You are on page 1of 1

Conor Fitzpatrick

PRODUCTION RISK ASSESSMENT - HOPE FILM


LOCATION: 136 Grange Road, South DATE: Director: Conor Fitzpatrick

Pre Control Post Control

What could cause WHO may be harmed RISK CONTROL MEASURES RISK
HARM? and HOW?
LOW 1 – 5 HIGH What measures have been LOW 1 – 5 HIGH
(List identified (Give consideration to implemented to reduce the
HAZARDS) people with special Risks Identified?

Risk Rating

Risk Rating
Likelihood

Likelihood
Severity

Severity
(L/M/H)

(L/M/H)
needs)

(1-5)

(1-5)

(1-5)

(1-5)
Avoid wires or make sure
Slips, trips and falls Anyone involved in 3 4 M they are in a safe position. 1 2 L
production

Broken equipment The person using the 2 2 L Be careful with equipment 1 1 L


specific equipment
Make sure to keep eyes on
Theft People in charge of 1 2 L equipment at all times and 1 1 L
equipment check all is in the right
place