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The laborers are


installing steel
decks for 3rd floor.

Laying of
steeldecks. Engr. Marvin Quilanlan
Scaffoldings for Field Engineer
steeldecks.
15-Mar-18 Formworks on Portal lift Wilson Baltazar
(Thursday) beams. One-bagger concrete Foreman The masons are
Plastering of outer mixer plastering the
left wall. Welding machine Laborers firewall.
Preparation for Carpenter
plastering of Mason
columns. 1st floor Welder

The mason is
preparing the
columns on 1st
floor for plastering.
EQUIPMENT PERSON/S INVOLVED
DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The carpenter is
fixing the forms on
beam corner.

Laying of
steeldecks. Engr. Marvin Quilanlan
Scaffoldings for Field Engineer
steeldecks.
15-Mar-18 Formworks on Portal lift Wilson Baltazar
(Thursday) beams. One-bagger concrete Foreman
Plastering of outer mixer
left wall. Welding machine Laborers
Preparation for Carpenter
plastering of Mason
columns. 1st floor Welder The laborers are
installing
scaffoldings for
steeldecks.
DATE/DAY ACTIVITY EQUIPMENT PERSON/S INVOLVED OBSERVATION DOCUMENTATION

The laborer is
making and laying
Laying of CHB on rebars for slab.
staircase.
Laying of
steeldecks. Engr. Marvin Quilanlan
Scaffoldings for Field Engineer
steeldecks.
16-Mar-18 Formworks on Portal lift Wilson Baltazar
(Friday) beams. One-bagger concrete Foreman The laborers are
Plastering of outer mixer
installing steeldecks
left wall. Welding machine Laborers
Preparation for Carpenter on third floor.
plastering of Mason
columns. 1st floor Welder
Rebar works on
slab.
Preparation of
flatform for concrete The laborers are
mixer. preparing the
platform for
concrete mixer.
The laborers are
preparing the
platform for
concrete mixer.

EQUIPMENT PERSON/S INVOLVED


DATE/DAY ACTIVITY OBSERVATION DOCUMENTATION

The mason is laying


CHB for walls on
Laying of CHB on staircase.
staircase.
Laying of
steeldecks. Engr. Marvin Quilanlan
Scaffoldings for Field Engineer
steeldecks.
16-Mar-18 Formworks on Portal lift Wilson Baltazar
(Friday) beams. One-bagger concrete Foreman The masons are
Plastering of outer mixer plastering the
left wall. Welding machine Laborers firewall.
Preparation for Carpenter
plastering of Mason
columns. 1st floor Welder
Rebar works on
slab.
Preparation of
flatform for concrete The laborer is fixing
mixer.
the scaffoldings for

steeldecks.
Preparation of
flatform for concrete The laborer is fixing
mixer.
the scaffoldings for

steeldecks.

You might also like