Professional Documents
Culture Documents
Pneumatic systems, a technical and economical way to transfer drilling waste and
minimize HSE impact.
Jaime Martinez, Swaco Nigeria, Diana Lopez, Swaco West Africa; Gordon Thomson and Richard Bingham, Swaco
Easter Hemisphere Operations
Abstract Introduction
Regulatory changes in environmental sensitive After January 16, 2001, the offshore discharge of
areas have reduced the allowable level of discharge of cuttings contaminated with greater than 1.0% residual
hydrocarbon content in drill cuttings to less than 1% by hydrocarbons on cuttings was effectively prohibited in
weight. This has resulted in cuttings either being injected UK waters. Rules have been tightening worldwide, with
in slurry form or transferred to shore for processing. As similar discharge regimes implemented in all western
these new regulations are extended to different areas of European waters, the Caspian Sea and other areas. In
the world, the requirements for reliable and cost effective the US, discharge regulations now require either
solutions as well as transfer of lessons learn become containment of contaminated cuttings or drying below
very important in the process of implementing new 6.9% retention on cuttings for base fluids that meet the
solutions. environmental performance criteria for IO 1618, and
Conventional system for transfer cuttings are based 9.4% retention on cuttings for base fluids that meet the
on the use of cuttings boxes in combination to environmental performance criteria for esters. Improved
mechanical feeding systems. Although this systems methods for moving cuttings either to containment, to
have proven to be reliable, different experiences from process before discharge, or to cuttings re-injection units
skip filling and handling identified the requirement for are required.
new bulk techniques for a safer containment and transfer
of drilled cuttings.
While the established solution for containing cuttings
offshore – “skip and ship” – is technically proven, it can
A bulk transfer and containment method for drilled
be troublesome. Boxes are filled with material on the rig
cuttings based on the use of positive air pressure
and transferred on at a time to an adjacent supply
conveying has been under development since 1998.
vessel. Very large numbers of crane lifts are required
Initial onshore trials proved the capability to convey drill
offshore, which requires a strong focus on safety
cuttings samples. A product development programme to
management. The number of skips involved creates
adapt this technology to the specific demands of oilfield
significant logistic management challenges. Operations
drilling was then undertaken. In autumn 2000, on-rig
may also be affected by weather.
containment and rig-to-boat transfer trials were carried
out on rigs drilling in UK waters.
A system that could move contaminated cuttings in a
This paper describes the successful application of sealed system by bulk transfer from rig to boat would
positive air pressure conveying for drill cuttings and eliminate these risks. Several possible technology
further applications for drilling cuttings transfer in options exist for the bulk transfer of materials.
different regions of the world
Mechanical systems such as augers, conveyor belts,
The authors will detail how in the past year full
containment and transfer systems have been and bucket conveyors are not suitable for rig-to-boat
transfer because of the distances and relative motion
successfully deployed in the North Sea, Russia and Gulf
involved, as well as the difficulty of ensuring total
of Mexico. The operating principles of the system are
described along with the design of the principal containment.
components. The performance of the system in practice Slurry-pumping technology is capable of
and the operational experience gained are considered. covering the distances involved, and has previously
been utilized in the oilfield to convey cuttings short
2 J Martinez, D Lopez, G. Thomson and R Bingham DPR—HSE2006-
distances. The principle of slurry-based systems is combined storage and conveying units located
adding fluid and mixing to suspend the solids in a liquid elsewhere on the rig. Each of these units, referred to as
3
mixture that can be pumped. The addition of fluid ISO-pumps, can store 20 – 25m of cuttings, depending
obviously increases the size of the waste stream, and on bulk density, The combined storage and conveying
may complicate subsequent processing. units are used for on-rig storage of cutting until the
supply vessel comes alongside.
