You are on page 1of 13

Demand Factor-Diversity

Factor-Utilization Factor-
Load Factor
By jiguparmar | November, 14th 2011

Originally published at Electrical Notes – Articles

(1) Demand factor


 Demand Factor = Maximum demand of a system / Total connected
load on the system
 Demand factor is always less than one.
 Example: if a residence having 6000W equipment connected has a
maximum demand of 300W, than demand factor = 6000W / 3300W =
55%.
 The lower the demand factor, the less system capacity required to
serve the connected load.
 Feeder-circuit conductors should have an ampere sufficient to carry
the load; the ampere of the feeder-circuit need not always be equal to
the total of all loads on all branch-circuits connected to it.
Remember that the demand factor permits a feeder-circuit ampere to be
less than 100% of the sum of all branch-circuit loads connected to the
feeder.
 Example: One Machine Shop has
Fluorescent fixtures=1 No, 5kW each, Receptacle outlets =1 No,
1500w each.
Lathe=1No, 10 HP, Air Compressor=1 No, 20 HP, Fire Pump=1 No, 15
HP.
 After questioning the customer about the various loads, the information
is further deciphered as follows:
 The shop lights are on only during the hours of 8 a.m. to 5 p.m.
 The receptacle outlets are in the office only, and will have computers
and other small loads plugged into them.
 The lathe is fully loaded for 5 minutes periods. The rest of the time
is setup time. This procedure repeats every 15 minutes.
 The air compressor supplies air to air tools and cycles off and on
about half the time.
 The fire pump only runs for 30 minutes when tested which is once a
month after hours.
Calculation:
Lighting Demand Factor = Demand Interval Factor x Diversity Factor.

 = (15 minute run time/ 15 minutes) x 1.0 = 1.0


 Lighting Demand Load = 5 kW x 1.0 = 5 kW
 Receptacle Outlet Demand Factor = Demand Interval Factor x Diversity
Factor
 = (15 minute run time / 15 minutes) x 0.1 = 0.1
 Receptacle Outlet Demand Load = 15 x 1500 watts x 0.1 = 2.25 kW
 Lathe Demand Factor = Demand Interval Factor x Diversity Factor.
 = (5 minute run time / 15 minutes) x 1.0 =0 .33
 Lathe Demand Load = 10 HP x .746 x .33 = 2.46 kW
 Air Compressor Demand Factor = Demand Interval Factor x Diversity
Factor.
 = (7.5 minute run time / 15 minutes) x 1.0 = 0.5
 Air Compressor Demand Load = 20 HP x .746 x .5 = 7.46 kW
 Fire Pump Demand Factor = Demand Interval Factor x Diversity Factor.
 = (15 minute run time/ 15 minutes) x 0.0 = 0.0
 Fire Pump Demand Load = 15 HP x .746 x 0.0 = 0.0 kW
 Summary of Demand Loads :
Equipment kW D.F. Demand KW
Lighting 5 1 5
Receptacle Outlets 22.5 .1 2.25
Lathe 7.5 .33 2.46
Air Compressor 15 0.5 7.46
Fire Pump 11.25 0.0 0.0
TOTAL 61.25 KW 17.17 KW

