The document discusses the installation of a hydroelectric turbine. It provides instructions on several key steps:
1) Checking drawing references and using the penstock as a reference point.
2) Seating the turbine and generator on a concrete floor or base frame carefully to avoid vibrations during concrete removal.
3) Aligning the turbine casing, generator, and runner centerlines.
Original Description:
Tips for small hydro francis turbine installation and setting
The document discusses the installation of a hydroelectric turbine. It provides instructions on several key steps:
1) Checking drawing references and using the penstock as a reference point.
2) Seating the turbine and generator on a concrete floor or base frame carefully to avoid vibrations during concrete removal.
3) Aligning the turbine casing, generator, and runner centerlines.
The document discusses the installation of a hydroelectric turbine. It provides instructions on several key steps:
1) Checking drawing references and using the penstock as a reference point.
2) Seating the turbine and generator on a concrete floor or base frame carefully to avoid vibrations during concrete removal.
3) Aligning the turbine casing, generator, and runner centerlines.
By Ifnu Setyadi G CASES : INSTALATION CENTERLINE REFERENCE
1. CHECK DRAWING REFERENCE
2. PENSTOCK MENJADI ACUAN 3. GUNAKAN ALAT UKUR SURVEY CASES : INSTALATION CENTERLINE REFERENCE CASES : INSTALATION 1. TURBIN & GENERATOR SEATED A. ON CONCRETE FLOOR
- SETTING HARUS HATI-HATI KARENA RAWAN GETARAN
- PEKERJAAN PEMBONGKARAN CONGCRETE SKETSA TURBIN-GENERATOR DI ATAS PONDASI CASES : INSTALATION 1. TURBIN & GENERATOR SEATED ON BASE FRAME SKETSA TURBIN DI ATAS BASE FRAME CASES : INSTALATION END PIPE PENSTOCK JOINING TO MIV FLANGE
HATI-HATI !!!!!!!
WELDED AFTER MIV & TURBINE ASSEMBLY
CASES : INSTALATION CENTERLINE ALIGNMENT 1. SETTING ALIGNMENT OF TURBINE CASING CENTER LINE 2. SETTING GENERATOR ALIGNMENT 3. SETTING RUNNER CASES : INSTALATION CENTERLINE ALIGNMENT 1. SETTING ALIGNMENT OF TURBINE CASING CENTER LINE 2. SETTING GENERATOR ALIGNMENT 3. SETTING RUNNER