Vacuum-conveying technology, which uses an
exhauster unit to crate a pressure differential and sucks
The units are then discharged through a flexible
material along a hose or pipeline in a low material/air
hose to identical units mounted on the deck of the supply
ratio, may be used successfully to convey cuttings short
vessel. When the supply vessel returns to harbor, the
distances, but it is not suitable for conveying drilled
loaded units on board may be discharged to onshore
cuttings from rig to boat at a sufficient rate over the
vehicles, to storage, or discharged directly in a harbor-
distances required.
side processing facility. Alternatively, the units may be
lifted directly from the vessel for road transport to a
Positive air pressure conveying, which uses cutting-processing facility.
compressed air to push granular materials through pipes
or hoses with a high ratio of material to air, is widely
Manpower requirements to operate the on-rig
used in industrial settings including coal-fired electricity
equipment consist of one to two dedicated men per shift,
generation, foundries and iron and steel works. The
depending on the phase of the well. Other than the
potential to use positive air pressure conveying
crane lifts for the hose, there is no requirement for the
technology to move drilled cuttings was first identified in
use of the rig crew in operating the system.
1998.
Trial Design
The first stage in installation of ISO-Pumps on the
The first full-scale bulk transfer trial took place in PSV was marine engineering design approval. In
June 2001. The aim of the trial was to clearly conjunction with the vessel owners and marine certifying
demonstrate the capability of the technology to convey authorities, a design analysis process was undertaken to
drilled cuttings from their production at the shale shakers ensure stability and security under maximum
through three stages of handling and finally resulting in environmental loading criteria.
the transfer of the cuttings from a Platform Supply
Vessel (PSV) to a storage/processing facility onshore at
Lerwick, Shetland. The PSV ISO-Pumps were mounted on a load-
spreading frame with sea fastenings designed to
4 J Martinez, D Lopez, G. Thomson and R Bingham DPR—HSE2006-
accommodate the corner blocks of the individual ISO- The PSV is located on the port side of the rig. The
Pumps. In turn the load-spreading frame was secured to flexible hose, fitted with lace-on flotation collars, is
the boat by bolt-down plates, attached to doubling plates lowered to the PSV from the main rig crane. The tilt
welded directly to the PSV deck and aligned with the table is lowered to the horizontal-landing position. The
mains PSV load-bearing deck beams. Once the initial PSV deck crew guides the hose onto the tilt-table
work was done to install the doubling plates, installation assembly. The hose is landed and is latched into the
of the equipment was carried out in under 12 hours. unit. The crane lowers off, ensuring all weight is
removed from the crane irrespective of PSV-induced
wave movement, and the strops connecting the hose to
Five ISO-Pumps were installed onto the PSV
the crane are released. With the crane disconnected
together with four R-Valves and appropriate air and
and clear of the PSV, and the hose securely latched in
material manifolds.
position, an hydraulic hand pump is used to elevate the
tilt table from the horizontal landing position to its
With the PSV ISO-Pumps full of drilled cuttings from working angle. The hose is mated with the rigid pipe on
the transfer down from the rig, the hose was the boat and the wing union is hammered closed. At this
disconnected. The Platform Supply Vessel is then sailed point the connection procedure is completed. Less than
to land to conduct the final phase of the handling 2 minutes was recorded to complete this entire process.
process.
On June 22. 2001, several days before the actual
Once back to port at Lerwick, the PSV ISO-Pumps drilling activities began; a trial was held to demonstrate
were to be connected to a conveying pipeline on the the functionality of the tilt table. For this the PSV was
quayside and the contaminated drilled cuttings conveyed brought along side the port side of the rig and the hose
from PSV to quayside storage tanks. In this particular lowered. The tilt table was used to engage the hose and
case, the conveying distance was approximately 197 ft then disengaged. Both stages were realized in direct
terminating, via a deflector hood, into 20-ft x 7 ½ -ft x 7 accordance to the operating procedure to the complete
½ -ft tanks. In order to mitigate any chance of drilled satisfaction of all involved parties. The PSV then sailed
cuttings escaping from the system other than at the back to the stand-off area.