(2) Diversity factor / simultaneity


factor (Ks)
 Diversity Factor = Sum of Individual Max. Demand. /Max. Demand
on Power Station.
 Diversity Factor = Installed load. /Running load.
 Diversity factor is usually more than one. (Since the sum of
individual max. demands >Max. Demand)
 The load is time dependent as well as being dependent upon
equipment characteristics. The diversity factor recognizes that the
whole load does not equal the sum of its parts due to this time
Interdependence (i.e. diverseness).
 When the maximum demand of a supply is being assessed it is not
sufficient to simply add together the ratings of all electrical equipment
that could be connected to that supply. If this is done, a figure
somewhat higher than the true maximum demand will be produced.
This is because it is unlikely that all the electrical equipment on a supply
will be used simultaneously.
 The concept of being able to De-rate a potential maximum load to an
actual maximum demand is known as the application of a diversity
factor.
 70% diversity means that the device in question operates at its nominal
or maximum load level 70% of the time that it is connected and turned
on.
 If total installed full load ampere is twice your running load ampere then
the diversity factor is two.
 If total installed full load ampere is four times your load in ampere then
the diversity factor is four.
 If everything (all electrical equipment) was running at full load at the
same time the diversity factor is equal to One
 Greater the diversity factor, lesser is the cost of generation of
power.
 Diversity factor in a distribution network is the ratio of the sum of the
peak demands of the individual customers to the peak demand of the
network.
 This will be determined by the type of service, i.e., residential,
commercial, industrial and combinations of such.
 Example-I: A distribution feeder serves 5 houses, each of which has a
peak demand of 5 KW. The feeder peak turns out to be 20 kW. The
diversity is then 20/25 or 0.8. This results from the timing differences
between the individual heating/cooling, appliance usages in the
individual customers.
 As supply availability decreases, the diversity factor will tend to
increase toward 1.00. This can be demonstrated when restoring service
after outages (called “cold starts”) as the system initial surge can be
much greater than the historical peak loads.
 Example-II: A sub-station has three outgoing feeders:
1. feeder 1 has maximum demand 10 MW at 10:00 am,
2. feeder 2 has maximum demand 12 MW at 7:00 pm and
3. feeder 3 has maximum demand 15 MW at 9:00 pm,
4. While the maximum demand of all three feeders is 33 MW at 8:00 pm.
 Here, the sum of the maximum demand of the individual sub-systems
(feeders) is 10 + 12 + 15 = 37 MW, while the system maximum demand
is 33 MW. The diversity factor is 37/33 = 1.12. The diversity factor is
usually greater than 1; its value also can be 1 which indicates the
maximum demand of the individual sub-system occurs
simultaneously.
 Diversity is the relationship between the rated full loads of the
equipment downstream of a connection point, and the rated load of the
connection point. To illustrate:
1. The building at these co-ordinates is fitted with a 100A main supply fuse.
2. The distribution board has 2no. 6A breakers, 1no. 20A breaker and 5no.
32A breakers, a total, potentially, of 192A.
 Not all these rated loads are turned on at once. If they were, then the
100A supply fuse would rupture, as it cannot pass 192A. So the
diversity factor of the distribution board can be said to be 192A/100A,
or 1.92, or 52%.
 Many designers prefer to use unity as the diversity factor in calculations
for planning conservatism because of plant load growth uncertainties.
Local experience can justify using a diversity factor larger than unity,
and smaller service entrance conductors and transformer requirements
chosen accordingly.
 The diversity factor for all other installations will be different, and would
be based upon a local evaluation of the loads to be applied at different
moments in time. Assuming it to be 1.0 may, on some occasions, result
in a supply feeder and equipment rating that is rather larger than the
local installation warrants, and an over-investment in cable and
equipment to handle the rated load current. It is better to evaluate the
pattern of usage of the loads and calculate an acceptable diversity
factor for each particular case.
 In the case of the example given above, achieving a diversity of 1.0 or
100% would require well over twice the cross-sectional area of copper
cable to be installed in a deep trench underneath a field, the rebuild of a
feeder cabinet to larger dimensions, more substantial overhead supply
cables for a distance exceeding 2km northwards and a different tariff,
where one pays rather more for a kWh than at present. The investment
required to achieve 1.0 simply isn’t justifiable in this particular case.
 Diversity factor is mostly used for distribution feeder size and
transformer as well as to determine the maximum peak load and
diversity factor is always based on knowing the process. You have to
understand what will be on or off at a given time for different buildings
and this will size the feeder. Note for typical buildings diversity factor is
always one. You have to estimate or have a data records to create 24
hours load graph and you can determine the maximum demand load for
node then you can easily determine the feeder and transformer size.
 The diversity factor of a feeder would be the sum of the maximum
demands of the individual consumers divided by the maximum demand
of the feeder. In the same manner, it is possible to compute the
diversity factor on a substation, a transmission line or a whole utility
system.
 The residential load has the highest diversity factor. Industrial loads
have low diversity factors usually of 1.4, street light practically unity and
other loads vary between these limits.
Diversity Factor in distribution Network
Elements of System Diversity Factors

Residential Commercial General Large


Power Industrial
Between individual users 2.00 1.46 1.45
Between transformers 1.30 1.30 1.35 1.05
Between feeders 1.15 1.15 1.15 1.05
Between substations 1.10 1.10 1.10 1.10
From users to transformers 2.00 1.46 1.44
From users to feeder 2.60 1.90 1.95 1.15
From users to substation 3.00 2.18 2.24 1.32
From users to generating station 3.29 2.40 2.46 1.45

Diversity Factor for distribution


switchboards
Number of circuits Diversity Factor (ks)
Assemblies entirely tested 2 and 3 0.9
4 and 5 0.8
6 to 9 0.7
10 and more 0.6
Assemblies partially tested in every case choose 1