intended terminal location, the conveying pipe from the
PSV to storage tanks was to be run on or within a
Trial Performance
temporary bunding constructed from plastic sheets and
tarpaulins. This precaution was primarily to satisfy local The cuttings blower was started up as drilling
permission requirements, as the chance of the hose commenced on an 8 ½ -in sidetrack. Whilst drilling
breaking is negligible and the material being conveyed through the whipstock, the cuttings were conveyed from
was principally solid rather than liquid. Monitoring of the cuttings blower to a ‘skip filling station’, where three
atmospheric VOCs during the discharge process took standard cuttings boxes can be filled via a series of
place to ensure safety and compliance with diverter valves. During this period, a level probe was
environmental regulations. used for the first time with the cuttings blower to provide
fully automatic control. This level probe ensures the
cuttings blower only cycles when sufficient material is
Comprehensive analysis of potential safety hazards available in the vibratory feed chute and therefore direct
and failures was undertaken in advance of the trial, with modulates the cycle frequency of the system to
emphasis on ‘engineering out’ any potential risks. correspond with the actual drilled cuttings production
rates.
Hose Connection Method
In order to make the hook-up between PSV and rig The drilled cuttings were directed to the five ISO-
without the need of any manual lifting of the 5-in. hose, a Pumps. This manual change over (rotation of a 90°-
purpose-designed assembly was manufactured and bend) took in the order of seven to eight minutes to
installed on the PSV. The assembly, known as a tilt complete. Filling of the ISO-Pump then commenced.
table, offers a simple, quick and safe solution to this
challenge.
At this stage of the trial, concerns from the Lerwick
processing facility regarding their available storage
The following describes the fundamental operations capacity necessitated a change to the original ISO-Pump
of the tilt table as it is used offshore. filling plans. Due to the limited reception capacity
available, a total volume of only 250 bbl was planned to
DRP- HSE2006- Pneumatic systems, a technical and economical way to transfer drilling waste and minimize HSE impact. 5
be shipped to shore. The eventual fill weights of the conveying lines heavily loaded with material and then
ISO-Pump were recorded as shown in Table 1. successfully restarted.
When the first ISO-Pump was filled to the 20 ½- The average discharge rate recorded was 20 tonnes
tonnes (approximately 70-bbl) level, the status of the first per hour (60 bbl/hr).
diverter valve on the ISO-Pump filling manifold was
changed to “through” from the previous “divert” position.
Once the ISO-Pumps were empty, the line airflows
The drilled cuttings being produced were now conveyed
were stopped and ISO-Pump pressure reduced to
into the second ISO-Pump without interruption to the
atmospheric. At this stage, the hose was disengaged
cuttings blower operation.
and capped before being lifted off the PSV. No material
was released during the hose-disconnection operation.
Whilst the second ISO-Pump was filling, the first
ISO-Pump was discharged down to the PSV via the tilt
Discharge of the ISO-Pumps At Lerwick
table, a conveying airflow was established and the
integrity of the pipe and the hose verified. With both line
and tank airflow confirmed at the ISO-Pump, the outlet Conveying Route
valve on the pump was opened. With the standard ISO- The discharge from the ISO-Pumps rose about 6 ft
Pump discharge characteristics, the cuttings were turning through 90° into the diverter valves and into a
discharged with the tank pressure reached common return line. At the edge of the boat, this was
approximately 60 psi. attached to a 60-ft flexible hose that joined into the fixed
landline for conveying into the storage containers.
During the discharge cycle of the ISO-Pump, the
overboard hose was observed to be relatively stable as it At the end of the fixed landline was a short flexible
lay on the water level, with the aid of floatation collars. A hose feeding into two 90° bends rising about 7 ft and
small degree of flexing of the hose was evident particular leading over the reception tank to the deflector box.
at the lift onto the PSV.
ISO-Pump 4 was discharged next. Partway through An average discharge rate of 35 tonnes/r hour was
the discharge, the reception tank became full and recorded for the volume of drilled cuttings that was
discharge was suspended by closing the outlet valve analyzed as having an oil-on-cuttings value of 7%.
and isolating the line air.
The cuttings had an angle of repose of 60 - 70°.
The changeover took about 20 minutes and, when Consequently, the cuttings built up in the onshore
complete, the air line was re-established and the outlet reception container beneath the discharge hood
valve opened. Material flow started immediately with no resulting in poor distribution along with container’s full
problems. 20-ft length. The need was identified for an improved
discharge arrangement to achieve a larger working
capacity for each container.
The discharge of ISO-Pump 5 was similar to that of
ISO-Pump 2.
Monitoring of the air in the discharge area for VOCs
found there to be no measurable emissions.
After all ISO-Pumps were discharged, they were re-
pressurized and a small amount of additional material
was conveyed. Full System Deployment: August 2001
In August 2001 the quantity of equipment was
After conveying the system was stripped down. increased to include a total of nine ISO-Pumps on the rig
Very little material was found in the conveying lines, and 10 on the PSV, along with an increased number of
although the outlets of three of the systems had a small R-Valves and the existing cuttings blower on the rig.
amount of material left in the outlet valve area. Minor additional hookup pipework was required. The
capacity of the system was increased to enable a full 12
¼ -in. section to be contained. In practice, the figure of
Analysis of the discharge data showed an average the nine ISO-Pumps was determined by space
mass flow rate of 35 tonnes/hour (120 bbl/hr). This rate limitations on the starboard riser deck.
approached the design transfer rate of 40 tonnes/hour,
Three boat trips were made to transfer the material
conveying the same material that conveyed at 20
from the rig to the reception facility at Lerwick. Average
tones/hour from rig to boat. The principle explanation for
conveying rate from rig to b oat was 34.6 mt/hr, and from
the difference between these two rates is the conveying-
boat to shore 43.0 mt/hr.
pipework route, which on the semi-submersible rig was
relatively complex and included a length of sloping pipe
at a descent angle known to adversely affect conveying The average conveying rates achieved for both the
performance, whereas the boat to shore discharge route rig-to-boat and boat-t o-shore transfers were higher than
was relatively simple and nearer to the design ideal. those in the June trial. This was partly a result of the
modifications to the pipework arrangements, and partly a
result of variation in materials conveyed. Since variation
Conclusions from the June Trial
in material condition is the norm in drilled cuttings, it is
All parties involved judged the loading and discharge concluded that variations in conveying rate must also be
of the rig ISO-Pumps as very successful. The average considered to the norm.
discharge rate of 20 tonnes/hour from rig to boat (68
bbl/hr) was below the anticipated level. Potential pipe
route modifications were identified to improve on this Gulf of Mexico Bulk Trial: October/November 2001
value for subsequent projects. The tilt-table operations A cuttings-blower unit was installed on a drillship
demonstrated the capability to make hose connections operating in Florida waters. It was required to fully
to the PSV without the need for manual handling. contain and transfer to shore all cuttings from the 17 ½ -
in. section and subsequent sections.
The discharge of the four boat ISO-Pumps to shore
reception was successfully conducted with no It was possible to tie the PSV alongside the drillship
operational or HSE concerns. The ISO-Pumps were and a means was devised to transfer the cuttings directly
successfully operated in stop/start mode to enable to into skips mounted on the deck of the PSV without
discharge hood to be repositioned over empty containers intermediate storage on the rig. Fifty standard cuttings
as the discharge progressed. boxes were laid out on the deck of the PSV in ten
transverse rows of five. Diverter valves were used to
direct cuttings along pipework to the set of 10 boxes,
and a length of flexible hose was used to connect the
DRP- HSE2006- Pneumatic systems, a technical and economical way to transfer drilling waste and minimize HSE impact. 7
A couple of line blockages were caused by over- After the complete development of the pneumatic
filling boxes. These were easily cleared by stopping the system for cuttings transfer, it’s implementation in
blower unit, switching to another box closer in the line to different regions of the world has proven to be a
the blower unit and clearing the remaining material into technical, cost effective and safe alternative to transfer
the selected box. At the same time, the cuttings in the cuttings. Over 50 jobs have been completed in North
full box were spread away from the lid to leave some Sea, Gulf of Mexico, Caspian Sea, Russia, West
room in the box. The blower unit was routed back to the Shetland and Scandinavia. Table 2 shows a summary
full box, and an empty blow cycle performed, this cleared of the different type of cuttings transferred, drilling fluids
the remaining material from the last section of line and used and number of jobs in each region.