Diversity Factor for according to circuit


function (IEC 60439)
Circuits Function Diversity Factor (ks)
Lighting 0.9
Heating and air conditioning 0.8
Socket-outlets 0.7
Lifts and catering hoist
For the most powerful motor 1
For the second most powerful motor 0.75
For all motors 0.8

Diversity Factor for an apartment block


Apartment Diversity Factor (ks)
2 To 4 1
5To 19 0.78
10To 14 0.63
15To 19 0.53
20To 24 0.49
25To 29 0.46
30 To 34 0.44
35 To 39 0.42
40To 40 0.41
50 To Above 0.40
 Example: 5 story apartment building with 25 consumers, each having 6
kVA of installed load.
The total installed load for the building is: 36 + 24 + 30 + 36 + 24 = 150
kVA
The apparent-power supply required for the building is: 150 x 0.46 = 69
kVA
 It is a matter of common experience that the simultaneous operation of
all installed loads of a given installation never occurs in practice, i.e.
there is always some degree of diversity and this fact is taken into
account for estimating purposes by the use of a simultaneity factor /
Diversity Factor (ks).
 The Diversity factor ks is applied to each group of loads (e.g. being
supplied from a distribution or sub-distribution board). The
determination of these factors is the responsibility of the designer, since
it requires a detailed knowledge of the installation and the conditions in
which the individual circuits are to be exploited. For this reason, it is not
possible to give precise values for general application.
Designing Size of Electrical Switchgear by use of
Demand Factor and Diversity Factor:
 Diversity factors are used by utilities for distribution transformer sizing
and load predictions.
 Demand factors are more conservative and are used by NEC for
service and feeder sizing.
 Demand factors and diversity factors are used in design.
 For example, the sum of the connected loads supplied by a feeder is
multiplied by the demand factor to determine the load for which the
feeder must be sized. This load is termed the maximum demand of the
feeder. The sum of the maximum demand loads for a number of sub
feeders divided by the diversity factor for the sub feeders will give the
maximum demand load to be supplied by the feeder from which the sub
feeders are derived.
 Example-1: Suppose We have four individual feeder-circuits with
connected loads of 250 kVA, 200 kVA, 150 kVA and 400 kVA and
demand factors of 90%, 80%, 75% and 85% respectively. Use a
diversity factor of 1.5.
 Calculating demand for feeder-circuits
 250 kVA x 90% = 225 kVA
 200 kVA x 80% = 160 kVA
 150 kVA x 75% = 112.5 kVA
 400 kVA x 85% = 340 kVA
 837.5 kVA
 The sum of the individual demands is equal to 837.5 kVA.
 If the main feeder-circuit were sized at unity diversity: kVA = 837.5
kVA ÷ 1.00 = 837.5 kVA.
 The main feeder-circuit would have to be supplied by an 850
kVA transformer.
 However, using the diversity factor of 1.5, the kVA = 837.5 kVA ÷
1.5 = 558 kVA for the main feeder.
 For diversity factor of 1.5, a 600 kVA transformer could be used.
 Example-2: A conveyor belt made up of six sections, each driven
by a 2 kW motor. As material is transported along this belt, it is
first carried by section 1, and then each section in succession until
the final section is reached. In this simple example only one
section of conveyor is carrying material at any point in time.
Therefore five motors are only handling no-load mechanical losses
(say .1 kW) keeping the belts moving whilst one motor is handling
the load (say 1 kW). The demand presented by each motor when it
is carrying its load is 1 kW, the sum of the demand loads is 6 kW
but the maximum load presented by the system at any time is only
1.5 kW.
 Diversity factor =Sum of Individual Max. Demand / Max. Demand =
6 KW / 1.5 KW =4.
 Demand Factor = Maximum demand / Total connected load = 1.5
KW / 12 KW = 0.125.