hence the blockage. Then conveying was switched to
the next box. One important aspect in the use of pneumatic
systems is the complete elimination of skips at the rig
For most of the 17 ½ -in. section, the lithology was site which not only reduces the risk associated with
the same (shale), with occasionally a higher percentage crane lifts but also the man power required to fill out and
of marl (A clay-type material). The last 250 ft of hole move skips on the rig. This has also been reflected in
was siltstone, sand and shale. significant cost reductions to operators.
During a couple of well sweeps, the timer was The ability of the pneumatic system to maintain high
overridden and the blower unit was manually run as fast transfer volumes has also been demonstrated trough it’s
as possible. This was continued until the surge of use in large hole sections and high drilling rates. The
returns from the well was past, at which point automatic system has been used in 17 ½”, 16” and 12 ¼” and 8 ½”
cycling was reinstated. hole sections drilling at rates up to 340 ft/hr. Formation
drilled included Shale, Siltstone, Claystone and Sand.
Charts 1 and 2 show historical data from jobs completed
The total cuttings production for the 17 ½ -in. section up to September 2002.
was 933 bbl to the PSV, for 1,693 ft drilled. In addition,
150 bbl of cuttings were transferred to boxes in the
moon pool area by backup systems resulting from the
first well sweep. During this section the RIP started at Conclusions
40 ft/hr (for 320 ft) then increased to 80 ft/hr (1170 ft)
Positive air pressure bulk-transfer technology has
with peaks to approximately 120 ft/hr. Drilling of the 17
½ -in. section was never interrupted until it was been applied to solve the problem of bulk transfer of drill
cuttings. Full-scale bulk-transfer systems have been
completed.
successfully fitted to rig and to PSV. OBM cuttings with
varying characteristics have been safely and
Overall, the operator’s personnel were very pleased successfully transported to shore reception facilities.
with the performance of the blower unit, and drilling was Average transfer rates of between 20 tonnes/hour (68
never stopped or slowed down as a result of its bbl/hr) and 43 tonnes/hour (146 bbl/hr) were recorded.
operation.
8 J Martinez, D Lopez, G. Thomson and R Bingham DPR—HSE2006-
For the UK installation in particular, fewer rig It can be concluded that this technology is a
personnel were required to operate the equipment, significant advance in drill cuttings handling, and to date
crane operations were reduced to a handful of hose lifts, demonstrates to be one the most reliable technology for
and the contaminated materials were kept within a bulk transfer of drilling minimizing the risk from the use
sealed system until discharged into onshore reception of skips on the rig and minimizing the environmental
tanks. Health and safety and environmental risks were impact of offshore drilling operations.
much reduced.
1000
900
800
Cuttings mass (MT)
700
600 MT Cuttings
500
400
300
200
100
0
1
Jo 7
35
50
0
4
6
3
b1
b1
b1
b2
b2
b2
b4
b4
b1
b3
b3
b4
b5
b
b
Jo
Jo
b
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jobs from 2001 and 2002
250.00
200.00 17 1/2” hole
150.00 size
100.00
50.00
0.00
b7
16
25
35
44
53
b1
0
9
b1
b1
b1
b2
b3
b3
b4
b4
b5
b2
Jo
Jo
b
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo
Jo