(3) Load factor


 Load Factor = Average load. /Maximum load during a given period.
 It can be calculated for a single day, for a month or for a year.
 Its value is always less than one. Because maximum demand is always
more than avg. demand.
 It is used for determining the overall cost per unit generated.
Higher the load factor, lesser will be the cost per unit.
 Load Factor = Load that a piece of equipment actually draws / Load it
could draw (full load).
 Example: Motor of 20 HP drives a constant 15 HP load whenever it is
on.
 The motor load factor is then 15/20 = 75%.
 Load factor is term that does not appear on your utility bill, but does
affect electricity costs. Load factor indicates how efficiently the
customer is using peak demand.
 Load Factor = ( energy (kWh per month) ) / ( peak demand (kW) x
hours/month )
 A high load factor means power usage is relatively constant. Low load
factor shows that occasionally a high demand is set. To service that
peak, capacity is sitting idle for long periods, thereby imposing higher
costs on the system. Electrical rates are designed so that customers
with high load factor are charged less overall per kWh.
 For Example
 Customer A – High Load Factor
 82% load factor = (3000 kWh per month x 100%) / 5 kW x 730
hours/month.
 Customer B – Low Load Factor
 41% load factor = (3000 kWh per month x 100%) / 10kW x 730
hours/month.
 To encourage the efficient use of installed capacity, electricity rates are
structured so the price per kWh above a certain load factor is lower.
The actual structure of the price blocks varies by rate.

(4) Utilization factor (Ku)


 In normal operating conditions the power consumption of a load is
sometimes less than that indicated as its nominal power rating, a fairly
common occurrence that justifies the application of a utilization factor
(ku) in the estimation of realistic values.
 Utilization Factor = the time that an equipment is in use/the total
time that it could be in use.
 Example: The motor may only be used for eight hours a day, 50 weeks
a year. The hours of operation would then be 2000 hours, and the
motor Utilization factor for a base of 8760 hours per year would be
2000/8760 = 22.83%. With a base of 2000 hours per year, the motor
Utilization factor would be 100%. The bottom line is that the use factor
is applied to get the correct number of hours that the motor is in use.
 This factor must be applied to each individual load, with particular
attention to electric motors, which are very rarely operated at full load.
In an industrial installation this factor may be estimated on an average
at 0.75 for motors.
 For incandescent-lighting loads, the factor always equals 1.
 For socket-outlet circuits, the factors depend entirely on the type of
appliances being supplied from the sockets concerned.

Maximum demand
 Maximum demand (often referred to as MD) is the largest current
normally carried by circuits, switches and protective devices. It does not
include the levels of current flowing under overload or short circuit
conditions.
 Assessment of maximum demand is sometimes straightforward. For
example, the maximum demand of a 240 V single-phase 8 kW shower
heater can be calculated by dividing the power (8 kW) by the voltage
(240 V) to give a current of 33.3 A. This calculation assumes a power
factor of unity, which is a reasonable assumption for such a purely
resistive load.
 There are times, however, when assessment of maximum demand is
less obvious. For example, if a ring circuit feeds fifteen 13 A sockets,
the maximum demand clearly should not be 15 x 13 = 195 A, if only
because the circuit protection will not be rated at more than 32 A. Some
13 A sockets may feed table lamps with 60 W lamps fitted, whilst others
may feed 3 kW washing machines; others again may not be loaded at
all.
 Lighting circuits pose a special problem when determining MD. Each
lamp-holder must be assumed to carry the current required by the
connected load, subject to a minimum loading of 100 W per lamp holder
(a demand of 0.42 A per lamp holder at 240 V). Discharge lamps are
particularly difficult to assess, and current cannot be calculated simply
by dividing lamp power by supply voltage. The reasons for this are:
1. Control gear losses result in additional current,
2. the power factor is usually less than unity so current is greater, and
3. Chokes and other control gear usually distort the waveform of the current
so that it contains harmonics which are additional to the fundamental
supply current.
 So long as the power factor of a discharge lighting circuit is not less
than 0.85, the current demand for the circuit can be calculated from:
 current (A) = (lamp power (W) x 1.8) / supply voltage (V)
 For example, the steady state current demand of a 240 V circuit
supplying ten 65 W fluorescent lamps would be: I = 10X65X1.8A / 240 =
4.88A
 Switches for circuits feeding discharge lamps must be rated at twice the
current they are required to carry, unless they have been specially
constructed to withstand the severe arcing resulting from the switching
of such inductive and capacitive loads.
(5) Coincidence factor
 The coincidence factor =Max. demand of a system / sum of the
individual maximum demands
 The coincidence factor is the reciprocal of the diversity factor
Demand Factor & Load Factor according
to Type of Industries
Type of Industry Demand Load Utilization
Factor Factor Factor (DF x
LF)
Arc Furnace 0.55 0.80 0.44
Induction Furnace 0.90 0.80 0.72
Steel Rolling mills 0.80 0.25 0.20
Mechanical/ Electrical
a) Single Shift 0.45 0.25 0.11
b) Double Shift 0.45 0.50 0.22
Cycle Industry 0.40 0.40 0.16
Wire products 0.35 0.40 0.14
Auto Parts 0.40 0.50 0.20
Forgings 0.50 0.35 0.17
Cold Storage
a) Working Season 0.60 0.65 0.39
b) Non-Working Season 0.25 0.15 0.04
Rice Sheller’s
a) Working Season 0.70 0.80 0.56
b) Non-Working 0.05 0.30 0.01
Season
Ice Candy Units
a) Working Season 0.50 0.65 0.32
b) Non-Working Season 0.50 0.10 0.05
Ice Factories
a) Working Season 0.80 0.65 0.52
b) Non-Working Season 0.80 0.10 0.08
Cotton Ginning
a) Working Season 0.70 0.25 0.17
b) Non-Working Season 0.10 0.10 0.01
Spinning Mills 0.60 0.80 0.48
Textile Industry 0.50 0.80 0.40
Dyeing and Printing 0.40 0.50 0.20
Ghee Mills 0.50 0.50 0.25
Oil Mills 0.70 0.50 0.35
Solvent Extraction Mills 0.45 0.50 0.22
Plastic 0.60 0.25 0.11
Soap 0.50 0.25 0.12
Rubber (Foot Wear) 0.45 0.35 0.16
Distilleries 0.35 0.50 0.17
Chemical Industry 0.40 0.50 0.20
Gas Plant Industry 0.70 0.50 0.35
Paint and Colour 0.50 0.40 0.20
Factory
Sugar 0.30 0.45 0.13
Paper 0.50 0.80 0.40
Flour Mills(Single 0.80 0.25 0.20
Shift)
Atta Chakies 0.50 0.25 0.12
Milk Plants 0.40 0.80 0.32
Printing Presses 0.35 0.30 0.10
Repair Workshops 0.40 0.25 0.10
Bottling Plants 0.40 0.35 0.14
Radio Stations 0.55 .0.45 0.25
Telephone exchange 0.50 0.90 0.45
Public Water Works 0.75 0.40 0.30
Medical Colleges 0.60 0.25 0.15
Hospitals 0.25 0.90 0.22
Nursing Homes 0.50 0.50 0.25
Colleges and Schools 0.50 0.20 0.10
Hotels and Restaurants 0.75 0.40 0.30
Marriage Palaces 1.00 0.25 0.25

Demand Factor & Load Factor according


to Type of Buildings:
Individual Facilities Demand Load
Factor Factor
Communications – buildings 60-65 70-75
Telephone exchange building 55-70 20-25
Air passenger terminal building 65-80 28-32
Aircraft fire and rescue station 25-35 13-17
Aircraft line operations building 65-80 24-28
Academic instruction building 40-60 22-26
Applied instruction building 35-65 24-28
Chemistry and Toxicology 70-80 22-28
Laboratory
Materials Laboratory 30-35 27-32
Physics Laboratory 70-80 22-28
Electrical and electronics systems 20-30 3-7
laboratory
Cold storage warehouse 70-75 20-25
General warehouse 75-80 23-28
Controlled humidity warehouse 60-65 33-38
Hazardous/flammable storehouse 75-80 20-25
Disposal, salvage, scrap building 35-40 25-20
Hospital 38-42 45-50
Laboratory 32-37 20-25
Dental Clinic 35-40 18-23
Medical Clinic 45-50 20-23
Administrative Office 50-65 20-35
Single-family residential housing 60-70 10-15
Detached garages 40-50 2-4
Apartments 35-40 38-42
Fire station 25-35 13-17
Police station 48-53 20-25
Bakery 30-35 45-60
Laundry/dry cleaning plant 30-35 20-25
K-6 schools 75-80 10-15
7-12 schools 65-70 12-17
Churches 65-70 5-25
Post Office 75-80 20-25
Retail store 65-70 25-32
Bank 75-80 20-25
Supermarket 55-60 25-30
Restaurant 45-75 15-25
Auto repair shop 40-60 15-20
Hobby shop, art/crafts 30-40 25-30
Bowling alley 70-75 10-15
Gymnasium 70-75 20-45
Skating rink 70-75 10-15
Indoor swimming pool 55-60 25-50
Theater 45-55 8-13
Library 75-80 30-35
Golf clubhouse 75-80 15-20
Museum 75-80 30-35

You might also like